Unit 2 Primary Containment Vessel Internal Investigation
|
|
- Judith Lloyd
- 6 years ago
- Views:
Transcription
1 Unit 2 Primary Containment Vessel Internal November 30, 2017 Tokyo Electric Power Company Holdings, Inc.
2 1. Conditions inside the Unit 2 PCV According to accident development analysis, it is assumed that part of the melted fuel fell to the plenum at the bottom of the Reactor Pressure Vessel (RPV) or onto the pedestal, with some still remaining in the core. PCV Internal January, March 2012 Muon measurement suggests that most of the fuel debris is at the bottom of the RPV. FW CS Muon measurement suggests that there is fuel on the outer periphery of the core X-53 penetration It is assumed that there is a hole either at or near the center of the RPV based on the conditions of the surrounding CRD observed during the PCV Internal and from the damage seen to grating. X-6 penetration Internal January, February 2017 CRD Rail August 2013 Past Area Steam was observed during the PCV Internal. 1
3 2. PCV Internal results in Jan. Feb It was found that a part of grating was missing during the pre-investigation of the inside of the pedestal conducted through the guide pipe during the PCV Internal from January to February, Lower part of CRD CRD housing support brackets PIP cable CRD replacer Access to underground Slot Opening TIP guide pipe support Fallen grating Flat bar Slot opening CRD rail end Reference Inside Unit 5 pedestal Fallen object TIP guide pipe support Deformed grating Flat bar Area not complied with image processing TIP guide pipe Reference Photo taken during periodic inspection inside Unit 2 pedestal The TIP guide pipe and its supports were removed to inspect Unit 5. Images provided and processed by the International Research Institute for Nuclear Decommissioning (IRID) 2
4 3. Outline of the next PCV Internal Plan :Conditions under the platform where fuel debris may exist will be examined. opening Control rod drive (CRD) replacement rail Primary Containment Vessel (PCV) RPV area Camera hung down point It may not be possible to lower the investigation device due to conditions below the platform Control Rod Drive (CRD) Housing PCV penetration pipe used before (X-53 penetration) Approx. 7.2m PCV penetration pipe to be used (X-6 penetration) Area to be investigated Opening (slot) Basement 3
5 4. method (1/2) The telescopic device used in the PCV internal investigation conducted between Jan. to Feb will be improved so that it can extend the length of the guide pipe and has a camera-mounted investigation device affixed to the end After the investigation device reaches the area above the missing part of the grating inside the pedestal, the camera will be lowered to examine under the platform. This improvement will enable the investigation device to reach the end of the guide pipe inside the pedestal, much further than during the investigation conducted in January~February, and allow conditions above the platform, such as the CRD housing, to be reexamined. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters PCV penetration pipe (X-6 penetration) Cable drum Alternative shield Cable Control Rod Drive Cable feeding machinery Long shot camera unit Telescopic top outline view Pan-tilt camera, light Outline of pre-investigation inside the pedestal (Telescopic investigation device) 4
6 4. method (2/2) Just like the PCV internal investigation conducted in January~February, a boundary will be formed as shown below by sealing the sliding part of the guide pipe with double O-rings and pressurizing the pipe with nitrogen to prevent gas inside PCV from leaking outside and affecting the surrounding environment during the investigation. A similar boundary will be formed for the sliding part of the cable as well. Dust concentration will be monitored during the operation to check that gas inside the PCV does not leak or affect the surrounding environment. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters PCV penetration pipe (X-6 penetration) Cable drum Control Rod Drive Pressured nitrogen Isolation valve (open) Inside of PCV Cable Boundary Pressured nitrogen Sliding part of guide pipe is sealed with O- rings. Sliding part of cable is sealed with O-rings. Sliding part of cable sealed Pan-tilt camera, lighting 5
7 5. Process flow plan Operation FY2017 December January February Advance preparation Training On site preparation PCV Internal PCV Internal 6
Primary Containment Vessel Internal Investigation, Sampling and Analysis
Primary Containment Vessel Internal Investigation, Sampling and Analysis July 26, 2018 Tokyo Electric Power Company Holdings, Inc. 1. Overview Ascertaining conditions inside the PCV, the characteristics
More informationAdvanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning
Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning Eiichiro WATANABE Waste Technology Section Division of Nuclear Fuel Cycle and Waste Technology Department of Nuclear
More informationResearch and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station
WRFPM 2014 Sendai, Japan Research and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station September 15, 2014 KENDA Hirofumi International Research Institute for Nuclear
More informationWM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA
Fukushima Inspection Manipulator 15485 Matt Cole, Kurion Takashi Mitsui, Yuji Morigaki * 1, Toshinori Dekura* 2, * 3 *1: IHI Corporation, Yokohama, Kanagawa, Japan *2: International Research Institute
More informationOverview of IRID R&D -Focusing on Debris Investigation-
Overview of IRID R&D -Focusing on Debris Investigation- 28 th April, 2017 Atsufumi Yoshizawa Executive Director International Research Institute for Nuclear Decommissioning (IRID) This achievement is obtained
More informationIRID Annual Research Report 2015
IRID Annual Research Report 05 5F, Toyokaiji Building, -- Nishi-Shimbashi, Minato-ku, Tokyo 05-000, Japan Main Phone Number:+8--645-860 URL http://irid.or.jp Printed on recycled paper. Published: July
More informationCurrent Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning
2017 IAEA General Conference, Side Events Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning @Vienna International Centre, Vienna September 18, 2017 Naohiro MASUDA Chief
More informationR&D for Fuel Debris Retrieval
R&D for Fuel Debris Retrieval at Fukushima Daiichi Nuclear Power Station June 2018 Kenro TAKAMORI International Research Institute for Nuclear Decommissioning (IRID) This achievement is obtained from the
More informationEstimation of current status inside RPV and PCV at Fukushima daiichi NPS
Estimation of current status inside RPV and PCV at Fukushima daiichi NPS July 3, 2017 Tokyo Electric Power Company Holdings, Incorporated Shinya Mizokami This document is based on the result of Subsidy
More informationOVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D
OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D 16 NOVEMBER, 2011 Hiroshi RINDO JAPAN ATOMIC ENERGY AGENCY Table of Contents 1. What s happened at Fukushima Dai-Ichi NPSs
More informationF, 3 Toyokaiji Building, Nishi-Shimbashi, Minato-ku, Tokyo , Japan Published: March 2016
Ever since its establishment in August 2013, the International Research Institute for Nuclear Decommissioning (IRID) has been fully committed to an urgent challenge research and development of technologies
More informationTechnical Strategic Plan for Decommissioning of the Fukushima Daiichi. Nuclear Power Station of. Tokyo Electric Power Company Holdings, Inc.
Technical Strategic Plan 2017 for Decommissioning of the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Holdings, Inc. Overview August, 2017 Nuclear Damage Compensation and Decommissioning
More informationAnnual Research Report
Annual Report 2017 5F, 3 Toyokaiji Building, 2-23-1 Nishi-Shimbashi,Minato-ku, Tokyo 105-0003,Japan Phone Number:+81-3-6435-8601 URL http://www.irid.or.jp/en Printed on recycled paper. Published: July
More informationThe Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station
The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station August 30, 2012 Tokyo Electric Power Company 2 Introduction Unit 4 reactor building has been damaged
More informationImportance of Innovation for D&D at Fukushima Daiichi NPS
Importance of Innovation for D&D at Fukushima Daiichi NPS March 5, 2014 Kazuhiro Suzuki International Research Institute for Nuclear Decommissioning 無断複製 転載禁止技術研究組合国際廃炉研究開発機構 International Research Institute
More informationCurrent Situation of Fukushima- Daiichi Nuclear Power Plants and Difficulties in the Defueling Plan
Current Situation of Fukushima- Daiichi Nuclear Power Plants and Difficulties in the Defueling Plan International Experts' Workshop on the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Plant
More information4. Current Status (1) Fukushima Daiichi Nuclear Power Station
4. Current Status (1) Fukushima Daiichi Nuclear Power Station 0 Plant Parameters (Fukushima Daiichi) as of October 12, 2012 at 5:00 RPV Water Injection [m 3 /h] FW Unit 1 2.9 Unit 2 2.1 Unit 3 2.1 CS 2.0
More informationApproaches to the decommissioning and contaminated water management for Fukushima Daiichi Nuclear Power Station
Nuclear Damage Compensation and Decommissioning Facilitation Corporation Approaches to the decommissioning and contaminated water management for Fukushima Daiichi Nuclear Power Station 1st International
More informationTopics Fukushima 15 September 2015 No.70
Topics Fukushima 15 September 2015 No.70 Examination of reactor cores using laser Analysis of elemental composition in fuel debris became possible How is the present situation of the reactor cores inside
More informationR&D of nuclear decommissioning under an integrated management sy
IRID gathers knowledge from aroun R&D of nuclear decommissioning under an integrated management sy Decommissioning of Fukushima Daiichi is unique, unprecedented and extremely difficult gathering global
More informationReplacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head
Unit 2, Genkai Nuclear Power Plant Replacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head Replacement works for the above components were conducted at Unit 2 of the Genkai
More informationThe 4th Progress Report
The 4th Progress Report on the Investigation and Examination of Unconfirmed and Unresolved Issues on the Development Mechanism of the Fukushima Daiichi Nuclear Accident December 17, 2015 Tokyo Electric
More informationAnnual Research Report 2016
Annual Research Report 2016 Printed on recycled paper. 5F, 3 Toyokaiji Building, 2-23-1 Nishi-Shimbashi,Minato-ku, Tokyo 105-0003,Japan Phone Number:+81-3-6435-8601 URL http://www.irid.or.jp/en Published:
More informationSide Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano
Side Event of IAEA General Conference Severe Accident Analyses of Fukushima-Daiich Units 1 to 3 Harutaka Hoshi and Masashi Hirano Japan Nuclear Energy Safety Organization (JNES) September 17, 2012 Side
More informationINTRODUCTION IN FUKUSHIMA WATER LEAK PROBLEM
U.P.B. Sci. Bull., Series C, Vol. 78, Iss. 1, 2016 ISSN 2286-3540 INTRODUCTION IN FUKUSHIMA WATER LEAK PROBLEM Radu SECAREANU 1, Ilie PRISECARU 2 The purpose of the paper is to present the water leak problem
More informationUnit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment
Summary of Decommissioning and Contaminated Water Management March 3, 217 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water Treatment Main decommissioning works and
More informationImplementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline)
Implementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline) December 7, 2012 Tokyo Electric Power Company 1 1. Post-Earthquake
More informationUnit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration
Summary of Decommissioning and Contaminated Water Management February 1, 2018 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water Treatment Main decommissioning works
More informationExpert Panel on Monju Decommissioning 6 th March 2018
1 Expert Panel on Monju Decommissioning 6 th March 2018 Steve Beckitt Chief Nuclear Officer DSRL 2 PFR Decommissioning Dounreay 3 Decommissioning Synergies Primary Systems 4 Decommissioning Synergies Primary
More informationRecommendations are based on validity of above assumptions.
RST Assessment offukushima Daiichi Units, UNIT ONE ASSUMPTIONS: (based on input from multiple data source: JAIF, NISA, TEPCO, & GEH) Core Status: Core is contained in the reactor pressure vessel, reactor
More informationR&D activities related to the fuel debris retrieval from the Fukushima Daiichi NPS
IAEA International Experts Meeting on Strengthening Research and Development Effectiveness in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant R&D activities related to the fuel debris
More informationFUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie
FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie The BWR reactor vessel spray(core spray) and feed water spray systems are designed to inject water into
More information150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS
ULEB 150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS WARNING: THIS FLUE KIT HAS BEEN MANUFACTURED IN ACCORDANCE WITH AS/NZS 2918:2001 AND TESTED TO APPENDIX F. TO ENSURE SAFETY THIS
More informationFukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami
Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami 14:46 March 11th 2011 (Please see Summary-1 report for detail.) Tohoku Pacific
More informationExamination into the reactor pressure increase after forced depressurization at Unit-2, using a thermal-hydraulic code
Attachment 2-9 Examination into the reactor pressure increase after forced depressurization at Unit-2, using a thermal-hydraulic code * This document is generated based on the evaluation upon contract
More information150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS
150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS WARNING: THIS FLUE KIT HAS BEEN MANUFACTURED IN ACCORDANCE WITH AS/NZS 2918:2001 AND TESTED TO APPENDIX F. TO ENSURE SAFETY THIS FLUE
More information150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS
150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS WARNING: THIS FLUE KIT HAS BEEN MANUFACTURED IN ACCORDANCE WITH AS/NZS 2918:2001 AND TESTED TO APPENDIX F. TO ENSURE SAFETY THIS FLUE
More informationDecommissioning of Dairyland Power s Lacrosse Boiling Water Reactor
Decommissioning of Dairyland Power s Lacrosse Boiling Water Reactor Dairyland Power Cooperative The plant achieved initial criticality in July, 1967. Full power was reached in August, 1969 and was declared
More informationEfforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station
Efforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station By Nuclear Accident Response Office, Agency for Natural Resources & Energy, Ministry of Economy, Trade & Industry Introduction
More informationSpecification (Summary version for reference)
Specification (Summary version for reference) 1. Item name Robot 1, for investigating the wall surfaces of the torus room (the detailed design of a device for investigating the underwater wall surfaces
More informationNUCLEAR. Nuclear Reactor Pressure Vessel Seals
NUCLEAR Nuclear Reactor Pressure Vessel Seals SEALING CONCEPT Technetics Group is the world s leading manufacturer of Nuclear Reactor Pressure Vessel (RPV) Closure Head Seals. In addition, Technetics Group
More informationOverview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station
Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station June 7, 2013 Fukushima Daini Nuclear Power Station 目的外使用 複製 開示禁止東京電力株式会社 0 The 2011 off the Pacific
More informationLessons learned from ongoing decommissioning project of Fugen NPS
Workshop on "Current and Emerging Methods for Optimizing Safety and Efficiency in Nuclear Decommissioning, Sarpsborg, Norway, 7th 9th February 2017 Lessons learned from ongoing decommissioning project
More informationUnit 1. Unit 2. Unit 3. PCV gas phase temperatures (recent quarter) * The trend graphs show part of the temperature data measured at multiple points.
Inflow into building (m 3 /day) Exposure dose (msv/year) I. Confirmation of the reactor conditions 1. Temperatures inside the reactors Through continuous reactor cooling by water injection, the temperatures
More informationStrategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori
Nuclear Damage Compensation and Decommissioning Facilitation Corporation Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori International
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationEfforts for the restoration at Fukushima Daiichi Nuclear Power Plants
PF3-2013-000001 PSN-2013-0069 Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants January 31, 2013 Executive Officer, Corporate Senior Vice president Chief Technology Executive, Power
More informationPIP PCEPA003 Process Analyzer System Field Installation Guidelines
January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities,
More informationNuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) and Strategic Plan for Decommissioning of Fukushima Daiichi NPS.
Nuclear Damage Compensation and Decommissioning Facilitation Corporation Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) and Strategic Plan for Decommissioning of Fukushima
More informationUnit 4. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration. Design and manufacturing of devices / equipment
Main decommissioning works and steps Summary of Decommissioning and Contaminated Water Management September 28, 2017 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water
More informationFukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka
No.58 Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka 3.4 Fukushima-4 Reactor When the earthquake and tsunami occurred on March 11th, Fukushima Unit 4 (F4) was in its periodic shut-down stage,
More informationCOFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping]
COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping] IRPA 12 12 th International Congress of the International Radiation Protection Association Buenos Aires,
More informationUnit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration
Summary of Decommissioning and Contaminated Water Management January 31, 2019 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water Treatment Main decommissioning works
More informationUNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY
Revision No.: New Page 1 of 10 I. PURPOSE Machine guarding is an essential element of providing a safe and healthful environment for employees and others in any facility. Serious injury can result from
More informationImmediate Countermeasures
September 3, 2013 Agency for Natural Resources and Energy, METI of Japan 2 nd Fact sheet: Overview of Contaminated Water Issue at TEPCO s Fukushima Daiichi NPS On June 19, 2013, TEPCO announced that ground
More informationMaintenance Technologies for SCC which Support Stable Operations of Pressurized Water Reactor Power Plants
Maintenance Technologies for which Support Stable Operations of Pressurized Water Reactor Power Plants KOJI OKIMURA* 1 MASAYUKI MUKAI* 1 KAZUHIKO KAMO* 2 NOBUYUKI HORI* 1 KOICHIRO MASUMOTO* 1 MASAAKI KUROKAWA*
More informationMVV ENVIRONMENT DEVONPORT SEPTEMBER 2017 OUTAGE MECHANICAL WORKS SPECIFICATION.
MVV ENVIRONMENT DEVONPORT SEPTEMBER 2017 OUTAGE MECHANICAL WORKS SPECIFICATION. SCOPE OF MECHANICAL WORK The following list of works details the mechanical works intended to be carried out on the plant
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationMid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO Digest Version
December 21, 2011 [Provisional Translation] Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCODigest Version 1. Story behind the Mid-and-long-term
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationUK ABWR - NEW NPP DESIGN FOR UK
IAEA PLiM2017 [IAEA-CN-246-085] UK ABWR - NEW NPP DESIGN FOR UK 25-October-2017 Kazuhiro YOSHIKAWA Masaaki HAYASHI Yasuhiro MABUCHI Daisuke TANIGUCHI Hitachi-GE Nuclear Energy, Ltd. Contents 1. Introduction
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationThe EPR Reactor: Evolution to Gen III+ based on proven technology. Andrew Teller, Senior Technical Advisor, AREVA
The EPR Reactor: Evolution to Gen III+ based on proven technology Andrew Teller, Senior Technical Advisor, AREVA Building on the Achievements of the N4 and Konvoi Reactors N4 KONVOI High output (1475MWe)
More informationProgress Status Classified by Countermeasures
Progress Status Classified by :Progressed (Legend color changed) Legend Implemented Under construction Field work started, but construction not started Appendix 2 Field work not started yet Areas Issues
More informationUnit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment
Summary of Decommissioning and Contaminated Water Management April 27, 217 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water Treatment Main decommissioning works and
More informationImmediate Countermeasures
September 3, 2013 Agency for Natural Resources and Energy, METI of Japan 2 nd Fact sheet: Overview of Contaminated Water Issue at TEPCO s Fukushima Daiichi NPS On June 19, 2013, TEPCO announced that ground
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationConergy SolarFamulus II
Conergy SolarFamulus II Installation manual www.conergy.com Table of Contents Table of Contents SolarFamulus II for universal use on flat roofs 1 Introduction 1 1.1 Short description 1 1.2 Intended use
More informationNEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS
NEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS Anders Lindström, Bo Wirendal and Maria Lindberg Studsvik Nuclear AB Department RadWaste SE 611 82 Nyköping Sweden ABSTRACT The project that
More informationRevised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4
Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4 Tatsuya Shinkawa Director, Nuclear Accident Response Office, Agency for Natural Resources and Energy,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More information15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview
Evaluation of the report of Tokyo Electric Power Company regarding the inflow of water that accumulated in the process main building into the incineration building at the Fukushima Daiichi Nuclear Power
More informationBerkeley Boilers Project. Studsvik Symposium April 2014
Berkeley Boilers Project Studsvik Symposium April 2014 Berkeley NPP Twin Magnox Reactors Operating 1962 1989 First UK commercial reactor to enter decommissioning Currently managed on behalf of the Nuclear
More informationAccident Progression & Source Term Analysis
IAEA Training in Level 2 PSA MODULE 4: Accident Progression & Source Term Analysis Outline of Discussion Overview of severe accident progression and source term analysis Type of calculations typically
More informationh Installation Manual
h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires
More informationWest Valley Demonstration Project. Project Update
West Valley Demonstration Project Project Update Craig Rieman February 24, 2010 Citizen Task Force 20475_1 Safety Performance As of February 19, 2010, WVDP employees have worked more than 2.3 million hours
More informationRegulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station
Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station July 3, 2017 Hiroshi YAMAGATA Nuclear Regulation Authority (NRA), Japan 1 Contents Contaminated water Radioactive
More informationMechanical Structure Design Features of the KALIMER-600 Sodium-cooled Fast Reactor
Mechanical Structure Design Features of the KALIMER-600 Sodium-cooled Fast Reactor Jae-Han Lee 1, Chang-Gyu Park 1, Jong-Bum Kim 1, and Gyeong-Hoi Koo 1 1) Fast Reactor Development Group, Korea Atomic
More informationThe 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations
The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place:
More informationMajor Influential Issues on the Accident Progressions of Fukushima Daiichi NPP
1/12 Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP Summary M. Naitoh, M. Pellegrini. H. Suzuki, H. Mizouchi, and H. Okada The Institute of Applied Energy, Japan This paper
More informationInstallation Instructions
Installation Instructions Flue Gas System Basic Kit GA-K - Chimney Flue Gas System for GB125 Oil Condensing Boiler For trained and certified installers Please read carefully prior to installation. 6 720
More informationAREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals
AREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals Jan Hendrik Bruhn GmbH/ IBRZ-G Varna, June 10 th 2010 Content General Requirements for Dismantling Projects Stade NPP
More informationUnit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration
Summary of Decommissioning and Contaminated Water Management December 21, 2017 Secretariat of the Team for Countermeasures for Decommissioning and Contaminated Water Treatment Main decommissioning works
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationResults of the Sixth Soundness Inspection of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station
Results of the Sixth Soundness Inspection of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station August 28, 213 Tokyo Electric Power Company 1. Purpose of Inspection Unit 4 Reactor Building
More informationInstallation Manual For Conical Tanks. INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS
INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS Page 1 of 10 INDEX 1. Health & Safety 3 2. Introduction 3 3. Requirements 3 4. Working Area 3 5. Equipment 3 6. 2 and 3 metre tank above ground
More informationIRID Annual Research Report
IRID Annual Research Report 2014 Printed on recycled paper. Published: March 2015 Contents Greetings This report presents a collection of the results of the Research & Development (R&D) projects which
More informationFukushima Daiichi Decontamination and Decommissioning : Current Status and Challenges. Alios Iwaki Performing Arts Center August 6, 2018.
The 3 rd International Forum on the Decommissioning of the Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Decontamination and Decommissioning : Current Status and Challenges Alios Iwaki Performing
More informationNRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station
NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station September 18, 2017 Yutaka HARA Nuclear Regulation Authority (NRA), Japan 1 Contents Approach in NRA s Regulation
More informationOutline of New Safety Standard (Design Basis) (DRAFT) For Public Comment
Provisional Translation (Feb.13,2013 Rev.0) February 6, 2013 Outline of New Safety Standard (Design Basis) (DRAFT) For Public Comment 0 February 6, 2013 Outline of New Safety Standard (Design Basis) (DRAFT)
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationElectrical Isolation
Electrical Isolation Period 6 Practical Applications 2017 February 21-23, 2017 Mark E. Anderson M.T.S 1 Introduction Common isolating fittings & their installation Uses & locations of isolating fittings
More informationFukushima Daiichi Nuclear Power Station Unit No.1
Fukushima Daiichi Nuclear Power Station Unit No.1 Report on Earthquake Response Analysis of the Reactor Building, Important Equipment and Piping System for Seismic Safety using Recorded Seismic Data of
More informationPassive Heat Removal System Testing Supporting the Modular HTGR Safety Basis
Passive Heat Removal System Testing Supporting the Modular HTGR Safety Basis Various U.S. Facilities Office of Nuclear Energy U.S. Department of Energy Jim Kinsey Idaho National Laboratory IAEA Technical
More information2. Roadmap towards Restoration from the Accident
2. Roadmap towards Restoration from the Accident (Step 2 Completed on December 16, 2011) All Rights Reserved 2011The Tokyo Electric Power Company, Inc. 0 Summery of the Step 2 Completion of Roadmap towards
More informationNDE SOLUTIONS INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION
INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION Specialists in nondestructive examination has specialized in automated nondestructive testing of nuclear reactor primary components and more specifically on steam
More informationMid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO
(Provisional translation) Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO December 21, 2011 Nuclear Emergency Response Headquarters Government
More informationTRANSPORTATION AND OTHER DAMAGE
TRANSPORTATION AND OTHER DAMAGE Effects of Wind Contact with an overpass Wind fallen tree damage Contact with a guard rail Contractor doing repairs for transit damage done by a transporter while shipping
More information