1 Ellund capacity - Creating new capacity at Ellund (DE) Maja Klejs Pedersen and Poul Johannes Jacobsen 11 December 2014 User Group 1

2 Capacity maximisation CAM Article 6 Energinet.dk sees two options We request your input Timeline: 11 Dec. 14: User group Input is welcome until 15 Jan. 15: sent to DERA 1 Oct. 15: effective 11 December 2014 User Group 2

3 Capacity situation at Ellund Firm, 1 Jan Ellund Border GUD: 1,191,000 OGE: 171,616 GUD: 1,191,000 OGE: 171,616 kwh/h Denmark Germany Energinet.dk GUD and OGE Numbers are in million kwh/h The problem! How to solve it? GUD: 0 OGE: 0 GUD: 4,215,200 OGE: 0 kwh/h Available capacity = Blue Technical capacity = Black Future new capacity has already been allocated to Open Season contracts - GUD 11 December 2014 User Group 3

4 Keep in mind - Ellund flow lasts 3 months Mainly southbound from September to December 11 December 2014 User Group 4

5 Capacity situation at Ellund Firm - Two potential solutions 1. Flow commitment 2. Counter-Flow Nomination Right with a twist Two ways to reach the same goal Let us know which you prefer 11 December 2014 User Group 5

6 Capacity situation at Ellund Firm - Two potential solutions 1. Flow commitment 2. Counter-Flow Nomination Right with a twist Two ways to reach the same goal Let us know which you prefer 11 December 2014 User Group 6

7 Flow Commitment Size of FC Ellund Border Denmark Germany Germany from 2016: Long products are expected to be less costly than short products Energinet.dk GUD and OGE 11 December 2014 User Group Numbers are in million kwh/h Available capacity = Blue Technical capacity = Black Question 1 What capacity do you prefer? Yearly Quarterly Monthly Daily New firm capacity Fact: Daily capacity is available via the German shortterm UIOLI

8 Flow Commitment Shipper requirements Denmark Germany Size of FC Energinet.dk GUD and OGE Numbers are in million kwh/h Available capacity = Blue Technical capacity = Black Energinet.dk requirements in relation to shippers: 1. Holding Ellund Capacity: Firm (DK) and Firm (DE) GUD or OGE (e.g. must be booked as year or quarter products, in order to create a month product) (only available as bundled cap.) New firm capacity 2. Nomination restrictions See next slide 11 December 2014 User Group 8

9 Flow Commitment Nomination restriction Denmark Germany Size of FC Energinet.dk GUD and OGE Numbers are in million kwh/h Two options: 1. Shipper controls capacity, except when he is requested to flow gas Lead time: 4 hours 2. Nominations are locked in due New time in firm view of marketing of capacity the product on PRISMA E.g. the 1 st Monday prior to the month, if a month product No renomination right Available capacity = Blue Technical capacity = Black Question 2 Which option do you prefer? 11 December 2014 User Group 9

10 The new firm capacity Denmark Energinet.dk Question 3 If flow-commitment supply is higher than maximum demand, should we use: Pro rata? Auctions? New capacity will be equal to the flow commitment Germany Size of FC GUD and OGE Numbers are in million kwh/h Available capacity = Blue Technical capacity = Black Maximum new capacity is equal to technical entry capacity in Germany Will be sold on PRISMA e.g. Monthly, rolling to daily and within-day 11 December 2014 User Group 10

11 Payment of flow commitment Question 4 Views on the payment? Denmark Germany Size of FC Energinet.dk GUD and OGE Numbers are in million kwh/h Available capacity = Blue Technical capacity = Black Gas flow has lately been southbound Energinet.dk therefore proposes to pay a sum equivalent to the capacity charge Ellund DK This means that only volume tariff will be paid in DK In Germany, normal tariffs will be paid (Interruptible will have a 10% price discount) 11 December 2014 User Group 11

12 Capacity situation at Ellund Firm - Two potential solutions 1. Flow commitment 2. Counter-Flow Nomination Right with a twist Two ways to reach the same goal Let us know which you prefer 11 December 2014 User Group 12

13 Counter-Flow Nomination Right with a twist Counter-Flow Nomination Right (CFNR) an option at GUD today Here with a twist to release firm e.g. monthly capacity on the Germany side Denmark Today Energinet.dk Ellund Border New CFNR-WT product Nomination: 1st Monday month-1 (final) Reduced Tariff 3 2 Germany GUD New firm e.g. monthly capacity offered on PRISMA 11 December 2014 User Group 13

14 CFNR-WT: Linking contracts Links between contract 3 and 2 in the Danish system, and info on contract 1 and 4 in DE Flow on contract 3 <= 2 Same flow in contract 2 and 1, and in 3 and 4 as they have the same nomination due to lesser off rule The new capacity offered (5) will be = to the capacity (3) All contracts must be firm Question 1 (again) What capacity do you prefer? Yearly Quarterly Monthly Daily Denmark Germany Energinet.dk Ellund Border GUD New CFNR-WT product Nomination: 1st Monday month-1 (final) Reduced Tariff 11 December 2014 User Group New firm e.g. monthly capacity offered on PRISMA 5

15 CFNR-WT: Nomination limitations Example with a month product: Nominations are locked on the 1st Monday prior to the month. PRISMA Calendar for Monthly products: Example November Cap 3 rd Monday - Start of AUCTION 20 October nd Monday Publication of amount of capacity 13 October st Monday Nominations are locked 06 October 2014 This is the final nomination no renomination right For all four contracts, listed no. 1 to 4 on the previous slide. 11 December 2014 User Group 15

16 CFNR-WT: Tariff recommendation Tariff recommendation (Denmark): A. Volume tariff at exit: full payment B. Capacity tariff at exit: no capacity tariff Question 4 (again) Views on the payment? The shipper buys firm capacity The shipper has the capacity part refunded after the period, when it has been verified that the Shipper has lived up to his obligation. In Germany, normal tariffs are paid (Interruptible will have a 10% price discount) 11 December 2014 User Group 16

17 Comparison Question 5 Which of the two products do you prefer? Flow Commitment CFNR-WT Not linked to other capacities Linked to import capacity An option in GUD and OGE Only available in GUD Max cap. 1,362,616 kwh/h Max. cap. 4,215,200 kwh/h 11 December 2014 User Group 17

18 Final question Question 6 Should any of these new products be applied on other locations? Nybro Dragør? 11 December 2014 User Group 18

19 Test year 1. This product and the tariff are intended for a 1-year test period 1. After 1 year, there will be an evaluation e.g.: Is there a need for the product? Is the tariff at the right level? Does the product function as intended? Would other products be better? 11 December 2014 User Group 19

20 Thank You! We request your input Timeline: 11 Dec. 14: User group Input is welcome until 15 Jan. 15: sent to DERA 1 Oct. 15: effective 11 December 2014 User Group 20

21 New Capacity in Ellund - Questions Question 1 What capacity do you prefer? Yearly Quarterly Monthly Daily Question 6 Should new products be applied on other locations? Nybro Dragør Question 2 (nominations) What is the preferred option? 1. TSO option to change nomination Lead time: 4 hours 2. Nominations are locked e.g. 1 month before and no renomination Question 3 If flow-commitment supply is higher than maximum demand, should we use: Pro rata? Auctions? Question 5 Question 4 Views on the payment? Which of the two products do you prefer? 11 December 2014 User Group 21

22 New Capacity in Ellund - Answers 1/2 1. What capacity do you prefer: Main conclusion Daily products - are enough for trading Monthly products - good for supply obligations Discussion included: Shipper: Cannot see that there is a need for this product Energinet.dk: How can a new shipper come into the Danish market, if no firm capacity is available? Shipper: Not a problem, possible to buy interruptible capacity it is not likely to be interrupted. Energinet.dk: Referring to the work of the EU commission: Although the individual shippers' preferences differ, during the Public Consultation the stakeholders generally agreed that in order to be able to compete for customers, they need firm long term capacity rights. [Commission staff working document (on CMP), Brussels , p. 5] 2. What is the preferred option (TSOs to control nomination)? No real feedback 3. If there is a need to restrict the volume of the product, which method should be used? Main conclusion Auctions the lowest bids win Discussion included: Shipper: Preference for simulations auctions, where the size of the flow commitment acquired (southbound flow) is determined by the size of the Ellund (DE) demand (capacity for northbound flow). Energinet.dk: This is a good suggestion, but not possible to implement in practice. A TSO cannot sell firm capacity which it does not have. It therefore needs to acquire the firm capacity prior to selling it. 11 December 2014 User Group 22

23 New Capacity in Ellund - Answers 2/2 4. Views on proposed payment? Main conclusion CFNR does not move gas, therefore should no volume tariff be applied Concerns on who shall pay, if this does not lead to new Ellund revenue ( DK) Discussion included: Shipper: There are two different products, therefore should there be two different prices. Shipper: The CFNR product is designed to cancel a Northbound gas flow already nominated by the shipper. Danish entry capacity has already been paid for and CFNR sees to that no gas is moved, therefore no further costs should apply - neither capacity, nor volume tariff. 5. Which of the two products do you prefer? Main conclusion Some say YES to both products want a choice Some say NO to both products Discussion included: Shipper: Why not offer both products? This gives a choice for the shipper to select the product which best suits this situation. Creates more opportunities in the market. Shipper: Another way to create available firm capacity on the German side is to have Open Season contract holders to sell some of there capacity. 6. Should new products be applied on other locations? Main conclusion No direct reply, probably most relevant in Ellund Comments are welcome planed to be sent to DERA on the 15 th of January December 2014 User Group 23

Exhibit G to the General Terms and Conditions Forward Flow as of 2018

Exhibit G to the General Terms and Conditions Forward Flow as of 2018 CAM and CMP implementation and general rules General provisions Terms defined in the Conditions shall have the same meaning when used herein. This Exhibit G shall form part of the Conditions as amended

More information

Exhibit G to the General Terms and Conditions Forward Flow as of 2018

Exhibit G to the General Terms and Conditions Forward Flow as of 2018 CAM and CMP implementation and general rules General provisions Terms defined in the Conditions shall have the same meaning when used herein. This Exhibit G shall form part of the Conditions as amended

More information

Exhibit G to the General Terms and Conditions Forward Flow November 2015

Exhibit G to the General Terms and Conditions Forward Flow November 2015 CAM and CMP implementation and general rules Introduction In this Exhibit G BBL Company sets out the conditions following from the implementation of CAM and CMP. This exhibit G is not exhaustive because

More information

APPENDIX E.1: PROCEDURE FOR THE MARKETING OF CAPACITIES AT THE PIRINEOS VIRTUAL INTERCONNECTION POINT

APPENDIX E.1: PROCEDURE FOR THE MARKETING OF CAPACITIES AT THE PIRINEOS VIRTUAL INTERCONNECTION POINT APPENDIX E.1: PROCEDURE FOR THE MARKETING OF CAPACITIES AT THE PIRINEOS VIRTUAL INTERCONNECTION POINT Version dated [01/04/2017] NOTICE The purpose of this document is to describe in detail the procedures

More information

Exhibit G to the General Terms and Conditions Forward Flow as of 2018November 2015

Exhibit G to the General Terms and Conditions Forward Flow as of 2018November 2015 CAM and CMP implementation and general rules General provisions Terms defined in the Conditions shall have the same meaning when used herein. This Exhibit G shall form part of the Conditions as amended

More information

Network Code. on Capacity Allocation Mechanisms

Network Code. on Capacity Allocation Mechanisms 6 March 2012 Network Code on Capacity Allocation Mechanisms An ENTSOG Network Code for ACER review and Comitology Procedure This document constitutes the Capacity Allocation Mechanisms Network Code developed

More information

Stakeholder Workshop II

Stakeholder Workshop II Brussels, 30 June 2015 Stakeholder Workshop II On issues related to bundling of capacities Brussels, 30 June 2015 Disclaimer This presentation does not reflect a commitment content wise nor time wise for

More information

Workshop CAM, CMP. GTS shippermeeting, 21 November 2012

Workshop CAM, CMP. GTS shippermeeting, 21 November 2012 Workshop CAM, CMP GTS shippermeeting, 21 November 2012 1 Chatham house rule When a meeting, or part thereof, is held under the Chatham House Rule, participants are free to use the information received,

More information

EU Gas Market Reform what does it mean in practice?

EU Gas Market Reform what does it mean in practice? EU Gas Market Reform what does it mean in practice? Alex Barnes, Head of Regulatory Affairs Energy Forum 2012 Vilnius 18 th December 2012 European gas markets are facing major changes... DG ENERGY / ACER

More information

European Developments

European Developments European Developments Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission Workgroup

More information

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Practices for Grid Code Harmonization Examining Capacity Allocation and Congestion Management Fotis Thomaidis Partner,

More information

Introduction of Entry Capacity to Northern Ireland Transitional Arrangements

Introduction of Entry Capacity to Northern Ireland Transitional Arrangements Introduction of Entry Capacity to Northern Ireland Transitional Arrangements Business Rules Revised Post-Consultation Version 1.1 13 th October 2014 Contents 1. Introduction: Background and Purpose...

More information

Coordinated implementation of the Network Code on Capacity Allocation Mechanisms. Information Memorandum

Coordinated implementation of the Network Code on Capacity Allocation Mechanisms. Information Memorandum Coordinated implementation of the Network Code on Capacity Allocation Information Memorandum February 2014 INDEX Disclaimer... 4 1 Background... 5 2 Auctions... 6 2.1 2014 auctions... 6 2.2 2015 auctions

More information

SIKKERHEDSGUIDE NØDUDGANGE HJERTESTARTER SAMLINGSSTED

SIKKERHEDSGUIDE NØDUDGANGE HJERTESTARTER SAMLINGSSTED SIKKERHEDSGUIDE NØDUDGANGE HJERTESTARTER SAMLINGSSTED USER GROUP ON TARIFFS 4 October 2017 Nina Synnest Sinvani Dok. nr. 17/03101-27 2 AGENDA This is the second User Group in the process of implementing

More information

Find out more about. Capacity subscriptions at Obergailbach, Virtualys, Taisnières B and Oltingue PIR

Find out more about. Capacity subscriptions at Obergailbach, Virtualys, Taisnières B and Oltingue PIR Find out more about Capacity subscriptions at Obergailbach, Virtualys, Taisnières B and Oltingue PIR + + You are active on GRTgaz upstream network and want to subscribe for capacity at Network Interconnection

More information

on the conditions for the application of FDA UIOLI pursuant to paragraph a) - d) of the CMP Guidelines

on the conditions for the application of FDA UIOLI pursuant to paragraph a) - d) of the CMP Guidelines Case Id: 3a123382-8301-48f8-a8f7-a674b1c3a961 Date: 19/09/2016 11:44:04 ACER Call for Evidence on the conditions for the application of FDA UIOLI pursuant to paragraph 2.2.3.1 a) - d) of the CMP Guidelines

More information

Gas Transmission Charging Methodology Statement. Gas Year 2016/17

Gas Transmission Charging Methodology Statement. Gas Year 2016/17 Gas Transmission Charging Methodology Statement Gas Year 2016/17 Contents 1. Introduction... 3 Part A - POSTALISED CHARGES... 6 2. Process for setting Forecast Postalised Charges... 6 3. Calculation of

More information

Roadmap for early implementation of the Network Code on Capacity Allocation Mechanisms (CAM NC)

Roadmap for early implementation of the Network Code on Capacity Allocation Mechanisms (CAM NC) Roadmap for early implementation of the Network Code on Capacity Allocation Mechanisms (CAM NC) 1 st EU Stakeholders meeting Brussels, 6 March 2013 Agenda AGENDA TOPICS INDICATIVE TIMING 1. Opening and

More information

Gas Transmission Charging Methodology Statement. Gas Year 2017/18

Gas Transmission Charging Methodology Statement. Gas Year 2017/18 Gas Transmission Charging Methodology Statement Gas Year 2017/18 Contents 1. Introduction... 3 Part A - POSTALISED CHARGES... 6 2. Process for setting Forecast Postalised Charges... 6 3. Calculation of

More information

ENTSOG s Capacity conversion model

ENTSOG s Capacity conversion model 2017-07-24 ENTSOG AISBL; Av. de Cortenbergh 100, 1000-Brussels; Tel: +32 2 894 5100; Fax: +32 2 894 5101; info@entsog.eu, www.entsog.eu, VAT No. BE0822 653 040 Background On October 13 th, 2016 the amendment

More information

Brussels/Ljubljana, TITRE 1 April 2015

Brussels/Ljubljana, TITRE 1 April 2015 Open House meeting Stakeholder input for ACER s recommendation on the Network Code on rules regarding harmonised Transmission tariff structures for gas Brussels/Ljubljana, TITRE 1 April 2015 1 Agenda Agenda

More information

Entry Point Registrations

Entry Point Registrations Entry Point Registrations Business Rules Revised Post-Consultation Version 1.1 13 th October 2014 Contents 1. Introduction... 3 2. Relevant Context... 3 3. Entry Point Registrations - Principles... 4 4.

More information

Tariff Network Code. An Overview

Tariff Network Code. An Overview Tariff Network Code An Overview SEPTEMBER 2018 Content INTRODUCTION................. 2 AIM OF THE CODE............... 4 DESCRIPTION OF KEY ELEMENTS... 6 SCOPE...........................................

More information

APPENDIX B.1: RULES FOR SUBSCRIPTION AND ALLOCATION ON THE MAIN NETWORK. Version dated [01/11/2017]

APPENDIX B.1: RULES FOR SUBSCRIPTION AND ALLOCATION ON THE MAIN NETWORK. Version dated [01/11/2017] APPENDIX B.1: RULES FOR SUBSCRIPTION AND ALLOCATION ON THE MAIN NETWORK Version dated [01/11/2017] 1 Description of the capacity offer on the main network The daily capacities marketed on the main network

More information

European Update. 2nd July 2015

European Update. 2nd July 2015 European Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 2nd July 2015 1. General Update

More information

EXIT DEFRIBILLATOR (AED) MEETING POINT

EXIT DEFRIBILLATOR (AED) MEETING POINT HOST EMERGENCY EXIT DEFRIBILLATOR (AED) MEETING POINT SHIPPERS FORUM 15 March 2018 2 14.20 Coffee break and networking PROGRAMME 12.00 Lunch and networking 13.00 Welcome Clement Johan Ulrichsen, Energinet

More information

Official Journal of the European Union. (Non-legislative acts) REGULATIONS

Official Journal of the European Union. (Non-legislative acts) REGULATIONS 17.3.2017 L 72/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and

More information

Draft position paper for consultation. Exploring the feasibility of implicit allocation in the (North West) European gas market

Draft position paper for consultation. Exploring the feasibility of implicit allocation in the (North West) European gas market Draft position paper for consultation Exploring the feasibility of implicit allocation in the (North West) European gas market The Hague, 1 October 2012 1 / 16 1 Introduction 1.1 Background The Council

More information

EU Gas Market Reform what does it mean in practice?

EU Gas Market Reform what does it mean in practice? EU Gas Market Reform what does it mean in practice? Alex Barnes, Head of Regulatory Affairs Energy Forum 2012 Vilnius 18 th December 2012 European gas markets are facing major changes... DG ENERGY / ACER

More information

EU Network Code Implementation Project

EU Network Code Implementation Project EU Network Code Implementation Project Frequently Asked Questions Version 3.0 1 Contents 1. Introduction... 3 1.1. New Questions... 3 2. General... 3 2.1. CAM Network Code: Background and Scope... 3 2.2.

More information

Market Consultation Session

Market Consultation Session Market Consultation Session February 19, 2013 Fluxys non-binding document for discussion & information purposes only (subject to managment approval) Objective of today s session Feedback on consultation

More information

1. Part 1: Introduction Overview of suggested measures and changes Part 2: Process for market involvement... 3

1. Part 1: Introduction Overview of suggested measures and changes Part 2: Process for market involvement... 3 Tyra shutdown 2019-2022 - Market Consultation 1/21 Energinet Tonne Kjærsvej 65 DK-7000 Fredericia MEMO TYRA SHUTDOWN 2019-2022 2022 - MARKET CONSULTATION +45 70 10 22 44 info@energinet.dk VAT no. 28 98

More information

European Network Code Workshop

European Network Code Workshop European Network Code Workshop Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Gas European

More information

The Baltic Pipe Project

The Baltic Pipe Project The Baltic Pipe Project Open Season Process Julie Frost Szpilman Klassificering: 1 Agenda Presentation of the Baltic Pipe Project Presentation of the planned Open Season Process Latest news of Tyra 2 The

More information

Framework Guidelines on Capacity Allocation Mechanisms for the European Gas Transmission Network FG-2011-G August 2011

Framework Guidelines on Capacity Allocation Mechanisms for the European Gas Transmission Network FG-2011-G August 2011 Framework Guidelines on Capacity Allocation Mechanisms for the European Gas Transmission Network FG-2011-G-001 3 August 2011 Agency for the Cooperation of Energy Regulators Trg Republike 3 1000 Ljubljana

More information

PRISMA Auction of OMV Gas Storage GmbH on 1 March Product Information & Marketing Procedure. Baumgarten / CEGH (VTP) OMV Gas & Power

PRISMA Auction of OMV Gas Storage GmbH on 1 March Product Information & Marketing Procedure. Baumgarten / CEGH (VTP) OMV Gas & Power PRISMA Auction of on 1 March 2018 Product Information & Marketing Procedure Baumgarten / CEGH (VTP) OMV Gas & Power 1. operates gas storage facilities in Austria for more than 40 years. Our Customers benefit

More information

Towards efficient and effective congestion management of the European gas transmission network:

Towards efficient and effective congestion management of the European gas transmission network: Amstelveenseweg 998 1081 JS Amsterdam Phone: + 31 20 520 7970 Email: secretariat@efet.org Website: www.efet.org Towards efficient and effective congestion management of the European gas transmission network:

More information

The catalog is updated at least when new data is published in the Energi Data Service, and consists of the following two parts:

The catalog is updated at least when new data is published in the Energi Data Service, and consists of the following two parts: This data catalog provides a comprehensive overview of the data and datasets in Energi Data Service. The data catalog is based entirely on metadata, and is aimed at all present and potential users of Energi

More information

THE BALTIC PIPE PROJECT APPENDIX 3.D. - STANDARD FRAMEWORK AGREEMENT (APPENDIX 2 OF THE RULES FOR GAS TRANSPORT) FOR MARKET CONSULTATION

THE BALTIC PIPE PROJECT APPENDIX 3.D. - STANDARD FRAMEWORK AGREEMENT (APPENDIX 2 OF THE RULES FOR GAS TRANSPORT) FOR MARKET CONSULTATION THE BALTIC PIPE PROJECT - STANDARD FRAMEWORK AGREEMENT (APPENDIX 2 OF THE RULES FOR GAS TRANSPORT) FOR MARKET CONSULTATION 6 December 2016 1 Shipper Framework Agreement between the Shipper and Energinet.dk

More information

Demand assessment report for the incremental capacity process starting 2017 between Denmark and GASPOOL

Demand assessment report for the incremental capacity process starting 2017 between Denmark and GASPOOL Demand assessment report for the incremental capacity process starting 2017 between Denmark and GASPOOL 2017-07-27 This report is a joint assessment of the potential for incremental capacity projects conducted

More information

Consultation on the integration of gas markets of Czech Republic and Austria

Consultation on the integration of gas markets of Czech Republic and Austria Consultation on the integration of gas markets of Czech Republic and Austria TABLE OF CONTENTS A. INTRODUCTION... 3 B. OBJECTIVE OF THE CONSULTATION... 5 C. RULES OF THE PUBLIC CONSULTATION... 5 D. THE

More information

Gas Charging Review. NTSCMF 6 September 2016 Interim Slide Pack - Update to be provided on 1 September 2016.

Gas Charging Review. NTSCMF 6 September 2016 Interim Slide Pack - Update to be provided on 1 September 2016. Gas Charging Review Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. NTSCMF 6 September 2016

More information

Demand assessment report for the incremental capacity process starting 2017 between Denmark and NetConnect Germany

Demand assessment report for the incremental capacity process starting 2017 between Denmark and NetConnect Germany Demand assessment report for the incremental capacity process starting 2017 between Denmark and NetConnect Germany 2017-07-27 This report is a joint assessment of the potential for incremental capacity

More information

EU Code Implementation Programme

EU Code Implementation Programme EU Code Implementation Programme Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission

More information

COMMISSION STAFF WORKING DOCUMENT. Guidance on best practices for congestion management procedures in natural gas transmission networks

COMMISSION STAFF WORKING DOCUMENT. Guidance on best practices for congestion management procedures in natural gas transmission networks EUROPEAN COMMISSION Brussels, 11.7.2014 SWD(2014) 250 final COMMISSION STAFF WORKING DOCUMENT Guidance on best practices for congestion management procedures in natural gas transmission networks EN EN

More information

Overview of issues, solutions and open questions in the CAM NC early implementation process

Overview of issues, solutions and open questions in the CAM NC early implementation process Overview of issues, solutions and open questions in the CAM NC early implementation process Information for 2 nd CAM Roadmap groups meetings ACER Ljubljana 18 September 2013 Issues and open questions being

More information

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Contextualizing Transmission Grid Codes in the Natural Gas System - The Intersection of Transmission and Distribution

More information

UNC 0616: Capacity Conversion Mechanism for Interconnection Points. UNC Modification. 01 Modification. 02 Workgroup Report

UNC 0616: Capacity Conversion Mechanism for Interconnection Points. UNC Modification. 01 Modification. 02 Workgroup Report UNC Modification UNC 0616: Capacity Conversion Mechanism for Interconnection Points At what stage is this document in the process? 01 Modification 02 Workgroup Report 03 04 Draft Modification Report Final

More information

22 February 2017 Cork

22 February 2017 Cork VRF Workshop 22 February 2017 Cork 1 Agenda 1. Introduction and EU Context 2. Review of Existing VRF Product Processes Usage to date 3. Industry Views on VRF Tariffing Structure 4. Discussion 5. Next Steps

More information

Gas Charging Review. NTSCMF 5 April 2017 Final slide pack Update provided on 3 April All slides added or updated are marked with a blue star

Gas Charging Review. NTSCMF 5 April 2017 Final slide pack Update provided on 3 April All slides added or updated are marked with a blue star Gas Charging Review Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. NTSCMF 5 April 2017 Final

More information

ACER and the Transparency Platform

ACER and the Transparency Platform ACER and the Transparency Platform Csilla Bartók Team Leader Network Codes, Gas Department ENTSOG 11 th Transparency Workshop Vienna, 6 December 2017 ACER s transparency assessment - Background The legal

More information

Network codes workshop

Network codes workshop 4 October 2017 ENTSOG capacity model 2017 Network codes workshop Jan Vitovský Subject Manager, Capacity, ENTSOG Capacity according to Art. 21 CAM NC 1. As from 1 January 2018, transmission system operators

More information

Introducing PRISMA European Capacity Platform

Introducing PRISMA European Capacity Platform Introducing PRISMA European Capacity Platform Background of the company and current developments Allocation of Gas Transmission Capacities in the Energy Community Workshop 14 March 2016, Vienna Agenda

More information

GTE+ Capacity Product Coordination First Phase Report

GTE+ Capacity Product Coordination First Phase Report First Phase Report Rue Ducale 83 Tel +32 2 209 05 00 gie@gie.eu.com B 1000 Brussels Fax +32 2 209 05 01 www.gie.eu.com Gas Infrastructure Europe (GIE) represents the interest of the infrastructure industry

More information

Interconnector (UK) Limited. IUK Access Code

Interconnector (UK) Limited. IUK Access Code Interconnector (UK) Limited IUK Access Code Issue 5 March 2018 Contents SECTION A INTRODUCTION... 1 1. IUK Access Code... 1 2. Transportation Services... 1 3. Nominations and Matching Procedures... 1 4.

More information

NATURAL GAS TRANSPORTATION SERVICES PROVIDED BY IUK BETWEEN GB AND BELGIUM

NATURAL GAS TRANSPORTATION SERVICES PROVIDED BY IUK BETWEEN GB AND BELGIUM NATURAL GAS TRANSPORTATION SERVICES PROVIDED BY IUK BETWEEN GB AND BELGIUM Issue 5 March 2018 www.interconnector.com DISCLAIMER This IUK Access Agreement Summary ( IAAS ) has been prepared by Interconnector

More information

Business Rules. Incremental Proposal

Business Rules. Incremental Proposal INC00148-14 2 April 2014 DRAFT Business Rules I. Introduction The objective of this document is to specify business rules based on the ACER Guidance for the amendment on the CAM NC and the ACER Tariff

More information

Financial Transmission Rights

Financial Transmission Rights PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM

More information

Virtual Workshop on PJM ARR and FTR Market 2017/2018

Virtual Workshop on PJM ARR and FTR Market 2017/2018 Virtual Workshop on PJM ARR and FTR Market 2017/2018 PJM State & Member Training Dept. Webex February 10, 2017 PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information

More information

Gas transmission Technical and Economic Aspects for TSOs

Gas transmission Technical and Economic Aspects for TSOs European Summer School 2015 Economic and Legal Aspects of the Electricity, Gas and Heat Market Gas transmission Technical and Economic Aspects for TSOs Ina Adler (ONTRAS Gastransport GmbH) 1 Agenda 1.

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 4: Forward Capacity Auction Prepared by: Alberta Electric System Operator Date: January 26, 2018 Table of Contents

More information

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. Version 2.

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. Version 2. Virtual Reverse Flow: at Interconnection Points Implementing EU Regulations Code Modification No. A064 Business Rules 16 th January 2015 Version 2.0 i VERSION CONTROL Version Date Description 1.0 19 th

More information

Interconnector (UK) Limited IUK Access Code

Interconnector (UK) Limited IUK Access Code Interconnector (UK) Limited IUK Access Code Issue 2 May 2015 subject to NRA approval Contents SECTION A INTRODUCTION... 1 1. IUK Access Code... 1 2. Capacity... 1 3. Nominations and Matching Procedures...

More information

A study on the implementation status of TAR NC in six northwest European countries

A study on the implementation status of TAR NC in six northwest European countries A study on the implementation status of TAR NC in six northwest European countries A study for Gasunie Transport Services 1 SAFER, SMARTER, GREENER Presentation outline 1 Introduction DNV GL 2 Introduction

More information

ACCESS CODE FOR TRANSMISSION. Attachment B: Subscription & Allocation of Services

ACCESS CODE FOR TRANSMISSION. Attachment B: Subscription & Allocation of Services NON BINDING DOCUMENT FOR CONSULTATION PURPOSES ONLY ACCESS CODE FOR TRANSMISSION Attachment B: Subscription & Allocation of Services Based on version approved by CREG on 26 March 2015 1 of 72 Table of

More information

THE BALTIC PIPE PROJECT OPEN SEASON COPENHAGEN, WARSAW NOVEMBER/DECEMBER 2016 MODEL PAPER

THE BALTIC PIPE PROJECT OPEN SEASON COPENHAGEN, WARSAW NOVEMBER/DECEMBER 2016 MODEL PAPER THE BALTIC PIPE PROJECT COPENHAGEN, WARSAW NOVEMBER/DECEMBER 2016 OPEN SEASON 2017 MODEL PAPER CONTENTS Invitation to the Open Season process of the Baltic Pipe Project...4 Introduction of the Baltic Pipe

More information

IUK Access Agreement Summary. 10 Oct 2013

IUK Access Agreement Summary. 10 Oct 2013 IUK Access Agreement Summary 10 Oct 2013 Preface This document (the IUK Access Agreement Summary or IAAS ) describes the transportation model and the related services offered by Interconnector (UK) Limited

More information

CEER workshop on barriers for gas storage product development. GIE / GSE Brussels, 17 February 2017

CEER workshop on barriers for gas storage product development. GIE / GSE Brussels, 17 February 2017 CEER workshop on barriers for gas storage product development GIE / GSE Brussels, 17 February 2017 Agenda 1. Introduction: GIE / GSE and speakers 2. Current situation of the European gas storage market

More information

1 September 2017 GAS MARKET ENTRY REPORT: THE NETHERLANDS

1 September 2017 GAS MARKET ENTRY REPORT: THE NETHERLANDS 1 September 2017 GAS MARKET ENTRY REPORT: THE NETHERLANDS 1 Table of Contents GAS WHOLESALE TRADING IN THE NETHERLANDS COUNTRY OVERVIEW TABLE... 4 Legal framework... 6 Structure of the market and services...

More information

Explanation of the NTS SO and TO Commodity Charges for the formula year 2014/15 October 2014

Explanation of the NTS SO and TO Commodity Charges for the formula year 2014/15 October 2014 Explanation of the NTS SO and TO Commodity Charges for the formula year 2014/15 October 2014 National Grid sets its charges to recover the price controlled allowances set by Ofgem. The current price control

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Initial Trial Report VERSION: 1.0 STATUS: Final for Publication DATE: 29 th SEPTEMBER 2017 Contents Introduction... 3 Objectives

More information

Natural gas transport contract. Appendix B1: Rules for subscription and allocation on the Main Grid

Natural gas transport contract. Appendix B1: Rules for subscription and allocation on the Main Grid Natural gas transport contract Appendix B1: Rules for subscription and allocation on the Main Grid Version of 1st January 2016 Contents 1. DESCRIPTION OF THE CAPACITY OFFER ON THE MAIN GRID... 3 2. GENERAL

More information

Bacton Entry Capacity Retaining flexibility through modification to overrun regime. Nick Wye

Bacton Entry Capacity Retaining flexibility through modification to overrun regime. Nick Wye Bacton Entry Capacity Retaining flexibility through modification to overrun regime Nick Wye Splitting Bacton Capacity Ofgem is proposing that capacity at Bacton should be allocated to the UKCS ASEP or

More information

... Art. 30 (1)(b)(i) Information on the allowed and/or target revenue

... Art. 30 (1)(b)(i) Information on the allowed and/or target revenue Art. 30 (1)(a) Information on parameters used in the applied reference price methodology related to the technical characteristics of the transmission system Capacity prognosis for calendar year 2018 Weighted

More information

AB AMBER GRID RULES FOR ACCESS TO THE NATURAL GAS TRANSMISSION SYSTEM

AB AMBER GRID RULES FOR ACCESS TO THE NATURAL GAS TRANSMISSION SYSTEM TRANSMISSION SYSTEM OPERATOR AB AMBER GRID AB AMBER GRID RULES FOR ACCESS TO THE NATURAL GAS TRANSMISSION SYSTEM Version 3.0 Vilnius, 2015 TABLE OF CONTENTS 1. GENERAL PROVISIONS... 3 2. DEFINITIONS AND

More information

IUK is key infrastructure in physically connecting pipeline systems and markets

IUK is key infrastructure in physically connecting pipeline systems and markets 2018 Introduction to IUK IUK is key infrastructure in physically connecting pipeline systems and markets First Gas 1 st October 1998 System Capacity GB to BE: 20bcm/yr BE to GB: 25.5bcm/yr IUK Flows: April

More information

The present ACER Guidance to ENTSOG provides a framework for the development of a

The present ACER Guidance to ENTSOG provides a framework for the development of a ACER guidance to ENTSOG on the development of amendment proposals to the Network Code on Capacity Allocation Mechanisms on the matter of incremental and new capacity 1. Introduction a) The Network Code

More information

Interconnector (UK) Limited

Interconnector (UK) Limited Interconnector (UK) Limited IUK Access Code Consultation Version October 2013 Contents SECTION A TRANSPORTATION SYSTEM GENERAL PRINCIPLES 1. Transportation... 1 SECTION B CAPACITY 1. Transportation System

More information

Update on the implementation of GR-BG Projects. Angeliki D. Mourtzikou, Head of Oil & Gas Dept. Regulatory Authority for Energy

Update on the implementation of GR-BG Projects. Angeliki D. Mourtzikou, Head of Oil & Gas Dept. Regulatory Authority for Energy Update on the implementation of GR-BG Projects Angeliki D. Mourtzikou, Head of Oil & Gas Dept. Regulatory Authority for Energy Presented at the 30 th Regional Coordination Committee Meeting & 21th Stakeholder

More information

on the conditions for the application of FDA UIOLI pursuant to paragraph a) - d) of the CMP Guidelines

on the conditions for the application of FDA UIOLI pursuant to paragraph a) - d) of the CMP Guidelines Case Id: c8d4ee05-ccfc-464f-a253-4c5fad681ae0 Date: 13/09/2016 11:53:22 ACER Call for Evidence on the conditions for the application of FDA UIOLI pursuant to paragraph 2.2.3.1 a) - d) of the CMP Guidelines

More information

Appendix 1: General Terms & Conditions for Entry/Exit Contracts (entry/exit sys- tem) Contents

Appendix 1: General Terms & Conditions for Entry/Exit Contracts (entry/exit sys- tem) Contents Contents Appendix 1: General Terms & Conditions for Entry/Exit Contracts (entry/exit system) 1 Section 1 Conclusion of contract 3 Section 2 Definitions of terms 4 Section 2a Admission to the primary capacity

More information

Outline of the European Roadmap for CAM

Outline of the European Roadmap for CAM Outline of the European Roadmap for CAM Clara Poletti GRI Coordinator 10 th NW Stakeholder Group TITRE 22-23 November 2012 Background (1/2) Madrid Forum XXI (March 2012) => called for the early implementation

More information

THE ITALIAN REGULATORY AUTHORITY FOR ELECTRICITY GAS AND WATER

THE ITALIAN REGULATORY AUTHORITY FOR ELECTRICITY GAS AND WATER RESOLUTION OF 4 AUGUST 2016 464/2016/R/GAS COMPLETING THE IMPLEMENTATION OF EUROPEAN PROVISIONS RELATING TO THE RESOLUTION OF CONGESTIONS AT INTERCONNECTION POINTS WITH OTHER COUNTRIES OF THE NATIONAL

More information

GASMARKNADSRÅDET. Joint Balancing Zone, Questionnaire feedback. Malmö, 13 september 2017

GASMARKNADSRÅDET. Joint Balancing Zone, Questionnaire feedback. Malmö, 13 september 2017 GASMARKNADSRÅDET Joint Balancing Zone, Questionnaire feedback Malmö, 13 september 2017 Gasmarknadsrådet 13 September 2017 1 AGENDA Background to the questionnaire Questionnaire feedback Timeline for the

More information

Demand assessment report for the incremental capacity process starting 2017

Demand assessment report for the incremental capacity process starting 2017 Demand assessment report for the incremental capacity process starting 2017 between GASPOOL and TTF market area 2017 07 27 This report is a joint assessment of the potential for incremental capacity projects

More information

New UI Design. Shipper training. October 2015

New UI Design. Shipper training. October 2015 New UI Design Shipper training October 2015 Agenda Introduction New User Interface: General Changes New User Interface: Registration Process New User Interface: Auctions Special Focus: Within-day New User

More information

Capacity Allocation Concepts in the RO-HU-AT Open Season Procedure

Capacity Allocation Concepts in the RO-HU-AT Open Season Procedure Capacity Allocation Concepts in the RO-HU-AT Open Season Procedure Dated February 3, 2016 EconGas GmbH Donau-City-Straße 11 Christoph Rejlek +43 (0)50205 8410 +43 (0)66488456909 Christoph.rejlek@econgas.com

More information

eni proposed UNC Mod 501C

eni proposed UNC Mod 501C eni proposed UNC Mod 501C November 5 th 2014 eni.com 1 Splitting the Bacton ASEP is a unique challenge CAM implementation means Bacton ASEP must undergo a unique and fundamental change but Mod 501 is not

More information

UNOFFICIAL TRANSLATION

UNOFFICIAL TRANSLATION UNOFFICIAL TRANSLATION REPUBLIC OF LATVIA PUBLIC UTILITIES COMMISSION COUNCIL RESOLUTION Riga, 13.04.2017 No. 1/16 (Minutes No. 15, para. 4) Rules of Use of the Natural Gas Transmission System 1. The regulations

More information

The New Market Model in Austria a case study

The New Market Model in Austria a case study The New Market Model in Austria a case study Harald Stindl, Joint Managing Director, Gas Connect Austria Vienna, 31 January 2013 Gas Connect Austria and the OMV Group Gas &Power Activities OMV Group Activities:

More information

Project proposal for the Federal Network Agency for approval of a procedure initiated in 2017 to build incremental capacity at the border between the

Project proposal for the Federal Network Agency for approval of a procedure initiated in 2017 to build incremental capacity at the border between the Project proposal for the Federal Network Agency for approval of a procedure initiated in 2017 to build incremental capacity at the border between the Russian Federation and GASPOOL 20 December 2018 1 This

More information

12-16 June Prisma reporting section Design sprint

12-16 June Prisma reporting section Design sprint 12-16 June 2017 Prisma reporting section Design sprint Welcome Coffee, internet, toilets, smoking Namahn 4 Human-centred design, digital, product-service systems An experienced, international, multidisciplinary

More information

Reliability Pricing Model (RPM) DRAFT Business Rules

Reliability Pricing Model (RPM) DRAFT Business Rules Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional

More information

UNOFFICIAL TRANSLATION

UNOFFICIAL TRANSLATION UNOFFICIAL TRANSLATION REPUBLIC OF LATVIA PUBLIC UTILITIES COMMISSION COUNCIL RESOLUTION Riga, 13.04.2017 No. 1/16 (Minutes No. 15, para. 4) Rules of Use of the Natural Gas Transmission System 1. The regulations

More information

AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW

AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW SHIPPE ERS MANUAL for information purposes only Warsaw/ Leipzig, March 2013 PAGE 1 / 15 CONTENTS: I. GENERAL INFORMATION... 3 II. DEFINITIONS... 3 III. REQUIREMENTS

More information

Moffat Virtual Reverse Flow

Moffat Virtual Reverse Flow GAS4/26/1174956 Basic Transporter Virtual Reverse Flow Arrangements 7 th July 2011 Moffat Virtual Reverse Flow - Basic Transporter Virtual Reverse Flow Arrangements - Consultation Paper 7 th July, 2011

More information

Capacity Booking Platform Regulation

Capacity Booking Platform Regulation Capacity Booking Platform Regulation Operational Rules of the Regional Booking Platform Version 1.6. Applicable from 1 October 2018 FGSZ Zrt. 1 Table of Contents Preamble... 5 1. Definitions... 5 2. General

More information

CRE consultation on the implementation of regulated access to underground gas storage in France

CRE consultation on the implementation of regulated access to underground gas storage in France CRE consultation on the implementation of regulated access to underground gas storage in France n EFET response 23 January 2018 The European Federation of Energy Traders (EFET) thanks CRE for the opportunity

More information

Appendix 1 Entry/Exit Contract Terms & Conditions (entry/exit system) Section 1 Conclusion of contract

Appendix 1 Entry/Exit Contract Terms & Conditions (entry/exit system) Section 1 Conclusion of contract Appendix 1: Entry/Exit General Terms & Conditions (entry/exit system) The document is available in German and English. Only the original German version is legally binding. Section 1 Conclusion of contract

More information

Capacity Allocation Concepts in the RO-HU-AT Open Season Procedure