COMPLETION OF THE FIRST PHASE OF HLW VITRIFICATION AT THE WEST VALLEY DEMONSTRATION PROJECT
|
|
- Sophie Christina McDowell
- 6 years ago
- Views:
Transcription
1 COMPLETION OF THE FIRST PHASE OF HLW VITRIFICATION AT THE WEST VALLEY DEMONSTRATION PROJECT William F. Hamel, Jr., U. S. Department of Energy - West Valley Demonstration Project Paul J. Valenti and Daniel I. Elliott, West Valley Nuclear Services Company, Inc. ABSTRACT The first phase of high-level radioactive waste (HLW) processing at the West Valley Demonstration Project (WVDP) was completed on June 10, This accomplishment represents over 9.32 million curies of cesium-137/strontium-90 (approximately 85% of the total estimated curie inventory) removed from the underground waste storage tanks, leaving only tank heel wastes remaining to be removed. Through this first phase, starting with the initiation of HLW vitrification operations in July 1996, 211 canisters of borosilicate waste glass have been produced. Each canister holds approximately 2,000 kilograms of glass and has a contact dose rate of nearly 2,700 rem per hour. HLW vitrification at the WVDP encompasses waste mobilization and transfer, slurry feed preparation, joule-heated melter operation, canister handling and temporary storage, and melter off-gas treatment. Many challenges have been met throughout the first phase of processing, especially in the realm of remote operations within the vitrification process cell. This paper describes the successful first phase of HLW processing operations at this facility, the process technology applied, operating experience gained, and lessons learned from continuous operation. BACKGROUND AND HISTORY The WVDP was established in 1980 by the United States Congress as a U. S. Department of Energy (DOE) high-level radioactive waste management project. The mission of the project was to demonstrate solidification techniques that could be used to prepare HLW for transportation to, and disposal at, a federal repository. The DOE contracted with West Valley Nuclear Services, Co., Inc. (WVNS), a subsidiary of the Westinghouse Electric Company, to manage the project. The WVDP is located approximately 30 miles south of Buffalo at the site of the former nuclear fuel reprocessing plant at West Valley, NY. The plant was constructed in 1966 and ceased operations in 1972, after reprocessing approximately 640 metric tons of spent nuclear fuel. About 2,300 cubic meters (600,000 gal.) of high-level liquid plutonium extraction (PUREX) process waste was neutralized with sodium hydroxide and stored in an underground carbon steel tank. A sludge, consisting mostly of ferric hydroxide, precipitated to the bottom of the tank leaving a relatively clear liquid supernatant above the sludge. The primary radioactive isotope in the liquid was cesium-137. The other radioactive isotopes, primarily strontium-90, became part of the sludge. A reprocessing campaign for fuel containing thorium produced roughly 30 cubic meters (8,000 gal.) of acidic thorium extraction (THOREX) process waste which was stored in a separate underground stainless steel tank.
2 The supernatant portion of the HLW was pretreated by zeolite ion-exchange between 1988 and This process removed more than 99% of the cesium-137, allowing the remaining supernatant phase, that contained roughly 88% of the nonradioactive sodium, to be processed as low-level waste. Between 1991 and 1994, the remaining PUREX sludge underwent a series of washes to remove interstitial sulfate salts. The wash liquid was processed through the ionexchange columns. Both the decontaminated supernatant and the sludge wash solutions were processed, solidified in a cement matrix, and temporarily stored as low-level radioactive waste. The combination of supernatant and sludge washing pretreatment reduced the projected number of canisters required by nearly a factor of ten. Upon completion of the waste pretreatment, the cesium-loaded, ion-exchange media and the acidic THOREX wastes were combined with the washed PUREX waste to create a single homogeneous waste feed stream for the vitrification process. Between 1984 and 1989, the WVDP successfully performed a Functional and Checkout Testing of Systems (FACTS) program. The FACTS program demonstrated the ability of a full-scale vitrification process to produce high-quality glass on a production schedule. Approximately 150,000 kilograms (165 tons) of borosilicate glass was produced and 37 tests were performed using nonradioactive isotopes to produce a waste glass as close as practical to the projected HLW glass form. Lessons learned from FACTS led to improved designs on process components including: the submerged bed scrubber, the canister turntable, equipment to abate oxides of nitrogen in the melter off-gas, melter nozzle supports and nozzle liners, the melter off-gas nozzle film cooler, and the melter feed sampling equipment. Portions of the full-scale test facility (i.e., the concentrator feed makeup tank, the melter feed hold tank) were reassembled and reused in the final operating facility. Additionally, a Scaled Vitrification System (SVS) was designed, built, and operated in order to understand and evaluate the exact chemistry controls needed to process WVDP waste. The WVDP feed is a nitrate-based slurry. If the melter feed slurry is too reducing, metals may precipitate out of the mix and accumulate on the bottom of the melter. Significant metal accumulation within the melter could allow a short circuit between the melter electrodes, effectively ending the useful life of the melter. If the slurry is too oxidizing, gas generation could lead to foaming within the melter. Foam generation precludes adequate process control of the glass pool. At the WVDP, oxidation-reduction control is accomplished through the addition of sugar to the feed slurry. In the melter, sugar reacts with nitrated slurry and heat to form oxides of nitrogen that exit the melter in the off-gas stream. This reaction promotes reduction of oxygen in the molten glass, alleviating the concern for foaming. SVS proved to be a valuable asset in developing an acceptable range for oxidation-reduction indicators in the slurry feed. After construction of the Vitrification Facility (VF) was complete, an integrated test program was executed by WVDP test engineers. Testing progressed from component and subsystem demonstration first using water, then with nonradioactive slurry, and finally with fully integrated system test runs to produce filled canisters of nonradioactive glass. The performance testing incorporated extensive use of existing standard operating procedures and developmental operating procedures to allow for continual procedure refinement, procedure validation, and to provide operating experience and training opportunities for personnel prior to radioactive
3 operations. The integrated test runs culminated with approval for radioactive operations in June The first phase of the HLW vitrification campaign, representing the processing of approximately 85% of the total estimated curie inventory, was completed on June 10, See Table I for a production summary through this milestone. TABLE I WVDP VITRIFICATION PROCESS PHASE I OPERATING STATISTICS (As of 10 June 1998) 71% Plant Availability Y ~12,100 feeding hours Y ~ 4,950 nonfeeding hours 211 Canisters Filled Y 436,546 kilograms of glass produced Y 90.27% average fill height 68 HLW Transfers Y Over 9.46 million curies (Cs-137 and Sr-90) VITRIFICATION PROCESS OVERVIEW The goal of the vitrification process is to convert the HLW from its initial sludge/liquid form into a borosilicate glass waste form contained within stainless steel canisters. The canisters can then be stored temporarily in the High-Level Waste Interim Storage Facility (HLWISF) in the existing Main Plant (see figure 1). The following section provides a summary description of the vitrification process. The HLW is transferred from the Waste Tank Farm (WTF) HLW tank (Tank 8D-2) into the VF Concentrator Feed Makeup Tank (CFMT) where it is combined with an in-cell recycle stream from the off-gas scrubbing Submerged Bed Scrubber (SBS). CFMT samples are collected and the contents are concentrated by evaporation, removing excess water. The amount of glassforming chemicals to be added to the HLW is determined by analyzing the waste composition and predicting the volume of waste to be processed - one slurry batch in the CFMT usually produces just over three canisters of waste glass. Once ready, the chemicals are transferred into the CFMT and the CFMT is again sampled to ensure the feed composition will result in target glass characteristics. Following verification of the desired feed composition, the mixture is transferred into the Melter Feed Hold Tank (MFHT). The melter is pulse-fed from the MFHT using an air displacement slurry (ADS) pump.
4 Figure 1. Vitrification Process Flow Diagram In the slurry-fed ceramic melter (SFCM), the water will evaporate from the feed and the remaining solids will calcine. The calcined wastes and glass-formers accumulate on the surface of the glass pool to form a crust, referred to as the cold cap. The size of the cold cap is reflected in the temperature of the air space above it (melter plenum) and is managed by controlling the addition rate of the slurry feed. The feed rate is periodically manually adjusted to maintain the plenum temperature between 400 o C and 600 o C. The melter has two side electrodes and one bottom electrode, creating three circuits to pass electrical current through the glass pool and maintain its temperature within the range of 1,100 o C and 1,200 o C. The molten glass is periodically airlifted into a stainless steel canister. The canister is positioned under the melter with the canister turntable - a four-position, four-canister device - which allows two canisters to cool, while one canister is available for removal/replacement, and a fourth canister is being filled. During an airlift, the pour stream is visually monitored by closed circuit TV. The glass level within the canister is visually monitored using an infrared level detection system (ILDS), where a shielded infrared camera scans the canister surface to detect increased surface temperature and translates that information into a graphic image for the operator. Glass production rate typically exceeds 35 kilograms per hour, resulting in a normal canister fill time of roughly 58 hours. The cooled canister is removed from the turntable and moved to the weld station, where a stainless steel lid is welded to the canister. From the weld station, the canister is then moved to the canister decontamination station, where decontamination of the canister surface is accomplished by chemical etching. Welded and decontaminated canisters are moved from the Vitrification Process Cell to the HLWISF where they are placed into racks for interim storage.
5 During melting, steam, volatile elements evaporating from the glass pool, and feed particles entrained in the process off-gas will be vented to the off-gas treatment system. The first stage of the process is the SBS, where off-gases are quenched and particulate is scrubbed through a submerged bed of ceramic spheres. After the SBS, the off-gas is drawn through a high-efficiency mist eliminator (HEME) to remove mist and fine particulate. It is then heated and passes through a high-efficiency particulate air (HEPA) filter to remove particulate. At this point, the off-gas is essentially free of radiological pollutants. It then passes into another building via an underground trench, where oxides of nitrogen (NOx) are abated by catalytic reaction with ammonia. A final stage of HEPA filtering is also provided in this building prior to venting the off-gas to the environment through the plant stack. The primary process vessels are all maintained at relative vacuums by the vessel vent system. The vessel vent gas passes from a header through a condenser until it joins the off-gases prior to the HEME preheater. The vessel vent system also provides a means to bypass the SBS in the event the melter off-gas line becomes plugged. A canister load-in facility is provided for introducing canisters into the processing facility. Canisters are inserted horizontally through a cylindrical shield door into the Equipment Decontamination Room (EDR). The canisters are then upended and placed on the transfer cart using a crane. The radio-controlled transfer cart transports them into the primary process cell, where they are moved into a canister storage rack for eventual loading into the turntable. OPERATIONAL EXPERIENCES AND LESSONS LEARNED Melter Operation During startup testing with nonradioactive glass, the WVDP melter experienced chronic blockages in the glass pour stream. The blockages were the result of a failed barrier between the melt chamber and the discharge chamber, allowing glass migration and subsequent buildup at the bottom of the discharge chamber. The melter was repaired and placed back into service. Just prior to radioactive operations, excessive production and an accumulation of very thin glass fibers (angel hair) led to blockages in the glass pour stream. Prior to radioactive operations, the glass buildup was removed and a flow-reducing orifice was installed to reduce the airflow from the discharge chamber to the main melt chamber. Limiting the airflow through the discharge chamber seemed to successfully reduce angel hair production to an acceptable level. Angel hair formation, however, has not been, nor will it ever be, completely eliminated. Periodic accumulation of angel hair in the melter discharge port has been successfully overcome by rebalancing the discharge heater loads to maximize the temperature around the discharge port and melt the accumulated glass from the chamber. Shortly following the start of radioactive operation, a significant restriction in the melter off-gas piping (prior to the SBS) developed. The restriction was suspected to be caused by the collection of dried melter feed adhering to the inside surface of the piping. Remote radiation surveys showed the buildup to be occurring at an acute (45 degree) elbow just a few feet from the melter.
6 Design modifications incorporated to mitigate the blockage included the following: A water flush line was installed into the melter air injection line. Water is periodically introduced into the off-gas stream to steam clean the piping. A flow-restricting orifice was installed in the air line supplying motive force air for the melter ADS pump. Reduction in the airflow rate reduced the atomization of the melter feed as it was pulsed into the melter plenum. This made it less likely for the feed material to be swept into the off-gas piping. As melter operation progressed through the first phase of HLW processing, the electrical resistance of the molten glass pool decreased significantly. The electrical resistance values associated with each of the three electrode circuits are presently less than one third of their initial values observed at the start of radioactive processing. This phenomenon has been attributed to an accumulation of electrically conductive deposits, consisting mainly of ruthenium, rhodium, and palladium, within the WVDP melter. The shape of the melter cavity is essentially an inverted, truncated, pyramid. WVDP experience with the FACTS melter and supporting data from the testing of other joule-heated melters indicates that the conductive sludge layer may be accumulating primarily in the dihedral corners of the WVDP melter, forming preferential current paths between the melter electrodes. As relatively more current passes through these deposits, a lower percentage of the total electrode current is available to maintain molten glass temperature, leading to higher required electrode current demands. A mathematical model was created to predict the future trend of melter resistance. The model predicts, as shown in figure 2, that the rate of decrease in melter electrical resistance slows considerably over time. The actual observed trend in resistance correlates well with the predicted values. Furthermore, since the HLW tank sludge is the source of these noble metals, future metal deposition is limited to the remaining, limited, inventory in the HLW tank and should not impact continued operation of the WVDP melter.
7 Figure 2. Corner Model Validation The throughput capability of the WVDP melter requires a low average slurry feed flowrate. The pulsing design of the ADS pump has provided a low average feed rate while generating high slurry velocity and high back pressure. These characteristics have resulted in essentially no plugging problems normally encountered with slurry transport. The original ADS feed pump was finally replaced in July 1998 after more than two years and nearly a million operating cycles. In January of 1997, airborne contamination at levels slightly above ambient air was detected in an operating aisle outside the Vitrification Cell. Subsequent engineering assessment determined that the contamination had been transported from the melter discharge section, driven by a minor pressure transient in the melter, along electrical conduits that supply power to the melter discharge heaters. The barriers installed to seal the conduits from the ex-cell operating aisle had not been totally effective in preventing the contamination migration. To prevent future pressurization of the conduits, the conduits were vented within the Vitrification Cell. In addition, HEPA filter vents were installed on the ex-cell portion of the conduits to prevent any further spread of contamination. No further problems associated with these conduits have occurred to date. Feed Preparation and Sampling Initial waste transfers from the Waste Tank Farm (WTF) to the VF had lower curie contents than anticipated (i.e., less than 100,000 curies cesium-137/strontium-90 per batch). An additional
8 sludge mobilization pump was installed into an existing HLW tank riser in a low-flow area within the tank where solids were apparently mounding. Careful management of the HLW tank level also increased batch curie inventory. Leakage of seal water from one of the mobilization pumps added significant water to the HLW tank whenever it was operated. By periodically decanting the accumulated liquid, the solids concentration in the transfers to the VF was optimized while minimizing the transfer pump plugging problems associated with pumping slurries. Subsequent waste transfers typically exceeded 200,000 curies. Approximately 18 months after the initial waste transfer, the pump that transfers slurry from the HLW tank to the VF failed, effectively idling the vitrification process. Replacement of the nearly 50-foot long, highly contaminated, pump proved to be a complex task. Prior to removal of the failed pump, the pump and riser in which it was located were sprayed down in an effort to lower radiation levels near the work area. Radiation levels near the top of the riser were higher than initially predicted. This was presumably due to the process fluid, which is used to lubricate the close-tolerance shaft bearings, spraying the inner wall of the riser as it exits the bearing interface. The replacement pump was modified to direct this process fluid lubrication flow back to the tank without spraying the upper riser walls. The replacement pump was also designed with sideintake suction ports instead of a bottom-intake suction port to more efficiently transfer the suspended solids in the HLW slurry. In the feed preparation process, HLW is combined with SBS recycle liquid in the CFMT and then concentrated by evaporation prior to the addition of glass-forming chemicals. The batch cycle time associated with sample analysis and chemical mixing has been reduced since the start of radioactive operations on two fronts. First, due to the relative consistency of the waste composition, slurry acceptance engineers now generate chemical premix recipes well in advance of the final (post waste analysis) recipe. Independent verification of recipe calculations has virtually eliminated the need for corrective (and time consuming) chemical shims. Secondly, the turnaround times for laboratory chemical analyses have been drastically reduced. Early analytical cell mockup training and experience accumulated by the lab technicians has reduced the time required for various feed batch analyses by more than 50 percent, saving more than 66 hours on the total batch cycle time. However, as the curie content in the HLW tank diminished, the HLW stream became more dilute. This eventually required multiple HLW transfers and evapora-tion cycles to complete a single feed batch. This has increased the batch preparation time and led to periods where melter feed was idled while awaiting the completion of the next batch. Cell maintenance activities were then sched-uled in concert with these idle periods in order to reduce the impact of maintenance on process operating efficiency. A wider range of glass compositions has been studied to expand the range of acceptable glass recipes. These compositions include glasses with little or no uranium or thorium, which have become relatively more depleted from the waste as the tank empties. With a broader range of acceptable compositions, the necessity for small adjustments in the feed will virtually be eliminated. The Vitrification Cell in-line slurry sampling units were modified based upon input from plant operators to improve the ease of remote operation. Typical sampling time was reduced from
9 eight hours to one hour. Routine (daily) water flushing of the in-cell sampling lines was incorporated to preclude line blockages. One phenomenon observed during feed preparation involved the generation of NO x gases during the addition of glass-forming chemicals to the concentrated HLW in the CFMT. As the acidic chemicals were mixed with the basic HLW slurry, NO x gases were generated at rates that exceeded the system s capacity to abate the gases, resulting in visual emissions from the exhaust stack. Efforts to mitigate the emissions included: Establishing an air sweep on the CFMT to dilute the gases as they were generated. Ensuring that the catalytic converter bed was saturated with ammonia prior to the start of chemical mixing (i.e., when the melter is idle and not generating NO x gases). Making a separate addition of dilute nitric acid to the HLW slurry prior to the chemical mixing. Whereas the addition of glass-formers must be made at a flow rate of roughly 60 gallons per minute; to prevent solids settling in the transfer pipe, dilute nitric acid could be added at significantly lower flow rates, limiting the gas generation rate to a controllable range. Vessel level, density, and pressure indications within the Vitrification Cell are provided by bubbler assemblies. A control scheme that includes automatic periodic air blow-downs has maintained the bubblers in the CFMT and MFHT relatively free from plugging. Recent modifications to the automatic blow-down cycles have included a small (~100 milliliters) injection of demineralized water into the bubbler probes at the start of the cycle and are proving to be effective in maintaining clear bubbler lines. Canister Fill The WVDP HLW canisters are required to be filled at least 80% full. Originally, canisters were typically filled to the 85% level. Through the field experience gained with the video imaging capabilities of the ILDS system, canisters are now normally filled approximately 90% full. While the ILDS-based levels are backed up by mass balance calculations, the accuracy provided by the ILDS system for determining the canister fill level has been outstanding. The final (reported) canister fill verification is performed by direct measurement of the glass level (using a measuring stick device) at the vitrification weld station. The variation between the canister fill level provided by direct measurement and that provided by the ILDS is usually within 1%. A significant lesson learned is that a large canister opening is vital to the success of the WVDP vitrification process. The glass pour stream must fall a distance of over 1.5 meters from the end of the trough before entering the canister. Lateral movement in the pour stream can (and does) occur due to melter pressure fluctuations, variations in the airlift flowrate, or effects of air inleakage to the discharge chamber. The large canister opening (0.42 meters in diameter) has proven to be an effective design feature to accommodate pour stream deflections.
10 Canister Handling and Remote Operations Canister closure (lid welding) using a pulsed gas tungsten arc process has become routine. There have been only a few canister lid welds that were just outside the normal range for weld parameters. The welds were corrected by simply reperforming the automatic weld. The ease of reworking a canister lid by rewelding has proven to be one of the major advantages of this system. A significant challenge was offered when it was determined, after 177 canisters had been welded, that the current readings associated with the closure welds were inaccurate. Acceptance of production canister closure welds is based upon measured welding parameters, including weld electrode current values, being within ranges established by qualification testing. An unmonitored ground loop present in the welder control console resulted in unmeasured current being delivered to the weld electrode. Through subsequent testing, the magnitude of the previously unmonitored current was determined to be less than 10 percent of the total current. Additional test closure welds were made and evaluated (visual inspections, leak tests, burst tests, and metallographic examinations) to ensure that previous actual weld currents provided acceptable closure welds. Canister decontamination operations have also become routine. Early difficulties with tank temperature control and cooling coil pressurization were corrected with minor piping modifications and control loop tuning adjustments. The process generates significant volumes of neutralized decontamination and rinse solutions. Through careful scheduling of vitrification evolutions, decontamination and rinse solutions have been effectively managed by reintroducing them into the melter feed batch makeup process. Most of the down-time associated with the WVDP vitrification campaign can be attributed to maintenance and repair of remotely operated equipment. Maintenance of components within the Vitrification Cell is accomplished primarily by remote replacement. Most of the electrical and mechanical (piping) connections are made within the cell using replaceable jumpers with 3-jaw connectors called PUREX TM connectors and an electrical impact wrench suspended from a crane. Even with six, fixed, closed-circuit television (CCTV) cameras; one movable CCTV camera; and three CCTV cameras fixed on the process crane; good visual access to in-cell components is not always available. A significant lesson learned from the WVDP vitrification experience is the importance of proper visual access to in-cell components, especially those components with moving parts. A recent opportunity with replacement of the ADS feed pump bears this out. As the new feed pump and air-supply jumper were being reassembled in the cell, the PUREX connectors were not sealing properly. Because of the lack of adequate visual access, it was necessary to remove the pump from its tank, mount it on a fixture (specifically designed and fabricated to support this maintenance task) located directly in front of a cell viewing window, and attempt to mate the pump with its air-supply jumper. It was only then that a mechanical interference was identified on the ADS pump and corrective actions could be undertaken. The installation and fit of the rigid, in-cell jumpers requires close dimensional tolerances on jumper design and fabrication. WVDP experience with remote jumper placement has led to
11 design changes that provide some flexibility in the jumpers. By providing a spring-loaded support plate to connect the PUREX connector to the jumper s support structure, the PUREX connector is allowed to float as much as 19 mm (0.75 in.) in a direction perpendicular to the cell wall, while still maintaining the necessary rigidity of the jumper to allow proper remote handling. This has provided an additional margin of error in the design and fabrication of spare jumpers. This is especially important when considering that spare jumpers cannot be test fitted prior to placing them into the Vitrification Cell. SUMMARY On June 19, 1996 the Secretary of the Department of Energy approved the initiation of radioactive operations at the WVDP. On July 5, 1996 the first HLW canister was filled. As of June 10, 1998 the WVDP Vitrification Facility had operated at an overall availability (actual time feeding slurry to the SFCM) of approximately 71% and produced 211 HLW canisters of HLW glass. Over 9.46 million curies of cesium-137 and strontium-90 have been removed from underground storage tanks. This accomplishment represents just over 85% of the total activity to be processed and signifies the completion of the first phase of HLW processing at the WVDP. The vitrification process systems have been performing as designed since initiating radioactive operations. Exhaustive functional and integrated testing using waste simulant has limited the unscheduled downtime within the WVDP vitrification process. While the opportunities involving remote maintenance on vitrification system equipment continue to provide challenges, strong problem-solving skills and efficient use of unscheduled process downtime for scheduled maintenance has contributed greatly to the high system availability at the WVDP.
WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA
ABSTRACT Use of the Waste-Incidental-to-Reprocessing Citation Process at the West Valley Demonstration Project - 12250 Dan Sullivan,* Linda Suttora*, Sonny Goldston**, Robert Petras***, Laurene Rowell,
More informationWest Valley Demonstration Project Overview
West Valley Demonstration Project Overview Bryan Bower DOE WVDP Director May 3, 2016 www.energy.gov/em 1 The former nuclear fuel reprocessing facility at West Valley Vitrification Facility (Vit) Main Plant
More informationThe following assumptions apply for the immobilization alternatives:
Technical Summary Report for Surplus Weapons-Usable Plutonium Disposition 2.3 IMMOBILIZATION ALTERNATIVES A total of six immobilization variants covering the three reasonable alternatives addressed in
More informationRIVER PROTECTION PROJECT WASTE TREATMENT PLANT CONCEPT AND APPROACH. M. J. Lawrence, British Nuclear Fuels Ltd., Inc.
RIVER PROTECTION PROJECT WASTE TREATMENT PLANT CONCEPT AND APPROACH M. J. Lawrence, British Nuclear Fuels Ltd., Inc. ABSTRACT The River Protection Project Waste Treatment Plant (RPP-WTP) is a privatized
More informationTHE SAVANNAH RIVER SITE ACCELERATED CLEAN-UP MISSION: SALT WASTE DISPOSAL. P. C. Suggs USDOE Savannah River Site Aiken, South Carolina
THE SAVANNAH RIVER SITE ACCELERATED CLEAN-UP MISSION: SALT WASTE DISPOSAL P. C. Suggs USDOE Savannah River Site Aiken, South Carolina R. E. Edwards, Jr., J. T. Carter and H. H. Elder Westinghouse Savannah
More informationInfrared Thermography at the Savannah River Site
Infrared Thermography at the Savannah River Site David Gleaton Savannah River Site ABSTRACT The Savannah River Site (SRS) is a Department of Energy (DOE), government-owned, company-operated (GOCO) industrial
More informationThe Solidification of High-Level Radioactive Wastes
The Solidification of High-Level Radioactive Wastes by John R Grover Since the earliest days of nuclear energy, the management of radioactive wastes has been a major concern, both for the public and those
More informationIn the early 1990s, KHNP considered vitrification technology as a prospective candidate for the
Commissioning Tests of the Ulchin LLW Vitrification Facility In Korea - 9107 Kyung-Hwa Yang, Sang-Woon Shin, Chan-Kook Moon Nuclear Engineering and Technology Institute-KHNP Yuseong, Daejeon 305-353, South
More informationSupplemental Treatment Hanford Immobilized Low Activity Waste Discussion National Academies of Sciences, Engineering, and Medicine
Supplemental Treatment Hanford Immobilized Low Activity Waste Discussion National Academies of Sciences, Engineering, and Medicine Alex Smith Washington State Department of Ecology March 1, 2018 Outline
More informationINEEL HEPA Filter Leach System: A Mixed Waste Solution. By Mark Argyle, Rick Demmer, Kip Archibald, Ken Pierson, Kimberlee Shackelford, and Ken Kline
ABSTRACT INEEL HEPA Filter Leach System: A Mixed Waste Solution By Mark Argyle, Rick Demmer, Kip Archibald, Ken Pierson, Kimberlee Shackelford, and Ken Kline Lockheed Martin Idaho Technology Company Idaho
More informationVitrification Technology for Treating Low-Level Waste from Nuclear Facilities
Vitrification Technology for Treating Low-Level Waste from Nuclear Facilities ONIKI Toshiro : Nuclear Fuel Cycle Project Department Nuclear Power Operations NABEMOTO Toyonobu : Manager, Nuclear Fuel Cycle
More informationVEK VITRIFICATION PLANT ON THE WAY TO HOT OPERATION. J. Fleisch, M. Weishaupt Forschungszentrum Karlsruhe Bereich Stilllegung Nuklearer Anlagen
VEK VITRIFICATION PLANT ON THE WAY TO HOT OPERATION J. Fleisch, M. Weishaupt Forschungszentrum Karlsruhe Bereich Stilllegung Nuklearer Anlagen G. Roth Forschungszentrum Karlsruhe, Institut für Nukleare
More informationWM 05 Conference, February 27 March 3, 2005, Tucson, AZ THE ARCHIMEDES FILTER PLANT: A NEW CONCEPT FOR REDUCING THE AMOUNT OF HLW AT HANFORD
THE ARCHIMEDES FILTER PLANT: A NEW CONCEPT FOR REDUCING THE AMOUNT OF HLW AT HANFORD J. Gilleland, C. Ahlfeld, C. Little, H. Pluche, K. Umstadter, J. Wagoner Archimedes Technology Group, 5660 Eastgate
More informationAn overview of the Saltstone production process is shown in Figure 1.
ABSTRACT Saltstone Processing of 0.1 Ci/gal Waste at Savannah River Site Aaron V. Staub, Jason L. Adams, and Chris H. Beheler Savannah River Remediation, Aiken, SC 29808 Storage space constraints in the
More informationNuclear Fuel Cycle Indian Scenario
Nuclear Recycle Group Nuclear Fuel Cycle Indian Scenario KAILASH AGARWAL Associate Director, NUCLEAR RECYCLE GROUP BHABHA ATOMIC RESEARCH CENTRE DEPARTMENT OF ATOMIC ENERGY MUMBAI, INDIA Advanced Fuel
More informationAnalysis of Approaches for Supplemental Treatment of Low-Activity Waste at the Hanford Nuclear Reservation
Analysis of Approaches for Supplemental Treatment of Low-Activity Waste at the Hanford Nuclear Reservation Delmar Noyes, Assistant Manager Presented by: U.S. Department of Energy, Office of River Protection
More informationControlling NOx and other Engine Emissions
Controlling NOx and other Engine Emissions Extensive Emissions Control Experience in Stationary Diesel and Natural Gas Engines Distributed Power Generation Cogeneration Plants (CHP) Gas Compression & Transmission
More informationThe waste water treatment plant will treat
Waste Water Treatment Plant The waste water treatment plant will treat groundwater and surface water pumped from the existing Port Granby Waste Management Facility during excavation of the waste and continue
More informationVitrification of Simulated LILW Using Induction Cold Crucible Melter Technology
Vitrification of Simulated LILW Using Induction Cold Crucible Melter Technology C.W. Kim, J.K. Park, S.W. Shin, T.W. Hwang, J.H. Ha M.J. Song Nuclear Environment Technology Institute(NETEC) Korea Hydro
More informationEXPERIENCE USING THE EPRI DFD PROCESS TO DECONTAMINATE SCRAP CONTROL ROD DRIVES AND SHROUD HEAD BOLTS. Joseph M. Harverson Alaron Corporation
EXPERIENCE USING THE EPRI DFD PROCESS TO DECONTAMINATE SCRAP CONTROL ROD DRIVES AND SHROUD HEAD BOLTS Joseph M. Harverson Alaron Corporation ABSTRACT Alaron, as a licensee of the EPRI DfD process, has
More informationEvaporative Gas Cooling and Emissions Control Solutions
Evaporative Gas Cooling and Emissions Control Solutions for the Iron and Steel Industry MEGTEC ENERGY ENVIRONMENTAL B&W MEGTEC Solutions for the Iron & Steel Industry Our Pedigree Babcock & Wilcox MEGTEC
More informationPRESENTATION OF CONDENSATE TREATMENT
Via Pietro Nenni, 15-27058 VOGHERA ITALY Tel. +39 0383 3371 Fax +39 0383 369052 E-mail: info@idreco.com PRESENTATION OF CONDENSATE TREATMENT THE CONDENSATE TREATMENT The absence of impurities in feed water
More informationVitrification Melter
Waste-Incidental-to-Reprocessing Evaluation for the West Valley Demonstration Project Vitrification Melter February 2012 Prepared by the U.S. Department of Energy West Valley, New York This page is intentionally
More informationWM2011 Conference February 27 - March 3, 2011, Phoenix, AZ
The Hanford Waste Feed Delivery Operations Research Model - 11248 Joanne Berry, EnergySolutions, Richland, Washington 99354 Benjamin Gallaher, Washington River Protection Solutions, Richland, Washington,
More informationDECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS
DECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS - 9023 J. Fleisch, M. Weishaupt, W. Pfeifer Wiederaufarbeitungsanlage Karlsruhe,
More informationReplacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head
Unit 2, Genkai Nuclear Power Plant Replacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head Replacement works for the above components were conducted at Unit 2 of the Genkai
More informationCustom Systems Built to Exacting Client Specification
Custom Systems Built to Exacting Client Specification Laboratory Reactor Systems Parr Instrument Company is pleased to work with customers in the design and assembly of complete laboratory or pilot plant
More informationElectric Furnace Off-Gas Cleaning Systems Installation at PT Inco ABSTRACT
Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco Paykan Safe and Matt Russell WorleyParsons Gas Cleaning, Irving, Texas USA ABSTRACT PT Inco is a ferronickel smelter in Soroako, Sulawesi,
More informationDISPOSAL OF NONROUTINE HIGH LEVEL WASTE IN DWPF CANISTERS AT SAVANNAH RIVER SITE A PRECEDENT THROUGHOUT THE DWPF COMPLEX
DISPOSAL OF NONROUTINE HIGH LEVEL WASTE IN DWPF CANISTERS AT SAVANNAH RIVER SITE A PRECEDENT THROUGHOUT THE DWPF COMPLEX J.W. Ray, D.C. Iverson Defense Waste Processing Facility Washington Savannah River
More informationTruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>
TruePeak TDLS200 NH 3 Slip Measurement One Background One Two Three Four Gas-Fired Installations The SCR control system must be able to perform in a range of conditions Flue gases from
More informationRADIOACTIVE WASTE MANAGEMENT AT CERNAVODA NPP AFTER 5 YEARS OF EXPERIENCE
International Conference Nuclear Energy for New Europe 2002 Kranjska Gora, Slovenia, September 9-12, 2002 www.drustvo-js.si/gora2002 RADIOACTIVE WASTE MANAGEMENT AT CERNAVODA NPP AFTER 5 YEARS OF EXPERIENCE
More informationKEYWORDS: Deaerator, Condensate, Oxygen Removal, Boiler Feed Water, Heater, Water Treatment
Does Your Deaerator Really Work? JACK B. PRATT CONSULTANT WWW.DEAERATORS.COM ORIN HOLLANDER CONSULTANT Email orinholl@aol.com ALTAIR EQUIPMENT CO. INC. WARMINSTER, PA. WWW.ALTAIREQUIPMENT.COM KEYWORDS:
More informationTHE NUCLEAR FUEL CYCLE
THE NUCLEAR FUEL CYCLE Uranium is a slightly radioactive metal that is found throughout the earth s crust It is about 500 times more abundant than gold and about as common as tin Natural uranium is a mixture
More informationⅠ Outline of the Plant
Rokkasho Reprocessing Plant is first commercial plant in Japan,adopting the technology developed on the basis of more than 40years of operation results in both France and United Kingdom, as well as operating
More informationLecture 23. Nitrophosphate Fertilizers Part 1
Lecture 23 Nitrophosphate Fertilizers Part 1 Introduction Nitrophosphate is the generally accepted term for any fertilizer that is produced by a process involving treatment of phosphate rock with nitric
More informationSulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard
Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard Introduction SRU s (Sulfur Recovery Units) are critical pieces of equipment in refineries and gas plants. SRUs remove sulfur compounds from certain
More information25fh DOE/NRC NUCLEAR AIR CLEANING AND TREATMENT CONFERENCE
25fh DOE/NRC NUCLEAR AIR CLEANING AND TREATMENT CONFERENCE AIR PURGE APPLIED TO SUBSTANTIALLY MITIGATE STACK RELEASE LEVELS RESULTING FROM BWR FUEL LEAK Peter G. Dorosko, PE Carolina Power & Light Brunswick
More informationCEMENT PLANT ENVIRONMENTAL TECHNOLOGY FOR ACHIEVING HIGH SO 2 REMOVAL
CEMENT PLANT ENVIRONMENTAL TECHNOLOGY FOR ACHIEVING HIGH SO 2 REMOVAL Sara Safariyeganeh sara.safariyeganeh@mecsglobal.com Cary Joe Lovett, PE joe.lovett@holcim.com Abstract - The EPA has adopted revised
More informationFacility Improvements and Modifications to Extend the Operational Life of the Modular Caustic-Side Solvent Extraction Process
Facility Improvements and Modifications to Extend the Operational Life of the Modular Caustic-Side Solvent Extraction Process - 16082 Carl Scherman, Annah Garrison, and Earl Brass Savannah River Remediation,
More informationSTUDSVIK PROCESSING FACILITY PYROLYSIS/STEAM REFORMING TECHNOLOGY FOR VOLUME AND WEIGHT REDUCTION AND STABILIZATION OF LLRW AND MIXED WASTES
STUDSVIK PROCESSING FACILITY PYROLYSIS/STEAM REFORMING TECHNOLOGY FOR VOLUME AND WEIGHT REDUCTION AND STABILIZATION OF LLRW AND MIXED WASTES J. Bradley Mason, Thomas W. Oliver, Marty P. Carson, G. Mike
More informationUSE OF A DEEP AND NARROW POOL TO STORE SPENT FUEL ABSTRACT
USE OF A DEEP AND NARROW POOL TO STORE SPENT FUEL O. Novara, O. Beuter, M. Ratner, M. Flores Comisión Nacional de Energía Atómica Av. Del Libertador 8250 (C1429BNP). Buenos Aires Argentina ABSTRACT Storage
More informationCoke Manufacturing. Environmental Guidelines for. Multilateral Investment Guarantee Agency. Industry Description and Practices. Waste Characteristics
Multilateral Investment Guarantee Agency Environmental Guidelines for Coke Manufacturing Industry Description and Practices Coke and coke by-products (including coke oven gas) are produced by the pyrolysis
More informationCrystallization of Ruthenium Dioxide during Vitrification of HLW, and its Effect on Leachability of the Glass
Crystallization of Ruthenium Dioxide during Vitrification of HLW, and its Effect on Leachability of the Glass - 9032 Youichi Enokida, Kayo Sawada, and Kazuyoshi Uruga EcoTopia Science Institute, Nagoya
More informationMETHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF
METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF THE AP1000 TM REACTOR Erik Slobe slobeed@westinghouse.com Westinghouse Electric Company LLC 1000 Westinghouse Drive Cranberry Township,
More informationNot Reviewed by WMSymposia, Inc.
Application of Inorganic SIAL Matrix and Movable Technology in Solidification of the TRU Sludges and Sludge/Resin Mixtures D. Majersky, S. Sekely, D. Zavodska, M. Breza AllDeco 919 31 Jaslovske Bohunice
More informationTreatment of Spent Nuclear Fuel with Molten Salts
Treatment of Spent Nuclear Fuel with Molten Salts Michael Goff Deputy Associate Laboratory Director Operations Nuclear Science and Technology Idaho National Laboratory 2008 Joint Symposium on Molten Salts
More informationUtilizing ScaleBlaster to Reduce Lime Scale Build-up in an Industrial Wastewater Treatment Plant
Utilizing ScaleBlaster to Reduce Lime Scale Build-up in an Industrial Wastewater Treatment Plant Documented by The Village of Sauget Physical/Chemical Plant May, 2015 Purpose Case Study: Utilizing ScaleBlaster
More informationWM2008 Conference, February 24-28, 2008, Phoenix, Arizona. The technological Aspects of Liquid Radioactive Waste Treatment
The technological Aspects of Liquid Radioactive Waste Treatment - 8353 Tibor Krajc, Marian Stubna, Milan Zatkulak VUJE, a.s. Okruzna 5, 918 64 Trnava, Slovak Republic Martin Slezak, Vladimir Remias JAVYS,
More informationPPC specializes in maximum efficiency air pollution control equipment using a variety of different
PPC specializes in maximum efficiency air pollution control equipment using a variety of different technologies. These include wet and dry electrostatic precipitator devices (ESP) for particulate control,
More informationSuccessful Hot Operation of the German Vitrification Plant VEK Results and Experiences Paper 11277
Successful Hot Operation of the German Vitrification Plant VEK Results and Experiences Paper 11277 J. Fleisch, W. Grünewald*, G. Roth*, F-J. Schmitz, W. Tobie*, M. Weishaupt WAK Rückbau- und Entsorgungs-
More informationDownsizing a Claus Sulfur Recovery Unit
INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com
More informationCECEBE Technologies Inc.
98.2.8 Improving Furnace-Boiler System in Sulfuric Acid Plants Dr. Gordon M. Cameron and Dr. Dahya Bhaga CECEBE Technologies Inc. 4 Wellesbourne Crescent Toronto, Ontario Canada, M2H 1Y7 Tel: (416) 490-9840
More informationControl of the Reduction/Oxidation State of the High Level Waste Form in the Defense Waste Processing Facility at the Savannah River Site
Control of the Reduction/Oxidation State of the High Level Waste Form in the Defense Waste Processing Facility at the Savannah River Site - 12451 Jonathan M. Bricker, Terri L. Fellinger, Aaron V. Staub,
More informationModeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S.
Modeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S. E. L. Fuller, S. Basu, and H. Esmaili Office of Nuclear Regulatory Research United States Nuclear Regulatory
More informationTank Closure Progress at the Department of Energy s Idaho National Engineering Laboratory Tank Farm Facility
Tank Closure Progress at the Department of Energy s Idaho National Engineering Laboratory Tank Farm Facility K.A. Lockie U.S. Department of Energy Idaho Operations Office 1955 Fremont Avenue Idaho Falls,
More informationPRESENTED AT THE NUCLEAR
PRESENTED AT THE NUCLEAR INTEGRATION PROJECT WORKSHOP THE BACK-END: HEALING THE ACHILLES HEEL OF THE NUCLEAR RENAISSANCE BY R. G. WYMER VANDERBILT UNIVERSITY MARCH 4, 2008 CONTRIBUTIONS OF SELECTED ACTINIDES
More informationHANFORD S SY-101 WASTE TRANSFER
ABSTRACT HANFORD S SY-101 WASTE TRANSFER R. E. Raymond CH2M HILL Hanford Corporation C. E. Hanson and K. L. Morris COGEMA Engineering Corporation The surface level in the 241-SY-101 (SY-101) waste storage
More informationWM 03 Conference, February 23-27, 2003, Tucson, AZ
STABILIZATION OF UNDERGROUND SOLVENT STORAGE TANKS T.R. Smail, A.M. Herb, M.C. Hall Westinghouse Savannah River Site Savannah River Technology Center Building 723-A, Aiken, SC 29808 ABSTRACT The Old Solvent
More informationAP1000 European 11. Radioactive Waste Management Design Control Document
11.2 Liquid Waste Management Systems The liquid waste management systems include the systems that may be used to process and dispose of liquids containing radioactive material. These include the following:
More informationThe planning and design of effective wet duct/stack systems For coal fired utility power plants
The planning and design of effective wet duct/stack systems For coal fired utility power plants David K. Anderson David Anderson is currently a Principal/Owner of Alden Research Laboratory, the oldest
More informationWM2011 Conference, February 27 - March3, 2011, Phoenix, AZ
West Valley Demonstration Project Past, Present and Future 11203 James Blankenhorn,* Bryan Bower,** *West Valley Environmental Services, LLC, West Valley, New York **U.S. Department of Energy West Valley
More informationNEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS
NEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS Anders Lindström, Bo Wirendal and Maria Lindberg Studsvik Nuclear AB Department RadWaste SE 611 82 Nyköping Sweden ABSTRACT The project that
More informationRESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED
RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft
More informationFIG. 1. Fort St. Vrain Nuclear Generation Station.
Invited Paper XA9848067 FORT ST. VRAIN DECOMMISSIONING PROJECT M. FISHER Public Service Company of Colorado, Denver, Colorado, USA Abstract Public Service Company of Colorado (PSCo), owner of the Fort
More informationWM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA
Installation and Operation of GeoMelt In Container Vitrification in NNL Central Lab Active Rig Hall at Sellafield 15328 Keith Witwer *, Eric Dysland *, Steve Woosley *, Charlie Scales **, John McGibbon
More informationWM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Integrated Waste Feed Qualification Program for Direct LAW Feed to WTP 16421
Integrated Waste Feed Qualification Program for Direct LAW Feed to WTP 16421 Aruna Arakali*, Stuart Arm ***, Peter Benson*, Garth Duncan **, Renee Davis ***, Mike Thien *** * URS-AECOM, Richland, WA 99354
More informationWhite Paper. Fire Sprinkler Riser Corrosion. (May 2014) Jeffrey Kochelek (Engineered Corrosion Solutions, LLC) V.1.0.1
White Paper Fire Sprinkler Riser Corrosion (May 2014) Jeffrey Kochelek (Engineered Corrosion Solutions, LLC) V.1.0.1 Copyright 2014 Engineered Corrosion Solutions, LLC. All rights reserved. This white
More informationHow Air Bearings Moved Tons of Nuclear Waste
https://www.powermag.com/how-air-bearings-moved-tons-of-nuclear-waste/?printmode=1 How Air Bearings Moved Tons of Nuclear Waste 01/01/2019 Randy Manus Heavy loads must often be moved at power plants of
More informationSalt Processing through Ion Exchange at the Savannah River Site Selection of Exchange Media and Column Configuration
WM2009 Conference, March 1-5, 2009, Phoenix, AZ Salt Processing through Ion Exchange at the Savannah River Site Selection of Exchange Media and Column Configuration - 9198 ABSTRACT Renee H. Spires, Timothy
More informationAPPLICABILITY. (1) Except as provided in Section (b), this rule is applicable to all vapor degreasing operations.
RULE 67.6.2 VAPOR DEGREASING OPERATIONS (Adopted & Effective 5/23/07; Rev. Effective (date of adoption)) (a) APPLICABILITY (1) Except as provided in Section (b), this rule is applicable to all vapor degreasing
More informationNOTIFICATION ON SCHEDULE OF PRESCRIBED SUBSTANCES UNDER ATOMIC ENERGY ACT January 2006
NOTIFICATION ON SCHEDULE OF PRESCRIBED SUBSTANCES UNDER ATOMIC ENERGY ACT 1962 20 January 2006 Click here for hindi version THE SCHEDULE Category 0 : Nuclear materials, nuclear-related other materials,
More informationHANFORD TANK WASTE TREATMENT SYSTEM. T. Z. Smith, S. A. Wiegman U.S. Department of Energy, Office of River Protection
HANFORD TANK WASTE TREATMENT SYSTEM T. Z. Smith, S. A. Wiegman U.S. Department of Energy, Office of River Protection ABSTRACT J. O. Honeyman CH2MHILL Hanford Group, Inc. The US Department of Energy is
More informationINVESTIGATION OF THE BUILDING LIQUID EFFLUENT PIPE WORK AS PART OF THE AGEING MANAGEMENT AT SAFARI-1
INVESTIGATION OF THE BUILDING LIQUID EFFLUENT PIPE WORK AS PART OF THE AGEING MANAGEMENT AT SAFARI-1 N.F. Khathi and J.C. Mostert SAFARI-1 South African Nuclear Energy Corporation (Necsa), P.O. Box 582,
More informationLiquid-Liquid Extraction Equipment
Liquid-Liquid Extraction Equipment Jack Law Idaho National Laboratory Introduction to Nuclear Chemistry and Fuel Cycle Separations Las Vegas July 2011 Outline Introduction Role of separations equipment
More informationVVER-440/213 - The reactor core
VVER-440/213 - The reactor core The fuel of the reactor is uranium dioxide (UO2), which is compacted to cylindrical pellets of about 9 height and 7.6 mm diameter. In the centreline of the pellets there
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA
Small Scale Mixing Demonstration Batch Transfer and Sampling Performance of Simulated HLW - 12307 Jesse Jensen, Paul Townson, and Matt Vanatta EnergySolutions, Engineering and Technology Group, Richland,
More informationExpert Panel on Monju Decommissioning 6 th March 2018
1 Expert Panel on Monju Decommissioning 6 th March 2018 Steve Beckitt Chief Nuclear Officer DSRL 2 PFR Decommissioning Dounreay 3 Decommissioning Synergies Primary Systems 4 Decommissioning Synergies Primary
More informationWM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA
Waste Treatment & Immobilization Plant, a Leader in the International Glass Community 16003 Albert Kruger *, William Hamel * * US DOE, Office of River Protection, Richland, Washington 99352 USA ABSTRACT
More informationPRESENTATION OF NUCLEAR APPLICATIONS OF CONDENSATE TREATMENT
Via Pietro Nenni, 15-27058 VOGHERA ITALY Tel. +39 0383 3371 Fax +39 0383 369052 E-mail: info@idreco.com PRESENTATION OF NUCLEAR APPLICATIONS OF CONDENSATE TREATMENT 0. MAIN CONDENSATE TREATMENT 1. REACTOR
More informationTOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY. By N. Ramachandran, Ion Exchange (India) Ltd
TOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY By N. Ramachandran, Ion Exchange (India) Ltd Large quantities of water are required to produce steel and steel products - typically 180-200 m 3 of water per
More informationCURRENT STATUS ON FAST REACTOR PROGRAM IN KAZAKHSTAN
CURRENT STATUS ON FAST REACTOR PROGRAM IN KAZAKHSTAN Presented at the 47 th Annual Meeting of the Technical Working Group on Fast Reactors IAEA, Vienna, 19-23 May, 2014 by S. Andropenkov, National Atomic
More informationT-125 EVOLUTION OF THERMAL REMEDIATION. Technical Paper T-125. EVOLUTION OF THERMAL REMEDIATION by Wendell R. Feltman P.E.
T-125 EVOLUTION OF THERMAL REMEDIATION Technical Paper T-125 EVOLUTION OF THERMAL REMEDIATION by Wendell R. Feltman P.E. ASTEC encourages its engineers and executives to author articles that will be of
More informationMobile processing systems for radioactive waste and disused sealed radioactive sources. Peter Ivanov
Mobile processing systems for radioactive waste and disused sealed radioactive sources Peter Ivanov Radioactivity group National Physical Laboratory, UK ICTP/IAEA Workshop, 2 6 November 2015, ICTP - Trieste,
More informationWM 05 Conference, February 27 March 3, 2005, Tucson, AZ STORED LIQUID WASTE REMEDIATION PROGRAM, PHASE 1, AT CHALK RIVER LABORATORIES
ABSTRACT STORED LIQUID WASTE REMEDIATION PROGRAM, PHASE 1, AT CHALK RIVER LABORATORIES R.P. Denault, P. Heeney, E. Plaice, K. Schruder, Waste Remediation & Enhancement Projects Division D. Wilder, Site
More informationMECS SULFOX High Energy Efficient Sulfuric Acid Process Technology for cleaning up Lean & Wet Sulfurous Off-gasses
MECS SULFOX High Energy Efficient Sulfuric Acid Process Technology for cleaning up Lean & Wet Sulfurous Off-gasses Sulphuric Acid Conference 4 6 MAY 2009 SUN CITY, SOUTH AFRICA day s Topics MECS Introduction
More informationThe ELIPSE Process: An Underwater Plasma Technology for Liquid Treatment
The ELIPSE Process: An Underwater Plasma Technology for Liquid Treatment - 16026 F.Lemont*, M.Marchand, M.Mabrouk, D.Milelli, JM.Baronnet CEA, DEN, DTCD, SCDV, LPIC, F-30207 Bagnols sur Cèze, France *
More informationSpent Fuel Storage Operational Experience With Increased Crud Activities. I. Barnabás Public Agency for Radioactive Waste Management (PURAM), Hungary
Spent Fuel Storage Operational Experience With Increased Crud Activities I. Barnabás Public Agency for Radioactive Waste Management (PURAM), Hungary T. Eigner Paks NPP, Hungary I. Gresits Technical University
More informationExperimental Tests of Ultrasonic Decontamination of Metal Radioactive Waste Vasilyev A.P. ANO MCEB Post box 912, Moscow, Russia,
Experimental Tests of Ultrasonic Decontamination of Metal Radioactive Waste - 9012 Vasilyev A.P. ANO MCEB Post box 912, Moscow, Russia, 101000 Lebedev N.M. Open Company «Alexander - Plus» 102 Blagoveschenskaya,
More informationNEW TECHNOLOGIES IN COAL-FIRED THERMAL POWER PLANTS FOR MORE EFFECTIVE WORK WITH LESS POLLUTION
UDK 621.311.22:502.174 Dip.el.eng. Igor SEKOVSKI NEW TECHNOLOGIES IN COAL-FIRED THERMAL POWER PLANTS FOR MORE EFFECTIVE WORK WITH LESS POLLUTION Abstract Today people make a lot of analysis, of work of
More informationCondensate System Troubleshooting andoptimization
Condensate System Troubleshooting andoptimization One of the prime considerations in the operation of a boiler is feedwater quality. The better the feedwater, the less likely that water-related problems
More informationWM 2010 Conference, March 7-11, 2010, Phoenix, AZ
Thermal Treatment of UK Intermediate and Low Level Radioactive Waste: A Demonstration of the GeoMelt Process Towards Treatment of Sellafield Waste - 10507 ABSTRACT Keith Witwer and Eric Dysland Impact
More informationEnergy Production Systems Engineering
Welcome to Energy Production Systems Engineering USF Polytechnic Engineering tom@thomasblairpe.com Session 10: Environmental Controls Spring 2012 Plant Environmental Control Systems Power plant Environmental
More informationDRAFT IMPLEMENTING DECREE. of 2016
1. ------IND- 2016 0202 CZ- EN- ------ 20160523 --- --- PROJET II. DRAFT IMPLEMENTING DECREE of 2016 on the requirements for the safe management of radioactive waste and on the decommissioning of nuclear
More informationWest Valley Demonstration Project. Project Update
West Valley Demonstration Project Project Update Craig Rieman February 24, 2010 Citizen Task Force 20475_1 Safety Performance As of February 19, 2010, WVDP employees have worked more than 2.3 million hours
More informationPROCESS CONCEPT FOR THE STORED LIQUID WASTE REMEDIATION PROGRAM, PHASE 1, AT CHALK RIVER LABORATORIES
PROCESS CONCEPT FOR THE STORED LIQUID WASTE REMEDIATION PROGRAM, PHASE 1, AT CHALK RIVER LABORATORIES E. Plaice, R. Prokopowicz, R. Ponnan, R. Thatipamala, P. Brewster AECL, Chalk River Laboratories MS
More informationI. Hugon, J.L. Dussossoy Commissariat à l Énergie Atomique (CEA), CEA/DEN/DTCD/SECM BP 17171, Bagnols sur Cèze, France
Qualification of In-Can Melting Process Applied to Vitrification of High Activity Waste Solutions (HAWS) at the CEA s Valduc Center: Description of Process and Equipment, Methodology and Initial Results
More informationValve Nest Filter with Time Clock Control Installation and Operation Manual
Valve Nest Filter with Time Clock Control Installation and Operation Manual Effective 5/24/12 Effective 5/24/12 Table of Contents Operating Data. 1 Pre-Installation Data... 2 Filter Parameters Installation
More informationRadiation Control in the Core Shroud Replacement Project of Fukushima-Daiichi NPS Unit #2
General Radiation Control in the Core Shroud Replacement Project of Fukushima-Daiichi NPS Unit #2 Yasunori Kokubun, Kazuyuki Haraguchi, Yuji Yoshizawa, Yasuo Yamada Tokyo Electric Power Co, 22 Kitahara
More informationGlossary of Freeze Drying Terms
Glossary of Freeze Drying Terms PRECISION FREEZE DRYERS MADE IN THE USA Laboratory Pharmaceutical Industrial Benchtop Floor Models For Clinical, Production & General Use Amorphous Amorphous material usually
More informationTank Waste and Nuclear Materials Disposition. Steve Schneider Director, Office of Tank Waste Management (EM-21) March
Tank Waste and Nuclear Materials Disposition Steve Schneider Director, Office of Tank Waste Management (EM-21) March 2012 www.em.doe.gov 1 The key strategy for the disposition of tank waste is the successful
More information