FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL

Size: px
Start display at page:

Download "FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL"

Transcription

1 Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA PVP FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL H. J. Ahn, B. C. Kim, J. W. Sa, Y. J. Lee, K. H. Hong, H. S. Kim, J. S. Bak, K. J. Jung National Fusion Research Institute Daejeon, Republic of Korea K. H. Park, T. S. Kim, J. S. Lee, Y. K. Kim, H. J. Sung Hyundai Heavy Industries Ulsan, Republic of Korea K. Ioki, B. Giraud, C. H. Choi, & Y. Utin ITER Organization St. Paul lez Durance, France ABSTRACT The ITER vacuum vessel (VV) is a double walled torus structure and one of the most critical components in the fusion reactor. The design and fabrication of the VV as nuclear equipment shall be consisted with the RCC-MR code based on French fast breeder reactor. The VV is a heavy welded structure with 60 mm thick shells, 40 mm ribs and flexible housing of 275 mm diameter. The welding distortion should be controlled since the total welding length is over 1500 m. To satisfy the design requirement, the electron beam welding (EBW) and narrow gap gas tungsten arc welding (GTAW) techniques are to be applied and developed through the fabrication of mock-ups. The fabrication design has been developed to manufacture the main vessel and port structures in accordance with the RCC- MR code. All fabrication sequences including welding methods are also established to meet the demanding tolerance and inspection requirement by HHI as a supplier. The ITER Organization (IO) was conceived as long ago as 1985 but was only formally established on 24 October 2007, following an agreement between the People s Republic of China, the European Union (EU), the Republic of India (IN), Japan, the Republic of Korea (KO), the Russian Federation (RF) and the United States of America. The ITER VV procurement sharing includes the production of 7 sectors by the EU, 2 sectors by KO, the upper ports by RF, the VV supports and the lower and equatorial ports by KO, the in-wall shielding by IN and the assembly by IO. As one of the providers, Korea Domestic Agency (KODA) and Hyundai Heavy Industries (HHI) have performed the fabrication design of the main vessel and port structures based on IO s Build-to-Print design in accordance with the RCC-MR code. This paper presents details of the fabrication design and mock-ups developed by KO to manufacture two sector and port structures. INTRODUCTION The international thermonuclear experimental reactor (ITER), currently under construction in the south of France, aims to demonstrate that fusion is an energy source of the future. ITER is based on the 'tokamak' concept of magnetic confinement so that the plasma is contained in a doughnutshaped vacuum vessel as shown in Figure 1. The fuel, a mixture of Deuterium and Tritium (two isotopes of Hydrogen) is heated to temperatures over 150 million C forming hot plasma. Strong magnetic fields are used to keep the plasma away from the walls; these are produced by superconducting coils surrounding the vessel, and by an electrical current driven through the plasma [1]. Figure 1: The configuration of the ITER Tokamak. 1 Copyright 2011 by ASME

2 DESCRIPTION OF VACUUM VESSEL The ITER vacuum vessel (VV) is a double walled torus structure and one of the most critical components in the fusion reactor. Its primary function is to provide a high quality vacuum for the stable plasma and it becomes a major safety barrier for ITER. It consists of nine 40 degree vessel sectors with many port structures like long nozzles of a pressure vessel as shown in Figure 2. and flows through the lower port and is routed in an internal supply structure to the bottom of each sector [3]. The VV is supporting blankets, divertors and ELM/VS coils on the interior surface of the vessel. The blanket modules are attached to the flexible support housing (FSH) mounted on the inner shell by flexible supports and keys. The hinge type gravity supports are located below lower ports and sustain the VV weight and its electro-magnetic loads. The supports are radially free to move for thermal expansion but restrained vertically and toroidally. Figure 2: ITER Vacuum Vessel. Main parameters of the VV are summarized in Table 1 [2]. The vessel is a heavy welded structure with 60 mm thick shells, 40 mm ribs and flexible housings of 275 mm diameter. Its weight is about 5250 tons and its torus outer diameter and height are 19.4 m and 11.4 m, respectively. Parameter Torus outer diameter Torus inner diameter Configuration - Inboard straight region - Inboard top/bottom - Outboard region Operating condition 1 - Normal operation - During baking Design condition - Main vessel - Ports Interior surface area Interior volume Table 1: Main VV Parameters. Description (value) 19.4 m 11.4 m Cylindrical Double curvature Mainly double curvature 100 ºC / 0.8 MPa (Absolute) 200 ºC / 2.1 MPa (Absolute) 200 ºC / 2.6 MPa (Absolute) 250 ºC / 5.0 MPa (Absolute) ~850 m 2 ~1600 m 3 Note 1) VV operating condition is based on the temperature and pressure of the cooling water inlet. The interspace between the vacuum vessel double walls is filled with in-wall shielding (IWS) and cooling water. The shielding structures, which occupy about 60% of the in-wall space, provide efficient neutron shielding. The heat deposition in the VV due to neutron heating is removed by high pressure cooling water during plasma operation. The water is supplied MATERIALS OF VACUUM VESSEL The main material is austenitic stainless steel with controlled nitrogen contents and tight limitation of impurities such as cobalt, niobium and boron. The choice of materials for the VV has significant influence on cost, performance, maintainability, licensing, detailed design parameters, and waste disposal. The primary reason for the choice of materials shown in Table 2 [2] is their high mechanical strength at operating temperatures, water resistive properties, excellent fabrication characteristics, and low cost relative to other candidates. This is achieved as a result of an optimal combination of the main alloying elements, carbon, nitrogen, nickel, chromium, manganese and molybdenum, with a tight specification of their allowable composition range. This steel is qualified by RCC-MR Code 2007 [4]. Items Table 2: Materials used for VV and IWS. Material Main Vessel SS316L(N)-ITER Grade 1 Ports SS316L(N)-ITER Grade 1 SS 304L (EN grade ) SS 304 (EN grade1.4301) In-wall shielding 304B4 or 304B7 (UNS S30464/7) (UNS 43000) Bolts Alloy 718 or Steel 660 (EN grades) XM-19 (B8R) Note 1) Special requirements for 316L(N)-IG are as follows; Nitrogen control (0.06~0.08%) to keep consistent strength Limitation of impurities: - Co(0.05%): reduction of contact dose and gamma heating - Nb(0.01%): reduction of activated waist - Boron (0.0001%): limit He production 2) Borated steels are containing 1 or 2 weight % boron. CLASSIFICATION AND APPLIED CODES The VV provides high quality vacuum for plasma and primary radioactivity confinement boundary. The VV is classified into a safety important class (SIC) component based on the French safety and quality order The VV design shall take into account the various loads combinations for which the VV safety functions are needed including seismic events. 2 Copyright 2011 by ASME

3 The VV consists of an assembly of a number of individual nuclear pressure equipments (NPE) as per definition of the NPE Order 2005 [5]. The assembly will appear only after welding of the components supplied to the ITER site. The VV and some port sections are multi-chamber equipments. According to regulatory requirement, NPE Order, the VV are classified into category and nuclear level as shown in Table 3. An Agreed Notified Body (ANB) contracted by the IO is in charge of the conformity assessment in order to demonstrate that the necessary safety requirements are satisfied [6]. The RCC-MR Code, Edition 2007, is selected as the design and construction code for mechanical components of nuclear installations. For items which are not covered by the Code, ITER Organization s technical specifications are used. The VV and ports are classified as Class 2 box structure components and applicable design rules are provided in the RCC-MR RC 3800 chapter and complemented by Appendix 19. The design and construction code for IWS blocks is ASME III NC. Table 3: Category and nuclear level for Vacuum Vessel. Equipment All cooled by VV primary heat transfer system (PHTS) (3.0 MPa) - Main vessel (9 sectors) - All port stub extensions - All port extension of lower ports - Port extension of equatorial NB ports Upper ports - Port extensions cooled by First Wall/ Blanket PHTS (5.0 MPa) Regular equatorial ports - Port extensions cooled by First Wall/ Blanket PHTS (5.0 MPa) No NPE Order Classification Category IV Category IV Category III Level N2 Level N3 Level N3 custom-machined splice plates which will be thicker than the VV wall to allow misalignment between sectors [2]. Figure 3: Composition of a VV Sector. The segment has inner and outer shells, T-shape poloidal ribs, flexible support housings, in-vessel coil supports and port stub like Figure 4. The lower segment has special attachments such as gussets, pipe penetrations, triangular supports and divertor rails. These are to be made using forging blocks. SECTOR DESIGN FOR THE VACUUM VESSEL The VV is to be fabricated in the factory as nine sectors each spanning 40 degree. The weight of each sector is about 200 tons and its height and width are 13 m and 6 m, respectively. 60 mm-thick stainless steel plates forms a doublewall that contains additional 250 tons of IWS. A 40 degree sector consists of four major segments which are inboard segment (PS1), upper segment (PS2), equatorial segment (PS3) and lower segment (PS4) as shown in Figure 3. The baseline fabrication scheme of a VV sector is the welding of four poloidal segments with segment splices [3]. According to the baseline assembly scheme for the VV sector developed by IO, each sector will be sub-assembled with a pair of Toroidal Field (TF) coils and thermal shield segments in the ITER Assembly Hall. The sub-assembled sectors are then transferred into ITER pit, in sequence, to complete sector assembly. VV sectors are welded together to form three sets of VV triples these triplets are then aligned and welded together. Welding between the sectors to be joined is conducted by fitting Figure 4: Configuration of Lower Segment. 3 Copyright 2011 by ASME

4 DESIGN OF THE VV PORTS The vacuum vessel has 18 ports at the upper level of the machine, 14 regular and 3 NB ports at the equatorial level, and 9 port and 18 local penetrations at the lower level. A typical port structure is attached to the port stub (integral to the main vessel) and includes a stub extension and a port extension. The end portion of the port extension is normally equipped with a closure plate that provides the primary vacuum boundary. The port extension is connected to the cryostat with a connecting duct that is a part of the secondary vacuum boundary (except the NB ports). The basic port arrangement is shown in Figure 5 and a summary of port usage and inside dimensions are summarized in Table 4 [3]. Figure 5: The Basic Port Arrangement (Typical Sector). used for the RF plasma heating and current drive, plasma diagnostics, for positioning the plasma limiters and test modules, etc. An access to the blanket modules for maintenance will be also through the regular equatorial ports. The NB ports will provide access for the neutral beams for the plasma heating and current drive, and the diagnostics. The lower RH/Diagnostics ports will be used for the divertor cassette maintenance and diagnostics and the lower cryopump ports will be used for the vacuum pumping, pellet/gas injection and piping. The local penetrations are used for the divertor water piping, IVV, GDC, location of the VS coil feeders, and so on. WELDING METHODS The shapes of the VV and ports are very complicated double structure and require severe dimension control. Based on these considerations, narrow gap gas tungsten arc welding (GTAW) and electron beam welding (EBW) procedures were considered as the main welding process. GTAW processes are divided into a manual type and a machine type in terms of their accessibility and productivity. HHI has developed three different welding equipments which are to be applied in main shell butt welding, rib to shell welding and shell to FSH with narrow gap joint and hot wire system. T-shape adapters are introduced to the welding joints between outer shell and rib, which satisfies the code requirements such as the full penetration weld and the minimum distance between the welds due to lots weld components and complexity of assembly. The details of major welding joint for inboard and outboard segments are demonstrated in Figure 6 and 7. For EBW between inner shell and FSHs, tight fit-up with gap less than 0.1 mm is required to achieve required welding quality. For outer shell welding, narrow U-type groove as shown in Figure 6(a) shall be required because of the single side accessibility. For both sides accessing region, K-type groove is adopted like (b). Table 4: Summary of Port Usage and Inside Dimensions. Port Port Type Inside Dimensions (m) No. Upper (width) x 1.16 (height) Equatorial - Regular - Heating Neutral Beam - Heating/Diagnostic Neutral Beam (width) x 2.2 (height) (width) x 1.36 (height) (width) x 1.36 (min. height) (width) x (min. height) Lower - RH/Diagnostics - Cryopumps - Local penetrations (width) x (height) 1.39 (width) x (height) Various sizes (a) (b) (c) The port structures have many functions. The upper ports will be used for diagnostics, EC plasma stabilization, and blanket/vv water piping. The regular equatorial ports will be Figure 6: Welding Joint Details for Inboard Segment. (a) FSHs and center rib to outer shell. (b) Ribs on inner shell. (c) Side ribs on outer shell. 4 Copyright 2011 by ASME

5 (a) (b) (c) (d) (a) (b) (c) Figure 7: Welding Joint Details for Outboard Segment. (a) FSHs and port stub to inner shell. (b) Ribs on inner shell. (c) FSHs and port stub to outer shell. In case of welds to be examined by ultrasonic test (UT), the minimum distance between the welds is the larger 1.5 times the thickness of the thickest part to be assembled or 40 mm. These welding designs comply with the code requirements such as the full penetration weld and the minimum distance between the welds as well as 100% volumetric NDE condition. FABRICATION SEQUENCE OF A SEGMENT The manufacturing sequence of segments is developed to satisfy the design requirement. EBW and narrow gap TIG welding techniques are adopted and developed through the manufacturing mock-ups. Each segment is to be made according to the following common fabrication sequence; 1. Cutting and forming of inner and outer shells 2. Welding of inner shells 3. Welding of ribs to the inner shell 4. Machining FSH holes and welding FSH to the inner shell 5. Machining port hole and welding port stub 6. Welding support ribs for IWS 7. Assembly of IWS 8. Welding the outer shells 9. Final machining of a segment An inboard segment has a lot of attachments welded which are 48 FSH, 12 intermodular keys, 6 centering keys and so on. These FSH and keys are welded on the inner shell by EBW process under full vacuum in order to minimize welding distortion and to increase productivity. Due to the limitation of the vacuum chamber in available facility, inner shell of the inboard segment divides into two pieces for EBW. Figure 8 shows the fabrication sequence of an inboard segment briefly. Several strong jigs will be used to minimize welding distortion as sketched in red. (e) (f) (g) (h) Figure 8: Fabrication Sequence of an Inboard Segment (PS1). (a) Bending shells and machining of holes for key. (b) TIG welding of ribs and E-beam welding of keys. (c) E-beam welding of keys. (d) Hole machining for FSHs. (e) E-beam welding of FSHs. (f) Upper & Lower shells welding and IWS ribs. (g) Installing IWS. (h) Cover welding of outer shell. SEGEMTNS ASSEMBLY SCHEME The baseline fabrication scheme of a VV sector is welding of four poloidal segments with segment splices. For minimizing the welding deformation during final joint of segments, HHI has been developed the design of segment joints without poloidal rib splices to reduce the butt welding work of poloidal ribs as shown in Figure 9. Reduced weld joints will release the risk of sector tolerance mismatch. Figure 9: Segment Joint Configuration of PS2 and PS3. Figure 10 shows the joint details for each segment joint. Prior to machining on final welding of segment, 3-dimensional 5 Copyright 2011 by ASME

6 (3D) measurement of each segment should be conducted to collect their locations and adjust machining quantities. And the margin will be machined to provide proper welding condition. Scallops are needed in the welding line intersecting areas and can provide the space to take radiographic test (RT) on inner shell weld. The scallop will not be applied on both 40 o side ribs for leak tightness of one complete sector. (b) Interface bracket of gusset welding. (c) T-rib welding on the upper part of inner shell. (d) Lower part of inner shell and support pad welding. (e) Rail support welding. (f) T-rib welding on the lower part of inner shell. (g) Welding upper and lower part of inner shell. (h) Waterstopping flange welding and joint area cutting. (i) Outer shell welding. (a) (b) (c) (d) Figure 10: Joint Details for Final Segment Assembly. (a) PS1 and PS2. (c) PS2 and PS3. (b) PS1 and PS4. (d) PS3 and PS4. FABRICATION SCHEME OF THE LOWER PORT The manufacturing sequence of lower port stub extension is developed to satisfy the design requirement. Narrow gap GTAW welding techniques are adopted and developed through the manufacturing mock-ups for port stub extension. Figure 11 shows the sequence of the lower port stub extension briefly. MOCK-UP FABRICATION HHI decided to make the partial full scale mock-up to develop their fabrication procedures as shown in Figure 12 [7] [8]. The first mock-up, VV inboard segment mock-up (VISM) is to develop and stabilize EBW techniques. The lower parts of the inboard segment are made for the optimization of EBW techniques including repair and NDE method development. The second mock-up is 20 degree VV upper segment mock-up (VUSM). This is for the verification of forming, machining technique, welding sequence optimization and distortion control. By this mock-up, HHI will also ensure that NG-GTAW welding method, NDE procedures, and dimension inspection method are applicable to the final production. In addition, 10 degree partial mock-up for the triangular support of lower segment (VLTM) is planned to develop the copper cladding fabrication method. Full scale lower port mock-up (VLPM) is also under the fabrication to assess fabrication feasibility for the VV ports. (a) (b) (c) (d) (e) (f) (g) (h) (i) Figure 11: Fabrication Sequence of a Port Stub Extension. (a) Upper part of Inner shell welding and machining. Figure 12: R&D Mock-up for the Fabrication Feasibility Study. (a) VISM: VV inboard segment mock-up. (b) VUSM: VV upper segment mock-up. (c) VLTM: VV lower-segment triangular support mock-up. (d) VLPM: VV lower port mock-up. Stainless steel 316L was used for the mock-up fabrication because its properties and material contents are close to the ITER graded stainless steel 316L(N)-IG except nitrogen and radioactive impurity contents control for the ITER grade one. As a first step of mock-up fabrication, the EBW test with the specimen was performed to find the optimum welding 6 Copyright 2011 by ASME

7 parameters. After the survey of welding parameters by bead on plate welding, the liner butt joint and circular welding test were performed. Figure 13 shows the radiographic test of result for the liner butt joint welding specimen [8]. The both side EBW shows the optimum results and is selected as a basic welding scheme. (b) Figure 13: RT Result of Linear Butt Joint EBW. The components of each mock-up are under fabrication except VLPM for design finalization. Except outer shell, all the VISM components were assembled. Electron beam welding method was applied to the assembly of flexible support housings, center keys, and intermodular keys to minimize weld distortion as shown in Figure 14. The other components such as ribs and inner shells were assembled by narrow gap GTAW. To check assembly feasibility of IWS, one set of IWS was fabricated. After then, assembly of outer shells will be done including final dimensional inspection. Major issues for the VISM fabrication were the distortion of inner shell due to lots of weld components and feasibility of NDE. Application of EBW reduced risk of weld distortion considerably and there were no problems in RT and UT for the inner shell weld components. During fabrication, design of jigs and fixtures was finalized. Figure 14: Fabrication of VV Inboard Segment Mock-up (VISM). (a) Inner shell side view. (b) Outer shell side view. For VUSM, the region of the VV inner shell has 3D shapes and it consists of four kinds of 3D zones as shown in Figure 15. Since both zone 1 and zone 2 are divided by two shells, inner shell of VV upper segment is to be divided by 6 shells. All the inner shells were 3D formed by the cold forming as shown in Figure 16 through 19. Each formed shell was measured using 3D measuring system like Figure 20 and machined for weld preparation as Figure 21. The inner shell is under the stage of fit-up to assembly jig (Figure 22) for the welding like Figure 23. During the VUSM R&D works, major issues are the weld distortion and thickness reduction due to 3D forming. The jigs and fixtures were designed to minimize the weld distortion for the VV sector fabrication. HHI is considering maximum 9% of inner shell thickness reduction due to cold forming so that the structural analysis was done for the load conditions given from ITER organization. The results of stress analysis including limit analysis are complied with the RCC-MR code requirements. (a) Figure 15: Inner Shell Shape of Upper Segment. 7 Copyright 2011 by ASME

8 Figure 16: Formed Inner Shell for Zone 1. Figure 20: 3-Dimensional Measuring of Zone 1. Figure17: Formed Inner Shell for Zone 2. Figure 21: Machining for Weld Preparation. Figure 18: Formed Inner Shell for Zone 3. Figure 22: Jig Setting. Figure 19: Formed Inner Shell for Zone 4. Figure 23: Fit-up on the Jig and Measuring. 8 Copyright 2011 by ASME

9 SUMMARY The fabrication design has been developed to manufacture the main vessel and port structures based on IO s Build-to-Print design in accordance with the RCC-MR code. All fabrication sequences including welding methods are also established to meet the demanding tolerance and inspection requirement by HHI as a supplier. Welding designs comply with the code requirements such as the full penetration weld and the minimum distance between the welds as well as 100% volumetric NDE condition. Through the fabrication of several mock-ups, the fabrication design of VV sectors and ports will be verified and refined in the near future. ACKNOWLEDGMENTS This work has been supported partially by the Ministry of Education, Science and Technology of the Republic of Korea under the Korean ITER project contract. REFERENCES 1. ITER: the world s largest Tokamak, ITER website, 2. ITER 2009 Baseline Plant Description (PD), ITER Organization, ITER DDD 1.5 Vacuum Vessel, ITER Organization, Design and Construction Rules for Mechanical Components of Nuclear Installation, RCC-MR, French Association for the Design, Construction and Operating Supervision of the Equipment for Electro-Nuclear boilers (AFCEN), Edition Arrete du 12 decembre 2005 relatif aux equipements sous pression nucleaires (ESPN), Order dated 12 th December 2005 concerning nuclear pressure equipment (NPE Order 2005). 6. Ioki, K. et al., ITER vacuum vessel design and construction, Fusion Engineering and Design, vol. 85, , Bak, J. S. et al., Preparations for the ITER Vacuum Vessel Construction, 23 rd IAEA Fusion Energy Conference, October 2010, Deajeon, Korea. 8. Kim. B. C. et al., Fabrication Design Progress of ITER Vacuum Vessel in Korea, 23 rd IAEA Fusion Energy Conference, October 2010, Deajeon, Korea. 9 Copyright 2011 by ASME

ITER The way to a benign and limitless new energy

ITER The way to a benign and limitless new energy ITER The way to a benign and limitless new energy source A global collaboration has been formed to test the feasibility of fusion Page 1 ITR/1-1 Preparations of the ITER Vacuum Vessel Construction 11 October,

More information

ITER The way to a benign and limitless new energy

ITER The way to a benign and limitless new energy ITER The way to a benign and limitless new energy source A global collaboration has been formed to test the feasibility of fusion Page 1 ITR/1-1 Preparations of the ITER Vacuum Vessel Construction 11 October,

More information

Call for Nomination. Vacuum Vessel Assembly Welding

Call for Nomination. Vacuum Vessel Assembly Welding Call for Nomination Vacuum Vessel Assembly Welding Purpose ITER will be the world's largest experimental facility to demonstrate the scientific and technical feasibility of fusion power. The Vacuum Vessel

More information

ITER Vacuum Vessel Status and Procurement

ITER Vacuum Vessel Status and Procurement ITER Vacuum Vessel Status and Procurement IBF, Nice 11 December 2007 Presented by K. Ioki Tokamak Department, ITER Organization 1 VV design Design Review Activities VV Procurement Contents Main Vessel

More information

Status of Design and R&D Activities for ITER Thermal Shield

Status of Design and R&D Activities for ITER Thermal Shield ITR/P1-41 1 Status of Design and R&D Activities for ITER Thermal Shield W. Chung 1), K. Nam 1), C. H. Noh 1), D. K. Kang 1), H. K. Park 1), H. J. Ahn 1), J. S. Bak 1), K. J. Jung 1), K. Ioki 2), Y. Utin

More information

Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components

Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components K. Ioki and V. Chuyanov for the ITER International Team and Participant Teams ITER International Team, Boltzmannstr.

More information

Preparations for the ITER Vacuum Vessel Construction

Preparations for the ITER Vacuum Vessel Construction 1 ITR/1-1 Preparations for the ITER Vacuum Vessel Construction J. S. Bak (1), B. C. Kim (1), J. W. Sa (1), S. Wu (2), K. Ioki (2), L. Jones (3), P. Savrukhin (4), H. Pathak (5), Y. J. Lee (1), K. H. Hong

More information

Status of Design and Research & Development for ITER Sector Sub-assembly Tools

Status of Design and Research & Development for ITER Sector Sub-assembly Tools 1 ITR/P1-47 Status of Design and Research & Development for ITER Sector Sub-assembly Tools K.O. Nam 1), H.K. Park 1), D.J. Kim 1), H.J. Ahn 1), J.H. Lee 2), K.K. Kim 2), K. Im 3), R. Shaw 3) 1) National

More information

Key Features and Progress of the KSTAR Tokamak Engineering

Key Features and Progress of the KSTAR Tokamak Engineering 1 Key Features and Progress of the KSTAR Tokamak Engineering J. S. Bak, C. H. Choi, Y. K. Oh, Y. S. Kim, N. I. Her, K. H. Im, H. L. Yang, B. C. Kim, I. K. Yoo, J. W. Sa, H. K. Kim, M. Kwon, G. S. Lee,

More information

Design Progress and Analysis for ITER Thermal Shield

Design Progress and Analysis for ITER Thermal Shield 1 IT/P7-21 Design Progress and Analysis for ITER Thermal Shield W. Chung 1), K. W. Nam 1), C. H. Noh 1), B. C. Kim 1), J. W. Sa 1), Y. Utin 2), K. Ioki 2), N. I. Her 2), J. Yu 2), H. J. Ahn 1), K. J. Jung

More information

QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT

QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT R. Martínez-Oña, A. García, M.C. Pérez, Tecnatom, Spain; G. Pirola, Ansaldo Nucleare, Italy ABSTRACT The vacuum vessel

More information

VV procurement by the EU

VV procurement by the EU ITER Business Forum Meeting Nice, December 13, 2007 VV procurement by the EU L. Jones, EFDA 1 CONTENTS 1. VV Sharing and EU Scope 2. VV Contract Requirements 3. VV Specification 4. EU companies and Institutes

More information

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1)

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1) Technical Summary IO/14/CFT/9560/ACS CP/1 Version 2.0 dated 29/09/14 Technical Summary Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1) Control of modifications Version Section(s)

More information

ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme

ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme K. Ioki 1), W. Daenner 2), K. Koizumi 3), V.Krylov 4), A. Cardella 1), F. Elio 1), M. Onozuka 1), ITER Joint Central

More information

Call for Nomination Documents IDM UID W37G6V. VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION

Call for Nomination Documents IDM UID W37G6V. VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION IDM UID W37G6V VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION Call for Nomination Documents Vacuum Vessel In-Service Inspection_Phase 3, Lot 1 (WP5): Summary

More information

ITER Assembly Opportunities

ITER Assembly Opportunities ITER Assembly Opportunities Assembly Workshop Robert Shaw ITER Organization 1 Assembly Workshop Robert Shaw Nice France 10-12 December 2007 Acropolis Congress Centre Contents Overview of the ITER Machine

More information

Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary of Technical Specifications

Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary of Technical Specifications IDM UID TVL3N8 VERSION CREATED ON / VERSION / STATUS 21 Oct 2016 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Call for Nomination Documents Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary

More information

Documentation required to be presented by. DAs and Material Manufacturers

Documentation required to be presented by. DAs and Material Manufacturers ITER_D_2MT72B v2.2 Documentation required to be presented by DAs and Material s in accordance with Regulatory and Code requirements for the ITER Vacuum Vessel and Port components Abstract This document

More information

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING Route de Vinon-sur-Verdon - CS 90 046-13067 St Paul Lez Durance Cedex - France ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING CALL FOR NOMINATION Ref. IO/CFN/14/11176/PMT SUMMARY

More information

Technical Summary. 1. Purpose

Technical Summary. 1. Purpose 1. Purpose Technical Summary The purpose of this procurement is to establish a contract to provide mechanical and electrical plant installation works in the following areas on the ITER Site in Saint-Paul

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

The ITER Blanket System Design Challenge

The ITER Blanket System Design Challenge The ITER Blanket System Design Challenge Presented by A. René Raffray Blanket Section Leader; Blanket Integrated Product Team Leader ITER Organization, Cadarache, France With contributions from B. Calcagno

More information

Technical Summary. Purpose. ITER_D_RZ5S7J v2.1

Technical Summary. Purpose. ITER_D_RZ5S7J v2.1 Purpose Technical Summary The purpose of this project is to provide mechanical and electrical plant installation works in the following Buildings on the ITER Site in Saint-Paul Lez Durance, France: Building

More information

Technical Summary for the Tokamak Assembly Works- A0

Technical Summary for the Tokamak Assembly Works- A0 IDM UID S7YD73 VERSION CREATED ON / VERSION / STATUS 30 Jan 2017 / 1.3 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for the Tokamak Assembly

More information

Current Status of the KSTAR TF Superconducting Magnet Development

Current Status of the KSTAR TF Superconducting Magnet Development Journal of the Korean Physical Society, Vol. 49, December 2006, pp. S240 S244 Current Status of the KSTAR TF Superconducting Magnet Development B. S. Lim, J. Y. Choi, S. Lee, C. S. Kim, I. S. Woo, D. J.

More information

INFORMATION DAY. Fusion for Energy (F4E)

INFORMATION DAY. Fusion for Energy (F4E) INFORMATION DAY 26th November 2013, Zagreb Fusion for Energy (F4E) Part 2 Status of the ITER Project and Achievements Jesus Izquierdo Technical Coordination and Integration 1 THE ITER PROJECT MAIN SYSTEMS

More information

Technology Development for the Construction of ITER Superconducting Magnet System

Technology Development for the Construction of ITER Superconducting Magnet System Technology Development for the Construction of ITER Superconducting Magnet System K. Okuno, H. Nakajima, M. Sugimoto, T. Isono, K. Kawano, N. Koizumi, K. Hamada, Y. Nunoya, Y. Nabara, K. Kitamura, M. Oshikiri,

More information

Dimensional Control Systems 3DCS and ITER, the World s Largest Tokamak Experiment

Dimensional Control Systems 3DCS and ITER, the World s Largest Tokamak Experiment , the World s Largest Tokamak Experiment December, 2012 Kristy Erdodi Benjamin Reese Tom Halcrow , the World s Largest Tokamak Experiment The Project: ITER ITER is a global collaboration involving China,

More information

DEMO Concept Development and Assessment of Relevant Technologies

DEMO Concept Development and Assessment of Relevant Technologies 1 FIP/3-4Rb DEMO Concept Development and Assessment of Relevant Technologies Y. Sakamoto, K. Tobita, H. Utoh, N. Asakura, Y. Someya, K. Hoshino, M. Nakamura, S. Tokunaga and the DEMO Design Team Japan

More information

Technical Specifications (In-Cash Procurement)

Technical Specifications (In-Cash Procurement) IDM UID V5MEWY VERSION CREATED ON / VERSION / STATUS 21 Jul 2017 / 1.1 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Call for Nomination: Summary of the Technical

More information

KSTAR Assembly and Vacuum Commissioning for the 1 st Plasma

KSTAR Assembly and Vacuum Commissioning for the 1 st Plasma 1 FT/P3-4 KSTAR Assembly and Vacuum Commissioning for the 1 st Plasma H. L. Yang, H. K. Kim, K. M. Kim, J. W. Sa, S. T. Kim, H. T. Kim, G. P. Kim, K. S. Lee, K. H. Kim, S. H. Seo, S. H. Hahn, Y. K. Oh,

More information

TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE

TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE ERIC VILLEDIEU IAEA WORKSHOP DAEJEON KOREA 2018, 7 TH 10 TH OF MAY ISFNT-12 14-18 September 2O15 PAGE 1 CONTENT o o Problematic CFETR exercice Tokamak

More information

FUSION TECHNOLOGY INSTITUTE

FUSION TECHNOLOGY INSTITUTE FUSION TECHNOLOGY INSTITUTE Two-Dimensional Nuclear Analysis in Support of ITER Blanket Module Design W I S C O N S I N M.E. Sawan May 2011 UWFDM-1393 FUSION TECHNOLOGY INSTITUTE UNIVERSITY OF WISCONSIN

More information

Concept of power core components of the SlimCS fusion DEMO reactor

Concept of power core components of the SlimCS fusion DEMO reactor Concept of power core components of the SlimCS fusion DEMO reactor K. Tobita, H. Utoh, Y. Someya, H. Takase, N. Asakura, C. Liu and the DEMO Design Team Japan Atomic Energy Agency, Naka, Ibaraki-ken, 311-0193

More information

ASTM Standards for Pipe & Fittings

ASTM Standards for Pipe & Fittings for Pipe & Fittings There are many International Standards for stainless and carbon steel pipes and fittings. The list below is a basic overview of some of these. For more in-depth details of these Standards

More information

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

Technical Summary for TCC0 Global overview of the scope for TCC0 contract IDM UID V89YJN VERSION CREATED ON / VERSION / STATUS 06 Oct 2017 / 2.0 / Signed EXTERNAL REFERENCE / VERSION Technical Specification Technical Summary for TCC0 Global overview of the scope for TCC0 contract

More information

Design Status of JT-60SA Vacuum Vessel

Design Status of JT-60SA Vacuum Vessel J. Plasma Fusion Res. SERIES, Vol. 9 (2010) Design Status of JT-60SA Vacuum Vessel Yusuke K. SHIBAMA, Kei MASAKI, Shinji SAKURAI, Kiyoshi SHIBANUMA and Akira SAKASAI Japan Atomic Energy Agency, Naka, Ibaraki-ken

More information

ARIES Safety-Related Components and Nuclear Grade Requirements

ARIES Safety-Related Components and Nuclear Grade Requirements ARIES Safety-Related Components and Nuclear Grade Requirements L. El-Guebaly, University of Wisconsin-Madison L. Cadwallader and B. Merrill Idaho National Laboratory Contributors: N. Taylor (ITER) and

More information

2.15 Tokamak Seismic Analysis

2.15 Tokamak Seismic Analysis 2.15 Tokamak Seismic Analysis 2.15.1 Introduction 1 2.15.2 Input Conditions 3 2.15.2.1 Design Response Spectra 3 2.15.2.2 Damping Coefficients 4 2.15.3 Model Overview 4 2.15.4 Main Results Under SL-2 Seismic

More information

ITER Status & Opportunities. Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier

ITER Status & Opportunities. Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier ITER Status & Opportunities Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier AGENDA Fusion ITER Fusion for Energy (F4E) Project status Business Opportunities what/how? F4E

More information

Industry experience, views and comments - Hollming Works Oy. Mr. Mika Korhonen Development Manager Hollming Works Oy

Industry experience, views and comments - Hollming Works Oy. Mr. Mika Korhonen Development Manager Hollming Works Oy Industry experience, views and comments - Hollming Works Oy Mr. Mika Korhonen Development Manager Hollming Works Oy Contents Company information Narrow Gap Welding Technologies 3D Cold Forming 3.6.2010,

More information

Fully Active Cooled In-vessel Components of EAST Tokamak

Fully Active Cooled In-vessel Components of EAST Tokamak 1 FTP/P1-30 Fully Active Cooled In-vessel Components of EAST Tokamak Y.T. Song, X. Ji, G. Shen, T.J. Xu, Z.B. Zhou, L. Cao, X.F. Liu, W.W. Xu, X.B. Peng, S.M. Wang, P, Zhang, N. Zhu, J.F. Wu, D.M. Gao,

More information

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA PVP2011-57675 PVP2011- PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE

More information

SECTION III DIVISIONS 1 AND 2

SECTION III DIVISIONS 1 AND 2 SECTION III DIVISIONS 1 AND 2 Subject Interpretation File No. Division 1 Appendix N, Table N-1230-1; Damping Values (1998 Edition)... III-1-04-27 NI03-025 Code Cases 2142-1 and 2143-1... III-1-04-22 NI03-019

More information

The world s first commercial LNG fuel tank made of high manganese austenitic steel

The world s first commercial LNG fuel tank made of high manganese austenitic steel The world s first commercial LNG fuel tank made of high manganese austenitic steel Jiwon Yu 1), Kihwan Kim 1), Do-Won Seo 1), Sung Tae Yun 1), Geon Shin 1), Hyun Kug Lee 2) 1) POSCO 2) Ilshin Marine Transport

More information

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up INSTITUTE FOR PLASMA RESEARCH (An Autonomous Institute of Department of Atomic Energy, Government of India) Near Indira Bridge; Bhat; Gandhinagar-382428; India PART-I (B) Technical Specification for Fabrication,

More information

R & D of the Fabrication Technology for ITER Magnet Supports

R & D of the Fabrication Technology for ITER Magnet Supports ITR/P1-45 R & D of the Fabrication Technology for ITER Magnet Supports 1 P. Y. Lee*, 1 C.J.Pan, 1. L. Hou, 1 S.L.Han, 1 Z.C.Sun, 1 X. R. Duan, 1 Y. Liu, 2 F. Savary, 2 Y. K. Fu and 2 R. Gallix, 2 N. Mitchell

More information

Summary Technical Specification. In-vessel Survey Development

Summary Technical Specification. In-vessel Survey Development Version 1.3 Summary Technical Specification In-vessel Survey Development Page 1 of 8 BACKGROUND Background ITER is a joint international research and development project that aims to demonstrate the scientific

More information

EU considerations on Design and Qualification of Plasma Facing Components for ITER

EU considerations on Design and Qualification of Plasma Facing Components for ITER EU considerations on Design and Qualification of Plasma Facing Components for ITER Patrick Lorenzetto, F4E Barcelona with inputs from B. Riccardi (F4E), V. Barabash and M. Merola (ITER IO) on Readiness

More information

The Tokamak Concept. Magnetic confinement. The Tokamak concept

The Tokamak Concept. Magnetic confinement. The Tokamak concept Major radius Minor radius The Tokamak Concept ITER is based on the tokamak concept. A tokamak is a device able to produce and confine a large volume of high temperature plasma -a mixture of electrons and

More information

Historical overview on Vacuum suitable Welding and fatigue resistance in Research Devices

Historical overview on Vacuum suitable Welding and fatigue resistance in Research Devices Historical overview on Vacuum suitable Welding and fatigue resistance in Research Devices Martin Wolf E-mail:emartin.wolf@gmail.com Summary New inventions change the approach of vacuum suitable welding

More information

Safety Classification of Mechanical Components for Fusion Application

Safety Classification of Mechanical Components for Fusion Application Safety Classification of Mechanical Components for Fusion Application 13 rd International Symposium on Fusion Nuclear Technology 25-29 September 2017, Kyoto, Japan Oral Session 1-2: Nuclear System Design

More information

The use of Heavy Plate in the fabrication of Urea Pool Reactor

The use of Heavy Plate in the fabrication of Urea Pool Reactor The use of Heavy Plate in the fabrication of Urea Pool Reactor (by F. Foroni, F. Fusari, N. Maestri, P. Marangoni, F. Orlandi) Abstract One of the principal items of high pressure equipment in the design

More information

ITER REMOTE HANDLING SYSTEM

ITER REMOTE HANDLING SYSTEM ITER REMOTE HANDLING SYSTEM Alessandro Tesini ITER International Organization Remote Handling Section 1 Remote Handling A.Tesini Nice France 10-12 December 2007 Acropolis Congress Centre Contents 1. ITER

More information

Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL

Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL Presentation of Case Study Manufacture of a Helium/Hydrogen Heat Exchanger to the ASME Code presented

More information

JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1

JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1 JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1 Abstract. 1) CEA, DEN, DTN, Nuclear Technology Department, CEA Cadarache. F-13108

More information

Examples Page 43 of 45

Examples Page 43 of 45 UHDE-STANDARD Welding UN WELDED JOINTS V416-01 for vessels and equipment Part 2 (M) Examples Page 43 of 45 Item Figure Application Requirements Notes Small pad type flanges of austenitic steel, clad vessel

More information

The following considerations are taken into account for designing the NUHOMS MP197 packaging.

The following considerations are taken into account for designing the NUHOMS MP197 packaging. 14th International Symposium on the Packaging and Paper # 164 Transportation of Radioactive Materials (PATRAM 2004), Berlin, Germany, September 20-24, 2004 NUHOMS - MP197 Transport Cask Peter Shih, TRANSNUCLEAR,

More information

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1 ITER Organization Françoise Flament Head of Procurement Arrangements & Contracts Division Page 1 1. Overview of the IO Procurement System 2. Business Opportunities 3. IO Procurement Processes and Procedures

More information

Divertor Cassette Body Overview of the Annex B F4E-OMF-444

Divertor Cassette Body Overview of the Annex B F4E-OMF-444 Divertor Cassette Body Overview of the Annex B F4E-OMF-444 Barcelona, 2013-03-12 Disclaimer: data is given for information only and cannot be considered as binding for the on-going Call for Tender 1 Content

More information

3ème RV Business du Nucléaire Civil en PACA. ITER Organization Future Call for Tenders

3ème RV Business du Nucléaire Civil en PACA. ITER Organization Future Call for Tenders 3ème RV Business du Nucléaire Civil en PACA ITER Organization Future Call for Tenders Disclaimer: The views and opinions expressed herein do not necessarily reflect those of the ITER Organization Outline

More information

ITER R&D Needs, Challenges, and the Way Forward

ITER R&D Needs, Challenges, and the Way Forward ITER R&D Needs, Challenges, and the Way Forward Bernard Bigot Director General ITER Organization, Cadarache, France Fusion Power Co-ordinating Committee Mtg, IO Headquarters, 24 Jan 2018 1 Context of ITER

More information

ITER ITA NEWSLETTER NO. 22, MAY 2005 INTERNATIONAL ATOMIC ENERGY AGENCY, VIENNA, AUSTRIA ISSN

ITER ITA NEWSLETTER NO. 22, MAY 2005 INTERNATIONAL ATOMIC ENERGY AGENCY, VIENNA, AUSTRIA ISSN ITER ITA NEWSLETTER NO. 22, MAY 2005 INTERNATIONAL ATOMIC ENERGY AGENCY, VIENNA, AUSTRIA ISSN 1727 9852 RECENT JAPANESE PARTICIPANT TEAM (JA-PT) ACTIVITIES By Dr. M. Mori, Leader JA-PT, JAERI 1. Introduction

More information

First steps towards a European design and construction code for research reactors

First steps towards a European design and construction code for research reactors First steps towards a European design and construction code for research reactors C.Pascal - B.Drubay AREVA TA - CEA SEMT/LISN& AFCEN chairman of RCC-MRx Sub commission IGORR 13 Knoxville, september 2010

More information

Fusion R&D Strategy from A Technology Viewpoint

Fusion R&D Strategy from A Technology Viewpoint Fusion R&D Strategy from A Technology Viewpoint Mohamed A. Abdou UCLA Presented at ISFNT-4, Tokyo, Japan 7 April, 1997 The Region Immediately Surrounding the Plasma Divertor / First Wall / Blanket /Vacuum

More information

COMPLETION OF THE FIRST TF COIL STRUCTURE OF ITER

COMPLETION OF THE FIRST TF COIL STRUCTURE OF ITER FIP1-1 / CN258 COMPLETION OF THE FIRST TF COIL STRUCTURE OF ITER M. NAKAHIRA, M. IGUCHI, T. SAKURAI, H. OZEKI, E. FUJIWARA, K. TAKANO, Y.S. HONG, M. INO, M. NISHINO, N. KOIZUMI (QST) N. SAWA, D. HARA,

More information

GUIDELINES FOR INSPECTION OF HULL WELDS

GUIDELINES FOR INSPECTION OF HULL WELDS CCS Rule Change Notice For GUIDELINES FOR INSPECTION OF HULL WELDS Version: October 2017. RCN No.1 Effective date: 1 January, 2018 Beijing CHAPTER 3 QUALIFICATION TESTS OF WELDERS Section 1 General Provisions

More information

High performance blanket for ARIES-AT power plant

High performance blanket for ARIES-AT power plant Fusion Engineering and Design 58 59 (2001) 549 553 www.elsevier.com/locate/fusengdes High performance blanket for ARIES-AT power plant A.R. Raffray a, *, L. El-Guebaly b, S. Gordeev c, S. Malang c, E.

More information

European Experience In Transport / Storage Cask for Vitrified Residues

European Experience In Transport / Storage Cask for Vitrified Residues ABSTRACT European Experience In Transport / Storage Cask for Vitrified Residues L. Blachet, C. Otton, D. Sicard AREVA TN International Because of the evolution of burnup of spent fuel to be reprocessed,

More information

Development of the High Voltage Bushing for the ITER NBI

Development of the High Voltage Bushing for the ITER NBI J. Plasma Fusion Res. SERIES, Vol. 9 (2010) Development of the High Voltage Bushing for the ITER NBI Hiroyuki TOBARI, Takashi INOUE, Masayuki DAIRAKU, Naotaka UMEDA, Mieko KASHIWAGI, Masaki TANIGUCHI,

More information

Improved Design of a Helium- Cooled Divertor Target Plate

Improved Design of a Helium- Cooled Divertor Target Plate Improved Design of a Helium- Cooled Divertor Target Plate By X.R. Wang, S. Malang, R. Raffray and the ARIES Team ARIES-Pathway Meeting University of Wisconsin, Madison April 23-24, 2009 Critical Design

More information

CHAPTER 4. Design of Innovative Creep Testing Facility under Flowing. Sodium

CHAPTER 4. Design of Innovative Creep Testing Facility under Flowing. Sodium CHAPTER 4 Design of Innovative Creep Testing Facility under Flowing Sodium 4.1 Introduction In this chapter, design of an innovative creep testing system comprising of a lever arm type creep machine with

More information

Recent Progress of GIS/GDC Design and Manufacturing for ITER

Recent Progress of GIS/GDC Design and Manufacturing for ITER 1 Recent Progress of GIS/GDC Design and Manufacturing for ITER W.Li 1), B.Li 1), M.Wang 1), J.Zeng 1), T.Jiang 1), Z.Xia 1), Z.Wu 1) S.Marayama 2), Y.Yang 2) 1) Southwestern Institute of Physics, Chengdu,

More information

Graded approach practices for the mechanical components of French research reactor projects

Graded approach practices for the mechanical components of French research reactor projects Graded approach practices for the mechanical components of French research reactor projects Claude PASCAL RMR/RR Rabat IAEA conference, november 2011 Content Context Classification of SSCs Associated Requirements

More information

QUALIFICATION OF THE ULTRASONIC INSPECTIONS OF VACUUM VESSEL WELDS OF THE ITER REACTOR

QUALIFICATION OF THE ULTRASONIC INSPECTIONS OF VACUUM VESSEL WELDS OF THE ITER REACTOR More Info at Open Access Database www.ndt.net/?id=18508 QUALIFICATION OF THE ULTRASONIC INSPECTIONS OF VACUUM VESSEL WELDS OF THE ITER REACTOR ABSTRACT F. Fernández, A. García, M.C. Pérez, R. Martinez-Oña

More information

Status Report and Documentation of DCLL Design

Status Report and Documentation of DCLL Design Status Report and Documentation of DCLL Design He primary and secondary loops footprint at TCWS DCLL design evolution DCLL, DEMO inboard routing assessment Documentation of DCLL design Clement Wong, Dick

More information

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi The Code is a large document and it is sometimes very difficult to understand. Even for many of us who work with it every day. In my opinion there is no one person who could be termed as a Code Expert.

More information

9. VACUUM TANK 9. VACUUM TANK

9. VACUUM TANK 9. VACUUM TANK 9. VACUUM TANK This system constitutes the external part of the solenoid cryostat. The vacuum tank, made of stainless steel, is cantilevered from the central ring of the barrel yoke. It houses and supports

More information

Remote Maintenance Topic Summary

Remote Maintenance Topic Summary UKAEA - RACE Remote Maintenance Topic Summary Oliver Crofts 5 th IAEA DEMO Programme Workshop Daejeon, Korea 7 th to 10 th May 2018 Tokamak architecture RM Strategies must be defined early to drive the

More information

Summary of Major Features of ARIES- ST and ARIES-AT Blanket Designs

Summary of Major Features of ARIES- ST and ARIES-AT Blanket Designs Summary of Major Features of ARIES- ST and ARIES-AT Blanket Designs Presented by A. René Raffray University of California, San Diego with the Contribution of the ARIES Team and S. Malang APEX Meeting,

More information

ZIRCALOY WELDING IN OPAL REACTOR REFLECTOR VESSEL

ZIRCALOY WELDING IN OPAL REACTOR REFLECTOR VESSEL ZIRCALOY WELDING IN OPAL REACTOR REFLECTOR VESSEL Ortiz L. and Martínez R. INVAP SE, S. C. de Bariloche, Río Negro, Argentina Abstract This paper describes the development of the Zircaloy 4 welding processes

More information

ASME B31.3 Process Piping

ASME B31.3 Process Piping ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1 Piping Development Process 1. Establish applicable system

More information

Oregon State University s Small Modular Nuclear Reactor Experimental Program

Oregon State University s Small Modular Nuclear Reactor Experimental Program Oregon State University s Small Modular Nuclear Reactor Experimental Program IEEE Conference on Technologies for Sustainability August 1, 2013 Portland, Oregon Brian Woods Oregon State University brian.woods@oregonstate.edu,

More information

Long term renovation inside KSTAR vacuum vessel toward steady state operation

Long term renovation inside KSTAR vacuum vessel toward steady state operation IAEA SSO Long term renovation inside KSTAR vacuum vessel toward steady state operation Jong-Gu Kwak, S.W. Jung, S.G. Kim, J.H. Kim, D.R. Lee K-DEMO On behalf of KSTAR team NFRI, Korea KSTAR ITER Near term(~2021)

More information

Wendelstein 7-X A technology step towards DEMO

Wendelstein 7-X A technology step towards DEMO A technology step towards DEMO Hans-Stephan Bosch Max-Planck Institute for Plasma Physics Greifswald, Germany 18th Internatinal Toki Conference, December 9 13, 2008, Toki-City, Japan 1-YKA06-Y0001.0 The

More information

DTT FLEXIBILITY: VV, DIVERTOR, FW AND REMOTE HANDLING ISSUES. G. Di Gironimo on behalf of DTT team

DTT FLEXIBILITY: VV, DIVERTOR, FW AND REMOTE HANDLING ISSUES. G. Di Gironimo on behalf of DTT team DTT FLEXIBILITY: VV, DIVERTOR, FW AND REMOTE HANDLING ISSUES G. Di Gironimo on behalf of DTT team DTT Workshop, Frascati, 19-20 June 2017 G. Di Gironimo DTT Workshop Frascati 19-20 June 2017 1 DTT FLEXIBILITY:

More information

ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service

ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1. Scope 1.1 This specification 2 covers wrought carbon steel and alloy steel fittings

More information

Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications

Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications More info about this article: http://www.ndt.net/?id=21122 Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications

More information

Preliminary Design of ITER Component Cooling Water System and Heat Rejection System

Preliminary Design of ITER Component Cooling Water System and Heat Rejection System Preliminary Design of ITER Component Cooling Water System and Heat Rejection System A.G.A. Kumar 1, D.K. Gupta 1, N. Patel 1, G. Gohil 1, H. Patel 1, J. Dangi 1, L. Sharma 1, M. Jadhav 1, L. Teodoros 2,

More information

BUREAU OF INDIAN STANDARDS Draft Indian Standard

BUREAU OF INDIAN STANDARDS Draft Indian Standard For Comments Only BUREAU OF INDIAN STANDARDS Draft Indian Standard STEEL PLATES FOR PRESSURE VESSEL FOR INTERMEDIATE AND HIGH TEMPERATURE SERVICE INCLUDING BOILERS (Third Revision of IS 2002) ICS 77.140.30

More information

SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY FORGINGS

SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY FORGINGS TECHNICAL LITERATURE: ASME SB-381 [ASTM B381] Company Website: www.metalspiping.com Your Reliable Supplier of Titanium & Nickel Alloys SB-381 SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY FORGINGS ð13þ

More information

WELDING Topic and Contents Hours Marks

WELDING Topic and Contents Hours Marks Topic and Contents Hours Marks 3.1 Introduction 04 Marks Classification and selection of welding process. Working principle of Gas welding and types of flames. 3.2 Arc welding process 08 Marks Metal arc,

More information

DCLL Blanket for ARIES-AT: Major Changes to Radial Build and Design Implications

DCLL Blanket for ARIES-AT: Major Changes to Radial Build and Design Implications DCLL Blanket for ARIES-AT: Major Changes to Radial Build and Design Implications L. El-Guebaly Fusion Technology Institute UW - Madison ARIES-Pathways Project Meeting December 12-13, 2007 Georgia Tech

More information

Hydrogen Fusion The frontier in abundant CO 2 -free energy generation

Hydrogen Fusion The frontier in abundant CO 2 -free energy generation Hydrogen Fusion The frontier in abundant CO 2 -free energy generation Mark Uhran US ITER Project Office Briefing to: East Tennessee Environmental Business Association 26 September, 2013 Oak Ridge, TN A

More information

A feasible DEMO blanket concept based on water cooled solid breeder

A feasible DEMO blanket concept based on water cooled solid breeder 1 FTP/P7-33 A feasible DEMO blanket concept based on water cooled solid breeder Y. Someya 1, K. Tobita 1, H. Utoh 1, K. Hoshino 1, N. Asakura 1, M. Nakamura 1, Hisashi Tanigawa 2, M. Enoeda 2, Hiroyasu

More information

Design and Development of Lower Divertor for JT-60SA

Design and Development of Lower Divertor for JT-60SA 1 FTP/P1-29 Design and Development of Lower Divertor for JT-60SA S. Sakurai, H. Higashijima, H. Kawashima, Y. K. Shibama, T. Hayashi, H. Ozaki, K. Shimizu, K. Masaki, K. Hoshino, S. Ide, K. Shibanuma,

More information

Hot Cell Complex Building Engineering Contract (REVISED)

Hot Cell Complex Building Engineering Contract (REVISED) Hot Cell Complex Building Engineering Contract (REVISED) Call for Nomination It is important to note that participation in this tender process will NOT cause a conflict of interest (and hence exclusion)

More information

FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA

FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA Pallav Chattopadhyay, B K Rai & Y S Trivedi Larsen & Toubro Limited India Abstract:

More information

ARIES-ACT-DCLL NWL Distribution and Revised Radial Build

ARIES-ACT-DCLL NWL Distribution and Revised Radial Build ARIES-ACT-DCLL NWL Distribution and Revised Radial Build L. El-Guebaly and A. Jaber Fusion Technology Institute University of Wisconsin-Madison http://fti.neep.wisc.edu/uwneutronicscenterofexcellence Contributors:

More information

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Page 1 / 15 Ver. 1.1 TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Abstract The experimental fusion reactor ITER will require the European supply of the Poloidal

More information