VV procurement by the EU

Size: px
Start display at page:

Download "VV procurement by the EU"

Transcription

1 ITER Business Forum Meeting Nice, December 13, 2007 VV procurement by the EU L. Jones, EFDA 1

2 CONTENTS 1. VV Sharing and EU Scope 2. VV Contract Requirements 3. VV Specification 4. EU companies and Institutes involved in the ITER/EU VV Sector Manufacture Design and R&D 5. ITER/EU VV Sector Manufacture Design and R&D 6. VV Sector Construction Stages 7. Proposed EU VV Sector Manufacture Schedule 2

3 The VV is shared between 4 Parties Korea 2 Sectors, Equatorial and Lower ports, Vessel Supports) Russia Upper Ports India In-wall shielding EU 7 Sectors The EU contract will be to make 7 D-shaped Sectors and then weld the upper and lower ports to them The VV Sector Assembly is to be carried out by the EU under a different contract and will not be presented here 3

4 VV Contract Requirements The VV Sector Tender for 7 ITER VV Sectors will be for firms or consortia which have the capabilities as follows: Large assembly workshop with 600 Ton crane and height access of 15 m Facilities for machining large and heavy components Experience in quality welding of stainless steel thick sections Access to deliver the 13m x 7m x 7m Sectors to a sea port High level of Quality Assurance Certification Highly qualified engineering personnel for CAD design, analysis, inspection, programme management and QA Access to advanced computer engineering calculation facilities and programs A project management team with considerable experience in procurement and subcontracting of large stainless steel components Advanced NDT (Ultrasonic and X-ray Inspection) experience and facilities Tender Issue September, 2008 Contract Start May,

5 EU companies and Institutes involved in the ITER/EU VV Sector Manufacture Design and R&D 19 Companies and Institutes in 9 Countries have contributed to the work shown in this presentation Czech Republic 1. Institute of Applied Mechanics, Brno Finland 1. Hollming Works, Kankaanpää Works Oy 2. Univ. of Tampere France 1. AREVA, Lyon 2. DCNS, Nantes 3. CEA, Arceuil 4. CEA, Saclay Germany 1. AREVA, Erlangen 2. MAN-DWE, Deggendorf 3. Pro-Beam, Burg Holland 1. NRG, Petten 2. Exploform, Rijswijk Italy 1. Ansaldo Ricerche, Genoa 2. SIMIC, Camerana Slovenia 1. Univ. of Ljubiana Spain 1. Iberdrola, Madrid 2. Technatom, Madrid UK 1. Phoenix Inspection Systems, Warrington 2. TWI, Abington 5

6 EU VV Sector Manufacture Design and R&D Sector Manufacturing Possible Manufacturing Routes No-Segments With Segments Biggest problem is the tight tolerances, +-10 mm and +-5 mm at the edges Finished Segments Semi-Finished Segments Finished Segments E-Beam Welded Finished Segments Arc Welded Semi-Finished Segments Arc Welded 6

7 No-Segments VV Construction Method The Inner shell is first completed with a jig with large hydraulic jacks, which can force correct shape. The inner segment is completed with the outer shell by EB welding A local E-Beam welding system is used to weld the inner shell to the housings Advantage is that the shape can be very well controlled Disadvantage is that all the work is done in a large facility 7

8 Semi-Finished Segments VV Construction Method The Segments are completed apart from the outer shell, with heavy jigs welded to the inner shell to prevent distortion The Segments are joined and then the outer shell added Advantage is that the Segment joining can be made without undue distortion Disadvantage is that the jigs are expensive to make and remove 8

9 Finished Segments VV Construction Method The Sector is divided Poloidally into 4 Segments Inboard (shown here) - Upper - Equatorial - Lower Each Segment is finished before being welded to the others There is a problem with the joining of the segments to maintain the shape Disadvantage is that the segment joining may lead to distortion Advantage is that each Segment can be made is a smaller facility 9

10 Finished Segments VV Construction Method R&D Sector Model (1) A ful-sized part of a poloidal sector, weighing 20 Tons, was constructed by Ansaldo/SIMIC Italy, including the Segment joint between the inboard and upper Segment. A frame was included to replace the stiffness of the rest of the Sector and obtain realistic distortion results 10

11 Finished Segments VV Construction Method R&D Sector Model (2) WELD DISTORTION PREDICTION To gain information on welds shrinkage and deformations, all types of welded joints were reproduced, simulating their constraints, by validation mock-ups with temperature and distortion measurements Housing Outer Shell The structure was built up on heavy 80 mm thick jigs, welded to the inner shell Inner Shell Rib JIG Two Segments were finished separately on the jigs. The cylindrical parts welded with EB welding 11

12 Finished Segments VV Construction Method R&D Sector Model (3) WELD DISTORTION PREDICTION The joint between the two segments was welded. The distortion were measured by 3D Laser Scan with a grid spacing 70x70 mm 85% of the surface (blue points) complies with the target fabrication tolerances (± 5 mm) All surfacesare within the 10 mm required tolerance 12

13 Finished Segments VV Construction Method R&D Sector Model (4) SYSWELD Weld Distortion Analysis The complete assembly process was simulated with computer analysis by IAM, Brno 34 weld joints with 1970 beads were used in a Local-Global method There was very good agreement between measurement and calculation This method can (and will) be used to predict the distortion for the complete VV Sector fabrication 13

14 Finished Segments VV Construction Method Using E Beam Welding only (1) With the conventional fabrication method, the structure is built starting with the inner shell, adding ribs and cylindrical features, and then carrying out the closure weld The disadvantage is that the arc welding produces large distortions unless controlled In this all-eb welded method, the box structure is first produced, then the cylindrical features stepwise added Thus all welds may be inspected through the access holes 14

15 Finished Segments VV Construction Method Using E Beam Welding only (2) This all-eb welded method is possible due to the existence of very large EB chambers at Pro- Beam, Germany, and DCNS and CNIM, France 15

16 Finished Segments VV Construction Method Using E Beam Welding only (3) First at DCNS, Nantes, a smaller validation mock-up has been constructed to verify the techniques and welding processes The shells are held by clamps and machined so that the precise fit-up with the ribs is achieved 16

17 Finished Segments VV Construction Method Using E Beam Welding only (4) The manufacture of the full-size inboard segment is proceeding. The shielding blocks can be easily lowered from above and secured through the access holes to be used later for cylindrical features 17

18 VV Sector R&D UT Inspection (1) Technatom, Spain: Use of existing scanning device to Sector mock-up for UT inspection 18

19 VV Sector R&D UT Inspection (2) At Phoenix Inspection and CEA Saclay (with phased array), specialised UT techniques have been developed to reliably inspect the one sided closure welds of the outer shell, where no access to the root side is possible 19

20 VV Specification The Appendices form the bulk of the Specification and include: 14 Mandatory Technical Appendices 6 Informative Technical Appendices MANDATORY Manufacturing Requirements Welding Procedures Specifications 2-D Drawings NDE Methods Dimensional Inspection APPENDICES Additional Testing Packing, shipping and handling Supplier structural verification Final Acceptance Validation Mock-ups INFORMATIVE APPENDICES Vacuum Vessel Description Possible Manufacturing Routes ITER Structural Calculations Previous VV R&D 3-D CATIA models Vacuum Requirements Engineering Analysis Pressure, Flow Testing Information required for Tender Information valid only for Tender 20

21 VV Sector Construction 1 Pre-Procurement Procurement of Stainless Steel Base Material by F4E Forgings produced for EB welded VV Prototype The ITER Grade 316 (N) material has up to a 15 month delivery period, so to avoid schedule delays, F4E will purchase about 40% of this material for freeissue to the Supplier 21

22 VV Sector Construction 2 Design Studies Mock up Designs Design Calculations + SYSWELD Manufacturing Procedures Intermediate Design Review Manufacturing Drawings Documentation for the Notified Body The first design activity is to complete the concept of the assembly method and design the Validation Mock-Ups An important milestone after 5 months is the ITER design review to include calculation and French Authority acceptance of design, before the manufacturing drawings and material procurement can proceed 22

23 Manufacturing Development VV Sector Construction 3 Validation Mock-Ups and Studies are required to ensure that the ITER specification is achieved. A. Large Mock-ups, Machines and Studies to ensure manufacturing tolerances A1. Segment joining - inboard and outboard welding access and distortion A2. SYSWELD calculations and validation of model of assembly method with instrumented welding coupons A3. Development of special machines for manufacture, e.g for local machining of FH bores and Sector Edges and EB local welding of Housings to Inner Shell B. Smaller Mock-ups to validate special ITER requirements B1. One sided welding issues Gas protection and UT Inspection B2. Shell Surface Water channels Cleaning, Corrosion, Cleaniness B3. Shell Surface Vacuum facing High Vacuum performance, Emissivity B4. Shielding Plates Assembly, especially at segment joints 23

24 Tooling Fabrication VV Sector Construction 4 Procurement of machining device Jig Fabrication Jig-Supports Erection Frames Upending Frame Vertical Support Transportation frame The assembly method assumed here uses steel jigs which must have a greater stiffness than the VV in order to suppress most of the welding distortion 80 mm thickness plate with a total weight the same as the finished VV construction is used The jigs are not re-useable as they have to be massively welded to the inner shell 24

25 The duration of the most complicated and largest (36% of total) segment is 1 year and 2 months. The triangular section introduces severe complications VV Sector Construction 5 Lower Segment Production Triangular Support Fabrication Welding to Inner Shell Pieces Inner Shell Pieces welding Ribs to Inner Shell Welding Port Stub Welding Housings m/c+ EB Weld Outer Shell welding 25

26 VV Sector Construction 6 Auxiliary Items Production The manufacture of Blanket Manifolds, brackets and splice plates does not lie on the critical path 26

27 Assembly to form Sector VV Sector Construction 7 Bring in the segments in sequence Lower-Inboard- Equatorial-Upper Ports Welding Cutting, Surface Cleaning Removal of Jigs The Finishing Frame works, required to achieve the tolerances includes: the machining of each flexible housing bore > 200 per Sector the machining of the thread of each flexible housing the machining of each key facing surface the machining of the edges of the Sector with a J welding preparation 27

28 VV Sector Construction 8 Testing, Assembly of Auxiliary Items and Delivery Vacuum Leak Tests Pressure Test Installation of Blanket Manifolds, Diagnostics Dimensional and Final Acceptance Packing Shipping to Cadarache The execution of the Vacuum Leak testing involves the construction of a temporary enclosure for the Helium gas and pumping of the VV interspace. Should any leaks occur, there may be considerable delays before the leak is localised 28

29 VV Sector Schedule 29

Call for Nomination. Vacuum Vessel Assembly Welding

Call for Nomination. Vacuum Vessel Assembly Welding Call for Nomination Vacuum Vessel Assembly Welding Purpose ITER will be the world's largest experimental facility to demonstrate the scientific and technical feasibility of fusion power. The Vacuum Vessel

More information

QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT

QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT QUALIFICATION OF ULTRASONIC INSPECTIONS IN THE ITER VACUUM VESSEL MANUFACTURING PROJECT R. Martínez-Oña, A. García, M.C. Pérez, Tecnatom, Spain; G. Pirola, Ansaldo Nucleare, Italy ABSTRACT The vacuum vessel

More information

ITER The way to a benign and limitless new energy

ITER The way to a benign and limitless new energy ITER The way to a benign and limitless new energy source A global collaboration has been formed to test the feasibility of fusion Page 1 ITR/1-1 Preparations of the ITER Vacuum Vessel Construction 11 October,

More information

ITER The way to a benign and limitless new energy

ITER The way to a benign and limitless new energy ITER The way to a benign and limitless new energy source A global collaboration has been formed to test the feasibility of fusion Page 1 ITR/1-1 Preparations of the ITER Vacuum Vessel Construction 11 October,

More information

ITER Vacuum Vessel Status and Procurement

ITER Vacuum Vessel Status and Procurement ITER Vacuum Vessel Status and Procurement IBF, Nice 11 December 2007 Presented by K. Ioki Tokamak Department, ITER Organization 1 VV design Design Review Activities VV Procurement Contents Main Vessel

More information

Preparations for the ITER Vacuum Vessel Construction

Preparations for the ITER Vacuum Vessel Construction 1 ITR/1-1 Preparations for the ITER Vacuum Vessel Construction J. S. Bak (1), B. C. Kim (1), J. W. Sa (1), S. Wu (2), K. Ioki (2), L. Jones (3), P. Savrukhin (4), H. Pathak (5), Y. J. Lee (1), K. H. Hong

More information

Industry experience, views and comments - Hollming Works Oy. Mr. Mika Korhonen Development Manager Hollming Works Oy

Industry experience, views and comments - Hollming Works Oy. Mr. Mika Korhonen Development Manager Hollming Works Oy Industry experience, views and comments - Hollming Works Oy Mr. Mika Korhonen Development Manager Hollming Works Oy Contents Company information Narrow Gap Welding Technologies 3D Cold Forming 3.6.2010,

More information

Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components

Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components Convergence of Design and Fabrication Methods for ITER Vacuum Vessel and In-vessel Components K. Ioki and V. Chuyanov for the ITER International Team and Participant Teams ITER International Team, Boltzmannstr.

More information

ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme

ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme ITER-FEAT Vacuum Vessel and Blanket Design Features and Implications for the R&D Programme K. Ioki 1), W. Daenner 2), K. Koizumi 3), V.Krylov 4), A. Cardella 1), F. Elio 1), M. Onozuka 1), ITER Joint Central

More information

FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL

FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA PVP2011-57143 FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM

More information

Status of Design and R&D Activities for ITER Thermal Shield

Status of Design and R&D Activities for ITER Thermal Shield ITR/P1-41 1 Status of Design and R&D Activities for ITER Thermal Shield W. Chung 1), K. Nam 1), C. H. Noh 1), D. K. Kang 1), H. K. Park 1), H. J. Ahn 1), J. S. Bak 1), K. J. Jung 1), K. Ioki 2), Y. Utin

More information

Summary Technical Specification. In-vessel Survey Development

Summary Technical Specification. In-vessel Survey Development Version 1.3 Summary Technical Specification In-vessel Survey Development Page 1 of 8 BACKGROUND Background ITER is a joint international research and development project that aims to demonstrate the scientific

More information

Technical Summary for the Tokamak Assembly Works- A0

Technical Summary for the Tokamak Assembly Works- A0 IDM UID S7YD73 VERSION CREATED ON / VERSION / STATUS 30 Jan 2017 / 1.3 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for the Tokamak Assembly

More information

Status of Design and Research & Development for ITER Sector Sub-assembly Tools

Status of Design and Research & Development for ITER Sector Sub-assembly Tools 1 ITR/P1-47 Status of Design and Research & Development for ITER Sector Sub-assembly Tools K.O. Nam 1), H.K. Park 1), D.J. Kim 1), H.J. Ahn 1), J.H. Lee 2), K.K. Kim 2), K. Im 3), R. Shaw 3) 1) National

More information

Call for Nomination Documents IDM UID W37G6V. VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION

Call for Nomination Documents IDM UID W37G6V. VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION IDM UID W37G6V VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION Call for Nomination Documents Vacuum Vessel In-Service Inspection_Phase 3, Lot 1 (WP5): Summary

More information

ITER Assembly Opportunities

ITER Assembly Opportunities ITER Assembly Opportunities Assembly Workshop Robert Shaw ITER Organization 1 Assembly Workshop Robert Shaw Nice France 10-12 December 2007 Acropolis Congress Centre Contents Overview of the ITER Machine

More information

Key Features and Progress of the KSTAR Tokamak Engineering

Key Features and Progress of the KSTAR Tokamak Engineering 1 Key Features and Progress of the KSTAR Tokamak Engineering J. S. Bak, C. H. Choi, Y. K. Oh, Y. S. Kim, N. I. Her, K. H. Im, H. L. Yang, B. C. Kim, I. K. Yoo, J. W. Sa, H. K. Kim, M. Kwon, G. S. Lee,

More information

Technical Specifications (In-Cash Procurement)

Technical Specifications (In-Cash Procurement) IDM UID V5MEWY VERSION CREATED ON / VERSION / STATUS 21 Jul 2017 / 1.1 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Call for Nomination: Summary of the Technical

More information

Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary of Technical Specifications

Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary of Technical Specifications IDM UID TVL3N8 VERSION CREATED ON / VERSION / STATUS 21 Oct 2016 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Call for Nomination Documents Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary

More information

NUMERICAL SIMULATION OF THE WELDING PROCESS - DISTORTION AND RESIDUAL STRESS PREDICTION, HEAT SOURCE MODEL DETERMINATION

NUMERICAL SIMULATION OF THE WELDING PROCESS - DISTORTION AND RESIDUAL STRESS PREDICTION, HEAT SOURCE MODEL DETERMINATION NUMERICAL SIMULATION OF THE WELDING PROCESS - DISTORTION AND RESIDUAL STRESS PREDICTION, HEAT SOURCE MODEL DETERMINATION 15 NUMERICAL SIMULATION OF THE WELDING PROCESS - DISTORTION AND RESIDUAL STRESS

More information

DRAFT DOCUMENT SUBJECT TO MODIFICATIONS. Foreseen Procedure. Estimated spending

DRAFT DOCUMENT SUBJECT TO MODIFICATIONS. Foreseen Procedure. Estimated spending TENDER DETAILS SUMMARY WP Ref. Division Name WP10/BA/03 Broader Approach Foreseen Procedure Estimated spending Magnets Strand qualification phase tests Negotiated < 250k Aim: quality control for NbTi strands

More information

Divertor Cassette Body Overview of the Annex B F4E-OMF-444

Divertor Cassette Body Overview of the Annex B F4E-OMF-444 Divertor Cassette Body Overview of the Annex B F4E-OMF-444 Barcelona, 2013-03-12 Disclaimer: data is given for information only and cannot be considered as binding for the on-going Call for Tender 1 Content

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

Design Progress and Analysis for ITER Thermal Shield

Design Progress and Analysis for ITER Thermal Shield 1 IT/P7-21 Design Progress and Analysis for ITER Thermal Shield W. Chung 1), K. W. Nam 1), C. H. Noh 1), B. C. Kim 1), J. W. Sa 1), Y. Utin 2), K. Ioki 2), N. I. Her 2), J. Yu 2), H. J. Ahn 1), K. J. Jung

More information

Simulation of electron beam welding distortions for the ITER Vacuum Vessel

Simulation of electron beam welding distortions for the ITER Vacuum Vessel 20th International Conference on Structural Mechanics in Reactor Technology (SMiRT 20) Espoo, Finland, August 9-14, 2009 SMiRT 20-Division Applied Computations, Simulation and Animation, Paper 1682 Simulation

More information

EU considerations on Design and Qualification of Plasma Facing Components for ITER

EU considerations on Design and Qualification of Plasma Facing Components for ITER EU considerations on Design and Qualification of Plasma Facing Components for ITER Patrick Lorenzetto, F4E Barcelona with inputs from B. Riccardi (F4E), V. Barabash and M. Merola (ITER IO) on Readiness

More information

ITER Status & Opportunities. Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier

ITER Status & Opportunities. Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier ITER Status & Opportunities Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier AGENDA Fusion ITER Fusion for Energy (F4E) Project status Business Opportunities what/how? F4E

More information

BUREAU OF INDIAN STANDARDS. Draft Indian Standard

BUREAU OF INDIAN STANDARDS. Draft Indian Standard For official use only BUREAU OF INDIAN STANDARDS Draft Indian Standard DOC: WRD 12(575)C November 2011 RECOMMENDATIONS FOR INSPECTION, TESTING AND MAINTENANCE OF RADIAL GATES AND ROPE DRUM HOISTS PART

More information

Contents EN 14015:2004 (E) page

Contents EN 14015:2004 (E) page Contents page Foreword... 11 1 Scope... 12 2 Normative references... 13 3 Terms, definitions, symbols and abbreviations... 15 3.1 Terms and definitions... 15 3.2 Symbols... 19 3.3 Abbreviations... 21 4

More information

GUIDELINES FOR INSPECTION OF HULL WELDS

GUIDELINES FOR INSPECTION OF HULL WELDS CCS Rule Change Notice For GUIDELINES FOR INSPECTION OF HULL WELDS Version: October 2017. RCN No.1 Effective date: 1 January, 2018 Beijing CHAPTER 3 QUALIFICATION TESTS OF WELDERS Section 1 General Provisions

More information

European Experience In Transport / Storage Cask for Vitrified Residues

European Experience In Transport / Storage Cask for Vitrified Residues ABSTRACT European Experience In Transport / Storage Cask for Vitrified Residues L. Blachet, C. Otton, D. Sicard AREVA TN International Because of the evolution of burnup of spent fuel to be reprocessed,

More information

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up INSTITUTE FOR PLASMA RESEARCH (An Autonomous Institute of Department of Atomic Energy, Government of India) Near Indira Bridge; Bhat; Gandhinagar-382428; India PART-I (B) Technical Specification for Fabrication,

More information

MSC Solutions for Additive Manufacturing Simufact Additive

MSC Solutions for Additive Manufacturing Simufact Additive MSC Solutions for Additive Manufacturing Simufact Additive 15.01.2018 Simufact Product Portfolio Cold Forming Hot Forging Sheet Metal Forming Mechanical Joining Powder Bed Fusion Arc Welding Laser Beam

More information

TABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8

TABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8 TABLE OF CONTENTS 1.0 INTRODUCTION Page 3 2.0 SCOPE Page 3 3.0 REFERENCES Page 4 4.0 REQUIREMENTS Page 5 5.0 QUALITY ASSURANCE Page 8 6.0 SUBMITTALS Page 9 7.0 PREPARATION FOR SHIPMENT Page 10 Page 2 of

More information

The ITER Blanket System Design Challenge

The ITER Blanket System Design Challenge The ITER Blanket System Design Challenge Presented by A. René Raffray Blanket Section Leader; Blanket Integrated Product Team Leader ITER Organization, Cadarache, France With contributions from B. Calcagno

More information

Large Seal Test Rig Technical Specification

Large Seal Test Rig Technical Specification IDM UID R7WQNK VERSION CREATED ON / VERSION / STATUS 05 Aug 2015 / 1.3 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Large Seal Test Rig Technical Specification

More information

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011. DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:

More information

Architectural Wall Products Guide Specifications

Architectural Wall Products Guide Specifications Western States Metal Roofing 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 Architectural Wall Products Guide Specifications FORMED METAL WALL PANELS This Guide Specification is

More information

SECTION AWNINGS

SECTION AWNINGS SECTION 10 73 13 AWNINGS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Fixed metal awnings. 1.2 DEFINITIONS A. Awning: An architectural projection that provides weather protection,

More information

FUSION TECHNOLOGY INSTITUTE

FUSION TECHNOLOGY INSTITUTE FUSION TECHNOLOGY INSTITUTE Two-Dimensional Nuclear Analysis in Support of ITER Blanket Module Design W I S C O N S I N M.E. Sawan May 2011 UWFDM-1393 FUSION TECHNOLOGY INSTITUTE UNIVERSITY OF WISCONSIN

More information

Edward W. Russell and Brian L. Anderson Lawrence Livermore National Laboratory Prepared by LLNL under Contract DE-AC52-07NA27344

Edward W. Russell and Brian L. Anderson Lawrence Livermore National Laboratory Prepared by LLNL under Contract DE-AC52-07NA27344 Comparison of German and American Fabrication Standards for Transportation and Storage Containments of High Level Radioactive Material Type B Packages 15055 ABSTRACT Edward W. Russell and Brian L. Anderson

More information

Mezzanines By Design Page 1

Mezzanines By Design Page 1 SECTION 05120 STRUCTURAL STEEL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions and Division 1 apply to this Section. 1.2 SUMMARY

More information

Design for welding: Design recommendations

Design for welding: Design recommendations Design for welding: Design recommendations Arc welding can be used to weld almost any kind of assembly, including even complex structures. Arc weldments use a wide variety of ferrous and non ferrous metals.

More information

PF Coils 2-6 Manufacturing Scope of the different contracts

PF Coils 2-6 Manufacturing Scope of the different contracts PF Coils 2-6 Manufacturing Scope of the different contracts Focus on Engineering Integrator and Winding Tooling PF Coils Information Meeting Barcelona - 15 th October 2012 This presentation is intended

More information

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

Technical Summary for TCC0 Global overview of the scope for TCC0 contract IDM UID V89YJN VERSION CREATED ON / VERSION / STATUS 06 Oct 2017 / 2.0 / Signed EXTERNAL REFERENCE / VERSION Technical Specification Technical Summary for TCC0 Global overview of the scope for TCC0 contract

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS

TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS 1.0 SCOPE This Specification establishes the requirements for manufacture, inspection, testing and supply

More information

The use of Heavy Plate in the fabrication of Urea Pool Reactor

The use of Heavy Plate in the fabrication of Urea Pool Reactor The use of Heavy Plate in the fabrication of Urea Pool Reactor (by F. Foroni, F. Fusari, N. Maestri, P. Marangoni, F. Orlandi) Abstract One of the principal items of high pressure equipment in the design

More information

Grading of the Management System Requirements to the Safe

Grading of the Management System Requirements to the Safe Grading of the Management System Requirements to the Safe Transport of Radioactive Materials Y.E. Tawfik ETRR-2 Complex, Egyptian Atomic Energy Authority, Cairo Egypt Received: 1/3/2016 Accepted: 7/6/2016

More information

Summary Technical Specification Building 13 - Metrology Laboratory

Summary Technical Specification Building 13 - Metrology Laboratory Summary Technical Specification Building 13 - Metrology Laboratory Page 1 of 6 1. Purpose The purpose of this Call for Nomination is to identify potential companies or consortia having the capacity to

More information

Australian/New Zealand Standard

Australian/New Zealand Standard AS/NZS 1665:2004 AS/NZS 1665 Australian/New Zealand Standard Welding of aluminium structures AS/NZS 1665:2004 This Joint Australian/New Zealand Standard was prepared by Joint Technical Committee WD-003,

More information

REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017

REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 G. MANENTI, V. PESCUMA AND S. SARTI, ALFA LAVAL OLMI SPA, ITALY, PROVIDE AN OVERVIEW OF THE DELIVERY SCHEDULE FOR A KEY PIECE OF HEAT TRANSFER EQUIPMENT, PROCESS

More information

SECTION STRUCTURAL METAL FRAMING

SECTION STRUCTURAL METAL FRAMING SECTION 05100 STRUCTURAL METAL FRAMING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Structural steel framing including lintels, shelf angles, bearing plates, anchor bolts and other items as shown on

More information

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1 ITER Organization Françoise Flament Head of Procurement Arrangements & Contracts Division Page 1 1. Overview of the IO Procurement System 2. Business Opportunities 3. IO Procurement Processes and Procedures

More information

STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS

STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY 1234 MARKET STREET, PHILADELPHIA, PA 19107 STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS REVISION DATE SPECIFICATION # F-S-304_

More information

M-03 HEAT EXCHANGERS

M-03 HEAT EXCHANGERS Guideline No.: M-03(201610) M-03 HEAT EXCHANGERS Issued date: October 28, 2016 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection

More information

Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL

Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL Presentation of Case Study Manufacture of a Helium/Hydrogen Heat Exchanger to the ASME Code presented

More information

Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications

Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications More info about this article: http://www.ndt.net/?id=21122 Weld defects analysis of 60 mm thick SS316L mock-ups of TIG and EB welds by Ultrasonic inspection for fusion reactor vacuum vessel applications

More information

INSTRUCTIONS FOR THE MANUFACTURE AND THE INSPECTION OF WELDED STEEL ASSEMBLIES

INSTRUCTIONS FOR THE MANUFACTURE AND THE INSPECTION OF WELDED STEEL ASSEMBLIES INSTRUCTIONS FOR THE MANUFACTURE AND THE 1. OBJECT AND FIELD OF APPLICATION 3 2. SUPPLIER 3 3. SUBCONTRACTING 3 4. WELDING 4 4.1 Welding documentation 4 4.2 Welding procedure specifications (WPS) 4 4.3

More information

Manufacture of Material Handling Equipment

Manufacture of Material Handling Equipment Manufacture of Material Handling Equipment TTS (Transportation Technology Systems) has more than 25 years of experience in manufacturing of industrial equipment, bridges and other large steel structures

More information

Fusion for Energy The European Domestic Agency for ITER. F4E Contracts & Procurement Unit

Fusion for Energy The European Domestic Agency for ITER. F4E Contracts & Procurement Unit Fusion for Energy The European Domestic Agency for ITER F4E Contracts & Procurement Unit Market Policy Group Agenda 1. Fusion Energy 2. ITER 3. Europe in ITER: F4E Fusion for Energy 4. F4E Contractual

More information

Diagnostic Port Plugs Manufacturing Expert. Technical Specifications

Diagnostic Port Plugs Manufacturing Expert. Technical Specifications Diagnostic Port Plugs Manufacturing Expert Technical Specifications Version 1.0 Date: 17/07/2012 Name Affiliation Author S PITCHER/M KEANE CHD / DIAGNOSTICS Reviewers M WALSH CHD/ DIAGNOSTICS Approver

More information

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Page 1 / 11 Ver. 1.3 MANAGEMENT SPECIFICATION FOR THE IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Abstract This document specifies the management requirements: the Supplier shall

More information

Storage & loading on site SOFREGAZ

Storage & loading on site SOFREGAZ Large Cryogenic above ground LNG Tank Full Containment (9% inner wall + Pre-stressed concrete outer wall) Typical Construction Sequence March 4 th 2011 Storage & loading on site Storage & loading on site

More information

Thick section laser welding

Thick section laser welding Thick section laser welding Chris Allen 1 Scope How thick is thick? Possible applications Advantages and challenges of thick section laser welding Traditional thick section laser welding techniques CO

More information

Manufacture of industrial machines, bridges and large metal structures

Manufacture of industrial machines, bridges and large metal structures Manufacture of industrial machines, bridges and large metal structures TTS (TRANSPORTATION TECHNOLOGY SYSTEMS) HAS MORE THAN 25 YEARS OF EXPERIENCE IN MANUFACTURING OF INDUSTRIAL EQUIPMENT, BRIDGES AND

More information

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING Route de Vinon-sur-Verdon - CS 90 046-13067 St Paul Lez Durance Cedex - France ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING CALL FOR NOMINATION Ref. IO/CFN/14/11176/PMT SUMMARY

More information

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1)

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1) Technical Summary IO/14/CFT/9560/ACS CP/1 Version 2.0 dated 29/09/14 Technical Summary Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1) Control of modifications Version Section(s)

More information

Introduction. 1. Outline of fan case ring

Introduction. 1. Outline of fan case ring A near-net-shape (NNS) ring-rolling process was developed to reduce the forging weight of a rolled, fan case front, ring made of Ti-6Al-4V. This was achieved by optimizing the ring-rolling process in which

More information

MAH MACHINE CO., INC S. Central Avenue Cicero, Illinois

MAH MACHINE CO., INC S. Central Avenue Cicero, Illinois MAH MACHINE CO., INC. 3301 S. Central Avenue Cicero, Illinois 60804 www.mahmachine.com Presentation Outline MAH Machine History and Overview Industries & Markets Served MAH Departments & Capabilities Assembly

More information

MECHANICAL DESIGN AND ENGINEERING OF THE 3.9 GHZ, 3 RD HARMONIC SRF SYSTEM AT FERMILAB

MECHANICAL DESIGN AND ENGINEERING OF THE 3.9 GHZ, 3 RD HARMONIC SRF SYSTEM AT FERMILAB MECHANICAL DESIGN AND ENGINEERING OF THE 3.9 GHZ, 3 RD HARMONIC SRF SYSTEM AT FERMILAB D. Mitchell, M. Foley, T. Khabiboulline, N. Solyak, FNAL, Batavia, IL 60510, USA Abstract The mechanical development

More information

Architectural Roof and Wall Products Guide Specifications

Architectural Roof and Wall Products Guide Specifications Architectural Roof and Wall Products Guide Specifications Western States Metal Roofing 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 FORMED METAL WALL PANELS This Guide Specification

More information

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Page 1 / 15 Ver. 1.1 TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Abstract The experimental fusion reactor ITER will require the European supply of the Poloidal

More information

SECTION (formerly 05425) PRE-ENGINEERED, PRE-FABRICATED COLD-FORMED STEEL ROOF & FLOOR TRUSSES

SECTION (formerly 05425) PRE-ENGINEERED, PRE-FABRICATED COLD-FORMED STEEL ROOF & FLOOR TRUSSES SECTION 05 44 00 (formerly 05425) PRE-ENGINEERED, PRE-FABRICATED COLD-FORMED STEEL ROOF & FLOOR TRUSSES PART 1 GENERAL 1.1 SUMMARY A. Section includes pre-engineered, pre-fabricated cold-formed steel framing

More information

C. Miscellaneous Metal Fabricators are specified elsewhere in Division 5.

C. Miscellaneous Metal Fabricators are specified elsewhere in Division 5. SECTION 05 1200 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.01 SUMMARY A. Extent of structural steel work is shown on drawings, including schedules, notes and details to show size and location of members,

More information

AMERICAN INSTITUTE OF TIMBER CONSTRUCTION AITC

AMERICAN INSTITUTE OF TIMBER CONSTRUCTION AITC AMERICAN INSTITUTE OF TIMBER CONSTRUCTION 7012 South Revere Parkway Suite 140 Centennial, Colorado 80112 Telephone (303) 792-9559 http://www.aitc-glulam.org AITC 115-2009 STANDARD FOR FABRICATED STRUCTURAL

More information

Dimensional Control Systems 3DCS and ITER, the World s Largest Tokamak Experiment

Dimensional Control Systems 3DCS and ITER, the World s Largest Tokamak Experiment , the World s Largest Tokamak Experiment December, 2012 Kristy Erdodi Benjamin Reese Tom Halcrow , the World s Largest Tokamak Experiment The Project: ITER ITER is a global collaboration involving China,

More information

Guidelines for the Construction of Pressure Vessel Type Tanks Intended for the Transportation of Anhydrous Ammonia at Ambient Temperatures

Guidelines for the Construction of Pressure Vessel Type Tanks Intended for the Transportation of Anhydrous Ammonia at Ambient Temperatures (1992) (1992/Corr.) Guidelines for the Construction of Pressure Vessel Type Tanks Intended for the Transportation of Anhydrous Ammonia at Ambient Temperatures 1. Scope 1.1 These Guidelines complement the

More information

ADVANCING ADDITIVE MANUFACTURING IN AEROSPACE AM-AERO14

ADVANCING ADDITIVE MANUFACTURING IN AEROSPACE AM-AERO14 ADVANCING ADDITIVE MANUFACTURING IN AEROSPACE AM-AERO14 ADDITIVE MANUFACTURING Aerospace is leading the way in adopting additive manufacturing (AM) for the manufacturing industry. AM allows aerospace manufacturers

More information

This document is a preview generated by EVS

This document is a preview generated by EVS EUROPEAN STANDARD NORME EUROPÉENNE EUROPÄISCHE NORM DRAFT pren 10025-2 March 2011 ICS 77.140.10; 77.140.45; 77.140.50 Will supersede EN 10025-2:2004 English Version Hot rolled products of structural steels

More information

DESIGN AND FABRICATION OF SERPENTINE TUBE TYPE SODIUM TO AIR HEAT EXCHANGERS FOR PFBR SGDHR CIRCUITS

DESIGN AND FABRICATION OF SERPENTINE TUBE TYPE SODIUM TO AIR HEAT EXCHANGERS FOR PFBR SGDHR CIRCUITS DESIGN AND FABRICATION OF SERPENTINE TUBE TYPE SODIUM TO AIR HEAT EXCHANGERS FOR PFBR SGDHR CIRCUITS Aravinda Pai, T.K.Mitra, T. Loganathan and Prabhat Kumar Prototype Fast Breeder Reactor Project Bharatiya

More information

Prototype Manufacturing and Testing of Components of the ECH Upper Launcher for ITER

Prototype Manufacturing and Testing of Components of the ECH Upper Launcher for ITER 1 Prototype Manufacturing and Testing of Components of the ECH Upper Launcher for ITER S. Schreck*, G. Aiello, G. Gantenbein, A. Meier, T.A. Scherer, P. Spaeh, D. Strauss, A. Vaccaro Karlsruhe Institute

More information

Technology Development for the Construction of ITER Superconducting Magnet System

Technology Development for the Construction of ITER Superconducting Magnet System Technology Development for the Construction of ITER Superconducting Magnet System K. Okuno, H. Nakajima, M. Sugimoto, T. Isono, K. Kawano, N. Koizumi, K. Hamada, Y. Nunoya, Y. Nabara, K. Kitamura, M. Oshikiri,

More information

NON-DESTRUCTIVE EVALUATION OF CLOSE DIE FORGED MAIN BODY OF PRIMARY SYSTEM VALVES

NON-DESTRUCTIVE EVALUATION OF CLOSE DIE FORGED MAIN BODY OF PRIMARY SYSTEM VALVES Proceedings of the National Seminar & Exhibition on Non-Destructive Evaluation NDE 2011, December 8-10, 2011 NON-DESTRUCTIVE EVALUATION OF CLOSE DIE FORGED MAIN BODY OF PRIMARY SYSTEM VALVES PK Sharma

More information

Architectural Roof Products Guide Specifications

Architectural Roof Products Guide Specifications Western States Metal Roofing 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 Architectural Roof Products Guide Specifications FORMED METAL ROOF AND WALL PANELS This Guide Specification

More information

Fusion: the fundamental principle

Fusion: the fundamental principle The ITER Project The ITER Project The ITER Project aims to demonstrate the scientific and technological feasibility of fusion power for peaceful purposes. Iter project is an international cooperation between

More information

Architectural Roof Products Guide Specifications

Architectural Roof Products Guide Specifications Western States Metal Roofing 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 Architectural Roof Products Guide Specifications FORMED METAL ROOF AND WALL PANELS This Guide Specification

More information

WELDING TECHNOLOGY AND WELDING INSPECTION

WELDING TECHNOLOGY AND WELDING INSPECTION WELDING TECHNOLOGY AND WELDING INSPECTION PRESENTED BY: GOPAL KUMAR CHOUDHARY SVL ENGINEERING SERVICES CHENNAI CONTENTS: DEFINATION TYPES OF WELDING ELECTRODE GEOMETRY EQUIPMENT QUALITY PROCESS SAFETY

More information

EXPERIENCES ON MASSIVE QUALIFICATION TEST BLOCK COMBINING MANY INSPECTION OBJECTS

EXPERIENCES ON MASSIVE QUALIFICATION TEST BLOCK COMBINING MANY INSPECTION OBJECTS EXPERIENCES ON MASSIVE QUALIFICATION TEST BLOCK COMBINING MANY INSPECTION OBJECTS Raimo Paussu, Jani Pirinen; Fortum Power and Heat Ltd, Espoo, Finland Petri Luostarinen, Fortum Power and Heat Ltd, Loviisa

More information

Inspection and Welding Repairs of Pressure Vessels

Inspection and Welding Repairs of Pressure Vessels Inspection and Welding Repairs of Pressure Vessels BY S. V. GUPTE B.E., D.M.E. ASNT LEVEL III - RT,MT,PT,VT PRESSURE VESSEL INSPECTOR (API 510), (CCOE) PAINT AND COATING INSPECTOR (NACE INDIA) LEAD AUDITOR

More information

SPECIFICATION OF NEOPRENE RUBBER SEALS

SPECIFICATION OF NEOPRENE RUBBER SEALS SPECIFICATION OF NEOPRENE RUBBER SEALS 1.0 SCOPE This specification establishes the requirements for the manufacture, inspection, testing, packing, guarantee & supply of Neoprene Rubber Seals for Fuelling

More information

QUALITY ASSURANCE PROTOCOL (QAP)

QUALITY ASSURANCE PROTOCOL (QAP) PREFACE This Standard details the level of documentation that PVT.LTD (IET) will provide during a contract for fabricating tank(s) or portable equipment s. Extensive documentation is required for this

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries

More information

CNC PROFILING PLATE ROLLING SUBMERGED ARC WELDING

CNC PROFILING PLATE ROLLING SUBMERGED ARC WELDING CNC PROFILING PLATE ROLLING SUBMERGED ARC WELDING HDS Energy has over thirty years experience in the design, manufacture and installation of bespoke boiler solutions for large energy and power projects

More information

SILOS IN MODULAR CONSTRUCTION Lower costs maximum flexibility

SILOS IN MODULAR CONSTRUCTION Lower costs maximum flexibility SILOS IN MODULAR CONSTRUCTION Lower costs maximum flexibility Silo Technology www.zeppelin.com INTELLIGENT DESIGN Zeppelin Bolt-Tec silos Our intelligent design ensures your technological lead: from now

More information

B. Shop Drawings: For metal lockers. Include plans, elevations, sections, details, and attachments to other work.

B. Shop Drawings: For metal lockers. Include plans, elevations, sections, details, and attachments to other work. SECTION 10 5113 - METAL LOCKERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 906 FEBRUARY 1993 CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL 906.01 SCOPE 906.02 REFERENCES 906.03 DEFINITIONS TABLE OF CONTENTS 906.04 SUBMISSION

More information

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B SECTION 05 5213 - PIPE RAILINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system. PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Fusion welded and rackable ornamental steel picket fence system. B. Related sections: 1. Section 03310 Concrete Work for post support. 2. Section 09960

More information

Architectural Roof and Wall Products Guide Specifications

Architectural Roof and Wall Products Guide Specifications Architectural Roof and Wall Products Guide Specifications 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 FORMED METAL ROOF AND WALL PANELS This Guide Specification is to be used

More information