Norfolk Southern s Online Rebuild of the Coosa River Bridge
|
|
- Kerry Simon
- 5 years ago
- Views:
Transcription
1 Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida Telephone: Facsimile: AREMA 2002 ANNUAL CONFERENCE September 24, 2002 at 11:00 a.m.
2 ABSTRACT Bridges built in the early 1900 s frequently require complete replacement based on a combination of factors including new loading considerations, deteriorating material conditions, and functional obsolescence. The existing steel trusses on the Coosa River Bridge had reached the end of their useful life based on fatigue and material condition. However, the stone piers were still in good condition and could last for many years to come. In an effort to keep project costs down to a minimum and take advantage of the good pier conditions, the rebuild of the Coosa River Bridge adopted a rehabilitation strategy for the substructure and a replacement strategy for the superstructure. This paper outlines the key design features for the successful rehabilitation of the substructure and rolling in of new truss spans. The project s performance exhibits how a complex project can be executed on-time, on-budget, without change-orders. Introduction Norfolk Southern Railway (NS) crosses the Coosa River in Childersburg, Alabama, at Milepost P , providing a critical strategic link between Columbus, Georgia, and Birmingham, Alabama, that serves as an alternate route and relief valve for rail congestion in Atlanta. Built in 1906, the existing Coosa River Bridge was comprised of an approach trestle and three 150-foot and one 200-foot Pratt truss spans supported on narrow stone piers founded on rock. The existing bridge had several fatigue-related problems and operated under a permanent slow order. The line routinely carries a low average tonnage, but when congestion in Atlanta develops, the line s importance increases dramatically. The flexibility the line offers was deemed very important to NS and necessitated the bridge s rebuild after NS determined in June 1999 that the bridge was nearing the end of its serviceable life and full or partial replacement would be required. Minimized line outages were critical to Norfolk Southern In September 1999, NS hired HDR to design and assemble construction documents for the bridge rebuild. Due to cost and schedule considerations, rehabilitation of the existing bridge was selected over full replacement. Additionally, any line outages for the rebuild would have to be minimized and the rehabilitated bridge would have to include greater track clearances. The rebuilt bridge
3 was planned to be in service within 18 months, including design and construction efforts. Due to operational requirements, any line outages for the rebuild could not exceed 24 hours, although three of the four required track outages were actually less than 12-hours. The Contractor elected to use a time-proven and economical method for an on-line replacement consisting of a controlled demolition of the existing truss spans followed by roll-in of the fully erected replacement truss spans from adjacent falsework. Special post-tensioning and doweling integrated the new cap with the existing pier cap and shaft. Rehabilitated Piers Of the original bridge structure, only the existing abutments, piers, pier caps and foundations were retained for use in the rehabilitated structure. The requirement of greater track clearances necessitated the use of wider trusses, and consequently, wider caps. Because the existing piers and pier caps were determined to be in good structural condition, they were incorporated into the rehabilitation. Although incorporating the existing piers and abutments into the rehabilitation would save time and money over a complete reconstruction, widening the caps of these substructures would present some unique challenges for their construction while maintaining rail traffic. The existing caps were encapsulated inside new, wider caps to accommodate the wider trusses. The new concrete pier caps were constructed while the bridge was still in service with trains going overhead. New truss bearings were supported outside the limits of the existing caps, which meant that the new trusses would be entirely supported on the new cap areas. The bond between existing stone substructures and the new concrete would be critical to transfer the large shear forces created by the truss loads. A combination of reinforcing dowels and post-tensioning bars were selected to create a positive bond and moment transfer between the existing stone and new concrete caps.
4 The wider trusses also required extensions to the abutment backwalls and wingwalls. This was accomplished by using a short jump span to allow excavation and construction at the abutments. New Bolted Warren Trusses Early in the design phase, NS decided to use bolted construction for the new truss spans in lieu of welded construction. Bolted steel construction inherently has better fatigue performance, which increases the service life of the new trusses. However, the bolted construction generally costs a little more and takes longer to fabricate. The four bolted trusses used 2,800,000 pounds of A709 Grade 50W (unpainted weathering steel) and required 145,400-7/8 inch diameter high-strength bolts. Computerized numeric drilling yielded high accuracy. The new Warren Truss replacement spans were fabricated using computerized numeric drilling. In addition, truss spans generally require shop assembly prior to shipment to ensure proper fit up prior to arrival in the field. In this case, the first truss span was shop assembled and the resulting assembled truss confirmed the accuracy of the fabrication process. The remaining three truss spans utilized a virtual shop assembly by assembling key components to confirm fit up while the rest were modeled by computer. This process coupled with close coordination from the steel detailer, fabricator, contractor and engineer yielded highly accurate bolted truss spans that did not require any field reaming.
5 Controlled Demolition/Roll-In New trusses were erected on adjacent falsework and rolled into place. procedure required procurement of special permits for the demolition. The Contractor Scott Bridge Company had the construction option to either float-out/floatin or roll-out/roll-in the truss spans. The contractor selected a hybrid technique utilizing controlled demolition and a roll-in procedure based on the site conditions and its preference. The controlled demolition/ roll-in procedure for each of the four truss spans was conducted without delay or additional track time. The river depth was a concern for the demolition, because it did not provide a lot of extra freeboard for the new trusses to roll over the demolished truss spans lying in the river. The Additionally, the Contractor provided extra safety in their falsework design by securing additional temporary falsework clearances prior to detonation of explosives. The trusses were actually rolled to the outside of the falsework to provide additional blast clearances (25- foot clear versus 5-foot normal clear). The contractor still shielded the new trusses during demolition procedures, but this unique approach provided an extra factor of safety for the protection to this important route. Each existing truss span was demolished using controlled explosive procedures. CONCLUSION With a tight schedule, clear communication was the key to this successful project. As a result of the focused team effort, the online rebuild of the Coosa River Bridge P was completed on budget, on schedule and with zero change orders/claims throughout design and construction. Norfolk Southern can now operate the line at posted speed and preserve the line s relief valve capability.
6 ACKNOWLEDGEMENTS Technical Assistance and review by Willie Benton, NS Corp, Atlanta, GA, and Chuck Davis, Scott Bridge Company, Opelika, Alabama.
CSX BRIDGE OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS. Introduction
CSX BRIDGE 122.6 OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS AREMA PRESENTATION September 13, 1999 Presented by: Rick Garro, P.E. Assistant Chief Engineer
More informationSteel Railway Bridge Fatigue and the Evolution of Railway Car Loadings
1 Steel Railway Bridge Fatigue and the Evolution of Railway Car Loadings The Current State and Future Challenges of Railway Bridges Stephen M. Dick, PE, SE, Ph.D. Hanson Professional Services 2 Discussion
More informationIntroduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring
Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot
More informationNORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR
NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationSafe, innovative, quality construction since Riding on the Strength
Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time
More informationSR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA
ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationNORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA
NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection
More informationMARTA Rapid Transit Bridges
MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More information2.0 Purpose. 3.0 Work Plan. Page 1 of 7
2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationPHASING CONSIDERATIONS FOR BRIDGES
PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationREHABILITATION PACKAGE 4-a
4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationDESIGN AND FLOAT-IN CONSTRUCTION OF A 500 FT. TRUSS SPAN
DESIGN AND FLOAT-IN CONSTRUCTION OF A 500 FT. TRUSS SPAN Kevin R. Eisenbeis, PE, SE Harrington & Cortelyou, Inc. 911 Main Street, Suite 1900, Kansas City, MO 64105 Phone: 816 421 8386 Fax: 816 471 6109
More informationGilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013
1 Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013 PRESENTERS: Marc Papini Parsons Brinckerhoff, Project Manager Jim Holtje, P.E. PCL Civil Constructors,
More informationAREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota
AREMA 2008 Annual Conference LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota 55904 507-281-5188 Steve K. Jacobsen, PE 2 LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS
MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS SECTION 1 - MISCELLANEOUS STANDARDS 1.00.01 -.05 Table of Contents 1.11.01 Decimal Parts of a Foot and Inch 1.21.01 Factors
More informationSTATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION
STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION PRELIMINARY DESIGN SUBMISSION REPORT For U.S. Route 130 Over Raccoon Creek Bridge Township of Logan Gloucester County, New Jersey Prepared By: Structural
More informationSOUTHEAST TEXAS CONTINUING EDUCATION BRIDGE INSPECTION, MAINTENANCE AND REPAIR
EXAM No.109 BRIDGE INSPECTION, MAINTENANCE AND REPAIR 1. Elements of a Bridge Maintenance Program include: A. Inspection and maintenance. B. Inspection and repair. C. Maintenance and documentation. D.
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 OFS:MJF 1 of 10 APPR:JAB:POJ:09-29-18 FHWA:APPR:10-01-18 a. Description. This work consists of
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 OFS:MJF 1 of 10 APPR:JAB:POJ:07-07-17 FHWA:APPR:07-11-17 a. Description. This work consists of
More informationReplacing the Aging US 52 Mississippi River Bridge
2019 TRANSPORTATION & HIGHWAY ENGINEERING CONFERENCE F. Duncan, PE, G. Hasbrouck, PE and A. Dour, PE Replacing the Aging US 52 Mississippi River Bridge February 26, 2019 Project Overview US 52 / IL 64
More informationJeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C
Accelerated Design-Build Replacement of SEPTA s Crum Creek Viaduct Jeffrey D. Knueppel, P.E. General Manager Robert L. Lund, Jr., P.E. Assistant General Manager EM&C Key Presentation Take-Aways NEED TO
More informationEconomical Design / Case Studies
Economical Design / Case Studies Alabama Technology Transfer Center Workshop Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation Competitiveness of
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure
More informationFoundation Strengthening Of Bascule Piers At The Bridge Of Lions
Paper No. 22 Foundation Strengthening Of Bascule Piers At The Bridge Of Lions Structural Elements Jian Huang, Ph.D., P.E. G. Alan Klevens, P.E. Lichtenstein Consulting Engineers TENTH BIENNIAL SYMPOSIUM
More informationPresented by: Taya Retterer BRG Webinar July 30, 2012
Presented by: Taya Retterer BRG Webinar July 30, 2012 PHASED CONSTRUCTION RECOMMENDATIONS FOR BRIDGES Will be posted to the TxDOT Website http://www.dot.state.tx.us/business/contractors_consultants/bridge/default.htm
More informationDesign & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:
Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,
More informationNEWINGTON-DOVER WELCOME
NEWINGTON-DOVER Spaulding Turnpike / Little Bay Bridge Project WELCOME SENH/NH-ASCE Joint Meeting September 28, 2011 VHB, Inc. Presentation Outline Introduction Project Overview Bridge Design Considerations
More informationASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa
2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price
More informationFort (M-85) Street Bascule Bridge
Fort (M-) Street Bascule Bridge DESIGN Overview History Geotech/Substructures Superstructure Aesthetics CONSTRUCTION Steel and Machinery Fabrication Existing Bridge Removal Road Reconstruction Bridge Replacement
More informationReplacement of BNSF Bridges near Princeton, IL & near Wyanet, IL. Authors. Number of Words 6875
Replacement of BNSF Bridges 106.58 near Princeton, IL & 110.26 near Wyanet, IL Authors Principal Author Jason E. Cunningham, PE, SE Bridge Engineer Hanson Professional Services Inc. 7625 N. University
More informationGrade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.
Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing
More informationAccelerated Bridge Construction in USA
Accelerated Bridge Construction in USA Abstract Rush hour traffic is a common daily occurrence in the USA. Highway and bridge construction further aggravates the situation. The Federal Highway Administration
More informationARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company
James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 1
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 1 OFS:MJF 1 of 10 APPR:JAB:POJ:09-29-18 FHWA:APPR:10-01-18 a. Description. This work consists of
More informationJane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions
Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Scott Eshleman, P.E., S.E, CVS, Stanley Consultants Keith Sargent, P.E., Thomas Engineering Group, LLC February
More informationATHABASCA RIVER BRIDGE REHABILITATION PROJECT
ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed
More informationConstruction of the Salt River Bridge and Mitigation of Unforeseen Subsurface Conditions
Construction of the Salt River Bridge and Mitigation of Unforeseen Subsurface Conditions ABSTRACT Duncan Paterson PE PhD, HDR Inc. (principal author) Steve Lorek, PE, HDR Inc. Doug Voegele, PE, HDR Inc.
More informationPRECAST CONCRETE GIRDER ERECTION
7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks
More informationPROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012
PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375
More informationAbo Canyon Second Main Track
Abo Canyon Second Main Track Thomas Schmidt Director Engineering Services BNSF Railway David Miller Manager Engineering BNSF Railway Abo Canyon Second Main Track Building 5 miles of a second track through
More informationSTRUCTURES INSPECTION CERTIFICATION TRAINING COURSE
STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE Code Pre/Route AFE Function Part 0 1000 7116 1174 N Hadley Eisenbeisz Bridge Construction Engineer Rick Brandner Mitchell Area Darrell utter Assistant
More informationKEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses
Replacement of the BNSF Approach Spans over the Mississippi River DAVID ROGOWSKI, P.E. AND JOSH CRAIN, Genesis Structures Inc., Kansas City, Missouri and DAN SIEVE AND KEVIN BECKER, Walsh Construction
More informationMINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION
MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION Common Name: Camp Ripley Bridge Bridge Number: 4969 Identification Number: Location: Feature Carried: TH 115 Feature
More informationUSE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES
David P. Hohmann, P.E., and John M. Holt, P.E. 1 USE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES Submission Date: July 31, 2002 Word Count: 2529 David P. Hohmann, P.E. Director, Bridge Design Branch Bridge
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More information1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY
Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be
More informationAESTHETIC AND TECHNOLOGICAL CONCEPTS FOR THE NEW ROUTE 9 SOUTHBOUND BRIDGE AND THE REHABILITATION OF THE EDISON BRIDGE
Over the Raritan River, New Jersey 29 AESTHETIC AND TECHNOLOGICAL CONCEPTS FOR THE NEW ROUTE 9 SOUTHBOUND BRIDGE AND THE REHABILITATION OF THE EDISON BRIDGE After 62 years of service without a major reconstruction,
More informationENHANCING STEEL BRIDGES
ENHANCING STEEL BRIDGES A series of NSBA focus groups brings to light methods to improve the cost, speed and quality of steel bridges By Andy Johnson and Bill McElency Of critical importance to designers
More informationPresentation Outline
St. John s Tunnel Rehabilitation A Demonstration of Successful Fast- Track Design and Construction Christopher P. Russell, P.E. Shannon & Wilson Inc., Staff Engineer Gregory R. Fischer, Ph.D., P.E. Shannon
More informationWidening the Harrods Creek Arch Bridge
Approaches to Historic Bridge Rehabilitation Case Study #1 Widening the Harrods Creek Arch Bridge Richard Sutherland, P.E. Daryl Carter, P.E. Presenter s Logo 1 Case Study #1 Harrods Creek Arch Bridge
More informationSEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE
SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE Paul Gauvreau University of Toronto, Canada (formerly J. Muller International) Thomas E. Kelly, Jr. Earth Tech/J.
More informationJacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida
Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida By: Bryan K. Haye, Senior Project Manager; Michael J. Shostak, P.E., Vice President; and Clinton C. Lalla,
More informationJANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25
General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO
More informationSIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE
SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada
More informationHighway Bridge Structure Components
Highway Bridge Structure Components Basic Bridge Components 1 Deck and 2 Stringer 3 Bearing 4 Pedestal 5 Footing 6 Piles 7 Underpass 8 Embakment 9 Live Loading Basic Bridge Components 1-Deck & wearing
More informationACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE
ACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE JOHN MITCHELL, MEHEDI CHOWDHURY, MICHAEL CHAN, PETER WILES Opus International Consultants Ltd SUMMARY Adopting an Accelerated Bridge
More informationDESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD
2018 Purdue Road School Transportation Conference Rendering by Touchstone Architecture Martin Furrer, PE, SE March 6, 2018 DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD Project Location
More informationFort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future
Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Richard A. Wianecki, PE, Hardesty & Hanover, Okemos, MI Jane Abadir, PE, LEED A P, SOMAT Engineering Detroit, MI Rouge
More information7 Bridges in 74 Days. NC 12 Detour
7 Bridges in 74 Days (Or Less) NC 12 Detour Ocracoke NC 12 Bridges Ocracoke NC 12 Bridges Existing 7 bridges built in 1950's Timber structures w/ ACP Clear width 22.5 ft. 36 to 152 ft. long Limited redirective
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More informationQuality Assurance Review for Bridge Construction
Quality Assurance Review for Bridge Construction March 7, 2000 Date Project No. County-Route-Section Project Contacts Contractor TABLE OF CONTENTS Reinforcing Steel... 2 Concrete... 2 Structural Steel...
More informationRt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening
Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction
More informationSINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.
SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical
More informationRequirements for Measuring and Pricing of Structural Concrete
Requirements for Measuring and Pricing of Structural Concrete October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing
More informationSTATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY
STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY NEWINGTON-DOVER, 11238S August 15, 2016 Vanasse Hangen Brustlin, Inc.
More information3.0 TEMPORARY DETOUR BRIDGES
3.0 TEMPORARY DETOUR BRIDGES Table of Contents 3.1 General...1 3.2 STORAGE SITES:...2 3.3 BID ITEMS:...2 3.4 INDEX OF PLAN SHEETS with H-Pile:...3 3.5 INVENTORY SHEET FOR DETOUR BRIDGES WITH H-PILE:...4
More informationI-94/I-69 Interchange Bridge Construction
I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer
More informationBoeing North Bridge: Lessons Learned in Accelerated Bridge Construction
Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction Gregory A. Banks, Myles Parrish, Charles W. Spry WSDOT ABC Workshop April 2015 Project Overview Location Located in Renton, WA PROJECT
More information2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS
2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS HECO-6 GENERAL Pre-construction conference Preconstruction meeting Scheduled by SI with the Contractor, UBO, A/E, and relevant subs prior to commencement
More informationTraffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))
11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of
More informationBoeing North Bridge in Washington State
Boeing North Bridge in Washington State Gregory A. Banks ABC-UTC Webinar May 2015 Project Overview -Location Located in Renton, WA PROJECT SITE RENTON 2 Project Overview Site Layout Lake Washington Existing
More informationSECTION 2831 ITEM F-162 CHAIN-LINK FENCES
SECTION 2831 ITEM F-162 CHAIN-LINK FENCES PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications and the details
More information2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE
Gusset Plates 2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE (50 Responses) Page 1 of 11 1) How many trusses are in your state? 2302 trusses owned by the state 8202 trusses owned by local agencies 2) What percentage
More informationExecutive Summary. ES-1 Introduction. ES-2 Background
ES-1 Introduction The Federal Transit Administration (FTA) and the (CTDOT) are preparing a combined Environmental Assessment (EA), Section 4(f) Evaluation, and Environmental Impact Evaluation (EIE) to
More informationSt. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer
St. Anthony Falls I-35W Bridge Replacement ASHE National Conference June 13, 2014 Dustin Thomas, P.E. I-35W Bridge Construction Engineer The Former Bridge - 9340 Opened to traffic in 1967 Steel truss bridge
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationConceptual Design Report
Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE
More informationStructural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options
Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements
More informationESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA
ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek
More informationWhy Rebuild It When You Can Reuse It? An Introduction to Foundation Reuse
Why Rebuild It When You Can Reuse It? An Introduction to Foundation Reuse Andy Boeckmann University of Missouri Motivations for Foundation Reuse Lifespan of foundation generally exceeds lifespan of overlying
More informationSTANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation
STANDARDIZED CONCRETE BRIDGES IN TEXAS John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation ABSTRACT Standardized concrete bridge plans are used extensively
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationStrengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions
13 th BIENNIAL SYMPOSIUM OCTOBER 25-28, 2010 Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions Jian Huang, Ph.D., P.E. and R. Wayne McLennon, P.E. TranSystems Corporation 2400 E. Commercial
More informationAMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE HISTORIC BRIDGE REHABILITATION AND MAINTENANCE CASE STUDY
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationSweet Creek Road Retaining Wall Replacement. Mapleton, OR
Sweet Creek Road Retaining Wall Replacement Mapleton, OR Technical Information Project Completion Date: April 30, 2013 Project Location: Mapleton, OR Size of Project: 15,000 SF, 870 CY Concrete Strength
More informationPueblo's New 4th street
PROJECT Pueblo's New 4th street BRIDGE Bridge aesthetics selected by the Pueblo community complement the bridge theme, which blends contemporary sculpture, natural environment, and Pueblo heritage. Rendering:
More informationFEBRUARY 13, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $9,000,000.00) Bids. Kokosing Construction Company, Inc. $8,623,609.96
General Info Number: PROJECT NO. 43-19-02 Description: BRIDGE DECK REPAIR AND REHABILITATION OHIO TURNPIKE OVER ABANDONED RAILROAD M.P. 34.2, OHIO TURNPIKE OVER STATE ROUTE 108 M.P. 34.5, COUNTY ROUTE
More informationSPECIAL INSPECTION AND TESTING AGREEMENT
COUNTY OF MENDOCINO DEPARTMENT OF PLANNING AND BUILDING SERVICES 860 NORTH BUSH STREET UKIAH CALIFORNIA 95482 120 WEST FIR STREET FT. BRAGG CALIFORNIA 95437 STEVE DUNNICLIFF, DIRECTOR PHONE: 707-234-6650
More information