1 Florida DOT efforts toward improving Post Tension Durability By William Nickas 1 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 73

2 Post-Tensioning Strategies Enhanced PT Systems Multiple Tendons Paths FDOT PT Strategy Fully Grouted Tendons Watertight Bridges Anchor Protection (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 2 of 73

3 Requirements Florida PT Strategy Enhanced PT Systems Fully Grouted Tendons Anchor Protection Watertight Bridges Multiple Tendon Paths Pre-Approved PT Systems Pre-Bagged Grout Requirements Three-Level Continuous Protection Anchorage Plastic Ducts Accessibility with Improved Cell Class Positively Low Point Sealed Injection Requirements Ducts Semi-Standard Permanent Plastic Requirements Drawings Anchor Caps 4 Certified Pressure Levels Grouters of Testing Protection and Inspectors No Dry Joints Controlled Semi Standard Rates Details of Grouting Pre-formed Tapered Holes Anchorages Flow Rate Testing Sealed of at Ejected all Times Material Drip Notches at Anchorages Inspect Voids and Secondary Grout Bottom Slab Drains Requirements Sealed Surfaces of Secondary Pours Wearing Maximize Surfaces Use of Smaller for Ride Tendons not Protection No Impact Permanent Due Tensile to Loss Stresses of Critical Tendon Compensation for Loss Due to Corrosion (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 3 of 73

4 Critical Nature of Tendons Essential Critical Very High High Moderate ¼ Point Hinge P/C BC Continuity at EJ P/C SBS External EJ Spans P/C SBS External Typical Spans P/C BC Anchor in Blister P/C BC Anchor on Face P/C BC Bottom Continuity CIP Cantilever & Continuity Flat Slab - Transverse P/C BC Top Continuity (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 4 of 73

5 Balanced Cantilever Construction (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 5 of 73

6 Balanced Cantilever Construction (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 6 of 73

7 Critical Nature of Tendons Type of Construction CIP on Falsework CIP Balanced Cantilever P/C Balanced Cantilever P/C Span-By-Span P/C Beam w/ CIP Slab Structural Purpose Superstructure Substructure Construction vs. Permanent Bonded vs. Unbonded Tendon Protection System Mat ls Duct, Anchor, Grout Wet vs. Dry Joints Risk of Exposure Maintainability Access to inspect components Applicability of test methods Ability to be replaced Redundancy External # & Distribution of Tendons (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 7 of 73

8 Contents Precast Balanced Cantilever Precast Span-by-Span Spliced I-Girders CIP Balanced Cantilever CIP on Falsework Substructures Transverse Superstructure (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 8 of 73

9 More Specifically FDOT POST- TENSIONING STANDARDS FOR SEGMENTAL AND GIRDER POST-TENSIONED TENSIONED BRIDGES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 9 of 73

10 OBJECTIVE TO PROVIDE CONSISTENCY AND UNIFORMITY IN THE DESIGN, DETAILING, AND CONSTRUCTION OF POST-TENSIONED TENSIONED STRUCTURES IN ORDER TO PROVIDE A HIGHER QUALITY PRODUCT WITH A MINIMUM COST INCREASE (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 10 of 73

11 OBJECTIVE MORE SPECIFICALLY, TO IMPROVE THE QUALITY OF PT HARDWARE, GROUTING, AND ANCHOR PROTECTION IN ORDER TO REDUCE THE INCIDENCES OF RECHARGE AND CORROSION IN POST-TENSIONED TENSIONED STRUCTURES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 11 of 73

12 OBJECTIVE IMPLEMENTATION STRATEGIES IMPLEMENTED STRATEGY 1 ENHANCED POST-TENSIONING TENSIONING SYSTEMS and installations(pti) SEALING OF GROUT PORTS, VENTS AND DRAINS STRATEGY 2 FULLY GROUTED TENDONS(ASBI) ACCESSIBLE ANCHORS GROUTING OF TENDONS / GENERAL PROCEDURES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 12 of 73

13 OBJECTIVE STRATEGY 3 MULTI-LEVEL LEVEL ANCHOR PROTECTION ANCHORS AT EXPANSION JOINTS / INSIDE BOXES / BLISTERS EMBEDDED ANCHORS STRATEGY 4 WATERTIGHT BRIDGES: Double Face Epoxy ACCESS, LIFTING HOLES DRIP NOTCHES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 13 of 73

14 DRAWING INDICES INSTRUCTIONAL NOTES POST-TENSIONING TENSIONING VERTICAL PROFILES POST-TENSIONING TENSIONING ANCHORAGE PROTECTION POST-TENSIONING TENSIONING ANCHORAGE AND GROUTING DETAILS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 14 of 73

15 INSTRUCTIONAL NOTES DESIGNER TO PROVIDE TENDON PROFILE AND ANCHOR PROTECTION TYPE FOR EACH TYPE OF TENDON TENDON PROFILE AND ANCHOR PROTECTION TYPE TO BE INCLUDED IN THE PT SCHEDULE (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 15 of 73

16 INSTRUCTIONAL NOTES TENDON PROFILES MAY BE AMENDED BY THE ENGINEER EOR RESPONSIBLE FOR REVIEWING THE CONTRACTORS GROUTING PLAN (SHOP DRAWINGS) DEVIATIONS FROM THE STANDARDS SHALL BE APPROVED BY THE FDOT (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 16 of 73

17 POST-TENSIONING TENSIONING VERTICAL PROFILES TYPICAL PROFILES FOR POST- TENSIONING TENDONS USED IN SUPERSTRUCTURE - GIRDER - SEGMENTAL SUBSTRUCTURE - HAMMERHEADS - STRADDLE BENTS VERTICAL APPLICATIONS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 17 of 73

18 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 18 of 73

19 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 19 of 73

20 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 20 of 73

21 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 21 of 73

22 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 22 of 73

23 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 23 of 73

24 TYPICAL TENDON PROFILES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 24 of 73

25 SUBSTRUCTURE VERTICAL PROFILES SUBSTRUCTURE ELEVATION OF BASE OF TENDON SHALL BE A MINIMUM OF FOR SUBSTRUCTURES OVER LAND FOR SUBSTRUCTURES OVER OR NEAR WATER (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 25 of 73

26 ANCHORAGE PROTECTION EXPOSED SURFACES AND EXPANSION JOINTS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 26 of 73

27 ANCHORAGE PROTECTION EXPOSED SURFACES AND EXPANSION JOINTS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 27 of 73

28 ANCHORAGE PROTECTION CANTILEVER TENDONS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 28 of 73

29 ANCHORAGE PROTECTION PT GIRDERS AND BULB-T S (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 29 of 73

30 ANCHORAGE PROTECTION PT GIRDERS AND BULB-T S (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 30 of 73

31 ANCHORAGE PROTECTION INTERIOR ANCHORS IN CELLULAR BOXES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 31 of 73

32 ANCHORAGE PROTECTION TRANSVERSE TENDONS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 32 of 73

33 ANCHORAGE PROTECTION POST-TENSIONING TENSIONING BARS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 33 of 73

34 ANCHORAGE PROTECTION POST-TENSIONING TENSIONING BARS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 34 of 73

35 ANCHORAGE & GROUTING DETAILS FACE INSPECTED ANCHOR WITH GROUT INLET (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 35 of 73

36 TOP INSPECTED ANCHOR STEP 1-1 INSTALLATION & SHIPPING (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 36 of 73

37 TOP INSPECTED ANCHOR STEP 2 - GROUTING (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 37 of 73

38 TOP INSPECTED ANCHOR STEP 3 - INSPECTION (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 38 of 73

39 TOP INSPECTED ANCHOR STEP 4 - PROTECTION (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 39 of 73

40 HORIZONTAL SURFACES REMOVAL OF GROUT PIPE (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 40 of 73

41 HORIZONTAL SURFACES REMOVAL OF GROUT PIPE (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 41 of 73

42 HORIZONTAL SURFACES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 42 of 73

43 HORIZONTAL SURFACES FILLING GROUT PIPE POCKETS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 43 of 73

44 HIGH POINT INSPECTION GROUT OUTLET (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 44 of 73

45 VERTICAL SURFACES GROUT OUTLET CONNECTION TO TENDON (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 45 of 73

46 VERTICAL SURFACES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 46 of 73

47 VERTICAL SURFACES INSPECTION & POCKET PREPARATION (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 47 of 73

48 VERTICAL SURFACES FILLING POCKET WITH EPOXY GROUT (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 48 of 73

49 GROUT OUTLET 3 TO 6 FT FROM HIGH POINTS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 49 of 73

50 GROUT INLET / OUTLET AT LOW POINTS OF TENDON (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 50 of 73

51 ANCHORAGE & GROUTING DETAILS GROUTING AT LOW POINTS SPAN X SPAN CONSTRUCTION (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 51 of 73

52 ANCHORAGE & GROUTING DETAILS GROUTING AT LOW POINTS SPAN X SPAN CONSTRUCTION (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 52 of 73

53 BLOCK-OUTS OUTS AND TEMPORARY ACCESS HOLES (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 53 of 73

54 Reminder Details are great but one must always INTEGRATE STRATEGIES INTO THE CONSTRUCTION AND MATERIALS SPECIFICATIONS 54 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 54 of 73

55 POST-TENSIONING TENSIONING SYSTEM example items INSPECTABLE ANCHORS BAR COUPLERS PERMANENT GROUT CAPS INLETS AND OUTLETS DUCT SCHEDULE 40 STEEL OR PLASTIC POLYPROPYLENE CORRUGATED DUCT POLYETHYLENE SMOOTH DUCT (DR 17) PRESSURE TESTING COMPONENTS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 55 of 73 55

56 PLASTIC DUCT AND CONNECTIONS example issues ALL COMPONENTS ASSEMBLED INTO PRESSURE TESTED SYSTEMS POLYPROPYLENE CORRUGATED DUCT FOR INTERNAL TENDONS GREATER STIFFNESS WITH LESS HEAT GAIN POLYETHYLENE DUCT THICK WALL WITH PRESSURE PIPE CHEMISTRY IN-PLACE TESTING FOR LEAKS BEFORE GROUTING 56 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 56 of 73

57 Education is Critical (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 57 of 73

58 Proper Material is Critical Standardized Details with PCI (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 58 of 73

59 Why not always use Plastic Duct? 59 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 59 of 73

60 NeXt Generation at Saw Grass FDOT D-4 and C O of FDOT pioneered a project: Watertight Bridge strategy Balanced against analytical exercise to determine critical tendons for selective inspection and repair grouting 60 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 60 of 73

61 Carbon and Kevlar Grid 61 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 61 of 73

62 Over lay 62 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 62 of 73

63 Sawgrass Developmental Project Bridge Length = 3990 feet Width = 40 feet 200 Days of MOT= $35,000 Epoxy Overlay= $36.30 per Sq. Yd. Joint Sealant =$24.60 per Lin. Ft. No LL capacity loss due to light weight Stay tuned: 2008 another repair, Hopeful that Future Costs should come down Close monitoring to see if meet 10 year service life 63 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 63 of 73

64 Leakage at Segment Joints (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 64 of 73

65 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 65 of 73

66 new Tendon Removal (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 66 of 73

67 85% of strength (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 67 of 73

68 new Autopsy Inspection Video from Skyway Pier 133NB (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 68 of 73

69 new A tendon with 17 Strands or 119 wires With 65 pitted wires and 50 Broken wires (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 69 of 73

70 Pier 133 NB SE Tendon NE Tendon (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 70 of 73

71 Mag Flux (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 71 of 73

72 Findings (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 72 of 73

73 QUESTIONS / ANSWERS (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 73 of 73

Durability of Post-Tensioning: fib Bulletin 33 and FHWA Scan tour Findings. Presented by Brett Pielstick P.E., F.ASCE

Durability of Post-Tensioning: fib Bulletin 33 and FHWA Scan tour Findings. Presented by Brett Pielstick P.E., F.ASCE Durability of Post-Tensioning: fib Bulletin 33 and FHWA Scan tour Findings Presented by Brett Pielstick P.E., F.ASCE 1 Introduction Early Durability Issues Assessment Concrete Society TR-47 FHWA Scan Tour

More information

SUNSHINE SKYWAY BRIDGE

SUNSHINE SKYWAY BRIDGE SUNSHINE SKYWAY BRIDGE Retrofit of the Post-Tensioned Precast Transition Pier Columns on the Sunshine Skyway Bridge Presented by: Antonio Ledesma, P.E. May 7, 2012 SUNSHINE SKYWAY BRIDGE, FLORIDA Presentation

More information

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What

More information

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 2004 Specifications CSJ: 0028-09-111 SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 1. Description. Construct cast-in-place segmental concrete box girder superstructure according to the plans,

More information

NDT in Grouted PT Inspection for Bridges

NDT in Grouted PT Inspection for Bridges NDT in Grouted PT Inspection for Bridges PTI Technical Conference & Exhibition Miami, FL May 8, 2007 Hong-gang gang Cao CTLGroup (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 37

More information

SUMMARY SHEETS OF HYBRID CONNECTIONS

SUMMARY SHEETS OF HYBRID CONNECTIONS APPENDIX E SUMMARY SHEETS OF HYBRID CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix E E-1 APPENDIX E SUMMARY SHEETS OF HYBRID CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix E E-2 Location:

More information

SUMMARY SHEETS OF INTEGRAL CONNECTIONS

SUMMARY SHEETS OF INTEGRAL CONNECTIONS APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-1 APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-2

More information

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1 Department of Civil Engineering Lecture 2.1 Methods of Prestressing Advantages of Prestressing Section remains uncracked under service loads Reduction of steel corrosion (increase durability) Full section

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction 2018 Virginia Concrete Conference March 2, 2018 Bardia Emami, PE Outline Projects

More information

EXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS

EXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS EXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS Larry B. Krauser, General Technologies, Inc., Stafford, TX Post-tensioning tendon protection strategies for precast elements

More information

Special Considerations for Maintenance of the Sunshine Skyway Bridge

Special Considerations for Maintenance of the Sunshine Skyway Bridge Florida Department of TRANSPORTATION Special Considerations for Maintenance of the Sunshine Skyway Bridge 2014 NATIONAL BRIDGE PRESERVATION PARTNERSHIP CONFERENCE James J. Jacobsen, P.E. District Structures

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Requirements for Measuring and Pricing of Structural Concrete

Requirements for Measuring and Pricing of Structural Concrete Requirements for Measuring and Pricing of Structural Concrete October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing

More information

GROUTING OF BRIDGE POST-TENSIONING TENDONS

GROUTING OF BRIDGE POST-TENSIONING TENDONS GROUTING OF BRIDGE POST-TENSIONING TENDONS T R A I N I N G M A N U A L Broadway Bridge Daytona Beach, Florida JULY 2002 GROUTING OF BRIDGE POST-TENSIONING TENDONS TRAINING MANUAL To be used as a supplement

More information

Connections between precast girders and cap beam

Connections between precast girders and cap beam Emerging ABC Connection Details for High Seismic Areas Connections between precast girders and cap beam Sri Sritharan Wilson Engineering Professor CCEE Department, Iowa State University Collaborator Dr.

More information

Use of BS 5400: Part 4: 1990

Use of BS 5400: Part 4: 1990 Volume 1 Section 3 Part 1 NRA BD 24/00 The Design of Concrete Road Bridges and Structures Use of BS 5400: Part 4: 1990 December 2000 St. Martin s House, Waterloo Road, Dublin 4. Tel:+353 1 660 2511 Fax

More information

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be

More information

Florida s Flexible Filler Experience. Dr. Natassia Brenkus, The Ohio State University

Florida s Flexible Filler Experience. Dr. Natassia Brenkus, The Ohio State University Florida s Flexible Filler Experience Dr. Natassia Brenkus, The Ohio State University Motivation Cost-effective method of bridge construction Prestressed Concrete Durability Issues Poor grouting practice

More information

716 - POST-TENSIONING (Haunched Slab Bridges) SECTION 716. POST-TENSIONING (Haunched Slab Bridges)

716 - POST-TENSIONING (Haunched Slab Bridges) SECTION 716. POST-TENSIONING (Haunched Slab Bridges) SECTION 716 POST-TENSIONING (Haunched Slab Bridges) 716.1 DESCRIPTION Provide and install all post-tensioning system components as shown in the Contract Documents to construct a post-tensioned haunched

More information

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed Construction Measurement III SBQ3314 Precast Pre stressed Concrete Works Dr. Sarajul Fikri Mohamed Table of Contents 1. Pre stressed concrete in bridgeworks: technological aspects 2. SMM2 measurement rules

More information

Long Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge

Long Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge Design Features and Prestressing Aspects of Long Key Bridge { i Thomas M. Gallaway* Principal Cutler-Gallaway Services, Inc. Consulting Engineers San Antonio, Texas Long Key Bridge, a spectacular example

More information

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer US-131 Over the Muskegon River Corey Rogers, P.E. Bridge Construction Engineer NB and SB US-131 Each bridge is a three-span, 580 foot long, cast-in-place, post-tensioned concrete box girder structure resting

More information

Accelerated Bridge Construction in USA

Accelerated Bridge Construction in USA Accelerated Bridge Construction in USA Abstract Rush hour traffic is a common daily occurrence in the USA. Highway and bridge construction further aggravates the situation. The Federal Highway Administration

More information

***************************************************************************************************************

*************************************************************************************************************** 03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************

More information

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors 2004 Specifications CSJ 0581-02-121 & 0200-11-100 SPECI SPECIFICATION 4401 Prestressed Ground Anchors 1. Description. Install post-tensioned permanent ground anchors in place, with grouting as required

More information

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 905 MAY 1994 CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE 905.01 SCOPE 905.02 REFERENCES 905.03 DEFINITIONS TABLE OF CONTENTS 905.04

More information

TECHNICAL SESSION 3. Strengthening, Repair & Rehabilitation

TECHNICAL SESSION 3. Strengthening, Repair & Rehabilitation TECHNICAL SESSION 3 Strengthening, Repair & Rehabilitation 2004 PTI Technical Session 3 T. Theryo, P. Garcia - Repair of Sunshine Skyway Bridge The Post-Tensioning Column Repair of High Level Approaches

More information

MARTA Rapid Transit Bridges

MARTA Rapid Transit Bridges MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , & TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed

More information

TAB.3 13 Post Tensioning Terminology (PTT)

TAB.3 13 Post Tensioning Terminology (PTT) TAB.3 13 Post Tensioning Terminology (PTT) PTI Technicical Advisory Board Page 0 of 34 The following Post-Tensioning Terminology (PTT) document contains the consensus definitions for terms relating to

More information

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: VDOT Modifications to the AASHTO LRFD Bridge Design Specifications, 8 th

More information

Concrete Prestressed Concrete Pretensioned Concrete Posttensioned Concrete Typical Tendon Layout

Concrete Prestressed Concrete Pretensioned Concrete Posttensioned Concrete Typical Tendon Layout Concrete 45 1.13.0 Prestressed Concrete Concrete in which internal stresses (forces) are induced by means of prestressing steel tendons such that tensile stresses resulting from loads are counteracted

More information

Corrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge

Corrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge Corrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge by Siva Venugopalan Principal SCS, Inc. siva007@verizon.net (610) 692-6551 6551 March 7, 2007 Count on Concrete for Performance Slide 1

More information

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 1 of 23 The following presentation discusses

More information

3ft, 4 ft., 6 ft., and 8 ft. First Defense HC Handling and Installation Instructions

3ft, 4 ft., 6 ft., and 8 ft. First Defense HC Handling and Installation Instructions 3ft, 4 ft., 6 ft., and 8 ft. First Defense HC Handling and Installation Instructions Page 2 Materials Supplied By Hydro International 3 ft./ 4 ft./ 6 ft./ 8 ft. diameter top slab 3 ft./ 4 ft./ 6 ft./ 8

More information

WJE ENGINEERS SPECIALIZED POST-TENSIONING ASSESSMENT AND REPAIR. Western Bridge Engineers Seminar. September 10, :30 AM

WJE ENGINEERS SPECIALIZED POST-TENSIONING ASSESSMENT AND REPAIR. Western Bridge Engineers Seminar. September 10, :30 AM Western Bridge Engineers Seminar September 10, 2015 8:30 AM SPECIALIZED POST-TENSIONING ASSESSMENT AND REPAIR WJE ENGINEERS ARCHITECTS MATERIALS SCIENTISTS Outline WJE PT assessments PT basics Initial

More information

Special Requirements for Precast Bent Cap Connections C General

Special Requirements for Precast Bent Cap Connections C General Attachment CS1. Proposed Article 8.13.8 Special Requirements for Precast Bent Cap Connections (AASHTO LRFD Bridge Construction Specifications, 2 nd Edition with 2006, 2007, 2008, and 2009 Interims) 8.13.8

More information

PRECAST CONCRETE GIRDER ERECTION

PRECAST CONCRETE GIRDER ERECTION 7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

Lesson 7 REINFORCING CAGE. Version 1-1/

Lesson 7 REINFORCING CAGE. Version 1-1/ Lesson 7 REINFORCING CAGE 7-1 Version 1-1/15 7-1 Learning Outcomes Describe cage construction Determine the circumference of a shaft and rebar cage and calculate the required number of side spacers. Explain

More information

Miami Marlins Baseball Park

Miami Marlins Baseball Park Miami Marlins Baseball Park Roof Support Track Beams Construction by Incremental Lifting Project Owner Miami Dade County General Contractor Hunt-Moss JV Frame Contractor Formworks-Baker Concrete JV Engineer

More information

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,

More information

SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS

SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS APPENDIX B SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix B B-1 APPENDIX B SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix

More information

FEBRUARY 2019 LRFD BRIDGE DESIGN 5-1

FEBRUARY 2019 LRFD BRIDGE DESIGN 5-1 FEBRUARY 2019 LRFD BRIDGE DESIGN 5-1 5. CONCRETE STRUCTURES Reinforced and prestressed concrete are used extensively in bridge projects. In addition to general design guidance and information on detailing

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2017 to December 31, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT July 1, 2017 to September 30, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

NCHRP Project Michael Culmo, PE CME Associates, Inc.

NCHRP Project Michael Culmo, PE CME Associates, Inc. NCHRP Project 12-102 Michael Culmo, PE CME Associates, Inc. Acknowledgements NCHRP: Waseem Dekelbab Project Panel Ahmad Abu-Hawash Iowa DOT Norman P. Marzano Jr. Rhode Island DOT Carmen Swanwick Utah DOT

More information

Art Mould Plastics "SUPPORTING THE REINFORCING CONCRETE INDUSTRY SINCE 1966"

Art Mould Plastics SUPPORTING THE REINFORCING CONCRETE INDUSTRY SINCE 1966 Art Mould Plastics "SUPPORTING THE REINFORCING CONCRETE INDUSTRY SINCE 1966" 1 of 10 Table of Contents Individual Support Chairs Linden Chairs. 3 Sand Plates 3 X-Chairs.. 4 Rod Spacers.. 4 Type-A. 5 Sand

More information

Construction of Long Key Bridge

Construction of Long Key Bridge Construction of Long Key Bridge ^G1 '4 Jean Muller Chairman of the Board and Technical Director Figg and Muller Engineers, Inc. Tallahassee, Florida MARATHON Conch Key Duck Key Long Key Fig. 7. Location

More information

Report D4.3. Field demo of bridge in Florida

Report D4.3. Field demo of bridge in Florida SEACON Sustainable concrete using seawater, salt-contaminated aggregates, and non-corrosive reinforcement Start date: October 1, 2015 Duration: 30 months Report D4.3 Field demo of bridge in Florida Author(s)

More information

ITEM 426 PRESTRESSING Definitions. For this Item, the following definitions shall apply:

ITEM 426 PRESTRESSING Definitions. For this Item, the following definitions shall apply: ITEM 426 PRESTRESSING 426.1. Description. This Item shall govern for the furnishing, fabricating, storing and handling of prestressing materials, for the prestressing of precast members, and for the prestressing

More information

Post-tensioned Structures Solutions for Repair and Protection

Post-tensioned Structures Solutions for Repair and Protection Post-tensioned Structures Solutions for Repair and Protection Concrete Preservation Alliance Vector Construction, Vector Corrosion Technologies, and Vector Corrosion Services are working to advance the

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights

More information

SPECIAL SPECIFICATION 4492 Tie Back Anchors

SPECIAL SPECIFICATION 4492 Tie Back Anchors 2004 Specifications CSJ 0504-02-022 SPECI SPECIFICATION 4492 Tie Back Anchors 1. Description. This Item shall govern for the installation of tie-back anchors in place, with grouting as required in accordance

More information

Post-tensioned Concrete Design PT Installation Guidance

Post-tensioned Concrete Design PT Installation Guidance Post-tensioned Concrete Design PT Installation Guidance Lee Maartensz Construction Manager - Structural Systems UK Ltd PT Installation Bonded Flat Slabs Installation 1 Flat Slabs Beam and Slab Installation

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2016 to December 31, 2016 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

JULY 2014 LRFD BRIDGE DESIGN 5-1

JULY 2014 LRFD BRIDGE DESIGN 5-1 JULY 014 LRFD BRIDGE DESIGN 5-1 5. CONCRETE STRUCTURES Reinforced and prestressed concrete are used extensively in bridge projects. In addition to general design guidance and information on detailing practices,

More information

4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions

4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions 4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions Page 2 Materials Supplied By Hydro International Ledger Angle (x4) Top Slab Top Riser Benching Skirt 4ft./6ft. Downstream Defender

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 855 POST-TENSIONING APRIL 20, 2018

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 855 POST-TENSIONING APRIL 20, 2018 STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 855 POST-TENSIONING APRIL 20, 2018 855.01 Description 855.02 Qualifications and Inspection 855.03 Engineered Drawings 855.04 Alternate

More information

William R. Bennett Bridge. W.R. Bennett Bridge, Kelowna, B.C. Canada. July 2005 to December 2008

William R. Bennett Bridge. W.R. Bennett Bridge, Kelowna, B.C. Canada. July 2005 to December 2008 William R. Bennett Bridge W.R. Bennett Bridge, Kelowna, B.C. Canada. July 2005 to December 2008 Contract Details Scope: Design & Build the new W.R. Bennett Floating Bridge & Decommission existing Okanagan

More information

Barrier Cable Systems, Inc.

Barrier Cable Systems, Inc. 055220 BARRIER CABLE SYSTEMS PART 1- GENERAL 1.1 DESIGN The 2012 IBC compliant barrier systems must meet both following requirements: A. For automobile restraint: the systems shall be able to withstand

More information

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

Method of Measurement for Road Works Series MM Structural Concrete

Method of Measurement for Road Works Series MM Structural Concrete Method of Measurement for Road Works Series MM 1700 - CC-RMP-01700 December 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012 PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375

More information

Hybrid prestressed concrete bridges with steel truss webs-sarutagawa bridge and Tomoegawa bridge

Hybrid prestressed concrete bridges with steel truss webs-sarutagawa bridge and Tomoegawa bridge IABSE-JSCE Joint Conference on Advances in Bridge Engineering-III, August 21-22, 2015, Dhaka, Bangladesh. ISBN: 978-984-33-9313-5 Amin, Okui, Bhuiyan, Ueda (eds.) www.iabse-bd.org Hybrid prestressed concrete

More information

John Bergman, P.E. Project Manager HDR ICA 62 Brigade St., Suite A3 Charleston, SC 29403

John Bergman, P.E. Project Manager HDR ICA 62 Brigade St., Suite A3 Charleston, SC 29403 January 15, 2018 John Bergman, P.E. Project Manager HDR ICA 62 Brigade St., Suite A3 Charleston, SC 29403 Sub: Re: Field Memo Water Intrusion into Tendon Ducts I-526 James B. Edwards Bridge over the Wando

More information

Stay-Cable Replacement Design

Stay-Cable Replacement Design Stay-Cable Replacement Design Mississippi River Bridge Luling, Louisiana Christopher Ligozio CTLGroup Copyright Post-Tensioning Institute all rights reserved. Page 1 of 35 Luling Bridge Copyright Post-Tensioning

More information

POST TENSIONED SLABS. Imagineering the possibilities

POST TENSIONED SLABS. Imagineering the possibilities POST TENSIONED SLABS Imagineering the possibilities imagineering... CCL post - tensioned slab solutions represent continuous development through involvement in building structures worldwide. CCL systems

More information

NEW SEGMENTAL DUCT COUPLER FOR POST-TENSIONING TENDONS

NEW SEGMENTAL DUCT COUPLER FOR POST-TENSIONING TENDONS NEW SEGMENTAL DUCT COUPLER FOR POST-TENSIONING TENDONS Joe Harrison, P.E., Vice President, Marketing General Technologies, Inc. 13022 Trinity Drive Stafford, TX 77477 Email: jharrison@gti-usa.net Phone:

More information

PHASING CONSIDERATIONS FOR BRIDGES

PHASING CONSIDERATIONS FOR BRIDGES PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural

More information

CONCRETE TECHNOLOGY CORPORATION

CONCRETE TECHNOLOGY CORPORATION PRECAST, PRESTRESSED HOLLOW CORE SLABS DESIGN CRITERIA & SPAN-LOAD CHARTS Introduction 2 Design Criteria for Development of the Span-Load Charts 2 Related Publications 3 Manufacturing Tolerances 4 8" Bare

More information

INSPECTION AND LOAD RATING OF P-T SEGMENTAL BRIDGES. Elias Ajami, PE Illinois Tollway Brett Sauter, PE, SE Ciorba Group

INSPECTION AND LOAD RATING OF P-T SEGMENTAL BRIDGES. Elias Ajami, PE Illinois Tollway Brett Sauter, PE, SE Ciorba Group INSPECTION AND LOAD RATING OF P-T SEGMENTAL BRIDGES Elias Ajami, PE Illinois Tollway Brett Sauter, PE, SE Ciorba Group PRESENTATION SUMMARY 1. About the Illinois Tollway 2. Project Location and Information

More information

Special Provision No. 109S17 June 2017

Special Provision No. 109S17 June 2017 AMENDMENT TO OPSS 905, NOVEMBER 2014 Special Provision No. 109S17 June 2017 OPSS 905, November 2014 Construction Specification for Steel Reinforcement for Concrete is deleted in its entirety and replaced

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES Massachusetts Department of Transportation Highway Division I-95 / Whittier Bridge Replacement Type Study Report 6. Evaluation of

More information

Statement of Special Inspections

Statement of Special Inspections Statement of Special Inspections SUCF Project No: Project Title: Registered Design Professionals in Responsible Charge: (Name) (Address) Architect: Structural Engineer: Mechanical Engineer: Identification

More information

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length Construction of Extradosed Bridge in the Government Financed Section EUI-NAM PARK, PM, Incheon Bridge Section 5, Doosan Construction & Engineering corporation KYUNG-KUK JUNG, GM, Incheon Bridge Section

More information

Intermountain Section AWWA Conference - 2.0MG Layton Water Tank. Jake O Brien

Intermountain Section AWWA Conference - 2.0MG Layton Water Tank. Jake O Brien Intermountain Section AWWA Conference - 2.0MG Layton Water Tank Jake O Brien Presentation Outline Layton City s decision process Tank Design/Construction Tendon Tanks - don t shed the good stuff Layton

More information

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

ACHD Bridge and Culvert Policy DRAFT

ACHD Bridge and Culvert Policy DRAFT ACHD Bridge and Culvert Policy DRAFT Standard Drawings and additional construction details are contained in the separate ACHD Bridge Design Guide and are hereto made part of this policy by reference. DEFINITIONS

More information

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:

More information

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre 10.26.2016 HNTB Corporation Outline Overview of WV TPK Ghent NB Bridge Existing Conditions ABC Deck Replacement Alternatives

More information

BS EN :2004 EN :2004 (E)

BS EN :2004 EN :2004 (E) Contents List 1. General 1.1 Scope 1.1.1 Scope of Eurocode 2 1.1.2 Scope of Part 1-1 of Eurocode 2 1.2 Normative references 1.2.1 General reference standards 1.2.2 Other reference standards 1.3 Assumptions

More information

Ministry of Forests & Range

Ministry of Forests & Range Ministry of Forests & Range DRAWING SCHEDULE DRAWING No. / MODEL TYPE STD-EC-040-01 STD-EC-040-02 STD-EC-040-03 STD-EC-040-04 STD-EC-040-05 STD-EC-040-06 STD-EC-040-07 STD-EC-040-08 DESCRIPTION REV. DATE

More information

AMERICAN SEGMENTAL BRIDGE INSTITUTE GROUTING COMMITTEE INTERIM STATEMENT ON GROUTING PRACTICES

AMERICAN SEGMENTAL BRIDGE INSTITUTE GROUTING COMMITTEE INTERIM STATEMENT ON GROUTING PRACTICES AMERICAN SEGMENTAL BRIDGE INSTITUTE GROUTING COMMITTEE INTERIM STATEMENT ON GROUTING PRACTICES American Segmental Bridge Institute 9201 N. 25 Avenue, Suite 150B Phoenix, Arizona 85021 Tel: (602) 997-9964

More information

PRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT

PRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT PRECAST PRESTRESSED CONCRETE PAVEMENT The Standard Specifications are revised as follows: SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION 509 - PRECAST PRESTRESSED CONCRETE PAVEMENT 290 509.01

More information

SELECTING POST-TENSIONING TENDON PROTECTION LEVELS

SELECTING POST-TENSIONING TENDON PROTECTION LEVELS Proceedings fib Symposium PRAGUE 2011 ISBN 978-80-87158-29-6 Topic 2: Poster Session SELECTING POST-TENSIONING TENDON PROTECTION LEVELS Larry B. Krauser Abstract Post-tensioning is the primary structural

More information

Value of Specifying Grouted Field Personnel Certification. May 2012 PTI Convention - Nashville Gregory Hunsicker, P.E.

Value of Specifying Grouted Field Personnel Certification. May 2012 PTI Convention - Nashville Gregory Hunsicker, P.E. Value of Specifying Grouted Field Personnel Certification May 2012 PTI Convention - Nashville Gregory Hunsicker, P.E. Course Objective Quality of materials and workmanship are critical to the performance

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

ACHIEVING PROTECTION OF INTERNAL TENDONS THROUGH CONTINUOUS DUCT ENCLOSURES IN SEGMENTAL BRIDGE CONSTRUCTION

ACHIEVING PROTECTION OF INTERNAL TENDONS THROUGH CONTINUOUS DUCT ENCLOSURES IN SEGMENTAL BRIDGE CONSTRUCTION Proceedings fib Symposium PRAGUE 2011 ISBN 978-80-87158-29-6 Session 2B-6: Construction Technology ACHIEVING PROTECTION OF INTERNAL TENDONS THROUGH CONTINUOUS DUCT ENCLOSURES IN SEGMENTAL BRIDGE CONSTRUCTION

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

Bijan Khaleghi, Ph, D. P.E., S.E.

Bijan Khaleghi, Ph, D. P.E., S.E. 0 Submission date: July, 0 Word count: 0 Author Name: Bijan Khaleghi Affiliations: Washington State D.O.T. Address: Linderson Way SW, Tumwater WA 0 INTEGRAL BENT CAP FOR CONTINUOUS PRECAST PRESTRESSED

More information

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS Quarterly Progress Report For the period ending August 31, 2018 Submitted by: PIs - Armin Mehrabi, Hesham Ali Graduate Students - Mohamadtaqi

More information

A New Precast Concrete Deck System for Accelerated Bridge Construction

A New Precast Concrete Deck System for Accelerated Bridge Construction A New Precast Concrete Deck System for Accelerated Bridge Construction George Morcous 1(&), Fouad Jaber 2, and Jason Volz 2 1 University of Nebraska-Lincoln, Omaha, NE, USA 2 Nebraska Department of Roads,

More information

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction

More information