Section 603. CONCRETE PAVEMENT RESTORATION

Size: px
Start display at page:

Download "Section 603. CONCRETE PAVEMENT RESTORATION"

Transcription

1 Section 603. CONCRETE PAVEMENT RESTORATION Description. This work consists of restoring concrete pavement including the following: A. Removing and repairing portions of a concrete pavement, one lane wide and 100 feet long, or less, with reinforced and non-reinforced portland cement concrete, with the type of joint required; B. Diamond grinding portland cement concrete pavement; C. Resawing and sealing existing longitudinal pavement joints; D. Sawing, cleaning, and sealing cracks in concrete pavements; E. Removing sections of concrete pavement, one lane wide and greater than 100 feet long in accordance with section 204 or subsection B.1, as determined by the Engineer; and F. Replacing sections of concrete pavement one lane wide and greater than 100 feet long in accordance with section 602. Refer to Standard Plan R-44 Series, R-45 Series and the contract for details Materials. Provide material in accordance with the following: Concrete, Grades, P1, P1M Concrete, Grades P-MS, P-NC Course Aggregate, 21AA, 22A Curing Materials for Pavements Insulating Blankets HMA Mixtures for Restoring Shoulders Steel Reinforcement Epoxy Coated Dowel Bars and Deformed Tie Bars Joint Materials For concrete pavement repairs, the Engineer will determine the required concrete grade, based on the required opening of repairs to traffic, in accordance with Table The Engineer will not require 28-day compressive strength test cylinders for concrete pavement repairs. Table Opening to Traffic Strengths From Casting to Scheduled Opening Concrete Grade Minimum Flexural Strength <72 hours Grade P-NC 300 psi 3 days Grade P1, P1M 550 psi Provide the cement and admixture combinations necessary to obtain the strength specified in Table in the required time period. Do not use 327

2 a calcium chloride admixture. Provide coarse aggregate with no greater than 2.5 percent absorption in accordance with ASTM C 127. The Engineer will proportion Grade P-NC mixtures. Provide the mixture as ready-mixed concrete, with the required consistency, to the project. Use Grade P-NC concrete patching mixture containing 658 pounds per cubic yard (7 sacks) of cement when the forecasted air temperature is above 59 F. Use 752 pounds per cubic yard (8 sacks) of concrete when the forecasted air temperature is 59 F or less. The Contractor may provide a non-chloride, Type C, or Type E, set accelerating admixture, from the Qualified Products List, with the required cement content to achieve the flexural strength of 300 psi by the required opening-to-traffic time Construction. A. Equipment Requirements. Provide equipment necessary to perform the work in accordance with section 602 and the following: 1. Drilling Machine. Provide a drilling machine and use methods to drill holes in the existing pavement vertical surfaces in accordance with the following: a. Drill the holes to the required diameter and depth (±½ inch) midway between the top and bottom surfaces of the concrete pavement. b. Drill holes parallel to the pavement surface and parallel to the longitudinal joint within a tolerance of ± inch. c. When positioned against the face of the existing pavement, drill holes parallel to the longitudinal joint. d. Support the drill on rails that rest on the pavement surface at both ends of an 8 foot long repair, or by other alignment methods approved by the Engineer, to ensure holes meet the requirements of subsection A.1.b. e. Provide a drill that uses mechanically applied pressure for forward and reverse travel. Match the drill and pressure mechanism to drill the nominal depth holes to prevent cracking the concrete and causing spalls more than ½ inch horizontally or vertically. f. Equip the drill with a snug fitting drill guide bushing, positioned against the face of the concrete to prevent eccentricity or overriding of the holes more than 1 /16 inch, and to maintain the alignment tolerances. g. Space bars in accordance with Standard Plan R-44 Series. 328

3 h. Drill dowel bar holes and deformed tie bar holes for transverse joints with a diameter of 1 inch, and 9 inches ± inch deep. i. Drill deformed lane tie bar holes for longitudinal joints with a diameter of ¾ inch and 7 inches ± inch deep. 2. Grout Dispenser. a. Bulk Grout Systems. For bulk grouting, provide a grout dispenser and static mixing nozzle system recommended by the grout material manufacturer. Use a machine that proportions the components, mixes the components as they are extruded through the static nozzle, and deposits the mixed material in the back of the hole. If using a bulk grout system, provide two bulk grout dispensers on the project or provide one bulk grout dispenser and a two-day supply of prepackaged grout material, dispensers, and static mixing nozzles. b. Prepackaged Injection Grout Systems. For prepackaged injection grouting, provide a grout dispenser and static mixing nozzle supplied by the manufacturer of the grout material. Use a static mixing nozzle capable of depositing grout to the back of the hole. 3. Vibratory or Roller Screeds. Provide a steel-shod vibratory screed, with the weight and vibrating frequency required to screed concrete flush with the existing pavement in a single pass. Provide a roller screed with the weight and speed required to screed the concrete surface flush with the existing pavement in two or more passes. Provide screeds at least 6 inches longer than the width of the concrete pavement repair. 4. Diamond Grinding Equipment. Provide diamond blades, spaced as required for the application, and mounted on a self-propelled machine designed for grinding and texturing pavement. Use equipment that will not cause damage to the underlying surface of the pavement. Do not use grinding equipment that ravels or spalls the concrete pavement, fractures aggregate, or damages the transverse or longitudinal joints. Provide grinding equipment that produces the required texture. To remove residue and excess water, provide vacuum equipment that extracts the slurry material from the pavement and prevents dust from escaping into the air. 329

4 5. Equipment for Sawing and Sealing Cracks. Provide equipment for sawing and sealing cracks in accordance with subsection A.13. Equip the saw with a diamond blade with a diameter of 8 inches or less. B. Construction of Concrete Pavement Repair. Construct concrete pavement repairs, 50 feet long, or less, in accordance with section 602, except as modified by this subsection. To make repairs, remove existing concrete pavement in sections at least 4 feet long. If the repair area is less than 4 feet from an existing joint, remove the existing concrete pavement to at least one foot beyond the joint. If the repair area is less than 8 feet from the next repair area, remove the concrete pavement between the two areas. For repairs greater than 15 feet long, control the grade by separately casting adjacent lanes, ramps, or shoulders in the repair area. For repairs greater than 50 feet long, establish and control grades in accordance with subsection If the lane adjacent to a repair area is damaged, cast the repair area and open to traffic, then perform the removal and recasting of concrete repairs in the adjacent lane. The Engineer must approve the adjacent lane repair. 1. Removing Existing Pavement (Concrete Pavement Repair). a. Removing and Repairing Pavement Damaged by the Contractor. The Engineer will not allow the use of removal equipment that damages the concrete pavement required to remain in place. If the plans do not show the disturbance of the base, complete the work in accordance with this subsection. Repair remaining concrete pavement, damaged during removal operations, at no additional cost to the Department. Saw cut, remove, dispose, and provide additional concrete to repair spalls at no additional cost to the Department. Fill isolated spalls, less than 10 square inches, with a hot-poured joint sealant. Repair the following in accordance with subsection P.2: i. Isolated spalls, at least 10 square inches; ii. Numerous spalls in the same joint area; and iii. Intermediate spalls. 330

5 Repair major spalls in accordance with subsection P.3 by re-sawing. Place the new saw cuts in line with, or at least 2 feet from, saw cuts in adjacent lane repair areas. b. Planned Pavement Removal and Repair. Remove part-depth or full-depth hot mix asphalt (HMA) patches, included in the portion of pavement being removed, as removal of concrete, without regard to additional effort that may be involved in the removal of dissimilar materials. Avoid disturbing the base during removal. If the plans show repair areas that include concrete shoulders, perform shoulder removal using the same method as concrete pavement removal. If the repair areas include repairing concrete curb, curb and gutter, or valley gutter, remove the curbing adjacent to the repair and in line with the joints of the repair. If curbing removal leaves a section length, less than 6 feet from the saw cut to the nearest existing curb joint, remove the concrete curb to the existing joint. Construct the curb joint at the existing joint. Do not extend the joint created by the concrete pavement repair into the curb. Do not begin sawing more than two weeks before concrete pavement removal. Saw the concrete full depth using multiple passes within the same 12-hour period, or in one pass. Make straight, transverse saw cuts, at right angles to the centerline of the concrete pavement, within a tolerance of ±1 inch per lane width. Saw the longitudinal joint full depth between adjacent lanes, ramps, shoulders, or curb and gutter. Use water, immediately after sawing, to flush slurry off the surface of the pavement. Place concrete repairs the same day as the removal of existing concrete pavement. Remove concrete pavement between narrowly spaced saw cuts at the end of a slab with air hammers and hand tools. Except for utility cuts, install lifting devices in the slab. Lift the slab without disturbing the base. Clean the area with hand tools. Remove slurry from sawed surfaces. 2. Installing Dowels or Deformed Tie Bars in Transverse Joints. Drill the faces of the existing concrete pavement to allow the insertion of dowel bars or deformed tie bars. Re-drill holes that do not meet the required depth, diameter, and alignment at no additional cost to the Department. 331

6 After drilling the holes, clean with a blast of oil-free compressed air with at least 90 psi. Fully insert the air wand into the holes. After cleaning the holes, fill with a grout selected from the Qualified Products List. Fill the holes with grout to their full length to ensure the grout covers the embedded length of the inserted dowel bars or deformed bars. Slowly insert the bars into the holes using hand pressure and a twisting motion, until fully seated. Wipe excess grout, extruded around the bars onto the face of the concrete, using a metal trowel. Do not proceed until the Engineer verifies the dowel bars are properly installed and the grout set. For expansion joints (Erg), drill or punch the fiber filler to match the location of the holes in the existing pavement. Drill or punch the holes in the fiber filler to produce neat, clean holes without excessively tearing the filler. After grouting the dowel bars in place, install the filler and position it against the existing pavement. Extend the fiber filler the full depth of the repair and install flush with the existing pavement surface. Ensure fiber filler fully contacts, and covers the entire vertical surface of the sawed joint face. Place fiber filler in one continuous length across the joint, except for pavements wider than the nominal lane width, the Engineer will allow a short piece of filler. Coat the portions of dowel bars that extend beyond the face of the existing pavement or the fiber filler with an approved bond-breaking coating. Do not coat deformed bars used with tied joints (Trg) or grouted-in-place lane ties with bond-breaking coating. Install an approved expansion cap on the end of each dowel bar for expansion joints (Erg), after applying the bond breaker. 3. Site Preparation. If the plans show base corrections, excavate and backfill in accordance with section 205 and section 302. If the existing base is greater than 2 inches lower than the required grade, and the condition existed before concrete removal, correct the low base by adding base course aggregate and compacting to the required density and elevation. If the existing base is 2 inches or less below the required grade, or lower than the required grade as the result of concrete pavement removal operations, fill the area with concrete during repair construction. Set forms to the line and grade shown on the plans. Use one-piece forms for repairs 10 feet or less. For repairs greater than 10 feet, use forms that lock together or splice sections to provide a continuous form. Provide metal or wood forms. If using wood forms, 332

7 provide 2-inch thick lumber for shoulder side forms and 1-inch thick lumber for side forms between lanes. Position and support reinforcement in accordance with the standard plans. 4. Longitudinal Joints. If casting more than one lane in a single pour, construct longitudinal joints in line with the existing longitudinal joints. Make the depth of the longitudinal joint the thickness of the pavement. Construct longitudinal joints by sawing before opening to traffic or by forming. Do not construct an external longitudinal joint between concrete pavement repairs and concrete curbing or shoulders. Install lane ties in accordance with Standard Plan R-44 Series. Construct grouted-in-place lane ties in accordance with subsection B.2, for deformed bars used with tied joints (Trg), except the Engineer will allow the use of handheld drills. 5. Transverse Joints. If the contract requires an existing curb left in place, and there is an expansion space in the adjacent lane repair, saw or chip an expansion joint (Esc) in the curb. Construct the joint in line with and equal width to the expansion joint in the adjacent lane repair. Shape the fiber joint filler to match the curb cross section. 6. Placing Concrete. Immediately before concrete placement, wet the faces of the existing pavement and the surface of the aggregate base with water. Cast each repair in one continuous full-depth operation. Consolidate the concrete using a hand-held immersion-type vibrator, approved by the Engineer. Consolidate the concrete around dowel bars, deformed tie bars, and deformed lane tie bars. 7. Finishing Concrete. Strike off the surface flush with the existing pavement surface at least twice with a vibratory or roller screed. Do not float in lieu of striking off. For repairs 15 feet long or less, place the screed parallel to the centerline of the roadway. For repairs greater than 15 feet long, place the screed perpendicular to the centerline. While the concrete is still plastic, check that the edges of the repair surface are flush with the edges of the existing concrete pavement, and test to ensure the repaired surface meets the required line and grade. Use a straightedge in accordance with this subsection. 333

8 For repairs 10 feet long or less, place the straightedge parallel to the pavement centerline with the ends resting on the existing pavement and draw the straightedge across the repair. For repairs 10 feet long, or less, use a straightedge no greater than 6 inches longer than the repair. Ensure the straightedge remains in contact with the existing pavement while drawing it across the repair. Correct high or low spots greater than inch, recheck the surface after making corrections, and eliminate irregularities. For repairs greater than 10 feet long, straightedge in accordance with subsection I. Make the first and the last measurement with half the straightedge resting on the existing pavement. Make the second and the next to last measurement with 2 inches to 3 inches of the straightedge resting on the existing pavement. Correct high or low spots greater than inch. Before texturing, run an edger with a -inch to ¼-inch radius along the perimeter of the repair. Remove temporary forms after the concrete attains the strength required to prevent sagging or spalling upon removal of the forms. 8. Texturing. Texture the surface of the repair to match texturing on the adjacent concrete pavement. 9. Stenciling. Stencil the month and the year in each repair in accordance with subsection L. If repair operations cause the removal of the existing stationing, stencil the station in the repair at the required location. 10. Curing. Apply curing compound immediately after free water evaporates from the concrete pavement surface. Do not delay curing compound application for other work during concrete pavement placing and finishing operations. Continuously apply curing compound. Use white membrane curing compound, unless the repair requires a bituminous overlay. For repairs requiring bituminous overlay, use transparent curing compound. Apply the required curing compound in two coats, at a rate of at least 1 gallon per 25 cubic yards for each coat. Stop concrete pavement placement if the curing compound application process fails to meet the requirements specified in this subsection. Maintain the placed and finished concrete in a continuously moist condition until membrane curing compound application. Fog mist the pavement without damaging the concrete pavement surface. 334

9 Reapply curing compound immediately to surfaces damaged by rain, joint sawing, Contractor foot traffic, or other activities. Place insulated blankets to meet open-to-traffic requirements and protect the concrete pavement from weather damage. Provide insulated blankets at least 2 inch thick. When the air temperature falls below 50 F during the curing period, place blankets over the repaired area, as soon as the curing compound dries. Secure edges and seams in the blanket to prevent heat loss. Protect the concrete until it attains the minimum flexural strength specified in subsection Conform to methods included in the concrete quality control plan, the method for achieving the open-to-traffic strength within the required time period. The Contractor may use the maturity method to determine the inplace, opening-to-traffic flexural strength, if the Contractor makes the necessary preliminary flexural strength versus opening-to-traffic time correlations before placing the concrete. Cure test beams for open-to-traffic strengths the same as the repair. 11. Cleaning Joints. Before blast cleaning, remove concrete from the top of the filler in the expansion joint. Immediately before sealing joints, blast clean, except tied joint (Trg), and clean with a jet of compressed-air, free of oil and water, with at least 90 psi. Place a silicone coated, paper bond breaker tape, with pressure sensitive adhesive on one side, in the bottom of the contraction joint (Crg) groove after the final cleaning and before sealing. 12. Sawing and Sealing Joints. Do not construct reservoirs for seals in the following joints that do not require sealing: a. Longitudinal bulkhead joints; b. Joints in base course repairs; c. Joints in repairs constructed in preparation for HMA overlays; and d. Reinforced grouted tied joints. For all other joints and saw cuts in concrete pavements, shoulders, or gutters, caused by overcutting, clean and seal using hot-poured joint sealant. Before sealing joints with fiber filler, remove the joint fiber filler at the concrete pavement surface by sawing 1 inch wide and 1½ inches deep. 335

10 Saw joint grooves for the contraction joints (Crg) as required by the contract. Saw joint grooves for C2 joints and E2 joints after the concrete pavement attains the strength required to prevent excess raveling or spalling, but before random cracks develop. The Engineer will not allow forming of joint grooves. Saw the initial relief cut and extend the groove to the plan width and depth in accordance with subsection N, or initially saw to the width and depth shown on the plans. 13. Resealing Transverse and Longitudinal Pavement Joints. After completion of concrete pavement repairs, spall repairs, and pavement texturing, seal transverse and longitudinal concrete pavement joints with hot-poured sealant in accordance with subsection S. Resaw the transverse and longitudinal joints over the existing joint groove to produce a finished joint with two freshly sawed faces. Immediately after sawing, flush the joint groove with water to remove the slurry and debris. After final cleaning of the joints, insert a backer rod into the joint, creating a 1:1 width to depth ratio for hot-poured sealant. Seal the joint groove to no greater than inch (after cooling) below the concrete pavement surface. 14. HMA Shoulder Replacement. Before opening to traffic, restore HMA shoulders to the existing line and grade using a plant-mixed HMA, as directed by the Engineer. Replace cold patch mixtures for temporary patching with plant-mixed HMA, unless the plans show shoulder reconstruction as part of the project. Compact the HMA using mechanical or hand methods required for the size of the repair area. Fill the voids and compact flush with the surrounding shoulder. Place HMA at the required compaction temperatures. Properly dispose of materials removed from the shoulder. 15. Opening to Traffic. Ensure the concrete pavement attains the required minimum flexural strength, and ensure joints are sawed in accordance with subsection B.12 before opening to traffic. The Engineer will allow traffic over the repair before the Contractor cleans and seals the joints. C. Diamond Grinding Concrete Pavement. Complete joint restoration work, except sealing, before diamond grinding. Diamond grind concrete pavement in the longitudinal direction beginning and ending at lines perpendicular to the pavement centerline. Stop grinding if conditions cause water to freeze. 336

11 Do not disturb Reflective Pavement Markers (RPM). Taper grinding to the existing pavement surface within 2 inches of the RPM. Texture at least 95 percent of the pavement surface unless otherwise directed by the Engineer. The Engineer will not require extra depth grinding to eliminate minor depressions. After initial grinding, regrind faulted areas, greater than 1 /16 inch, at transverse cracks and joints, until faulting is less than 1 /16 inch. Uniformly grind a parallel corduroy-type texture, consisting of grooves from 1 /16 inch to inch wide, 1 /16 inch deep, and from 1 /16 inch to inch on center. Ensure the mean texture depth is at least 0.03 inch, in accordance with ASTM E 965. Construct a uniform transverse slope with no depressions or misalignment greater than inch when checked with a 10-foot straightedge. The Engineer will not apply straightedge requirements across longitudinal joints or outside ground areas. Provide for cross slope drainage. To provide drainage and the required riding surface, transition grind auxiliary or ramp lanes from the mainline edge. The Engineer will determine the transitions from ground to unground pavement surfaces. Seal joints after grinding. 1. Control and Disposal of Grinding Residue. Before beginning grinding, obtain the Engineer s approval of the grinding residue spreading and disposal method. Do not allow grinding residue to enter enclosed drainage systems. If approved by the Engineer, spread residue along the roadway slopes with the following restrictions: a. Spread residue at least 5 feet away from the curb. b. Do not spread the residue within 100 feet of a natural stream or lake. c. Do not spread residue within 5 feet of a water-filled ditch. If surface runoff occurs, collect and haul the grinding residue to an Engineer-approved location on the project. Collect, haul and dispose of grinding residue at no additional cost to the Department. 2. Testing Diamond Grinding Residue. The Department will take random samples of the grinding residue and cooling water for chemical testing. Allow Department personnel access to obtain the samples. 337

12 D. Sawing and Sealing Pavement Joints. Saw, or re-saw, clean, and seal longitudinal and transverse concrete pavement joints in accordance with subsection S and the following. Use low-modulus hot-poured joint sealant. Repair spalls before resawing the longitudinal joint and as directed by the Engineer. Saw longitudinal and transverse joints in new repairs as required by the contract. Resaw existing longitudinal and transverse joints from 1 inch to 1¼ inches deep, and from ¼ inch to ½ inch wide. Immediately after sawing, flush the joint groove with water to remove slurry and debris. Saw, or resaw, longitudinal joints before resealing the intersecting transverse joints. Provide a final cleaning just before sealing, in accordance with subsection R. After the final cleaning, insert a backer rod into the longitudinal joint to provide a 1:1 width to depth ratio of joint sealant. Ensure the joint faces and pavement surface are dry before sealing joints. Seal the joint groove to no greater than inch (after cooling) below the surface of the pavement. E. Sawing and Sealing Cracks. Seal cracks with a hot-poured sealant as follows: Saw cracks from ½ inch to inch deep and from inch to ½ inch wide. After sawing, use hand tools or a lightweight chipping hammer to remove slivers of concrete, less than 1 inch wide, along the crack. Immediately before sealing, blast both faces of the sawed crack with dry abrasive to remove contamination and texture the faces. After dry abrasive blasting, clean the crack of debris and residue with oil-free compressed air with at least 90 psi. Ensure the joint faces and pavement surface are dry before sealing joints. If the crack below the sealant reservoir is greater than inch wide, insert a backer rod into the crack to form the bottom of the reservoir at the required depth. Seal the crack to no greater than inch (after cooling) below the surface of the pavement. If required by the crown of the roadway and the slope of the shoulder, fill the reservoir in two or more passes, place temporary dikes in the sealed reservoir, or use both methods. Remove the temporary dikes before the sealant fully cools and seal the resulting cavity. Apply the additional sealant before the previous application becomes contaminated. 338

13 Measurement and Payment. Pay Item Pay Unit Pavt Repr, Rem... Square Yard Saw Cut, Intermediate... Foot Pavt Repr, Reinf Conc, inch... Square Yard Pavt Repr, Nonreinf Conc, inch... Square Yard Non-Chloride Accelerator... Gallon Joint, Contraction, Crg... Foot Joint, Expansion, Erg... Foot Joint, Expansion, Esc... Foot Joint, Tied, Trg... Foot Lane Tie, Epoxy Anchored... Each Diamond Grinding Conc Pavt... Square Yard Sawing and Sealing Longit Pavt Joints... Foot Sawing and Sealing Trans Pavt Joints... Foot Resealing Trans Joints with Hot-Poured Rubber... Foot Resealing Longit Joints with Hot-Poured Rubber... Foot Crack Sealing, Conc Pavt... Foot Cement... Ton A. Price Adjustments for Concrete Pavement Repairs. The Engineer will determine the final concrete pavement repair thickness in accordance with subsection C. The Department may core the concrete pavement repairs and will adjust the unit prices for repairs that do not meet the required depth or the required reinforcement location in accordance with subsection B. Pavement Repair, Removal. The Department considers Pavt Repr, Rem the removal of pavement sections without disturbing the base, as shown on the plans. The unit price for Pavt Repr, Rem includes the cost of the following: 1. Moving from repair to repair; 2. Saw cutting; 3. Removing adjacent concrete shoulders, curb, curb and gutter, and valley gutter; 4. Removing part-depth or full-depth HMA patches; 5. Lifting the repair section without disturbing the base; 6. Loading, hauling, and disposing of the removed material; and 7. Placing HMA mixture, as necessary, to restore the shoulders to the existing line and grade. The Department will include the pay item, Saw Cut, Intermediate for sections of pavement on which the plans show Pavt Repr, Rem. The Department will not include the pay item, Saw Cut, Intermediate for 339

14 sections of pavement on which the plans show Pavt, Rem. The Department will pay for intermediate saw cuts for concrete pavement repairs over 6 feet long, but less than 50 feet long, to allow loading onto hauling units, as Saw Cut, Intermediate. The Department will not pay separately for additional saw cuts, made by the Contractor to reduce slabs into pieces smaller than one lane width by 6 feet long. The Department will pay for the removal of portions of concrete that contain partial, or full-depth HMA patches as Pavt Repr, Rem. C. Pavement Repair, Reinforced Concrete, and Pavement Repair, Non-reinforced Concrete. The Department will establish a concrete pavement thickness for repairs, as shown on the plans, based on the original plan thickness of the existing concrete pavement plus 1 inch. The minimum thickness of the concrete pavement repair may vary by no greater than ±1 inch from the thickness shown on the plans. The Department will not pay separately for work required to correct low base conditions caused by Contractor removal operations. The Department will pay for site preparation to correct base, more than 2 inches below the required grade, not caused by Contractor operations, under the relevant pay items. If the contract does not include a relevant pay item, the Department will pay for base corrections greater than 2 inches deep, not caused by Contractor operations, as extra work. 1. Repair. The Engineer will measure Pavt Repr, Reinf Conc, and Pavt Repr, Nonreinf Conc, of the thickness specified, longitudinally along the pavement surface, and will use the transverse dimension shown on the plans. The unit prices for Pavt Repr, Reinf Conc, and Pavt Repr, Nonreinf Conc include the cost of the following: a. Moving from repair to repair; b. Providing, placing, finishing, texturing, stenciling, and curing the concrete; c. Providing and placing bar chairs and the steel reinforcement; and d. Providing additional concrete, as necessary, to correct low base conditions that do not exceed 2 inches measured from the required grade. 2. Tied Joints (Trg). The unit price for Joint, Tied, Trg includes the cost of the following: a. Removing saw slurry from the pavement surface and sawed faces; 340

15 b. Drilling and cleaning holes for dowel bars and deformed bars; c. Providing, mixing, and installing grout; and d. Providing and installing dowel bars or deformed bars. 3. Contraction Joints (Crg). The unit price for Joint, Contraction, Crg includes the cost of work specified by subsection C.2 and the following: a. Sawing the joint grooves; b. Cleaning and preparing the joint groove; c. Providing and applying the dowel bar bond breaker coating; d. Providing and installing the bond breaker tape; and e. Providing and installing the joint groove sealant. D. Concrete Grade P-NC. If the Engineer determines the time from casting the repair area to the intended opening-to-traffic requires the use of Grade P-NC concrete mixtures, the Engineer will measure, and the Department will pay for the extra cement based on the following: 1. If the forecasted air temperature is above 59 F, 94 pounds per cubic yard; or 2. If the forecasted air temperature is 59 F and below, 188 pounds per cubic yard. E. Type C and Type E Non-Chloride Accelerator. If the Engineer requires the addition of Type C or Type E non-chloride accelerator to the concrete mixture, the Engineer will measure, and the Department will pay for Non-Chloride Accelerator based on the quantity printed on the automated batch ticket. The Department will make deductions for wasted or rejected materials. F. Repair of Concrete Shoulders, Curbs, and Curb and Gutter. The Engineer will measure repairs for concrete shoulders, curbs, and curb and gutter as Pavt Repr, Nonreinf, Conc, at the same thickness as adjacent concrete pavement repairs. The Department will pay for repairing concrete shoulders, curbs, and curb and gutter as Pavt Repr, Nonreinf, Conc. G. Joints. 1. Joint, Expansion, Esc. The unit price for Joint, Expansion, Esc includes the cost of sawing and chipping the joint and providing and installing the joint filler material. 2. Expansion, Erg. The unit price for Joint Expansion Erg includes the cost of the following: a. Making the saw cuts required at the ends of the repairs; 341

16 b. Removing the saw slurry from the pavement surface and sawed faces; c. Drilling and cleaning the holes for the dowel bars and deformed bars; d. Providing, mixing, and installing the grout; e. Providing and installing the dowel bars and deformed bars; f. Providing and applying the dowel bar bond breaker coating; g. Providing, drilling or punching, and installing the fiber filler; h. Providing and installing the dowel bar expansion caps; i. Sawing the joint grooves; j. Cleaning and preparing the joint groove; and k. Providing and installing the joint groove sealant. The Department will pay for sawing depths, greater than 1 inch below the depth shown on the plans, as extra work. 3. Transverse Plane-of-Weakness Joints D1. The Engineer will measure, and the Department will pay for transverse plane-ofweakness joints D1 in accordance with subsection Transverse Plane-of-Weakness Joints U. The unit prices for other concrete pavement repair pay items include the cost of transverse plane-of-weakness joints U. H. Lane Tie, Epoxy Anchored. The unit price for Lane Tie, Epoxy Anchored includes the cost of the following: 1. Drilling and cleaning the holes; 2. Providing, mixing, and installing the grout; and 3. Providing and installing the deformed bars. The unit prices for other pay items include the cost of final trim and clean-up, part-width construction, and restoring shoulders. I. Diamond Grinding Concrete Pavement. The Engineer will include the final textured surface area in the measurement for Diamond Grinding Conc Pavt. The Department will not deduct minor areas of untextured pavement if the minor areas total no greater than 5 percent of the area shown on the plans. The unit price for Diamond Grinding Conc Pavt includes the cost of collecting, hauling, and spreading grinding residue. The unit prices for other pay items include the cost of additional passes or regrinding to meet ride quality requirements. J. Longitudinal Pavement Joints and Transverse Pavement Joints. The unit prices for Sawing and Sealing Longit Pavt Joints and Sawing 342

17 and Sealing Transv Pavt Joints include the cost of sawing or resawing, cleaning, and sealing the joints with hot-poured rubber. K. Resealing Transverse and Longitudinal Joints with Hot-Poured Rubber. The Engineer will measure Resealing Transv Joints with Hot-Poured Rubber and Resealing Longit Joints with Hot-Poured Rubber in a straight line in the direction of each joint. The unit prices for Resealing Transv Joints with Hot-Poured Rubber and Resealing Longit Joints with Hot-Poured Rubber include the cost of removing existing sealants, cleaning, and sealing the joints. L. Crack Sealing, Concrete Pavement. The Engineer will measure Crack Sealing, Conc Pavt in a straight line in the direction of each crack. 343

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course. SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721

More information

Section 602. CONCRETE PAVEMENT CONSTRUCTION

Section 602. CONCRETE PAVEMENT CONSTRUCTION Section 602. CONCRETE PAVEMENT CONSTRUCTION 602.02 602.01. Description. This work consists of constructing a jointed portland cement concrete pavement, unbonded concrete overlay, base course, or shoulder,

More information

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications: FAST TRACK FULL DEPTH CONCRETE REPAIR Item No. FULL DEPTH CONCRETE REPAIR Item No. PARTIAL DEPTH CONCRETE REPAIR Item No. FAST TRACK PARTIAL DEPTH CONCRETE REPAIR Item No. Special Provision No. 399S43

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

BASE CONSTRUCTION MATERIALS A Aggregate

BASE CONSTRUCTION MATERIALS A Aggregate BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3

More information

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures

More information

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS 603.1 DESCRIPTION Determine the smoothness of the pavement surface and correct the deficiencies as specified in the Contract Documents. For the purposes of this

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

A. Submittal Procedures: See Article 13 of the General Conditions.

A. Submittal Procedures: See Article 13 of the General Conditions. SECTION 321313 - CONCRETE PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Driveways. 2. Roadways. 3. Parking lots. 4. Curbs and gutters. 5. Walks. B. Proposed Substitutions: See Article 2,

More information

Section 811. PERMANENT PAVEMENT MARKINGS

Section 811. PERMANENT PAVEMENT MARKINGS 811.01 Section 811. PERMANENT PAVEMENT MARKINGS 811.01. Description. This work consists of providing and applying retroreflective permanent pavement markings in accordance with the Michigan Manual on Uniform

More information

This specification refers to the following standards, specifications, or publications:

This specification refers to the following standards, specifications, or publications: PRECAST CONCRETE SLAB REPAIR - Item No. Special Provision No 363S01 February 2013 Amendment to OPSS 363, April 2008 OPSS 363, Construction Specification for Repairing Rigid Pavement with Precast Concrete

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

FIVE STAR PRODUCTS, INC. (800)

FIVE STAR PRODUCTS, INC.  (800) FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 Page 1 of 11 DESIGN-A-SPEC GUIDELINES FIVE STAR RS ANCHOR GEL CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS PART

More information

Construction Specification for Concrete Bus Pad

Construction Specification for Concrete Bus Pad Engineering & Construction Services Division Standard Specifications for Road Works TS 3.41 June 2017 for Concrete Bus Pad Table of Contents SCOPE... 3 REFERENCES... 3 DEFINITIONS... 3 DESIGN AND SUBMISSION

More information

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction Warm Mix Asphalt (WMA) Guide Specification for Highway Construction Division 400 - Asphalt Pavements and Surface Treatments SECTION 4XX - WARM MIX ASPHALT (WMA) PAVEMENT Warm mix asphalt (WMA) is the generic

More information

DOWEL BAR RETROFIT DO S AND DON TS

DOWEL BAR RETROFIT DO S AND DON TS DOWEL BAR RETROFIT DO S AND DON TS WA-RD 576.1 October 2003 Washington State Transportation Commission Strategic Planning and Programming in cooperation with the U.S. Department of Transportation Federal

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

507 SLURRY SEAL AND MICRO-SURFACING 1 of 8 CATEGORY 500 PAVING SECTION 507 SLURRY SEAL SECTION 507 SLURRY SEAL AND MICRO-SURFACING

507 SLURRY SEAL AND MICRO-SURFACING 1 of 8 CATEGORY 500 PAVING SECTION 507 SLURRY SEAL SECTION 507 SLURRY SEAL AND MICRO-SURFACING 507 SLURRY SEAL AND MICRO-SURFACING 1 of 8 CATEGORY 500 PAVING SECTION 507 SLURRY SEAL 489 DELETE: SECTION 507 SLURRY SEAL in its entirety. INSERT: The following. SECTION 507 SLURRY SEAL AND MICRO-SURFACING

More information

Section 708. PRESTRESSED CONCRETE BEAMS Description. Manufacture and erect prestressed concrete beams.

Section 708. PRESTRESSED CONCRETE BEAMS Description. Manufacture and erect prestressed concrete beams. 708.0 Section 708. PRESTRESSED CONCRETE BEAMS 708.0 Description. Manufacture and erect prestressed concrete beams. 708.02 Materials. Use materials meeting the following. Mortar and Grout... 702 Cement...

More information

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS CONCRETE SIDEWALKS AND DRIVEWAYS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

SECTION CONCRETE PAVING FOR PEDESTRIAN AREAS. A. This Section includes exterior cement concrete pavement for the following:

SECTION CONCRETE PAVING FOR PEDESTRIAN AREAS. A. This Section includes exterior cement concrete pavement for the following: SECTION 321313 CONCRETE PAVING FOR PEDESTRIAN AREAS PART 1 GENERAL 1.1 SUMMARY A. This Section includes exterior cement concrete pavement for the following: 1. Walkways. 2. Courtyards. 3. Plazas. 4. Pedestrian

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3 CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3

More information

TECHNICAL SPECIFICATIONS

TECHNICAL SPECIFICATIONS TECHNICAL SPECIFICATIONS ITEM 00663 TRAFFIC BUTTONS & PAVEMENT MARKERS 663.1 Description. This item shall consist of furnishing and installing traffic buttons and reflectorized pavement markers and jiggle

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007 (Revision 2) Page 1 of 21 CONCRETE CONSTRUCTION

City of Brandon Division 2 Standard Construction Specifications Section January 2007 (Revision 2) Page 1 of 21 CONCRETE CONSTRUCTION January 2007 (Revision 2) Page 1 of 21 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 STANDARDS 1.05 QUALITY ASSURANCE The General Conditions of the Contract,

More information

PORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer)

PORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer) PORTLAND CEMENT CONCRETE OVERLAYS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Bonded Concrete Overlays Over Concrete B. Bonded Concrete Overlays Over Asphalt C. Unbonded Concrete Overlays Over Concrete (with

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION

MICHIGAN DEPARTMENT OF TRANSPORTATION MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR OPEN-GRADED DRAINAGE COURSE, MODIFIED FOR JOB NUMBER 110616 (PORTLAND CEMENT-TREATED PERMEABLE BASE USING CRUSHED CONCRETE) CFS:JFS 1 of 5 APPR:ARB:TES:11-06-14

More information

CONSTRUCTION BULLETIN

CONSTRUCTION BULLETIN CONSTRUCTION BULLETIN State Construction Office Engineering and Regional Operations Bituminous Surfacing on Structure Decks: Specification Language Bulletin #2016-06, Page 1 of 3 Date: November 2 nd, 2016

More information

1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.

1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas. SECTION 1300 - ASPHALTIC CONCRETE PAVEMENT 1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas. 1302 GENERAL. Pavement shall be constructed to the lines, grades,

More information

Mix Design & Construction -1-

Mix Design & Construction -1- Mix Design & Construction -1- AGENDA RCC Mix Design RCC Mix Production RCC Construction Process -2- THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL Natural

More information

MIDLAND COUNTY ROAD COMMISSION

MIDLAND COUNTY ROAD COMMISSION MIDLAND COUNTY ROAD COMMISSION BID FORM Sealed Proposals will be received at the office of the Board of Road Commissioners, County of Midland, at 2334 N. Meridian Road, Sanford, Michigan, 48657, until:

More information

Section 504. MICRO-SURFACING

Section 504. MICRO-SURFACING 504.01 Section 504. MICRO-SURFACING 504.01. Description. This work consists of preparing existing pavement and providing and placing a micro-surfacing mixture. 504.02. Materials. Provide materials in accordance

More information

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments Asphalt Pavement Preservation: Evaluation, Maintenance & Rehabilitation Maintenance & Rehabilitation Treatments Identification of Alternative Treatments Before selecting a treatment for a pavement, we

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

550 Surface Treatments

550 Surface Treatments Table of Contents 550 Surface Treatments... 550-1 550.1 Introduction... 550-1 551 Crack Sealing... 550-1 551.1 Project Selection... 550-1 551.2 Design Considerations... 550-1 552 Chip Sealing... 550-2

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

INDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT SCOPE Pre-Construction Meeting... 3

INDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT SCOPE Pre-Construction Meeting... 3 INDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT 830. 1 SCOPE... 3 1.1 Pre-Construction Meeting... 3 Page 830. 2 MATERIALS... 3 2.1 Sampling and Testing... 3 2.2 Supply... 3 2.3 Cement... 4 2.4 Fly Ash...

More information

FIVE STAR PRODUCTS, INC. (800)

FIVE STAR PRODUCTS, INC.  (800) FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 1 of 12 DESIGN-A-SPEC GUIDELINES FIVE STAR STRUCTURAL CONCRETE V/O CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information

FOR PROJECTS INITIATED Page -1- AFTER FEBRUARY 1, 2010 REVISION 13 ITEM 360 CONCRETE PAVEMENT

FOR PROJECTS INITIATED Page -1- AFTER FEBRUARY 1, 2010 REVISION 13 ITEM 360 CONCRETE PAVEMENT Page -1- AFTER FEBRUARY 1, 2010 ITEM 360 CONCRETE PAVEMENT 360.1 Description. This item shall consist of a pavement of Portland cement concrete with reinforcement. The pavement shall be as shown on the

More information

SECTION CONCRETE LINED CANALS AND RESERVOIRS

SECTION CONCRETE LINED CANALS AND RESERVOIRS SECTION 02511 CONCRETE LINED CANALS AND RESERVOIRS PART 1 GENERAL 1.01 SECTION INCLUDES Canal linings shall be constructed where shown on the drawings. The lining will be unreinforced concrete containing

More information

Section 401. PIPE CULVERTS

Section 401. PIPE CULVERTS 401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

BITUMEN-SET PRECAST CONCRETE PAVING SLABS

BITUMEN-SET PRECAST CONCRETE PAVING SLABS SECTION 32 14 13.16 BITUMEN-SET PRECAST CONCRETE PAVING SLABS (1995 MasterFormat Section 02784) NOTE: This guide specification is the U.S. for concrete paving slabs adhered with a neoprene mastic to a

More information

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007 Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION March 22, 2007 Description: This work consists of furnishing and applying asphalt rubber binder followed by an application of treated cover aggregate

More information

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation Design and Construction of Concrete Overlays By: James K. Cable, P.E. Cable Concrete Consultation PCC OVERLAY AGENDA Current design & construction features What is needed in a PCC overlay set of plans?

More information

Section 505. CHIP SEALS

Section 505. CHIP SEALS Section 505. CHIP SEALS 505.01. Description. This work consists of preparing the pavement surface and providing and placing a single chip seal, double chip seal, or shoulder chip seal. 505.02. Materials.

More information

CW 3615 RIPRAP TABLE OF CONTENTS

CW 3615 RIPRAP TABLE OF CONTENTS December 2014 SPECIFICATION CW 3615 R4 CW 3615 RIPRAP TABLE OF CONTENTS 1. GENERAL CONDITIONS... 1 3. DESCRIPTION... 1 5. MATERIALS... 1 5.1 General... 1 5.2 Rock... 1 5.3 Random Stone Riprap... 1 5.4

More information

CITY OF FARGO SPECIFICATIONS CONCRETE PAVING

CITY OF FARGO SPECIFICATIONS CONCRETE PAVING SECTION 2100 CONCRETE PAVING PART 1 DESCRIPTION OF WORK The work to be done under these Specifications and the accompanying plans consist of furnishing all labor, material, accessories, and plant necessary

More information

SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES

SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES GUIDE SPECIFICATION SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES PART 1 - SCOPE 1.01 WORK INCLUDED: 1.1.1 This guide covers the

More information

A. Testing Laboratory Services: Section B. Excavation, Site Fill and Rough Grading: Section Sub-Base Course Material (If requested).

A. Testing Laboratory Services: Section B. Excavation, Site Fill and Rough Grading: Section Sub-Base Course Material (If requested). SECTION 02500 - PART 1 - GENERAL 1.01 RELATED WORK SPECIFIED ELSEWHERE A. Testing Laboratory Services: Section 01411. B. Excavation, Site Fill and Rough Grading: Section 02200. C. Concrete: Section 03310.

More information

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket 1993 Specifications CSJ 0331-04-045 SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket 1. Description. This Item shall govern for the furnishing, installing and energizing a sacrificial

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-03 01 30.71 (April 2006) ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-03930 (September 1999) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00

More information

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT SS-400G Page 1 of 3 This supplementary specification replaces Section 414, Portland Cement Concrete

More information

PAVEMENT MARKINGS. F. Grooves Cut for Pavement Markings, Symbols, and Legends

PAVEMENT MARKINGS. F. Grooves Cut for Pavement Markings, Symbols, and Legends PAVEMENT MARKINGS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Permanent Pavement Markings, Symbols, and Legends B. Removable Pavement Markings, Symbols, and Legends C. Temporary Delineators D. Raised Pavement

More information

SECTION SITE CONCRETE

SECTION SITE CONCRETE SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , & TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed

More information

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING 402.1 Description. This work shall consist of placing, spreading and compacting a bituminous mixture as shown on the plans or as directed by the engineer.

More information

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B401: DELETED B402: DELETED B403: DELETED B404: STRUCTURE/CULVERT IDENTIFICATION SIGNS B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B406: ITEM 514 - FIELD PAINTING, MISC.; REPAIR PAINTING

More information

***************************************************************************************************************

*************************************************************************************************************** 09330 QUARRY TILE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 09 30 16 ***************************************************************************************************************

More information

BIO-AQUIFER STORM SYSTEM

BIO-AQUIFER STORM SYSTEM BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone

More information

Chapter 4 Portland Cement Concrete Pavement Guidelines and Policies Publication Edition Change 1 CHAPTER 4

Chapter 4 Portland Cement Concrete Pavement Guidelines and Policies Publication Edition Change 1 CHAPTER 4 CHAPTER 4 PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) GUIDELINES AND POLICIES 4.1 CONCRETE PAVEMENT RESTORATION (CPR) A. Preliminary Engineering. The major considerations in the design of a rehabilitation

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS March 2, 2015 806.01 Description 806.02 JMF Field Adjustments 806.03

More information

Construction Specification for Concrete Unit Pavers

Construction Specification for Concrete Unit Pavers Engineering & Construction Services Division Standard Specifications for Road Works TS 3.80 September 2017 for Concrete Unit Pavers Table of Contents TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS

More information

CONSTRUCTION SUMMARY REPORT

CONSTRUCTION SUMMARY REPORT Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard

More information

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or

More information

SDDOT CONSTRUCTION MANUAL PROJECT MANAGEMENT SECTION CHAPTER 18 INSPECTION CHECKLISTS TABLE OF CONTENTS. Job Guide General Instructions 18-2

SDDOT CONSTRUCTION MANUAL PROJECT MANAGEMENT SECTION CHAPTER 18 INSPECTION CHECKLISTS TABLE OF CONTENTS. Job Guide General Instructions 18-2 TABLE OF CONTENTS ITEM PAGE Job Guide General Instructions 18-2 Construction Signing and Traffic Control 18-3 Job Guide for Concrete Curb, Gutter, Walk, Driveway & Barrier 18-5 Job Guide for Paving Concrete

More information

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for

More information

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES INTENT: To provide a system for reconstruction of concrete or masonry structures to stop inflow, infiltration, exfiltration, and

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

SECTION CONCRETE PAVING SLABS SET IN MORTAR

SECTION CONCRETE PAVING SLABS SET IN MORTAR SECTION 32 14 13.16 CONCRETE PAVING SLABS SET IN MORTAR (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs mortared to a concrete base and grouted joints

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 11/21/2014 Project 140560 Addendum No. 2 PID No. 82972 HAM IR 275

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

PRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT

PRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT PRECAST PRESTRESSED CONCRETE PAVEMENT The Standard Specifications are revised as follows: SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION 509 - PRECAST PRESTRESSED CONCRETE PAVEMENT 290 509.01

More information

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of

More information

4-07 Asphalt Treated Permeable Base (ATPB)

4-07 Asphalt Treated Permeable Base (ATPB) 1 1 0 1 0 1 Supplement Division with the following: (November 0,, APWA GSP) -0 Asphalt Treated Permeable Base (ATPB) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course

More information

DIVISION 32 EXTERIOR IMPROVMENTS

DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVEMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340 DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340 PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. The General provisions of the contract, including GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS AND

More information

Special Specification 3005 Scrub Seal Treatment

Special Specification 3005 Scrub Seal Treatment Special Specification 3005 Scrub Seal Treatment 1. DESCRIPTION 2. MATERIALS 3. EQUIPMENT Construct a surface treatment consisting of 1 or more applications of a single layer of asphalt emulsion that is

More information

610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT

610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT 610.1 DESCRIPTION Construct a wearing surface composed of an asphalt prime coat followed by the applications of 2 asphalt seal coats and cover material as specified

More information

ARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound

ARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound ARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade.

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade. MANUFACTURER S SPECIFICATIONS Section 03330 LIME CONCRETE ST. ASTIER NATURAL HYDRAULIC LIME CONCRETE PART 1 GENERAL 1.01 General A. This section describes the requirements for floors and slabs on grade.

More information

CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF CONTENTS CITY OF TORONTO TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS TS 4.70 November 2007 CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF

More information

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2

More information

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,

More information

ITEM 458 WATERPROOFING FOR STRUCTURES

ITEM 458 WATERPROOFING FOR STRUCTURES ITEM 458 WATERPROOFING FOR STRUCTURES 458.1. Description. This Item shall govern for the furnishing and placing of waterproofing on concrete and steel bridge decks of railroad structures and on other structures

More information

1.2 Reference Standard: NOFMA - National Oak Flooring Manufacturers Association Grading Standards.

1.2 Reference Standard: NOFMA - National Oak Flooring Manufacturers Association Grading Standards. WOOD FLOORING GENERAL INFORMATION 1.1 This section applies to factory finished wood strip flooring. 1.2 Reference Standard: NOFMA - National Oak Flooring Manufacturers Association Grading Standards. 1.3

More information

Section 508. CHIP SEALS Description. Prepare the surface and apply the specified single chip seal, double chip seal or shoulder chip seal.

Section 508. CHIP SEALS Description. Prepare the surface and apply the specified single chip seal, double chip seal or shoulder chip seal. 508.01 Section 508. CHIP SEALS 508.01 Description. Prepare the surface and apply the specified single chip seal, double chip seal or shoulder chip seal. 508.02 Materials. Use materials meeting the following.

More information

SECTION CONTROLLED LOW STRENGTH MATERIAL

SECTION CONTROLLED LOW STRENGTH MATERIAL SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL January 2000 Page 1 of 10 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 APPROVALS PART 2 PRODUCTS 2.01 CEMENT 2.02 WATER The General Conditions of the Contract,

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information