Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo
|
|
- Juliana Holland
- 6 years ago
- Views:
Transcription
1 Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo
2 Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons Learned 2
3 3 Moncton New Brunswick
4 Moncton and Riverview New Brunswick Causeway with gate on Riverview side Petticodiac River 4 Petticodiac Lake
5 Petticodiac River Flows into Bay of Fundy Tidal estuary World s largest tides ±40 feet every 5.5 hours Unique tidal bore (up to 2m high wave pre 1960 s) 5
6 6 Petticodiac River The river is 129 km long and has a 3,000 km² drainage basin. Largest River basin in Eastern Canada Commercial fishing industry existed on the Petticodiac until the late 1960s Atlantic Salmon, Gaspereau (Alewife), Smelt and Sturgeon
7 7 Moncton Ship Building
8 8
9 9
10 Causeway Construction Controversial construction of causeway begins
11 11
12 12
13 13
14 14
15 15
16 16
17 Impact of Causeway Construction Petticodiac Lake Headpond is formed Volume of water (tidal prism) is substantially reduced Volume of sediment in the river is increased dramatically 17
18 18 Impact of Causeway Construction
19 19 Impact of Causeway Construction
20 20 Impact of Causeway Construction
21 Impact of Causeway Construction Post causeway Tidal bore a few centimetres to 0.75m high Pre causeway up to 2m high No fish passage Loss of estuary, rare shell fish and fish... 21
22 River Restoration Project Remove causeway and gates and replace with bridge 22
23 Three Stage Project Stage 1 protection and preparatory works Relocate watermain located in front of gates dykes, riprap, design, and baseline monitoring $20 million Stage open gates during spring flush and monitor Stage construct and operate the bridge and monitor Total project cost estimate $68 million 23
24 Project Overview Moncton Former Landfill Existing Watermain Causeway Gates 24 Moncton Watermain Relocation Riverview
25 Project Requirements Moncton Riverview Conceptual Transmission Line 25 Moncton Watermain Relocation
26 Project Requirements Open cut Connection Moncton Trenchless Connection Open cut Riverview 26 Moncton Watermain Relocation
27 Key Project Requirements Install new 762mm (30in) ID watermain Conceptual pipe alignment length is approx. 550m Minimum top of pipe depth is -6m for scour protection under new channel Trenchless Pipe test pressure is 1655kPa (240psi) Open cut pipe test pressure is 1379kPa (200psi) 27 Moncton Watermain Relocation
28 Key Project Requirements Design and build contract to include: Trenchless and open pipe installation Connection to existing watermain Watermain commissioning Critical commission date is February 28, 2010 Need spring runoff to clean out sediment deposits in Petticodiac River 28 Moncton Watermain Relocation
29 PROJECT DESIGN TEAM Project Client New Brunswick Department Supply and Services Consultant Consortium AMEC Causeway Project Lead Paul Belyea P.Eng. Geotechnical Engineer ADI Limited Watermain Reconstruction Project Lead Boyd Touchie Project Manager Dr. Mark Knight Trenchless Expert Jacques Whitford Associates (Stantec Consulting) Geotechnical Lead Dr. Arun Valsangkar P.Eng. 29 Moncton Watermain Relocation
30 Project Design Approach 1. Prequalify contractor Ensure have equipment and experience to complete project Ensure completed similar projects in the past. 2.Contractor design build project Ensure project constructible using contractor equipment 3. June 11, 2009 issue Request for Qualification (RFQ) documents 4. June 29, 2009 RFQ closed Three responses submitted and one late submission Design team reviewed and rated submissions No contractor qualified 30 Moncton Watermain Relocation
31 Project Design Approach Phase II Design-Build is best contract approach to ensure project completed on time and budget Design team will complete construction design review to determine costs and construction issues Will invite three contractors to respond to request for proposals Design team will recommend three contractors to bid Design team will prepare RFP for October 2009 contract award Each contractor will be paid $40,000 for submission of a complete bid package 31 Moncton Watermain Relocation
32 Proposed Project Milestones Proposed Date August 14, 2009 September 1, 2009 September 15, 2009 October 2, 2009 October 5, 2009 October 19, 2009 December 29, 2009 February 5, 2009 February 28, 2009 Milestone Description RFP to Proponents Bidder Meeting and Provision of Information Package Submission of RFP to NBDSS Contract Award Placement of Pipe Order Equipment Mobilization and Commencement of Site Works Commencement of Trenchless and Open Cut Pipe Works Completion of Pipe Installations and Pipe Connections Watermain Commissioning 32 Moncton Watermain Relocation
33 Design Brief To ensure successful on budget and on time project Design Team needed to identify: construction risks and challenges project costs 33 Moncton Watermain Relocation
34 Design Brief Looked at three construction options: 1. A1 Horizontal Directional Drilling (HDD) 40in Steel then slipline with 36in OD HDPE product pipe 30in Ductile Iron as product pipe 2. A2 Horizontal Directional Drilling (HDD) Install two 24in steel casing and slipline with 24in HDPE 3. B Microtunnel 34 Moncton Watermain Relocation
35 Inferred Site Geology Along Conceptual Alignment 10.0m 0 m 100m 200m 300m 400m 500m 600m BH27 BH26 BH25 Sand BH24 BH7 BH23 BH6 BH22 0.0m -10.0m Till Head Pond Fill (Gravel) Silt Silt Sand -20.0m Bedrock Till Sand with gravel -30.0m 35 Moncton Watermain Relocation
36 Option A1 - HDD to -8m Install steel casing: slip line with 762mm(30in) product pipeline BH m Sand 0 m 100m 200m 300m 400m 500m 600m BH6 BH26 BH25 BH24 BH7 BH23 BH22 0.0m -10.0m -20.0m Till Bore reamed to 1321mm (52in) Bedrock Head Pond Fill (Gravel) Silt Silt Till Sand Sand with gravel -30.0m 36 Moncton Watermain Relocation
37 Option A1 - HDD to -8m Install steel casing then slip lined with 762mm(30in) product pipeline Pipe length = approx 530m (1739 feet) Drill entrance angle 17 degrees Drill exit angle 8 degrees Drill exit before drainage ditch Causeway Existing Ditch Headpond Sand Till Very Loose Silt Silty Sand Bore ream to 1321mm (52in) Till Sandstone/Mudstone bedrock Fill Fill Very Loose Silt Sand and Gravel 37 Moncton Watermain Relocation
38 Option A1 - HDD to -8m Install steel casing: slip line with 762mm (30in) product pipe Install 1016mm (40in) steel casing 12.7mm (0.5in) thick in a 1321mm (52in) reamed borepath Required to withstand installation forces Eliminates post construction decontamination issues Estimated required drill rig pipe pullback force: 1505kN (338,500lbs force) with rollers and pipe buoyancy 2962kN (666,000lbs force) with no rollers and pipe buoyancy 38 Moncton Watermain Relocation
39 Option A1 - HDD to -8m 914mm (36in) DR-11 HDPE product pipe 914mm (36in) DR-11 HDPE (PE3408) product pipe approved by AWWA 1103 kpa (160 psi) working pressure - Max test pressure is 1655 kpa (240psi) which meets City design criteria Pipe ID is 738mm(29.06in) with OD =914mm (36in) Diameter less than 762mm (30in) required Pipe price quoted at $305,000 Pipe fusion price quoted at $25,000 Currently new PE4710 (new resin) is not AWWA approved for potable water therefore not considered for this project 60-day lead time required for pipe delivery 39 Moncton Watermain Relocation
40 Option A1 - HDD to -8m 762mm(30in) Ductile Iron Product Pipe 762mm(30in) ductile iron with Flexi-joint as product pipe 1724kPa (250psi)working pressure- max test pressure is greater than 2069kPa (300psi) exceeds design requirements Pipe ID is 785mm(30.9in) with bell joint OD of 937mm(36.9in) Will fit inside 1016mm (40in) steel pipe 85 days lead time required for pipe delivery Pipe cost $452,000CAD ($400,725USD) Corrosion protection and monitoring needs to be addressed in design and construction 40 Moncton Watermain Relocation
41 Option A1 - HDD to -8m Construction Risks Major risk is bore collapse in silty sand on Moncton side Risk can be reduced by: Soil characterization of lower fill Using smallest diameter bore Installation of conductor steel casing Careful selection/monitoring of drill fluids Inadvertent drill fluid release Risk can be reduced by: Monitoring bore drill fluid pressure and drill procedures 41 Moncton Watermain Relocation
42 Option A1 - HDD to -8m Cost Estimate $5 to 6 million Includes pipe materials, drilling, site preparation and pipe installation Does not include open trench pipe construction, concrete valve chambers and connections 42 Moncton Watermain Relocation
43 Option A2 - HDD to -8m Install two 711mm(28in) steel casings Slip line with 610mm(24in) product pipe 10.0m 0.0m -10.0m BH27 0 m 100m 200m 300m 400m 500m 600m Till Sand BH26 BH25 Till -20.0mBore reamed to 1016mm (40in) Bedrock Bore reamed to (40in) BH24 BH7 BH23 BH6 Head Pond Fill (Gravel) Silt Silt BH22 Sand Sand with gravel -30.0m 43 Moncton Watermain Relocation
44 Option A2 - HDD to -8m Install two 711mm(28in) steel casing then slip lined with 610mm(24in) product pipe 1016mm (40in) reamed bore path required Option is not considered feasible as it requires drilling two bores of similar diameter to option A1 610mm (24in) is not significantly less than Option A1 762mm (30in) product pipe Installation of two pipes will require complex connection issues 44 Moncton Watermain Relocation
45 10.0m Drive shaft 0.0m -10.0m Option B - Microtunnel BH27 Reception 0 m 100m 200m 300m 400m shaft 500m 600m Till Sand BH26 BH25 BH24 BH7 BH23 BH6 Head Pond Fill (Gravel) Silt Silt BH22 Sand -20.0m Bedrock Till Sand with gravel -30.0m 45 Moncton Watermain Relocation
46 Option B - Microtunnel Option B requires two shafts 18m (59ft) deep drive shaft on Riverview side at BH21 18m (59ft) deep reception shaft on Moncton side at BH16 Drive distance approx 500m (1640ft) Drive will require at least two internal intermediate jacking stations (IJS) to complete drive 46 Moncton Watermain Relocation
47 Option B - Microtunnel Distance of drive is approaching current laser technology limits Alignment passes through mixed ground conditions Bedrock, till, silty sand and sand/gravel At least 1524mm (60in) boring machine required for person entry and access to machine face Machine diameter limited to contractor availability Person entry/face access requires safety issues 47 Moncton Watermain Relocation
48 Option B Microtunnel Shafts Moncton side shaft design and construction challenging due to: Soft soils and upward gradients Resisting hydrostatic and earth pressures will require robust bracing system Grouting of bedrock required to control hydraulic gradients Need testing and monitoring to determine effectiveness Sheet piles must be driven to bedrock even for shaft base at elevation - 8 to -10m Cost estimate $3.0 to $4.0 million Construction could take several months to complete Risk of major delays due to shaft construction difficulties 48 Moncton Watermain Relocation
49 Option B Microtunnel Risks Mixed face and variable ground conditions Wear on cutters Safety requirements for personnel to access face and remove intermediate jacking stations Limit of laser alignment technology offline and grade will significantly increase jacking force 49 Moncton Watermain Relocation
50 Cost Estimate Shafts Total cost for construction of two shafts $3 to $4 million Pipeline installation $5 to $7 million Function of diameter of machine used and difficult to estimate Total pipeline cost estimate $8 to $11 million 50 Moncton Watermain Relocation
51 Others Considerations Looked at HDD into bedrock as proposed in RFQ Construction will require 30m (98ft) plus shaft at BH-16 Method deemed not constructible due to: Need to construct deep shafts Pumping and operation issues resulting from deep shafts Cost 51 Moncton Watermain Relocation
52 Summary HDD Option A1 Microtunnelling Trenchless Pipeline Construction Cost $5 to 6 million $5 to 7 million Shafts None required Moncton and Riverside $3 to 4 million total Auxiliary construction* $1.2 million $0.8 million Total Cost $6.2 to 7.2 million $8.8 to 11.8 million *Includes: open trench pipe laying, connections, concrete chambers, and site works 2 million project budget needed to be increased 52 Moncton Watermain Relocation
53 Risk and Material HDD Option A1 Microtunnelling Pipeline Installation: Risk of Failure Shafts : Risk of Construction Delay Low-medium in silty sand Low in till and bedrock None Medium to High High Pipe Product Ductile Iron PCCP, Ductile, HDPE Casing 1016mm (40in) steel 1524mm (60in) concrete or steel 53 Moncton Watermain Relocation
54 Design Issues Proposed bridge embankment will induce loads on pipe Embankment loads need to be considered in the pipe design Any minor changes in location of bridge abutment will have direct impact on the watermain design and performance Data from BH 36 indicates coarse rock fill may exist to elevation -11m Geotechnical boring data critical to successful project 54 Moncton Watermain Relocation
55 RFP Three companies selected and requested to bid on RFP $40,000 provided to companies to cover bid costs provided complete bid package submitted Required stamped engineering design drawings Two bids received $6.4 and $7.2 million Michels Canada awarded contract Used detailed bid review scoring system (cost 20 percent) Each design team member reviewed bids independently 55 Moncton Watermain Relocation
56 Construction Bore depth -10m Install casing on Moncton and Riverview Complete an intersect bore using American Augers DD220 Moncton side (pipe entrance) American Augers DD330 Moncton side (pipe entrance) Estimated Max pull back 152,000lbs with buoyancy and 325,000lbs with air in pipe Install 36in HDPE pipe 56
57 Intersect Bore Construction 10.0m 0 m 100m 200m 300m 400m 500m 600m BH27 BH26 BH25 Sand BH24 BH7 BH23 BH6 BH22 0.0m -10.0m Till Head Pond Fill (Gravel) Silt Intersect Point Silt Sand -20.0m Bedrock Till Sand with gravel -30.0m 57
58 58 Construction
59 59 Construction
60 60 Construction
61 61 Push-Pull Ream Construction
62 62 Construction
63 Construction Project completed on time and budget No significant construction issues Geotechnical data was accurate Contractor stated project with best geotechnical data Causeway Gates opened April 14, Moncton Watermain Relocation
64 Lessons Learned Formation of design team was critical Project required to be contractor design build Meet tight construction details Geotechnical data critical for route selection Completion of design review critical to identify critical issues Geotechnical issues Project cost Pipe order and delivery issues Project schedule Trenchless construction requires design by experienced engineers 64 Moncton Watermain Relocation
65 Questions
APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer
APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY
More informationWESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY
WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY Bryan Thompson, Town of Westport Abhinav Huli, Haley & Aldrich, Inc Lori Carriero, P.E., Tighe & Bond PRESENTATION OUTLINE
More informationPipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.
Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods
More informationSioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons
WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction
More informationFifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River
Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River 3 rd Annual Rocky Mountain Regional No Dig Conference & Exhibition Westminster, CO November 8, 2012 David Bennett,
More informationCutting-Edge Trenchless Technology Proposed for Challenging CSO Project
North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TM1-T2-03 Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project
More informationKing County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal
North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle
More informationWARNING DO NOT BID ON THIS PROJECT
WARNING DO NOT BID ON THIS PROJECT Nick H. Strater, P.G., Associate, Brierley Associates, Bedford, NH Brian C. Dorwart, P.E., P.G., Sr. Consultant, Brierley Associates, Bedford, NH For projects advertised
More informationTrenchless Pipeline Crossings
Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going
More informationKathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016
www.norcalpug.com Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 Kathryn Wallin Bennett Trenchless Bo Botteicher Underground Solutions Project Area Existing Sewers 66-inch
More informationMartha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines
Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Introduction Purpose Provide engineers and owners
More informationA Trenchless Approach to Lift Station Elimination
A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationREDUCING RISK AND VISITOR IMPACTS
REDUCING RISK AND VISITOR IMPACTS Trenchless Solutions for Liberty Island Paul J. Mourt, PE Project Rules To Live By 1 Expect the Unexpected Do your homework 2 Risks need to be evaluated on every project
More informationWhat do you mean we can t do HDD?
Clark Public Utilities Salmon Creek Crossing What do you mean we can t do HDD? Presented by Matt Hickey, PE Murray, Smith & Associates, Inc. and Russ Knutson, PE Clark Public Utilities Project Team Clark
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationPipe Ramming with HDD. Presentation Outline
EXAMINING PIPE RAMMING DESIGN- A FORENSIC ANALYSIS OF A HIGH RISK PROJECT Kimberlie Staheli, Ph.D., P.E. Staheli Trenchless Consultants Seattle, WA, USA Presentation Outline Pipe Ramming State of the Art
More informationNorth End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No
Hauled Wastewater Receiving Facilities Page 1 Part 1 General 1.1 SECTION INCLUDES.1 Materials and installation for sewage force mains. 1.2 RELATED SECTIONS.1 CW 2110 Watermains and all specifications referenced
More informationExperts in tunneling with Tunnel Boring Machines
www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution
More information8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation
8Re: Northern Access 2016 Project Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation Dear Mr. Horey and Mr. Hoover, Mr. Bradden Horey Mr. Brent Hoover P.E. Project
More informationAgenda for Today s Workshop
Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour
More information5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.
Highlights. How to use a Jet Pump? Jet pump for HDD New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters Dr. Marc Peters, Herrenknecht AG Full-Face Hole opener & Downhole Jet
More informationTechnology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill
Trenchless Technology Planning, Equipment, and Methods Mohammad Najafi Mc Gravu Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto
More informationTake Me to the Other Side:
Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional
More information2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995
2013 ASCE Agenda Introduction Difficult Ground Microtunneling in Difficult Ground Craig Camp July 31, 2013 Microtunneling Characteristics (NASTT) Earth pressure balancing Hydrostatic pressure balancing
More informationHDD Training. Mitigation. Mark Miller, PE Jon Robison, PE
HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing
More information2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January
Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations
More informationTHE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject
56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea
More informationDirect Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety
North American Society for Trenchless Technology (NASTT) NASTT s 216 No-Dig Show Dallas, Texas March 2-24, 216 TA-T5-3 Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic
More informationE-Power Pipe : A new trenchless method for underground cable installation
E-Power Pipe : A new trenchless method for underground cable installation Dr. Gerhard Lang Jan 31, 2018 - UCT 2018, Track XI High Voltage Power Grid in Germany. Intention to replace nuclear power plants
More informationGeotechnical Investigations Water Main Construction
Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine
More informationCS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS
TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger
More informationUse of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii
Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Reyn Hashiro 1, P.E., M. ASCE, Devin Nakayama 2, P.E. M. ASCE, and James Kwong 3, Ph.D., P.E., M. ASCE 1 Associate, Yogi Kwong
More informationTrenchless Technology
TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology
More information4. FISH PASSAGE CONCEPTS
Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,
More informationSelecting Watermain Materials for Replacement Projects
April 28, 2015 Selecting Watermain Materials for Replacement Projects Presenter: Jonathon P. Meyer, P.E. Senior Project Engineer Acknowledgements Central Lake Joint Action Water Agency Village of Oak Lawn
More information1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.
MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction
More informationFUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC
Fusible C-900 Fusible C-905 FPVC Installations Trenchless Horizontal directional drilling Sliplining Pipe bursting Jack-and-bore carrier pipe Open-Cut Applications Features and Benefits Gasketless, leak-free,
More informationWESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY
WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY By: Bryan Thompson, Town of Westport, CT Abhinav Huli, Haley & Aldrich, Inc. Lori Carriero, Tighe & Bond Figure 1: Project
More informationCreated by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq
Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure
More informationB701 WATERMAINS- OPSS 701
B701 - OPSS 701 701.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.
More informationNo-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.
No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for
More informationSliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)
ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING
More informationHorizontal Directional Drilling
Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social
More informationDIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE
SECTION 308 BORING AND JACKING PART 2 MATERIALS 2.2 STEEL CASING PIPE E. Casing pipe length shall conform to City of Meridian Standard Drawing SW1 Casing Length Requirements. 2.4 CARRIER PIPE SKIDS A.
More informationThere are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.
Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications
More informationIII. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE
III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the
More informationB441 - WATERMAINS - OPSS GENERAL
B441 - - OPSS 441 441.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01
More informationLARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS
North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper A-1-01 LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS Kathryn Wallin 1, Matthew
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01
More informationDesign Data 4. Jacking Concrete Pipe
Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationMultiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line
PA AWWA Conference Bethlehem PA May 8, 2014 Multiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line Western Berks Water Authority Bern Township Transmission Main
More informationDIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING
DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as
More informationAnalysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore
Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga,
More informationThe City of Redwood City Completes Trenchless Sewer Installation under Highway 101
The City of Redwood City Completes Trenchless Sewer Installation under Highway 101 By Nick Lazarakis, PE, Kennedy/Jenks Consultants Special Thanks to: James Bowland, PE, Kennedy/Jenks Consultants Brad
More informationCITY OF RICHMOND INVITATION TO TENDER
CITY OF RICHMOND INVITATION TO TENDER Contract T.2892 Contract: AC Watermain Replacement, Comstock Area The City of Richmond invites tenders for construction work at the above-mentioned locations. Work
More informationDIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM
DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.
More informationSECTION TRENCHLESS INSTALLATION
SECTION 02250 PART 1 GENERAL 1.01 Section Includes A. Trenchless installation of casing pipe. B. Trenchless installation of carrier pipe. C. Open cut installation of casing pipe. 1.02 Description of Work
More informationPipe Jacking. Japan Sewage Works Association
Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,
More informationThe new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump
The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded
More informationIPC Company & DPI Presentation. February 2017
IPC Company & DPI Presentation February 2017 WHO WE ARE OVERVIEW Innovative Pipeline Crossings Inc. (IPC) Founded in 2013, in Calgary Private Company Since July 2016 under new Management Supervisory Board
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS
ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.
More informationAGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT:
AGENDA HEADING: Unfinished Business AGENDA REQUEST COMMISSION MEETING DATE: June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell AGENDA ITEM NO: VI.2. Originating Department SUBJECT: Department
More informationB. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.
33 05 23 TRENCHLESS UTILITY INSTALLATION SECTION 1 GENERAL 1.1 SUMMARY A. This specification addresses systems of piping and general requirements for water distribution and sewer collection systems which
More informationDIRECT PIPE AS AN ALTERNATIVE TO HDD, METHOD AND CASE STUDIES
DIRECT PIPE AS AN ALTERNATIVE TO HDD, METHOD AND CASE STUDIES Authors : Presenter : Dr Gerhard Lang, Business Development Manager, Herrenknecht AG Diana Pfeff, Product Manger, Herrenknecht AG Ben Hayes,
More informationChallenges on HDD Pipeline Shore Approach
OIL & GAS Challenges on HDD Pipeline Shore Approach DNV GL New Recommended Practice Luis D'Angelo - Danilo Machado 02 November 2016 1 SAFER, SMARTER, GREENER Agenda Objectives Why to use HDD in Shore Approach?
More informationYOUR GROUND DRILLING PARTNERS.
YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT
More informationSwagelining for Water Transmission & Sewer Force Main Renewal 16 through 65.
Swagelining for Water Transmission & Sewer Force Main Renewal 16 through 65 www.murphypipelines.com Murphy Pipelines Services For 2 through 65 Water & Force Main Replacement Trenchless Design Design Build
More informationHDPE Alliance 101 Annual Meeting Features and Cases. Peter Dyke, Murray Sullivan
HDPE Alliance 101 Annual Meeting Performance December 6 th 2017 Characteristics, Features and Cases Peter Dyke, Murray Sullivan Jimmy Dang, PE SPECIAL THANKS SPECIAL THANKS Murray Sullivan Alliance Membership
More informationApplicant s Proposed Mitigation Statements Seward Highway 75-90, POA , Turnagain Arm Phase 1 May 2017
Applicant s Proposed Mitigation Statements Seward Highway -, POA 2013-448, Turnagain Arm Phase 1 May 2017 Avoidance The project is geographically constrained by Turnagain Arm tidal mudflats on one side
More informationITEM 432 TUNNEL CONSTRUCTION
AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.
More informationTRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.
TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de
More informationCC1602 Microtunneling
CC1602 Microtunneling H.H. Sheikh Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae rachel@ictd.ae Course Introduction: Significant technical advances and increases in the utilization
More informationPlessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions
Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared
More informationDeep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control. Glenn Weist, P.E.
Deep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control Glenn Weist, P.E. Columbus, Ohio May 10, 2012 Agenda Background Project Description Regulatory Synopsis Stakeholder
More informationShort Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON
Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Earth Boring Co. Limited Trenchless Since 1947 Founded in Streetsville
More informationMicrotunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.
Microtunnelling Building infrastructures and power supply systems underground, while life above continues unaffected. 2 Comprehensive Microtunnelling Solutions A reliably functioning infrastructure which
More informationSection HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.
Section 02450 PART 1 GENERAL 1.01 SUMMARY A. This Section includes: 1. Installing water line by directional drilling methods. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for water lines installed
More informationH. Underground Transmission System Design
H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationSPECIFICATION : BORING AND JACKING
SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationGeotechnical Exploration and Evaluation Report
Geotechnical Exploration and Evaluation Report Nassau Reclaimed Water Main From Radio Avenue to Harts Road Nassau County, Florida CSI Geo Project No.: 71-17-329-04 Client Project No.: JEA 09302-049-01
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More informationGENERAL NOTES FOR FORCE MAINS: *CONTACTOR SHALL HAVE RICHMOND UTILITIES PERSONNEL ON SITE WHEN DIGGING OVER OR AROUND UTILITY LINES AND PUMP STATIONS. CONTRACTOR SHALL SCHEDULE EXCAVATION WITH RICHMOND
More informationCase History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River
DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,
More informationSECTION HORIZONTAL DIRECTIONAL DRILLING
SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using
More informationPipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2
Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers
More informationDesign Data 4M. Jacking Concrete Pipe
Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationAlternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project
Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Bernie Ashyk 1, Christopher Lucie, P.E. 2, Jeffrey LeBlanc, P.E. 3 1 Shook Walbridge JV, Project Manager;
More informationFor NGTL to file calculation of operating condition on pull back stress analysis.
NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at
More informationMultiple Large Diameter Microtunnels with Limited Ground Cover
North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 Paper No. TM2-T5-04 Multiple Large Diameter Microtunnels with Limited Ground Cover Steve
More informationPile Driving Issues. Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT
Pile Driving Issues Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT Goldilocks?? This soil it too hard This soil is too soft This soil is just right! This soil is too hard Prestressed concrete
More informationDRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S COMBINED OUTFALL SYSTEM
North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S
More informationE&S BMP DESIGN. Working Toward a Better Conclusion
E&S BMP DESIGN Working Toward a Better Conclusion Are Compost Socks Enough? Compost socks are excellent BMPs when properly used and maintained However, they do have limitations Compost Socks The right
More informationSPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006
Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable
More informationCHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD
North American Society for Trenchless Technology (NASTT) No-Dig Show 2012 Nashville, TN Paper A-2-04 CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD Christopher
More information