Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

Size: px
Start display at page:

Download "Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo"

Transcription

1 Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo

2 Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons Learned 2

3 3 Moncton New Brunswick

4 Moncton and Riverview New Brunswick Causeway with gate on Riverview side Petticodiac River 4 Petticodiac Lake

5 Petticodiac River Flows into Bay of Fundy Tidal estuary World s largest tides ±40 feet every 5.5 hours Unique tidal bore (up to 2m high wave pre 1960 s) 5

6 6 Petticodiac River The river is 129 km long and has a 3,000 km² drainage basin. Largest River basin in Eastern Canada Commercial fishing industry existed on the Petticodiac until the late 1960s Atlantic Salmon, Gaspereau (Alewife), Smelt and Sturgeon

7 7 Moncton Ship Building

8 8

9 9

10 Causeway Construction Controversial construction of causeway begins

11 11

12 12

13 13

14 14

15 15

16 16

17 Impact of Causeway Construction Petticodiac Lake Headpond is formed Volume of water (tidal prism) is substantially reduced Volume of sediment in the river is increased dramatically 17

18 18 Impact of Causeway Construction

19 19 Impact of Causeway Construction

20 20 Impact of Causeway Construction

21 Impact of Causeway Construction Post causeway Tidal bore a few centimetres to 0.75m high Pre causeway up to 2m high No fish passage Loss of estuary, rare shell fish and fish... 21

22 River Restoration Project Remove causeway and gates and replace with bridge 22

23 Three Stage Project Stage 1 protection and preparatory works Relocate watermain located in front of gates dykes, riprap, design, and baseline monitoring $20 million Stage open gates during spring flush and monitor Stage construct and operate the bridge and monitor Total project cost estimate $68 million 23

24 Project Overview Moncton Former Landfill Existing Watermain Causeway Gates 24 Moncton Watermain Relocation Riverview

25 Project Requirements Moncton Riverview Conceptual Transmission Line 25 Moncton Watermain Relocation

26 Project Requirements Open cut Connection Moncton Trenchless Connection Open cut Riverview 26 Moncton Watermain Relocation

27 Key Project Requirements Install new 762mm (30in) ID watermain Conceptual pipe alignment length is approx. 550m Minimum top of pipe depth is -6m for scour protection under new channel Trenchless Pipe test pressure is 1655kPa (240psi) Open cut pipe test pressure is 1379kPa (200psi) 27 Moncton Watermain Relocation

28 Key Project Requirements Design and build contract to include: Trenchless and open pipe installation Connection to existing watermain Watermain commissioning Critical commission date is February 28, 2010 Need spring runoff to clean out sediment deposits in Petticodiac River 28 Moncton Watermain Relocation

29 PROJECT DESIGN TEAM Project Client New Brunswick Department Supply and Services Consultant Consortium AMEC Causeway Project Lead Paul Belyea P.Eng. Geotechnical Engineer ADI Limited Watermain Reconstruction Project Lead Boyd Touchie Project Manager Dr. Mark Knight Trenchless Expert Jacques Whitford Associates (Stantec Consulting) Geotechnical Lead Dr. Arun Valsangkar P.Eng. 29 Moncton Watermain Relocation

30 Project Design Approach 1. Prequalify contractor Ensure have equipment and experience to complete project Ensure completed similar projects in the past. 2.Contractor design build project Ensure project constructible using contractor equipment 3. June 11, 2009 issue Request for Qualification (RFQ) documents 4. June 29, 2009 RFQ closed Three responses submitted and one late submission Design team reviewed and rated submissions No contractor qualified 30 Moncton Watermain Relocation

31 Project Design Approach Phase II Design-Build is best contract approach to ensure project completed on time and budget Design team will complete construction design review to determine costs and construction issues Will invite three contractors to respond to request for proposals Design team will recommend three contractors to bid Design team will prepare RFP for October 2009 contract award Each contractor will be paid $40,000 for submission of a complete bid package 31 Moncton Watermain Relocation

32 Proposed Project Milestones Proposed Date August 14, 2009 September 1, 2009 September 15, 2009 October 2, 2009 October 5, 2009 October 19, 2009 December 29, 2009 February 5, 2009 February 28, 2009 Milestone Description RFP to Proponents Bidder Meeting and Provision of Information Package Submission of RFP to NBDSS Contract Award Placement of Pipe Order Equipment Mobilization and Commencement of Site Works Commencement of Trenchless and Open Cut Pipe Works Completion of Pipe Installations and Pipe Connections Watermain Commissioning 32 Moncton Watermain Relocation

33 Design Brief To ensure successful on budget and on time project Design Team needed to identify: construction risks and challenges project costs 33 Moncton Watermain Relocation

34 Design Brief Looked at three construction options: 1. A1 Horizontal Directional Drilling (HDD) 40in Steel then slipline with 36in OD HDPE product pipe 30in Ductile Iron as product pipe 2. A2 Horizontal Directional Drilling (HDD) Install two 24in steel casing and slipline with 24in HDPE 3. B Microtunnel 34 Moncton Watermain Relocation

35 Inferred Site Geology Along Conceptual Alignment 10.0m 0 m 100m 200m 300m 400m 500m 600m BH27 BH26 BH25 Sand BH24 BH7 BH23 BH6 BH22 0.0m -10.0m Till Head Pond Fill (Gravel) Silt Silt Sand -20.0m Bedrock Till Sand with gravel -30.0m 35 Moncton Watermain Relocation

36 Option A1 - HDD to -8m Install steel casing: slip line with 762mm(30in) product pipeline BH m Sand 0 m 100m 200m 300m 400m 500m 600m BH6 BH26 BH25 BH24 BH7 BH23 BH22 0.0m -10.0m -20.0m Till Bore reamed to 1321mm (52in) Bedrock Head Pond Fill (Gravel) Silt Silt Till Sand Sand with gravel -30.0m 36 Moncton Watermain Relocation

37 Option A1 - HDD to -8m Install steel casing then slip lined with 762mm(30in) product pipeline Pipe length = approx 530m (1739 feet) Drill entrance angle 17 degrees Drill exit angle 8 degrees Drill exit before drainage ditch Causeway Existing Ditch Headpond Sand Till Very Loose Silt Silty Sand Bore ream to 1321mm (52in) Till Sandstone/Mudstone bedrock Fill Fill Very Loose Silt Sand and Gravel 37 Moncton Watermain Relocation

38 Option A1 - HDD to -8m Install steel casing: slip line with 762mm (30in) product pipe Install 1016mm (40in) steel casing 12.7mm (0.5in) thick in a 1321mm (52in) reamed borepath Required to withstand installation forces Eliminates post construction decontamination issues Estimated required drill rig pipe pullback force: 1505kN (338,500lbs force) with rollers and pipe buoyancy 2962kN (666,000lbs force) with no rollers and pipe buoyancy 38 Moncton Watermain Relocation

39 Option A1 - HDD to -8m 914mm (36in) DR-11 HDPE product pipe 914mm (36in) DR-11 HDPE (PE3408) product pipe approved by AWWA 1103 kpa (160 psi) working pressure - Max test pressure is 1655 kpa (240psi) which meets City design criteria Pipe ID is 738mm(29.06in) with OD =914mm (36in) Diameter less than 762mm (30in) required Pipe price quoted at $305,000 Pipe fusion price quoted at $25,000 Currently new PE4710 (new resin) is not AWWA approved for potable water therefore not considered for this project 60-day lead time required for pipe delivery 39 Moncton Watermain Relocation

40 Option A1 - HDD to -8m 762mm(30in) Ductile Iron Product Pipe 762mm(30in) ductile iron with Flexi-joint as product pipe 1724kPa (250psi)working pressure- max test pressure is greater than 2069kPa (300psi) exceeds design requirements Pipe ID is 785mm(30.9in) with bell joint OD of 937mm(36.9in) Will fit inside 1016mm (40in) steel pipe 85 days lead time required for pipe delivery Pipe cost $452,000CAD ($400,725USD) Corrosion protection and monitoring needs to be addressed in design and construction 40 Moncton Watermain Relocation

41 Option A1 - HDD to -8m Construction Risks Major risk is bore collapse in silty sand on Moncton side Risk can be reduced by: Soil characterization of lower fill Using smallest diameter bore Installation of conductor steel casing Careful selection/monitoring of drill fluids Inadvertent drill fluid release Risk can be reduced by: Monitoring bore drill fluid pressure and drill procedures 41 Moncton Watermain Relocation

42 Option A1 - HDD to -8m Cost Estimate $5 to 6 million Includes pipe materials, drilling, site preparation and pipe installation Does not include open trench pipe construction, concrete valve chambers and connections 42 Moncton Watermain Relocation

43 Option A2 - HDD to -8m Install two 711mm(28in) steel casings Slip line with 610mm(24in) product pipe 10.0m 0.0m -10.0m BH27 0 m 100m 200m 300m 400m 500m 600m Till Sand BH26 BH25 Till -20.0mBore reamed to 1016mm (40in) Bedrock Bore reamed to (40in) BH24 BH7 BH23 BH6 Head Pond Fill (Gravel) Silt Silt BH22 Sand Sand with gravel -30.0m 43 Moncton Watermain Relocation

44 Option A2 - HDD to -8m Install two 711mm(28in) steel casing then slip lined with 610mm(24in) product pipe 1016mm (40in) reamed bore path required Option is not considered feasible as it requires drilling two bores of similar diameter to option A1 610mm (24in) is not significantly less than Option A1 762mm (30in) product pipe Installation of two pipes will require complex connection issues 44 Moncton Watermain Relocation

45 10.0m Drive shaft 0.0m -10.0m Option B - Microtunnel BH27 Reception 0 m 100m 200m 300m 400m shaft 500m 600m Till Sand BH26 BH25 BH24 BH7 BH23 BH6 Head Pond Fill (Gravel) Silt Silt BH22 Sand -20.0m Bedrock Till Sand with gravel -30.0m 45 Moncton Watermain Relocation

46 Option B - Microtunnel Option B requires two shafts 18m (59ft) deep drive shaft on Riverview side at BH21 18m (59ft) deep reception shaft on Moncton side at BH16 Drive distance approx 500m (1640ft) Drive will require at least two internal intermediate jacking stations (IJS) to complete drive 46 Moncton Watermain Relocation

47 Option B - Microtunnel Distance of drive is approaching current laser technology limits Alignment passes through mixed ground conditions Bedrock, till, silty sand and sand/gravel At least 1524mm (60in) boring machine required for person entry and access to machine face Machine diameter limited to contractor availability Person entry/face access requires safety issues 47 Moncton Watermain Relocation

48 Option B Microtunnel Shafts Moncton side shaft design and construction challenging due to: Soft soils and upward gradients Resisting hydrostatic and earth pressures will require robust bracing system Grouting of bedrock required to control hydraulic gradients Need testing and monitoring to determine effectiveness Sheet piles must be driven to bedrock even for shaft base at elevation - 8 to -10m Cost estimate $3.0 to $4.0 million Construction could take several months to complete Risk of major delays due to shaft construction difficulties 48 Moncton Watermain Relocation

49 Option B Microtunnel Risks Mixed face and variable ground conditions Wear on cutters Safety requirements for personnel to access face and remove intermediate jacking stations Limit of laser alignment technology offline and grade will significantly increase jacking force 49 Moncton Watermain Relocation

50 Cost Estimate Shafts Total cost for construction of two shafts $3 to $4 million Pipeline installation $5 to $7 million Function of diameter of machine used and difficult to estimate Total pipeline cost estimate $8 to $11 million 50 Moncton Watermain Relocation

51 Others Considerations Looked at HDD into bedrock as proposed in RFQ Construction will require 30m (98ft) plus shaft at BH-16 Method deemed not constructible due to: Need to construct deep shafts Pumping and operation issues resulting from deep shafts Cost 51 Moncton Watermain Relocation

52 Summary HDD Option A1 Microtunnelling Trenchless Pipeline Construction Cost $5 to 6 million $5 to 7 million Shafts None required Moncton and Riverside $3 to 4 million total Auxiliary construction* $1.2 million $0.8 million Total Cost $6.2 to 7.2 million $8.8 to 11.8 million *Includes: open trench pipe laying, connections, concrete chambers, and site works 2 million project budget needed to be increased 52 Moncton Watermain Relocation

53 Risk and Material HDD Option A1 Microtunnelling Pipeline Installation: Risk of Failure Shafts : Risk of Construction Delay Low-medium in silty sand Low in till and bedrock None Medium to High High Pipe Product Ductile Iron PCCP, Ductile, HDPE Casing 1016mm (40in) steel 1524mm (60in) concrete or steel 53 Moncton Watermain Relocation

54 Design Issues Proposed bridge embankment will induce loads on pipe Embankment loads need to be considered in the pipe design Any minor changes in location of bridge abutment will have direct impact on the watermain design and performance Data from BH 36 indicates coarse rock fill may exist to elevation -11m Geotechnical boring data critical to successful project 54 Moncton Watermain Relocation

55 RFP Three companies selected and requested to bid on RFP $40,000 provided to companies to cover bid costs provided complete bid package submitted Required stamped engineering design drawings Two bids received $6.4 and $7.2 million Michels Canada awarded contract Used detailed bid review scoring system (cost 20 percent) Each design team member reviewed bids independently 55 Moncton Watermain Relocation

56 Construction Bore depth -10m Install casing on Moncton and Riverview Complete an intersect bore using American Augers DD220 Moncton side (pipe entrance) American Augers DD330 Moncton side (pipe entrance) Estimated Max pull back 152,000lbs with buoyancy and 325,000lbs with air in pipe Install 36in HDPE pipe 56

57 Intersect Bore Construction 10.0m 0 m 100m 200m 300m 400m 500m 600m BH27 BH26 BH25 Sand BH24 BH7 BH23 BH6 BH22 0.0m -10.0m Till Head Pond Fill (Gravel) Silt Intersect Point Silt Sand -20.0m Bedrock Till Sand with gravel -30.0m 57

58 58 Construction

59 59 Construction

60 60 Construction

61 61 Push-Pull Ream Construction

62 62 Construction

63 Construction Project completed on time and budget No significant construction issues Geotechnical data was accurate Contractor stated project with best geotechnical data Causeway Gates opened April 14, Moncton Watermain Relocation

64 Lessons Learned Formation of design team was critical Project required to be contractor design build Meet tight construction details Geotechnical data critical for route selection Completion of design review critical to identify critical issues Geotechnical issues Project cost Pipe order and delivery issues Project schedule Trenchless construction requires design by experienced engineers 64 Moncton Watermain Relocation

65 Questions

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY Bryan Thompson, Town of Westport Abhinav Huli, Haley & Aldrich, Inc Lori Carriero, P.E., Tighe & Bond PRESENTATION OUTLINE

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction

More information

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River 3 rd Annual Rocky Mountain Regional No Dig Conference & Exhibition Westminster, CO November 8, 2012 David Bennett,

More information

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TM1-T2-03 Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

WARNING DO NOT BID ON THIS PROJECT

WARNING DO NOT BID ON THIS PROJECT WARNING DO NOT BID ON THIS PROJECT Nick H. Strater, P.G., Associate, Brierley Associates, Bedford, NH Brian C. Dorwart, P.E., P.G., Sr. Consultant, Brierley Associates, Bedford, NH For projects advertised

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 www.norcalpug.com Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 Kathryn Wallin Bennett Trenchless Bo Botteicher Underground Solutions Project Area Existing Sewers 66-inch

More information

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Introduction Purpose Provide engineers and owners

More information

A Trenchless Approach to Lift Station Elimination

A Trenchless Approach to Lift Station Elimination A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

REDUCING RISK AND VISITOR IMPACTS

REDUCING RISK AND VISITOR IMPACTS REDUCING RISK AND VISITOR IMPACTS Trenchless Solutions for Liberty Island Paul J. Mourt, PE Project Rules To Live By 1 Expect the Unexpected Do your homework 2 Risks need to be evaluated on every project

More information

What do you mean we can t do HDD?

What do you mean we can t do HDD? Clark Public Utilities Salmon Creek Crossing What do you mean we can t do HDD? Presented by Matt Hickey, PE Murray, Smith & Associates, Inc. and Russ Knutson, PE Clark Public Utilities Project Team Clark

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Pipe Ramming with HDD. Presentation Outline

Pipe Ramming with HDD. Presentation Outline EXAMINING PIPE RAMMING DESIGN- A FORENSIC ANALYSIS OF A HIGH RISK PROJECT Kimberlie Staheli, Ph.D., P.E. Staheli Trenchless Consultants Seattle, WA, USA Presentation Outline Pipe Ramming State of the Art

More information

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No Hauled Wastewater Receiving Facilities Page 1 Part 1 General 1.1 SECTION INCLUDES.1 Materials and installation for sewage force mains. 1.2 RELATED SECTIONS.1 CW 2110 Watermains and all specifications referenced

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation 8Re: Northern Access 2016 Project Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation Dear Mr. Horey and Mr. Hoover, Mr. Bradden Horey Mr. Brent Hoover P.E. Project

More information

Agenda for Today s Workshop

Agenda for Today s Workshop Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour

More information

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights. Highlights. How to use a Jet Pump? Jet pump for HDD New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters Dr. Marc Peters, Herrenknecht AG Full-Face Hole opener & Downhole Jet

More information

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill Trenchless Technology Planning, Equipment, and Methods Mohammad Najafi Mc Gravu Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto

More information

Take Me to the Other Side:

Take Me to the Other Side: Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional

More information

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995 2013 ASCE Agenda Introduction Difficult Ground Microtunneling in Difficult Ground Craig Camp July 31, 2013 Microtunneling Characteristics (NASTT) Earth pressure balancing Hydrostatic pressure balancing

More information

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing

More information

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations

More information

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject 56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea

More information

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety North American Society for Trenchless Technology (NASTT) NASTT s 216 No-Dig Show Dallas, Texas March 2-24, 216 TA-T5-3 Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic

More information

E-Power Pipe : A new trenchless method for underground cable installation

E-Power Pipe : A new trenchless method for underground cable installation E-Power Pipe : A new trenchless method for underground cable installation Dr. Gerhard Lang Jan 31, 2018 - UCT 2018, Track XI High Voltage Power Grid in Germany. Intention to replace nuclear power plants

More information

Geotechnical Investigations Water Main Construction

Geotechnical Investigations Water Main Construction Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Reyn Hashiro 1, P.E., M. ASCE, Devin Nakayama 2, P.E. M. ASCE, and James Kwong 3, Ph.D., P.E., M. ASCE 1 Associate, Yogi Kwong

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

4. FISH PASSAGE CONCEPTS

4. FISH PASSAGE CONCEPTS Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,

More information

Selecting Watermain Materials for Replacement Projects

Selecting Watermain Materials for Replacement Projects April 28, 2015 Selecting Watermain Materials for Replacement Projects Presenter: Jonathon P. Meyer, P.E. Senior Project Engineer Acknowledgements Central Lake Joint Action Water Agency Village of Oak Lawn

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC Fusible C-900 Fusible C-905 FPVC Installations Trenchless Horizontal directional drilling Sliplining Pipe bursting Jack-and-bore carrier pipe Open-Cut Applications Features and Benefits Gasketless, leak-free,

More information

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY By: Bryan Thompson, Town of Westport, CT Abhinav Huli, Haley & Aldrich, Inc. Lori Carriero, Tighe & Bond Figure 1: Project

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

B701 WATERMAINS- OPSS 701

B701 WATERMAINS- OPSS 701 B701 - OPSS 701 701.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.

More information

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e. No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE SECTION 308 BORING AND JACKING PART 2 MATERIALS 2.2 STEEL CASING PIPE E. Casing pipe length shall conform to City of Meridian Standard Drawing SW1 Casing Length Requirements. 2.4 CARRIER PIPE SKIDS A.

More information

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

B441 - WATERMAINS - OPSS GENERAL

B441 - WATERMAINS - OPSS GENERAL B441 - - OPSS 441 441.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS

LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper A-1-01 LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS Kathryn Wallin 1, Matthew

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Design Data 4. Jacking Concrete Pipe

Design Data 4. Jacking Concrete Pipe Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Multiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line

Multiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line PA AWWA Conference Bethlehem PA May 8, 2014 Multiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line Western Berks Water Authority Bern Township Transmission Main

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga,

More information

The City of Redwood City Completes Trenchless Sewer Installation under Highway 101

The City of Redwood City Completes Trenchless Sewer Installation under Highway 101 The City of Redwood City Completes Trenchless Sewer Installation under Highway 101 By Nick Lazarakis, PE, Kennedy/Jenks Consultants Special Thanks to: James Bowland, PE, Kennedy/Jenks Consultants Brad

More information

CITY OF RICHMOND INVITATION TO TENDER

CITY OF RICHMOND INVITATION TO TENDER CITY OF RICHMOND INVITATION TO TENDER Contract T.2892 Contract: AC Watermain Replacement, Comstock Area The City of Richmond invites tenders for construction work at the above-mentioned locations. Work

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

SECTION TRENCHLESS INSTALLATION

SECTION TRENCHLESS INSTALLATION SECTION 02250 PART 1 GENERAL 1.01 Section Includes A. Trenchless installation of casing pipe. B. Trenchless installation of carrier pipe. C. Open cut installation of casing pipe. 1.02 Description of Work

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded

More information

IPC Company & DPI Presentation. February 2017

IPC Company & DPI Presentation. February 2017 IPC Company & DPI Presentation February 2017 WHO WE ARE OVERVIEW Innovative Pipeline Crossings Inc. (IPC) Founded in 2013, in Calgary Private Company Since July 2016 under new Management Supervisory Board

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.

More information

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT:

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT: AGENDA HEADING: Unfinished Business AGENDA REQUEST COMMISSION MEETING DATE: June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell AGENDA ITEM NO: VI.2. Originating Department SUBJECT: Department

More information

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act. 33 05 23 TRENCHLESS UTILITY INSTALLATION SECTION 1 GENERAL 1.1 SUMMARY A. This specification addresses systems of piping and general requirements for water distribution and sewer collection systems which

More information

DIRECT PIPE AS AN ALTERNATIVE TO HDD, METHOD AND CASE STUDIES

DIRECT PIPE AS AN ALTERNATIVE TO HDD, METHOD AND CASE STUDIES DIRECT PIPE AS AN ALTERNATIVE TO HDD, METHOD AND CASE STUDIES Authors : Presenter : Dr Gerhard Lang, Business Development Manager, Herrenknecht AG Diana Pfeff, Product Manger, Herrenknecht AG Ben Hayes,

More information

Challenges on HDD Pipeline Shore Approach

Challenges on HDD Pipeline Shore Approach OIL & GAS Challenges on HDD Pipeline Shore Approach DNV GL New Recommended Practice Luis D'Angelo - Danilo Machado 02 November 2016 1 SAFER, SMARTER, GREENER Agenda Objectives Why to use HDD in Shore Approach?

More information

YOUR GROUND DRILLING PARTNERS.

YOUR GROUND DRILLING PARTNERS. YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT

More information

Swagelining for Water Transmission & Sewer Force Main Renewal 16 through 65.

Swagelining for Water Transmission & Sewer Force Main Renewal 16 through 65. Swagelining for Water Transmission & Sewer Force Main Renewal 16 through 65 www.murphypipelines.com Murphy Pipelines Services For 2 through 65 Water & Force Main Replacement Trenchless Design Design Build

More information

HDPE Alliance 101 Annual Meeting Features and Cases. Peter Dyke, Murray Sullivan

HDPE Alliance 101 Annual Meeting Features and Cases. Peter Dyke, Murray Sullivan HDPE Alliance 101 Annual Meeting Performance December 6 th 2017 Characteristics, Features and Cases Peter Dyke, Murray Sullivan Jimmy Dang, PE SPECIAL THANKS SPECIAL THANKS Murray Sullivan Alliance Membership

More information

Applicant s Proposed Mitigation Statements Seward Highway 75-90, POA , Turnagain Arm Phase 1 May 2017

Applicant s Proposed Mitigation Statements Seward Highway 75-90, POA , Turnagain Arm Phase 1 May 2017 Applicant s Proposed Mitigation Statements Seward Highway -, POA 2013-448, Turnagain Arm Phase 1 May 2017 Avoidance The project is geographically constrained by Turnagain Arm tidal mudflats on one side

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de

More information

CC1602 Microtunneling

CC1602 Microtunneling CC1602 Microtunneling H.H. Sheikh Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae rachel@ictd.ae Course Introduction: Significant technical advances and increases in the utilization

More information

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared

More information

Deep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control. Glenn Weist, P.E.

Deep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control. Glenn Weist, P.E. Deep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control Glenn Weist, P.E. Columbus, Ohio May 10, 2012 Agenda Background Project Description Regulatory Synopsis Stakeholder

More information

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Earth Boring Co. Limited Trenchless Since 1947 Founded in Streetsville

More information

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected. Microtunnelling Building infrastructures and power supply systems underground, while life above continues unaffected. 2 Comprehensive Microtunnelling Solutions A reliably functioning infrastructure which

More information

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods. Section 02450 PART 1 GENERAL 1.01 SUMMARY A. This Section includes: 1. Installing water line by directional drilling methods. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for water lines installed

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Geotechnical Exploration and Evaluation Report

Geotechnical Exploration and Evaluation Report Geotechnical Exploration and Evaluation Report Nassau Reclaimed Water Main From Radio Avenue to Harts Road Nassau County, Florida CSI Geo Project No.: 71-17-329-04 Client Project No.: JEA 09302-049-01

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

GENERAL NOTES FOR FORCE MAINS: *CONTACTOR SHALL HAVE RICHMOND UTILITIES PERSONNEL ON SITE WHEN DIGGING OVER OR AROUND UTILITY LINES AND PUMP STATIONS. CONTRACTOR SHALL SCHEDULE EXCAVATION WITH RICHMOND

More information

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,

More information

SECTION HORIZONTAL DIRECTIONAL DRILLING

SECTION HORIZONTAL DIRECTIONAL DRILLING SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

Design Data 4M. Jacking Concrete Pipe

Design Data 4M. Jacking Concrete Pipe Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Bernie Ashyk 1, Christopher Lucie, P.E. 2, Jeffrey LeBlanc, P.E. 3 1 Shook Walbridge JV, Project Manager;

More information

For NGTL to file calculation of operating condition on pull back stress analysis.

For NGTL to file calculation of operating condition on pull back stress analysis. NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at

More information

Multiple Large Diameter Microtunnels with Limited Ground Cover

Multiple Large Diameter Microtunnels with Limited Ground Cover North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 Paper No. TM2-T5-04 Multiple Large Diameter Microtunnels with Limited Ground Cover Steve

More information

Pile Driving Issues. Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT

Pile Driving Issues. Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT Pile Driving Issues Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT Goldilocks?? This soil it too hard This soil is too soft This soil is just right! This soil is too hard Prestressed concrete

More information

DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S COMBINED OUTFALL SYSTEM

DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S COMBINED OUTFALL SYSTEM North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S

More information

E&S BMP DESIGN. Working Toward a Better Conclusion

E&S BMP DESIGN. Working Toward a Better Conclusion E&S BMP DESIGN Working Toward a Better Conclusion Are Compost Socks Enough? Compost socks are excellent BMPs when properly used and maintained However, they do have limitations Compost Socks The right

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD North American Society for Trenchless Technology (NASTT) No-Dig Show 2012 Nashville, TN Paper A-2-04 CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD Christopher

More information