concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste

Size: px
Start display at page:

Download "concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste"

Transcription

1 concrete THE MAGAZINE OF THE CONCRETE SOCIETY Volume 51 November 2017 Issue09 Visit: Precast car park The Avenue MSCP, Bracknell Clean water Treating hydro-demolition waste Sustainability by the sea Colwyn Bay seafront

2 Off-site hybrid concrete construction drives the Avenue MSCP, Bracknell The new major town centre redevelopment at Bracknell, Berkshire was under discussion and planning for nearly 20 years before finally opening in September Norman Brown and Scarlett Allan-Stubbs of PCE discuss the design and build of the development s multistorey car park. Known as the Lexicon, the town centre development has been undertaken by the Bracknell Regeneration Partnership, a joint venture between Legal and General, Schroders and Bracknell Forest Council, to provide much-needed extensive shopping, restaurant, entertainment and facilities to surpass the expectations of today s public. A significant part of the development of this next generation of shopping and leisure facilities is the multistorey car park. Called the Avenue Car Park, it remains open 24 hours a day and provides 1306 car parking spaces including specific spaces for disabled and electric-car charging. With an anticipated average parking time of two hours it was essential that a large volume of cars could easily gain access and egress, with the various levels easily accessible, and to give drivers a good parking experience with their safety and security paramount. The tender period for the whole development started just over three years before the Lexicon s opening date, during the middle of 2014, with the award of the main contract in early During this period, PCE worked in co-operation with Mace, developing a hybrid design-and-build solution, principally using off-site engineered precast concrete components, to provide a solution for the five suspended levels car park structure that would also incorporate an area of multi-level retail space at its front. Minimising the height of the structure was a necessary planning requirement and the development s central location meant that maximising the amount of off-site construction would reduce the total number of vehicle deliveries required to enter the centre of Bracknell, as well as a reduction in the number of on-site operatives and management needed to construct the 18 concrete

3 Frame erection in progress using PCE Slingsafe safety method for safe unloading. Millennium Way elevation, including the dominant ramp structures which assist the architectural aspirations with timber cladding and a living green wall. Car park deck ramp interface. Note the curved ends of the ramps commenced inside of the main structure to maximise site usage. Compared to other off-site solutions of similar span, the GT floor units provide a reduced overall floor depth and structural dead load. The finished car park is attractive for users, with its open approach enabled by the long-span design philosophy. concrete 19

4 structural frame. This produces a faster on-site erection period and a reduction in the overall carbon footprint of the project s construction. Mace was awarded the project in February 2015, which resulted in structural design work starting in earnest, with the commencement of off-site production of the precast concrete units in July, thus enabling the erection of the structure to proceed in late November of that year. Critical The use of three-dimensional BIM techniques was critical during the tender period and following the contract award, enabling PCE to develop the car park element of the structure as an efficient precast hybrid concrete solution using its in-house designed-and-developed long-span GT flooring units. The prestressed concrete GT units are designed to meet the required car park structural loading criteria without the need for the casting of any additional on-site reinforced structural concrete over their top surface, which gives a significant reduction in on-site activities and associated disruption, enabling following trades to progress more rapidly. Due to the car park deck being nonrectangular in plan and the development s principal anchor stores, adjacent to either side of the car park, having differing floor levels, all of the decks were required to fall in two directions. In certain areas, this required design development of the GT flooring units to enable them to be splayed, cast with a 25mm fall across their top surfaces and the use of solid GT units to support reinforced concrete cheese wedge -shaped units. The longest unit was 17.8m by 1.5m wide which included a splayed end, while the solid slabs weighed 22 tonnes. In certain areas, having a 25mm fall across the width of the GT unit was insufficient to provide the transitions required, which resulted in the bearing corbels of the supporting beams and walls also having to be stepped. Prior to production commencing, two full-scale mockups were prepared to prove the structural geometry and adequacy of the non-standard GT units and supporting beams. Compared to other off-site solutions of similar span, the GT floor units provide a reduced overall floor depth and structural dead load, which leads to a reduction in height and weight of the supporting precast concrete bearer beams, as well as a more efficient design of other structural frame components. Beams had protection fixed to them prior to being erected and with the tidy deck areas maintained during construction giving enhanced health and safety for off-site construction. The stepped corbel beams to accommodate falls and transitions were evaluated by a full-scale mock-up at the precast factory. 20 concrete

5 Complex ramp geometry showing the one-piece portal beam column arrangement used. Level 3 with high-quality factory brush finish to surface of precast concrete manufactured GT flooring units. The Avenue For the Avenue MSCP, a consistent highquality anti-slip brush finish was required for the surface of the car park floors. This was easily achieved with the GT units due to the high-quality control capabilities of factoryengineered concrete. For the adjoining retail section of shorter and varying spans a hybrid structural solution of precast columns, Delta beams, hollowcore units and in-situ concrete was chosen. Lift cores and the central stair core were formed using flat-pack walls due to the requirement of corbels to pick up the bearing of the adjacent floor units The two side stair cores were framed with precast columns and beams. A further interesting challenge for the PCE team was the design and delivery of the two curved and handed ramps on the external face of the car park adjacent to Bracknell s Millennium Way which form the up and down access between the floors. This ramp structure used precast reinforced concrete goalposts to enable the structural bearing of the precast floor slabs to avoid using separate column and beams. Perimeter beams were a combination of straight and curved in plan which spanned between the goalposts to support the prestressed concrete plate flooring for the straight sections. Normally reinforced concrete curved and sloping plates at the ends of the ramps were cast from moulds integral with those for the curved beams, ensuring accuracy of fit on-site. A reinforced structural topping across the plate flooring was also used. Accurate electronic detailing of the different components and close control of the casting accuracy of all the precast concrete units ensured that the ramps complex geometry was easily achieved. In total, over 3500 precast units were erected during the 40-week on-site programme. During the project, PCE further developed its electronic QA and paperless control systems to ensure that components were manufactured and delivered on a justin-time basis and easily erected to the quality expected and with a high regard to all aspects of health and safety. Nickie Brown, PCE managing director, says, The Avenue multistorey car park at Bracknell is an excellent example of a design-and-build off-site engineered hybrid concrete structure. We were able to use the latest electronic technology and intelligence, including BIM, to design and detail, share data between all the parties involved and provide control systems. All this has enabled the use of structural concrete to be the most viable and efficient construction material choice for this building. Client Architect Consultant engineer Quantity surveyor Main contractor Specialist hybrid structural frame contractor Bracknell Regeneration Partnership Chapman Taylor Arup Aecom Mace PCE concrete 21

INTERNSHIP REPORT GOUTHAM.J

INTERNSHIP REPORT GOUTHAM.J INTERNSHIP REPORT GOUTHAM.J M.E Structural Engineering SNS College of Technology, Coimbatore Mail : tcegoutham@gmail.com TEEMAGE PRECAST IN College Road, 1st Cross Street, Tirupur 641602. TamilNadu, India.

More information

Lattice Plate Flooring

Lattice Plate Flooring Lattice Plate Flooring Introduction Pekso Precast manufacturers and supplies a range of precast concrete structural building products ranging from foundations and flooring systems that includes Lattice

More information

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign

More information

Concrete Framing systems. Design choices. Basic flavors

Concrete Framing systems. Design choices. Basic flavors Concrete Framing systems Design choices Site Cast Concrete gives a designer a lot of freedom in the design and construction of walls, columns and surface textures. When it comes to spanning, concrete offers

More information

PRE-CAST HOUSE CONSTRUCTION

PRE-CAST HOUSE CONSTRUCTION PRE-CAST HOUSE CONSTRUCTION BDA is a Planning and Development Authority Jurisdictional Area is 1370 sq.km. Developed 64 Layouts Distributed 1,40,000 of sites Developed Infrastructure Works like Ring Roads

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014

ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014 ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 (23.885176N, 90.399821E) 08 MARCH 2014 1 2 Observations 3 Highly stressed columns Cursory calculations indicate column at a high working stress.

More information

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural

More information

REPAIR AND STRENGTHENING SPECIALISTS

REPAIR AND STRENGTHENING SPECIALISTS REPAIR AND STRENGTHENING SPECIALISTS SPECIALISED ENGINEERED SOLUTIONS FOR STRUCTURES CCL Qatar WLL PO Box 24396, Al Muthaf Street, Alaqaria Tower, Floor 10, Doha, Qatar T: +974 4458 3998 E: cclqatar@cclint.com

More information

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format Basic Construction of the CANADACAR System The CANADACAR System is a prefabricated, engineered and constructed freestanding parking garage structure that utilizes superior technology combining pre-cast

More information

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS FLOOR SYSTEM ANALYSIS Objective The objective of the following breadth study is to determine if an alternative floor system for Building N would be more advantageous than the existing floor system. The

More information

A-One Polar Ltd. Bhulta,Rupgonj,Narayangonj. ( , ) 27th April 2014

A-One Polar Ltd. Bhulta,Rupgonj,Narayangonj. ( , ) 27th April 2014 1 A-One Polar Ltd Bhulta,Rupgonj,Narayangonj. (23.754782,90545710) 27th April 2014 2 Observations Observations Knitting & Garments building Building 1 1 3 4 Observations Roof structure: no roof bracing

More information

HOLLOW CORE FLOORS SPEED AND STRENGTH

HOLLOW CORE FLOORS SPEED AND STRENGTH HOLLOW CORE FLOORS SPEED AND STRENGTH CONTENTS 2 3 4 5 7 8 9 10 12 13 14 INTRODUCTION PRECAST CONCRETE FLOORS T HE A DVANTAGES BISON HOLLOW CORE FLOORS BEARINGS FALSE CEILINGS AND SOFFIT FIXINGS BISON

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015 Tolerances for Concrete Construction Thomas J Downs P.E., FACI President Forensic Experts Minneapolis, MN What is it? Tolerances for Concrete Construction When did we start this anyway? Who said we needed

More information

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible

More information

Portland HOLLOWCORE. The obvious choice

Portland HOLLOWCORE. The obvious choice Portland HOLLOWCORE Portland The obvious choice Introduction 1 Technical Information 2-3 Decking 4 Walling 5 Staircases 6 Environmental Benefits 7 Advantages 7 Complete precast solution 8 Requirements

More information

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan

More information

Structural Inspection Report

Structural Inspection Report Revision: Issue 2 Date: 23 rd June 2014 Cherry Pvt. Ltd. Florence Fashions Ltd. Ultimate Ltd. Chandand Fashion Ltd. Joy Fashion Ltd. Structural Inspection Report Authors: Adrian Ryan, Cathal Mac an tsearraigh

More information

IMPACT

IMPACT www.strusoft.com Project Project Management Scheduling Erection Planning Erection Simulation Design Production AutoCAD - Revit Precast Cast/Bed Planning Resource Handling Design - Detailing Shop Drawings

More information

BEAM & BLOCK SYSTEM. 108mm. 175mm Deep (160mm) Wide Beam. 160mm

BEAM & BLOCK SYSTEM. 108mm. 175mm Deep (160mm) Wide Beam. 160mm RH F RACKHAM HOUSEFLOORS BEAM & BLOCK SYSTEM BEAM & BLOCK SYSTEM 1. THE BEAMS 60mm 108mm 90mm 75mm 75mm 100mm 175mm 100mm 175mm 125mm 100mm 175mm Deep Beam 175mm Deep (160mm) Wide Beam 225mm Deep Beam

More information

The difference is Guidance for the preparation of Deck Manufacturing Schedules

The difference is Guidance for the preparation of Deck Manufacturing Schedules The difference is Guidance for the preparation of Deck Manufacturing Schedules innovation, commitment, support. 2 Guidance for the preparation of Deck Manufacturing Schedules Minimum Requirements for Schedule

More information

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 2 October 29 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

Spring Hill Suites Marriott

Spring Hill Suites Marriott Spring Hill Suites Marriott Project Location: Amarillo, TX Prepared for: Girder Slab Technologies Contact: Daniel Fisher, Sr. January 15, 2008 Prepared by: Monica Stockmann Regional Engineer: Erika Winters-Downey

More information

Demidec. cornish concrete products Demidec Flooring and Permanent Formwork

Demidec. cornish concrete products Demidec Flooring and Permanent Formwork Demidec cornish concrete products Demidec Flooring and Permanent Formwork Demidec What is Demidec? Demidec is a thin precast concrete plate, typically 60mm deep, although this can vary depending on the

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

Hollowcore Floors. The ideal structural floor solution for all building types in all sectors.

Hollowcore Floors. The ideal structural floor solution for all building types in all sectors. Hollowcore Floors Hollowcore Floors The ideal structural floor solution for all building types in all sectors. 2 3 System Overview Prestressed hollowcore units form part of the comprehensive range of precast

More information

Totaling approximately 617,000

Totaling approximately 617,000 Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street

More information

Chartered Membership Examination

Chartered Membership Examination Chartered Membership Examination 1 Chartered Membership Examination Friday 8 January 2016 Structural Engineering Design and Practice 09.30 13.00 and 13.30 17.00 (Discussion between individuals is not permitted

More information

MassBloc Permeable Instant Wall System

MassBloc Permeable Instant Wall System PIPELINE SYSTEMS 131 004 www.rocla.com.au MassBloc Permeable Instant Wall System PIPELINE SYSTEMS MassBloc Retaining Wall Permanent Retaining Structures The Rocla MassBloc retaining wall system comprises

More information

Wall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel

Wall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel Wall Panels Structural wall panel Architectural wall panel Cladding wall panel Sandwich wall panel Wall Panels Assorted styles and colours Reveals and other patterns Painted finish Bolted, welded and knife

More information

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Christopher McCune Structural Option Eight Tower Bridge Faculty Advisor: Dr. Hanagan October 31 st, 2005 Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Executive Summary This technical

More information

Design of precast concrete structures with regard to accidental loading

Design of precast concrete structures with regard to accidental loading 1 Design of precast concrete structures with regard to accidental loading Ir. Arnold Van Acker Belgium Former chairman fib Commission on Prefabrication 1. INTRODUCTION A structure is normally designed

More information

The designer shall also submit additional information required by the University as described and underlined below.

The designer shall also submit additional information required by the University as described and underlined below. I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design

More information

Invitation to Tender. Reference: IOSVSP4P-Metal

Invitation to Tender. Reference: IOSVSP4P-Metal 1 Invitation to Tender Metal fabrication / installation works at Plot 4, Porthmellon Industrial Estate, St Marys, Isles of Scilly Reference: IOSVSP4P-Metal 1 2 1 Background/Introduction Plot 4 Porthmellon

More information

Concert Halls, Lyric Theatres and Performing Arts Venues

Concert Halls, Lyric Theatres and Performing Arts Venues APPLICATIONS AP-SVI-Concert Halls-13a Acoustic isolation of: CONCERT HALLS Concert Halls, Lyric Theatres and Performing Arts Venues Concert halls are an important and popular part of arts and leisure culture

More information

Apparel Gallery Ltd.

Apparel Gallery Ltd. Apparel Gallery Ltd. 147-148, Norshinghpur, Asulia, Savar, Dhaka (23.929985N,90.304914E) 23 March 2014 1 2 Observations Building 1 Heavy loading due to raised floor area on Ground Floor 3 Building 1 Raised

More information

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Construction of the Superstructure of Major Sea Crossings

Construction of the Superstructure of Major Sea Crossings Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge 2 Second Penang Bridge Donghai Bridge

More information

The Merits of Structural Steelwork

The Merits of Structural Steelwork B309 12pp Final 11/12/02 11:14 AM The Merits of Structural Steelwork Page 2 The Purpose of this Reference Manual The guide, which has been prepared by BCSA, should be used in discussions with clients and

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

Hollowcore. Roof & Floor Systems. Roof & Floor Systems. Commercial Applications

Hollowcore. Roof & Floor Systems. Roof & Floor Systems. Commercial Applications Hollowcore Roof & Floor Systems Roof & Floor Systems Two Rivers Senior Housing Precast columns Precast Inverted Tee Beams Commercial Applications Hollowcore Roof & Floor Systems Wilmar Wastewater Treatment

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 1 October 5 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

Chartered Membership Examination

Chartered Membership Examination The Institution of Structural Engineers Chartered Membership Examination Thursday 3 APRIL 2008 Structural Engineering Design and Practice 9.30a.m. 1p.m. and 1.30 5p.m. (Discussion between individuals is

More information

INFORMATIONAL PACKAGE ACCESSORY RESIDENTIAL BUILDINGS (INCLUDING DETACHED GARAGES, STORAGE BUILDINGS & WORKSHOPS)

INFORMATIONAL PACKAGE ACCESSORY RESIDENTIAL BUILDINGS (INCLUDING DETACHED GARAGES, STORAGE BUILDINGS & WORKSHOPS) 1102 4 th Street Telephone: 306-634-1819 Estevan, Saskatchewan, Canada Fax: 306-636-2199 S4A 0W7 INFORMATIONAL PACKAGE ACCESSORY RESIDENTIAL BUILDINGS (INCLUDING DETACHED GARAGES, STORAGE BUILDINGS & WORKSHOPS)

More information

Fully framed glass panels

Fully framed glass panels Fully framed glass panels design elements G1 Fully framed glass panels G1 design The G1 is a fully framed balustrade solution suiting a refined and deliberate architectural style. Rather than minimising

More information

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung POST-TENSIONING APPLICATION AND TECHNOLOGY Moe Kyaw Aung Overview 1. Background 2. Basic Design Concept 3. Application and Benefits 4. Components of Post-tensioning System 5. Installation Process 6. Construction

More information

DESIGN FOR PROGRESSIVE COLLAPSE 1

DESIGN FOR PROGRESSIVE COLLAPSE 1 Your Partner in Structural Concrete Design TN447_progressive_collapse_110713 DESIGN FOR PROGRESSIVE COLLAPSE 1 Bijan O Aalami 2 This Technical Note outlines the design of column-supported conventionally

More information

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00 Description Page No Summary Amount Summary 1/7 230,694.60 22,019.25 22,642.65 2/6 96,801.30 80,150.60 114,056.00 Total Per Unit (MYR) 327,495.90 102,169.85 136,698.65 Total Unit(s) X 1 2 2 Total Per Type

More information

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE Introduction to Echo Floors The oldest company in the group, established in Gauteng in 1982. The core business is the manufacture

More information

Aluma EasySet Continuing Innovation from Aluma S ystems

Aluma EasySet Continuing Innovation from Aluma S ystems Product Sheet Aluma EasySet Aluma Systems Concrete Construction Aluma EasySet Continuing Innovation from Aluma S ystems Introduction With more than 35 years of experience in shoring and formwork, Aluma

More information

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck)

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck) SECTION 13125 ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck) PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866) TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED

More information

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems University of Nebraska - Lincoln DigitalCommons@University of Nebraska - Lincoln Architectural Engineering -- Dissertations and Student Research Architectural Engineering Spring 4-20-2012 A Composite Structural

More information

Structural Inspection

Structural Inspection General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized

More information

TRANSFER OF THE IMS BUILDING TECHNOLOGY INTO DEVELOPING COUNTRIES

TRANSFER OF THE IMS BUILDING TECHNOLOGY INTO DEVELOPING COUNTRIES TRANSFER OF THE IMS BUILDING TECHNOLOGY INTO DEVELOPING COUNTRIES Radovan Dimitrijevic, Institute for Testing of Materials, Yugoslavia Sladjan Jovancov, Institute for Testing of Materials, Yugoslavia KEY

More information

Strengthening Structures Using Unstressed and Prestressed CFRP Plates

Strengthening Structures Using Unstressed and Prestressed CFRP Plates Strengthening Structures Using Unstressed and Prestressed CFRP Plates Michael Leeming Mouchel Consulting Limited, West Hall, Parvis Road, West Byfleet, Surrey, KT14 6EZ, UK Keywords: Carbon Fibre, Pre-stressing,

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this

More information

PRECAST FLOORING SOLUTIONS. v.4.1

PRECAST FLOORING SOLUTIONS. v.4.1 PRECAST FLOORING SOLUTIONS v.4.1 FPMCCANN.CO.UK Whether you require a small 60m 2 plot or a 10,000m 2 FP McCann is one of the UK s leading manufacturers of high quality precast concrete products. A family

More information

SHELVING, RACKING AND STORAGE CONCEPTS

SHELVING, RACKING AND STORAGE CONCEPTS SHELVING, RACKING AND STORAGE CONCEPTS 1 JULY 2017 FREE GUIDE ABOUT SUPERMARKET SHELVING Supermarket Shelving has been in the second hand shelving and racking Industry for over 30 years and we are able

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Minimising construction waste through project design

Minimising construction waste through project design Case Study: New South Glasgow Hospitals Minimising construction waste through project design Key facts Applying WRAP s Designing out Waste principles to the project design identified 21 areas of potential

More information

Addison LLC Project. Central Business District. City Council and Community Presentation December 6, 2010

Addison LLC Project. Central Business District. City Council and Community Presentation December 6, 2010 Addison LLC Project Central Business District City Council and Community Presentation December 6, 2010 CBD TIF I Original Project Area Established by Ordinance O-17-86 (With Sales Tax District) TIF I:

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

Iconic Twins - Two Pedestrian Bridges Kellyville

Iconic Twins - Two Pedestrian Bridges Kellyville Iconic Twins - Two Pedestrian Bridges Kellyville Ryan S Dewar, Beca Pty Ltd, Australia David J Duffield, The Hills Shire Council, Australia ABSTRACT With the rapid development of Sydney s outer suburbs,

More information

PT Slab Deflections. What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc PTI Annual Conference, Kansas City, MO

PT Slab Deflections. What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc PTI Annual Conference, Kansas City, MO PT Slab Deflections What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc. 2011 PTI Annual Conference, Kansas City, MO May 1, 2011 Types of Buildings Presentation Overview

More information

3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO

3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO 3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO PRINTED PARTS AND THE FABRICATION GAP Facade engineering is a balance of using standard stock shapes when possible and introducing

More information

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette ArcelorMittal Europe - Long Products Sections and Merchant Bars Office Building ArcelorMittal in Esch Alzette Location the country, at the heart of the iron and steel region. It has good access to the

More information

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity System Codes and Criteria Design Codes and Standards The design code used is the Wisconsin Administrative Code along with the State of Wisconsin Department of Commerce-Safety & Buildings Chapters Comm

More information

Session 5: Precast Concrete Floors. Rick Henry Courtesy of University of Auckland, Faculty of Engineering

Session 5: Precast Concrete Floors. Rick Henry Courtesy of University of Auckland, Faculty of Engineering Session 5: Precast Concrete Floors Rick Henry Courtesy of University of Auckland, Faculty of Engineering Background Precast concrete floors widespread in NZ Many advantages with precast units Connections

More information

Detached Garage Construction Information

Detached Garage Construction Information Detached Garage Construction Information In order to issue a building permit for construction of a detached garage, the applicant must submit: Completed development and building permit applications Method

More information

PRECAST FLOORING SOLUTIONS. v.4.0

PRECAST FLOORING SOLUTIONS. v.4.0 PRECAST FLOORING SOLUTIONS v.4.0 FPMCCANN.CO.UK Magherafelt UddingSton Alnwick Lisnaskea ARMAGH Weston Underwood Ellistown Byley Drakelow Telford Wellesbourne Lydney Grantham Littleport London Cadeby FP

More information

CHAPTER 3: Modern Methods of Construction (MMC)

CHAPTER 3: Modern Methods of Construction (MMC) CONTENTS 3.1.1 INTRODUCTION 3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS 3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC) 3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS 3.1.5 INSULATED CONCRETE

More information

AISC Steel & Timber Research for High-Rise Residential Buildings

AISC Steel & Timber Research for High-Rise Residential Buildings AISC Steel & Timber Research for High-Rise Residential Buildings Final Report December 4 th, 2017 SOM Designed Benchmark Concrete Building Skidmore, Owings, and Merrill, LLP 2017 224s Michigan Avenue Suite

More information

Sabah Shawkat Cabinet of Structural Engineering 2017

Sabah Shawkat Cabinet of Structural Engineering 2017 3.1-1 Continuous beams Every building, whether it is large or small, must have a structural system capable of carrying all kinds of loads - vertical, horizontal, temperature, etc. In principle, the entire

More information

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series SUMMARY David Samuelson Steel joists are growing in recognition as being a very economical

More information

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC. 320-226.5189 www.101developmentresources.com While every attempt has been made to insure the correctness of this handout, no guarantees are made to its accuracy

More information

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

Speedlock Pallet Racking

Speedlock Pallet Racking Assembly specification These instructions are to assemble Dexion Speedlock Pallet Racking which conforms with the specifications below. Frame heights not more than 4800mm Frame depths 840mm Not less than

More information

September Saddle Flooring Systems

September Saddle Flooring Systems September 2011 Saddle Flooring Systems Saddle Flooring Systems Saddle System Principles CMS Danskin Saddle Flooring Systems are dry floating floors which provide an easily levelled understructure for supporting

More information

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

More information

The Aizhai Suspension Bridge is

The Aizhai Suspension Bridge is INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing

More information

A. The extent of extruded aluminum walkway covers is shown on the Drawings and as specified herein.

A. The extent of extruded aluminum walkway covers is shown on the Drawings and as specified herein. SECTION 10530 - EXTRUDED ALUMINUM WALKWAY COVERS PART I - GENERAL.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General, Supplementary, and Special Conditions and Division

More information

How to fill in your Timber Frame Order Form

How to fill in your Timber Frame Order Form How to fill in your Timber Frame Order Form 1 General Would you like us to check slab or design the building to Architects drawings? Check Slab: Is the Slab in place already, if so has your architect checked

More information

Arup. FinnforestMerk. Plaza Mayor in Seville with the Metropol Parasol

Arup. FinnforestMerk. Plaza Mayor in Seville with the Metropol Parasol Arup FinnforestMerk Plaza Mayor in Seville with the Metropol Parasol Metropol Parasol Digital Timber Design The redevelopment of the Plaza de la Encarnación and the design of the unique free formed timber

More information

AASHTOWare BrD 6.8. BrR and BrD Tutorial. PS7-3 Stem PS Bridge Example

AASHTOWare BrD 6.8. BrR and BrD Tutorial. PS7-3 Stem PS Bridge Example AASHTOWare BrD 6.8 BrR and BrD Tutorial PS7-3 Stem PS Bridge Example BrR and BrD Training PS7 3 Stem PS Bridge Example From the Bridge Explorer create a new bridge and enter the following description data.

More information

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 The General Trade Knowledge examination will be administered in one session

More information

Structural Assessment Live Fire Training Building. FSCJ South Campus Jacksonville, Florida. Florida State College at Jacksonville

Structural Assessment Live Fire Training Building. FSCJ South Campus Jacksonville, Florida. Florida State College at Jacksonville Structural Assessment Live Fire Training Building FSCJ South Campus Jacksonville, Florida Florida State College at Jacksonville November 21, 2011 Report of a Structural Assessment of Live Fire Training

More information

WORKPLACE SAFETY AND HEALTH PRACTICES AWARD 2011

WORKPLACE SAFETY AND HEALTH PRACTICES AWARD 2011 WORKPLACE SAFETY AND HEALTH PRACTICES AWARD 2011 Silent Black Balls (SB2) COMPANY INTRODUCTION In Singapore, we act as the main contractor in construction projects for both private and public sectors Over

More information

Cracks in Industrial Concrete Floors

Cracks in Industrial Concrete Floors Cracks in Industrial Concrete Floors This Flooring Technical Note considers the types of cracks specific to concrete industrial floors and the typical causes of non-structural cracks. It does not look

More information

SCREW PILE APPLICATION SHEETS

SCREW PILE APPLICATION SHEETS SCREW PILE APPLICATION SHEETS Advantages of screw piles Exceptionally fast installation rate up to 2... linear metres of pile installed per minute Load bearing capacities of over 300kN SWL Load bearing

More information

Carpenter Level 2 Rev. September 2017

Carpenter Level 2 Rev. September 2017 Level 2 A5 Site Layout II Duration: 14 hours 7 hours 7 hours Upon completion of this unit the apprentice will demonstrate knowledge of site layout tools and equipment and their applications and procedures

More information

Eric Alwine Structural Option George Read Hall The University of Delaware Dr. Boothby Technical Assignment #2 October 31, 2005 EXECUTIVE SUMMARY:

Eric Alwine Structural Option George Read Hall The University of Delaware Dr. Boothby Technical Assignment #2 October 31, 2005 EXECUTIVE SUMMARY: EXECUTIVE SUMMARY: THIS REPORT IS A COMPARISON OF ALTERNATE FLOOR SYSTEMS FOR GEORGE READ HALL. FOUR DIFFERENT SYSTEMS WERE DESIGNED AND COMPARED TO THE EXISTING HAMBRO FLOOR SYSTEM. THE FOUR SYSTEMS WERE

More information

The Design of St. Vincent s University Hospital Redevelopment, Dublin, Ireland - Inception to Completion - Cultural Differences in Hospital Design

The Design of St. Vincent s University Hospital Redevelopment, Dublin, Ireland - Inception to Completion - Cultural Differences in Hospital Design The Design of St. Vincent s University Hospital Redevelopment, Dublin, Ireland - Inception to Completion - Cultural Differences in Hospital Design Wednesday, 10 September 2008, 10:30 Presenter Donal Blake

More information

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E.

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E. The courthouse exterior. Courtesy of NLA/HLM Architects. United States Courthouse Sacramento, Robert D. McCartney, S.E. CA Modern Steel Construction / November 2001 Public entrances to courtrooms occur

More information

PERFECT SLABS Bernie de Klerk

PERFECT SLABS  Bernie de Klerk PERFECT SLABS www.perfectslabs.co.za perfectslabs@gmail.com Bernie de Klerk 071 622 99 33 WHAT ARE PRE-STRESSED HOLLOW CORE SLABS? Hollow core slabs are pre-stressed panels constructed with hollow cores

More information