SHOTCRETE DESIGN FOR IRRIGATION CANAL LINING

Size: px
Start display at page:

Download "SHOTCRETE DESIGN FOR IRRIGATION CANAL LINING"

Transcription

1 SHOTCRETE DESIGN FOR IRRIGATION CANAL LINING Syed Hasan 1, Gunvant Vaghela 2, James Yip 3, Ben Chung 4 ABSTRACT: The major artery of Lake Wyangan irrigation system is the 16km long Lake View Branch Canal (LVBC) which was installed mainly in The 75mm thick reinforced concrete lining is currently in a poor condition with significant water loss through seepage and needs replacement as part of Lake Wyangan Modernisation project. The main factors to be considered in the selection of a lining type include durability, seepage loss, construction cost and time, and maintenance cost. For irrigation canals, the use of concrete (cast in place or precast) with or without reinforcement is the most common practice of canal lining. A shotcrete lining (unreinforced or fibre reinforced) is uncommon for irrigation canals and there has been limited (if any) documentation of its recent usage in Australia. A trial comprising approximately 27m long prototype (with fibre reinforced and unreinforced) shotcrete lining of different joint configurations constructed on ground having similar properties to the LVBC was undertaken. On the basis of the trial result together with cost and performance, unreinforced shotcrete lining with transverse and longitudinal control joints was selected as the preferred canal lining option for un-obstructed flow of water without excessive seepage. This paper provides details of the LVBC renewal, including a literature review of irrigation canal lining, the development of design and the validation process. KEYWORDS: Shotcrete, Prototype model, Fibre-reinforced, Unreinforced. 1 INTRODUCTION Lake Wyangan Modernisation project (a key component of Murrumbidgee Irrigation s Modernisation Program) involves the replacement of the ageing concrete lined irrigation channel system with a modern and efficient water delivery system to service around 200 land holdings in Lake Wyangan catchment. The Australian Government is providing funding of $50 million for this project as part of the Private Irrigation Infrastructure Operators Program in NSW. An Alliance, MIA Renewal Alliance, comprising Murrumbidgee Irrigation Limited, GHD, UGL Infrastructure and John Holland Group was set up to plan, design and construct the modernisation project. The 16km long Lake View Branch Canal (LVBC) was built mainly in The existing 75mm thick reinforced concrete canal [1] is at the end of its design life and is being refurbished as follows: Canal bank lining is being demolished and replaced with 85mm thick unreinforced shotcrete lining. Majority of the canal is being widened to increase its capacity. Canal bed lining will be retained where lining condition is good, otherwise the bed will be upgraded by overlaying 75mm thick unreinforced concrete. 2 CURRENT PRACTICES OF LINING CONSTRUCTION A limited literature review of canal linings has indicated the following: Most concrete linings installed in older channels in the United States were reinforced. Recently, to reduce construction cost, reinforcement has been omitted wherever possible. (Stevenson, 1999) has reported that it is generally better to use unreinforced concrete [2]. Reinforcement cannot be justified, except under unusual conditions such as high back pressure, high flow velocities and where movement of the subgrade is a possibility. Unreinforced concrete linings are more susceptible to damage by 1 Syed Hasan, GHD Pty Ltd, Sydney. syed.hasan@ghd.com 2 Gunvant Vaghela, GHD Pty Ltd, Sydney. gunvant.veghela@ghd.com 3 James Yip, GHD Pty Ltd, Sydney. james.yip@ghd.com 4 Ben Chung, GHD Pty Ltd, Sydney. ben.chung@ghd.com

2 hydrostatic pressure and subgrade movement, however this is more than offset by the difference in cost when compared to a reinforced lining. Unreinforced concrete fractures more readily than reinforced concrete, thus relieving the pressure and reducing the area of damage. Steel reinforcement, controls crack widths however it complicates construction and will lead to deterioration associated with corrosion. A recent option for reinforcement in concrete involves the addition of fibre reinforcement, synthetic or steel fibres (approximately 20-40mm long) [2]. A successful concrete lined channel must be durable and remain substantially watertight to give many years of low-maintenance service life. The success of a concrete liner is highly dependent on its installation and materials used. [2]. Concrete, cast in place or pre-cast, with or without reinforcement is a common type of lining for irrigation canals. The disadvantages of this type of lining are its relative high cost, the long period of time required for its installation and its lack of capability to adjust itself to differential settlement of the underlying soil [3]. A nominal weldmesh reinforcing layer in canal lining has proved to be of assistance in keeping maintenance and repair costs to a minimum by distributing stresses caused by temperature effects and other minor operational loading. For this reason it is usual practice in the Department of Water Affairs, South Africa [4] to place this reinforcement. However, there are certain cases where an unreinforced concrete lining is both preferable and acceptable. Construction joints, placed transversely across the canal at about 3m intervals, are convenient for hand-lining in which alternate slabs are cast sequentially thereby limiting tensile stress development. Corps practice [5], prior to the 1960 s, was to utilise concrete pavement with expansion and contraction joints for paved trapezoidal channels. The experience with these channels shows that substantial joint maintenance is required. When concrete paving is used for trapezoidal channels in soils, it should be continuously reinforced concrete pavement (CRCP) [5] [It must be noted that these channels are designed for vehicular traffic, hence the use of the term pavement ]. Unreinforced shotcrete is considered suitable for applications where there are no applied loads, or when, tension is not applied to the shotcrete material [6]. Channels, reservoirs and spillways can be constructed by excavating the required shape and shotcreting directly freeform onto the exposed rock or earth. Shotcrete has the ability to be placed, compacted and finished (possibly in one pass) in cases requiring high access, freeform or very thick linings. Some examples include the Olympic Whitewater Stadium Channel in Sydney and Shannon Creek Dam Spillway in Grafton NSW [6]. Unreinforced shotcrete canal lining was used in North Unit Canal, USA with excellent condition after 10 years of service [7]. 3 DESIGN OF CANAL LINING 3.1 DESIGN CRITERIA The criteria used in the design of canal lining are as follows: Convey the required flow (as defined by the hydraulic analysis, this requires an increase in the available waterway area); Be constructible and suitable for construction within the window available at the winter shutdown; Substantially water tight but not required to be a water retaining structure; Prevent erosion and dispersion of the soil behind the canal lining; Retain the existing canal bed where the condition of the existing bed allows this; Level of durability sufficient to achieve design life of 80 years (with maintenance as required); and Not to be designed for equipment or traffic loading 3.2 DESIGN DEVELOPMENT OF CANAL LINING MATERIAL The main factors considered in the selection of canal lining material include; durability for 80 years design life, seepage loss, maintenance cost, construction cost

3 and time (for construction during winter shutdown periods). The lining materials considered during detailed design stage are covered below Reinforced concrete lining cast-in-situ or precast The existing lining design of approximately 75mm thick reinforced concrete was reviewed and discounted on the basis of inadequate cover to the reinforcement to comply with current design standards. A conventionally reinforced concrete lining would need to be in the order of 140mm thick to provide longevity and robustness. However, it will result in a substantially higher cost than unreinforced lining. For this reason reinforced concrete cast-in-situ or precast lining was not considered to offer value for money Fibre-reinforced shotcrete Fibre reinforced shotcrete has higher capital cost and greater difficulty in construction in comparison with unreinforced shotcrete. Two types of fibre reinforcement were considered in this project: steel and synthetic (polypropylene) fibres. Steel fibres can assist with the long term control of drying shrinkage cracking by providing resistance to widening of cracks. To achieve this, sufficiently high dosage of steel fibres will be required, with the following implications: Cons: significant capital cost, and difficulty in achieving homogeneity and finishing of the shotcrete; and Pros: provide an added degree of tensile strength and larger contraction joint centres could be achieved. Synthetic fibres provide no material benefit for long term drying shrinkage, but can assist in the reduction of plastic cracking (cracking while the shotcrete is in a fresh state) and slumping during construction Unreinforced shocrete/concrete lining Unreinforced shotcrete/concrete lining requires contraction joints at close intervals to reduce the risk of crack development from drying shrinkage, temperature and moisture variation. A panel length of 3m was selected to match the typical existing panel joints of 6m spacing Selection of canal lining material On the basis of cost, durability and performance of prototype trial test panel s unreinforced shotcrete/concrete lining with transverse control joints at 3m spacing and expansion joints at 30m spacing was selected. 3.3 DETAILED DESIGN OF UNREINFORCED CANAL LINING During the detailed design of the unreinforced canal lining, comprising a shotcrete bank and a concrete bed, the following design considerations were taken into account : Hydrostatic uplift pressures The results of the geotechnical investigation have indicated that the canal is predominantly underlain by low permeability clay material. On this basis, groundwater inflow beneath the canal lining is unlikely to develop damaging uplift pressure when the canal is empty, and as such, no treatment has been specified. At localised areas of the canal where high ground water and sandy soil are encountered, weep holes and flap valves are proposed to allow drainage of the subgrade to minimise the effect of hydrostatic uplift Shrinkage and temperature effect To prevent cracking of unreinforced lining due to shrinkage and temperature effects, transverse contraction joints are designed at 3m spacing. The short panel length will minimise any cracking and enable easy replacement of panel in the event of further cracking or breaking. Transverse expansion joints at 30m spacing are also provided. Rearguard waterstops under contraction and expansion joints are required to mitigate seepage losses Reactive soil movement Due to the presence of medium to high plasticity clay along the canal alignment, an average 50mm of foundation movement is expected normal to the canal lining [8]. Such movement is expected to occur predominantly in the upper soil strata. A finite element model using STRAND-7 software was used to analyse the effect of soil heave on unreinforced panels. Heave effects in the transverse direction is expected to occur at the top of the bank with the potential to lead to the canal lining panels being unsupported. The structural analysis carried out has indicated that the resulting lifting is likely to lead to longitudinal stresses and cracking in the unreinforced lining. Therefore a longitudinal control joint at the mid height of the panel was introduced to allow the panel to articulate with the movement in the upper soil profile. A longitudinal joint at the junction of the canal base and bank was also provided to allow further articulation in the event of soil movement.

4 Furthermore, to limit direct infiltration and evaporation behind the lining, a bitumen coated geofabric is incorporated behind the crest of the bank extending 500mm back from the shotcrete lining Durability According to AS3735 the exposure classification of canal water is B2. The 80 year design life calls for a 85mm thick unreinforced S40 shotcrete lining, which includes15mm sacrificial thickness as an allowance for surface erosion Joint detailing Joint details were developed in consultation with MIA Renewal Alliance taking into consideration the design requirements. The canal bank subgrade would be covered with geofabric (Bidim A29) before placing shotcrete in order to reduce the risk of fine material loss through the lining cracks. The types of joints used in the canal lining are covered below: Transverse contraction joints Transverse joints are provided in the shotcrete lining for shrinkage and temperature movement in the longitudinal direction. Bending due to heave effect along the canal is negligible for joint spacing of 3.0m. Cold jointed 3m wide shotcrete panels are constructed with a hit and miss fashion and application of bond breaker at the cold joints thereby removing the need for a saw cut or crack initiator. A rear-guard waterstop is provided to mitigate against seepage loss. Sika the supplier of the nominated waterstop confirmed that the waterstop will accommodate the calculated joint movement. Joint sealant was not selected due to its lower design life, requiring maintenance and periodic replacement. Transverse expansion joints With the provision of expansion joints at 30m spacing thermal expansion is estimated as 6mm and short term (7 days after curing) shrinkage movement as 2mm. Therefore net movement of expansion joint is estimated to be approximately 4mm. The proposed 10mm wide expansion joint is capable of accommodating this movement. Similar to the transverse contraction joints, a rear-guard waterstop is provided without any joint sealant. Longitudinal joints Longitudinal joints are required to cater for bending of the lining resulting from reactive soil movement, covered in Section A longitudinal control joint is provided at the mid-level of the bank shotcrete lining to allow articulation of the panels in the event of foundation movement. Rear-guard waterstop is provided under longitudinal control joints. A 3mm wide wet formed tooled joint (D/3 depth) is provided to initiate cracking at the joint, where D is the thickness of shotcrete lining. Longitudinal joints in base slab The effect of foundation movement can extend to the junction between the base and bank of the canal causing rotation of the lining. A longitudinal joint is therefore provided at the base of the canal, 200mm away from the junction to mitigate the risk of an uncontrolled crack. A 3mm wide wet formed tooled joint and a rear-guard waterstop are provided. Details at top of bank The shotcrete at the top of the bank is provided with a 100mm return to avoid hanging up the shotcrete during placement. This will mitigate the formation of horizontal cracks at the top of bank as the fresh shotcrete naturally seeks to move down-slope. 4 TRIAL AND POST DESIGN VALIDATION In order to validate the performance of the lining design, a trial was carried out in April Approximately 27m long prototype canal, comprising nine panels was constructed in ground having similar properties to the LVBC. The panels were either fibre reinforced or unreinforced shotcrete. The performance of the lining was reviewed and the following observations were made: Addition of fibre in the shotcrete did not result in an improved performance when compared with the unreinforced panels. More time was required to clean the pump and hoses for fibre reinforced shotcrete. Shotcreting alternative panels controls thickness as edge forms act as thickness guides. Between the shotcrete panels, crack widths up to 1.5mm were observed. The cracks did not follow the cold joint due to bonding between adjacent panels as no bond breaker was applied during trail test. 5 CONCLUSION The trial test result validated the canal lining design and assisted in fine tuning the design to achieve better service performance. A 85mm thick unreinforced shotcrete lining with transverse contraction joints at 3m c/c and expansion

5 joints at 30m c/c was selected on the basis of cost, trial test and performance. The construction of the canal lining commenced in May 2013 with all the works scheduled to be completed by August Two winter shutdown periods will be required to complete the upgrading work. Photograph 1 to 4 shows the construction work of canal lining. Photograph 4: Concrete pouring on canal bed Photograph 1: Preparation for shotcrete application Photograph 5: Completed lining showing joints ACKNOWLEDGEMENT Photograph 2: Application of shotcrete to canal bank The author would like to acknowledge the contributions made by the entire Alliance Team. The innovations that are outlined in this paper are a direct result of successful Alliancing relationships. The author would also like to acknowledge Murrumbidgee Irrigation Limited, and the Department of Environment, Commonwealth of Australia for their approval to present this paper. REFERENCES Photograph 3: Roller finish to bank shotcrete panel [1] Canal Condition Assessment Lake View Branch; Report by GHD, 20 July, [2] e.html. [3] andardsandguidelines/canal%20lining.htm. [4] Guidelines for the design of canals and related structures; Department of Water Affairs, Forestry and Environmental Conservation, Pretoria, Republic of South Africa.

6 [5] Structural Design of Concrete Lined Flood Control Channels; US Army Corps of Engineers Department of the Army, EM , 30 April, [6] Recommended Practice Shotcreting in Australia; Prepared by Australian Shotcrete Society for the Concrete Institute of Australia, 2 nd Edition, September, [7] Canal lining demonstration project year 10 durability report; US Department of the Interior, Bureau of Reclamation, November, [8] LVBC Lining Uplift and Reactive Ground Movement; GHD Geotechnical Memorandum, 21/20216/187610, 05 February, 2013.

Prof. B.S. Thandaveswara. The various types of linings can be grouped into two categories: (i) Exposed and Hard

Prof. B.S. Thandaveswara. The various types of linings can be grouped into two categories: (i) Exposed and Hard Types of Linings The various types of s can be grouped into two categories: (i) Exposed and Hard Surface Linings, and (ii) Buried Membrane Linings. The advantages and disadvantages of various types of

More information

Control of Random Cracking in Concrete Residential Pavements

Control of Random Cracking in Concrete Residential Pavements Control of Random Cracking in Concrete Residential Pavements Eric Lume (National Engineer, SRIA) and Mark Turner (Chairman, Committee BD-098 Pavements) Abstract: AS 3727.1 Pavements Part 1: Residential

More information

SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS

SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS VOLUME 1 THE SPECIFICATION FOR HIGHWAY WORKS SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS Contents Clause Title Page 1100 (02/17) General 2 #1101 Precast Concrete

More information

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority SYNOPSIS In recent years, there has been heightened concern over the performance of half joints

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Mr. Paul Dunlap, California Department of Water Resources

Mr. Paul Dunlap, California Department of Water Resources Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction

More information

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM 6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, 23 25 October 2012 THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM Peter BUCHANAN Principal Dams Engineer, Bulk Water

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

DEPARTMENT OF THE ARMY EM U.S. Army Corps of Engineers CECW-ED Washington, DC

DEPARTMENT OF THE ARMY EM U.S. Army Corps of Engineers CECW-ED Washington, DC DEPARTMENT OF THE ARMY EM 1110-2-2007 U.S. Army Corps of Engineers CECW-ED Washington, DC 20314-1000 Manual No. 1110-2-2007 30 April 1995 Engineering and Design STRUCTURAL DESIGN OF CONCRETE LINED FLOOD

More information

Performance Floors for Warehouses and Distribution Centres. Kevin Dare, Managing Director, Face Consultants Ltd.

Performance Floors for Warehouses and Distribution Centres. Kevin Dare, Managing Director, Face Consultants Ltd. Performance Floors for Warehouses and Distribution Centres Kevin Dare, Managing Director, Face Consultants Ltd. Performance Floors for Warehouses and Distribution Centres. Kevin Dare, Face Consultants

More information

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Ö. Özen, H. Küsmez, A. Akman Dam and Tunnel Projects Director, İLCİ Holding & TR COLD Member, Ankara, Turkey

More information

Design of Rigid Pavements

Design of Rigid Pavements Traffic and Highway Engineering (ІІ) CVL 4324 Chapter 20 Design of Rigid Pavements Dr. Sari Abusharar Assistant Professor Civil Engineering Department Faculty of Applied Engineering and Urban Planning

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

General Information for Joints

General Information for Joints Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-1 General Information for Joints A. General Information The need for a jointing system in concrete pavements results from the desire

More information

Tile on Existing. Viewpoint

Tile on Existing. Viewpoint Viewpoint Tile on Existing Exterior Reinforced Concrete BalconieS By Steven C. Turner Exterior reinforced concrete balconies are often covered by tile set in mortar beds with grouted joints. These installations

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3 CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3

More information

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks CONSTRUCTION PROCEDURES AWWA D110 Type I Prestressed Concrete Tanks 2-3 4-5 6-7 8-9 10-11 12-13 14-15 16-17 Site Preparation Floor & Footings Wall Construction Roof Options Vertical Prestressing Abrasive

More information

PRODUCT DATA SHEET SikaProof Bentonite

PRODUCT DATA SHEET SikaProof Bentonite PRODUCT DATA SHEET NATURAL SODIUM BENTONITE BELOW GROUND WATERPROOFING SYSTEM (ONLY TO BE APPLIED BY A SIKA APPROVED CONTRACTOR) PRODUCT DESCRIPTION SikaProof Bentonite is a needle punched thermally locked

More information

Reinforced Concrete. S.Sreenath 17 May 2016

Reinforced Concrete. S.Sreenath 17 May 2016 Reinforced Concrete S.Sreenath 17 May 2016 Curing of Concrete Hardening of concrete is dependent on the presence of water. During mixing normally more water for full hydration. It is always necessary to

More information

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015 1 Overview: The purpose of Standard Bridge Drawing, AS-2-15, is to address details of approach slabs not previously addressed in the AS-1-81 Standard Bridge Drawing. Specifically, the drawing was initiated

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

MASONRY DETAILING SCHOOL OF ARCHITECTURE AND PLANNING: MIT. Shelf Angles. Image by MIT OCW.

MASONRY DETAILING SCHOOL OF ARCHITECTURE AND PLANNING: MIT. Shelf Angles. Image by MIT OCW. Shelf Angles Image by MIT OCW. Flashing Single Wythe Walls Image by MIT OCW. Flashing with Shear Transfer Image by MIT OCW. Flashing Reinforced Wall Image by MIT OCW. End Dams Flashing Laps 6 Drainage

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information

3/5/2014. Disclaimer and Waiver of Liability. Learning Objectives. Portland Cement Association

3/5/2014. Disclaimer and Waiver of Liability. Learning Objectives. Portland Cement Association Disclaimer and Waiver of Liability W-52 Concrete Surface Defects: Causes, Prevention, and Cure. Michelle L. Wilson, FACI Director, Education Portland Cement Association www.cement.org Wednesday, March

More information

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course. SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721

More information

MNDOT PAVEMENT DESIGN MANUAL

MNDOT PAVEMENT DESIGN MANUAL MNDOT PAVEMENT DESIGN MANUAL Chapter 9 truction and Rehabilitation Alternates MnDOT Pavement Engineer Date Contents Introduction... 1 900 Existing Pavement-Types... 2 910 Rehabilitation with HMA Overlay

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two. Design Manual Chapter 6 - Geotechnical 6C - Pavement Systems 6C-1 Pavement Systems A. General Information This section addresses the importance of pavement foundations and the potential for pavement problems

More information

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc. 1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement

More information

Integral Waterproofing

Integral Waterproofing BCBEC Luncheon June 14, 2012 Integral Waterproofing Presented by Joel Schwartz, P.Eng, FEC, BEP Background Case study of two large high-rise projects at False Creek in Vancouver, BC Case Study 1: Site

More information

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year.

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year. ICC-ES Evaluation Report ESR-1959 Issued July 1, 2011 This report is subject to renewal in one year. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council DIVISION:

More information

Maintaining your roads with Asphalt

Maintaining your roads with Asphalt Maintaining your roads with Asphalt Maintaining your roads with Asphalt Asphalt Overlays Rehabilitation of Concrete Roads Asphalt for Preventive Maintenance Asphalt Overlays Functional overlays Typically

More information

Table of Contents. July

Table of Contents. July Table of Contents 36.1 General... 3 36.1.1 Bridge or Culvert... 3 36.1.2 Box Culvert Size Restrictions... 4 36.1.3 Stage Construction for Box Culverts... 4 36.2 Dead Loads and Earth Pressure... 5 36.3

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

THE PERFORMANCE OF CONCRETE GROUND FLOOR SLAB REINFORCEMENT TO CONTROL SHRINKAGE CRACKING. D H Chisholm 1

THE PERFORMANCE OF CONCRETE GROUND FLOOR SLAB REINFORCEMENT TO CONTROL SHRINKAGE CRACKING. D H Chisholm 1 THE PERFORMANCE OF CONCRETE GROUND FLOOR SLAB REINFORCEMENT TO CONTROL SHRINKAGE CRACKING D H Chisholm 1 ABSTRACT In a typical residential concrete floor slab, the cast in strip footings on the slab perimeter

More information

Reinforced concrete slot channel

Reinforced concrete slot channel Applicable Bodies of Rules: DIN EN 1433»Drainage channels for vehicular and pedestrian areas«din 19580»Drainage channels for vehicular and pedestrian areas«the following laying instructions are general

More information

Pavement reinforcement

Pavement reinforcement Pavement reinforcement Reducing fatigue cracking 2 Innovative solutions for asphalt and unbound pavements and soft ground stabilisation Whether constructing a gravel forestry track over soft soil or resurfacing

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair

Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair Memorandum Number MERL 2011-34 Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair Missouri River Basin Project Solomon Division Glen Elder Unit - Kansas

More information

SECTION 1. AS MASONRY STRUCTURES CODE

SECTION 1. AS MASONRY STRUCTURES CODE mortarless masonry Design Manual Part 1 (AS 3700:2011) Section 1 Page: 1 SECTION 1. AS 3700 - MASONRY STRUCTURES CODE AS 3700:2011 Masonry structures is the current Australian standard for the design of

More information

PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE. Abstract

PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE. Abstract PERFORMANCE OF SOIL-CEMENT PLATING IN THE TEXAS PANHANDLE By: D.N. Clute, P.E.; M.S. Garsjo, P.E.; K.R. Worster, P.E. National Design, Construction, and Soil Mechanics Center, USDA-NRCS, Fort Worth, Texas

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures Journal of Civil Engineering and Architecture 9 (2015) 213-224 doi: 10.17265/1934-7359/2015.02.010 D DAVID PUBLISHING Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation,

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

prospec.com Concrete Repair & Restoration

prospec.com Concrete Repair & Restoration prospec.com Concrete Repair & Restoration Table of Contents Product Portfolio 3 Product Enhancements 4 Product Selection Matrices 5 Construction Grout & Precast Non-shrink grouts C-1107 Construction Grout

More information

ENGINEERING DIRECTIVE

ENGINEERING DIRECTIVE Number: E-95-001 Date: 2/2/95 ENGINEERING DIRECTIVE Ross B. Dindio (Signature on Original) CHIEF ENGINEER The purpose of this engineering directive is to formally notify ALL Department engineering personnel

More information

Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL

Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL Design and Construction Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL View of the Folsom Dam and the canyon just upstream of construction. The area

More information

Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway

Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway Michael D. McDonagh, P.E., P.Eng., WSP Parsons Brinckerhoff Andrew J. Foden, Ph.D., P.E., WSP Parsons Brinckerhoff

More information

ALL-IN-ONE THERMAL FLOOR SYSTEM NON STRUCTURAL TOPPING (NST)

ALL-IN-ONE THERMAL FLOOR SYSTEM NON STRUCTURAL TOPPING (NST) ALL-IN-ONE THERMAL FLOOR SYSTEM NON STRUCTURAL TOPPING (NST) Jablite All-in-One Thermal Floor System Non Structural Topping (NST) is an innovation-update on the patented Jablite All-in-One Thermal Floor

More information

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems Anchorplex retaining wall construction guide Building Anchorplex Retaining Wall Systems Table of Contents and ow to Use This Guide table of contents ow to Use This Guide. 2 About the Anchorplex System.

More information

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE September 1, 2003 CONCRETE MANUAL 5-694.800 5-694.810 GENERAL SPECIAL TYPES OF CONCRETE 5-694.800 In the general use of the word concrete, the idea implied is the conventional placement of the material

More information

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds Section 8: Amended Soil Mounds 8. Amended Soil Mounds 8. Amended Soil Mounds 8.1 Design...95 8.2 Installation...96 8.3 Inspection...101 8.4 Operation...101 8.5 Common technical issues...105 8.6 Case study...105

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams by James K. Mitchell, Sc.D., P.E., Dist. M.ASCE University of Alberta, Edmonton, Alberta October 6, 2010 1 SCOPE OF THE LECTURE

More information

STUCCO FAILURES and REMEDIATION Roger G. Morse AIA

STUCCO FAILURES and REMEDIATION Roger G. Morse AIA STUCCO FAILURES and REMEDIATION Roger G. Morse AIA Morse Zehnter Associates Rensselaer Technology Park 165 Jordan Road Troy, NY 12180 rgmorse@mzaconsulting.com Florida Environment Hot Humid High ground

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

GlasGrid Asphalt Pavement Reinforcement. October 21, 2016

GlasGrid Asphalt Pavement Reinforcement. October 21, 2016 GlasGrid Asphalt Pavement Reinforcement October 21, 2016 Introduction to Cracks Crack sources are numerous and varied Cracks are consistent pavements aren t Solutions for cracks have had mixed results

More information

Waterproofing Products for UNDERGROUND STRUCTURES

Waterproofing Products for UNDERGROUND STRUCTURES Waterproofing Products for Underground structures level: the parts of a building which are most often in contact with water and aggressive elements in the ground. All structures below ground level come

More information

Civil Engineering Construction Chapter 5

Civil Engineering Construction Chapter 5 Civil Engineering Construction Chapter 5 Introduction to Floor Dr Mohamad Syazli Fathi Department of Civil Engineering UTM RAZAK School of Engineering & Advanced Technology UTM International Campus August

More information

CONCRETE BLOCK PAVING FOR STEEP SLOPES Technical Note

CONCRETE BLOCK PAVING FOR STEEP SLOPES Technical Note CONCRETE BLOCK PAVING FOR STEEP SLOPES Technical Note CONSTRUCTION OF STEEP SLOPES The construction of roads on steep slopes poses particularly interesting challenges for road engineers. The horizontal

More information

Pavement Crack Treatment

Pavement Crack Treatment Pavement Crack Treatment Crack treatment overview. Why and when to treat cracks. Evaluating pavement and selecting product. Proper application and equipment. Pavement Crack Treatment Crack treatment overview.

More information

MOA Project # Golden View Drive Intersection & Safety Upgrades

MOA Project # Golden View Drive Intersection & Safety Upgrades Appropriate transitions can include extending the insulation beyond the roadway improvements, reducing the insulation thickness, or angling the insulation downward. Use of a frost tolerant section, an

More information

SigmaJoint. The Ultimate Joint J. Armouring & Load Transfer Systems. Metallic Leave-In-Place Contraction & Day Joints for INDUSTRIAL CONCRETE FLOORS

SigmaJoint. The Ultimate Joint J. Armouring & Load Transfer Systems. Metallic Leave-In-Place Contraction & Day Joints for INDUSTRIAL CONCRETE FLOORS SigmaJoint Metallic Leave-In-Place Contraction & Day Joints for INDUSTRIAL CONCRETE FLOORS TYPE - D TYPE - O The Ultimate Joint J Armouring & Load Transfer Systems SigmaJoint Introduction Joints are unavoidable

More information

Concrete Impregnated Fabric UK CHAMBER AWARDS MADE IN UK Knowledge Transfer Network NATIONAL WINNER

Concrete Impregnated Fabric UK CHAMBER AWARDS MADE IN UK Knowledge Transfer Network NATIONAL WINNER 13.06.UK MADE IN UK ROAD RAIL AGRO POWER PETROCHEM MINING DESIGN OTHER CHAMBER AWARDS 20 11 NATIONAL WINNER Knowledge Transfer Network Modern Built Environment MOST INNOVATIVE PRODUCT AT WORLD OF CONCRETE

More information

FINAL REPORT EVALUATION OF HYDRAULIC CEMENT CONCRETE OVERLAYS PLACED ON THREE PAVEMENTS IN VIRGINIA. Michael M. Sprinkel, P.E.

FINAL REPORT EVALUATION OF HYDRAULIC CEMENT CONCRETE OVERLAYS PLACED ON THREE PAVEMENTS IN VIRGINIA. Michael M. Sprinkel, P.E. FINAL REPORT EVALUATION OF HYDRAULIC CEMENT CONCRETE OVERLAYS PLACED ON THREE PAVEMENTS IN VIRGINIA Michael M. Sprinkel, P.E. Research Manager Celik Ozyildirim, Ph.D. Principal Research Scientist (The

More information

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE Karsten Beckhaus (1), Martin Larisch (2), Habib Alehossein (3,4) (1) BAUER Spezialtiefbau GmbH, Deutschland (2) Keller Australia Pty Ltd, Australia (3)

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams BIA Summer Water Resources Training Dam Safety Inspections Part 4 - Inspections July 28, 2012 Presented by Michael Johnson, Ph.D., P.E. Types of Inspections Periodic Inspections A comprehensive visual

More information

Providing proper drainage system

Providing proper drainage system Environment Friendly and Cost Effective Alternative to Conventional Graded Filters Providing proper drainage system for structures such as earth retaining structures, pavements, water front structures,

More information

Deck Joints and Bearings

Deck Joints and Bearings Deck Joints Deck Joints and Purpose is to: bridge the gap between spans protect the ends of the girders allow for expansion, contraction and rotational movement prevent water and salt from leakage Most

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects 2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD

More information

The New York City Transit (NYCT) Metropolitan

The New York City Transit (NYCT) Metropolitan Layers in New York City Overhead Tunnels By Frank E. Townsend III The New York City Transit (NYCT) Metropolitan Transportation Authority Capital Construction (MTACC) has several largescale projects throughout

More information

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS PERMEABLE PAVEMENTS (SUDS) This leaflet highlights the basic requirements for laying Ibstock clay pavers to form a permeable pavement. Ibstock clay pavers are intended for domestic use only i.e. patios

More information

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION The selection of a wall type and appropriate connection details is one of the most important

More information

New innovative technique for strengthening old buttress dams and multiple arch dams

New innovative technique for strengthening old buttress dams and multiple arch dams New innovative technique for strengthening old buttress dams and multiple arch dams Thomas Konow Consultant engineer Dam safety E-mail: thomas.konow@gmail.com ABSTRACT: This article presents a new method

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

SPECIFICATION FOR ENGINEERED FILLS

SPECIFICATION FOR ENGINEERED FILLS SPECIFICATION FOR ENGINEERED FILLS This specification is intended to be used for the engineered fill. The specification is suitable for most purposes but there may be special conditions existing at some

More information

Proudly Made in the U.S.A.

Proudly Made in the U.S.A. 5-Year Warranty Proudly Made in the U.S.A. Cast-In-Place (wet-set) 2 Cast-In-Place (wet-set) Tactile Proudly Made in the U.S.A. In stock colors White 37875 Brick Red 20109 Yellow 33538 Blue 15187 Safety

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Bozena Czarnecki, Ph.D., P.Eng., Principal Specialist, Engineering Practice, Tetra Tech Canada Inc. Barry Poon, P.Eng., The City of Calgary

Bozena Czarnecki, Ph.D., P.Eng., Principal Specialist, Engineering Practice, Tetra Tech Canada Inc. Barry Poon, P.Eng., The City of Calgary Concrete Sidewalk Design Analysis and Optimization for Improved Life Cycle and Sustainability Bozena Czarnecki, Ph.D., P.Eng., Principal Specialist, Engineering Practice, Tetra Tech Canada Inc. Barry Poon,

More information

Evaluation of Premature PCC Pavement Longitudinal Cracking in Colorado

Evaluation of Premature PCC Pavement Longitudinal Cracking in Colorado Evaluation of Premature PCC Pavement Longitudinal Cracking in Colorado Ahmad Ardani, Shamshad Hussain, and Robert LaForce Colorado Department of Transportation 4201 East Arkansas Avenue Denver, CO 80222

More information

Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007

Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007 Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007 Case Study Public Lands Project Objectives, Design and Performance Construct a green carpool

More information

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231. DRIVEWAYS, DRIVEWAYS & PATIOS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - CHARACTERISTICS CSA A231.2 TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min. Absorption - 5 % max. Freeze-thaw

More information

K_`j `e]fidxk`fe `j Yifl^_k kf pfl Yp Fncj?Xcc <em`ifed\ekxc nfib`e^ `e gxike\ij_`g n`k_ BcXi^\jk\i gif[lzkj% '/+, *., (/'(

K_`j `e]fidxk`fe `j Yifl^_k kf pfl Yp Fncj?Xcc <em`ifed\ekxc nfib`e^ `e gxike\ij_`g n`k_ BcXi^\jk\i gif[lzkj% '/+, *., (/'( Excellent Treatment PD0064, Issue 1 INSTALLATION INSTRUCTIONS FOR N3 to N5 NITRIFICATION BIODISCS Introduction PD0064, Issue 1 Klargester BioDiscs are manufactured in Glass Fibre Reinforced Polyester (GRP).

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

Solving Slope Protection Problems Geoweb Cellular Confinement System

Solving Slope Protection Problems Geoweb Cellular Confinement System Solving Slope Protection Problems Geoweb Cellular Confinement System Leaders In Advanced Geotechnology TM Slope Protection An Engineered Framework for Slope Protection The Presto Geoweb Cellular Confinement

More information

VERTI-BLOCK - DESIGN MANUAL

VERTI-BLOCK - DESIGN MANUAL Company Information General Information Verti-Block is the latest innovative forming system from Verti-Crete, LLC. Recognized worldwide for outstanding aesthetics and performance, Verti-Crete s proprietary

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

Sealing strips for concrete construction joints STOPO TYPE 3 catalog

Sealing strips for concrete construction joints STOPO TYPE 3 catalog 2017-07-26 1 Sealing strips for concrete construction joints STOPO TYPE 3 catalog WARNING: please always refer to the latest versions of these documents as published on our web site up to date. INFO@STOPO.CA

More information