1 Wind without borders a unique solution to Indian Scenario V.Balaji CM, SRLDC POSOCO M.Venkateshan Sr. Engr., SRLDC POSOCO P.Bhaskara Rao AGM, SRLDC POSOCO P.R.Raghuram GM, SRLDC POSOCO Abstract Dwindling reserves of coal and oil and mandate of Intergovernmental Panel on Climate Change and National Action Plan for Climate Change, Wind and other Renewable energy sources are to be harnessed to the fullest extent. However, Variability, Intermittency and Uncertainty of these renewable resources have been the biggest challenges in Integration of wind energy the world over. These intrinsic characteristics pose problems to system operators as they have to scramble for providing spinning reserves and vary the generation levels to their technical limits. As the penetration levels of these green sources increase, there is a need for enhancing the levels of reserves which is a luxury for a country facing severe deficits. The compulsions of system operation calls for treating these sources like any other generator as far as planning and accountability is concerned. The Regulators have offered various methods to fulfill the Renewable Purchase Obligation (RPO) either physically (across the Control Area seams) or virtually by procuring Renewable Energy Certificates (RECs). Exposing wind generation to power market across the regions may enhance the commercial viability of the wind projects. However, this is a challenge to the Regulators, planners and grid operators alike. Building an optimum transmission network, designing a suitable market pricing/commercial mechanism, implementation of robust settlement system etc. are some of the key areas for success of this objective. In this paper, the authors examine the issues facing the physical movement of wind power across seams, the commercial settlement aspects, the need for forecasting and scheduling and how surmounting such issues could help renewables participate dynamically in the power market. 1. Introduction Wind generation potential is limited to a few states (Control Areas) in India. The installed capacity of wind generators has witnessed steep growth in India since the middle of the last decade. The South-western parts of Tamilnadu, Central/North Karnataka, Maharashtra, Gujarat and Rajasthan have major pockets of wind generation. From May onwards, wind generation increases and help meet the summer demand. Monsoon periods of July to September produce maximum generation which tapers down upon receding of monsoon from October. Fig.1 shows typical (seasonal) variation patterns of wind production in Tamilnadu. In other states also similar pattern can be seen. Similarly Fig.2 shows typical generation on a maximum wind day. Fig. 3 gives an idea how wind varied from ~ 1000 MW to 70 MW in a typical day. Page 1 of 9
2 Seasonal pattern of Wind generation in TN for 2011 July June-11 September August May-11 MW 1050 January-11 December-11 October-11 November March-11 Apr March-11 February Hours January-11 February-11 March-11 Apr-11 May-11 June-11 July-11 August-11 September-11 October-11 November-11 December-11 Fig. 1 Typical (seasonal) patterns of wind production in TN over the year. In other states also similar pattern can be seen. Fig 2 Maximum wind day in TN (Max wind day: Tamilnadu 11/07/ Mu generated, 26.4% of total state consumption, max: 3770 MW, min 1925MW (35% of demand met by hrs) Variation of Wind in a typical day in TN on MW :00:00 00:37:00 01:14:00 01:51:00 02:28:00 03:05:00 03:42:00 04:19:00 04:56:00 05:33:00 06:10:00 06:47:00 07:24:00 08:01:00 08:38:00 09:15:00 09:52:00 10:29:00 11:06:00 11:43:00 12:20:00 12:57:00 13:34:00 14:11:00 14:48:00 15:25:00 16:02:00 16:39:00 17:16:00 17:53:00 18:30:00 19:07:00 19:44:00 20:21:00 20:58:00 21:35:00 22:12:00 22:49:00 23:26:00 Time Fig.3 Wind variation in a typical day. 08/07/2010 Page 2 of 9
3 Such large variations in renewable power, (in the absence of sufficient commercially viable reserves), may lead to huge load shedding or overdrawls from the Regional grid. In case of overdrawls, there will be not only a huge financial implication on heavy Unscheduled Interchanges (UI) charges but also threat to the security of the grid. 2.0 Problems in Sub transmission system : Traditionally, the transmission/ sub-transmission system in the areas of wind pockets witness low voltages due to low short circuit levels and generally high requirement of Reactive power by the Wind Turbine generators (WTG). Therefore, the power losses also are generally on the higher side in this system. Commercial recovery of these losses is a major issue for the State utility. Further due to low capacity Factor, there is a tendency to under-build the transmission system. These factors call for huge investment in evacuating transmission system. Huge financial implication and uncertainty in recovery of the investment could be some of the factors impeding investment in the evacuation of system. Right of way is also an issue in these areas. As the wind generators are located in areas with considerable vegetation, the connecting lines upto the pooling stations are prone to earth faults created by low clearances etc. Any large scale trippings of Wind Turbines in large Wind farms has the potential danger of cascading to disturbances in the sub transmission system. Therefore it essential that the wind mills have the ability to stay connected to the grid during voltage dips caused by short-circuit one or all phase of its terminal current upto a specified voltage level. This capability is called Fault Ride Through (FRT) /Low Voltage ride-through (LVRT). Therefore, it is better if regulatory provisions mandate enforcement of these capabilities. 3.0 Efforts of Regulators and policy makers Since the introduction of imbalance pricing mechanism with introduction of Availability Based Tariff in 2003 and Open access in Inter-State and intra-state transmission system in 2004 formal Power Market is established in India. After reforms by way of Electricity Act2003, unbundling of state electricity boards in phases and introduction of power Exchange platform in 2008 way was paved for strengthening the Power Market in a big way. It got matured under the regulatory supervision of the Central Commission and active participation from the Captive Power Plants, Independent Power Plants, bulk consumers, Extra High Tension consumers and state generators and power procurement utilities. 3.1 Measures already implemented : All the regulators have facilitated sale of power from all the Renewable Energy generators at a preferential tariff or Feed In Tariff (FIT) which ensures a cost-plus return on investment to the developer. Solar power is exempted from sharing transmission charges and losses. Further to bring grid parity, solar power is bundled with unallocated share of the state owned National Thermal Power Corporation and given to the host state, so that the average cost of solar power would come down to an affordable level. Page 3 of 9
4 With a view to give fillip to these generators, the Central Government had given sops like Accelerated Depreciation (AD), Generation Based Incentive (GBI) etc. The Regulators on their part had implemented Renewable Energy Certificate (REC) In the REC mechanism, each State utility is obligated to fulfill Renewable Purchase Obligation (RPO) as specified by its Regulators by purchasing either Renewable Energy directly or equivalent Certificates (RECs) as an indirect means of supporting the Renewable Energy generators. The price of these certificates are discovered in a national platform of the Power Exchanges. Fig. 4 shows the modus operandi of REC Under this mechanism, the RE generator can opt for selling the energy part of the power to host State at a Weighted Average Power Purchase cost specified by the concerned SERC and sell the RE Certificates at rates discovered in the Power exchange platform. Alternately, the power can be sold to a third party at any mutually negotiated price, and sell the RECs in power exchange. Accreditation of RE by State Agency RE Generator to Apply for Registration of RE Apply for REC By RE generator Generation of Power Confirmation of Generation by Apply for REC By RE generator Issue of REC Central Agency. Fig. 4 Modus operandi of REC Redeeming of REC in Px The REC mechanism received enthusiastic response from all the stake holders. Since the implementation, over 6,70,000 RECs were issued out of which over 6,09,000 were redeemed involving a trade amount of over Rs.1650 millions. 3.2 Measures under implementation stage : To enable the concerned Control Area to plan the reserves and load-generation balance, Forecasting and Scheduling of Grid connected wind and Solar generators is envisaged under Indian Electricity Grid Code. The same is expected to be implemented shortly. Eligible generators would be required to forecast their generation with a minimum accuracy of + 30%. Any deviation upto + 30% will not have any cost implication to the Renewable Energy generator. The RE generator can enter in to contract to supply power to any entity located any where in the country under Short Term Open Access at a price negotiated bilaterally. Such power will be scheduled by the concerned SLDC/ RLDCs and can be revised based on the Forecasted generation data, to minimize the impact of Unscheduled Interchanges from Regional Grid. Through this scheme, the wind generator is made accountable to forecast the production. The cost of Unscheduled Interchange by the host State due to this variation would be reimbursed from/to a nationally operated Fund called Renewable Regulatory Fund (RRF) which is operated by National Load Despatch Centre (NLDC). The burden of the Fund is expected to be socialized among all the States in the country. Page 4 of 9
5 4.0 International Experience : A study of European countries shows that, in most of the countries, though a matured Electricity Market is in place, in most of the countries the wind generators sell power under Feed-In-Tariff, which ensures a minimum guarantee price to the developer. The wind generator is generally not penalized for the imbalances, except in Belgium, Denmark, Spain, Sweden Netherlands, UK and Poland. In such cases, they are compensated with Green Certificates, which can be sold to the obligated entities in the market. In France they even participate in Auctions or spot markets also. In all these countries, they have to invariably forecast and schedule the generation with Gate closure time varying from ½hour to 24 hours. Table 1 summarizes the above. Fig 6 gives a glimpse of Venn diagram of countries following various incentive schemes. Table 1 International practices w.r.t incentives to Wind (Source: Wind Generation in Day-Ahead Energy Markets in Italy: Imbalances Penalties - C. Brunetto, M. Nicita and G. Tina, Member, IEEE powertech07/papers/297.pdf) All US Power Pools like MISO, NYISO, CAISO, PJM and ERCOT use forecasting of Wind. In Europe RTE, France, Canada and Brazil also have Wind Forecasting capabilities. In Spain, a dedicated control centre for Renewables is operational for forecasting, scheduling, assessing the reliability of the grid under various scenarios. Page 5 of 9
6 Fig 6 Venn diagram of countries following various incentive schemes. (AT- Austria, CY-Cyprus CZ-Checkoslovakia, DK, Denmark, EE- Estonia, ES-Spain, Fr-France, BG- Bulgaria, DE-Germany, GR-Greece, HU-Hungary, IE-Ireland, LT- Lithuania, LU-Luxemberg, PT-Portugal, NL-Netherland, SI- Slovania, SK-Slovakia, BE- Belgium, SE-Sweden, PL-Poland, FI-Finland, MT-Malta, IT-Italy, LA-Laos) 5.0 Unique Solution to Indian scenario : Although, in the states with high wind potential, the control area-wise the maximum penetration is about 30-40%, on an all India basis, it is only 3-5%. Therefore, problems of intermittency and variability can be better handled on an All India basis. As the penetration levels are increasing, the problems of host state brought by variability, uncertainty etc. also increase exponentially. Therefore, the Renewable Energy generator has to be made more accountable for the deviations and there is a need to treat him like any other type of generator yet giving due consideration to the variability aspect. Commercial responsibility for variations beyond a certain limit as specified by the regulator shall rest with the RE generator. This calls for Forecasting and scheduling the wind generation. A good short term wind forecast is a pre-requisite for successful market participation by wind generator. The forecast can facilitate the RE generator to reduce the adverse impact of deviations. It will also help the system operator to assess the Reliability and carry out operational planning. With a slew of incentives enumerated in the preceding paragraphs, the wind generators have enhanced the prospects of higher returns and in turn are encouraged to enter the power market which enhance their profitability. With market entry of the Renewable Energy generator will enable physical transport of wind power across the seams, so that the burden on the host state reduces. Further, in a larger grid issues related to wind integration can be Page 6 of 9
7 alleviated to a considerable extent. It is expected to induce a sense of accountability, enhance the profitability and viability of projects, attract investment, address grid parity issues. However, for a successful market participation, a strong backbone of transmission network free of congestion is a pre-requisite. Though the regulators are trying to facilitate trade across the boundaries, it is not happening due to lack of dedicated evacuation system. As can be seen in Fig. 7, the wind packets in the rural Western part of the country should get robust connectivity to the load centres spread around the major cities and industrial hubs. It is a known fact that sources of generation like Coal, Nuclear fuel, Oil etc can be transported to wherever generating stations are located. Whereas Renewable sources like wind, solar, micro hydro etc can not be transported. This calls for building of strong transmission network for evacuation. It is prudent to provide pooling stations and transmission network near to these areas with high potential after assessing the expected capacity addition. SOURCES OF RESOURCES HYDRO RESOURCES RESOURCES ARE FAR AWAY FROM LOAD CENTERS. NECESSITATES LONG TRANSMISSION LINKS FOR EVACUATION DELHI Source: Powerline (Siemens Ad), Oct-2006 KOLKATTA MUMBAI COAL BELT BANGALORE CHENNAI AREAS SHOWN ARE APPROXIMATE AND INDICATIVE Fig 7 Wind potential pockets vis-a-vis of Load centres 6.0 Building an evacuation a challenge Traditionally there has been a time lag in building wind projects vis-à-vis matching evacuation system due to multiple reasons range from such as concerns of optimal utilization of transmission network by a generating system with low Capacity utilization factor, lack of funds; uncertainty of project realization etc. Often the cost of transmission is recovered based on the energy transmitted in terms of per unit rates.. Due to low Capacity utilization Factor, the recovery is at a very low rate on a long periods, thus there could be some amount of reluctance to develop transmission/sub-transmission system. Page 7 of 9
8 Under these circumstances, not only generation potential may get stranded up, but also congestion may occur in the downstream network. Therefore there is an urgent need of providing a dedicated corridor for export of wind generation to outside the region. But the question is who will pay for the evacuation system and how to recover the investment within a reasonable time period; how to ensure capacity utilization in the lean seasons. It is required to understand that gestation periods for developing a wind farm is between 6-8 months, whereas that for evacuating transmission system is over 2 years. This may result in bottling up for wind potential. To avoid this, Plug and Play concept of infrastructure may be thought off on similar lines as Special Economic Zones (SEZs) for boosting the trade. In this concept, all necessary infrastructure like distribution network, pooling stations, augmentation/addition of substations and transmission both within the State/Region and across the inter-regional borders may be readily built so that RE generators will be able to erect a farm and connect to grid without any time lag. It is preferable to have some common agency to execute the evacuation system in a coordinated manner. 7.0 Harnessing the Reactive compensation available in WTG mill. Inherently, all the WTG are provided with Capacitive compensation to avoid penalties for reactive power drawl from the grid. During low wind seasons, such pockets of the grid generally witness low voltages and low short circuit levels. During such periods, the capacitive compensation can be utilized to supply reactive power to the grid. A suitable monetary compensation mechanism can be thought of under ancillary services concept. Conclusion : As the penetration of wind energy increases in the Indian grid, participation of wind generators in the market will help alleviate the problems of integration. It is opined that the wind generator has to adopt the mantra of Predict-Plan-Participate as a means to address for the challenges brought in Integration of Renewable to Grid. The congestion issues in wind evacuation in the sub transmission system are to be solved and a strong backbone of Inter-Regional corridor is to be provided for enabling a seamless trade across the Inter- Regional Borders. The wind generators have to participate in the scheduling and RRF mechanism mandated by the Central Regulator. Acknowledgement: Authors acknowledge the support given by Power System Operation Corporation Ltd. (POSOCO) to publish this paper. The views expressed in the article are that of the authors and not necessarily that of POSOCO. References : 1. CERC((Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, CERC (Indian Electricity Grid Code) Regulations, NLDC Procedure for implementation of the mechanism of Renewable Regulatory Fund 4. CERC(Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, Page 8 of 9
9 5. CIGRE 293 report of Working Group C1.3 on Electric Power System Planning with the Uncertainty of Wind generation April High capacity power transmission corridor - project inception report of Power Grid Corporation of India Limited 7. Wind Generation in Day-Ahead Energy Markets in Italy: Imbalances Penalties - C. Brunetto, M. Nicita and G. Tina, Member, IEEE powertech07/papers/297.pdf) Biography:- P.R.Raghuram is presently working as General Manager at SRLDC and is responsible for operation of the power system grid in Southern Region and for maintaining its safety and security. He has done his graduation in Electronics and Communications Engineering in 1978 from Malnad College of Engineering. He is a senior member of IEEE. His interests are Power system Economics and Protection P.Bhaskara Rao is presently working as Additional General Manager and is in-charge of Commercial & Contracts activities at SRLDC. He has done his graduation in Electrical Engineering in 1975 from JNTU Engineering College, Anantpur followed by M.Tech. in Power Systems Engineering from IIT, Kharagpur. He worked in Jyothi R&D Centre for two years and in Central Electricity Authority upto His fields of interest are Power System Engineering, operational and real time studies, and commercial aspects of Grid Management. V.Balaji is presently working as Chief Manager at SRLDC and is responsible for the commercial functions related to Regional Energy computations, operation of various pool accounts, Open Access, transmission pricing, integration of Renewables, and Regulatory affairs and Legal matters. He has done his graduation in Electrical & Electronics Engineering in 1986 from JNTU College of Engineering, Kakinada followed by M.Tech. in Power Systems from REC, Warangal. His field of interests are Reactive Power Compensation and Power System Economics, Tariff matters, Regulatory affairs, Power Market economics etc. M.Venkateshan is presently working as Senior Engineer at SRLDC and is responsible for the Operational Services function, development and maintenance of various programs like Web Scheduling, MIS etc. He has done his graduation in Electrical & Electronics Engineering in 2002 from BMS Evening College of Engineering, Bangalore. He earlier worked in operation of Chamera Hydro Electric Project of National Hydro Power Corporation. His field of interest are Power System Operation, SCADA and IT. Page 9 of 9
Core projects and scientific studies as background for the NREAPs. 9th Inter-Parliamentary Meeting on Renewable Energy and Energy Efficiency
Core projects and scientific studies as background for the NREAPs 9th Inter-Parliamentary Meeting on Renewable Energy and Energy Efficiency Brussels, 18.11.2009 Mario Ragwitz Fraunhofer Institute Systems
More informationEuropean Commission. Communication on Support Schemes for electricity from renewable energy sources
European Commission Communication on Support Schemes for electricity from renewable energy sources External Costs of energy and their internalisation in Europe Beatriz Yordi DG Energy and Transport External
More informationANNUAL PUBLICATION: detailed data. VOLUME OF EXPORTS FELL BY 4,7 PER CENT IN 2015 Export prices rose 0,7 per cent. 24 March 2016
ANNUAL PUBLICATION: detailed data 2 March 216 VOLUME OF EXPORTS FELL BY,7 PER CENT IN 21 Export prices rose,7 per cent According to Finnish Customs preliminary data, the value of Finland s goods exports
More informationWelcome to Presentation on Integration of RES to the WR grid. 02 nd Sept, 2015 Taj Lands End, Mumbai
Welcome to Presentation on Integration of RES to the WR grid 02 nd Sept, 2015 Taj Lands End, Mumbai Todays Topic Injection of Renewable power on a large scale and its effect on the stability of the grid
More informationCENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE
CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario
More informationMaking the Parcel Regulation work. 17th Königswinter Postal Seminar 5-7 February
Making the Parcel Regulation work 17th Königswinter Postal Seminar 5-7 February 2018 1 A lot going on. 2 Not just a parcel More A journey 3 AT DE DK FI FR IE LU NL SE CY EL ES IT MT PT BG HR HU
More informationEU 2020 Targets: Managing integration of wind in the Hungarian grid. Tari Gábor CEO. Wind Energy the Facts Tari G. 12 June 2009 Workshop,
EU 2020 Targets: Managing integration of wind in the Hungarian grid Tari Gábor CEO Wind Energy the Facts Workshop, 12.06.2009 Contents 2 Hungarian Electric Power System the facts Generation mix Consumption
More informationWind Energy The Facts
Wind Energy The Facts Bruce Douglas Chief Operating Officer European Wind Energy Association Riga 22 May 2009 WHAT IS THE EUROPEAN WIND ENERGY ASSOCIATION? EWEA is the voice of the wind industry, actively
More informationThe Renewable Energy Directive the role of National Renewable Energy Action Plans in reaching the 2020 targets
The Renewable Energy Directive the role of National Renewable Energy Action Plans in reaching the 2020 targets EUROPEAN COMMISSION Wind Energy the Facts Integrating wind power in Hungary, EWEA workshop
More informationFarm structures. This document does not necessarily represent the official views of the European Commission
Farm structures Content 1. EU farms - characteristics and trends... 3 Physical farm size... 4 Economic farm size... 8 Declining farm numbers... 11 Organisational structure... 13 Land ownership... 14 Farm
More informationEurope s water in figures
Europe s water in figures An overview of the European drinking water and waste water sectors 2017 edition EurEau The European Federation of National Water Services Introduction EurEau is pleased to present
More informationERGP (14) 24 report on QoS and end-user satisfaction ERGP REPORT 2014 ON THE QUALITY OF SERVICE AND END-USER SATISFACTION
ERGP REPORT 2014 ON THE QUALITY OF SERVICE AND END-USER SATISFACTION 1 Content Page 0. Executive summary 10 1. Background 14 2. Objectives 15 3. Methodology 16 4. Current situation regarding quality of
More informationMarket Mechanisms in India s Clean Energy Efforts
Market Mechanisms in India s Clean Energy Efforts Renewable Energy Certificate Mechanism Balawant Joshi Director, ABPS Infrastructure Advisory Pvt. Ltd. ABPS Infrastructure Advisory Advisory Pvt. Ltd October,
More informationPrepared for: IGD 2014
Prepared for: What is this presentation s aim and what is covered? What is the aim of the presentation? This presentation is to provide an overview of the largest European retail alliances in 04, their
More informationFlexibility in Indian Power System
www.nsgm.gov.in Flexibility in Indian Power System Atul Bali, NSGM-PMU, INDIA Indian Power Sector Overview Installed Capacity 329 GW Thermal: 66.7% Hydro: 13.5% Nuclear: 2.1% Renewables: 17.7% Peak Demand
More informationenergy in figures Energy
EU energy in figures Statistical pocketbook 2015 Energy This publication does not involve the European Commission in liability of any kind. Europe Direct is a service to help you find answers to your questions
More informationWorkshop on developed country targets. Bangkok, 3 April EU contribution
Workshop on developed country targets Bangkok, 3 April 2011 EU contribution 1 EU action so far: significant reductions, decoupled from GDP growth EU will meet the Kyoto target EU domestic emissions reduced
More informationGovernment of Gujarat Energy and Petrochemicals Department G.R. No.EDA B Sachivalaya, Gandhinagar. Dated the 25 July, 2013.
Wind Power Policy 2013 Government of Gujarat Energy and Petrochemicals Department G.R. No.EDA-102001-3054-B Sachivalaya, Gandhinagar. Dated the 25 July, 2013. Preamble Wind Power as an energy source is
More informationENERGY PRIORITIES FOR EUROPE
ENERGY PRIORITIES FOR EUROPE Presentation of J.M. Barroso, President of the European Commission, to the European Council of 4 February 2011 Contents 1 I. Why energy policy matters II. Why we need to act
More informationFarm Economics brief
Farm Economics brief N 2 EU production costs overview July 211 Contents The effect of the economic crisis on costs and margins Operating costs in the EU groups Highly contrasted costs among the Member
More informationPRICE SETTING IN THE ELECTRICITY MARKETS WITHIN THE EU SINGLE MARKET
PRICE SETTING IN THE ELECTRICITY MARKETS WITHIN THE EU SINGLE MARKET A report to the Committee on Industry, Research and Energy of the European Parliament February, 2006 Outline Characteristics of the
More information450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India
450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity
More informationOverview of the Legal Framework. New Policy Initiatives. Renewable Energy Certificate Mechanism
1 Overview of the Legal Framework New Policy Initiatives Renewable Energy Certificate Mechanism 2 3 Tariff regulations of the Regulatory Commissions to be guided by promotion of generation of electricity
More informationA Multi Stakeholder Perspective
A Multi Stakeholder Perspective 1 Agenda Wind Vision Initiative Setting up of Wind Vision : 200 GW by 2032 Recommendations Wind Project Development Regulatory Incentives Financing Wind Vision 2032 Grid
More informationPhosphorus Regulations in Europe
Phosphorus Regulations in Europe Outcome of an inventory in 27 countries involved in EU COST action 869 WG1 Meeting Hamar, 22 25 May 2007 Oscar Schoumans (NL) Alterra, Wageningen University and Research
More informationIntroduction to Solid Waste Management and Legal framework in the European Union
Introduction to Solid Waste Management and Legal framework in the European Union Mr ADRIAN COOPER, Chairman, West Midlands Resource Technical Advisory Body, United Kingdom 1 Scope Introduction: What is
More informationNon-technical Innovations Definition, Measurement & Policy Implications. The new service economy: growth and implications for service innovation
Karlsruhe, October 2008 Non-technical Innovations Definition, Measurement & Policy Implications The new service economy: growth and implications for service innovation Professor of Economic Policy, University
More informationSolid biofuel markets in Europe
Solid biofuel markets in Europe Eija Alakangas, VTT Eija Alakangas, VTT eija.alakangas@vtt.fi tel. +358 20 722 2550 And 15 partners of EUBIONET II Supported by the European Commission under the Intelligent
More informationCAP CONTEXT INDICATORS
CAP CONTEXT INDICATORS 2014-2020 45. EMISSIONS FROM AGRICULTURE 2017 update CONTEXT INDICATOR 45: EMISSIONS FROM AGRICULTURE 1. GHG emissions from agriculture GHG emissions from agriculture represent 9.8%
More informationSHIPMENTS TO ALL COUNTRIES OF THE EUROPEAN UNION
SHIPMENTS TO ALL COUNTRIES OF THE EUROPEAN UNION Services Express Delivery Classic Delivery Delivery from 24h to 72h: Delivery 3-6 working days: Express shipping is ideal in an emergency shipment. We guarantee
More informationInitiatives taken for Facilitating Large Scale Integration of Renewable Energy in India
Initiatives taken for Facilitating Large Scale Integration of Renewable Energy in India S K Soonee, K V S Baba, S R Narasimhan, S S Barpanda, S C Saxena, Mohit Joshi*, KVN Pawan Kumar Power System Operation
More informationRole of the trade unions in the protection and interest representation of employees in Europe
Role of the trade unions in the protection and interest representation of employees in Europe China-EU Forum, workshop 38a Beijing, 9-10 July 2010 Béla Galgóczi bgalgoczi@etui.org European social model:
More informationNEGOTIATING THE NEW WORLD OF WORK WHAT ROLE FOR COLLECTIVE BARGAINING?
NEGOTIATING THE NEW WORLD OF WORK WHAT ROLE FOR COLLECTIVE BARGAINING? Thorsten Schulten European Trade Union Institute International Conference: Shaping the new world of work 27-29 June 2016, Brussels
More informationWind in power 2014 European statistics. February 2015 THE EUROPEAN WIND ENERGY ASSOCIATION
Wind in power 2014 European statistics February 2015 1 WIND IN POWER: 2014 EUROPEAN STATISTICS Contents Executive summary... 3 2014 annual installations... 5 Wind power capacity installations... 5 Power
More informationRealizing the Flexibility Potential of Industrial Electricity Demand: Overview of the H2020 Project IndustRE
EMART Energy 2017: Commercial and Industrial Energy Users Amsterdam, 4 th October 2017 Realizing the Flexibility Potential of Industrial Electricity Demand: Overview of the H2020 Project IndustRE Dimitrios
More informationCore Theme Interim Report
INTERIM REPORT Core Theme Interim Report Core Theme 2: Cooperation Mechanisms Authors: André Poschmann, Anne-Maria Ide, Federal Ministry for Economic Affairs and Energy, Germany Sofía Martínez, Institute
More informationBest practices in implementing the Packaging Waste Directive to maximize efficient collection and recycling
Best practices in implementing the Packaging Waste Directive to maximize efficient collection and recycling Joachim QUODEN Managing Director of EXPRA International Conference Tenerife + Sostenible June
More informationDevelopment and Financing of Renewable Energy Projects in India
Development and Financing of Renewable Energy Projects in India A Perspective By K.S. Popli Director (Technical) Indian Renewable Energy Development Agency Limited New Delhi ( India ) World primary energy
More informationRenewable energy in Europe. E-turn 21 workshop Cologne, 10 May 2006
Renewable energy in Europe E-turn 21 workshop Cologne, 10 May 2006 Content 1. Introduction to Essent 2. EU policy 3. Support for renewable energy 4. Success factors 5. Outlook and recommendations Content
More informationERGP (12) 32 - Report on indicators on postal market ERGP REPORT ON INDICATORS ON POSTAL MARKET
ERGP REPORT ON INDICATORS ON POSTAL MARKET 30 November 2012 1 Contents ERGP (12) 32 - Report on indicators on postal market List of Tables... 3 List of Figures... 3 Terms and abbreviations... 3 Country
More informationI) Background information. 1. Age
Results of questionnaire for the general public on the revision of Directive 86/609/EEC on the protection of animals used for experimental and other scientific purposes I) Background information 1. Age
More informationInnovative grid-impacting technologies for pan-european system analyses: key GridTech results on Demand Response application
Innovative grid-impacting technologies for pan-european system analyses: key GridTech results on Demand Response application Angelo L'Abbate RSE SpA EC JRC Smart Mediterraneo workshop Bari, 24 June 2016
More informationInternational Journal of Engineering, Business and Enterprise Applications (IJEBEA)
International Association of Scientific Innovation and Research (IASIR) (An Association Unifying the Sciences, Engineering, and Applied Research) ISSN (Print): 2279-0020 ISSN (Online): 2279-0039 International
More informationImpact of Renewable Energy Certificate (REC) Mechanism in India
Impact of Renewable Energy Certificate (REC) Mechanism in India Authors: S. K. Soonee, K. V. S. Baba, U. K. Verma, Minaxi Garg, Shailendra Kr. Verma and K. C. Saini Power System Operation Corporation Ltd.
More informationCostas G. Theofylaktos
IENE Workshop: Energy and Geopolitics Roundtable Cogeneration Observatory and Dissemination Europe - CODE2 ROADMAP FOR COGENERATION OF HEAT & POWER FOR BULGARIA Costas G. Theofylaktos BoD of HACHP-Team
More informationEU Climate and Energy Policy Framework: EU Renewable Energy Policies
EU Climate and Energy Policy Framework: EU Renewable Energy Policies Buenos Aires 26-27 May 2015 Dr Stefan Agne European Commission DG Climate Action Energy 1 EU Climate and Energy Policy Framework 2 Agreed
More informationExcessive Deficit Procedure Statistics Working Group
Excessive Deficit Procedure Statistics Working Group 20 22 June 2016 Ampere Beginning at 9:30 Part B Item 5 Eurostat data collection on contingent liabilities and potential obligations overview of the
More informationABC of ABT - AVAILABILITY TARIFF
ABC of ABT - AVAILABILITY TARIFF INTRODUCTION What is Availability Tariff? The term Availability Tariff, particularly in the Indian context, stands for a rational tariff structure for power supply from
More informationWork life balance as a factor of gender equality which perspective? Some findings from the European Working Conditions Survey
Work life balance as a factor of gender equality which perspective? Some findings from the European Working Conditions Survey Agnès Parent-Thirion Senior programme manager working conditions Eurofound
More informationWhere is moving the electricity sector and how are Electric. Industry Investment Decisions Influenced by Potential
Where is moving the electricity sector and how are Electric Industry Investment Decisions Influenced by Potential Instability in the Regulatory Environment by : G. Dodero I.P.G. Industrial Project Group
More informationINNOVATION UNION SCOREBOARD 2011
INNOVATION UNION SCOREBOARD 2011 The Innovation Union's performance scoreboard for Research and Innovation 7 February 2012 The IUS report, its annexes and the indicators database are available at http://www.proinno-europe.eu/metrics
More informationREPOWERING OF OLD WIND FARMS IN INDIA
REPOWERING OF OLD WIND FARMS IN INDIA BIG OPPORTUNITY TO UNEARTH Rajendra V. Kharul Sr Fellow and Head Centre for Wind Power World Institute of Sustainable Energy, Pune 26 NOV. 2008, WIND INDIA 2008 1.
More informationQ3 FY Analyst Meet Mumbai February 10, 2017
Q3 FY 2016-17 Analyst Meet Mumbai February 10, 2017 Disclaimer By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations:
More informationBiogas from Co-Fermentation of Biowaste at a Waste Water Treatment Plant
Session 2 Biogas from Co-Fermentation of Biowaste at a Waste Water Treatment Plant 1 Energy policy in Europe goes towards reduction of consumption and increase of renewable energy sources for two main
More informationWind in power 2015 European statistics. February 2016 THE EUROPEAN WIND ENERGY ASSOCIATION
Wind in power 2015 European statistics February 2016 1 WIND IN POWER: 2015 EUROPEAN STATISTICS Contents Executive summary... 3 2015 annual installations... 5 Wind power capacity installations... 5 Power
More informationUTILITIES: HOW THE EU DIRECTIVE IS IMPLEMENTED AND HOW IT WORKS IN EU MEMBER STATES
A joint initiative of the OECD and the European Union, principally financed by the EU VIth IPA REGIONAL PUBLIC PROCUREMENT CONFERENCE UTILITIES: HOW THE EU DIRECTIVE IS IMPLEMENTED AND HOW IT WORKS IN
More informationHORIZON Spreading Excellence and Widening Participation. Twinning Info day. Telemachos TELEMACHOU Policy Officer Tel-Aviv, 28 February 2017
The EU Framework Programme for Research and Innovation HORIZON 2020 Spreading Excellence and Widening Participation Twinning Info day Telemachos TELEMACHOU Policy Officer Tel-Aviv, 28 February 2017 Background
More informationSolar Thermal. Europe 2006)
European Solar Thermal Industry Federation Markets (Trends in Europe and market statistics June 27 26) solar thermal Solar Thermal New opportunities and challenges through continuous growth Our industry
More informationDeveloping Infrastructure and Operating Models for Intermodal Shift - DIOMIS Intermodal Rail/Road Transport In Europe 2007
Developing Infrastructure and Operating Models for Intermodal Shift - DIOMIS http://www.uic.org/diomis Intermodal Rail/Road Transport In Europe 2007 Geneva 12&13 October 2009 Main objectives To deliver
More informationEuropean Parliament Eurobarometer (Standard EB 74.3 on Energy)
Directorate General for Communication Direction C - Relations with citizens Public Opinion Monitoring Unit Brussels, 31 January 2011 Parlemeter January 2011 European Parliament Eurobarometer (Standard
More informationRenewable energy technologies/sources path within EU 2020 strategy
Renewable energy technologies/sources path within EU 2020 strategy Analysis according to national renewable energy action plans and 2013 progress reports Manjola Banja, Fabio Monforti-Ferrario, Katalin
More informationStudy on Employment, Growth and Innovation in Rural Areas (SEGIRA)
Study on Employment, Growth and Innovation in Rural Areas (SEGIRA) ANNEX - Rural development policy on women and young people Client: European Commission, Directorate-General for Agriculture and Rural
More informationRenewable Energy Tariffs, RPO and REC Mechanism
Department of Industrial and Management Engineering Indian Institute of Technology Kanpur 4 th Forum of Regulators Capacity Building Programme for Officers of Electricity Regulatory Commissions 18 23 July,
More informationNERC Reliability Functional Model Technical Document Version 5
Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,
More informationHow to secure Europe s competitiveness in terms of energy and raw materials? The answer, my friend, is blowing in the wind
How to secure Europe s competitiveness in terms of energy and raw materials? The answer, my friend, is blowing in the wind Iván Pineda Head of Policy Analysis, EWEA PolyTalk 2014, Brussels Around 600 members
More informationCross border interconnections and inter-european cooperation. Cross border interconnections and inter- European cooperation
Cross border interconnections and inter- European cooperation Disclaimer The information on which this presentation is based derives from our own experience, knowledge, data and research. The opinions
More informationEvolution of Renewable Energy Support Mechanisms in Europe Influence on Biogas Market
Evolution of Renewable Energy Support Mechanisms in Europe Influence on Biogas Market Jan Stambasky EBA Executive Board Member Conference of Czech Biogas Association, 11 th October 2012, Trebon, Czech
More informationRENEWABLE ENERGY INTEGRATION IN TAMILNADU
RENEWABLE ENERGY INTEGRATION IN TAMILNADU Generator Installed Capacity in MW CGS Nuclear 6% PURCHASE (LTOA, MTOA) 18% TN Hydro 2308 TN Thermal 4320 TN Gas 516 TN IPP 746 CGS Thermal 15% CPP 3% TN IPP 3%
More informationEUROPEAN INNOVATION SCOREBOARD 2009 COMPARATIVE ANALYSIS OF INNOVATION PERFORMANCE
ROPEAN INNOVATION SCOREBOARD 2009 COMPARATIVE ANALYSIS OF INNOVATION PERFORMANCE The EIS report and its Annexes, accompanying thematic papers and the indicators database are available at http://www.proinno-europe.eu/metrics
More informationThe Role of Biodegradable Waste Management in Europe. Dr. Stefanie Siebert, Quality Manager, European Compost Network ECN
The Role of Biodegradable Waste Management in Europe Dr. Stefanie Siebert, Quality Manager, European Compost Network ECN About ECN About the European Compost Network ECN Exchange of Experience Circulation
More informationAttitudes towards radioactive waste in Switzerland Report
Federal Department of the Environment, Transport, Energy and Communications DETEC Swiss Federal Office of Energy SFOE Disposal of Radioactive Waste Section Author: tns-opinion August 2008 Attitudes towards
More informationPhoto: Thinkstock. Wind in power 2010 European statistics. February The European Wind energy association
Photo: Thinkstock Wind in power 21 European statistics February 211 1 WIND IN POWER: 21 EUROPEAN STATISTICS Contents Executive summary 21 annual installations Wind map 21 Wind power capacity installations
More informationSouthern California Edison Approach to Renewable Integration June 7, 2011
Southern California Edison Approach to Renewable Integration June 7, 2011 Page: 0 SCE s 2010 Resource Mix Natural Gas All Resources 100% = 75 billion kwh/yr Renewable Resources 100% = 14.5 billion kwh/yr
More informationPublic Services Online: how is Europe progressing? Web-based Survey on Electronic Public Services, Results October 2004 Brussels, February 2005
Public Services Online: how is Europe progressing? Web-based Survey on Electronic Public Services, Results October 2004 Brussels, February 2005 2005 Capgemini - All rights reserved - January 2005 1 Contents
More informationEPR and packaging what are current challenges and issues :
Third decade of EPR What lessons and experiences can be used for light sources and other products? Lund October 11 + 12, 2016 EPR and packaging what are current challenges and issues : Joachim Quoden EXPRA
More informationANNEXES. to the COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL
EUROPEAN COMMISSION Brussels, 23.7.2014 COM(2014) 520 final ANNEXES 1 to 3 ANNEXES to the COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL Energy Efficiency and its contribution
More informationAddressing youth unemployment in the EU
Addressing youth unemployment in the EU Youth employment is a priority for the European Union. The situation varies a lot across Europe. While there is no single solution to address this challenge, there
More informationBy Leaps. and Bounds. Lessons Learned from Renewable Energy Growth in China. By Ming Ni and Zhixin Yang
By Leaps By Ming Ni and Zhixin Yang and Bounds Lessons Learned from Renewable Energy Growth in China NEW WIND POWER INSTALLATIONS in China have doubled every year since 4. By 2010, China s wind generation
More informationDPD PRICE LIST Parcel delivery in Croatia and worldwide
DPD PRICE LIST Parcel delivery in Croatia and worldwide DPD PRICE LIST What makes us special DPD Croatia Ltd. is part of the international network of experts for delivery: DPD, Chronopost, SEUR and Interlink
More informationJawaharlal Nehru National Solar Mission
Jawaharlal Nehru National Solar Mission Deepak Gupta Secretary Ministry of New and Renewable Energy Government of India 8 th June, 2011 Jawaharlal Nehru National Solar Mission (JNNSM) India has set up
More informationEnergy Demand in The EU
Energy Demand in The EU A comparison of forecasts and ambitions - January 2011 - a contributing research paper to Energy Savings 2020: how to triple the impact of energy saving policies in Europe Energy
More informationPathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid
Greening the Grid Rajasthan Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include
More informationExternal Price Referencing an European overview
External Price Referencing an European overview Mag. (FH) Christine Leopold, MSc. PPRI conference, 29.09.2011 2011 Disclaimer and acknowlegdements The information and data provided in this presentation
More informationStrategy for Renewable Energy in Tamilnadu. Venue: The Raintree Hotel, St Mary s Road, Alwarpet, Chennai Date: 4 th and 5 th February, 2015
Strategy for Renewable Energy in Tamilnadu Venue: The Raintree Hotel, St Mary s Road, Alwarpet, Chennai Date: 4 th and 5 th February, 2015 Executive Summary Excellent Wind & Solar Insolation in many parts
More informationImportance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid
January 218 Importance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid Mridul Chadha (Consultant Power Solutions) at Climate Connect Limited Since
More informationEU Energy Market in Gas and Electricity State of Play and Implementation
EU Energy Market in Gas and Electricity State of Play and Implementation Matthias Altmann, Ludwig-Bölkow-Systemtechnik Antton Rönnholm, Centre for European Policy Studies CEPS European Parliament, ITRE
More informationFulfilment by Amazon (FBA) Programme Fees Valid as of 4 August 2015
Fulfilment by Amazon (FBA) Programme s Valid as of 4 August 205 It s Cost Effective and Simple Pay as you go no minimum requirements, setup charges or subscription fees. Ship your products to our fulfilment
More informationRadio Equipment Directive RED 2014/53/EU
Radio Equipment Directive RED 2014/53/EU MRA Workshop March 2016 Presented by: Jan Coenraads jan.coenraads@brynyago.com This presentation covers: Selection of RED issues with currently most questions asked.
More informationBackground paper. Electricity production from wind and solar photovoltaic power in the EU
Background paper Electricity production from wind and solar photovoltaic power in the EU February 2018 1 The 2009 Lisbon Treaty gave the European Union (EU) the authority to develop an energy policy containing
More informationemep Transboundary Pollution by Heavy Metals and Persistent Organic Pollutants in 2014 GERMANY Convention on Long-Range TransboundaryAir Pollution
Convention on Long-Range TransboundaryAir Pollution emep Co-operative programme for monitoring and evaluation of the long-range transmission of air pollutants in Europe DATA NOTE 5/ 20 16 August 2016 Transboundary
More informationPublishing date: 06/10/2017 Document title: We appreciate your feedback. Share this document
Publishing date: 6/1/217 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document Share this document ACER/CEER Annual
More informationCogeneration perspectives in the EU from the focus of CODE project
Cogeneration perspectives in the EU from the focus of CODE project Stane Merše CODE leader Eastern Region Jozef Stefan Institute, Energy Efficiency Centre, Ljubljana, Slovenia. Cogeneration Directive requirements
More informationWorking together to meet global energy challenges
Working together to meet global energy challenges Staff on loan From around the world From IEA and OECD member countries: Australia Austria Belgium Canada Chile Czech Republic Denmark Estonia Finland France
More informationClimate policy, Land and smart agriculture 2020, 2030
Climate policy, Land and smart agriculture 2020, 2030 Simon Kay DG Climate Action, Unit A2 JRC workshop, Arona May 2014 Climate Action Treatment of emissions related to agriculture and LULUCF in the EU's
More informationANNEXES. to the. Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
EUROPEAN COMMISSION Brussels, 20.7.2016 COM(2016) 479 final ANNEXES 1 to 6 ANNEXES to the Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL on the inclusion of greenhouse gas emissions
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationWIND POWER TARGETS FOR EUROPE: 75,000 MW by 2010
About EWEA EWEA is the voice of the wind industry actively promoting the utilisation of wind power in Europe and worldwide. EWEA members from over 4 countries include 2 companies, organisations, and research
More informationEUROPEAN INNOVATION SCOREBOARD 2008 COMPARATIVE ANALYSIS OF INNOVATION PERFORMANCE. January 2009
ROPEAN INNOVATION SCOREBOARD 2008 COMPARATIVE ANALYSIS OF INNOVATION PERFORMANCE January 2009 The EIS report and its Annexes, accompanying thematic papers and the indicators database are available at http://www.proinno-europe.eu/metrics
More informationWaste-to-Energy in Europe + implementation of the Waste Framework Directive
Confederation of European Waste-to-Energy Plants Waste-to-Energy in Europe + implementation of the Waste Framework Directive IFAT ENTSORGA 16 th September 2010 Munich Dr. Ella Stengler CEWEP Managing Director
More informationSAMPLE. Reference Code: GDAE6214IDB. Publication Date: September GDAE6214IDB / Published SEP 2012
Solar PV in Spain, Market Outlook to 2025 - Capacity, Generation, Levelized Cost of Energy (LCOE), Investment Trends, Regulations and Reference Code: GDAE6214IDB Publication Date: September 2012 GlobalData.
More information