Cost Monitoring & EoT

Size: px
Start display at page:

Download "Cost Monitoring & EoT"

Transcription

1 Cost Monitoring & EoT

2 MONITOR YOUR PROGRESS TRACKING CURVES Planned vs Actual

3 How your project performance is monitored by the Engineer Earned Value Analysis (EVA) evaluates project s cost performance by:» comparing planned value of work against earned value of work accomplished; and» comparing this earned value against actual costs incurred

4 EARNED VALUE CRITERIA Uses three criteria Planned Value (PV) (or BCWS) = what is planned to be done Earned Value (EV) (or BCWP) = budget of work actually done Actual Cost (AC) (or ACWP) = what was paid for work done End of the project PV = EV = Budget at Completion (BAC)

5 EXAMPLE Project of one month has budget of 10,000. End of month, 8,000 of work completed. Actual cost to complete this work is 8,500. PV = what is planned to be done (10,000) EV = budget of work actually done (8000) AC = what was paid for work done (8,500)

6 COST VARIANCE Cost variance is difference between budget and actual costs Cost variance (CV) = EV - AC (+ve means actual is less than budgeted) Cost Performance Index (CPI) = EV / AC (>1 means actual is less than budgeted) Example: CV = 8,000-8,500 = ie. cost overrun, CPI = 8,000 / 8,500 = 0.94 ie. cost overrun

7 SCHEDULE VARIANCE Schedule variance is difference between budget for work achieved and work planned Schedule variance (SV) = EV - PV (+ve means actual is more than scheduled) Schedule Performance Index (SPI) = EV / PV (+ve means actual is more than budgeted) Example: SV = 8,000-10,000 = ie. time overrun, SPI = 8,000 / 10,000 = 0.80 ie. time overrun

8 Relationship between PV, EV, AC, SV and CV

9 FORECASTING FINAL COST Estimate at Completion (EAC) EAC = Cost to-date + estimate to complete 2 kinds of cost overruns:» Current overrun (ie. cost variance)» Overrun at completion (ie. shown by EAC). See diagram.

10 Current overrun Overrun at completion

11 END OF PROJECT EV = PV CV = final overrun

12 FORECASTING FINAL COST EAC = AC + (BAC EV) CPI (CPI = Cumulative Cost Performance Index to date) Details» the remainder of work to be done (BAC-EV),» is adjusted by cost performance (CPI)» and the result added to the actual cost to date (AC) Example (CPI = 8,000 / 8,500 = 0.94) EAC = 8,500 + (10,000 - $8,000) = 10,

13 Example EV Cost Variance Analysis WP1 EV - AC = 8,000-8,000 = 0 WP 2: EV - AC = 9,600-9,000 = WP 3: EV - AC = 19,200-22,000 = - 2,800 Project: EV- AC = 36,800-39,000 = - 2,200» WP1 on budget,» WP2 under budget» WP3 is over budget.» Project over budget

14 Example EV Schedule Variance Analysis WP1: EV - PV = 8,000-8,000 = 0 WP2: EV - PV = 9,600-12,000 = - 2,400 WP3: EV - PV = 19,200-18,000 = +1,200 Project: EV - PV = ,000 = - 1,200» WP1 on schedule» WP2 behind schedule» WP3 ahead of schedule» Project behind schedule

15 COST REPORTS Typical cost report: Cost Code Item Budget $ Complet e % Earned value Actual cost Variance % Variance $ Estimate cost to complet e Estimate cost at completi on 100 General % Site work % Concrete % Masonry % Metals TOTAL

16 Clause 8 Commencement, Delays and Suspension The Date for Possession and the Date for Practical Completion are stated in the Annexure to the Contract Conditions. Cl 8.3 Programme Program is a contract document 28 days after notice to commence Contractor shall not w/o reasonable cause depart from program 16

17 Clause Delay Damages Failure of the Contractor to complete on time may give the Engineer the entitlement to deduct delay damages against the Contractor. A genuine pre-estimate of the actual loss likely to be suffered as result of the breach by the Contractor. If the delay is caused by the Client (or his reps/agents) the Contractor will be entitled to an extension of time and loss & expenses, subject to the provisions under the contract. 17

18 Time at large If the contractor cannot complete the works in time for reasons beyond its control and there is no extension of time granted, that means there is no longer a contractually agreed date for completion. Time is said to be at large. 18

19 Time at large Consequences of time at large are: there is no date from which delay damages can run & therefore client cannot deduct delay damages any more Contractor only obligated to complete the works in a reasonable time it will be difficult for a client to prove works weren t completed in a reasonable time Therefore, EoT clauses are included in construction contracts for the benefit of the Client 19

20 Clause EoT Therefore, if the EoT provision is to stay alive, the Engineer must fix a new postponed date for completion in the event of a Client caused delay. Therefore, the Engineer must be empowered by the contract conditions to grant EoT. (e.g. site possession) 20

21 Clause EoT Claim Notice of delay - the contractor can claim EoT within 28 days when he should have become aware of the causation occurring. It must be as a result of a qualifying cause of delay as per Clause 8.4 (a)-(e) and

22 Reasons for Extension of Time Two categories of reasons or qualifying causes:- 1. Client caused 2. Neutral events beyond control of both parties 22

23 Difficulties in Assessing EoTs Concurrent Delays Programming Float 23

24 Examples: Concurrent Delays Late provision of information by Engineer causes 5 days of delay. During this period, contractor causes 4 days of delay due to non-availability of workmen. Who should be responsible for how much delay? How much compensation should contractor get for delay damages? Client caused delay Contractor caused delay 24

25 Concurrent Delays When both non-qualifying and qualifying causes of delay overlap, Engineer apportions the delay to works according to the respective causes contribution. 25

26 Concurrent Delays 2. Client caused delay overlaps with a neutral delaying event Simple example: An owner-caused delay of 5 days overlaps with a neutral even on the 3 rd day 26

27 The issue of float - Prolongation Prolongation is defined as a critical delay which results when the time necessary for a critical activity is prolonged.

28 Prolongation Claim Prolongation claim is that which a contractor would make when the time necessary to complete a critical activity becomes longer than that originally planned owing to the event giving rise to the critical delay.

29 Prolongation Claim (Cont.) The delayed activity must be critical and must start and finish on a pre-determined scheduled day with no float time or flexibility. The delay should also have been caused due to circumstances beyond the contractor s control.

30 Example Delay Events Delay in possession of site Industrial conditions Inclement weather Delay in information/design Latent conditions Delay in client supplied materials

31 Delay in Possession of Site Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

32 Industrial Conditions - Bricklayers on Strike in April Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

33 Inclement Weather During June Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

34 Delay in Provision of HVAC Drawings Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

35 Latent Conditions During Excavations Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

36 Delay in Client Supplied Materials for External Finishes Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

37 Extension of time & payment for loss and expense A contractor may be entitled under the provisions of the contract to extension of time, but the grant of an extension of time in respect of such delays does not necessarily entitle him to additional payment for loss and expense.

38 Link between Extension of time & payment for loss and expense The loss lies where it falls Reimbursable extensions Employers fault Non-reimbursable extensions Neutral events

39 Delay in Possession of Site Employers Fault, Reimbursable Extension Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

40 Inclement Weather Neutral Event, Non-reimbursable Extension Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

41 Latent Conditions Neutral Event, Non-reimbursable Extension Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

42 Delay in Client Supplied Materials Employers Fault, Reimbursable Extension Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage

43 Financial Loss The Contractor will suffer financial cost as a result of delay by Client. This will include: Site overhead cost Head office overhead 43

44 On-site & off-site overheads On site (e.g.) supervision utility Insurance, etc (project based) Off site (e.g.) Office staff salaries rents Office equipment (apply to all projects) 44

45 Prolongation cost On-Site Costs Need to provide proof/assess on-site costs eg, extended preliminaries Total time related items X period of delay Contract Period Note: Contractor must show it has mitigated loss by standing down any s/cs and reallocating employees not needed in delay period 45

46 Cost of Preliminaries Requires examination of each item: Some time related charges Some fixed charges Some with elements of both fixed and time

47 Exercise Differentiate the following preliminaries between Time related and fixed Description Compliance with acts and regulations Temporary access, hoardings, protective barriers, screens, sign boards Scaffolding Time Related Fixed (Beginning) X Fixed (End) X Combined X Protection of exposed excavated surfaces Site office, other site buildings, storage space, labourers accommodation Provision of bulk bins and dumping of debris and waste Water, temporary lighting and power, telephone Protection of existing services, protection of the works Site staff Insurances and fees Performance bond X X X X X X X Safety Traffic control and road safety Plant and machinery Security and watching Testing and test facilities, samples, photographs Inspection of sewers and checking for levels, open up for inspection Housekeeping, cleaning up and reinstatement of works on completion X X X X X X

48 Example Description Cost ($) Insurance 225,000 Bonds & guarantees 35,000 Temporary Hoardings 25,000 Site office & maintenance 80,000 Site signboard 4,000 Site security 144,000 Plant for groundwork 40,000 Supervisory staff 240,000 Cleaning & handover 7,000 TOTAL 800,000

49 Example Description Cost ($) Category Insurance 225,000 Time Bonds & guarantees 35,000 Fixed Temporary Hoardings 25,000 Fixed Site office & maintenance 80,000 Combined Site signboard 4,000 Fixed Site security 144,000 Time Plant for groundwork 40,000 Time Supervisory staff 240,000 Time Cleaning & handover 7,000 Fixed TOTAL 800,000

50 Distribution of Total Preliminaries Total Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Insurance 225, , Bonds & guarantees 35,000 35,000 Temporary Hoardings 25,000 20,000 5,000 Site office & maintenance 80,000 25,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 Site signboard 4,000 3,000 1,000 Site security 144,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 Plant for groundwork 40,000 20,000 20,000 Supervisory staff 240,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 Cleaning & handover 7,000 10,000

51 Distribution of Time Related Preliminaries Total Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Insurance 225, , Site office & maintenance 60,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 Site security 144,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 Plant for groundwork 40,000 20,000 20,000 Supervisory staff 240,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 TOTAL 709,000 75,750 75,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750

52 Delay in Possession of Site 20 days delay in possession of site Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage Total Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Insurance 225, , Site office & maintenance 60,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 Site security 144,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 Plant for groundwork 40,000 20,000 20,000 Supervisory staff 240,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 TOTAL 709,000 75,750 75,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 Contractors entitlement = (75750/30)x20 = $ 50,500

53 Delay in Client Supplied Materials 40 days delay in client supplied materials Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Total Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Landscaping & external drainage surance 225, , e office & maintenance 60,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 e security 144,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 nt for groundwork 40,000 20,000 20,000 pervisory staff 240,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 TAL 709,000 75,750 75,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 55,750 Entitlement = (55750/30)x40 = $ 74,333

54 Off-Site or Head Office Overheads Formulas, eg. Hudson Formula Head office OH(%) x Contract sum x Period of delay Contract period 54

55 Prolongation Costs Loss of Profit Could claim that delay has prevented earning profit on another job Very difficult to prove: Was there another project to go to What profit %age could have been earned in market Did the delay really prevent the contractor from starting other projects? 55

56 Global Claims Sometimes lots of small events on contract cumulatively cause a delay, but do not individually cause a delay Therefore, cannot quantify exact delay caused by each one of these events So, Contractor ends up putting in a global claim, stating that all these events together caused delay and expense 56

57 Compensation for Concurrent Delays A single cause of delay presence no problem when dealing with prolongation claims. In practice many delays occur at the same time. Some delays will qualify additional payments, whilst others such as adverse weather may qualify only for an extension of time. Culpable delay by the contractor will not normally qualify for additional payment. In assessing the concurrent delay, dominant delay principles could be a deciding factor.

58 Dominant Delay Principle Non-recoverable in critical path, Qualifying recoverable in non-critical, no reimbursement. Recoverable in critical path, non-recoverable is non-critical, reimbursement permitted. Qualifying recoverable delay occur first, followed by nonqualifying delay (both delays on the same parallel critical paths), reimbursement should be permitted. Non-recoverable delay occur first, followed by qualifying recoverable delay (both delays on the same parallel critical paths), reimbursement doubtful.

59 Non-recoverable in critical path, Qualifying recoverable non-critical Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage Non-recoverable Qualifying recoverable No reimbursement

60 Recoverable in critical path, Nonrecoverable non-critical Activity Jan Feb Mar Apr May June July Aug Set Oct Nov Dec Site clearance Excavation for foundations Work up to DPC Columns Beams External walls Roof structure Roof covering Roof plumbing Doors & windows Plumbing & drainage HVAC Electrical work Infill walls External finishes Landscaping & external drainage Qualifying recoverable Non-recoverable Reimbursement Permitted

61 End of session Questions?

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline. Principles of Planning for Building and Construction by Eastwood Harris Pty Ltd Introduction Emergency Evacuation Timings Meals Mobile Phones Conduct of course Introductions: Your name Position Experience

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single

More information

Scream If You Want To Go Faster

Scream If You Want To Go Faster Project Controls Expo 13 October 2015 Emirates Stadium, London Scream If You Want To Go Faster The contractual, legal, financial and practical aspects of acceleration David Bordoli and Helen Bentley Introduction

More information

After solving all the case studies, please forward your answers to for an extra credit.

After solving all the case studies, please forward your answers to for an extra credit. CASE STUDIES Course Case Studies The case studies are designed to give you a glimpse of real life projects. Please give yourself enough time to solve each case study. After solving all the case studies,

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

FIDIC Claims: Management of Claims and Resolution of Disputes

FIDIC Claims: Management of Claims and Resolution of Disputes FIDIC Claims: Management of Claims and Resolution of Disputes Page 1 of 7 Why Attend With all FIDIC contracts there will be claims. This training course is designed to provide practical assistance to those

More information

Exam 2012, Lecture Project Management

Exam 2012, Lecture Project Management Exam 2012, Lecture Project Management Name: Matrikelnummer: Fachbereich: Hints: German text is permitted. Simple calculator is permitted. Dictionary is permitted. No computers. No books. Rather write less.

More information

SCHEDULE 5 ADDITIONAL PAVEMENT MARKING SERVICES

SCHEDULE 5 ADDITIONAL PAVEMENT MARKING SERVICES SCHEDULE 5 ADDITIONAL PAVEMENT MARKING SERVICES 1.0 Definitions 1.1 In this Schedule, unless the context otherwise requires: Delta Island means triangle shaped island at an intersection as pictured in

More information

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion Cashflow The significance to the contractor s cashflow of different patterns of payment from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years duration.

More information

Practical Strategies to Make Your Next Project Profitable

Practical Strategies to Make Your Next Project Profitable 55 th Annual TIAC Conference Practical Strategies to Make Your Next Project Profitable Matthew Nicholas Revay and Associates Ltd Toronto August 26, 2017 1 Profit in Construction 2 Profit In Construction»

More information

Richard E Murphy. Forecasting & Budgeting 28 Apr A: The traditional budgeting process toward tracking labor costs within the

Richard E Murphy. Forecasting & Budgeting 28 Apr A: The traditional budgeting process toward tracking labor costs within the Overview: This paper will describe: A: The traditional budgeting process toward tracking labor costs within the Enterprise Data Warehouse (EDW) of Zions Bancorporation. B. The method used to determine

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

IT Project Management. Essentials of IT project management 25 Sep 2017

IT Project Management. Essentials of IT project management 25 Sep 2017 IT Project Management Essentials of IT project management Accenture@NTNU 25 Sep 2017 ? 2 Essentials of IT project management 3 Definitions What do we mean by Project? A project is a temporary discrete

More information

TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3

TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3 TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3 PROJECT MANAGER S REPORT NO. 15 TO PLANNING AND DEVELOPMENT COMMITTEE Prepared by February 2001 TWEED HEADS HOSPITAL STAGE 3 REDEVELOPMENT PROJECT MANAGER S REPORT

More information

Measuring EV in an Agile World - How to Make it Work!

Measuring EV in an Agile World - How to Make it Work! Measuring EV in an Agile World - How to Make it Work! Laura Bier, Agile Track Chair Dave Scott, EVMP Chair 2017 EVMP Forum August 24 th & 25 th 1 Learning Objectives Gain an understanding of a lean approach

More information

Construction Cost Consultants and Quantity Surveyors Manitoba Hydro Capital Expenditure Review. January 2018

Construction Cost Consultants and Quantity Surveyors Manitoba Hydro Capital Expenditure Review. January 2018 Construction Cost Consultants and Quantity Surveyors January 2018 Powerhouse Complex July 2017 photograph provided by Manitoba Hydro Contents The Company What is a Quantity Surveyor The Keeyask Hydroelectric

More information

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017 WEBINAR The FIDIC 2017 Suite of Agreements Presenter: Vincent Leloup FIDIC Contracts Committee Exequatur, 2017 PROGRAMME 1. FIDIC 2017 SUITE OF AGREEMENTS ROOTS & HISTORY 2. FIDIC 2017 WHITE BOOK MAIN

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

Project Controls Expo 13 th Nov 2013

Project Controls Expo 13 th Nov 2013 Project Controls Expo 13 th Nov 2013 Twickenham Stadium, London From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle Copyright @ 2011. All rights reserved

More information

OU Workforce Management Requirements For Affordable Care Act Compliance

OU Workforce Management Requirements For Affordable Care Act Compliance OU Workforce Management Requirements For Affordable Care Act Compliance Applies to HSC-Based Programs Version 3.1 HSC Edition June 18, 2015 NOTE: The requirements of the federal Affordable Care Act continue

More information

INSITUTE OF APPRAISERS & COST ENGINEERS (IACE) (A Division of the Nigerian Society of Engineers) 2013 ANNUAL DISTINGUISHED LECTURE.

INSITUTE OF APPRAISERS & COST ENGINEERS (IACE) (A Division of the Nigerian Society of Engineers) 2013 ANNUAL DISTINGUISHED LECTURE. INSITUTE OF APPRAISERS & COST ENGINEERS (IACE) (A Division of the Nigerian Society of Engineers) 2013 ANNUAL DISTINGUISHED LECTURE g{xåx: COST ENGIN RING By Engr. Otis Anyaeji FNSE F.Val FNIMechE F.AutoEI

More information

Project Controls Expo

Project Controls Expo Project Controls Expo 9 Nov 2, London DELAY AND FORENSIC ANALYSIS Robert McKibbin : Director, Navigant Consulting Copyright @ 2. All rights reserved Introduction Delay in Construction Contracts: On-going

More information

Schedule Compression

Schedule Compression Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual

More information

REHABILITATION OF DRIVEWAY AND GROUND FLOOR OF THE SECOND BUILDING AT MIDDLE STREET OFFICE

REHABILITATION OF DRIVEWAY AND GROUND FLOOR OF THE SECOND BUILDING AT MIDDLE STREET OFFICE BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer

More information

Market Redesign and Technology Upgrade Budget and Schedule Report

Market Redesign and Technology Upgrade Budget and Schedule Report Market Redesign and Technology Upgrade Budget and Schedule Report Executive Sponsor: Charles A. King, PE Project Manager: Debi Le Vine Board of Governors Meeting October 17, 2007 General Session MRTU Executive

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Rehabilitation of Tunis & Omer Bin Abdel Aziz Sidewalks PAL 10-71488 : UXOs and Rubble Removal From Gaza Strip Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition 18 January 2017 SCL Delay & Disruption Protocol 2 nd Edition INTRODUCTION TIME - Methods of Delay Analysis

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Assessing Extensions of Time Tony Farrow Trett Consulting March 2006

Assessing Extensions of Time Tony Farrow Trett Consulting March 2006 Assessing Extensions of Time Tony Farrow Trett Consulting March 2006 Contracts require the Works to be completed by a set date, subject to the Contractor s entitlement of extensions of time under the Conditions

More information

Schedule Compression

Schedule Compression Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

Appendix C. Construction Programme

Appendix C. Construction Programme Appendix C Construction Programme Activity ID Activity Name Orig Dur Planned Start Planned Finish Revision 2 827d 14-Oct-13 31-Jul-16 0d Preliminaries 827d 14-Oct-13 31-Jul-16 0d Total Float Contract Key

More information

Case Studies Civil Construction Works

Case Studies Civil Construction Works Case Studies Civil Construction Works CASE STUDY OVERVIEW The purpose of this case study is to illustrate the benefits of implementing a Earned Value based Performance Measurement (EVPM) system to undertake

More information

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/ Connecting South Dakota and the Nation Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD 57709-1970 Phone: 605/394-2244 FAX: 605/394-1904 July 9, 2014

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) PAL 10-92895 - Emergency Removal and Crushing of Rubble and Debris Management Lot # 10: Site Preparation and Crushing of Concrete Rubble Bill of Quantity (BOQ) Bill of Quantity (BOQ) ITB 2015-039 PREAMBLE

More information

SECTION BID PROPOSAL FORM. Telephone NO: ( ) Facsimile NO: ( ) Oklahoma License NO:

SECTION BID PROPOSAL FORM. Telephone NO: ( ) Facsimile NO: ( ) Oklahoma License NO: ISSUE DATE: MARCH 21, 2012 (REVISION 2-08/31/12) PROJECT: CNB BUILDINGS 2 AND 3 CATOOSA, OKLAHOMA OWNER: BID TO: (Mail & Fax) CHEROKEE NATION BUSINESSES 777 WEST CHEROKEE STREET CATOOSA, OKLAHOMA 74015

More information

Application Of A Project Planning Methodology In Construction Work

Application Of A Project Planning Methodology In Construction Work ISSN: 2278 0211 (Online) Application Of A Project Planning Methodology In Construction Work Boskee Sharma Research Scholar Lakshmi Narain College of Technology, Bhopal, India Mr. K.N. Labh Reader Indian

More information

A Web-based Framework of Project Performance and Control System

A Web-based Framework of Project Performance and Control System A Web-based Framework of Project Performance and Control System Jui-Sheng Chou* National Taiwan University of Science and Technology, Department of Construction Engineering Taipei, Taiwan jschou@mail.ntust.edu.tw

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:

More information

Briefing on Provisions and Applications Of the Minimum Wage Ordinance

Briefing on Provisions and Applications Of the Minimum Wage Ordinance Briefing on Provisions and Applications Of the 1 Disclaimer Not a substitute for legal advice Information and materials are for sharing purpose only The relevant Ordinances themselves remain the sole authority

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

PROJECT COORDINATION & MANAGEMENT

PROJECT COORDINATION & MANAGEMENT 21-25 May 2017, Dubai 29 Oct - 02 Nov 2017, Dubai Introduction Projects frequently fail, not because of a lack of technical skills on the part of those executing the project, but because of inadequate

More information

How DCMA data driven metrics may be used for continuous EVMS process improvement

How DCMA data driven metrics may be used for continuous EVMS process improvement BDO INDUSTRY SPECIALTY SERVICES GROUP Program Optimization and Project Controls Solutions How DCMA data driven metrics may be used for continuous EVMS process improvement Dave Scott, dmscott@bdo.com dmscott@bdo.com

More information

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, Chapter 5 Project Scheduling (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, Project Scheduling Project Scheduling Project Scheduling important task to completed in

More information

NZQA Expiring unit standard version 2 Page 1 of 5. Prepare a schedule of quantities, cost estimate and tender documentation for landscape work

NZQA Expiring unit standard version 2 Page 1 of 5. Prepare a schedule of quantities, cost estimate and tender documentation for landscape work Page 1 of 5 Title Prepare a schedule of quantities, cost estimate and tender documentation for landscape work Level 5 Credits 15 Purpose This unit standard is for people working, or intending to work,

More information

PROJECT COORDINATION & MANAGEMENT

PROJECT COORDINATION & MANAGEMENT 01-05 Jul 2018, Dubai 04-08 Nov 2018, Dubai Introduction Projects frequently fail, not because of a lack of technical skills on the part of those executing the project, but because of inadequate coordination,

More information

Flexible Resource Adequacy Criteria and Must-Offer Obligation

Flexible Resource Adequacy Criteria and Must-Offer Obligation Flexible Resource Adequacy Criteria and Must-Offer Obligation February 13, 2014 Karl Meeusen, Ph.D. Market Design and Regulatory Policy Lead Stakeholder Meeting Agenda 2/13/14 Time Topic Presenter 12:30

More information

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158)

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) Appl. 22.158 158. Termination of Employment, 1982 INTERNATIONAL LABOUR OFFICE GENEVA REPORT FORM FOR THE TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) The present report form is for the use of countries

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

P1 Performance Operations

P1 Performance Operations Performance Pillar P1 Performance Operations 26 May 2010 Wednesday Morning Session Instructions to candidates You are allowed three hours to answer this question paper. You are allowed 20 minutes reading

More information

Application Pack 2. Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015

Application Pack 2. Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015 Application Pack 2 Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015 This guidance applies where a developer decides to requisition water mains and services

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Program UXOs and Solid Waste Management PAL 10-71646 Lot # 2 Removal of Solid Waste from Random sites in North Governorate Bill of Quantity (BOQ) Page 1 of 8 PREAMBLE TO BILL

More information

Customer Questions. Project Deliverables

Customer Questions. Project Deliverables Customer Questions Do you understand customer problem and needs? Can you design a system to solve customer problem or satisfy customer needs? How long will it take you to develop the system? How much will

More information

1.1. In these Terms of Business the following definitions apply:

1.1. In these Terms of Business the following definitions apply: Page 1 CONTRACT WITH THE CLIENT (SUPPLYING TEMPORARY STAFF SERVICES/CLIENT TERMS OF BUSINESS) 1. DEFINITIONS 1.1. In these Terms of Business the following definitions apply: Assignment Client means the

More information

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction P P Periodica Polytechnica Architecture 48(2), pp. 87-92, 2017 https://doi.org/10.3311/ppar.10833 Creative Commons Attribution b Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise

More information

Payroll Policy. Purpose of Policy. The policy is to cover the administration of the payroll service. Overview

Payroll Policy. Purpose of Policy. The policy is to cover the administration of the payroll service. Overview Purpose of Policy Overview Scope: Mandatory Policy The policy is to cover the administration of the payroll service The policy covers the range of services provided by payroll, the legislative requirements

More information

Building Contract Closeout. Ahmed Abd Alla Gouda, Chief Contracting Officer

Building Contract Closeout. Ahmed Abd Alla Gouda, Chief Contracting Officer Building Contract Closeout Ahmed Abd Alla Gouda, Chief Contracting Officer Content Construction Contracts Management from Award to Close Out. Barriers to Effective Construction Contract Management. Economy

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Programme of Assistance to the Palestinian People UXOs and Rubble Removal from Gaza Strip Removal of Residential and public Debris from North Governorate (Package 7)

More information

TEMPORARY AND PERSONAL ILLNESS LEAVES c. Whether the request is in compliance with Board policies;

TEMPORARY AND PERSONAL ILLNESS LEAVES c. Whether the request is in compliance with Board policies; Administrators The administrator s immediate supervisor may approve a request from an administrator for temporary leave and/or personal illness leave after considering these factors: a. The purpose for

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) Emergency Removal and Crushing of Rubble and Debris Management PAL 10-92895 Lot # 13: Rubble Removal from Different Locations of Gaza Governorates Bill of Quantity (BOQ) Bill of Quantity (BOQ) PREAMBLE

More information

Quarterly Maintenance Cost Report

Quarterly Maintenance Cost Report Quarterly Maintenance Cost Report October December 2018 Aurizon Network Table of Contents 1.0 Report Contents... 3 2.0 Network Performance Metrics... 4 2.1 Safety... 4 Injury Reporting Metrics... 4 Major

More information

Utility Bill Data Accounts Payable s Secret Weapon for Managing Costs and Addressing Stakeholder Questions

Utility Bill Data Accounts Payable s Secret Weapon for Managing Costs and Addressing Stakeholder Questions EBook Utility Bill Data Accounts Payable s Secret Weapon for Managing Costs and Addressing Stakeholder Questions Part 1 Situation Analysis Utility costs often rank in the top three operational expenses

More information

NOISE MITIGATION PROGRAM

NOISE MITIGATION PROGRAM Village of Matteson NOISE MITIGATION PROGRAM Q&A Session November 29, 2010 Meeting Agenda 1. Introduction of Staff 2. Overview of Noise Mitigation Program Eligibility Program Guidelines Eligible Improvements

More information

Tracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management

Tracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management Tracy Lo Terrell Place 575 7 th Street NW Washington DC November 4, 2002 Construction Management Alternate Systems and Methods Analysis Executive Summary Studies on the following subtopics are helpful

More information

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts) Volume (5) Number (8) August 2015 J. Appl. Environ. Biol. Sci., 5(8)55-69, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Commencement

More information

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Section 6 - Bill of Quantities Bill Nr. 1 Preliminaries

Section 6 - Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA requirements. (2) If CAM decides to cancel any s listed in the Bills

More information

Findings through Nov. 2016

Findings through Nov. 2016 BUILDING ENERGY SAVING ORDINANCE (BESO) DECEMBER 7, 2016 Findings through Nov. 2016 BESO Basics Update to RECO/CECO requiring tailored energy assessment at time of sale or periodically, based on building

More information

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management Fatima Boumahdi Faculty of Sciences, University of Blida, Soumâa, Algeria Fati_boumahdi@yahoo.fr

More information

THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution)

THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution) THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution) Answer to Q-1 Minimum price for making 500 units of AK 100 Materials: Rs. X (500 units 4kg) Rs.8 16,000 Y (500

More information

CONTRACT WITH THE TEMPORARY WORKERS (TERMS OF ENGAGEMENT/CONTRACT FOR SERVICES) 1.1. In these Terms of Engagement the following definitions apply:

CONTRACT WITH THE TEMPORARY WORKERS (TERMS OF ENGAGEMENT/CONTRACT FOR SERVICES) 1.1. In these Terms of Engagement the following definitions apply: Page 1 CONTRACT WITH THE TEMPORARY WORKERS (TERMS OF ENGAGEMENT/CONTRACT FOR SERVICES) 1. DEFINITIONS 1.1. In these Terms of Engagement the following definitions apply: Assignment Client means the period

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Construction Salah El Deen Road Median From Al Zawaida entrance to Al Maghazi Northern entrance PAL 10-00071488 Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

LIMITED DURATION CONTRACT OF EMPLOYMENT. Made and entered into by and between

LIMITED DURATION CONTRACT OF EMPLOYMENT. Made and entered into by and between LIMITED DURATION CONTRACT OF EMPLOYMENT Made and entered into by and between QUEST STAFFING SOLUTIONS A DIVISION OF ADCORP FULFILMENT SERVICES (PTY) LIMITED (the employer ) And (the employee ) Employee

More information

Effective Contract Preparation. Contents are subject to change. For the latest updates visit

Effective Contract Preparation. Contents are subject to change. For the latest updates visit Effective Contract Preparation Page 1 of 7 Why Attend The overall aim of this course is to provide participants with the knowledge, concepts and skills needed to perform all the tasks required in the pre-award

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

MBA Group Project Guidelines. Interim inspection to document accepted deliverables

MBA Group Project Guidelines. Interim inspection to document accepted deliverables MBA 520 - Group Project Guidelines Interim inspection to document accepted deliverables This week, you will begin work on your Group Project for this module. You will work as a group but will submit the

More information

Integrated Management Operating Model

Integrated Management Operating Model NAVAIR Public Release 08-977 Distribution: Statement A - (Approved for public release, distribution is unlimited) Integrated Management Operating Model Processes, Tools, Rhythm, EV Forecasting 1 Mr. Douglas

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Business plan toolkit

Business plan toolkit Business plan toolkit 1 Contents Page 3 5 5 5 6 6 7 8 8 9 10 10 10 12 12 13 14 14 14 15 19 19 20 21 22 22 Section The business at a glance The business in detail History Products and services Structure

More information

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011

FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 N. Jonathan Peress Conservation Law Foundation Clean Energy and Climate Change Program 1 It is change,

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Update March 2012 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_24Y2K9 Agenda 1. Overview of the

More information

Request for Proposal (RFP) Building Repair and Renovation Project. Instruction to Bidders (Project Management Consultants) & Eligibility Criteria

Request for Proposal (RFP) Building Repair and Renovation Project. Instruction to Bidders (Project Management Consultants) & Eligibility Criteria Section -I Request for Proposal (RFP) Building Repair and Renovation Project Instruction to Bidders (Project Management Consultants) & Eligibility Criteria 1. Project Management Consultants should submit

More information

Design Division Project Management & Engineering Department Anchorage: Performance. Value. Results.

Design Division Project Management & Engineering Department Anchorage: Performance. Value. Results. Design Division Anchorage: Performance. Value. Results. Mission Design and prepare construction documents that produce safe, functional and costeffective capital infrastructure projects, i.e., roads, drainage,

More information

Regular Voluntary Overtime - Annual Leave Pay Procedure

Regular Voluntary Overtime - Annual Leave Pay Procedure Regular Voluntary Overtime - Annual Leave Pay Procedure Issued by SPS If you require this procedure in another format please go to the end of this document for details. Purpose From 1 st January 2019 regular

More information

Constraints on how the Contractor Provides the Works

Constraints on how the Contractor Provides the Works Constraints on how the Contractor Provides the Works [DELETE AS APPROPRIATE: WHERE NOTIFIABLE CDM APPLIES:] CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2007 In line with the requirements of the above

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis

More information

Parametric Project Monitoring and Control: Performance-Based Progress Assessment and Prediction

Parametric Project Monitoring and Control: Performance-Based Progress Assessment and Prediction Parametric Project Monitoring and Control: Performance-Based Progress Assessment and Prediction Presented by: Mike Ross, Chief Engineer Galorath Incorporated 100 North Sepulveda Boulevard Suite 1801 El

More information

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

Section 3 Specification 3.24 Chip Seal Coat TABLE OF CONTENTS

Section 3 Specification 3.24 Chip Seal Coat TABLE OF CONTENTS TABLE OF CONTENTS 3.24 CHIP SEAL COAT... 1 3.24.1 GENERAL... 1 3.24.2 MATERIALS... 1 3.24.2.1 Aggregate... 1 3.24.2.2 Temporary Markers... 1 3.24.2.3 Asphalt... 1 3.24.2.4 Water... 1 3.24.2.5 Line Painting

More information