Tracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management

Size: px
Start display at page:

Download "Tracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management"

Transcription

1 Tracy Lo Terrell Place th Street NW Washington DC November 4, 2002 Construction Management Alternate Systems and Methods Analysis Executive Summary Studies on the following subtopics are helpful to understand the building systems and related construction costs. This will generate ideas that are useful for possible thesis topics: Alternative methods, value engineering and schedule compression. Site Layout Planning Site plans for excavation, superstructure and finish phases of the project are included in this section. A list of description explaining the key features of the site layout and detailed explanation of the site layout is put together. Material Management Requirements of supporting installment for two materials from the project are explained in detail. The requirements can be applied to the people working on the site and to the structure. Detailed Structural Systems Estimate A detailed structural estimate is prepared. This includes the foundation system, the quantity of concrete, quantity of steel for columns and beams, roof, equipment cost and others. Spreadsheets with quantity showing and estimate from MC2 are attached. General Conditions Estimate General Conditions estimate is developed from the Staffing plan that previous assignment had put together. This includes bonds and insurance that the general contractor had to pay for and R.S. Means is used for reference. Project Schedule A primavera schedule is prepared in this section. This is a more detailed schedule that is built from the previous assignment. This schedule shows the duration of the structural sequence, MEP rough-in, distribution and finishes. Cash Flow From the primavera schedule, each activity is associated with the cost and cost load schedule is prepared. Cash flow schedules for the owner and the general contractor are created. The S curve (Cumulative payments) is shown on the graph.

2 Site Layout Planning: There are three parts to the building: New West Building, Existing Hecht Company building and Gang of Four with a total of 634,890 square feet. MCI Center F street, NW Tarriff Building Hotel 7th Street, NW Hecht's Building Gang of Four New West Building New Building Not in project Terrell Place 8th Street, NW Firehouse Existing Building Future Residential Existing AARP NRC E Street, NW Housing/Theatre Office Terrell Place - Site Plan Not To Scale Loading Dock: Terrell Place is located in downtown Washington DC and site usage is very limited. There are two loading docks where trucks can unload material. One of the docks face the sidewalk, which has been temporarily closed on F street. Since space is limited, trucks do not have enough space to make U-turns. Trucks coming in from F street have to park parallel to the sidewalk to unload materials. Trucks can enter from the entrance to the existing parking lot next to the New West Building. It is a site for another future project that has yet to start. But again, space is very limited at that area and therefore, the project manager has to coordinate all the delivery schedules. Staging Area/Site Trailer: The general contractor trailer is located on the existing parking lot east of the New West Building. Other subcontractors trailers are located on the second floor of the existing Hecht s Building. Staging area is along F Street. The first floor of the Existing Hecht s Building is used as staging area as well. Parking: Space is very limited. However, there are about 15 parking spaces outside the general contractors trailers. They all line up after each other and it is very difficult to move the cars during the day. The parking spaces are only provided for the staff from the general contractor. Metro Station and Gallery Place are across from the site.

3 Crane: There are two tower cranes on site. Crane #1 is a tower crane with max jib length of and max capacity of 26,455 lbs. It is located on the New West Building. Crane #2 is a tower crane with max jib length of 135 and max capacity of 13,200lbs. It is located at the Gang of Four Building. They are shown on the site plan.. Neighboring Building: Terrell Place is located in downtown Washington DC. It is mainly a commercial district but there are also a few residential apartments in the area. MCI Center, a multi-purpose facility for concerts, family shows and sporting events, is located across from F Street. Other buildings under construction include a residential apartment and NRC- National Research Council, which are located a block away from Terrell Place. The Spy Museum, which opened in August 2002, is only 5 minutes walking from Terrell Place. Traffic, Pedestrian Pattern and Fences: One lane along 7 th street and F Street is closed due to construction. Fences are around the perimeter of the construction and extend to the traffic lane. The sidewalk along F Street is also closed. Temporary sidewalk along 7 th street is extended to the road. There are signs showing pedestrian the new traffic pattern. No temporary sidewalk for pedestrian is provided along 7 th street. Access Road: There is a temporary construction access road within the construction site, but it include only a small parking lot and a loading area for trucks. It is very challenging for trucks to back up within the site. Hoist: One material hoist is located on the east side of the New West Building. The location is convenient because the loading dock is next to it. Temporary Utilities: The general contractor has to coordinate with utility companies for transfer to permanent power. Temporary light and power, heat and ventilation, construction water, and toilets are provided.

4 Standpipes: Standpipes are provided in the enclosure of stairs. Hydrants, Water Line, Utility Location: They are shown on the site plan. Three sites plans were developed to represent the excavation, superstructure, and finish phases of the construction. More explanation on each site plan is described below: Excavation Plan There was a temporary access road for demolition debris removal during excavation phase so that the trucks and other equipments could get to Gang of Four. Trucks could not enter from 7 th street because there was a temporary sidewalk which blocked the entrance from 7th street. Therefore, all the trucks must enter the site from the entrance on F street. A ramp was built from the entrance on F street to the New West Building s basement level so that the trucks could have access to the lower level of the New West Building. Sheeting and shoring were built on the perimeter of the site during the excavation phase. Superstructure Two tower cranes were erected on site after foundation was completed. The cranes were there for erecting structural members and placing other heavy equipment on floors. Since all vehicle traffic had access to the site only from F street, a staging area was set up on F street for easy access. (7 th street was blocked off by temporary sidewalk) Finishes Subcontractor s trailers were inside the first few floors of the Hecht s building. Next to the trailers, they set up a storage area where they stored small equipments and tools. Staging area for material was set up along F Street. A material hoist was set up next to the staging area and it could transport to the material to the appropriate floor levels.

5

6

7

8 Material Management: Architects, general contractor and the subcontractors pay close attention to all the materials handling processes including fabrication, delivery, storage, and installation in order to achieve the best quality work. On the other hand, a safe environment for workers is also very important. Proper material management is essential for both obtaining the best quality work and providing a safe environment for workers. Under each section of the specifications, it states the requirement for each type of materials. Temporary utilities are stated in section 1510 in the specifications. It stated the general requirement for each utility including light and power, heat and ventilation, and construction water. Adequate temporary lighting and power are required for the building, the site, and the field offices to serve construction trades during the construction. Temporary ventilation is provided for comfort and protection of workers, for proper drying of wet work, and for proper curing of installed materials. Temporary Heat is provided to ensure suitable working conditions and also for storage of products and materials. These elements are tied with material management and in the following paragraphs, two specific materials: Cast-in-place concrete and Applied Fireproofing, are discussed in details. Cast-in-place concrete is used throughout the building. Cast-in-place concrete is used in foundations, machine and other equipment bases, concrete slabs and curbs. The quality of concrete is very crucial to the building and the contractor must provide extra care during the mixing and curing process. During mixing, if it is under hot weather or under conditions that will accelerate the setting of concrete, a shorter mixing time may be required. When air temperature is between 85 to 90 degrees Fahrenheit, the contractor must reduce the mixing and delivery time from 1 ½ hours to 75 minutes. When air temperature is above 97 degrees Fahrenheit, they must reduce the time to 60 minutes. During curing process, the contractor needs to protect the working area from premature drying, temperature extremes, rain and flowing water. They are required to cure continuously without allowing the concrete to dry: this will prevent hydration of cement and hardening of concrete. They also need to maintain the curing temperature; which is above 50 degrees Fahrenheit. Therefore, in cold weather, they will need to provide temporary heat to maintain the required temperature. In addition, when air temperature is below 40 degrees Fahrenheit or above 80 degrees Fahrenheit, the concrete needs to be tested hourly and a set of compression specimens is made each time. Applied Fireproofing is required to be handled with care, as described in the manufacturer s instructions. Before applying the fireproofing, the material must be stored in dry area without any damages. Materials must be used prior to the expiration date. Specific environmental requirements are to maintain an air and substrate temperature of 40 degrees Fahrenheit for 24 hours before, during, and for 24 hours after application; provide temporary enclosures and heat as required. For proper curing and thorough drying of fire resistive materials, the general contractor has to ensure natural ventilation is adequate. If it is inadequate, the general contractor must provide forced air circulation. There is no specific requirement on temporary electrical and power for both cast-in-place concrete and applied fireproofing. Therefore, requirements for those are simply followed as described in the temporary utilities sections provided by the contractor.

9 Detailed Structural Systems Estimate: Since there are three sections to the building, the structural takeoff is broken down by the following sections: New West Building (West), Existing Hecht Company building (Hecht), and Gang of Four building (Gang of Four). The New West Building is a cast-in-place, 11- story with mechanical penthouse, 1 occupied below grade level and 3 levels or below grade parking. The Existing Hecht Company building consists of the existing structure and historic façade and it is an 8 story building. New floor slabs and steel are added to the existing structure. The Gang of Four is a cast-in-place, 8 story with 1 below grade level. The structural estimate includes the following: Foundation Systems Slab on Grade Concrete Beams and Columns Elevated Slab Steel Beams and Columns The foundation system contains spread footings and wall footings. Plywood framing was used to form the work. First the general contractor dug the footing and wraps the footing in plywood, then rebar was set and inspected. Concrete was poured after the form work was ready. For vertical wall, the general contractor used the PERI wall forming system which large wall panels that were units designed for wall construction. Some advantages of using the PERI wall forming systems: BFD Alignment Coupler - Just 1 component for all connections - the BFD Alignment Coupler Few panel widths - PERI TRIO requires only 6 widths. Practical 300 mm increments in panel size and the 720 mm wide TRIO panel reduce stocks and increase utilization.

10 The large panel - The large panel with 2 heights and 2 widths Easy to clean - ECC powder coating and closed panel sections makes cleaning easier Reference: PERI: On columns, 2x4s and plywood with clamps were used to form the work. For shear walls, since there was a shortage on the PERI, prefabricated formwork system; plywood and stick framing were used to form the walls. For elevated slabs, scaffolding with ALUMNA beams with plywood on top was used. This method was selected because the number of drop heads around the columns and down-turned beams at the slab edge. The general contractor preferred to use the prefabricated formwork system if permitted. The next page is a summary of the structural system estimate. Estimate from MC2 include material, labor and equipments. The breakdown cost from MC2 and the quantity takeoff sheets are attached on the back of this report.

11 GANG OF FOUR WEST HECHTS Foundation Foundation Decks, Slabs and toppings Slab on grade $34,230 Column Footings $176,346 C1 $27,958 Column footings $33,326 Stepped Footing $10,121 LEVEL 1 $27,958 Grade Beams $15,877 TOTAL $186,467 LEVEL 2 $27,958 Slab on Grade $35,405 LEVEL 3 $26,909 TOTAL $118,838 Drop Panels LEVEL 4 $26,909 C3 $7,896 LEVEL 5 $26,909 Drop Panels C2 $5,246 LEVEL 6 $26,909 C1 $3,895 C1 $6,014 LEVEL 7 $26,909 LEVEL 1 $149 LEVEL 1 $5,546 LEVEL 8 $34,444 LEVEL 2 $5,162 LEVEL 2 $11,510 Roof $15,856 LEVEL 3 $3,468 LEVEL 3 $9,377 Elevator Machine Room $5,333 LEVEL 3 UPPER $3,409 LEVEL 4 $9,377 TOTAL $274,052 LEVEL 4 $2,768 LEVEL 5 $9,377 LEVEL 5 $3,813 LEVEL 6, 7, 8 $27,975 Concrete Beams LEVEL 6 $2,954 LEVEL 9 $9,377 LEVEL 1 $4,934 Penthouse $671 LEVEL 10 $9,377 LEVEL 2 $467 TOTAL $26,289 LEVEL 11 $9,377 LEVEL 3 $1,104 Roof $9,377 LEVEL 4 $1,104 Decks, Slabs and toppings Penthouse $12,873 LEVEL 5 $1,104 C1 $28,243 TOTAL $142,699 LEVEL 6 $1,104 LEVEL 1 $33,033 LEVEL 7 $1,104 LEVEL 2 $20,646 Decks, Slabs and toppings LEVEL 8 $806 LEVEL 3 $20,646 C3 $45,393 TOTAL $11,727 LEVEL 3 UPPER $20,646 C2 $39,887 LEVEL 4 $20,646 C1 $39,887 Steel Beams with Fireproofing LEVEL 5 $20,646 LEVEL 1 $36,295 C1 $1,816 LEVEL 6 $16,186 LEVEL 2 $39,722 LEVEL 1 $116,247 LEVEL 7 $16,186 LEVEL 3 $39,722 LEVEL 2 $72,958 LEVEL 8 $15,856 LEVEL 4 $39,722 LEVEL 3 $65,326 Penthouse $4,514 LEVEL 5 $39,722 LEVEL 4 $72,559 Roof $18,856 LEVEL 6 $39,722 LEVEL 5 $59,844 TOTAL $236,104 LEVEL 7 $39,722 LEVEL 6 $65,085 LEVEL 8 $39,722 LEVEL 7 $64,850 Concrete Columns LEVEL 9 $39,722 LEVEL 8 $100,117 C2 $19,242 LEVEL 10 $39,722 LEVEL 9 $110,435 C1 $20,114 LEVEL 11 $39,722 Roof $125,744 LEVEL 1 $17,961 Roof $46,872 Elevator Machine Roof $466,576 LEVEL 2 $16,363 Penthouse $18,581 TOTAL $1,321,557 LEVEL 3 $15,340 Elevator Machine Room $14,005 LEVEL 3 UPPER $19,242 TOTAL $638,140 TOTAL STRUCTURAL COST FOR HECHTS $1,607,336 LEVEL 4 $17,137 LEVEL 5 $14,144 Concrete Beams LEVEL 6 $11,183 C2 $532 LEVEL 7 $13,411 C1 $4,397 LEVEL 8 $10,488 LEVEL 1 $8,489 Roof $1,333 LEVEL 2 $2,655 Elevator Machine Room $2,940 LEVEL 3 $2,272 TOTAL $178,898 LEVEL 4 $2,450 LEVEL 5 $2,822 TOTAL STRUCTURAL COST FOR GANG OF FOUR $560,129 LEVEL 6 $2,863 LEVEL 7 $2,863 LEVEL 8 $2,863 LEVEL 9 $2,863 LEVEL 10 $2,905 LEVEL 11 $2,863 Elevator Machine Room $4,679 TOTAL $45,516 Steel Members with fireproofing LEVEL 3 $2,506 LEVEL 4 $2,506 LEVEL 5 $2,506 LEVEL 6 $2,506 LEVEL 7 $2,506 LEVEL 8 $2,506 LEVEL 9 $2,506 LEVEL 10 $2,506 LEVEL 11 $2,506 Roof $10,620 Elevator Machine Room $22,495 TOTAL $55,669 Concrete Columns C4 $39,182 C3 $32,917 C2 $36,087 C1 $35,015 LEVEL 1 $27,014 LEVEL 2 $28,493 LEVEL 3 $19,687 LEVEL 4 $28,493 LEVEL 6 $28,493 LEVEL 7 $28,493 LEVEL 9 $28,715 LEVEL 10 $26,289 LEVEL 11 $24,665 Elevator Machine Room $2,068 Roof $15,456 TOTAL $401,067 TOTAL STRUCTURAL COST OF TERRELL PLACE $ 3,637,023 TOTAL STRUCTURAL COST OF WEST $1,469,558

12 General Conditions Estimate: General Conditions include field activities overhead and home office costs.* The duration of the project is 25 months and all the items are generated by unit price multiplying the number of units. An attached staffing plan shows how the general contractor staffs the project. Items include in the general conditions are: Personnel Office supplies and expenses Office and facilities expenses Safety and security Project transportation Temporary protection Temporary utilities Clean up and check out cost Equipment Quality control cost Permit and Insurance Payment and performance Bond are not included for this project because the general contractor is not providing a bond to the owner due to the existing relationship between the owner and the general contractor. A detail breakdown on each cost is included on the following spreadsheet. Different sources: D4, R. S. Means 2002 and AE 472 were used to use for estimating the general conditions. *note: This estimate does not include home office overhead.

13 DETAILED GENERAL CONDITIONS ESTIMATE 0100 PERSONNEL UNITS QTY U/P TOTAL Senior Superintendent wk 100 2, ,000 Finishes Superintendent wk 32 1,800 57,600 MEP Coordinator wk 8 1,450 11,600 Façade Engineer wk 8 1,450 11,600 Asst. Superintendent wk 44 1,600 70,400 Project Manager wk 92 2, ,000 Project Engineer wk 100 1, ,000 Field Engineer wk 52 1,500 78,000 Office Engineer wk ,000 Summer Intern wk ,400 Secretary wk ,400 Project Executive wk 50 3, ,000 Cost Engineer wk 50 1,500 75, PERSONNEL 1,273, OFFICE SUPPLIES & EXPENSES UNITS QTY U/P TOTAL Office and Eng. Supplies mo ,000 Copy Machine ea Blueprints set ,500 Photos set ,900 Drinking Water and Ice mo Radios proj Postage mo Cell phone mo , OFFICE SUPPLIES & EXPENSES 19, OFFICE & FACILITIES EXPENSES UNITS QTY U/P TOTAL Trailer Rent mo ,000 Trailer Set Up & Dismantle proj Office Maintenance/Janitorial mo ,500 Sanitary Facilities mo ,125 Project Signs ea OFFICE & FACILITIES EXPENSES 21, SAFETY AND SECURITY UNITS QTY U/P TOTAL Safety Supplies and Expense proj 1 2, ,000 Fire Extinguishers ea SAFETY AND SECURITY 2, PROJECT TRANSPORTATION/TRAVEL UNITS QTY U/P TOTAL Pickup Trucks mo , PROJECT TRANSPORTATION/TRAVEL 47, TEMPORARY PROTECTION UNITS QTY U/P TOTAL Temporary Ladders ea Temporary Fence LF ,878 Temporary Sidewalk LF , TEMPORARY PROTECTION 16, TEMPORARY UTILITIES UNITS QTY U/P TOTAL Temporary Power Installation & Distribution pro Temporary Water Consumption mo ,575 Temporary Power Consumption mo ,000 Temporary Heat mo ,000 Telephone mo ,250 Sewer and Water Fees proj 1 1,500 1, TEMPORARY UTILITIES 16, CLEAN UP AND CHECK OUT UNITS QTY U/P TOTAL Final Clean Up sq ft 1 57, ,720 Dumpsters mo , CLEAN UP AND CHECK OUT 67, EQUIPMENT UNITS QTY U/P TOTAL Small Tools and Supplies mo , EQUIPMENT 18, QUALITY CONTROL UNITS QTY U/P TOTAL Quality Control proj 1 8, QUALITY CONTROL 8, PERMITS AND INSURANCE UNITS QTY U/P TOTAL Building Permits proj 1 1% 500,000 Street & Side permit proj 1 5,000 Builder's Risk Insurance proj % 295, PERMITS AND INSURANCE 800,000 TOTAL GENERAL CONDITIONS 2,289,776 1

14 Project Schedule: A construction schedule is used for several reasons. One of the reasons is to keep track of how much work is done. Another reason is to show the relationship between each contractor; how they will work together in a limited space. Monthly update of the schedule is usually done. A detailed construction schedule is developed by P3. It is mainly broken down into three sections of the building. The schedule includes the major milestone dates: construction start date, Crane Erect date, Tenant work start date, and others. It also breaks down the structural systems by floor, MEP rough-in, distribution and finishes.

15

16 Cash Flow: A cash forecast is a schedule that summarizes the estimated cash receipts, estimated disbursements, and available cash balances for some period into the future. Owner uses the chart to predict how much they are paying each month and the general contractor uses the chart to predict how much they are paying the subcontractors each month. The difference between the Owner s cash flow and the general contractor s cash flow is the owner usually keeps a percentage of the bill as retainage. According to the contract, the owner pays a month after the general contractor sends him the bill. Usually there is a retainage and retainage will be pay off when the construction is completed. In that month before the owner pays the general contractor, the general contractor needs to pay interest. Some general contractors borrow loans from bank and pay interest of it. *note: Information about retainage on Terrell place is 10% of the project cost. Reference: Construction Contracting by Richard H. Clough and Glenn A. Sears

17 Terrell Place Cash Flow Schedule Start End Schedule ofpercent Name Date Date Values Total Aug-01 Sep-01 Oct-01 Nov-01 Dec-01 Jan-02 Feb-02 Mar-02 Apr-02 May-02 Jun-02 Jul-02 Aug-02 Sep-02 Oct-02 Nov-02 Dec-02 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 3-Oct General Conditions 8/21/2002 9/30/2003 $2,349, $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 $93,990 Mobilization 8/21/2002 9/15/2003 $450, $225,000 $225,000 Demolition 9/15/2003 1/15/2003 $750, $93,750 $187,500 $187,500 $187,500 $93,750 Historic Restoration 10/1/2002 4/30/2003 $4,500, $642,857 $642,857 $642,857 $642,857 $642,857 $642,857 $642,857 Sitework 9/4/2001 2/28/2002 $3,000, $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 Foundation Excavation 2/13/2002 2/28/2003 $1,125, $1,125,000 Foundation Concrete 3/4/2002 5/6/2002 $2,500, $833,333 $833,333 $833,333 Concrete Structure 5/1/2002 3/5/2003 $1,950, $195,000 $195,000 $195,000 $195,000 $195,000 $195,000 $195,000 $195,000 $195,000 $195,000 Concrete Floors 5/1/2002 3/5/2003 $1,100, $110,000 $110,000 $110,000 $110,000 $110,000 $110,000 $110,000 $110,000 $110,000 $110,000 Precast Panels 1/2/2003 5/5/2003 $3,650, $912,500 $912,500 $912,500 $912,500 HVAC Rough-in 4/14/2002 4/2/2003 $4,500, $195,652 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 $391,304 Fire Protection 7/29/2002 4/2/2003 $3,500, $437,500 $437,500 $437,500 $437,500 $437,500 $437,500 $437,500 $437,500 Plumbing Rough-in 7/29/2002 4/2/2003 $2,550, $318,750 $318,750 $318,750 $318,750 $318,750 $318,750 $318,750 $318,750 Partitions 3/5/2003 8/1/2003 $110, $22,000 $22,000 $22,000 $22,000 $22,000 Electrical 4/14/2002 7/15/2003 $3,500, $116,667 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $233,333 $116,667 Ceiling Grid 4/7/2003 5/16/2003 $600, $400,000 $200,000 HVAC Finishes 4/2/2003 7/15/2003 $2,917, $833,649 $833,649 $833,649 $416,825 Fixtures 3/4/2003 8/15/2003 $5,046, $917,596 $917,596 $917,596 $917,596 $917,596 $458,798 Painting 5/16/2003 9/10/2003 $500, $62,500 $125,000 $125,000 $125,000 $62,500 Carpet 2/14/2003 4/14/2003 $968, $242,000 $484,000 $242,000 Furnishing 3/14/2003 5/14/2003 $1,000, $250,000 $500,000 $250,000 Commissioning 5/30/2003 9/30/2003 $40, $10,000 $10,000 $10,000 $10,000 Total $46,607, Monthly Total $318,990 $912,740 $1,424,347 $1,424,347 $1,424,347 $1,330,597 $2,361,847 $1,570,181 $1,882,499 $1,856,961 $1,023,628 $1,023,628 $1,779,878 $1,779,878 $1,779,878 $1,779,878 $1,779,878 $2,692,378 $2,934,378 $4,060,973 $4,155,068 $2,613,068 $2,235,568 $1,702,077 $687,788 $166,490 Cum. Total $318,990 $1,231,730 $2,656,077 $4,080,424 $5,504,772 $6,835,369 $9,197,216 $10,767,397 $12,649,896 $14,506,857 $15,530,485 $16,554,112 $18,333,990 $20,113,868 $21,893,746 $23,673,623 $25,453,501 $28,145,879 $31,080,256 $35,141,230 $39,296,298 $41,909,367 $44,144,935 $45,847,012 $46,534,800 $46,701,290 Retainage $31,899 $91,274 $142,435 $142,435 $142,435 $133,060 $236,185 $157,018 $188,250 $185,696 $102,363 $102,363 $177,988 $177,988 $177,988 $177,988 $177,988 $269,238 $293,438 $406,097 $415,507 $261,307 $223,557 $170,208 $68,779 $16, % Retainage Payment Request $318,990 $912,740 $1,424,347 $1,424,347 $1,424,347 $1,330,597 $2,361,847 $1,570,181 $1,882,499 $1,856,961 $1,023,628 $1,023,628 $1,779,878 $1,779,878 $1,779,878 $1,779,878 $1,779,878 $2,692,378 $2,934,378 $4,060,973 $4,155,068 $2,613,068 $2,235,568 $1,702,077 $687,788 $166,490 $0 Payment Received $0 $287,091 $821,466 $1,281,912 $1,281,912 $1,281,912 $1,197,537 $2,125,662 $1,413,162 $1,694,249 $1,671,265 $921,265 $921,265 $1,601,890 $1,601,890 $1,601,890 $1,601,890 $1,601,890 $2,423,140 $2,640,940 $3,654,876 $3,739,562 $2,351,762 $2,012,012 $1,531,869 $619,009 $4,819,970 Cumulative Received $0 $287,091 $1,108,557 $2,390,470 $3,672,382 $4,954,294 $6,151,832 $8,277,494 $9,690,657 $11,384,906 $13,056,171 $13,977,436 $14,898,701 $16,500,591 $18,102,481 $19,704,371 $21,306,261 $22,908,151 $25,331,291 $27,972,231 $31,627,107 $35,366,668 $37,718,430 $39,730,442 $41,262,311 $41,881,320 $46,701,290 Contractor's Payment $50,000 $45,000 $40,000 $35,000 Payment in Thousands $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $ Months 1

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

Wisconsin Place Residential Chevy Chase, MD. Jenna Marcolina Construction Management

Wisconsin Place Residential Chevy Chase, MD. Jenna Marcolina Construction Management Technical Assignment #2 November 2, 2007 Table of Contents Executive Summary Page 2 A. Detailed Project Schedule Page 3 B. Site Layout Planning Page 5 C. Assemblies Estimate Page 7 D. Detailed Structural

More information

Technical Assignment #3 Alternate System and Methods Analysis

Technical Assignment #3 Alternate System and Methods Analysis Sarah Lippai Construction Management JetBlue Training Facility Orlando International Airport Primary Faculty Consultant: Dr. Horman Due Date: Monday, November 15 th, 2004 Technical Assignment #3 Alternate

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

Technical Assignment #2 Cost and Methods Analysis

Technical Assignment #2 Cost and Methods Analysis Technical Assignment #2 Cost and Methods Analysis Devin Learn Construction Management Dr. Messner Lancaster General Hospital Lancaster, PA 10/30/2006 Technical Assignment 2 A. Executive Summary... 1 B..Detailed

More information

4. Technical Report #3: Alternate System and Methods Analysis

4. Technical Report #3: Alternate System and Methods Analysis 4. Technical Report #3: Alternate System and Methods Analysis 4.1. Executive Summary This technical assignment covers the analysis of various building system cost, scheduling, site planning, and general

More information

Tech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey

Tech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey Tech Assignment 1 University Medical Center of Princeton Plainsboro Road, Township of Plainsboro, New Jersey David Bodnar CM Chris Maget 10/5/2009 Table of Contents Executive Summary...3 Project Schedule

More information

Capital One Lecture Hall Addition

Capital One Lecture Hall Addition Capital One Lecture Hall Addition 1680 Capital One Drive McLean, VA 22101 Construction Management Option October 5, 2005 Technical Assignment 2: Cost and Methods Analysis Capital One Lecture Hall Addition

More information

Research Facility Core and Shell 2012

Research Facility Core and Shell 2012 Research Facility Core and Shell 2012 Technical Report 2 Timothy Maffett Construction Management Advisor: Dr. Messner San Anto, California Submitted: October 12, 2012 Executive Summary Design for Research

More information

TECHNICAL ASSIGNMENT #2

TECHNICAL ASSIGNMENT #2 DEREK C. BAUER CONSTRUCTION MANAGEMENT DR. MICHAEL HORMAN TECHNICAL ASSIGNMENT #2 OFFICE/RETAIL BUILDING WASHINGTON, D.C. SUBMITTED: NOVEMBER 2, 2007 TABLE OF CONTENTS Executive Summary... 2 Detailed Project

More information

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building

More information

Suburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company

Suburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company Image Courtesy of The Whiting-Turner Contracting Company Penn State AE Senior Capstone Project Nicholas J. Kline Construction Option Advisor Mr. Ray Sowers 3 Water Drainage 2 Exterior 3 Water Drainage

More information

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley Existing Project Conditions General Conditions Estimate The Center for Health Research and Rural Advocacy is constructed under the supervision of the Geisinger Facilities Division. The project team develops

More information

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING THE TOWERS AT THE CITY UNIVERSITY OF NEW YORK NEW YORK CITY, NEW YORK ROBIN SCARAMASTRO AE 481 W DR. MEMARI EXECUTIVE SUMMARY The Towers at

More information

Existing Construction Conditions

Existing Construction Conditions Tracy Lo Terrell Place 575 7 th Street NW Washington DC September 23, 2002 Construction Management Existing Construction Conditions Executive Summary For this assignment, I have sent out an email to gather

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Project Estimate Summary

Project Estimate Summary Project Estimate Summary Project Cost Evaluation Table 4 shows the Construction Cost, CC/SF, Total Cost, TC/SF, the Building Systems Cost, and Building Systems Cost/SF based on the budget for. Table 4

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Phase B. Site

Phase B. Site Michigan Avenue, NW Washington, DC 2000 Technical Report 2 Table of Contents Executive Summary 2 A. Detailed Project Schedule...3 B. Site Layout Planning.... C. Assemblies Estimate..5 D. Detailed Mechanical

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

Cafeteria Modernization

Cafeteria Modernization United States Department of the Interior Cafeteria Modernization Michael Gorman Construction Management Dr. RILEY Department of the Interior Cafeteria Modernization 1849 C Street NW, Washington D.C. October

More information

Office Building. Katey Andaloro. Technical Assignment #1. Washington, D.C. Construction Management Dr. John Messner

Office Building. Katey Andaloro. Technical Assignment #1. Washington, D.C. Construction Management Dr. John Messner Washington, D.C Technical Assignment #1 Table of Contents Executive Summary 2 Project Schedule Summary 3 Building Systems Summary 5 Project Cost Evaluation 9 Site Plan of Existing Conditions 13 Local

More information

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction P P Periodica Polytechnica Architecture 48(2), pp. 87-92, 2017 https://doi.org/10.3311/ppar.10833 Creative Commons Attribution b Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 21450» Total Man Hours on Project: 669792» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 7, 20 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Technical Assignment #2

Technical Assignment #2 Technical Assignment #2 * Front elevation rendering photo provided by Alexander Building Construction George Andonie Construction Option AE Faculty Consultant: Rob Leicht October 16 th, 2013 Executive

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Assemblies Estimate. The total price was modified using the city cost index for Miami, Florida.

Assemblies Estimate. The total price was modified using the city cost index for Miami, Florida. Assemblies Estimate The assemblies estimate was performed using Means Cost Works 2004 for substructures. This substructure estimate was composed using the following systems: Strip footings (L.F.) Spread

More information

Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4

Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4 Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS Executive Summary.1 Detailed Project Schedule..2 3 Site Layout Planning 4 Assemblies Estimate 5 Detailed Structural Estimate..6 7 General Conditions

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

College Football Hall of Fame HAMMOCK R

College Football Hall of Fame HAMMOCK R - Contract Schedule MILESTONES DESIGN / PRECONSTRUCTION PROCUREMENT Construction Procurement CONSTRUCTION Hardscape / Landscape Hall Of Fame Building Sitework Earthwork A1060 Mobilize 5 18-Feb-13 A 22-Feb-13

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: 135019» Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor

More information

Prequalification Form

Prequalification Form 1.0 General Information Date: 1.1 Name of Firm _ County Telephone Toll Free Fax Website _ for Bid Purposes: Name Phone 1.2 Legal Identity: Sole Proprietorship Partnership Corporation Limited Liability

More information

Technical Report #2. Matthew R Peyton

Technical Report #2. Matthew R Peyton Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study

More information

Cinema-Dining Terrace Expansion. Suburbia, USA. Technical Report II. Image Courtesy of The Whiting-Turner Contracting Company.

Cinema-Dining Terrace Expansion. Suburbia, USA. Technical Report II. Image Courtesy of The Whiting-Turner Contracting Company. Cinema-Dining Terrace Expansion Suburbia, USA Technical Report II Image Courtesy of The Whiting-Turner Contracting Company Nicholas Kline Cinema-Dining Terrace Expansion 10/16/2013 Executive Summary This

More information

Construction Project Management

Construction Project Management Technical Assignment 1 Construction Project Management Cathy Neiderer Pasadena Elementary School Technical Assignment 1 Table of Contents Executive Summary... 3 Project Schedule Summary... 4 Building Systems

More information

Section 5 - Project Logistics

Section 5 - Project Logistics Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,

More information

PLEASE READ AND SIGN RESIDENTIAL ENERGY CODE AND EROSION CONTROL!

PLEASE READ AND SIGN RESIDENTIAL ENERGY CODE AND EROSION CONTROL! CITY OF SOLON REQUIREMENTS FOR OBTAINING A SOLON BUILDING PERMIT City Office Telephone Number: 319/624-3755 Public Works Director 319/631-5071 Building Official Telephone Number 319/338-4939 office 319/321-6563

More information

Technical Assignment No. 2 Submitted: Friday, November 2 nd, 2007

Technical Assignment No. 2 Submitted: Friday, November 2 nd, 2007 THE NEW DICKINSON SCHOOL OF LAW University Park, PA Steve Ayer Construction Management Option Technical Assignment No. 2 Submitted: Friday, November 2 nd, 2007 CPEP Website: http://www.engr.psu.edu/ae/thesis/portfolios/2008/ska124/

More information

Voorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #110 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #110 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 22420» Total Man Hours on Project: 1081124» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued Hanging

More information

REDLAND TECHNOLOGY CENTER

REDLAND TECHNOLOGY CENTER REDLAND TECHNOLOGY CENTER 540 Gaither Road, Rockville, MD Shawn Pepple Construction Management Technical Assignment #2 October 24, 2008 Dr. Messner TABLE OF CONTENTS 2.1 Executive Summary.. 3 2.2 Detailed

More information

TECHNICAL ASSIGNMENT 2

TECHNICAL ASSIGNMENT 2 PENN STATE AE SENIOR THESIS 2011-2012 TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis BRIANNE KYLE Construction Management Thesis Advisor: Dr. Chimay

More information

Executive Summary. Introduction 1. Project Delivery 1 Project Delivery Method 1 Constructability Concerns 2

Executive Summary. Introduction 1. Project Delivery 1 Project Delivery Method 1 Constructability Concerns 2 Executive Summary Introduction 1 Project Delivery 1 Project Delivery Method 1 Constructability Concerns 2 Safety 3 Public Safety 3 Construction Worker Safety 3 Project Planning 4 Demolition 4 Dewatering

More information

Section 4 - Design and Construction Overview

Section 4 - Design and Construction Overview Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

SECTION TEMPORARY FACILITIES AND CONTROLS

SECTION TEMPORARY FACILITIES AND CONTROLS SECTION 015000 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 GENERAL A. Each Contractor shall be responsible for arranging for and providing construction facilities and temporary controls as required

More information

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

Voigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1.

Voigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1. Voigt 1 Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1 Executive Summary Located in northwest Washington, D.C. at the corner of

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

Coverage Per Gallon. Gallons Required. Coverage Per Gallon

Coverage Per Gallon. Gallons Required. Coverage Per Gallon Date: 2/16/2011 CLIENT PROJECT NAME Page 1 of 1 The Author of these Worksheet Templates makes no guarantees to the accuracy of any estimates based on the formulas or formats provided in these Worksheets

More information

Section Safety Section Cleanup. None Required

Section Safety Section Cleanup. None Required January 2000 Page 1 of 6 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED SECTIONS PART 2 PRODUCTS The General Conditions of the Contract, General Requirements, and Supplemental

More information

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630) C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) 353-8115 Fax: (630) 852-4709 BUILDING PERMIT INFORMATION PACKET Revised: October 2018 Building Codes: International Residential

More information

Technical Assignment II

Technical Assignment II Morgantown, WV Technical Assignment II October 24, 2008 Dr. Riley Carmen A. Brutico III Construction Management Table of Contents Page Executive Summary 3 A. Detailed Project Schedule 4 B. Site Layout

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #105 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #105 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 24125» Total Man Hours on Project: 965963» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued MEP Rough-In

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #103 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #103 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 25215» Total Man Hours on Project: 915333» Crafts On Project This Week: 23» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued MEP Rough-In

More information

Technical Assignment 1

Technical Assignment 1 Westinghouse Electric Company Nuclear Power Engineering Campus Technical Assignment 1 Construction Project Management Mark Speicher Advisor: Dr. David Riley October 5 th, 2009 09 TABLE OF CONTENTS EXECUTIVE

More information

AE Senior Thesis Sixth Street 1

AE Senior Thesis Sixth Street 1 AE Senior Thesis 2010 700 Sixth Street 1 Shane Flynn Hometown Lakewood, PA Have a family stone business Flynnstone Arlington National Cemetery Visit website for more info www.flynnstonerocks.com Arlington

More information

Renovation of an Office Building in Washington D.C.

Renovation of an Office Building in Washington D.C. Renovation of an Office Building in Washington D.C. Washington, D.C. Technical Report #2 Lynn Appel Construction Management Faculty Consultant: Dr. Riley Submitted: Executive Summary Technical Assignment

More information

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format Basic Construction of the CANADACAR System The CANADACAR System is a prefabricated, engineered and constructed freestanding parking garage structure that utilizes superior technology combining pre-cast

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE # 5A Metal and Structural Steel 09/01/11

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE # 5A Metal and Structural Steel 09/01/11 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: 05 1200 - STRUCTURAL STEEL FRAMING Complete; SECTION: 05 2100 - STEEL JOIST FRAMING Complete;

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

Marriott Hotel Projects. July/August 2012 Progress Report

Marriott Hotel Projects. July/August 2012 Progress Report Marriott Hotel Projects July/August 2012 Progress Report Report Dated: September 13, 2012 Marriott Hotel Projects Progress Report This is the first monthly report prepared by Dewberry Architects Inc. for

More information

Construction Management Study

Construction Management Study Construction Management Study CONSTRUCTION MANAGEMENT STUDY A construction management study of the alternate concrete system was done to examine the impact that changing the building s superstructure material

More information

Library In Metropolitan Washington, D.C.

Library In Metropolitan Washington, D.C. 1 Library In Metropolitan Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Rob Leicht Picture Provided by Multivista 2 Picture Provided by Multivista 3 Building Name: Library

More information

Construction Update. November 2015

Construction Update. November 2015 Construction Update November 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 1 2

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

TYPICAL APARTMENT FLOOR PLAN

TYPICAL APARTMENT FLOOR PLAN PHOTO #7 PHOTO #8 EAST 8TH STREET (60' WIDE STREET) P L P L PHOTO #4 P L P L A B C D E F G H I #21 ASTOR PLACE 11 STORY BUILDING HEIGHT = 130' (11 STORIES) STAIR #3 BROADWAY (100' WIDE STREET) L STAIR

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

More information

Best Buy Corporate Building D (4) Richfield, MN

Best Buy Corporate Building D (4) Richfield, MN Best Buy Corporate Building D (4) Thesis Proposal Professor Boothby December 12 th, 2008 Executive Summary: The Best Buy Corporate Building D is a 6 story building with a total area of 304,610 square feet.

More information

Technical Assignment 2 Cost and Schedule Analysis October 24, 2008

Technical Assignment 2 Cost and Schedule Analysis October 24, 2008 Technical Assignment 2 and Schedule Analysis October 24, 2008 Meghan Graber Construction Management Dr. Riley Integrated Science Center College of William & Mary Williamsburg, Virginia Graber TABLE OF

More information

Technical Assignment #1 VA State Capitol Thesis

Technical Assignment #1 VA State Capitol Thesis Eric Fritz Construction Management Dr. Messner VA State Capitol Extension and Renovation Richmond, VA October 4, 2004 Technical Assignment #1 Technical Assignment #1 VA State Capitol Thesis By Eric Fritz

More information

Building Architecture

Building Architecture The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Alternate Formwork System Evaluation

Alternate Formwork System Evaluation Alternate Formwork System Evaluation Executive Summary The current handset aluminum formwork system used in the Navy League Building s parking garage is a labor and material (plywood) intensive process.

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Technical Report II. Science and Technology Center. Coppin State University Baltimore, MD

Technical Report II. Science and Technology Center. Coppin State University Baltimore, MD Science and Technology Center Coppin State University Baltimore, MD Faculty Advisor: Dr. Messner Submission Date: EXECUTIVE SUMMARY This report provides a thorough analysis of a detailed project schedule

More information

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural

More information

WORK AND PROJECT REQUIREMENTS

WORK AND PROJECT REQUIREMENTS WORK AND PROJECT REQUIREMENTS BID PACKAGE 3A SITE CONCRETE & CONCRETE TURNKEY CRABAPPLE MIDDLE SCHOOL REPLACEMENT April 26, 2018 EXHIBIT B CONSTRUCTION DOCUMENTS AND SPECIFICATIONS shall be acknowledged

More information

Residential Building Permits

Residential Building Permits JWS INSPECTION SERVICE 3407-43B Avenue Lloydminster, Saskatchewan S9V-2G1Ph:780-808-5704 Email: jsydoruk@sasktel.net Residential Building Permits A residential building is a one or two unit dwelling, along

More information

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department. City of Goshen Instructions for Residential Permit Application Why do you need a building permit? Your home is a large investment, and if your construction project does not comply with the codes adopted

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

3. Anatomy of a Tower Retrofit

3. Anatomy of a Tower Retrofit 3. Anatomy of a Tower Retrofit 3. Anatomy of a Tower Retrofit The comprehensive retrofit of tower apartment buildings is not a common type of building rehabilitation project in Canada. There are cases

More information

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single

More information

JUSTIN WINGENFIELD CONSTRUCTION MANAGEMENT DR. DAVID RILEY TECH 1. Table of Contents

JUSTIN WINGENFIELD CONSTRUCTION MANAGEMENT DR. DAVID RILEY TECH 1. Table of Contents Table of Contents Executive Summary... 3 Project Schedule Summary... 4 Building Systems Summary... 6 Project Cost Evaluation... 10 Site Plan of Existing Conditions... 14 Local Conditions... 15 Client Information...

More information

VII. RELOCATION OF UNDERGROUND STORM RETAINAGE SYSTEM (UGS)

VII. RELOCATION OF UNDERGROUND STORM RETAINAGE SYSTEM (UGS) VII. RELOCATION OF UNDERGROUND STORM RETAINAGE SYSTEM (UGS) BACKGROUND: Carderock Springs Elementary School has an underground storm water retainage system (UGS) to manage volumetric flow of water from

More information