Feasibility Study. October Bicycle and Pedestrian Bridge over the North Channel of the Boise River. Eagle Road/Highway 55

Size: px
Start display at page:

Download "Feasibility Study. October Bicycle and Pedestrian Bridge over the North Channel of the Boise River. Eagle Road/Highway 55"

Transcription

1 October 2015 Feasibility Study Bicycle and Pedestrian Bridge over the North Channel of the Boise River Eagle Road/Highway 55 Prepared for: Community Planning Association of Southwestern Idaho (COMPASS) City of Eagle, Idaho Prepared by: J-U-B ENGINEERS, Inc. Alan Cukurs, P.E.

2 This page intentionally left blank.

3 Table of Contents Executive Summary... 1 Introduction... 3 History... 3 Existing Bridge... 4 Eagle Road... 4 Purpose of Feasibility Study... 5 Bike/Pedestrian Bridge Design Criteria... 6 City of Eagle Approval Process... 7 ITD District 3 Conditions and Considerations... 8 Initial Concept Explored... 9 Initial Concept: Lightweight Aluminum Bike/Pedestrian Bridge... 9 J-U-B s Investigation of this Concept... 9 Other Options Explored Concrete Beams Supported by Additional Pile Supported Piers Adjacent to Existing Bridge Three Span Steel Truss Attached to Existing Bridge Steel Truss Clear-Span Bridge Additional Considerations Funding Options Summary Ownership and Maintenance Cost Considerations Recommendation Next Steps Agencies and Other Parties Consulted Agencies Other Involved Parties... 17

4 Executive Summary 1 Executive Summary This document is a feasibility study that examines attaching a bike/pedestrian bridge to the existing Eagle Rd/SH-55 Bridge crossing the north channel of the Boise River in Eagle, Idaho. The proposed bridge would provide north-south connectivity to existing and future Greenbelt pathway and neighborhoods. J-U-B ENGINEERS, Inc. (J-U-B) was hired by COMPASS to perform this study. As part of the feasibility study process, J-U-B: Reviewed work that was completed prior to this study Reviewed existing bridge plans Performed a site visit Analyzed the existing bridge foundations for supporting a lightweight aluminum structure Investigated other options for widening the bridge for bicycle and pedestrian use Developed planning-level cost estimates for bike/pedestrian bridge structure options Coordinated this effort with Idaho Transportation Department (ITD) Attended two Eagle City Council meetings, presented information, sought input Attended an Eagle Parks and Pathways Development Commission meeting, presented Draft Feasibility Study, sought input Prior to J-U-B s involvement in this project, an aluminum bridge was investigated by others. A lightweight aluminum bridge option was originally proposed to avoid the need for additional pile foundations, and to minimize or eliminate in-stream construction; thereby reducing the cost. J-U- B determined that the originally proposed aluminum structure would overload the existing foundation pile capacities at the piers and would require additional piles. Other bridge options were investigated after J-U-B determined that in-stream work and additional pile foundations would most likely be required for an aluminum bicycle and pedestrian structure attached to the existing SH-55 Bridge. The three other options considered in this study are: OPTION 1: Widen the existing bridge with precast concrete beams supported by extending the existing piers and abutments with additional pile foundations OPTION 2: Widen the existing bridge with steel trusses supported by extending the existing piers and abutments with additional pile foundations OPTION 3: An independent steel bike/pedestrian truss bridge spanning the entire north channel of the Boise River J-U-B recommends Option 1. Table 1 includes a summary of the pros and cons for the options.

5 Executive Summary 2 Table 1: Concept Pros and Cons Concept/Option Initial Concept: Lightweight Aluminum Cantilever Bridge Based on preliminary analysis, this option does not appear to be feasible. The existing pile foundation cannot support the additional weight of the aluminum pedestrian bridge, along with the pedestrian loads. This option has been eliminated as an option for this study. Concept/Option Pros Cons OPTION 1: Concrete Beams Attached to Existing Bridge with Additional Pile Supported Pier adjacent to existing bridge. Vertical Pedestrian bridge loads are supported independent of the existing bridge. OPTION 2: Three Span Steel Truss Attached to Existing Bridge with Additional Pile Supported Pier adjacent to existing bridge. Vertical Pedestrian bridge loads are supported independent of the existing bridge. OPTION 3: Separate Steel Truss Clear-span Bridge Cost effective Similar in appearance as the existing bridge. Shallow profile will not change the visual appearance of the site. Future widening of the bridge by ITD would include sidewalks for pedestrians and bicyclists, therefore the only cost to the city would be the initial cost for widening. Preliminary estimated cost of bridge structure is approximately $600,000. Lighter than precast concrete which may reduce the cost of the additional foundation A low profile truss may be visually appealing Future widening of the bridge by ITD would include sidewalks for pedestrians and bicyclists, therefore the only cost to the city would be the initial cost for widening After ITD widens the bridge, the steel truss could be salvaged for use on other City pathway projects. Would not impact the SH-55 Bridge in the immediate future and in the future when SH-55 Bridge is replaced. Design life is not dependent on the existing SH-55 Bridge. Preliminary estimated cost of bridge structure is approximately $800,000. Service life of the new pedestrian bridge will not be fully utilized as the new construction will be replaced once the older existing bridge has reached its service life. Instream work will be required to construct new piles and piers. Greater level of coordination between the State and the City for construction and maintenance of the pedestrian structure. The steel truss bridge would likely be more costly compared to precast concrete. Similar Cons as Option 1 regarding service life and coordination with other agencies. Initial cost may be the greatest for this option. Relatively tall structure and may be a visual distraction for the site because it is adjacent to the relatively low profile SH-55 bridge.

6 Introduction 3 Introduction History The City of Eagle (City); Walk and Ride Eagle, LLC; Two Rivers Community; and the Idaho Transportation Department (ITD) have been collaborating together for a new proposed bicycle pedestrian bridge adjacent to the west side of State Highway 55 (SH-55) over the north channel of the Boise River. The City applied for Project Development funding from Community Planning Association of Southwest Idaho (COMPASS) to study the feasibility of the project. The ultimate goal is to provide the needed technical analysis and details for the City to seek federal funding in the near future for design and construction of the project. Project Location Map Currently, there is no separate north-south bike/pedestrian river crossing on Eagle Rd/SH-55. It is currently improved with five lanes (four thru-lanes and one center lane) and shoulders on both sides. The function of the center lane is to provide adequate room for vehicle stacking at the intersections of Riverside Drive to the north and Island Woods Drive to the south. With the increase of developing neighborhoods and businesses in this area, bike/pedestrian use of the existing bridge shoulders on SH-55 have increased. Citizens walking along the shoulder of the SH-55 bridge (June 2015) The northeast corner of the bridge is in close proximity to a Hotel with a number of other businesses located near the north side of the bridge on both sides of SH-55. An existing east-west bike/pedestrian path is located on the north side of the river crossing underneath the bridge at the north abutment. Utilities such as overhead power are located adjacent to the east side of the bridge. East Side of SH-55 bridge, utilities, hotel, pathway connection (June 2015)

7 Introduction 4 Existing Bridge West side of SH-55 bridge, looking south (June 2015) The existing SH-55 Bridge was constructed in two phases. The east half of the bridge was constructed in 1974 and the west half of the bridge was constructed in In general, the bridge is in good condition. However, the typical design life for a bridge such as this is approximately 75 years, which would give a remaining theoretical service life of 34 years based on the original construction year. Eagle Road Future Plans In addition to the remaining service life of the existing bridge structure, it is important to consider if there are any plans to widen Eagle Road. Currently, there are no plans to widen this section of Eagle Road. It is not identified in the COMPASS 2040 Communities in Motion (CIM) long-range plan nor any of ITD s plans. Right-of-Way and Easements There is approximately 90-feet of ROW along the bridge portion of SH-55 and established public access easements on the west side of the existing bridge to the north where the bike/pedestrian underpass connects to the greenbelt and to the south where the bike/pedestrian underpass connects to an existing dirt detached pathway. Once the preferred bridge option is selected, an evaluation of any additional right-of-way and/or easements should occur as part of the project development process. An easement from the Idaho Department of Lands for the Bridge crossing over Boise River will likely be required. Additionally, consultation with the Shoshone Bannock Tribes will be required as part of the environmental process associated with federal funding. All other required permits will be identified as part of the project development process (next phase).

8 Introduction 5 Purpose of Feasibility Study J-U-B was retained by COMPASS to further develop the concept and feasibility of attaching or supporting a bike/pedestrian bridge adjacent to the existing SH-55 Bridge. Previously, there was some investigation done by others for the use of a three span aluminum bridge with an aluminum bridge deck for its relatively lightweight material properties. This concept was conceived to eliminate or minimize impacts to the existing bridge. J-U-B investigated the feasibility of attaching an aluminum bike/pedestrian structure to the existing bridge without additional foundations. Furthermore, this feasibility study includes an investigation of alternative bridge concepts for bike/pedestrian crossing at this location. Upon ITD s approval of this feasibility study, the Project Development phase will begin. During the Project Development phase, a project description, scope of work, purpose and needs statement, list of permits needed, maps, cost estimates, a public/stakeholder outreach plan and an environmental scan will be prepared. The intent of the Project Development phase is to further develop the preferred concept, develop a funding strategy, and prepare adequate project information to support a future grant application.

9 Bike/Pedestrian Bridge Design Criteria 6 Bike/Pedestrian Bridge Design Criteria The American Association of State Highway and Transportation Officials (AASHTO) Guide for the Planning, Design, and Operation of Pedestrian Facilities and the AASHTO Guide for the Development of Bicycle Facilities require the pathway on the bridge to be a minimum of 10 feet of clear width for bike/pedestrian traffic. Additionally, the bridge and the approaches to the bridge would need to meet Americans with Disabilities Act (ADA) requirements. The minimum design life of the structure is 75 years. The bike/pedestrian Bridge would not adversely impact the existing SH-55 Bridge.

10 City of Eagle Approval Process 7 City of Eagle Approval Process In consultation with City Planning and Zoning Staff and Parks and Recreation Staff, the following considerations will need to be made as the project moves forward: POINT OF CONTACT: Mike Aho, Director, City of Eagle Parks and Recreation is the point of contact and will distribute the plans to the staff responsible for the review of the project. DESIGN REVIEW: This project lies within a Scenic Overlay District. Therefore, the City Planning and Zoning Department requires Design Review. Since it would be a City application, no formal applications or paperwork other than plans would be necessary for submittal, and the project would be a staff level review. TIMELINE: Staff level review may take 3-4 weeks depending on internal workload. City staff would present the project through its various phases to the Eagle Parks and Pathways Development Commission and City Council.

11 ITD District 3 Conditions and Considerations 8 ITD District 3 Conditions and Considerations The following is an excerpt from an from Greg Vitley with ITD District 3 Environmental Planning and needs to be considered as this project progresses. 1. Use of the existing shoulder is not viable due to current standards/safety on a high speed facility. 2. Be responsible for all costs associated with development and operations (engineering studies, environmental clearances, plans, mitigation, construction, coordination with ITD for construction inspection, and long term inspection and maintenance of the structure and pathway). a. ITD s impression is that the cost estimates provided at the previous meeting may not be sufficient for the work being contemplated, and suggests you consider obtaining an independent assessment and estimate by a professional engineer. 3. Demonstrate to ITD through engineering analysis what potential impacts, connection mechanisms, and load reduction the additional structure will have on the bridge. 4. Provide required width for two way traffic throughout the length of the pathway and provide an ADA compatible facility for liability purposes if the structure is in ITD ROW. Facilities for a shared-use pathway are required to be a minimum of 10 wide. ADA accommodations will be required for the connection between the new pathway and the existing greenbelt/pathway at the northwest corner of the bridge. Please refer to the AASHTO Guide for the Planning, Design, and Operation of Pedestrian Facilities AND the AASHTO Guide for the Development of Bicycle Facilities. 5. If ITD gives access for parking on the southwest side, the southeast parking would be eliminated. ITD District 3 s Development Services Manager, Jim Morrison, has been coordinating with the City of Eagle on this particular request. 6. Continue close coordination with ITD and obtain ITD approval of the project plans prior to construction. ITD realizes the increase in development in the area and your proposal has merit to mitigate your concerns regarding bike and pedestrian circulation. Generally, state highways are not constructed for bike and pedestrian circulation, therefore, it is encouraged that comprehensive planning for bike and pedestrian circulation to the extent possible, be apart from state highways (i.e.: greenbelt connections from the south slough to the north slough). Thanks again for your proposal. If you have any questions please call me.

12 Initial Concept Explored 9 Initial Concept Explored Initial Concept: Lightweight Aluminum Bike/Pedestrian Bridge The initial concept bridge is a three-span aluminum truss bridge. The spans would be the same as the existing bridge span lengths of 75 feet, 90 feet, and 75 feet. The bridge would have a 10-foot-wide clear pathway and would meet ADA requirements. The initial concept would involve supporting the aluminum bridge with new cantilever supports attached at the abutments and piers (eliminating the construction of additional foundations in the Boise River at abutments and piers). The riding/walking surface (the bridge deck) of the bike/pedestrian bridge was assumed to be at the same elevation, or nearly the same elevation as the existing SH-55 bridge deck. This maintains the vertical clearance below the bike/pedestrian bridge; allows for greater visibility of pedestrians for safety; better fits the site conditions at the existing abutments and river banks, and integrates well with the existing sidewalks at the northwest corner of the bridge. Locating the bridge on the west side of the existing highway facilitates maintenance for debris removal, which tends to collect on the east side (upstream side) of the bridge. J-U-B s Investigation of this Concept Initial Concept: Lightweight Aluminum Bike/Pedestrian Bridge Connecting the proposed aluminum bridge to the existing bridge without additional foundation support is not feasible. The existing bridge piles will not support the additional load of: the aluminum bridge, the weight of bicycle and pedestrian traffic, and the additional cantilever supporting the aluminum bridge. These additional loads would increase the total loads beyond the available capacity of the existing piles. The capacity of the existing piles and loads are shown on the existing bridge drawings. The reserve capacity of the existing foundation was computed and found to be less than the additional loads imparted by the aluminum bridge and the bike and pedestrian traffic supported by the aluminum bridge. Additional steel piles are required to support the proposed aluminum bridge option.

13 Other Options Explored 10 Other Options Explored J-U-B s preliminary analysis indicates that using lightweight material such as an aluminum bridge does not result in eliminating the need for additional foundation elements to support the bike/pedestrian bridge. Therefore, other bridge materials and types were investigated for attaching to the existing bridge. A three span steel truss bridge option and three span precast concrete beam option attached to the existing bridge were considered. The options attaching to the existing bridge assumed the same span lengths, pathway width and overall geometry as the initial aluminum bridge option. A single clear span steel truss bridge independent of the existing bridge was also considered. Concrete Beams Supported by Additional Pile Supported Piers Adjacent to Existing Bridge Attachment of any bike/pedestrian structure to the existing bridge abutments and piers is in essence, widening the existing bridge. Along with the aluminum and steel truss options, precast concrete beams similar to the existing bridge can be used to support a pedestrian pathway. Precast concrete beams are readily available and are likely to be less costly compared to the steel and aluminum truss options. Because the same materials and structural elements are used, the precast concrete beams may be more harmonious with the existing bridge and pathway. Any option of attaching a bike/pedestrian structure to the existing SH-55 Bridge should consider the remaining service life of the existing bridge. The new bike/pedestrian bridge may likely be limited to a remaining service life of 34 years, at which time the existing SH-55 Bridge along with the newly built bike/pedestrian bridge would be replaced. Concrete Beams Attached to Existing Bridge Option, looking southeast Before photo (left) After rendering (right)

14 Other Options Explored 11 Concrete Beams Attached to Existing Bridge Option, looking under the west side of the bridge Before photo (left) After rendering (right) Three Span Steel Truss Attached to Existing Bridge West side of SH-55 bridge, north abutment (June 2015) A preliminary analysis indicates that the foundation type and substructure type for a steel truss bridge would be similar to that of an aluminum bridge. The length of a single steel pile would be greater than what would be required for an aluminum structure. However, the cost for the additional pile length may not be substantial. A steel truss bridge may be a more cost effective bridge compared to an aluminum bridge. A steel truss bridge tends to be less costly compared to aluminum. A steel superstructure is also more resistant to corrosion compared to aluminum. However, the steel structure is heavier and imparts greater load at the supports. This can increase the cost of the foundation and substructure. If a truss type structure attached to the existing bridge is desired, an overall cost comparison between an aluminum and steel bridge should be developed to determine the most cost effective truss option to attach to the existing bridge.

15 Other Options Explored 12 Steel Truss Clear-Span Bridge A separate steel truss bridge clear spanning the Boise River on the west side of SH-55 may be a feasible option. This would consist of a 240-foot-long single-span, 14 foot-tall steel truss bridge, which would not be attached or supported by the existing SH-55 Bridge. Some benefits of clear spanning the River with a detached steel truss bridge include: A minimum 75 year design life can be achieved by keeping the new bridge Steel Truss Clear-Span Bridge Detached from Existing Bridge Option, independent of the existing looking southeast After rendering SH-55 Bridge. In the future, when the SH-55 Bridge is replaced, the bike/pedestrian bridge would remain. A clear span structure eliminates and or minimizes any adverse impacts on the current and the future SH-55 Bridge. Namely, a clear span bike/pedestrian structure eliminates the risk of increasing scour of the existing or future bridge foundations. Furthermore, the clear span structure minimizes impacts to the environment. Additional Considerations An aluminum bridge deck may not be desirable if it propagates sharp sounds from bike and pedestrian use. The issues of deck noise from bicyclists and pedestrians should be considered. Steel Truss Clear-Span Bridge Detached from A concrete deck may be the most durable and Existing Bridge Option, looking under the west side of quiet deck type for this application. A wood deck the bridge - After rendering may not be desirable from a durability and maintenance aspect. A single span truss bridge, regardless of the materials being used, will require a truss that is approximately 14 feet tall. This height would extend above the existing traffic barrier by approximately six feet.

16 Other Options Explored 13 The visual appearance of aluminum, steel, and concrete should be considered in the context of the bridge site. Shiny metallic materials may not be desirable in a pathway setting. Weathered steel, which develops a reddish patina may be more desirable. It has the added benefit of being relatively maintenance free as painting is not required. Precast concrete beams may be more visually harmonious with the existing bridge. A bridge with a pathway width of 12 feet provides greater safety for bicyclists and pedestrians. This would moderately increase the cost of the bridge, but should not significantly change any environmental impacts compared to a bridge with a 10-foot-wide pathway. Option 1 with precast concrete beams, will be less costly to increase the pathway from a 10 ft. wide to a 12 ft. wide pathway, compared to the singles span steel truss option.

17 Funding Options 14 Funding Options It is the City s intent, in partnership with COMPASS, to apply for federal and/or state funding sources to fund the design and construction of the Bridge and associated pathway connections. Potential funding sources include but are not limited to: SURFACE TRANSPORTATION PROGRAM-TRANSPORTATION MANAGEMENT AREAS-TRANSPORTATION ALTERNATIVES PROGRAM (STP-TMA-TAP): this funding source is managed by COMPASS. Funds could be used for design and construction of the bike/pedestrian bridge. A local match of 7.34 percent would be required. TRANSPORTATION ALTERNATIVES PROGRAM (TAP): this funding source is managed by ITD. Funds could be used for design and construction of the bike/pedestrian bridge. A local match of 7.34 percent would be required. RECREATIONAL TRAILS PROGRAM (RTP): this funding source is managed by Idaho Department of Parks and Recreation (IDPR). Funds could be used for trailhead improvements, trail connections, abutments, shared costs, etc. A local match of 20 percent would be required. LAND AND WATER CONSERVATION FUND (LWCF): this funding source is managed by IDPR. Funds could be used for planning, acquisition and development of needed land and water areas and facilities. A local match of 50 percent would be required. Partnerships, donations, and local matching dollars are also possibilities for leveraging grant funds.

18 Summary 15 Summary All bike/pedestrian bridge options involving attachment to the existing SH-55 Bridge would require extending the existing concrete bridge abutments and piers and require additional steel piles. All bike/pedestrian bridge options involving attachment to the existing SH-55 Bridge would likely have a service life of 34 years (same as the remaining service life of the original SH-55 Bridge). Precast concrete beams similar to the existing bridge beams should be used to widen the existing bridge for a bike/pedestrian path. This would likely be comparable to the cost of other options that attach to the existing bridge. An agreement between the City and ITD should be investigated to determine how this option would be funded along with how the future bike/pedestrian path would be funded once the entire bridge is replaced. An example might be that the City provides the funding to construct the widening for the bike/pedestrian pathway in the near future, followed by ITD funding the future replacement of the entire bridge to include the bike/pedestrian pathway once the service life has been reached for the SH-55 Bridge, or when the bridge is replaced. Clear spanning the North Channel of the Boise River with a 240-foot-long single-span steel truss bridge would maintain a 75-year service life and would eliminate and or minimize impacts to the existing SH-55 Bridge. Ownership and Maintenance As part of the project implementation process, the City and ITD will need to communicate and agree on responsibilities for maintenance of the pedestrian bridge. Cost Considerations Based on planning-level cost estimates, it is anticipated that the precast concrete option (Option 1) would be approximately $200,000 less expensive compared to the single span steel truss option (Option 3). If it is decided that a 12 foot wide pathway is desired, Option 1 consisting of three relatively short spans would have a significantly smaller increase in cost compared to Option 3 which is a single long span. Shorter span bridges are exponentially more effective in resisting loads resulting in significantly less expensive superstructures. Therefore, the cost is less sensitive to widening for shorter span bridges compared to longer span bridges; thus Option 1 would be better suited to consider widening the pathway from a 10 foot wide to a 12 foot wide pathway than Option 3.

19 Recommendation 16 Recommendation J-U-B recommends that Option 1, precast concrete beams with supports located at the same locations as the existing bridge, be advanced into the project development phase. Furthermore, we recommend that the recommendation be confirmed by updating the cost comparison of the two options (Option 1 and Option 3) by quantifying costs associated with pathway approaches, environmental and other non-bridge specific costs. A 10 foot wide pathway on the bridge is the minimum recommended width. However, for a shared use facility, which could see significant use, a bridge with a 12 foot wide path should be considered in the cost estimate for the recommended option. Next Steps Next steps to be completed in the project development phase (Phase 3) include: Confirm total project costs for the two options to include those costs not related to the bridge structure type such as environmental and bridge pathway approach costs. It is anticipated that incorporating these costs will not change the recommendation. However, for purposes of evaluating options in a complete fashion, we recommend that the total anticipated project costs be quantified. Begin project development on the recommended (preferred) option. Pursue the funding applications for the recommended option.

20 Agencies and Other Parties Consulted 17 Agencies and Other Parties Consulted Agencies COMPASS Don Matson Principal Planner, Transportation ITD Aaron Bauges District III Project Manager Sabrina Minshall Director of Planning Mary Ann Waldinger Principal Planner, Modeling City of Eagle Mike Aho Director, Parks & Recreation , Ext 214 Steve Noyes Trails Coordinator, Parks & Recreation Mike Ebright, P.E. Group III Design Leader, Bridge Section Matt Farrar, P.E. Chief Bridge Engineer Trii Buu, P.E. Construction and Materials Greg Vitley ITD District III Environmental Planning Nichoel Baird-Spencer, AICP Planner III, Planning and Zoning , Ext 211 Other Involved Parties MAADI Group Inc. Alex de la Chevrotiere President Ext: 225 Provided weight of aluminum bridges for 8 feet and 10 feet wide pathway. Rick Tholen Two Rivers; Walk and Ride Eagle, LLC f4ister@gmail.com Initiated the project in the initial/early project stages (aluminum bridge concept)

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

REHABILITATION PACKAGE 4-a

REHABILITATION PACKAGE 4-a 4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.

More information

Red Wing Bridge Alternates

Red Wing Bridge Alternates Alternate 1 Tied Arch Alternate 2 Simple Span Truss Alternate 1 Design Drawing Alternate 2 Design Drawing Similar Bridge Design to Alternate 1 Similar Bridge Design to Alternate 2 Evaluation Matrix for

More information

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report SCCRTC- MP 19.43 San Lorenzo River Bridge Walkway Widening Feasibility Report May 19, 2016 INTRODUCTION Jacobs Engineering Group was selected to provide a feasibility report for the Santa Cruz County Regional

More information

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO.

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. 5 Agenda: 1. Welcome/Introductions 2. Progress & Updates Since Previous

More information

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 December 2, 2014 Stakeholder s Meeting Purpose of Stakeholder Meeting Discuss the project and why it s happening Describe the process

More information

Kathleen Marie Lacey, Chief Comprehensive Planner Boise City Planning and Development Services Department. State Street Memorandum of Understanding

Kathleen Marie Lacey, Chief Comprehensive Planner Boise City Planning and Development Services Department. State Street Memorandum of Understanding MEMORANDUM TO: FROM: Mayor and Boise City Council Kathleen Marie Lacey, Chief Comprehensive Planner Boise City Planning and Development Services Department DATE: September 9, 2005 RE: State Street Memorandum

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 66532 227 th STREET (TWP 45) OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY SEPTEMBER 12, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION April 2016 ELLIS Engineering Inc. 214 Martindale Road, Suite 201 St. Catharines, Ontario L2S 0B2 www.ellis.on.ca

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 57518 CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY AUGUST 27, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY AYRES

More information

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017 Chester Bridge Environmental Assessment (EA) CAG Meeting #2 October 12, 2017 Agenda Introductions Purpose & Need review and Merger Approval Review of the Conceptual Alternatives Recap of the Public Meeting

More information

Cast in place concrete parapet and Ministry standard sidewalk railing.

Cast in place concrete parapet and Ministry standard sidewalk railing. BRIDGE INSPECTION BRIDGE NO./NAME 62-003A: Farwell Canyon FSR (21.00 KM) Inspection Date: September 12 th 2012 Inspected By: D. Chen, J. Rupar Gilliatt Year Built: 2007 Number of Spans: 3 Span Lengths:

More information

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012 PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

Carpinteria Avenue Bridge Replacement Project Description Introduction

Carpinteria Avenue Bridge Replacement Project Description Introduction Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 2440 TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER DISTRICT M HENNEPIN COUNTY OCTOBER 23, 2008 PREPARED FOR THE MINNESOTA DEPARTMENT

More information

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199)) 11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House SAN ANTONIO STREET BRIDGE AT COMAL RIVER Open House May 1, 2018 SAN ANTONIO STREET BRIDGE AT COMAL RIVER, NEW BRAUNFELS COMAL COUNTY OPEN HOUSE MAY 1, 2018 5:00 P.M 7:00 P.M. New Braunfels Civic/Convention

More information

The Norwich Street Bridge

The Norwich Street Bridge The Norwich Street Bridge Class Environmental Assessment Open House May 17, 2017 6:30-8 p.m. Guelph City Hall Phase 1 Phase 2 Project File Our Study Process: This study is being undertaken as a Schedule

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 84505 CSAH NO. 14 OVER THE OTTER TAIL RIVER DISTRICT 4 - WILKIN COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.

More information

Dave Ward Drive Pedestrian Overpass

Dave Ward Drive Pedestrian Overpass Dave Ward Drive Pedestrian Overpass Prepared For: City of Conway February 2017 City of Conway Prepared by: 831 Parkway, Suite C Conway, Arkansas 72034 February 2017 Garver Project No.: 15017432 Table

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN

More information

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,

More information

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change

More information

STRUCTURE SELECTION REPORT

STRUCTURE SELECTION REPORT STRUCTURE SELECTION REPORT Prepared for: City & County of Denver 201 West Colfax Avenue Denver, CO 80202 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse Way Suite 600 Centennial, CO 80111 June

More information

MEMORANDUM OF UNDERSTANDING STATE STREET/IDAHO 44 TRANSIT CORRIDOR IMPLEMENTATION COORDINATION

MEMORANDUM OF UNDERSTANDING STATE STREET/IDAHO 44 TRANSIT CORRIDOR IMPLEMENTATION COORDINATION MEMORANDUM OF UNDERSTANDING STATE STREET/IDAHO 44 TRANSIT CORRIDOR IMPLEMENTATION COORDINATION Between ADA COUNTY ADA COUNTY HIGHWAY DISTRICT CAPITAL CITY DEVELOPMENT CORPORATION CITY OF BOISE CITY OF

More information

Pinellas Bayway Bridge Replacement

Pinellas Bayway Bridge Replacement PT-13: Coastal and Ocean Engineering ENGI.8751 Undergraduate Student Forum Faculty of Engineering and Applied Science, Memorial University, St. john s, NL, Canada MARCH, 2013 Paper Code. (PT-13 - Wadden)

More information

Grade-Separated Trail Crossings How Do We Get Over There?

Grade-Separated Trail Crossings How Do We Get Over There? Grade-Separated Trail Crossings How Do We Get Over There? 2008 National Trails Symposium Rory Renfro, Alta Planning + Design Scott Belonger, Loris and Associates Peter Loris, Loris and Associates PRESENTATION

More information

1 layer of untreated timber running planks, 254 mm x 89 mm.

1 layer of untreated timber running planks, 254 mm x 89 mm. BRIDGE INSPECTION BRIDGE NO./NAME N2-103: Kootenay By-Pass (9.50 km) Inspection Date: September 23 rd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 4 Span Lengths: Spans 1

More information

New Jersey Turnpike Authority

New Jersey Turnpike Authority New Jersey Turnpike Authority DOCUMENT UPDATE REQUEST Forward to Assistant Chief Engineer, Design Initiator Russell Saputo, PE Submittal Date 6/21/16 Firm Stantec Consulting Services Inc. Telephone 201-587-9040

More information

9 Conclusion. 9.1 Introduction

9 Conclusion. 9.1 Introduction 9 Conclusion 9.1 Introduction This final chapter presents a synthesis of the evaluation criteria leading to conclusions and recommendations. Also included is a summary of the current status of the Tappan

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

CITY COUNCIL AGENDA Workshop Meeting: Tuesday, October 24, 2017

CITY COUNCIL AGENDA Workshop Meeting: Tuesday, October 24, 2017 1 2 CITY COUNCIL AGENDA Workshop Meeting: Tuesday, October 24, 2017 AGENDA ITEM: 2 Hear and deliberate on handrail, lighting, and walkway replacement options for Key Allegro Bridge on Bayshore Drive. SUBMITTED

More information

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 6646 CSAH NO. 36 OVER THE RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

STAFF REPORT. Project Description. Proposal. Snyderville Basin Planning Commission From:

STAFF REPORT. Project Description. Proposal. Snyderville Basin Planning Commission From: STAFF REPORT To: Snyderville Basin Planning Commission From: Ray Milliner, County Planner Date of Meeting: May 12, 2015 Type of Item: Public Hearing, No Action Process: Administrative Review RECOMMENDATION:

More information

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6 NORFOLK COUNTY MISENER DAM Site Number 980501 LYNN STREET, PORT DOVER 0.65 km N of Highway 6 Ontario Structure Inspection Manual - Inspection Form Site Number: 980501 Inventory Structure Name Misener Dam

More information

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE HISTORIC BRIDGE REHABILITATION AND MAINTENANCE CASE STUDY

More information

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting:

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting: a contract within the Total Project Cost budget of $123.2 million, and to proceed with project construction not to exceed a Total Project Cost of $62.6 million. This motion is effective September 27, 2012.

More information

Comparison of Bridge Rehabilitation versus Bridge Replacement Concepts

Comparison of Bridge Rehabilitation versus Bridge Replacement Concepts Comparison of Bridge Rehabilitation versus Bridge Replacement Concepts Technical Memorandum Introduction The comparison of rehabilitation versus replacement of the Sellwood Bridge is being conducted in

More information

Bridge and Culvert Design Standards

Bridge and Culvert Design Standards 3004 ROADWAY DESIGN STANDARDS 3004.1 Roadway Design Roadway planning and design for the public road system shall conform to the following guidelines and referenced specifications. Use the most current

More information

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No.

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No. VENETIAN CAUSEWAY (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE FM No. 422713-2-22-01 Efficient Transportation Decision Making (ETDM): 12756 Project

More information

Northgate Pedestrian Bridge Feasibility Study Report

Northgate Pedestrian Bridge Feasibility Study Report Northgate Pedestrian Bridge Feasibility Study Report DRAFT July 2011 King County Department of Transportation Road Services Division Bridge and Structural Design Unit 201 South Jackson Street Seattle,

More information

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD To: Steve Gramm, SDDOT Memo From: HDR Project: SDDOT I-190 Silver Street Interchange Study Rapid City, SD HDR Project No. 000000000137390 Date: December 27, 2011 RE: Replacement of Existing I-190 Twin

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 27510 CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY MAY 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.

More information

Maclay Bridge Preservation Alternatives Analysis

Maclay Bridge Preservation Alternatives Analysis Maclay Bridge Preservation Alternatives Analysis Bitterroot River W of Missoula BR 9032(65) UPN 6296000 August 30, 2018 Maclay Bridge Preservation Alternatives Analysis August 30, 2018 Table of Contents

More information

Two glulam slab girders, 365 mm x 1825 mm spaced at 3065 mm c/c.

Two glulam slab girders, 365 mm x 1825 mm spaced at 3065 mm c/c. BRIDGE INSPECTION BRIDGE NO. N2-038: Findlay-Lavington FSR (12.60 KM) Inspection Date: September 25, 2012 Inspected By: R. Veitch, M. Hanson Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi

More information

NJTPA Transportation Improvement Program Fiscal Years

NJTPA Transportation Improvement Program Fiscal Years Routes Name: CR 571 Mileposts: 4.85 DBNUM: N1127 County Route 571/County Route 527, Reconstruction, Toms River Township This project is for intersection improvements at CR 571 and CR 527 in Tom s River

More information

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction Introduction This memo presents a summary of a three dimensional (3D) analysis of the Organic concept for the proposed St. Croix River bridge project. The Organic concept has several attributes that are

More information

Section 13. Guidelines for the Design of Ground Mounted Sign Supports

Section 13. Guidelines for the Design of Ground Mounted Sign Supports Section 13 BDC11MR-04 13.1 Introduction Highway signs fall into two main categories, which are subdivided as follows: 1. Overhead Signs a. Sign Bridge Structures (GO) b. Sign Cantilever Structures (GO)

More information

SCOPE OF WORK AND DELIVERABLES

SCOPE OF WORK AND DELIVERABLES 1.0 PROJECT OVERVIEW The State of Minnesota (State) has identified the need for the replacement of Bridge 5308, a railroad bridge that carries the Canadian Pacific Railroad (CP Rail) over Trunk Highway

More information

NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River. Public Information Center

NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River. Public Information Center NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River Public Information Center June 24, 2015 PROJECT STATUS Study Began January 2014 Data collection

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 3 - MORRISON COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 3 - MORRISON COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 49528 CSAH NO. 26 OVER THE MISSISSIPPI RIVER DISTRICT 3 - MORRISON COUNTY OCTOBER 25, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE Code Pre/Route AFE Function Part 0 1000 7116 1174 N Hadley Eisenbeisz Bridge Construction Engineer Rick Brandner Mitchell Area Darrell utter Assistant

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

Town of Moraga Canyon Road Bridge Replacement Project October 10, 2018 Town Council Presentation

Town of Moraga Canyon Road Bridge Replacement Project October 10, 2018 Town Council Presentation Town of Moraga Canyon Road Bridge Replacement Project October 10, 2018 Town Council Presentation OVERVIEW History of Events 2018 Bridge Redesign Construction Schedule 2 ACRONYMS AND TERMINOLOGY FHWA =

More information

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION PRELIMINARY DESIGN SUBMISSION REPORT For U.S. Route 130 Over Raccoon Creek Bridge Township of Logan Gloucester County, New Jersey Prepared By: Structural

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

DECEMBER 2017 LRFD BRIDGE DESIGN 2-1

DECEMBER 2017 LRFD BRIDGE DESIGN 2-1 DECEMBER 2017 LRFD BRIDGE DESIGN 2-1 2. GENERAL DESIGN AND LOCATION FEATURES The design of a bridge typically takes place in two major phases of work: preliminary design and final design. During preliminary

More information

The FHWA Long-Term Bridge Performance Program

The FHWA Long-Term Bridge Performance Program The FHWA Long-Term Bridge Performance Program by John M. Hooks, J. M. Hooks & Associates An ever-growing volume of cars and trucks move people and goods on modern bridges spanning highways and topographical

More information

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION Common Name: Camp Ripley Bridge Bridge Number: 4969 Identification Number: Location: Feature Carried: TH 115 Feature

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 75501 COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY SEPTEMBER 24, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 60019 MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS AUGUST 29, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF

More information

Highway Bridge Structure Components

Highway Bridge Structure Components Highway Bridge Structure Components Basic Bridge Components 1 Deck and 2 Stringer 3 Bearing 4 Pedestal 5 Footing 6 Piles 7 Underpass 8 Embakment 9 Live Loading Basic Bridge Components 1-Deck & wearing

More information

Road M3 Chisinau Giurgiulesti/ Romanian Border Extension and Rehabilitation Project Draft Feasibility Study (December 2008)

Road M3 Chisinau Giurgiulesti/ Romanian Border Extension and Rehabilitation Project Draft Feasibility Study (December 2008) BRIDGE INSPECTION MANUAL Preface The aim of the bridge inspection is to produce a report of the structure which gives a clear and accurate description of its condition at the time for comparison with earlier

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

Current Damage Assessment and Bridge Replacement

Current Damage Assessment and Bridge Replacement Current Damage Assessment and Bridge Replacement Bella Vista Property Owner s Association Bella Vista Flood Study Project No. 102594 Revision B 2/26/2018 Current Damage Assessment and Bridge Replacement

More information

MOVABLE SPAN BRIDGES. Bridge of Lions, St. Augustine, Florida

MOVABLE SPAN BRIDGES. Bridge of Lions, St. Augustine, Florida MOVABLE SPAN BRIDGES Bridge of Lions, St. Augustine, Florida Location and Description of Setting: The Bridge of Lions crosses Matanzas Bay (part of the Intercoastal Waterway) and connects the city of St.

More information

ACHD Bridge and Culvert Policy DRAFT

ACHD Bridge and Culvert Policy DRAFT ACHD Bridge and Culvert Policy DRAFT Standard Drawings and additional construction details are contained in the separate ACHD Bridge Design Guide and are hereto made part of this policy by reference. DEFINITIONS

More information

2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE

2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE Gusset Plates 2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE (50 Responses) Page 1 of 11 1) How many trusses are in your state? 2302 trusses owned by the state 8202 trusses owned by local agencies 2) What percentage

More information

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted:

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted: 6.24 - MX - MIXED USE DISTRICT 6.24.1 INTENT: The purpose of the MX Mixed Use District is to accommodate the development of a wide-range of residential and compatible non-residential uses (including major

More information

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE Conference Center at the Maritime Institute Anne Arundel County, Maryland Thursday, April 28, 2016 Two bridges in Two Months - Accelerated

More information

Project Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information

Project Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information Get Involved VDOT representatives will review and evaluate any information received as a result of the public information meeting. The comment sheet in this brochure is provided to assist in making your

More information

SOUTH MEDFORD INTERCHANGE BRIDGES

SOUTH MEDFORD INTERCHANGE BRIDGES Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

CHAPTER 18 TEMPORARY ROADS AND BRIDGES

CHAPTER 18 TEMPORARY ROADS AND BRIDGES Change #1 - Revised 12/12 CHAPTER 18 TEMPORARY ROADS AND BRIDGES 18.0 INTRODUCTION These guidelines are to be used to design temporary roads and bridges where traffic will be maintained at the construction

More information

Mn/DOT BRIDGE INSPECTION REPORT

Mn/DOT BRIDGE INSPECTION REPORT 08/13/2007 Page 1 of 5 County: City: Township: WINONA DRESBACH Section: 33 Township: 105N Range: 04W Span Type: NBI Deck: 5 Super: 6 Sub: 6 Chan: 8 Culv: N Location: Route: Control Section: AT MINN/WISC

More information

CONCEPTUAL BASELINE ALIGNMENT

CONCEPTUAL BASELINE ALIGNMENT BRIDGE ABUTMENT CONCEPTUAL BASELINE ALIGNMENT EXISTING RIGHT OF WAY, TYP. BELLA BELLA DR 3RD AVE REGION NO. 10 PROPOSED FOX ISLAND BRIDGE STATE WASH. FEDERAL AID PROJECT NO. SHEET NO. EXH-01 TOTAL SHEETS

More information

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Richard A. Wianecki, PE, Hardesty & Hanover, Okemos, MI Jane Abadir, PE, LEED A P, SOMAT Engineering Detroit, MI Rouge

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges

FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges Lesson Background and Overview: The last lesson introduced the topic of water management relative to forest roads and further explored

More information

Hamilton Rapid Transit Preliminary Design and Feasibility Study

Hamilton Rapid Transit Preliminary Design and Feasibility Study Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT

More information

- FACT SHEET - THE GUIDING PRINCIPLES

- FACT SHEET - THE GUIDING PRINCIPLES THE GUIDING PRINCIPLES The General Plan begins with seven ideas that together create a vision for the City s future. When the City approved the General Plan in 1994, these idea were dubbed the Seven Guiding

More information

Frequently Asked Questions Connecting Palo Alto

Frequently Asked Questions Connecting Palo Alto Frequently Asked Questions Connecting Palo Alto www.cityofpaloalto.org/connectingpaloalto General Project Questions Q1: What is Connecting Palo Alto? A1: Connecting Palo Alto (formerly the Palo Alto Rail

More information

PHASING CONSIDERATIONS FOR BRIDGES

PHASING CONSIDERATIONS FOR BRIDGES PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural

More information

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS

More information

Bridge Asset Management City of Battle Creek Planning and Projects

Bridge Asset Management City of Battle Creek Planning and Projects Bridge Asset Management City of Battle Creek Planning and Projects Michigan Bridge Conference, March 20, 2013 Gregory B. Rickmar P.E., Public Works Department, City of Battle Creek Alan Halbeisen, P.E.

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

CHICAGO AVENUE BRIDGE STRUCTURE TYPE STUDY MEMO APRIL 2015

CHICAGO AVENUE BRIDGE STRUCTURE TYPE STUDY MEMO APRIL 2015 CHICAGO AVENUE BRIDGE STRUCTURE TYPE STUDY MEMO APRIL 2015 TABLE OF CONTENTS INTRODUCTION 2 BRIDGE ALTERNATIVE 1.3 BRIDGE ALTERNATIVE 2 13 BRIDGE ALTERNATIVE 3 27 BRIDGE ALTERNATIVE 4 39 LIFTING SCHEMES.

More information

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally

More information