Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and Independent System Operators

Size: px
Start display at page:

Download "Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and Independent System Operators"

Transcription

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and Independent System Operators Docket No. AD14-14 COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY ON RTO/ISO REPORTS ON PRICE FORMATION ISSUES On November 20, 2015, the Federal Energy Regulatory Commission (Commission or FERC issued an Order Directing Reports, 1 which required Regional Transmission Operators and Independent System Operators (collectively, RTOs/ISOs to respond separately to specific questions regarding various price formation issues. 2 The Order Directing Reports indicated that responsive comments on the reports would be due 30 days after the reports were filed, but in a March 7, 2016 Notice of Filing, established April 6, 2016 as the deadline. Herein, please find the Comments of Southern California Edison Company (SCE on the RTO/ISO reports two of the price formation issues addressed, specifically pricing of fast-start resources and commitments to manage multiple contingencies. I. Pricing of Fast-Start Resources As explained in the Report submitted by the California Independent System Operator (CAISO, the current design of the CAISO market allows resources with a limited operating range to set the locational marginal price (LMP through the Constrained Output Generator 1 Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and Independent System Operators, 153 FERC 61,221 (2015 (Order Directing Reports. 2 Specifically, (1 pricing of fast-start resources; (2 commitments to manage multiple contingencies; (3 look-ahead modeling; (4 uplift allocation; and (5 transparency. 1

2 (COG pricing mechanism. Because this pricing mechanism exists, an extended pricing mechanism such as the extended LMP used by the Midcontinent Independent System Operator (MISO should generally be avoided, as it can potentially lead to, or exacerbate, system-wide over-generation conditions. However, it is important to note that in the CAISO s market, resources generally are not penalized for excess or deficient energy, and as such these resources can chase prices in real-time when prices are above their dispatch signal, which could exacerbate an over-generation condition. II. Commitments to Manage Multiple Contingencies SCE does not support the CAISO s proposal to constrain its market optimization to address N-1-1 contingencies. As described in the PJM Report, typically when an operator dispatches the system to control for N-1 contingencies, rather than multiple contingencies, multiple contingencies should not be incorporated into the day-ahead or real-time market models, because it would create a divergence between dispatch instructions and pricing. This should be generally the case under normal conditions. Under specific system conditions, such as, for example, an attack on the grid or extreme weather conditions, or in few special cases described in ISO/RTOs Reports, multiple contingencies may need to be accounted for. Further, these conditions may occur only in real-time, and only for a limited time frame. When N-1-1 contingencies, which are a form of multiple contingencies, must be accounted for under specific system conditions, it is preferable that they be managed through local reserve products rather than multiple contingency constraints. By procuring a local reserve in targeted areas, resources in those areas can address N-1-1 events and restore the reserves lost as a result of the contingencies. These reserves can be co-optimized with energy, subsequently priced and procured through the markets. This approach would be beneficial, because it would provide market signals to, for instance, build fast-starting units that can satisfy the needs (to have local resources that can address 30 minute restoration, and may be able to lower costs by satisfying the requirements while offline. 2

3 Since most ISO/RTOs co-optimize energy, operating reserves, and regulation, the cost of solving for multiple contingencies through reserves is already included in the clearing prices. The calculation of clearing prices for each of these products incorporates resource lost opportunity cost, thus fairly compensating resources for each product in the majority of intervals. As described in the NYISO Report, the NYISO has found locational reserve regions to be an effective means of managing multiple contingencies. Further, the NYISO Report states that: When managing multiple contingencies there is often a limited period of time for the NYISO s operators to restore the system to normal operating conditions following the occurrence of the first contingency. This time element can best be modeled in current market platforms using a locational reserve requirement. Alternatively, the multiple contingencies can be modeled directly as the simultaneous loss of several transmission or generation elements. This modeling method has costly side effects. The modeling must immediately account for reduction in transmission capability which results in inefficient use of the transmission system and result in higher total production costs due to the dispatch of less efficient generation. This effectively requires the ISO or RTO to maintain costly transmission level reserves by holding back usable transmission and generation ramp capability in order to be able to immediately react to the multiple contingency event, should it occur. By securing for multiple contingencies in its market evaluations the NYISO provides power suppliers with commitment and dispatch instructions relating to these conditions in the same manner as securing for the single event contingencies; there is no out-of-the-ordinary communication required. 3 Although costly side effects on transmission use as described above seem to refer, to a large extent, to modeling N-2 contingencies, they also apply to N-1-1 contingencies. This is because a limit (e.g., N-1 System Operating Limit, which is typically lower than a normal limit of the transmission system would have to be used in order to model N-1-1 contingency constraints. Further, under the CAISO s proposal, significant complexities would likely be imposed to the existing market construct. For instance, it can add complexities to the LMP price 3 Report of the New York Independent System Operator at p

4 formation that makes price discovery difficult. It may create challenges to the existing design of revenue sufficiency and require material changes to the current congestion revenue rights products and processes. Moreover, recovering from an N-1-1 event is only a real-time requirement based on actual conditions when a specific event occurs. In contracts, when enforcing N-1-1 recovery in the day-ahead market, a day-ahead solution may represent false precision, in that the solution may not solve for actual physical need of a real-time N-1-1 contingency due to the impacts of virtual transactions and uncertainties in load/renewables forecasts embedded in the day-ahead solution, as well as other system changes such as outages that can take place after the day-ahead market closes. Therefore, in managing N-1-1 contingencies, using locational reserve products (as is being done or contemplated in MISO, PJM and NYISO is generally preferable to incorporating multiple contingency constraints as proposed by the CAISO. Respectfully submitted, ANNA VALDBERG ERIN K. MOORE /s/ Erin K. Moore By: Erin K. Moore Attorneys for SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California Telephone: ( Facsimile: ( erin.moore@sce.com Dated: April 6,

5 CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY ON RTO/ISO REPORTS ON PRICE FORMATION ISSUES upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Rosemead, California, this 6 th day of April, /s/ Vicki Carr-Donerson Vicki Carr-Donerson, Case Analyst SOUTHERN CALIFORNIA EDISON CO Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Docket No. ER06-615-041 COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY ON THE

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation ) ) ) Docket Nos. ER09-241-000 INTERVENTION AND COMMENTS OF SOUTHERN CALIFORNIA

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION POST-TECHNICAL CONFERENCE COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION POST-TECHNICAL CONFERENCE COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent

More information

Price Formation Education Session Day 1 Economic Dispatch

Price Formation Education Session Day 1 Economic Dispatch Slide 1 Price Formation Education Session Day 1 Economic Dispatch Anthony Giacomoni Melissa Maxwell Laura Walter December 4, 2017 Slide 2 Disclaimer Slide This is not a committee meeting. This session

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Uplift Cost Allocation and Transparency ) in Markets Operated by Regional ) Docket No. RM17-2-000 Transmission Organizations and

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation ) ) ) Docket No. ER14-480-000 INTERVENTION AND COMMENTS OF SOUTHERN CALIFORNIA

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) Docket No. RM Operator Corporation )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) Docket No. RM Operator Corporation ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. RM19-2-000 Operator Corporation ) COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION MOTION TO INTERVENE, COMMENTS, AND PROTEST OF SOUTHERN CALIFORNIA EDISON

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION MOTION TO INTERVENE, COMMENTS, AND PROTEST OF SOUTHERN CALIFORNIA EDISON UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Bloom Energy Corporation ) Docket No. EL18-10-000 MOTION TO INTERVENE, COMMENTS, AND PROTEST OF SOUTHERN CALIFORNIA EDISON In accordance

More information

Integrating High Levels of Variable Renewable Energy Sources

Integrating High Levels of Variable Renewable Energy Sources Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in ) Markets Operated by Regional ) Docket Nos. RM16-23; AD16-20 Transmission Organizations and )

More information

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011 Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration March 7-8, 2011 Agenda Greetings and Introductions Introduction of the Midwest ISO Overview of the Midwest

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southern California Edison ) Docket No. ER Company )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southern California Edison ) Docket No. ER Company ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison ) Docket No. ER04-1209-000 Company ) MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF FILING OF THE CALIFORNIA

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Grid Resilience in Regional Transmission ) Organizations and Independent System ) Docket No. AD18-7-000 Operators ) ) REPLY COMMENTS

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) PROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) PROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) ) ) ) Docket No(s) ER08 1281 005, 006, 007 and 010 PROTEST OF THE INDEPENDENT MARKET

More information

Price Formation. Eric Ciccoretti Attorney-Advisor Office of Energy Policy and Innovation Federal Energy Regulatory Commission June 13, 2017

Price Formation. Eric Ciccoretti Attorney-Advisor Office of Energy Policy and Innovation Federal Energy Regulatory Commission June 13, 2017 Price Formation Eric Ciccoretti Attorney-Advisor Office of Energy Policy and Innovation Federal Energy Regulatory Commission June 13, 2017 The views and opinions presented are mine alone and do not reflect

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) COMMENTS OF SOUTHWEST POWER POOL, INC.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) COMMENTS OF SOUTHWEST POWER POOL, INC. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Fast-Start Pricing in Markets Operated by Regional Transmission Organizations and Independent System Operators Docket No. RM17-3-000

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Promote Policy and Program Coordination and Integration in Electric Utility Resource Planning. Rulemaking

More information

FERC Docket EL Fast-Start Resources

FERC Docket EL Fast-Start Resources FERC Docket EL18-34-000 Fast-Start Resources Anthony Giacomoni December 18, 2018 PJM 2017 Session Objectives Review motivation for the FERC Order regarding faststart resources Review PJM s current special-pricing

More information

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Patricio Rocha Garrido Lisa Morelli Laura Walter Disclaimer This is not a committee meeting. This session is for educational

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Grid Reliability and Resilience Pricing ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Grid Reliability and Resilience Pricing ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Grid Reliability and Resilience Pricing ) Docket No. RM18-1-000 REPLY COMMENTS OF PJM INTERCONNECTION, L.L.C. ON THE UNITED STATES

More information

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Scott Harvey Member: California Market Surveillance Committee Folsom, California May 19, 2014 TOPICS ISO New England PJM MISO New York ISO

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Incentives for Distributed Generation and Distributed Energy Resources.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket No. EL

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket No. EL UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No. EL18-34-000 COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR THE CALIFORNIA INDEPENDENT

More information

U. S. SPOT MARKET REGULATION

U. S. SPOT MARKET REGULATION U. S. SPOT MARKET REGULATION NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION & MICHIGAN PUBLIC SERVICE COMMISSION TBILISI, GEORGIA November 30,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Revised Regulations Governing Small Power Production and Cogeneration Facilities ) ) ) ) ) Docket No. RM05-36-000 SOUTHERN CALIFORNIA

More information

August 15, Secretary. Dear Secretary Bose: July 15, Anna McKenna. Folsom, CA

August 15, Secretary. Dear Secretary Bose: July 15, Anna McKenna. Folsom, CA August 15, 20122 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System Operator Corporation Docket Nos.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) Docket No. EL18-34-000 ANSWER AND MOTION FOR LEAVE TO ANSWER OF THE INDEPENDENT MARKET MONITOR

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. EL

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. EL UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) Docket No. EL18-35-000 COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR THE CALIFORNIA INDEPENDENT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnecton, L.L.C. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnecton, L.L.C. ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnecton, L.L.C. ) Docket No. ER17-1138-000 MOTION TO INTERVENE AND PROTEST OF THE MISO INDEPENDENT MARKET MONITOR RELATED

More information

BILLING CODE P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. [Docket No. RM ]

BILLING CODE P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. [Docket No. RM ] This document is scheduled to be published in the Federal Register on 05/04/2018 and available online at https://federalregister.gov/d/2018-09455, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF

More information

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Regional Transmission Organizations and ) Docket No. RM16-5-000 Independent System Operators ) COMMENTS OF THE PENNSYLVANIA

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: December 6, 2017 Re: Decision on contingency

More information

Draft Whitepaper to Platte River Board of Directors

Draft Whitepaper to Platte River Board of Directors Draft Whitepaper to Platte River Board of Directors Report on Organized Power Markets RTOs and ISOs Presented for the October 2016 Board Meeting Overview This report on the potential formation of a regional

More information

March 18, Docket Nos. ER and EL Exceptional Dispatch Informational Report Covering Period up to February 2019

March 18, Docket Nos. ER and EL Exceptional Dispatch Informational Report Covering Period up to February 2019 California Independent System Operator Corporation March 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Docket No. RM16-5-000 Regional Transmission Organizations ) and Independent System Operators

More information

Regional Flexibility Markets

Regional Flexibility Markets CAISO Contingency Modeling Alternative: Regional Flexibility Markets March 2014 Southern California Edison Outline Concerns with the CAISO s N-1-1 proposal Alternative approach: Regional Flexibility Markets

More information

September 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Agreement.

September 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Agreement. Regulation James A. Cuillier Director FERC Rates & Regulation September 9, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

October 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto; and the Service Agreement.

October 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto; and the Service Agreement. James A. Cuillier Director FERC Rates & Regulation October 9, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant

More information

Convergence Bidding. Brian Theaker, Regional Governmental Affairs Manager The Williams Companies, Inc. All rights reserved.

Convergence Bidding. Brian Theaker, Regional Governmental Affairs Manager The Williams Companies, Inc. All rights reserved. Convergence Bidding Brian Theaker, Regional Governmental Affairs Manager 2006 The Williams Companies, Inc. All rights reserved. Benefits of Convergence Bidding Promotes convergence of Day-Ahead and Real-Time

More information

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket Nos. ER

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket Nos. ER BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket Nos. ER16-372-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE PENNSYLVANIA PUBLIC UTILITY COMMISSION IN SUPPORT OF

More information

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability

More information

THE MIDWEST INDEPENDENT TRANSMISSION SYSTEM OPERATOR (MISO) AND THE INDIANA UTILITY REGULATORY COMMISSION. Commissioner David Hadley And Bob Pauley

THE MIDWEST INDEPENDENT TRANSMISSION SYSTEM OPERATOR (MISO) AND THE INDIANA UTILITY REGULATORY COMMISSION. Commissioner David Hadley And Bob Pauley THE MIDWEST INDEPENDENT TRANSMISSION SYSTEM OPERATOR (MISO) AND THE INDIANA UTILITY REGULATORY COMMISSION Commissioner David Hadley And Bob Pauley Why Do We Want Transmission Companies Like RTOs? Prevent

More information

December 17, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

December 17, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation December 17, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ELECTRIC STORAGE PARTICIPATION ) IN REGIONS WITH ORGANIZED ) DOCKET NO. AD16-20-000 WHOLESALE ELECTRIC MARKETS ) ) RESPONSE OF THE

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

The Virtues of A Virtual RTO

The Virtues of A Virtual RTO The Virtues of A Virtual RTO Jim Mayhew Mirant September 26, 2003 Harvard Electricity Policy Group 1 A Virtual RTO? An Organization That is a RTO in All but Name? Minimum Attributes? Regional Security

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Key Issues and Consideration in Market Design, Operational and Oversight

Key Issues and Consideration in Market Design, Operational and Oversight Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities

More information

Price Formation. PJM Market Participants February 14, Joe Bowring Catherine Tyler

Price Formation. PJM Market Participants February 14, Joe Bowring Catherine Tyler Price Formation PJM Market Participants February 14, 2019 Joe Bowring Catherine Tyler ISSUES WITH PJM ORDC 2019 www.monitoringanalytics.com 2 PJM ORDC Shape PJM s ORDCs persistently raise prices and procure

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent Operator ) Corporation ) Docket No. ER10-500-000 MOTION FOR CLARIFICATION OR IN THE ALTERNATIVE REHEARING

More information

Single Schedule Market Pricing Issues

Single Schedule Market Pricing Issues Single Schedule Market Pricing Issues Presented by Scott Harvey and Susan Pope Phase 1 - Session 3 Module G: Market Power Mitigation June 29, 2017 Toronto, Ontario TOPICS June 2: Module A: Energy Pricing

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) New York Independent System Operator, Inc. ) Docket No. ER17-446-000 ) MOTION TO INTERVENE AND COMMENTS OF THE MARKET MONITORING

More information

Closer Look At EPA Proposed Rule 111D: Utility Perspective

Closer Look At EPA Proposed Rule 111D: Utility Perspective Closer Look At EPA Proposed Rule 111D: Utility Perspective The Council of State Governments Annual Conference August 11, 2014 Lopa Parikh Director of Federal Regulatory Affairs Edison Electric Institute

More information

ELECTRIC TRANSMISSION 201: Markets, ISO/RTOs and Grid Planning/Operations

ELECTRIC TRANSMISSION 201: Markets, ISO/RTOs and Grid Planning/Operations ELECTRIC TRANSMISSION 201: Markets, ISO/RTOs and Grid Planning/Operations Kevin Reeves Managing Director, Transmission Strategy American Electric Power Organized Markets Organized markets are managed by

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Grid Resilience in Regional Transmission ) Organizations and Independent System ) Docket No. AD18-7-00 Operators ) JOINT REPLY COMMENTS

More information

UTC Activity Pre and Post 162 FERC 61,139: January 1, 2017 through March 8, 2018

UTC Activity Pre and Post 162 FERC 61,139: January 1, 2017 through March 8, 2018 UTC Activity Pre and Post 162 FERC 61,139: January 1, 2017 through March 8, 2018 The Independent Market Monitor for PJM April 3, 2018 Monitoring Analytics 2018 www.monitoringanalytics.com This page intentionally

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional

More information

Secretary. Dear Secretary Bose: February. 16, 2013 to. Anna McKenna. Deputy General Counsel. Folsom, CA

Secretary. Dear Secretary Bose: February. 16, 2013 to. Anna McKenna. Deputy General Counsel. Folsom, CA April 15, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System Operator Corporation Docket Nos.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy Trading and Marketing Co. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy Trading and Marketing Co. ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Duke Energy Trading and Marketing Co. ) Docket No. EL03-152-000 PETITION FOR REHEARING OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

SUBMITTED VIA E-TARIFF FILING. August 4, 2017

SUBMITTED VIA E-TARIFF FILING. August 4, 2017 Millennium Tower 719 Second Avenue, Suite 1150 Seattle, WA 98104 (206) 623-9372 Phone (206) 623-4986 Fax SUBMITTED VIA E-TARIFF FILING August 4, 2017 The Honorable Kimberly D. Bose Secretary Federal Energy

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Docket No. ER06-615- REPORT OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Pacific Gas and Electric Company (U39E) for Approval of Demand Response Programs, Pilots and Budgets for Program Years 2018-2022.

More information

and on peak new ISO the monthly

and on peak new ISO the monthly March 1, 20122 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 RE: California Independent System Operator Corporation Docket No.

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP PJM 2017 2 Dispatch Rate Definition:

More information

ACKNOWLEDGEMENT. The following members of the Department of Market Monitoring contributed to this report:

ACKNOWLEDGEMENT. The following members of the Department of Market Monitoring contributed to this report: ACKNOWLEDGEMENT The following members of the Department of Market Monitoring contributed to this report: Eric Hildebrandt Keith Collins Jeffrey McDonald Brad Cooper Amol Deshmukh Erdal Kara Serhiy Kotsan

More information

January 15, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

January 15, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation January 15, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset Stakeholder Comment Template Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted Fernando E. Cornejo fernando.cornejo@sce.com Southern California Edison November 6, 2018 Please use this

More information

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal October 18, 2012 Prepared by: Market and Infrastructure Development Version: 1.0 California Independent System Operator Contents

More information

March 15, Secretary. Washington , DC Re: the above. referenced Corporation included in. granted in 2012.

March 15, Secretary. Washington , DC Re: the above. referenced Corporation included in. granted in 2012. March 15, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System Operator Corporation Docket Nos.

More information

Revenues from Ancillary Services and the Value of Operational Flexibility

Revenues from Ancillary Services and the Value of Operational Flexibility Revenues from Ancillary Services and the Value of Operational Flexibility October 31, 2002 LCG Consulting The Issue Research Highlights In a restructured electricity industry, markets govern the operation

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Docket No. RM16-5-000 Regional Transmission Organizations ) and Independent System Operators

More information

IN THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

IN THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION IN THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Alliance Companies, et al. Docket Nos. EL02-65-000, et al. INITIAL REPORT OF THE NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Udi Helman, Principal Market Economist Anjali Sheffrin, Chief Economist / Director, Market and Product Development

More information

Congestion Revenue Rights Auction Efficiency Track 1A Draft Final Proposal Addendum

Congestion Revenue Rights Auction Efficiency Track 1A Draft Final Proposal Addendum Congestion Revenue Rights Auction Efficiency March 8, 2018 Prepared by: M&IP California Independent System Operator Table of Contents 1 Executive Summary... 3 2 Initiative organization and scope... 5 2.1

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 31. Day-Ahead Market... 2 31.1 Bid Submission and Validation in the Day-Ahead Market... 2 31.2 Day-Ahead MPM Process... 2 31.2.1 The Market Power Mitigation Process... 3 31.2.2 Bid Mitigation

More information

Stepped Constraint Parameters. Issue Paper

Stepped Constraint Parameters. Issue Paper Stepped Constraint Parameters May 5, 2016 Table of Contents 1. Introduction... 3 2. Plan for Stakeholder Engagement... 4 3. Transmission constraint relaxation parameter... 5 4. Shift factor effectiveness

More information

FERC Order 764 Settlements

FERC Order 764 Settlements FERC Order 764 Settlements Spring Release 2014 The information contained in these materials is provided for general information only and does not constitute legal or regulatory advice. The ultimate responsibility

More information

Markets Report. Jennifer Warner-Freeman Senior Economist, Market Analysis January 22, PJM 2018

Markets Report. Jennifer Warner-Freeman Senior Economist, Market Analysis January 22, PJM 2018 Markets Report Jennifer Warner-Freeman Senior Economist, Market Analysis January 22, 2018 www.pjm.com Executive Summary PJM Wholesale Cost for 2017 was $49.64/MWh, up from full-year 2016 costs of $47.49/MWh.

More information

Attached to this Notice is a description of the seven panels that will be conducted at the technical conference.

Attached to this Notice is a description of the seven panels that will be conducted at the technical conference. This document is scheduled to be published in the Federal Register on 02/22/2018 and available online at https://federalregister.gov/d/2018-03649, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Amended Application of Southern California Edison Company (U 338-E) for Approval of Energy Efficiency Rolling Portfolio Business Plan.

More information

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017 Centralized Energy & Operating Reserves Markets: A MISO perspective 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

More information

6.1.9 IFM Initial Conditions

6.1.9 IFM Initial Conditions 6.1.9 IFM Initial Conditions A Generating Unit that was committed in the previous day s Day-Ahead Market (IFM or RUC) run (TD-2 for TD-1) but was de-committed before HE24 would normally be considered initially

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Metcalf Energy Center LLC ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Metcalf Energy Center LLC ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Metcalf Energy Center LLC ) Docket No. ER18-240-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

NEW YORK INDEPENDENT SYSTEM OPERATOR

NEW YORK INDEPENDENT SYSTEM OPERATOR Rate Schedule 1 Study Status Update Review of Other ISO/RTO s March 2011 TABLE OF CONTENTS 1.0 RATE STRUCTURES AT OTHER ISO S/RTO S...1 1.1 PJM...1 1.2 ISO-New England...3 1.3 California ISO...6 1.4 Midwest

More information

Advancing Renewable Alternatives

Advancing Renewable Alternatives Advancing Renewable Alternatives FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 Abigail Krich President, Boreas Renewables About Boreas Renewables

More information

Applying PROBE for Congestion Analysis and Grid Planning

Applying PROBE for Congestion Analysis and Grid Planning Applying PROBE for Congestion Analysis and Grid Planning August 1, 2003 Jim Mitsche JMitsche@power-gem.com 518 393 3834 1 Topics Analysis Objectives Nature of Congestion Cost & Cost Calculation What is

More information

December 3, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

December 3, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

DC Energy, Comments on Congestion Revenue Rights Auction (CRR) Auction Efficiency Draft Final Proposal

DC Energy, Comments on Congestion Revenue Rights Auction (CRR) Auction Efficiency Draft Final Proposal DC Energy, Comments on Congestion Revenue Rights Auction (CRR) Auction Efficiency Draft Final Proposal Submitted by Company Date Submitted Seth Cochran (512) 971-8767 DC Energy February 28, 2018 DC Energy

More information

California ISO. Issue Paper. Renewable Integration: Market and Product Review Phase 1

California ISO. Issue Paper. Renewable Integration: Market and Product Review Phase 1 Issue Paper Renewable Integration: Market and Product Review Phase 1 September 30, 2010 Issue Paper Phase 1 Table of Contents 1 Introduction and Overview... 3 2 Themes from the Issues Forum and Proposed

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY

More information

California ISO. Discussion & Scoping Paper on Renewable Integration Phase 2. Renewable Integration: Market and Product Review Phase 2

California ISO. Discussion & Scoping Paper on Renewable Integration Phase 2. Renewable Integration: Market and Product Review Phase 2 Discussion & Scoping Paper on Renewable Integration Phase 2 Phase 2 April 5, 2010 Issue Paper - Phase 2 Renewable Integration Table of Contents 1 Introduction... 3 2 Candidate Elements for the Comprehensive

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Consolidated Energy Imbalance Market initiative July 31, 2017 Straw Proposal Submitted by Company Date Submitted Paul Nelson Eric Little Southern California Edison August

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) COMMENTS OF NATIONAL GRID

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) COMMENTS OF NATIONAL GRID UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Grid Reliability and Resilience Pricing ) ) ) Docket No. RM18-1-000 COMMENTS OF NATIONAL GRID National Grid respectfully submits

More information

Load Granularity Refinements Issue Paper

Load Granularity Refinements Issue Paper Load Granularity Refinements Issue Paper September 22, 2014 Table of Contents I. Introduction... 3 II. Background... 3 III. Scope of Initiative and Plan for Stakeholder Engagement... 4 IV. FERC s Reasons

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Reliant Energy Etiwanda, LLC ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Reliant Energy Etiwanda, LLC ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Reliant Energy Etiwanda, LLC ) Docket No. ER99-4398-000 ) MOTION TO INTERVENE OUT OF TIME AND STATEMENT OF SUPPORT OF THE CALIFORNIA

More information