Iris Public Event 04 & 05 February 2013 University of Salzburg Unipark, Salzsburg

Size: px
Start display at page:

Download "Iris Public Event 04 & 05 February 2013 University of Salzburg Unipark, Salzsburg"

Transcription

1 Iris Public Event 04 & 05 February 2013 University of Salzburg Unipark, Salzsburg 05 R

2 INTRODUCTION: Background 2 ANTARES (AeroNauTicAl REsources Satellite based) is the Phase B Study of the ESA Iris Program for designing a new ATM - Dedicated Satellite Communication System for SESAR. It will be used for full 4D trajectory management. It consists of a new Communication Standard and associated Satellite System Infrastructures, namely: Space Segment, Ground Segment and User Terminals.

3 ANTARES PHASE B MAIN OBJECTIVES Specification and preliminary design of the overall Satellite Communication System and all its elements including Space and Ground Segment. 3 Specification, design, development and testing of a new Communication Standard for satellite-based Air Traffic Management communications up to the level required for international standardisation. Specification, design and development of a Verification Test Bed (CS VTB) in order to validate the end-to-end performance of the new communication standard, on the basis of the SESAR requirements. Design and Development of a prototype of a low-cost airborne user terminal.

4 OVERALL INDUSTRIAL CONSORTIUM: Core Team 4 The Industrial Consortium is leaded by THALES ALENIA SPACE (Italy) as Prime Contractor being also in charge of the Overall System (WP1) and Space Segment (WP4), with a Core Team taking benefit from the strength of key industrial partners, namely: INDRA ESPACIO: Communication Standard THALES AVIONICS LTD: User Terminal HONEYWELL: User Terminal THALES ALENIA SPACE, FRANCE: Ground Segment

5 OVERALL INDUSTRIAL CONSORTIUM Some additional eighteen Subcontractors are involved in specific tasks, providing relevant accountable expertise for the concerned areas of involvement, namely: 5 AETHIS, AIRTEL, ANTWERP SPACE, CAPGEMINI NORWAY, DLR, EVOLVING SYSTEMS, FREQUENTIS, GMV, IGUASSU SOFTWARE, IZT, JAST, NEXT, SINTEF, SPACEBEL, SPENG, UNIV SALBURG, WISER Industrial Consortium includes competencies to successfully fulfilling targeted B2 objectives and is fully committed to drive the programme to success.

6 OVERALL INDUSTRIAL CONSORTIUM 6 Space Engineering

7 OVERALL INDUSTRIAL CONSORTIUM TAS-I 7 WP1 TAS-I (System) WP2 INDRA (CS) WP3 (UT) WP4 TAS-I (SSEG) WP5 TAS-F (GSEG) USBG INDRA (CS) TAS-I (CS-VTB) THAV UK (UT-CA) HONEYWELL (UT GA) INDRA FREQUENTIS DLR AIRTEL FREQUENTIS SINTEF AIRTEL ANTWERP AIRTEL INDRA ANTWERP FREQUENTIS EVOLVSYS FREQUENTIS CAPGEMINI CAPGEMINI TAS-F IGUASSU GMV TAS-F WISER SINTEF IZT NEXT JAST SES Techcom SPENG IGUASSU Evolvsys TAS-F UBIZEN USBG SPACEBEL

8 ANTARES PROGRESS OVERVIEW The Phase B1 has been completed and closed. 8 The Phase B2 started in June 2012 and the technical work is currently on going with the industrial consortium fully committed to the timely achievement of concerned tasks. ANTARES will delivery: Detail Design Definition of the Operational System A Communication Standard verified on the Verification Test Bed Prototype of the UT

9 ANTARES KEY CONSIDERATIONS AND MAJOR BENEFITS 9 The ANTARES project will set the basis for providing a Satellite Communication System tailored to the requirements of SESAR JU and offering: ATM - dedicated Satellite Communication System Purposely designed for safety-of-life communication services (ATS/AOC+ADS-C+voice) so as to guarantee the high reliability and availability performances required as well as to minimise the user terminals cost and the L-band frequency spectrum usage. The overall system is dimensioned for low cost avionics by appropriately optimizing system, segment and Communication Standard features. A dedicated satellite communication system guarantees the priority to safety services.

10 ANTARES KEY CONSIDERATIONS AND MAJOR BENEFITS 10 Safety-of-life applications rigorously assured The safety-of-life applications are supported by respecting the stringent availability, continuity, integrity and latency requirements defined in the ESA SRD and in COCR documents by means of a specific system design. The design is based on: Extensive and comprehensive RAMS (Reliability, Availability, Maintainability and Safety) analyses at system and segments levels, A dedicated satellite constellation for the requested services availability An ad-hoc Communication Standard designed in order to comply with the COCR performance requirements

11 ANTARES KEY CONSIDERATIONS AND MAJOR BENEFITS Low cost User Terminal A satellite communication system designed to minimise the complexity as well as the production, installation and maintenance costs of the airborne User Terminal adopting a low cost aeronautical omni-directional like antenna suitable for all the aircraft categories. 11 Open Communication Standard fully and efficiently devoted to the avionics needs Designed to achieve the performances required for the Single European Sky new services in continental and oceanic airspace for all types of aircrafts (including rotary-wing) and, at the same time, minimizing the L-band frequency spectrum usage. The Communication Standard is designed so as to be suitable in any type of satellite system constellations (GEO, HEO, MEO etc.) and to operate in very large networks with high number of aircrafts. The Communication Standard specifications will be openly available to any interested party worldwide.

12 ANTARES KEY CONSIDERATIONS AND MAJOR BENEFITS Optimized system throughput An efficient use of communication resource is obtained by means of adaptive waveforms, dynamic resources assignment etc. 12 System compatibility to both centralized and de-centralized ground segment architectures, to be selected depending on service providers needs and future evolution of the ATM service scenario System designed to have high ATM traffic load flexibly The ANTARES system is able to support and accommodate variable traffic distribution over service area and to follow aircraft and data traffic growth over time. This is obtained by implementing system and satellite payload solutions to support flexible and reconfigurable frequency plan, power to beams allocation flexibility and by means of a suitable satellite constellation deployment strategy based on incremental traffic needs reducing commercial risks.

13 13 CONCLUDING REMARKS

14 ANTARES ACTIVITIES DURING Consolidation of the CS Technical Specifications by March- April System and Segments PDRs by 3 rd quarter Development the VTB Prototypes and Emulators by 4 th quarter VTB Assembly, Integration and Test Campaign thus providing a proper test environment for the CS. The VTB will be ready for use in January 2014.

15 ANTARES ACTIVITIES DURING The Test Bed will evaluate CS end to end performances in a real-time environment, including all the layers of the protocol stack suitably allocated to physical and logical domains. 15 The Verification Test Campaign will finally demonstrate the adequacy and suitability of the CS for the intended applications. By April 2014 ANTARES will provide a fully verified and tested Open Standard (Test Report).

16 ANTARES PHASE B2 ROAD MAP Q Q Q Q Q Q Q KO CS IDR VTB Specification Review CS FDR CS Technical Specific. Doc. VTB Final Review VTB Elements Acquisition UT PDR SYSTEM and GS PDR VTB AIT VTB Delivery VTB TRR CS TRR CS Verif. Test Campaign Test Report CS Final Acceptance Review

17 CONCLUSIONS The ANTARES Phase B2 will provide an optimized, flexible and completely justified System Design, including a new tested open standard: 17 Well supported by initial trade offs amongst several options Appropriately strenghtened by RAMS activities for integrity, continuity and availability purposes thus guaranting the high expectations of safety and performances for the future users Largely compliant with the new specifications requirements for air-ground Communication Infrastructures Best answering the user s requirements and end-to end concept of operations Thoroughly fulfilling the avionics needs Satisfactorily supporting the technical and operational requirements at the least possible cost for airspace users.

18 Thanks for your attention 05 R ANTARES Project Manager: G. RAIMONDO giacomo.raimondo@thalesaleniaspace.com

19 19 SUPPORT SLIDES

20 Industrial Consortium and Tasks Responsibility Sharing (1/4) 20 COMPANY WP TASK Overall Prime WP1, WP2, WP4 WP2, WP5 WP2 O/L System, Space Segment, Verification Test Bed OSI, OSI Applications and Legacy, ATN/OSI I/F VTB TC, FWD ACM Header Coding, GES/NCC TX WP1 and WP5 WP2 RAMS FWDL coding (LDPC), Aer. Channel. Charac. WP2 VTB TC and Sys. Load Emul.

21 Industrial Consortium and Tasks Responsibility Sharing (2/4) COMPANY WP TASK 21 WP1, WP2 and WP5 ATN/IPS I/F, VTB EATM Emul. WP5 GS Emulator Support WP3 User Terminal WP2 VTB GUI, GES/NCC CTL Design WP1,WP2 and WP5 CS, VTB GES/NCC Prototype, GS

22 Industrial Consortium and Tasks Responsibility Sharing (3/4) COMPANY WP TASK 22 WP2 WP1 WP2 WP1 and WP2 VTB Physical Channel Emul. UT Antenna design and modelling VTB System Load Emulator Support to Interference Analyis WP2 VTB On-Board UT Emul. Space Engineering WP 2 CS Return Link Multiple Access

23 Industrial Consortium and Tasks Responsibility Sharing (4/4) 23 COMPANY WP TASK WP1, WP2, WP5 GS, CS Signal.,Encap., Logon / off, Redudancy, ACM, VTB GS Emul. WP3 User Terminal WP2 VTB Test Result Processor WP1 and WP2 Traffic Analysis, VTB Logical Chan. and Applic. Emulators WP2 Return Link Interference Cancellation

Iris Annex. (Prepared by the European Space Agency) V1.1, 1/10/2008

Iris Annex. (Prepared by the European Space Agency) V1.1, 1/10/2008 Iris Annex (Prepared by the European Space Agency) V1.1, 1/10/2008 The task descriptions referring to the ESA Iris Programme are presented for the purpose of coordination and better understanding of interface

More information

Iris Public Event summary & activities in Salzburg, 5 February 2013

Iris Public Event summary & activities in Salzburg, 5 February 2013 Iris Public Event summary & activities in 2013 Salzburg, 5 February 2013 Summary: SESAR inputs foreseen during 2013 SESAR Deployment scheme 1. Approval of the governance scheme 2. Development of guidance

More information

Future Communications Infrastructure: An update on ECTL activities

Future Communications Infrastructure: An update on ECTL activities Future Communications Infrastructure: An update on ECTL activities Nikos Fistas EUROCONTROL / CND Iris Phase 1 Final Presentation Meeting ESA/ESTEC February 6 th, 2009 Content History Current ECTL FCI

More information

P Final Project Report

P Final Project Report P 09.24.00 Final Project Report Document information Project Title ADS-B In/Out for military aircraft Project Number 09.24.00 Project Manager Alenia Aermacchi Deliverable Name P.09.24.00 Final Project

More information

AIR NAVIGATION SERVICE PROVIDERS

AIR NAVIGATION SERVICE PROVIDERS THE DATA LINK COMPANY AIR NAVIGATION SERVICE PROVIDERS DATA LINK SOLUTIONS AIRTEL IS THE DATA LINK COMPANY We deliver Air Traffic Management (ATM) modernisation through the implementation of data link

More information

INVAP in Space. ITU International Satellite Symposium 2017 Bariloche, Argentina May. Commercial in Confidence 1

INVAP in Space. ITU International Satellite Symposium 2017 Bariloche, Argentina May. Commercial in Confidence 1 INVAP in Space ITU International Satellite Symposium 2017 Bariloche, Argentina 29-31 May Commercial in Confidence 1 Company background OPERATION INVAP operates as a private listed company It has no public

More information

SESAR Overview. WAKENET3 Europe Workshop. Paul Adamson SJU Programme Manager (WP6/12)

SESAR Overview. WAKENET3 Europe Workshop. Paul Adamson SJU Programme Manager (WP6/12) SESAR Overview WAKENET3 Europe Workshop Paul Adamson SJU Programme Manager (WP6/12) EUROPEAN CONTEXT Page 2 TODAY S SITUATION IN EUROPE Traffic growth cannot be sustained through the current fragmented

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title V&V Platform Development Project Number 03.03.02 Project Manager EUROCONTROL Deliverable Name Final Project Report Deliverable ID D01 Edition 01.00.01

More information

ACCEPTO - Airbus DS Command & Control EGS-CC based Product line for Tests and Operations

ACCEPTO - Airbus DS Command & Control EGS-CC based Product line for Tests and Operations ACCEPTO - Airbus DS Command & Control EGS-CC based Product line for Tests and Operations Workshop on Simulation for European Space Programmes (SESP) 24-26 March 2015 ESA-ESTEC, Noordwijk, The Netherlands

More information

SESSION 7A SESAR INNOVATIONS. Peter Hotham Chief of Technology & Innovation

SESSION 7A SESAR INNOVATIONS. Peter Hotham Chief of Technology & Innovation SESSION 7A SESAR INNOVATIONS Peter Hotham Chief of Technology & Innovation SESAR Innovations 7A-1 1 International ATM & Airports New Network Solutions New Generation of Network Management Tools Francisco

More information

Navigating CPDLC Mandate for ANSPs: Status and the Road to Completion WAC 2017

Navigating CPDLC Mandate for ANSPs: Status and the Road to Completion WAC 2017 Navigating CPDLC Mandate for ANSPs: Status and the Road to Completion WAC 2017 Contents CPDLC Deployment Status CPDLC Mandate ELSA Report SESAR DM Recovery Plan Deploying a Data Link System Data Link Components

More information

Industrial use cases: Description and business impact D1.2.b Avionics Use Case

Industrial use cases: Description and business impact D1.2.b Avionics Use Case Collaborative Large scale Integrating Project Open Platform for EvolutioNary Certification Of Safety critical Systems Industrial use cases: Description and business impact D1.2.b Avionics Use Case Work

More information

SESAR development and deployment

SESAR development and deployment SESAR development and deployment Global Challenges to Improve Air Navigation Performance Asilomar Conference Grounds, Pacific Grove, CA 13 February 2015 Rolf TUCHHARDT European Commission, DG MOVE SESAR

More information

Der virtuelle Entwurfsprozess (Virtual Spacecraft Design VSD)

Der virtuelle Entwurfsprozess (Virtual Spacecraft Design VSD) Der virtuelle Entwurfsprozess (Virtual Spacecraft Design VSD) Joachim Fuchs (joachim.fuchs@esa.int) Modelling and Simulation Section (TEC-SWM), Software and Technology Dept. Technical Directorate, ESA

More information

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS)

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS) SSPEDI SpS J.1(a), Attachment 1 80ARC018R0007 National Aeronautics and Space Administration Ames Research Center Moffett Field, CA 94035-0001 STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title CWP prototyping Project Number 10.10.03 Project Manager THALES Deliverable Name Final Project Report Deliverable ID D37 Edition 00.02..00 Template

More information

WHAT IS THE SESAR DEPLOYMENT PROGRAMME

WHAT IS THE SESAR DEPLOYMENT PROGRAMME WHAT IS THE SESAR DEPLOYMENT PROGRAMME 2. What is the SESAR Deployment Programme? 2.1 The regulatory framework In line with the overall arrangement of the SESAR Programme (depicted within the previous

More information

Success Story. OTRS Business Solution guarantees high availability of reliable customer service worldwide for SES Techcom Services.

Success Story. OTRS Business Solution guarantees high availability of reliable customer service worldwide for SES Techcom Services. OTRS Business Solution guarantees high availability of reliable customer service worldwide for SES Techcom Services. At a glance Company SES Techcom Services Tickets/month 80 Staff members using OTRS/Agents

More information

Contextual note SESAR Solution description form for deployment planning

Contextual note SESAR Solution description form for deployment planning Purpose: Release 5 SESAR Solution #101 Contextual note SESAR Solution description form for deployment planning This contextual note introduces a SESAR Solution (for which maturity has been assessed as

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title SWIM Design Project Number 14.01.03 Project Manager Indra Deliverable Name Final Project Report Deliverable ID D02 Edition 00.02.00 Template Version

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title IBP's Use Planning Project Number 03.02.02 Project Manager EUROCONTROL Deliverable Name Final Project Report Deliverable ID D11 Edition 01.00.00

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title Airborne Full 4D Trajectory Management Project Number 9.02 Project Manager Marianne MOLLER Deliverable Name Final Project Report Deliverable ID D07

More information

Preparing an initial Assessment of the SESAR Concept of Operations EP3: Single European Sky Implementation Support through Validation

Preparing an initial Assessment of the SESAR Concept of Operations EP3: Single European Sky Implementation Support through Validation Preparing an initial Assessment of the SESAR Concept of Operations EP3: Single European Sky Implementation Support through Validation Robert V Graham, EUROCONTROL Experimental Centre, France David Young

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title Integration of CDM in the SWIM environment Project Number 12.06.09 Project Manager Indra Deliverable Name Final Project Report Deliverable ID D23

More information

New Reliability Prediction Methodology Aimed at Space Applications. Briefing Meeting with Industry

New Reliability Prediction Methodology Aimed at Space Applications. Briefing Meeting with Industry New Reliability Prediction Methodology Aimed at Space Applications Briefing Meeting with Industry Luigi Bianchi Head of Dependability and Safety Assurance Section ESA/ESTEC Product Assurance and Safety

More information

Monitoring CO 2 anthropogenic emissions from space

Monitoring CO 2 anthropogenic emissions from space CO 2 anthropogenic emissions from space Richard Engelen 2015: CO 2 report To assess the need and opportunity for an independent European space-borne observation capacity for CO 2 to monitor and to verify

More information

Honeywell in Clean Sky2 And Planned Complementary Activities in the Czech Republic Marcela Sapáková

Honeywell in Clean Sky2 And Planned Complementary Activities in the Czech Republic Marcela Sapáková Honeywell in Clean Sky2 And Planned Complementary Activities in the Czech Republic Marcela Sapáková February 15 th, 2017 Ministry of Industry and Trade, Prague Honeywell in the Czech Republic ~ 900 AERO

More information

EGNOS End-to-End Validation Programme. Context, Means, Issues, and Risks

EGNOS End-to-End Validation Programme. Context, Means, Issues, and Risks EGNOS End-to-End Validation Programme Context, Means, Issues, and Risks Bret W. Durrett (Airsys ATM), C. Ruf, J-Y. Schneider (Airsys ATM) D. Flament, M. Colcombert (Alcatel Space Industries) J. Andrès

More information

Clean Sky 2 Joint Undertaking. 5 th Call for Proposals (CFP05): List and full description of Topics. Call Text. - November

Clean Sky 2 Joint Undertaking. 5 th Call for Proposals (CFP05): List and full description of Topics. Call Text. - November Clean Sky 2 Joint Undertaking 5 th Call for Proposals (CFP05): List and full description of Topics Call Text - November 2016 - The present preliminary version of the Call Text is released for information

More information

Software Acquisition Best Practices for Ground Systems

Software Acquisition Best Practices for Ground Systems GSAW 2007 Software Acquisition Best Practices for Ground Systems Suellen Eslinger Software Engineering Subdivision Computers and Software Division The Aerospace Corporation March 27, 2007 2003-2007 The

More information

THE FUTURE OF AIR TRAFFIC MANAGEMENT SAFE & EFFICIENT. An Update on SESAR. Prof. Dr. Peter Hecker Member of the Scientific Committee

THE FUTURE OF AIR TRAFFIC MANAGEMENT SAFE & EFFICIENT. An Update on SESAR. Prof. Dr. Peter Hecker Member of the Scientific Committee THE FUTURE OF AIR TRAFFIC MANAGEMENT SAFE & EFFICIENT An Update on SESAR Prof. Dr. Peter Hecker Member of the Scientific Committee EIWAC Tokyo - 10 November 2010 SETTING THE SCENE.. 2 EUROPEAN ATM CHALLENGES

More information

TECHNICAL REVIEWS AND AUDITS

TECHNICAL REVIEWS AND AUDITS Chapter 11 Technical Reviews and Audits CHAPTER 11 TECHNICAL REVIEWS AND AUDITS 11.1 PROGRESS MEASUREMENT The Systems Engineer measures design progress and maturity by assessing its development at key

More information

Satellite. The fully integrated and tested satellite is in storage at Thales Alenia Space, Cannes, since May 2008.

Satellite. The fully integrated and tested satellite is in storage at Thales Alenia Space, Cannes, since May 2008. SMOS Project Status Satellite (Payload & Platform) Launcher Ground Segment Mission Planning Mission Control X-band Receive Station Data Processing Ground Segment Processors System Integration & Test Near

More information

Introduction to the SESAR 2020 Programme Execution

Introduction to the SESAR 2020 Programme Execution Introduction to the SESAR 2020 Programme Execution 30 th April 2015 Edition 01.00.00 The purpose of this paper is to provide an introduction summary of the SESAR 2020 Programme Execution Framework. It

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title Airport Performance Assessment and Management Support Systems Project Number 12.07.03 Project Manager Indra Deliverable Name Final Project Report

More information

ICB Industry Consultation Body

ICB Industry Consultation Body ICB POSITION PAPER EASA RMT on revision of the SPI IR The European Commission is following a two-step approach for the revision of the SPI IR and has signalled that it is most likely to ask EASA to launch

More information

Small Satellite Rideshares on Commercial Resupply Missions to the International Space Station SmallSat Conference 2012

Small Satellite Rideshares on Commercial Resupply Missions to the International Space Station SmallSat Conference 2012 Small Satellite Rideshares on Commercial Resupply Missions to the International Space Station SmallSat Conference 2012 Joshua R. Robinson(Presenting) Daniel W. Kwon August 14, 2012 Introduction Gaining

More information

SESAR Exploratory Research. David Bowen Chief ATM, SESAR JU

SESAR Exploratory Research. David Bowen Chief ATM, SESAR JU SESAR Exploratory Research David Bowen Chief ATM, SESAR JU 1 SESAR vision targets 7 improvement areas LOOKING AT THE FLIGHT AS A WHOLE, WITHIN A FLOW AND NETWORK CONTEXT SESAR to enable step change in

More information

GALILEO JOINT UNDERTAKING

GALILEO JOINT UNDERTAKING GALILEO Research and Development Activities First call Activity C Introduction of GALILEO services using EGNOS STATEMENT OF WORK GJU/03/100/issue2/OM/ms Issue 2 100 issue2 6th FP C SOW 1 TABLE OF CONTENTS

More information

Questions and Answers N 2 15.CAT.OP.001

Questions and Answers N 2 15.CAT.OP.001 Questions and Answers N 2 15.CAT.OP.001 Question 1.Specification page 37: The contract implementation period is 18 months starting from the date of the entry into force of the contract (T0) vs. Contract

More information

MOIS MISSION OPERATIONS PREPARATION IN THE EGS-CC ERA

MOIS MISSION OPERATIONS PREPARATION IN THE EGS-CC ERA MOIS MISSION OPERATIONS PREPARATION IN THE EGS-CC ERA Wolfgang Heinen, Simon Reid European Space Architectures Workshop ( ESAW ), Darmstadt, 21 June 2017 1 23/06/2017 Commercial-in-Confidence 23/06/2017

More information

The role of research organizations in SESAR German Aerospace Center (DLR) Dr. Helmut H. Toebben Prof. Dr. Dirk Kuegler

The role of research organizations in SESAR German Aerospace Center (DLR) Dr. Helmut H. Toebben Prof. Dr. Dirk Kuegler DLR.de Chart 1 The role of research organizations in SESAR 2020 German Aerospace Center (DLR) Dr. Helmut H. Toebben Prof. Dr. Dirk Kuegler Netherlands Aerospace Centre (NLR) Roland Vercammen SINTEF Trond

More information

SESAR Progress. Specific focus on ATC related WPs (WP4, WP5,WP10) Prepared for ODT by Bernard Brunner 17th September 2009

SESAR Progress. Specific focus on ATC related WPs (WP4, WP5,WP10) Prepared for ODT by Bernard Brunner 17th September 2009 SESAR Progress Specific focus on ATC related WPs (WP4, WP5,WP10) Prepared for ODT by Bernard Brunner 17th September 2009 European Organisation for the Safety of Air Navigation Agenda General : Project

More information

Introduction to the SESAR 2020 Programme Execution

Introduction to the SESAR 2020 Programme Execution Introduction to the SESAR 2020 Programme Execution 12 th October 2015 Edition 01.00.01 The purpose of this paper is to provide an introduction summary of the SESAR 2020 Programme Execution Framework. It

More information

Industry Consultation Body. Role of the Interoperability sub-group. 18 th December 2008 ETSI

Industry Consultation Body. Role of the Interoperability sub-group. 18 th December 2008 ETSI Industry Consultation Body Role of the Interoperability sub-group 18 th December 2008 ETSI The Industry Consultation Body Created in 2004 by the SES Framework Regulation (Article 6, 549/2004): Without

More information

Adacel Technologies Limited 10 November Peter Landos Chairman

Adacel Technologies Limited 10 November Peter Landos Chairman Adacel Technologies Limited 10 November 2016 Peter Landos Chairman DISCLAIMER This presentation has been prepared by Adacel Technologies Limited (ACN 079 672 281) (Adacel or the Company). The information

More information

For personal use only

For personal use only Adacel Technologies Limited 10 November 2016 Peter Landos Chairman DISCLAIMER This presentation has been prepared by Adacel Technologies Limited (ACN 079 672 281) (Adacel or the Company). The information

More information

RAIL and SATELLITE. Role and Contribution of the Space Agency

RAIL and SATELLITE. Role and Contribution of the Space Agency RAIL and SATELLITE Role and Contribution of the Space Agency Mario CAPORALE Agenzia Spaziale Italiana Roma 22 January 2016 SOGEI Workshop GNSS technology advances in a multi-constellation framework 1 Space

More information

GSMA REGULATORY POSITION ON DRONES. August 2017

GSMA REGULATORY POSITION ON DRONES. August 2017 GSMA REGULATORY POSITION ON DRONES August 2017 GSMA Messages to EASA Consultation GSMA welcomes the opportunity to contribute to EASA s consultation on the Introduction of a regulatory framework for the

More information

The next generation of geostationary telecommunication platform

The next generation of geostationary telecommunication platform NEOSAT / ARTES 14 The next generation of geostationary telecommunication platform 13/11/2012 Rationale for NEOSAT Satellite systems represent 50% sales for ESA member states industry (3.1 B ). Telecommunications

More information

COMMERCIAL APPLICATIONS OF GLOBAL NAVIGATION SATELLITE SYSTEMS. UN Vienna, February 17 th 2014

COMMERCIAL APPLICATIONS OF GLOBAL NAVIGATION SATELLITE SYSTEMS. UN Vienna, February 17 th 2014 COMMERCIAL APPLICATIONS OF GLOBAL NAVIGATION SATELLITE SYSTEMS UN Vienna, February 17 th 2014 1 Telespazio Telespazio, a joint venture between Finmeccanica (67%) and Thales (33%), is one of the world s

More information

The Open Group Exam OG0-091 TOGAF 9 Part 1 Version: 7.0 [ Total Questions: 234 ]

The Open Group Exam OG0-091 TOGAF 9 Part 1 Version: 7.0 [ Total Questions: 234 ] s@lm@n The Open Group Exam OG0-091 TOGAF 9 Part 1 Version: 7.0 [ Total Questions: 234 ] https://certkill.com Topic break down Topic No. of Questions Topic 1: Volume A 100 Topic 2: Volume B 134 2 https://certkill.com

More information

ALTAIR Millennium s DARPA SeeMe Commercial Satellite Solution Technical (R)evolution. Presentation to: 2014 AIAA/USU Conference on Small Satellites

ALTAIR Millennium s DARPA SeeMe Commercial Satellite Solution Technical (R)evolution. Presentation to: 2014 AIAA/USU Conference on Small Satellites ALTAIR Millennium s DARPA SeeMe Commercial Satellite Solution Technical (R)evolution [SSC14-III-2} Presentation to: 2014 AIAA/USU Conference on Small Satellites Mike Scardera Director of Engineering mike.scardera@millennium-space.com

More information

SESAR: a European initiative for an enhanced ATM system

SESAR: a European initiative for an enhanced ATM system domaine Recherche & SESAR: a European initiative for an enhanced ATM system General overview and spotlight on the SESAR operational concept Patrick DUJARDIN R&D Manager DSNA/DTI Toulouse - France Tokyo,

More information

THE ROADMAP FOR DELIVERING HIGH PERFORMING AVIATION FOR EUROPE. European ATM Master Plan

THE ROADMAP FOR DELIVERING HIGH PERFORMING AVIATION FOR EUROPE. European ATM Master Plan THE ROADMAP FOR DELIVERING HIGH PERFORMING AVIATION FOR EUROPE European ATM Master Plan Executive Summary for ANSPs Edition 2015 EUROPEAN ATM MASTER PLAN EXECUTIVE VIEW EDITION 2015 EUROPEAN ATM MASTER

More information

GSC Operations Concept & Sentinels Collaborative Ground Segment

GSC Operations Concept & Sentinels Collaborative Ground Segment GSC Operations Concept & Sentinels Collaborative Ground Segment Pier Bargellini GSC Mission Management & Ground Segment Development EO Ground Segment Department, European Space Agency (ESRIN, Frascati)

More information

Effectiveness of the application of the Human Performance Assessment Process in SESAR 1

Effectiveness of the application of the Human Performance Assessment Process in SESAR 1 Twelfth USA/Europe Air Traffic Management Research and Development Seminar (ATM2017) Effectiveness of the application of the Human Performance Assessment Process in SESAR 1 Sharing Lessons Learnt Sonja

More information

SESAR and ASAS Opportunity

SESAR and ASAS Opportunity SESAR and ASAS Opportunity Bob Graham EUROCONTROL Experimental Centre Presentation Overview SESAR Concept Focus Opportunity for ASAS Challenges to overcome SESAR The objectives of SESAR are to eliminate

More information

Timing Design and Verification of Real-Time Systems with (m,k) Constraints: Current Practices at THALES RAFIK HENA THALES RESEARCH& TECHNOLOGY FRANCE

Timing Design and Verification of Real-Time Systems with (m,k) Constraints: Current Practices at THALES RAFIK HENA THALES RESEARCH& TECHNOLOGY FRANCE Timing Design and Verification of Real-Time Systems with (m,k) Constraints: Current Practices at THALES RAFIK HENA THALES RESEARCH& TECHNOLOGY FRANCE SOPHIE QUINTON INRIA GRENOBLE www.thalesgroup.com 2

More information

Integrating Legacy Software: Lessons and Hurdles

Integrating Legacy Software: Lessons and Hurdles Integrating Legacy Software: Lessons and Hurdles John Chobany, Associate Director Vehicle Concepts Department Architecture & Design Subdivision Systems Engineering Division The Aerospace Corporation 2

More information

Predictable results for unpredictable threats. Global ATM and Airport Systems

Predictable results for unpredictable threats. Global ATM and Airport Systems Predictable results for unpredictable threats Global ATM and Airport Systems SELEX Sistemi Integrati plays a leading role in developing innovative solutions to ensure efficient and safe management of airspace

More information

Guidelines for proposals preparation under the ESA satellite for 5G initiative 5G Validation Trials and Vertical Pilots

Guidelines for proposals preparation under the ESA satellite for 5G initiative 5G Validation Trials and Vertical Pilots estec European Space Research and Technology Centre Keplerlaan 1 2201 AZ Noordwijk The Netherlands Tel. (31) 71 5656565 Fax (31) 71 5656040 www.esa.int 15 November 2017 Subject: Guidelines for proposals

More information

C2X Compliance Assessment

C2X Compliance Assessment C2X Compliance Assessment ETSI TC ITS workshop February 5-6, 2013 Katrin Sjöberg 1 C2X Compliance Assessment Region-Wide Interoperability Minimum Performance Requirements Compatibility with Specific regulations

More information

The potential of Licensed Shared Access for the wireless broadband growth - Regulatory aspects of LSA

The potential of Licensed Shared Access for the wireless broadband growth - Regulatory aspects of LSA Research and Innovation The potential of Licensed Shared Access for the wireless broadband growth - Regulatory aspects of LSA Emmanuel Faussurier ANFR Chairman CEPT/WGFM Project Team FM53 faussurier@anfr.fr

More information

Single European Sky ATM Research (SESAR) Friday 6 th June 2008

Single European Sky ATM Research (SESAR) Friday 6 th June 2008 Single European Sky ATM Research (SESAR) Friday 6 th June 2008 Agenda 1. 11:00 Introductions 2. 11:10 Presentations from guest speakers 3. 12:00(ish) Open question forum 4. 13:30(ish) Lunch Running Order

More information

JTI-CS CFP06-REG-01-09

JTI-CS CFP06-REG-01-09 Clean Sky 2 Information Day dedicated to the 6 th Call for Proposal (CfP06) JTI-CS2-2017-CFP06-REG-01-09 Innovative Low Power De-Icing System Brussels, 22 February 2017 Estimated Funding Topic Value: 1200k

More information

LIFE CYCLE ASSET MANAGEMENT. Project Reviews. Good Practice Guide GPG-FM-015. March 1996

LIFE CYCLE ASSET MANAGEMENT. Project Reviews. Good Practice Guide GPG-FM-015. March 1996 LIFE YLE Good Practice Guide ASSET MANAGEMENT Project Reviews March 1996 Department of Energy Office of Field Management Office of Project and Fixed Asset Management ontents 1. INTRODUTION...1 2. PROJET

More information

The Space Network Ground Segment Sustainment (SGSS) Project: Developing a COTS-Intensive Ground System

The Space Network Ground Segment Sustainment (SGSS) Project: Developing a COTS-Intensive Ground System The Space Network Ground Segment Sustainment (SGSS) Project: Developing a COTS-Intensive Ground System Frank Herman, Linda Esker, Madeline Diep, Kathleen Dangle: Fraunhofer USA Jeremy Jacobsohn, GMV Rick

More information

Overview of CEPT regulatory activities on cognitive radio

Overview of CEPT regulatory activities on cognitive radio Overview of CEPT regulatory activities on cognitive radio Emmanuel Faussurier ANFR Chairman CEPT/WGFM Project Team FM53 faussurier@anfr.fr 12 December 2012 1 Background : ITU context Software-defined radio

More information

Navigation Support Services

Navigation Support Services OPS QMS QMS-EIMO-SERV-PR-4500-OPS Issue 1.1 May 2006 European Space Agency Agence spatiale européenne Copyright: 2004 European Space Agency : ii DOCUMENT APPROVAL Prepared by L. Agrotis, J. Dow, R. Zandbergen

More information

Space engineering ECSS. Ground systems and operations Part 2: Document requirements definitions (DRDs) ECSS-E-70 Part 2A EUROPEAN COOPERATION

Space engineering ECSS. Ground systems and operations Part 2: Document requirements definitions (DRDs) ECSS-E-70 Part 2A EUROPEAN COOPERATION -E-70 Part 2A EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space engineering Ground systems and operations Part 2: Document requirements definitions (DRDs) Secretariat ESA-ESTEC Requirements & Standards

More information

Contextual note SESAR Solution description form for deployment planning

Contextual note SESAR Solution description form for deployment planning 1 2 3 4 5 6 7 8 9 10 Contextual note SESAR Solution description form for deployment planning Purpose: This contextual note introduces a SESAR Solution (for which maturity has been assessed as sufficient

More information

SJU Multi annual Staff Policy Plan MULTIANNUAL STAFF POLICY PLAN P a g e

SJU Multi annual Staff Policy Plan MULTIANNUAL STAFF POLICY PLAN P a g e MULTIANNUAL STAFF POLICY PLAN 2012-2014 1 P a g e Table of Contents A. GENERAL OVERVIEW OF THE CURRENT SITUATION OF THE SESAR JOINT UNDERTAKING 4 1. The SESAR s activities... 4 1.1. The SESAR Joint Undertaking...

More information

SESAR Solution Regulatory Overview

SESAR Solution Regulatory Overview SESAR Solution Regulatory Overview Enhanced terminal operations with LPV procedures Document information Document Name Enhanced terminal operations with LPV procedures Edition 01.00.00 Abstract This document

More information

7. Model based software architecture

7. Model based software architecture UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process

More information

22 nd June 2010 Pullman Hotel, Brussels

22 nd June 2010 Pullman Hotel, Brussels 22 nd June 2010 Pullman Hotel, Brussels A European Commission Seventh Framework Programme This document is produced by the ALICIA consortium and the research leading to these results has received funding

More information

The SESAR Joint Undertaking is a EU body created by the EU Council (REG 219/2007)

The SESAR Joint Undertaking is a EU body created by the EU Council (REG 219/2007) EUROPEAN COMMISSION The SESAR family The SESAR Joint Undertaking is a EU body created by the EU Council (REG 219/2007) Its founding members are the European Community and the Eurocontrol Organisation Members

More information

SESAR European ATM Master Plan & SESAR2020

SESAR European ATM Master Plan & SESAR2020 SESAR European ATM Master Plan & SESAR2020 Paul Bosman EUROCONTROL ICNS 2017 GLOBAL MOBILITY CHALLENGES AND OPPORTUNITIES 2010 2020 2030 2040 2 SINGLE EUROPEAN SKY - SES Driven by performance Increased

More information

The software process

The software process The software process Process product Process properties Cost Effort Hours worked Punctuality Outline Activities Production (requirements, design, implementation), verification, management Phases Development,

More information

Safety Related Considerations in Autonomy

Safety Related Considerations in Autonomy Safety Related Considerations in Autonomy Dr. Guillaume Brat Intelligent Systems Division NASA Ames Research Center NASA ARMD Airspace Operations and Safety Program Presented at the OPTICS Workshop: FROM

More information

Prioritising safety in unmanned aircraft system traffic management

Prioritising safety in unmanned aircraft system traffic management White paper: drones Prioritising safety in unmanned aircraft system traffic Drones are proliferating throughout the world s airspace, making them impossible to ignore. As their numbers rise, the importance

More information

The vision from European Rail Industry. Peter Gurník UNIFE Technical Affairs Manager

The vision from European Rail Industry. Peter Gurník UNIFE Technical Affairs Manager The vision from European Rail Industry Peter Gurník UNIFE Technical Affairs Manager Who we are UNIFE represents the European Rail Supply Industry Based in Brussels since 1992 The trusted partner of European

More information

MOVEP 2012 Tutorial Safety, Dependability and Performance Analysis of Extended AADL Models

MOVEP 2012 Tutorial Safety, Dependability and Performance Analysis of Extended AADL Models MOVEP 2012 Tutorial Safety, Dependability and Performance Analysis of Extended AADL Models Part 1: Overview European Space Agency European Space Research and Technology Centre RWTH Aachen University Software

More information

TECHNICAL REVIEWS AND AUDITS FOR SYSTEMS, EQUIPMENT AND COMPUTER SOFTWARE

TECHNICAL REVIEWS AND AUDITS FOR SYSTEMS, EQUIPMENT AND COMPUTER SOFTWARE BY ORDER OF THE COMMANDER SMC Standard SMC-S-21 15 September 2009 ------------------------ Supersedes: New issue Air Force Space Command SPACE AND MISSILE SYSTEMS CENTER STANDARD TECHNICAL REVIEWS AND

More information

SESAR & NextGen Working together for Aviation Interoperability

SESAR & NextGen Working together for Aviation Interoperability SESAR & NextGen Working together for Aviation Interoperability Royal Aeronautical Society Annual Conference - London April 14 th 2011 Peter Hotham Chief of Technology & Innovation SESAR Joint Undertaking

More information

GNSS / GALILEO certification for rail safety applications Railway requirements and the strategic position of UIC

GNSS / GALILEO certification for rail safety applications Railway requirements and the strategic position of UIC GNSS / GALILEO certification for rail safety applications Railway requirements and the strategic position of UIC Presenting: George BARBU International Railway Union UIC Paris, France Abstact All railway

More information

SRR and PDR Charter & Review Team. Linda Pacini (GSFC) Review Chair

SRR and PDR Charter & Review Team. Linda Pacini (GSFC) Review Chair SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair Review Requirements Review requirements are taken from the following documents: GSFC STD 1001 Criteria for Flight Project Critical Milestone

More information

Assessment and Validation of Pioneering Concepts for Personal Air Transport Systems. Introduction to the PPLANE project

Assessment and Validation of Pioneering Concepts for Personal Air Transport Systems. Introduction to the PPLANE project Assessment and Validation of Pioneering Concepts for Personal Air Transport Systems Introduction to the PPLANE project Warsaw IoA, 7/07/2009 Claude Le Tallec (Onera), PPlane Coordinator The Fifth Element

More information

Software Architecture Challenges for Complex Systems of Systems

Software Architecture Challenges for Complex Systems of Systems Software Architecture Challenges for Complex Systems of Systems Barry Boehm, USC-CSE CSE Annual Research Review March 6, 2003 (boehm@sunset.usc.edu) (http://sunset.usc.edu) 3/18/03 USC-CSE 1 Complex Systems

More information

TAUPE Publishable Summary

TAUPE Publishable Summary TAUPE Publishable Summary Description and main objectives of the project TAUPE is a FP7 collaborative research project led by SAFRAN Engineering Services aiming at reducing the length and mass of the aircraft

More information

INNOVATING SES S TECHNOLOGY SOLUTIONS. Martin Halliwell, Chief Technology Officer

INNOVATING SES S TECHNOLOGY SOLUTIONS. Martin Halliwell, Chief Technology Officer INNOVATING SES S TECHNOLOGY SOLUTIONS Martin Halliwell, Chief Technology Officer Innovating SES s Technology Solutions Expanding flexibility and scalability of SES s global network and capabilities Delivering

More information

CMMI A-Specification. Version 1.7. November, For CMMI Version 1.2. This document is controlled by the CMMI Steering Group.

CMMI A-Specification. Version 1.7. November, For CMMI Version 1.2. This document is controlled by the CMMI Steering Group. CMMI A-Specification Version 1.7 For CMMI Version 1.2 November, 2007 This document is controlled by the CMMI Steering Group. CHANGE PAGE HISTORY This is the first release of the A-Spec for CMMI v1.2. Change

More information

NASA Aeronautics Airspace Operations and Safety Program

NASA Aeronautics Airspace Operations and Safety Program NASA Aeronautics Airspace Operations and Safety Program Discussion with the ARTR John A. Cavolowsky Director, AOSP Akbar Sultan Deputy Director, AOSP September 26, 2014 1 of 44 Ability to Manage Increasing

More information

Results & Impacts of ICAO ANC/12. Integration & Harmonisation of SESAR and NextGen into the global framework

Results & Impacts of ICAO ANC/12. Integration & Harmonisation of SESAR and NextGen into the global framework Results & Impacts of ICAO ANC/12 Integration & Harmonisation of SESAR and NextGen into the global framework ATM 2013 Seminar June 13 2013 Michael Standar Has endorsed: Revised Global Air Navigation Plan

More information

SUPPORTING GLOBAL HARMONISATION AND. Michael Standar, SESAR JU Chief Strategy & External Affairs

SUPPORTING GLOBAL HARMONISATION AND. Michael Standar, SESAR JU Chief Strategy & External Affairs SESAR SUPPORTING GLOBAL HARMONISATION AND INTEROPERABILITY Michael Standar, SESAR JU Chief Strategy & External Affairs Mobility challenges and opportunities 2010 2020 2030 2040 The need for harmonisation/interoperability

More information

Managing a multi-year 4 Million $ in Revenue program successfully for leading

Managing a multi-year 4 Million $ in Revenue program successfully for leading Experience Summary ABC +91-######### As********@email.com Managing a multi-year 4 Million $ in Revenue program successfully for leading Logistics client Have 7 Years of IT experience in full project lifecycle

More information

Open-Sourcing the Model-Based Systems Engineering Solution Capella

Open-Sourcing the Model-Based Systems Engineering Solution Capella Open-Sourcing the Model-Based Systems Engineering Solution Capella C. Boudjennah 1, B. Combemale 2, D. Exertier 3, Matthieu Helleboid 3, S. Lacrampe 1, M.A Peraldi-Frati 4 1 Obeo 2 University of Rennes

More information

NCLB AIM Workshop Cairo,11-13 September 2017 SWIM. IATA s Perspective

NCLB AIM Workshop Cairo,11-13 September 2017 SWIM. IATA s Perspective NCLB AIM Workshop Cairo,11-13 September 2017 SWIM IATA s Perspective IATA at 30,000 ft Mission to represent, lead and serve the airline industry Founded in Havana, Cuba on 1945 274 airline members Representing

More information

Managing Systems Engineering Processes: a Multi- Standard Approach

Managing Systems Engineering Processes: a Multi- Standard Approach Managing Systems Engineering Processes: a Multi- Standard Approach Rui Xue, Claude Baron, Philippe Esteban, Hamid Demmou To cite this version: Rui Xue, Claude Baron, Philippe Esteban, Hamid Demmou. Managing

More information

an integrated optimisation approach

an integrated optimisation approach Sustainable and intelligent management of energy for smarter railway systems in Europe an integrated optimisation approach Project co-funded by the European Commission Background Energy management is a

More information