1 Attachment B Statement of Work Statement of Work 1

2 Section 1 Overview Definitions Contract Objectives System Overview... 4 Section 2 Project Governance Structure and Staffing Requirements Cooperation with the Department and Other Entities Cooperation in the Event of a Subsequent Contractor Contractor Staffing Requirements... 8 Section 3 Project Administration Project Management Phase Gate Reviews Knowledge Transfer Disaster Preparedness / Disaster Recovery Section 4 Project Execution Performance Periods DDI Performance Period ST Performance Period OS Performance Period Section 5 Design, Development and Implementation (DDI) Performance Period DDI Performance Period Phase One: Initiation and Planning DDI Performance Period Phase Two: Requirements Elaboration DDI Performance Period Phase Three: System Design DDI Performance Phase Four: System Development and Test DDI Performance Phase Five: Data Conversion DDI Performance Phase Six: Testing DDI Performance Phase Seven: Implementation Section 6 Services Transition (ST) Performance Period Statement of Work 2

3 6.1 ST Performance Period Phase A Warranty Phase ST Performance Phase B Services Transition Phase Section 7 Operational Support (OS) Performance Period Section 8 Project Deliverables for All Phases Project Governance and Oversight Deliverables DDI Performance Period Phase One: Project Initiation Deliverables DDI Performance Period Phase Two: Requirements Elaboration DDI Performance Period Phase Three: System Design Deliverables DDI Performance Period Phase Four: System Development and Test Deliverables DDI Performance Period Phase Five: Data Conversion Deliverables DDI Performance Period Phase Six: Testing Deliverables DDI Performance Period Phase Seven: Implementation Deliverables ST Performance Period Phase A: Warranty Phase Deliverables ST Performance Period Phase B: Services Transition Phase Deliverables Additional Considerations Operational Support Performance Period Deliverables Statement of Work 3

4 Section 1 Overview 1.1 Definitions In this document, in addition to the definitions in the PUR 1000 and PUR 1001, capitalized terms shall have the meanings stated in the solicitation Attachment K, incorporated as Exhibit 3 of the Contract. Defined terms in the singular shall include the plural and vice versa, and the masculine, feminine, or neuter gender shall include all genders. 1.2 Contract Objectives The Department of Financial Services ( DFS, or the Department ) expectation for the RMIS replacement is that it will meet the Division of Risk Management s ( DRM or the Division ) business objectives, including: Improved Efficiency and Reduced Errors: The new system must collect and manage claim information, administer claims, provide workflow and other tools to support the ability of users to communicate with each other, accept and route information, work files and set reminders for key actions. Improved efficiency will enable adjusters to work on high priority items such as investigations and legal issues in a timelier manner. Improved Collaboration and System Integration: The new system should greatly increase the seamless technical integration of the Division with its partners, including third party administrators, other Divisions within the Department and other State and Federal Agencies. This integration should reduce or eliminate the extensive manual effort currently required to export and import data. Enable Self-Service Internally and Externally: The new system should support self-service by Division employees (for example, requesting standard reports), Vendors (for example, submitting invoices electronically) and State Agencies (for example, submitting a property update or claim notification electronically). Performance Measurement: The new system should support tracking and reporting of metrics and improve data access for performance management. 1.3 System Overview To support the Division s objectives, the new system is expected to include, but is not limited to: 1) Business Rules Engine 2) Web Based architecture 3) Document imaging and management, including tight integration with FileNet P8 4) Advanced search capabilities 5) Workflow management 6) Communication administration, including system integration Statement of Work 4

5 7) Customer relationship management, or tight integration with an external customer relationship management (CRM) system 8) Automated system interfaces 9) Data import / export, including batch processing 10) Reporting and dashboard tools 11) Enhanced security (role-based) 12) Auditing tools 13) System administration tools 14) Agency self-service portal The new system ( System ) is expected to support the following high-level business functions: 1) Policy administration, including Rating / Binding, issuing Certificates of Insurance with detailed property schedules, calculating premiums and processing no-cost endorsements. Note that the Department has unique Policy administration requirements related to potential annual changes in the organizational structure of various state agencies / policyholders (e.g. Legislatively mandated mergers or reorganizations that necessitate moving properties, claims or history). 2) Claims management, including first notice of loss / injury, validation of coverage, investigation, loss and loss adjustment expenses, reserving, subrogation, salvage and deductible recovery, vendor management, litigation management, claims payment, claims history, third party administrator (TPA) data integration and image and document management. 3) Finance and accounting, including premium and deductible billing, premiums and receivables collection, general ledger interface and payment processing. Note that the Department has unique Finance and Accounting (F&A) requirements related to interfacing with existing financial management systems and calculating deductibles. 4) Reporting, including statistical reporting to the Division of Worker s Compensation (DWC) and other entities, claims data reporting to DWC and Centers for Medicare and Medicare Services (CMS), management reporting, work tracking, auditing, claims monitoring and actuarial data reporting. Statement of Work 5

6 Section 2 Project Governance Structure and Staffing Requirements This project will be administered by the Department s Division of Information Systems (DIS) and Division of Risk Management. The expected organizational chart of the project team follows. The Contractor is expected to fully cooperate and participate with the Department and any of its partners or Vendors. Project Sponsor Executive Steering Committee Department Project Manager Department Contract Manager Third Party Business App Owners Contractor Project Coordinator Department Project Team Contractor Project Team Key Resources Include: Requirements Lead, Development Lead, Testing Lead, Training Lead, Implementation Lead and Transition Resource The Department s governance structure and stakeholders include: Role Responsibility Project Sponsor Responsible for funding and project resources. Responsible for strategic project direction. Escalation point for Project Director. Executive Steering Consists of members from DIS, DRM and other stakeholders. Committee Monitors ongoing project progress. Responsible for supporting project with Division resources as necessary. Responsible for decision making regarding scope, budget and schedule of the Department Contract Manager Department Project Manager Contractor Project Coordinator project. Day-to-day point of contact for the Department in interfacing with the Contractor post implementation. Has authority to make or obtain contractual decisions on behalf of the Department. Responsible for dispute resolution. Escalation point for the Department Project Manager. Reviews, verifies and approves invoices from the Contractor. Manages day-to-day execution of the project during implementation. Coordinates activities and communication between project team members. Interfaces with Contract Manager to review and approve Contractor deliverables. Acts as liaison between the project team, project support, the steering committee and project sponsor. The Contractor Project Coordinator is required to be a Project Management Institute (PMI) certified Project Management Professional (PMP). A member of Key Resources (see Section 2.3). Statement of Work 6

7 Role Contractor Project Team Contractor Transition Resource (see 3.3) Department Project Team Departmental Project Support Functional Leads and Business Process Owners Technical Leads, DBA, Application Development Leads Third-Party Business Application Owners Responsibility Single day-to-day point of contact for the Department in interfacing with the Contractor. Responsible for the successful execution of the contract scope of work and deliverables. Responsible for tracking and reporting status of project execution to the Project Manager. Acts as liaison between the Contractor and the Project Manager and DRM Contract Manager. Responsible for successful technical, business and management activities for design, development and implementation of the project. Key resources on the Project Team include: o Requirements Lead o Development Lead o Testing Lead o Training Lead o Implementation Lead o Transition Resource A member of the Key Resources (see Section 2.3). A technical member of the design, development and implementation team that stays on after Go-Live to provide onsite operational maintenance and support for two years during the Services Transition Performance Period. Employees or contractors of the Divisions of Risk Management or Information Systems assigned by the Department to support the system design, implementation and operation associated with this Contract. Department Legal, Human Resources, Procurement, Finance and Accounting and Budget staff that provide additional project support as necessary. DRM resources that act as subject matter experts in verifying and refining requirements, reviewing designs and interfaces, confirming data accuracy and performing user acceptance testing. DIS resources that act as subject matter experts on the expected architecture of the new system as well as interfacing with existing business systems. Provide data extracts and work with the Contractor Project Team to implement APIs and interfaces to achieve the expected level of integration with external business applications. Responsible for providing necessary documentation and information on the function of third party applications that the new system will attach to. Assists in understanding the data structures needed to move data seamlessly between applications. Provides necessary access and permissions to the third party system to enable integration or interfacing. Third-party business application owners can be employee of the Department, other state or Federal agencies or third-party Vendors under contract with the Department. 2.1 Cooperation with the Department and Other Entities As required by Attachment A Standard Contract, section 7.8; the Contractor and its subcontractor(s) agree to cooperate fully with the Department, Partners, oversight authorities and other contractors retained by the Department. 2.2 Cooperation in the Event of a Subsequent Contractor If the Contract, or any portion thereof, is terminated for any reason prior to its completion, the Contractor agrees to comply with the terms of Attachment A Standard Contract section 12, Statement of Work 7

8 including cooperating fully with the subsequent contractor. Such requirement shall exist notwithstanding the reasons for the retention of the subsequent contractor, including but not limited to cancellation, termination or expiration of the Contract with the Contractor. 2.3 Contractor Staffing Requirements The Contractor shall maintain staffing levels sufficient to complete the services and meeting the requirements specified in the Contract and statement of work. Proposed individuals skill levels should be consistent with the proposed System and services. The Contractor must provide resumes demonstrating appropriate experience for all proposed staff. The Department reserves the right to reject any proposed team members throughout the Contract period. The Contractor will identify key personnel in their reply. Key personnel ( Key Resources ) are those that the Department or Contractor deem essential to the successful execution of the Project. Key personnel includes, but is not limited to: Project Coordinator, Requirements Lead, Development Lead, Testing Lead, Training Lead, Implementation Lead and Transition Resource(s). The Contractor may not reassign any key project personnel except as provided for and in the manner described by section 7 of Attachment A Standard Contract. The Contractor may not knowingly employ or contract with any former employee of the Department in violation of section , Florida Statutes (F.S.). Statement of Work 8

9 Section 3 Project Administration The following sections describe the responsibilities of the Contractor and the Department with regards to general project execution tasks. Later sections describe responsibilities related to Design, Development and Implementation tasks. 3.1 Project Management Project management is the responsibility of the Department and the Contractor. The Contractor will designate a Project Management Institute (PMI) certified Project Management Professional (PMP ) to oversee Contractor activities on this project. This person may not be replaced without the prior consent of the Department. The Contractor Project Manager is responsible for the successful delivery of the Contractor s services in accordance with the Contract and statement of work. The Contractor will manage all Contractor and subcontractor (if any) activities as specified in the Project Management Plan (PMP). The Department will develop the PMP with appropriate input from the Contractor. All activities described in the PMP will be consistent with the Project Management Body of Knowledge (PMBOK) standards for project management. The Contractor will be responsible for maintaining consistent communications with the Department Project Manager and other members of the project team. The Department will establish a SharePoint site for maintaining project documentation and deliverables. The Contractor will use this library to store, access and reference documents and deliverables related to this contract Contractor Project Management Responsibilities 1) Provide input into the PMP. 2) Manage and direct Contractor and subcontractor staff. 3) Create and maintain a fully resource-loaded project schedule for all Design, Development and Implementation (DDI) activities. 4) Manage the project according to the agreed project schedule. 5) Prepare and submit weekly project status reports. 6) Participate in weekly project status meetings. 7) Prepare and distribute minutes from project status meetings within three business days of meeting. 8) Identify risks, issues and opportunities and submit to Project Manager. 9) Identify and notify Department Project Manager of scope, budget, schedule or resource issues. 10) Require compliance with project management, development, security and other standards of the Department from all Contractor and subcontractor resources. Statement of Work 9

10 11) Prepare formal reports and presentations. 12) Participate and cooperate with audits, reviews and quality activities. 13) Provide documents to the Project team for review in the formats and on the timeframes specified in the project schedule and Deliverable Expectation Documents (DEDs) and maintain project documentation in SharePoint site. 14) Maintain records in accordance with the Florida Sunshine laws as appropriate Department Project Management Responsibilities 1) Develop and maintain the PMP. 2) Work with the Contractor to develop or approve applicable project management templates. 3) Define reporting structures and expectations between project participants. 4) Facilitate the resolution of issues. 5) Facilitate the availability of Department staff. 6) Facilitate timely review and acceptance of project deliverables. 7) Review and approve schedules changes. 8) Review and approve risk or issue mitigation plans or activities. 9) Review and approve all Contractor project staff. 10) Review and approve project status reports. 11) Negotiate changes in scope as appropriate and necessary. 12) Coordinate with stakeholders to prepare for implementation. 13) Support the Contractor by providing required information timely. 14) Provide a SharePoint library for all project documentation. 15) Provide the Contractor with workspace at the Department s facilities in Tallahassee, Florida. 16) Provide the Contractor access to the Department s infrastructure, including server and operating system, network connectivity, database software and tools, and data storage as needed for the Project. The Contractor will use these resources in accordance with the Department s published usage and security guidelines. Any Contractor resources connected to the Department s infrastructure will be subject to inspection and approval. See: Phase Gate Reviews The Department will manage the progress of the Project according to phases as described in the Design, Development and Implementation section. Each phase concludes with a formal gate review of Project deliverables, risks, opportunities and accomplishments. These reviews give the Department and the Contractor an opportunity to determine whether the Project is making sufficient progress to continue. Successful completion of the gate review at the end of a Statement of Work 10

11 phase is the trigger that allows the Contractor to invoice the Department for Deliverables completed within that phase, per the process defined in Attachment A Standard Contract sections 8 (Acceptance of Deliverables) and 9 (Payment and Financial). 3.3 Knowledge Transfer The Department requires the Contractor to develop and execute a robust knowledge transfer plan. It is the intent of the Department to develop the internal capabilities to maintain the System after implementation. The Contractor must include in its proposal staffing for a two-year transition period after implementation. The resource(s) identified by the Contractor responsible for the Transition Period must be member(s) of the implementation team during the initial System implementation ( Transition Resource ). During this transition period, responsibility for maintaining the System will gradually transition from the Contractor to Department staff. During Design, Development and Implementation the Contractor is responsible for developing a transition plan that covers this two-year period. The Transition Plan should detail the knowledge that the Department must gain proficiency in and provide a schedule with testable milestones for the Department s resources to achieve. In addition, knowledge transfer will be an integral component of each phase gate, with functional and technical knowledge transfer expected to be a component of each major deliverable signoff Contractor Knowledge Transfer Responsibilities 1) Develop and maintain a Knowledge Transfer Plan for pre- and post- implementation. Plan must include phased hand-off, identify key knowledge, skills and abilities (KSAs) that Department staff must obtain and identify any foundational skill sets required to support the System (e.g. third-party tool use, programming language, etc.). 2) Conduct formal deliverable reviews / trainings for Department as appropriate. 3) Provide minutes of formal deliverable reviews. 4) Pre-implementation, assess and report to Department Project Manager on level of proficiency achieved by Department staff after each phase gate. 5) Post-implementation, assess and report monthly to Project Manager on level of Department proficiency and readiness to assume maintenance activities Department Knowledge Transfer Responsibilities 1) Identify key staff for knowledge transfer. 2) Ensure key staff is available to participate in reviews and trainings. 3) Obtain, at Departmental expense, any third-party tool training deemed required for assuming maintenance responsibilities for the new System (e.g. DB training, programming language training, etc.) Statement of Work 11

12 3.4 Disaster Preparedness / Disaster Recovery The Contractor shall work with the Department to become familiar with the Department s Disaster Recovery ( DR ) infrastructure. The Contractor shall then, within thirty (30) days of execution of the Contract, submit to the Department s Project Manager input to the Department s Disaster Preparedness Plan, including provisions for pre-disaster records protection and an alternative Recovery Plan that allows the Contractor to continue functioning in compliance with the Contract in the event of an actual emergency. The input to the Disaster Preparedness Plan shall also include Recovery Plans specific to the new System that details actions to be taken in the event of a natural disaster or disaster resulting from negligence, sabotage, mob action, etc. The Contractor should also be aware of the requirements of Attachment A Standard Contract, section 10.8 (Excusable Failure) Contractor Disaster Preparedness / Recovery Responsibilities 1) Work with the Department to understand the existing DR infrastructure. 2) Prepare input to the Disaster Preparedness Plan. 3) Execute the project-specific Disaster Recovery Plan as required during the Contract term in collaboration with the Department Department Disaster Preparedness / Recovery Responsibilities 1) Review, edit or approve the Contractor s input to the Disaster Preparedness Plan. 2) Provide the Contractor with the existing Disaster Recovery Plan for the Department s assets. 3) Execute the Disaster Recovery Plan after the Contract term. Statement of Work 12

13 Section 4 Project Execution Performance Periods The Project shall consist of three performance periods the Design, Development and Implementation (DDI) Performance Period, the Services Transition (ST) Performance Period and the optional Operations Support (OS) Performance Period. The DDI Performance Period includes all activities from the time of contract execution to System Go-Live. The Services Transition Performance Period begins at System Go-Live and continues for a period of two (2) years post Go-Live. The optional Operations Support Performance Period begins at the conclusion of the Services Transition period and continues for two (2) years. The Operations Support Performance Period tasks may be renewed for a period of five (5) years after completion of the initial contract term. 4.1 DDI Performance Period The DDI Performance Period includes all of the activities necessary to implement the new System, including data migration, report development, installation, configuration, customization and training. The DDI Performance Period is broken into Phases. The following Phases and approach may be updated to be consistent with the Contractor s SDLC as agreed to by the Department during negotiations. Phase One: Phase Two: Project Initiation and Planning Requirements Elaboration. Phase Three: System Design. Create functional, business process, technical, interface and data conversion designs. Phase Four: application. Phase Five: Phase Six: System Development and Test. Install, Configure, Code and Unit Test Data Conversion. Populate new System with legacy data from multiple sources. Testing. Phase Seven: Go-Live and Training. Move into production environment with required training and documentation. 4.2 ST Performance Period This Performance Period includes the warranty period and oversees the transition of maintenance capabilities from the Contractor to the Department post-implementation over a two-year timeframe after Go-Live. Phase A: Phase B: Warranty and Documentation Services Transition Statement of Work 13

14 4.3 OS Performance Period If the Department determines it is in the best interest of the Department and the State to engage the Contractor to provide ongoing Operational Support, the optional OS Performance Period would begin at the end of the two-year Services Transition Performance Period. If the Department selects this option, the Department and the Contractor must negotiate to refine the statement of work and document a detailed service level agreement (SLA). The agreed statement of work and SLA will be incorporated into the Contract by Amendment. Statement of Work 14

15 Section 5 Design, Development and Implementation (DDI) Performance Period 5.1 DDI Performance Period Phase One: Initiation and Planning During Project Initiation and Planning, the project will kick off and the Department and the Contractor will work together to define how the project and all tasks will be managed, including the definition of the System Development Life Cycle (SDLC). The Department will create a Project Management Plan (PMP). The Contractor will provide input and updates to the PMP. The plan will follow industry standard practices for project management and will include at a minimum, the methodology and approach for the project. Within thirty (30) days of contract initiation, the Contractor will conduct a kick-off meeting in coordination with the Department. All of the Contractor s key staff will attend the kick off meeting. The purpose of the meeting will be to review the project plan (including scope management, schedule management, risk management, change management, quality management, communication management and resource management) and the various deliverables associated with the complete SDLC of the project, as well as establishing general project understanding among the Stakeholders. Such understanding should include, but is not limited to, the identification, roles and responsibilities of stakeholders, the SDLC methodology the Contractor will employ, the processes that will be used to review and provide input into processes and deliverables, critical success factors and the performance measures that will be used to evaluate the Project. The Contractor shall conduct one or more additional project initiation meetings if deemed necessary by the Department to meet the goals and objectives of this phase. The Contractor and the Department will implement the workspace and development environment requirements agreed to during negotiations. This Contractor is expected to perform the work under this Contract at the Department s facilities in Tallahassee, Florida. The Contractor and the Department s Project Manager will work together to prepare the work site, including obtaining necessary background checks on Contractor staff, setting up work spaces, establishing necessary credentials and accounts and establishing the necessary technical environment. The Department expects that all workspace and technical environments will be operational within 30 days of the Contract execution. The Department s project team and the Department Project Manager will work together to develop and refine the PMP according to the project approach and schedule. The PMP will include various subcomponents, some of which are the responsibility of the Contractor to provide. Subcomponents shall be due either prior to the kick-off meeting or at the end of the phase gate, according to the following matrix: Subcomponent Responsibility Of Due Prior To Project Charter Department Kickoff Project Schedule Contractor Kickoff SDLC Methodology Contractor, with input from Kickoff Department Budget Management Plan Department Kickoff Schedule Management Plan Department, with input from Kickoff Contractor Project Change Control Management Department Kickoff Statement of Work 15

16 Subcomponent Responsibility Of Due Prior To Plan (includes scope and schedule) Deliverable Expectation Document Department, with input from Kickoff (DED) and Deliverable Checklists Contractor Phase Gate Approval Criteria Department Kickoff Phase Gate / Deliverable Review and Department Kickoff Acceptance Process Disaster Preparedness Plan Contractor Kickoff (within 30 days of contract execution) Communication Management Plan Department, with input from Phase Gate Contractor Document Management Plan Department, with input from Phase Gate Contractor Quality Management Plan Contractor Phase Gate Risk / Issue Management Plan Contractor Phase Gate Knowledge Transfer Plan Contractor Phase Gate Human Resource Management and Contractor Phase Gate Staffing Plan Configuration Management Plan Contractor, with input from Phase Gate Department Information Security Plan Department, with input from Contractor Phase Gate Contractor Initiate and Plan Responsibilities 1) Onboard Contractor staff, including required background checks. 2) Prepare PMP subcomponents according to the above schedule. 3) Provide input into planning deliverables that are the responsibility of the Department as needed. 4) Facilitate the Project kickoff meeting. 5) Capture minutes from the kickoff meeting and note any decisions or agreements. Minutes will be delivered for Department review and approval within three (3) business days of the kickoff. 6) Work with Department staff to establish workspace per the Contract. 7) Work with Department staff to establish the technical environment per the Contract. 8) Implement tool or database for tracking and reporting issues per the issue management plan Department Initiate and Plan Responsibilities 1) Obtain a MFMP Purchase Order to authorize Contractor work initiation. 2) Review, approve or reject all proposed Contractor staff. 3) Obtain results from Contractor and track successful completion of required background checks. 4) Prepare PMP subcomponents according to the above schedule. 5) Provide input into planning deliverables that are the responsibility of the Contractor as needed. Statement of Work 16

17 6) Supply workspace and configure required accounts and permissions as necessary for Contractor Project Team per the Contract. 7) Supply hardware, software and infrastructure for which the Department is responsible per the Contract. 8) Establish the SharePoint document repository for the Project. 9) Participate in the kickoff meeting. 10) Communicate with the Steering Committee and all key stakeholders regarding Project Initiation. 5.2 DDI Performance Period Phase Two: Requirements Elaboration The Contractor shall elaborate and refine the requirements provided in this ITN to generate specific, detailed requirements. The Contractor shall verify requirements with the Department and other stakeholders to ensure requirements are correct, understandable and testable. Additionally, the Contractor shall specifically evaluate the completeness of the requirements to ensure that all requirements have been captured and develop any additional requirements necessary to address the entire System. The Contractor shall generate detailed requirements by Joint Application Development (JAD) sessions or other Department-approved methodology proposed by the Contractor. The methodology must be consistent with the Contractor s approved SDLC. The Contractor s approach must acknowledge the time limitations of business users and facilitate and encourage the participation of all stakeholders (e.g., DRM, DIS, State Agencies) with efficient processes. The Contractor s methodology shall clearly indicate the process that will be followed during the requirements sessions. The Contractor will work with the Department s Project Manager to run requirements sessions and the Contractor shall prepare a clearly defined agenda at least three (3) business days prior to any meeting. The Contractor shall maintain minutes of the session and submit those to the Department for review and approval within three (3) business days of the meeting. In addition, the Contractor shall capture any modifications to the requirements according to the traceability requirements detailed below. The Contractor shall generate a Requirements Definition Document (RDD) to document the requirements. The RDD must include, but is not limited to, use cases, descriptions of System and user interfaces, communication interfaces, product functions, user characteristics, constraints and assumptions, external interface requirements, design constraints, and logical database requirements. Note that particular care must be applied to documenting requirements related to external system interfaces. External business applications such as FLAIR (the State s accounting system), FileNet (for Division document and image management) and CODA (the Department s cash receipts system) among others perform essential functions for the Division and must be supported. A listing of known external interfaces can be found in Attachment I. The Contractor shall document all interface requirements, including plans to migrate and deprecate business applications that will no longer be needed with the new System. The Contractor must maintain system requirements in a Requirements Management Tool. The Contractor shall provide this tool, subject to Department approval. The tool can be custom developed or industry standard, but must provide import/integration of standard tools such as Microsoft Excel, be web enabled and provide export/reporting features. The provided tool shall Statement of Work 17

18 include the ability to output a robust Requirements Traceability Matrix (RTM) to track the relationship between requirements and the developed System. The Contractor shall provide the Department with five (5) perpetual licenses for the tool for Department users if so requested. After completion of the Requirements Elaboration phase, requirements will be Baselined. Should additional requirements come to light during later phases of the DDI, the Contractor will utilize the same elaboration methodology employed in this phase. Additional requirements will be recorded in the requirements management tool and evaluated for inclusion through the Project s change management process Contractor Requirements Elaboration Responsibilities 1) Work with the Department to develop the DED for Phase Deliverables. 2) Provide a defined methodology to validate and maintain requirements including the process of how requirements validation sessions will be conducted. 3) Provide a proposed schedule of requirements validation sessions. 4) Ensure that the Contractor s functional and technical experts are on-site during the requirements validation sessions to address and answer any questions. 5) Provide an agenda for each requirements validation session a minimum of three (3) days prior to the meeting. 6) Conduct and document requirements validation sessions. 7) Manage time efficiently during the requirements session to ensure efficient use of the participants time. 8) Provide a report of each requirements validation session, including but not limited to: issues addressed, decisions made, and business rules linked to the requirements, workflows, forms, etc. to the Department s Project Manager within three (3) business days of the session. 9) Work with the Department to describe the business processes that will exist as a result of the proposed System implementation. 10) Validate needs through prototyping of functionality, navigation, and workflow. 11) Prepare the Requirements Definition Document, including interface descriptions. 12) Install and prepare the requirements management tool, as needed. 13) Provide training to Department staff in use of requirements management tool, as needed. 14) Enter requirements into the requirements management tool Department Requirements Elaboration Responsibilities 1) Work with the Contractor to develop the DED for Phase Deliverables. 2) Review and approve requirements elaboration schedule. Statement of Work 18

19 3) Participate in JAD or requirements elaboration meetings, with appropriate staff members to clearly describe required functionality and clarify needs to the Contractor. 4) Resolve any issues raised during requirements elaboration related to conflicting or unclear requirements. 5) Provide leadership in coordinating efforts with Department and partners for requirements elaboration. 6) Provide interpretation of legislative statutes and existing policies and procedures. 7) Identify business process owners with authority to provide input into requirements elaboration and process definition. 8) Work with the Contractor to describe new business processes that will result from use of the new System. 9) Review and approve all requirements deliverables, including meeting reports. 5.3 DDI Performance Period Phase Three: System Design Design Phase Functional Design The Contractor shall generate a conceptual system design and provide a Functional Design Document (FDD) for the proposed System. The FDD shall include, but not be limited to, data models and process models and must include both graphic and narrative component for each form, report, interface, conversion and enhancement. All business rules and workflows must be documented in detail. The Contractor shall develop prototypes to depict System functionality including user interface screens that will be available in the final System. The Contractor shall update the requirements management tool to reflect the relationship between requirements and design elements. At the completion of the System development, the Contractor shall ensure that the FDD is updated to represent the complete as-built new System. After acceptance of the Design phase by the Department, the functional design will be Baselined. The Contractor shall report all issues after this point through the accepted issue management process. The Contractor will record the issues in the accepted issue-tracking tool. Any modifications to the Functional Design Document after Baselining will be evaluated through the Project s change management process agreed to in the PMP Contractor Functional Design Responsibilities 1) Work with the Department to develop the DED for Phase Deliverables. 2) Prepare the Functional Design Document. 3) Prototype forms and screens, menu navigation and business functions. 4) Facilitate walk-throughs of the System design with business process owners. 5) Capture results or modifications from walk-throughs and update documentation as needed. Summary meeting minutes must be produced within three (3) business days of meeting. Statement of Work 19

20 6) Update the Requirements Management Tool as needed to reflect the relationship between requirements and the design Department Functional Design Responsibilities 1) Work with the Contractor to develop the DED for Phase Deliverables. 2) Provide input into the functional design. 3) Participate in reviews and walk-throughs of the proposed System design and provide direction and feedback. 4) Review and approve all Design deliverables, including meeting reports Design Phase Business Process Re-engineering The Contractor shall work with stakeholders to create re-engineered, future state Department business processes to reflect the approved System design and shall document the new business processes. The future state business processes should enable stakeholders to effectively realize the full benefits of System implementation. All in-scope business processes shall be documented in a final To-Be Process Models document and provided to the Department for approval Contractor Business Process Re-engineering Responsibilities 1) Work with the Department to develop the DED for Phase Deliverables. 2) Create future state Department and Partner business processes to reflect the System as designed. 3) Create business process deliverables. 4) Prepare an Organizational Change Management Plan to prepare for the implementation of the new System, including the activities necessary for the Department and Partners to successfully adopt the new System while minimizing the impact to staff productivity and business performance. This Plan shall include staff roles and responsibilities. 5) Prepare a Staffing and Productivity Impact Analysis Report based on the model for the new System. 6) Facilitate walk-throughs of business process designs with business process owners. 7) Capture results or modifications from walk-throughs and update documentation as needed. Summary meeting minutes must be produced within three (3) business days of meeting Department Business Process Re-engineering Responsibilities 1) Work with the Contractor to develop the DED for Phase Deliverables. 2) Participate in process design sessions. Statement of Work 20

21 3) Provide interpretation of applicable statutes, rules, Department and Partner policies and guidance documents. 4) Develop any internal policy changes required to support new business processes. 5) Participate in reviews and walk-throughs of proposed business processes and provide direction and feedback. 6) Review and approve all Design deliverables, including meeting reports Design Phase Technical Design The Department will work closely with the Contractor during the Technical Design. The Department reserves the right to directly participate in and contribute to tasks required during the Technical Design, in consultation with the Contractor. The Contractor will specify software languages and tools that are widely available in the market. The Contractor shall generate a Technical Design Document (TDD) with the final requirements for the System, including a configuration plan, infrastructure plan and physical and logical security plan. The Contractor shall update the Requirements Management Tool to reflect the relationship between requirements and design elements. The Contractor shall conduct informal reviews of the design as it is developed and provide the Department with access to informal review information and documentation. The Contractor shall develop its configuration management plan to include descriptions of the software configuration and customizations necessary to meet functional and non-functional requirements and interfaces. The Contractor s infrastructure plan must include a list of the hardware, software and network elements necessary to support the new System through implementation, production and ongoing support and maintenance. The infrastructure list shall include applicable Commercial- Off-The-Shelf (COTS) software, operating systems, relational database management systems, and other supporting software. The Contractor shall clearly identify all the proposed custom developed software. The Contractor shall provide an explanation of the associated benefits and risks for all recommended custom developed software. The Contractor will then work with DRM and DIS staff to evaluate existing resources to determine what hardware or software can be reused for the new System and evaluate alternatives for the System architecture. The Department s physical and logical Security Plan template must be included in the TDD. The Contractor will work with the DIS Information Security Office to complete the plan according to the Department s Information Systems Development Methodology (ISDM). The plan shall include, but is not limited to: resource access enforcement, separation of duties, session management, remote or mobile access policies, logging and monitoring, authentication and data risk assessment. The Department reserves the right to purchase any of the items specified in the TDD from another source instead of acquiring them from the Contractor if it is in the best interest of the Department. Statement of Work 21

22 After acceptance of the System Design phase by the Department, the Technical Design will be Baselined. This must occur prior to development beginning. The Contractor shall report all issues after this point through the accepted issue management process. The Contractor will record the issues in the accepted issue-tracking tool. Any modifications to the Technical Design Document after baselining will be evaluated through the Project s change management process. The FDD and the TDD, once Baselined, will comprise the agreement between the Department and the Contractor regarding the functionality and operation of the System Contractor Technical Design Responsibilities 1) Work with the Department to develop the DED for Phase Deliverables. 2) Collaborate with Department staff to finalize the technical design, including the database structure, load management, and storage and hardware requirements. 3) Work with Department staff to evaluate existing assets to determine what can be used to support the new System. 4) Assist the Department in completing the physical / logical Security Plan template. 5) Prepare the Technical Design Document. 6) Facilitate walk-throughs of the System design with technical Subject Matter Experts (SMEs). 7) Capture results or modifications from walk-throughs and update documentation as needed. Summary meeting minutes must be produced within three (3) business days of meeting. 8) Update the Requirements Management Tool as needed to reflect the relationship between requirements and the design Department Technical Design Responsibilities 1) Work with the Contractor to develop the DED for Phase Deliverables. 2) Collaborate with the Contractor on the technical design, particularly with regards to existing environments, Department standards, security requirements, storage, DR and network capabilities, etc. 3) Participate in reviews and walk-throughs of the proposed System design and provide direction and feedback. 4) Review and approve all Design deliverables, including meeting reports. 5) Procure necessary hardware or software Design Phase Interface Design A critical Division requirement is the seamless integration or interface of the proposed System with various external systems. A list of existing interfaces can be found in Attachment I. Some of these systems will be retired after implementation of the new System, as their functions will now be handled by the new System (for example, the Division currently uses a Microsoft Access application to issue and track invoices). Other systems will have to be modified to support an Statement of Work 22

23 electronic data interchange (EDI) with the new System (for example, the Department s cash receipts system, CODA, will likely need to be modified to support a live feed of data from the new system), or will remain as they are, but the new system must automate the now-manual data exchange and apply appropriate business logic to responses provided by the external system. Finally, some external business applications will need to be integrated with the new System for seamless user interaction (for example, FileNet or the Medical Case Manager s (MCM s) management system). The Department will work closely with the Contractor during the Interface Design. The Department reserves the right to directly participate in and contribute to tasks required during the Interface Design, in consultation with the Contractor. The Contractor shall collaborate with the Department to define and document all interfaces with external business applications. The Contractor shall generate Interface Definitions for each of the external business applications that will be supported, describing each interface in detail, specifying purpose, format, content, frequency, and transaction processing. Each EDI-based interface must include a data map for incoming transactions that describes how incoming data is transformed, how appropriate business rules are applied and how data is mapped to the new System s database. Each EDI-based interface must also include an export file definition, where needed, for outgoing data feeds. The export file definition must describe the field names, data type, length, allowable value limits, delimiter and any other data required by the target external business application. The Contractor shall manage and facilitate all meetings on interfaces, prepare meeting minutes, and track interface coordination status in the status meetings. The Contractor shall update the requirements management tool to reflect the relationship between requirements and design elements. After acceptance of the System Design Phase by the Department, the Interface Design will be Baselined. The Contractor shall report all issues after this point through the accepted issue management process. The Contractor will record the issues in the accepted issue-tracking tool. Any modifications to the Interface Definitions or design after Baselining will be evaluated through the Project s change management process, agreed to in the PMP Contractor Interface Design Responsibilities 1) Work with the Department to develop the DED for Phase Deliverables. 2) Work with external business system owners / developers to define the functional and technical design for interfacing with the new System. The Contractor will propose innovative Systems where appropriate to achieve the Department s objectives of eliminating manual effort to the degree possible and increasing data accuracy and timeliness. 3) Facilitate design meetings, prepare agendas and capture minutes of each interface session. Minutes, including issues addressed and decisions made, shall be submitted to the Department s Project Manager within three (3) business days of meeting. 4) Prepare the Interface Definitions. Statement of Work 23

24 5) Update the TDD as needed for additional hardware or software necessary to support integration or EDI. 6) Facilitate walk-throughs of the interface designs with functional and technical SMEs. 7) Capture results or modifications from walk-throughs and update documentation as needed. Summary meeting minutes must be produced within three (3) business days of meeting. 8) Update the Requirements Management Tool as needed to reflect the relationship between requirements and the design Department Interface Design Responsibilities 1) Work with the Contractor to develop the DED for Phase Deliverables. 2) Identify application owners for each external business application. 3) Facilitate and coordinate with application owners to be available for Contractor meetings. 4) Obtain access / cooperation of any external (non Departmental) entity required for interface design (e.g. MCM Vendor). 5) Participate as needed in design meetings. 6) Work with Contractor to understand business rules or transformations that will have to be applied to external business system responses. 7) Participate in reviews and walk-throughs of the proposed System design and provide direction and feedback. 8) Review and approve all Design deliverables, including meeting reports Design Phase Data Conversion Design STARS contains approximately 40 years of historical policy and claims data. In addition to STARS, DRM data exists in spreadsheets and databases where the existing system lacked the ability to store or process the data. The Department has a separate project underway to extract historical data from STARS, scrub and define it. The Department has not yet decided how much of the historical data will be brought into the new System. The Department will work closely with the Contractor during the Data Conversion Design. The Department, in consultation with the Contractor, reserves the right to directly participate in and contribute to tasks required during the Data Conversion Design. The Department will provide the Contractor with a data definition file. The Contractor will map that data to the new System s data model. The Contractor shall create a Data Conversion Plan that defines how the data will be imported, transformed and tested for accuracy postconversion. The Data Conversion Plan will be incorporated into the Contractor s Go-Live Plan. The Data Conversion Plan should also address how historical data can be archived and retrieved according to the System s established record management features. Statement of Work 24

State of Florida Department of Financial Services. Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System

State of Florida Department of Financial Services. Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System State of Florida Department of Financial Services Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System Addendum #2 Modifications to the ITN documentation ITN, Section 2.2, Schedule

More information

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures PROCEDURE Title: Information Technology (IT) Project Management and Governance Procedures Related Policy: FDJJ 1270 I. DEFINITIONS Agency for State Technology (AST) Rule Rules 74-1.001 through 74-1.009,

More information

STATE OF FLORIDA OFFICE OF FINANCIAL REGULATION ATTACHMENT - B. Statement of Work. Deferred Presentment Transaction System

STATE OF FLORIDA OFFICE OF FINANCIAL REGULATION ATTACHMENT - B. Statement of Work. Deferred Presentment Transaction System STATE OF FLORIDA OFFICE OF FINANCIAL REGULATION ATTACHMENT - B Statement of Work Deferred Presentment Transaction System Table of Contents 1 Overview and Project Purpose... 3 1.1 Background and Current

More information

Solution Analysis and Design Strategy (D18)

Solution Analysis and Design Strategy (D18) (D18) Department of Financial Services Date: 11/29/2018 Revision: 1.0 Table of Contents Table of Contents... 2 Revision History... 3 Executive Summary... 4 1 Introduction... 4 2 Solution Analysis and Design

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

Title: Project Director Location: Tallahassee, FL Clearance: none required

Title: Project Director Location: Tallahassee, FL Clearance: none required Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016 Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 2016 Meeting Minutes Facilitator: Robert

More information

Design, Development and Implementation (DDI) Project Management Plan (PMP)

Design, Development and Implementation (DDI) Project Management Plan (PMP) Design, Development and Implementation (DDI) Project Management Plan (PMP) Department of Financial Services Date: 11/15/2018 Revision: V1.0 Revision History Version Date Revision Notes 1.0 11/15/2018 Accepted

More information

Notice is hereby given of the following changes to the above-referenced SOLICITAITON:

Notice is hereby given of the following changes to the above-referenced SOLICITAITON: FLORIDA DEPARTMENT OF TRANSPORTATION Procurement Office 605 Suwannee Street, MS 20 Tallahassee, Florida 32399-0450 Phone: (850) 414-4381 Fax: (850) 414-4951 ADDENDUM NO. 2 DATE: May 10, 2016 RE: BID #:

More information

Project Management Methodology. Construct & Unit Test SubPhase

Project Management Methodology. Construct & Unit Test SubPhase Project Management Methodology & Unit Test SubPhase Course Purpose Familiarize team members with the & Unit Test Sub- Phase processes. Understand process flows, team member roles, and artifacts employed.

More information

HIPAA Summit VII. Preconference III. Advanced Strategies to Achieve ROI in Implementing HIPAA

HIPAA Summit VII. Preconference III. Advanced Strategies to Achieve ROI in Implementing HIPAA HIPAA Summit VII Preconference III Advanced Strategies to Achieve ROI in Implementing HIPAA Case Study Report: The Health Reinsurance Association (HRA) and Pool Administrators Inc. (PAI) By Karl Ideman,

More information

IBM Clinical Trial Management System for Sites

IBM Clinical Trial Management System for Sites Service Description IBM Clinical Trial Management System for Sites This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized users

More information

Reference B Project Management Requirements

Reference B Project Management Requirements Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master

More information

Invitation to Negotiate (ITN) Statewide Travel Management System ITN No D. Questions and Answers ITN Amendments

Invitation to Negotiate (ITN) Statewide Travel Management System ITN No D. Questions and Answers ITN Amendments Invitation to Negotiate (ITN) ADDENDUM NO. 1 Questions and Answers ITN Amendments September 2016 Contained herein are the responses to the questions submitted to the Department of Management Services (Department).

More information

Project Planning and Management (PPM) V2.0. WBS Dictionary

Project Planning and Management (PPM) V2.0. WBS Dictionary Project Planning and Management (PPM) V2.0 WBS Dictionary Software as a Service (SaaS) Version 1.0 August 2014 1 Table of Contents PPM V2.0 Work Breakdown Structure (WBS) Dictionary 1 Project Type: Software

More information

Attachment B Project Specifications

Attachment B Project Specifications TABLE OF CONTENTS INTRODUCTION... 4 SOFTWARE... 4 PROJECT FACILITIES AND OFFICE EQUIPMENT... 5 PROJECT STAFFING... 6 IMPLEMENTATION CONSIDERATIONS... 6 5.1 Project Phases... 7 5.2 Project Stages... 7 5.3

More information

Project Management Knowledge Areas SECTION III

Project Management Knowledge Areas SECTION III Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

Information Technology Independent Verification and Validation

Information Technology Independent Verification and Validation Florida Department of Management Services Information Technology Independent Verification and Validation RFP No. Work Plan and Methodology ; 2:30 PM EST 2150 River Plaza Drive Suite 380 Sacramento California

More information

Exhibit A - Scope of Services AMI Implementation Project Management Services

Exhibit A - Scope of Services AMI Implementation Project Management Services Exhibit A - Scope of Services AMI Implementation Project Management Services Deliver to: City of Santa Rosa 90 Santa Rosa Avenue Santa Rosa, CA 95401 Attn: Kimberly Zunino City of Santa Rosa June 2, 2016

More information

EXHIBIT A: STATEMENT OF WORK

EXHIBIT A: STATEMENT OF WORK EXHIBIT A: STATEMENT OF WORK TABLE OF CONTENTS 1. INTRODUCTION 2. PROJECT PLANNING AND MANAGEMENT 6 3. INFRASTRUCTURE / TECHNICAL ENVIRONMENT 10 r-e'" 4. FMS UPGRADE 13 4.1 BUILD PHASE 13 4.2 ACHIEVE PHASE

More information

IBM Clinical Trial Management System for Sites

IBM Clinical Trial Management System for Sites Service Description IBM Clinical Trial Management System for Sites This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized users

More information

I - PROJECT STATUS OVERVIEW

I - PROJECT STATUS OVERVIEW Project Sponsor: Denise Arnold Project Manager: Naru Nayak Status Report : 10/1/2015 12/31/2015 Project R&C Category: Pre-Charter Phase - 3 Initiation/Planning Phase To Be Assessed Start : July 01, 2015

More information

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services Contract Administration: Tips for Improving your Contract Administration Process Jennifer Adling Director of Procurement Services Contract Administration Following the award of a contract, the management

More information

Department of Health STATEMENT OF WORK Operations and Maintenance Services For the Web-Based Michigan WIC Data System Bureau of WIC Program Services

Department of Health STATEMENT OF WORK Operations and Maintenance Services For the Web-Based Michigan WIC Data System Bureau of WIC Program Services Department of Health STATEMENT OF WORK Operations and Maintenance Services For the Web-Based Michigan WIC Data System Bureau of WIC Program Services Section I Purpose: With the passage into law of House

More information

EXHIBIT K: PROJECT ASSUMPTIONS GENERAL AND PROJECT ADMINISTRATION ASSUMPTIONS

EXHIBIT K: PROJECT ASSUMPTIONS GENERAL AND PROJECT ADMINISTRATION ASSUMPTIONS EXHIBIT K: PROJECT ASSUMPTIONS CGI has specified general project assumptions as well as assumptions associated with specific tasks, activities, roles and responsibilities. These additional assumptions

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project September 2016 Date: 10/12/2016 Version 1.0 Table of Contents Executive

More information

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 3 FACILITATOR: MELISSA TURNER 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: DAYMON JENSEN, RACHAEL LIEBLICK, MELISSA TURNER Budget FY

More information

2. Services. The Scope of Work is amended by adding additional work. The additional work is detailed in the attached Exhibit A.

2. Services. The Scope of Work is amended by adding additional work. The additional work is detailed in the attached Exhibit A. AMENDMENT TO THE PERSONAL SERVICES AGREEMENT Amendment No. 4 Agreement #105972/31700039 Project Number: IT14AA This Amendment No. 4 to Personal Services Agreement is entered into effective between the

More information

UC Modernization Project - Phase 2b

UC Modernization Project - Phase 2b State of Florida Agency for Workforce Innovation UC Modernization Project - Phase 2b #10-ITN-001-SS - UC Modernization Project - Phase 2b (UCCBIS) System Design, Development and Implementation Accenture

More information

Monthly IV&V Assessment Report (December 1 31, 2015)

Monthly IV&V Assessment Report (December 1 31, 2015) Monthly IV&V Assessment Report (December 1 31, 2015) Department of Financial Services Date: 01/13/2016 Version 1.0 Table of Contents Department of Financial Services Executive Summary... 4 Project... 4

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project October 2017 Date: 11/13/2017 Version 1.0 Table of Contents Executive

More information

Contents About This Guide... 5 Upgrade Overview... 5 Examining Your Upgrade Criteria... 7 Upgrade Best Practices... 8

Contents About This Guide... 5 Upgrade Overview... 5 Examining Your Upgrade Criteria... 7 Upgrade Best Practices... 8 P6 EPPM Upgrade Best Practices Guide 16 R2 September 2016 Contents About This Guide... 5 Upgrade Overview... 5 Upgrade Process... 5 Assessing the Technical Environment... 6 Preparing for the Upgrade...

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project February 2018 Date: 3/12/2018 Version 1.0 Table of Contents Executive

More information

EXECUTIVE STEERING COMMITTEE MEETING

EXECUTIVE STEERING COMMITTEE MEETING 2 EXECUTIVE STEERING COMMITTEE MEETING DEPARTMENT OF REVENUE BUILDING 2 NOVEMBER 1, 2017 3 ROLL CALL AND OPENING REMARKS FACILITATOR: RYAN WEST, CHAIR 4 REVIEW OF SEPTEMBER 27, 2017 MEETING MINUTES FACILITATOR:

More information

3.0 INTRODUCTION - PERFORMANCE SPECIFICATIONS Purpose of Procurement

3.0 INTRODUCTION - PERFORMANCE SPECIFICATIONS Purpose of Procurement 3.0 INTRODUCTION - PERFORMANCE SPECIFICATIONS 3.1. Purpose of Procurement The overall objective of this Request for Quote is to obtain the services of a qualified Information Technology consulting firm

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

DEPARTMENT OF REVENUE BUILDING 2 DECEMBER 13, 2017

DEPARTMENT OF REVENUE BUILDING 2 DECEMBER 13, 2017 DEPARTMENT OF REVENUE BUILDING 2 DECEMBER 13, 2017 3 ROLL CALL AND OPENING REMARKS FACILITATOR: RYAN WEST, CHAIR 4 REVIEW OF NOVEMBER 1, 2017 MEETING MINUTES FACILITATOR: MELISSA TURNER 5 FLORIDA PALM

More information

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required

More information

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.

More information

Project Plan City of Newport News; Department of Health and Human Services

Project Plan City of Newport News; Department of Health and Human Services Project Plan City of Newport News; Department of Health and Human Services 7/14/2010 Harmony Information Systems, Inc. 12120 Sunset Hills Road, Suite 500 Reston, VA 20190 MAIN: 703-674-5100 www.harmonyis.com

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

CSE AUTOMATED MANAGEMENT SYSTEM. Florida Department of Revenue CAMS Project Procurement and Contract Management Plan Version 1.00

CSE AUTOMATED MANAGEMENT SYSTEM. Florida Department of Revenue CAMS Project Procurement and Contract Management Plan Version 1.00 CAMS CSE AUTOMATED MANAGEMENT SYSTEM Florida Department of Revenue CAMS Project Procurement and Contract Management Plan Version 1.00 Revision History Date Version Description Author 04/30/2007 0.01 Broke-out

More information

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Quality Assurance Plan v04.02 Prepared by: Approved by: QUALITY ASSURANCE PLAN APPROVALS QA/QC Program

More information

Fixed Scope Offering for Oracle Fusion Procurement. Slide 1

Fixed Scope Offering for Oracle Fusion Procurement. Slide 1 Fixed Scope Offering for Oracle Fusion Procurement Slide 1 Today s Business Challenges Adopt leading Global SCM practices & strategies across the entire enterprise value chain to move into the future.

More information

Invitation to Negotiate

Invitation to Negotiate Invitation to Negotiate Programming, Design, and Consulting Services Lisa Daws 4/3/2012 CLERKS OF COURT OPERATIONS CORPORATION Table of Contents Agency Background... 3 Statement of Purpose... 3 Scope of

More information

SELECTION CRITERIA AND PROCESS

SELECTION CRITERIA AND PROCESS Page 12 of 49 / ATTACHEMENT 1 - ADDENDUM 3: replace pages 12-16 with the following: Super User Training Admin Training Representatives from the IT, Legal, Finance, Neighborhood Services, and Police Departments

More information

IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM)

IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM) IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM) DK_INTC-8838-00 11-2011 Page 1 of 17 Table of Contents 1.Scope of Services...3 2.Definitions...3

More information

Agenda Item. Issue under Consideration: Contract #12-037, Technology Assessment Master Agreement

Agenda Item. Issue under Consideration: Contract #12-037, Technology Assessment Master Agreement Agenda Item Item: 6a Issue under Consideration: Contract #12-037, Technology Assessment Master Agreement Current Status: The County has an existing agreement with VC3, Incorporated to provide management

More information

REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE RFP INFORMATION

REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE RFP INFORMATION REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE NEW YORK ehealth COLLABORATIVE CONTACT NAME EMAIL ADDRESS SUBMISSION DEADLINE RFP INFORMATION NYeC RFP rfpcontact@nyehealth.org September

More information

V3 Pension Administration System Solution. January 2014 Monthly Board Update

V3 Pension Administration System Solution. January 2014 Monthly Board Update V3 Pension Administration System Solution January 2014 Monthly Board Update Agenda V3 Monthly Update Page Project Overall Status Update 3 V3 PASS Project Status Gantt Chart 4 PASS V3 Project Milestones

More information

Information Services Group Public Sector

Information Services Group Public Sector IV&V Assessment Report - Deliverable IVV2.2 Presented by: Information Services Group Public Sector December 12, 2018 2018 Information Services Group, Inc. All Rights Reserved Copyright 2018, Information

More information

PMI LUNCH AND LEARN OCTOBER 29, 2018

PMI LUNCH AND LEARN OCTOBER 29, 2018 PMI LUNCH AND LEARN OCTOBER 29, 2018 Agenda Project Update Procurement Activities Lessons Learned PMI Lunch and Learn 10/29/2018 PMI Lunch and Learn 10/29/2018 Florida PALM Project Update Establishment

More information

Appendix 1 LifeCycle Packaged Implementations. RightNow LifeCycle Packaged Implementation Overview. Project Critical Success Factors.

Appendix 1 LifeCycle Packaged Implementations. RightNow LifeCycle Packaged Implementation Overview. Project Critical Success Factors. RightNow LifeCycle Packaged Implementation Overview The following pages are the standard statement of work for RightNow s packaged LifeCycle Implementations. Since RightNow s project management methodology

More information

PURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A"

PURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY A PURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A" 1. SOFTWARE QUALITY PROGRAM. This attachment establishes the software quality requirements

More information

Texas Department of Human Services Long Term Care Regulatory, page 1. Nomination Form

Texas Department of Human Services Long Term Care Regulatory, page 1. Nomination Form Texas Department of Human Services Long Term Care Regulatory, page 1 Nomination Form Title of Nomination: Long Term Care Regulatory Web Accessible Facility EnRollment (WAFER) Project/System Manager: Raj

More information

Report No. AHCA A February Agency Agreements EXECUTIVE SUMMARY

Report No. AHCA A February Agency Agreements EXECUTIVE SUMMARY Report No. AHCA-1617-04-A February 2018 Office of Inspector General Internal Audit Agency Agreements EXECUTIVE SUMMARY As part of the Agency for Health Care Administration (Agency) fiscal year 2016-2017

More information

Project Management Professionals

Project Management Professionals A COLLECTION OF INTERVIEW QUESTIONS FOR Project Management Professionals When interviewing a Project Manager, it s important to set up the discussion for the first couple of minutes in an open dialogue.

More information

County of Sutter. Management Letter. June 30, 2012

County of Sutter. Management Letter. June 30, 2012 County of Sutter Management Letter June 30, 2012 County of Sutter Index Page Management Letter 3 Management Report Schedule of Current Year s 4 Schedule of Prior Auditor Comments 9 Prior Year Information

More information

WRITTEN ANSWERS TO QUESTIONS RECEIVED

WRITTEN ANSWERS TO QUESTIONS RECEIVED WRITTEN ANSWERS TO QUESTIONS RECEIVED All written questions are reproduced in the same format as submitted by the Respondent. IT denotes technical question and response DP denotes purchasing or admin question

More information

IBM Clinical Development

IBM Clinical Development Service Description IBM Clinical Development This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized users and recipients of the

More information

Executive Steering Committee Meeting. Department of Revenue Building 1, Room 1220/1221 September 14, 2016

Executive Steering Committee Meeting. Department of Revenue Building 1, Room 1220/1221 September 14, 2016 Executive Steering Committee Meeting Department of Revenue Building 1, Room 1220/1221 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of August 2016 Meeting Minutes Facilitator:

More information

INSTRUCTIONS Column A: Column B: Mandatory Preferred Optional Information Column C: Column D: Column F:

INSTRUCTIONS Column A: Column B: Mandatory Preferred Optional Information Column C: Column D: Column F: INSTRUCTIONS One vendor may propose one or more potential solution packages (product configurations) to meet the Department's requirements. Please complete a separate workbook for each proposed solution

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

SECTION 1 BUSINESS OPERATIONS...

SECTION 1 BUSINESS OPERATIONS... Contents SECTION 1 BUSINESS OPERATIONS... 2 1.1 SUNCOM CLIENTS... 2 1.1.1 Intrinsic Clients... 2 1.1.2 Required Clients... 2 1.1.3 Discretionary Clients... 2 1.1.3.1 Committed Discretionary Clients...

More information

IBM Emptoris Contract Management on Cloud

IBM Emptoris Contract Management on Cloud Service Description IBM Emptoris Contract Management on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the company and its authorized users and recipients

More information

IBM Emptoris Strategic Supply Management on Cloud

IBM Emptoris Strategic Supply Management on Cloud Service Description IBM Emptoris Strategic Supply Management on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the company and its authorized users and

More information

Activation, Transition & Close Out Step 7. July 13, 2012

Activation, Transition & Close Out Step 7. July 13, 2012 Activation, Transition & Close Out Step 7 July 13, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project April 2016 Date: 5/11/2016 Version 1.0 Table of Contents Executive Summary...

More information

Administrative Services About Administrative Services

Administrative Services About Administrative Services About The Department oversees and directs the operations of Finance, Human Resources, Sales Tax, Purchasing, Information Technology, Risk Management, Budget, the Public Information Office, Front Desk Reception,

More information

4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Approach

4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Approach 4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Our approach to providing ongoing Operations and Maintenance support for ACCESS Florida focuses on stability of the existing system, retaining

More information

Contract Management Handbook. Texas Government Code, Title 10, Subtitle F, Chapter Statewide Contract Management

Contract Management Handbook. Texas Government Code, Title 10, Subtitle F, Chapter Statewide Contract Management Texas Medical Board Contract Management Handbook Purpose: Policy: Authority: To provide the agency with a consistent policy that delineates staff roles and responsibilities for contract management. Pursuant

More information

BPO Service Level Agreement

BPO Service Level Agreement BPO Service Level Agreement Versión / Version: 2.3 Código Documento / Document Code: AVSP-BPO-OD-001-SLA Fecha Emisión / Distribution Date: November 30, 2014 Elaboró / Created by: Revisó / Reviewed by:

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project February 2016 Date: 3/10/2016 Version 1.0 Table of Contents Executive

More information

Ambulance Contract Billing Report October 12, 2016 KEY CONTROL FINDING RECOMMENDATION STATUS The City should:

Ambulance Contract Billing Report October 12, 2016 KEY CONTROL FINDING RECOMMENDATION STATUS The City should: Ambulance Contract Billing Report October 12, 2016 The City should: General Recordkeeping Inconsistencies exist in the basic recordkeeping related to ambulance calls. Continue with the implementation of

More information

GUIDE TO THE CHANGES IN PMP simpl learn i

GUIDE TO THE CHANGES IN PMP simpl learn i GUIDE TO THE CHANGES IN PMP- 2015 simpl learn i Table of contents Introduction the purpose of this manual 1 New Tasks: Initiating 3 New Tasks: Planning 4 New Tasks: Executing 6 New Tasks: Monitoring and

More information

DEPARTMENT OF REVENUE BUILDING 1 AUGUST 22, 2018

DEPARTMENT OF REVENUE BUILDING 1 AUGUST 22, 2018 DEPARTMENT OF REVENUE BUILDING 1 AUGUST 22, 2018 3 FACILITATOR: RYAN WEST 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: MELISSA TURNER, PAUL LAVERY Scope and Schedule - Prologue 6 Scope and Schedule Contract

More information

IBM Operational Decision Manager on Cloud

IBM Operational Decision Manager on Cloud Service Description IBM Operational Decision Manager on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized users and

More information

Project Manager s Roadmap We re all smarter together

Project Manager s Roadmap We re all smarter together Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References

More information

Dated: April 30, 2014

Dated: April 30, 2014 ADDENDUM #2 for NEW REQUESTS FOR PROPOSALS AIRPORT CITYWORKS IMPLEMENTATION at CHARLOTTE DOUGLAS INTERNATIONAL AIRPORT for the CITY OF CHARLOTTE, NORTH CAROLINA Dated: April 30, 2014 1. Are there additional

More information

Request for Quote (RFQ) Information Technology Department Review

Request for Quote (RFQ) Information Technology Department Review Request for Quote (RFQ) Information Technology Department Review The Clerks of Court Operations Corporation ( CCOC ) is a legislatively created corporate entity, created under Section 28.35, Florida Statutes.

More information

DEPARTMENT OF CHILDREN AND FAMILIES. REQUEST FOR INFORMATION Contract Management System

DEPARTMENT OF CHILDREN AND FAMILIES. REQUEST FOR INFORMATION Contract Management System DEPARTMENT OF CHILDREN AND FAMILIES REQUEST FOR INFORMATION Contract Management System This is a Request for Information pursuant to Rule 60A-1.042, F.A.C., for planning purposes only. This is not a solicitation

More information

Vendor Cloud Platinum Package: Included Capabilities

Vendor Cloud Platinum Package: Included Capabilities Solution Overview Third-Party Risk Management Vendor Cloud Platinum Package: Included Capabilities The Vendor Cloud Platinum package provides the highest level of risk management capabilities, offering

More information

Owner's Representative Scope Matrix - D/B Rev 10/28/2013

Owner's Representative Scope Matrix - D/B Rev 10/28/2013 Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope

More information

Question ID RFP Section RFP Page # Paragraph Question AHIM Response Questions and Answers Released October 10, 2016 Regarding Additional Guidance

Question ID RFP Section RFP Page # Paragraph Question AHIM Response Questions and Answers Released October 10, 2016 Regarding Additional Guidance Question ID RFP Section RFP Page # Paragraph Question AHIM Response Questions and Answers Released Regarding Additional Guidance 1 Additional Guidance Addendum 2 Additional Guidance Addendum 3 Additional

More information

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST)

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST) REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION Submittal Date: April 22, 2016 @ 11:00 AM (PST) Issued by: Southern California Coastal Water Research Project 3535 Harbor Blvd., Suite 110

More information

Connoisseur Solutions Project Procurement Management

Connoisseur Solutions Project Procurement Management Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes

More information

RFP NO A CONTRACT FOR THE PROCUREMENT AND INSTALLATION OF AN ENTERPRISE RESOURCE PLANNING SYSTEM PART V. EVALUATION CRITERIA AND PROCESS

RFP NO A CONTRACT FOR THE PROCUREMENT AND INSTALLATION OF AN ENTERPRISE RESOURCE PLANNING SYSTEM PART V. EVALUATION CRITERIA AND PROCESS 1.0 OVERALL PROPOSER EVALUATION CRITERIA 1.1 OVERALL PROPOSER EVALUATION AND CRITERIA The evaluation committee will select a best solution based on a weighted scoring system. The following table presents

More information

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000 This summary identifies the additional TL 9000 Release 4.0 requirements beyond those stated in ISO 9001:2000. See the TL 9000 R4.0 Handbook for the actual TL 9000 R4.0 requirements. ISO 9001:2000 section

More information

Security Monitoring Service Description

Security Monitoring Service Description Security Monitoring Service Description Contents Section 1: UnderdefenseSOC Security Monitoring Service Overview 3 Section 2: Key Components of the Service 4 Section 3: Onboarding Process 5 Section 4:

More information

1. Introduction. 2. Scope of Work and Timeframes

1. Introduction. 2. Scope of Work and Timeframes 1. Introduction This Statement of Work ("SOW") is incorporated into the Master Subscription Agreement/Quote (the "Agreement") between ("Wrike") and Licensee dated Effective Date of the Agreement. If any

More information

IBM Emptoris Supplier Lifecycle Management on Cloud

IBM Emptoris Supplier Lifecycle Management on Cloud Service Description IBM Emptoris Supplier Lifecycle Management on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized

More information

Sample Delivery Schedule

Sample Delivery Schedule Sample Delivery Schedule The following model delivery schedule will provide the list of expected s with their proposed due date, and an illustration of a possible financial consequence. The milestones

More information

Bid No A - Contract for the Procurement and Installation of an Enterprise Resource Planning System for the City of East Point

Bid No A - Contract for the Procurement and Installation of an Enterprise Resource Planning System for the City of East Point Department of Finance Lolita Grant, Director 2777 East Point Street East Point, Georgia 30344 MAYOR Jannquell Peters COUNCIL MEMBERS Ward A Alexander Gothard Sharon D. Shropshire DATE: June 2, 2017 TO:

More information

Statement of Work 1 Decade Software Company, LLC

Statement of Work 1 Decade Software Company, LLC Appendix C- Statement off Work Reference Agreem ment Number: 2011-670 Revision 3. 0 09/20/2011 Contents Contents... 1 1. Project Background... 1 2. Project Deliverables... 1 3. System Deployment... 2 4.

More information

DEPARTMENT OF ELDER AFFAIRS (DOEA) PROJECT CHARTER. ENTERPRISE CLIENT INFORMATION AND REGISTRATION TRACKING SYSTEM (ecirts) PROJECT FOR

DEPARTMENT OF ELDER AFFAIRS (DOEA) PROJECT CHARTER. ENTERPRISE CLIENT INFORMATION AND REGISTRATION TRACKING SYSTEM (ecirts) PROJECT FOR JEFFREY S. BRAGG, SECRETARY DEPARTMENT OF ELDER AFFAIRS (DOEA) PROJECT CHARTER FOR ENTERPRISE CLIENT INFORMATION AND REGISTRATION TRACKING SYSTEM (ecirts) PROJECT JULY 17, 2018 20180622_CIRTS_Project_Charter_v1.05

More information