1 Internal Audit Follow-Up Report Toll Operations Contract Management TxDOT Internal Audit Division

2 Objective Assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously communicated in the Toll Operations Contract Management audit issued August Summary Results Testing consisted of an evaluation of 14 MAPs to determine if corrective actions were implemented as agreed. MAP Status Comments 14 Closed Corrective actions have been completed. Toll Operations Division has developed corrective actions to demonstrate completion of the Management Action Plans. However, issues relating to the contract, including certain performance required by the vendor, had not been fully resolved by the date of this engagement. Scope The scope included a review of submitted documentation regarding Toll Operations Division s (TOD) contract management and oversight activities and the implementation of a contractual performance measure process. The engagement was performed by Alberto Calderon and Lindsay Bibeau (Engagement Lead). The engagement was conducted during the period from May 23, 2016 to July 15, Methodology The methodology used to complete the objective of the engagement work included: Reviewed prior audit report findings and Management Action Plans (MAPs) Conducted interviews with key personnel in Toll Operations Division (TOD), such as, the division director, the project manager, and quality assurance/quality control personnel to understand the actions taken to mitigate the risks previously identified Examined Project Management Professional (PMP) certifications for both TOD and those employees from a third-party consultant provider supporting TOD operations Reviewed the Project Management Institute Project Management Body of Knowledge (PMBOK) guidelines that were used to help ensure TOD has implemented Standard Operating Procedures (SOPs) for the TOD projects in accordance with these procedures Reviewed listing and content of newly created SOPs, including Project Management Office (PMO) and Key Performance Indicators (KPI) that will assist TOD in monitoring and reviewing operational activities and KPIs Reviewed monitoring reports, templates, and project matrices detailing planned activities used to verify TOD is tracking projects and receiving accurate KPI reports used for performance measurements Reviewed TOD s Strategic Plan, organizational chart, and other reports from an additional third party consultant to document TOD s efforts for process improvements August

3 Background This report is prepared for the Texas Transportation Commission and for the Administration and Management of TxDOT. The report presents the results of the Toll Operations Contract Management Follow-Up engagement which was conducted as part of the Fiscal Year 2016 Audit Plan. In June 2013, TxDOT entered into a contract with a vendor to modernize the customer service center system. This modernization included converting existing toll accounts to a new system, merging accounts to simplify account maintenance for customer, implementing a new interactive voice response system, and updating other customer service capabilities to improve the customers experience. The contract included milestones, which were to be completed by the vendor to enable transition from the previous toll system. The contract further established key performance indicators which were to be used by TOD to help monitor vendor performance as established by the contract. We conducted this follow-up engagement in accordance with Generally Accepted Government Auditing Standards and in conformance with the International Standards for the Professional Practice of Internal Auditing. Those standards require that we plan and perform the engagement to obtain sufficient, appropriate evidence to provide a reasonable basis for our conclusions based on our engagement objective. Recommendations to mitigate risks identified were previously provided to management during the original engagement to assist in the formulation of the management action plans referenced in this report. The Internal Audit Division uses the Committee of Sponsoring Organizations of the Treadway Commission (COSO) Internal Control Integrated Framework version August

4 Detailed MAP Follow-Up Status MAP Status: Closed Corrective actions have been completed. Original Audit Finding Number 1: Contract Management/Oversight Framework MAP Owner: Rick Nelson, Director, Toll Operations Division MAP 1.1: Project Management Processes TxDOT will implement Project Management Institute (PMI) PMBOK guideline usage by TxDOT, consultants, and vendor to ensure a well-designed process is implemented and becomes standard operating procedure for contract and project management. Original Completion Date: October 15, 2015 Actual Completion Date: May 19, 2016 MAP Owner: Roland Silva, Quality Assurance/Quality Control, Toll Operations Division MAP 1.3: Standard Operating Procedure Development Phase 2 TOD will continue its development of TOD staff SOPs which will address each TOD SME s specific oversight and monitoring activities of specific operations processes. Original Completion Date: November 15, 2015 Actual Completion Date: June 6, 2016 MAP Owner: Brian Smallwood, Director, Operational Excellence, Toll Operations Division MAP 1.4: Verification & Validation Processes TOD will expand its verification/validation activities to include process audits by TOD operational area SMEs which will be subject to review and audit by TOD QA/QC Team. Activities identified on MAP 1.2 monitoring SOPs will be audited periodically according to a TOD QC Audit Schedule and subject to regular spot checks. Results and any recommendations will be reported to the Director of Operational Excellence and Toll Operations Director when needed and/or on a quarterly basis. In the interim, TOD will continue its monitoring of identified key processes and coordinate appropriate actions with vendor through existing regularly scheduled Issues Review, Release Planning and QA/QC meetings. Original Completion Date: October 15, 2015 Actual Completion Date: June 30, 2016 August

5 MAP Owner: Rick Nelson, Director, Toll Operations Division MAP 1.5: Independent 3 rd party review of operations TOD will work with an independent consultant to provide an independent information technology assessment of contract management and review of operations to provide specific areas of focus to improve both. Consultant will also provide an independent validation of vendor contract and performance by implementing tools using Tableau and Crystal Reports. These tools will be owned and used by TOD to monitor contract performance after the initial assessment. Original Completion Date: December 15, 2015 MAP Owner: Rick Nelson, Director, Toll Operations Division MAP 1.6: Additional PMO process Third party PMP certified consultant implementation of a project matrix detailing approved projects, project owners, resources assigned, percentage of employees time assigned to project, project approved schedule by budget assigned and expended by month. This matrix will include all planned and approved activities for the next 18 months and project and/or contract managers will report monthly at TOD staff meetings on these projects. Original Completion Date: October 15, 2015 Actual Completion Date: March 15, 2016 MAP Owner: Linda Sexton, Deputy Director, Toll Operations Division MAP 1.7: Atkins PMO Certified Managers TOD will direct their third party consultant in writing to provide the PMP certified project manager(s) required by contract and to adhere to PMBOK guidelines. Original Completion Date: September 15, 2015 MAP Owners: Rick Nelson, Director, Toll Operations Division Linda Sexton, Deputy Director, Toll Operations Division MAP 1.8: TOD Organization TOD will evaluate its present organizational structure and provided a recommendation to the TXDOT CFO of any needed changes required to address unsatisfactory ratings noted in this Internal Audit Report. Original Completion Date: November 15, 2015 August

6 MAP Owners: Rick Nelson, Director, Toll Operations Division Linda Sexton, Deputy Director, Toll Operations Division MAP 1.9: TxDOT PMO Certified Managers TOD will require all identified TOD project managers to obtain PMP certification and use PMBOK guidelines in managing projects. Phase 1 certification of three TxDOT project managers will be completed by December 15, Phase 2 will provide a plan to certify all remaining TxDOT TOD project managers. Original Completion Date: February 15, 2016 Actual Completion Date: May 05, 2016 MAP Owners: Rick Nelson, Director, Toll Operations Division Teresa Lemons, Funds Management Section Director, Toll Operations Division MAP 1.10: Procure Project Management Software Develop action plan to procure and implement third party software for Project Management designed around the PMBOK guidelines to provide a dashboard/score card using both qualitative and quantitative information on all approved tasks and projects. Said software shall provide a transparent dashboard/score card and shall be accessible 24x7 to senior management of TOD and any other users approved by TxDOT CFO. Original Completion Date: January 15, 2016 Actual Completion Date: May 15, 2016 MAP Owner: Teresa Lemons, Funds Management Section Director, Toll Operations Division MAP 1.11: TOD Budget Officer Recruit and hire an individual who is a Certified Public Accountant to fill the Budget Officer position to provide Generally Accepted Accounting Principles compliance guidance to TOD. Original Completion Date: September 15, 2015 August

7 Original Audit Finding Number 2: Performance Measure Achievement MAP Owner: Brian Smallwood, Director, Operational Excellence, Toll Operations Division MAP 2.1: Complete Implementation Milestones TOD will continue to coordinate with the vendor to identify and prioritize the resolution of incomplete implementation milestones. o TOD is meeting with the vendor twice weekly to identify issues impeding implementation and to prioritize the evaluating of solution releases through Issues and Release Planning meetings. Original Completion Date: October 15, 2015 MAP Owner: Brian Smallwood, Director, Operational Excellence, Toll Operations Division MAP 2.2: Complete Key Performance Indicator (KPI) Reports TOD will continue to evaluate KPI reports available and drive this report review effort, including validation and approval of vendor performance reporting. TOD will deliver a formal report Validation and Release process document to the vendor to facilitate the validation of the KPI reports. TOD currently meets with the vendor s Technical Reporting team daily to resolve KPI report issues and prioritize their report fixes or enhancement necessary for accurate and complete KPI reporting. A meeting will also be scheduled targeted at gaining a more comprehensive understanding of Vector 4G data and database relationships to facilitate report and data validation. Original Completion Date: November 15, 2015 MAP Owners: Rick Nelson, Director, Toll Operations Division Linda Sexton, Deputy Director, Toll Operations Division MAP 2.4: System Monitoring Improvements TOD will implement third party software to automate lane audits and monitor system performance. Original Completion Date: December 15, 2015 August

8 MAP Owners: Linda Sexton, Deputy Director, Toll Operations Division Brian Smallwood, Director, Operational Excellence, Toll Operations Division MAP 2.5: Interim Performance Reporting TOD will calculate performance measure achievement by using statistics provided by the vendor and independently evaluate the data to assess damages. This will be done until such time as required reports are approved by TxDOT through Operational Observation Period and available for use. Original Completion Date: November 15, 2015 Actual Completion Date: May 15, 2016 Closing Comments The results of this MAP Follow-Up engagement were discussed with Toll Operations Division on August 9, The Internal Audit team appreciates the cooperation and assistance received from the Toll Operations Division during this engagement. August

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Toll Operations Division Customer Service Operations TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services Contract and Work Authorizations TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk

More information

Internal Audit Report

Internal Audit Report Internal Audit Report IT Service Level Contract Management/Billing TxDOT Office of Internal Audit Objective To assess TxDOT s process of review and approval for vendor service level achievement as a method

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services Contract and Work Authorizations TxDOT Internal Audit Division Objective Assess the status of corrective actions for high-risk

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Construction Inspection Program TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Objective To assess the status of corrective actions for

More information

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Internal Audit Report Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Objective To evaluate the effectiveness and efficiency of the PEPS

More information

Internal Audit Report. Toll Operations: FHWA Reporting TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations: FHWA Reporting TxDOT Office of Internal Audit Internal Audit Report Toll Operations: FHWA Reporting TxDOT Office of Internal Audit Objective To determine whether Toll Operations Division (TOD) is providing federally required reporting to the Federal

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Preventive Maintenance Equipment & Fleet TxDOT Internal Audit Division Objective To determine if there are adequate practices for ensuring the inspection, maintenance, and repair

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Fuel Consumption Oversight and Coordination TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs)

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Contract Risk Assessment and Management TxDOT Internal Audit Division Objective To determine if contracting practices ensure adequate risk assessment input, review, and management.

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Construction Inspection Program TxDOT Internal Audit Division Objective To determine if an adequate process exists to ensure sufficient coverage and qualifications to inspect construction

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Non-Capitalized (Controlled and Non-Controlled) Consumables Management TxDOT Internal Audit Division Objective To determine whether districts and divisions have an adequate process

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Purchasing Process Efficiency TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Public Transportation Grants Indirect and Direct Cost Monitoring TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Bulk Fuel Management and Reporting TxDOT Internal Audit Division Objective To assess the status of corrective actions for high risk Management Action Plans (MAPs) previously

More information

Quality Assurance / Quality Control Plan

Quality Assurance / Quality Control Plan Quality Assurance / Quality Control Plan Table of Contents MANAGEMENT APPROACH... 3 SUBCONTRACT MANAGEMENT... 3 QUALITY MANAGEMENT APPROACH... 3 METHODOLOGY... 4 CONCEPT OF OPERATIONS... 5 QUALITY MANAGEMENT

More information

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan WORK PLAN FL IT IV&V Work Plan PART THREE - WORK PLAN AND IV&V METHODOLOGY ID Task Name Duration 1 FL IT IV&V Project Work Plan 261 days 2 DDI / SI Contract Award 0 days 3 Project Initiation and Planning

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Contract Administration TxDOT Internal Audit Division Objective To assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated

More information

Internal Audit Report. CDA Monitoring Process TxDOT Audit Office

Internal Audit Report. CDA Monitoring Process TxDOT Audit Office Internal Audit Report CDA Monitoring Process TxDOT Audit Office Objective Evaluate the key monitoring responsibilities and oversight to ensure adequate coverage is provided; distribution of exception reporting/evaluations

More information

Project Management. Risk Management

Project Management. Risk Management Brandt s History of IV&V Success Using over 30 years of experience supporting local, state, and federal agencies, Brandt provides IV&V services using proven, strategic methodologies to ensure project success

More information

Internal Audit Report. Contract Administration: 601CT Contracts TxDOT Internal Audit Division

Internal Audit Report. Contract Administration: 601CT Contracts TxDOT Internal Audit Division Internal Audit Report Contract Administration: 601CT Contracts TxDOT Internal Audit Division Objective Review contract administration and governance of 601CT contracts for structural compliance with laws

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) 4.5 Perform Integrated Change Control How a person may percieve change: paideiagroup.com 4.5 Perform Integrated Change Control Consider what change is: Crossing unknown territory Departing

More information

Quality Management. Fundamentals of Project Management For the Acting PM. Jonathan Blake, PMP. NYS Forum Project Management Workgroup.

Quality Management. Fundamentals of Project Management For the Acting PM. Jonathan Blake, PMP. NYS Forum Project Management Workgroup. Fundamentals of Project Management For the Acting PM Presented by NYS Forum Project Management Workgroup Quality Management Jonathan Blake, PMP Project Management Workgroup What is Project Quality Management?

More information

Internal Audit Follow-Up Report. Compass TxDOT Office of Internal Audit

Internal Audit Follow-Up Report. Compass TxDOT Office of Internal Audit Internal Audit Follow-Up Report Compass TxDOT Office of Internal Audit Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated in the Compass

More information

Project Management Knowledge Areas SECTION III

Project Management Knowledge Areas SECTION III Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report General Controls Review - IT TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously communicated

More information

Program Management. a practical application. November 19 th, Project Management Symposium Breakout Session D

Program Management. a practical application. November 19 th, Project Management Symposium Breakout Session D 0 Program Management a practical application November 19 th, 2010 2010 Project Management Symposium Breakout Session D 1 Overview As projects become larger and more complex, the effective management of

More information

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION Project Procedures BASIS OF OPERATION 09/21/2012 PAGE 1 OF 13 1.0 PURPOSE The purpose of this procedure is to establish the basis of operations that ensures that Project activities, including engineering,

More information

PgMP Exam Prep Training - 4 Days

PgMP Exam Prep Training - 4 Days PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp

More information

Project Management Professionals

Project Management Professionals A COLLECTION OF INTERVIEW QUESTIONS FOR Project Management Professionals When interviewing a Project Manager, it s important to set up the discussion for the first couple of minutes in an open dialogue.

More information

Title: Project Director Location: Tallahassee, FL Clearance: none required

Title: Project Director Location: Tallahassee, FL Clearance: none required Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management

More information

Information Technology Independent Verification and Validation

Information Technology Independent Verification and Validation Florida Department of Management Services Information Technology Independent Verification and Validation RFP No. Work Plan and Methodology ; 2:30 PM EST 2150 River Plaza Drive Suite 380 Sacramento California

More information

Internal Controls. June-20-17

Internal Controls. June-20-17 Internal Controls June-20-17 Background The Audit Committee is responsible for ensuring the adequacy and effectiveness of HRM s systems of internal control in relation to financial controls and risk management

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Bulk Fuel Management and Reporting TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously

More information

Cancer Prevention and Research Institute of Texas

Cancer Prevention and Research Institute of Texas Report Date: C O N T E N T S Page Internal Audit Report Transmittal Letter To The Oversight Committee... 1 Background... 2 Follow-Up Objective and Scope... 2 Executive Summary... 3 Conclusion... 3 Detailed

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program 1 Charter Direct and Manage Work Monitor and Control Work Perform Integrated Change Control Close or Phase 2 Vinai Prakash, PMCHAMP.COM 1 Defines how the project is executed,

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project September 2016 Date: 10/12/2016 Version 1.0 Table of Contents Executive

More information

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set4.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are

More information

Internal Controls Over Financial Reporting (ICoFR) Overview and Practical Aspects

Internal Controls Over Financial Reporting (ICoFR) Overview and Practical Aspects Internal Controls Over Financial Reporting (ICoFR) Overview and Practical Aspects What is Internal Financial Control (IFC)? As per Section 134 of Companies Act, 2013 Internal financial controls (IFC) means

More information

Internal Audit Report. Vegetation Management: Non-Contracted Herbicide Operations TxDOT Office of Internal Audit

Internal Audit Report. Vegetation Management: Non-Contracted Herbicide Operations TxDOT Office of Internal Audit Internal Audit Report Vegetation Management: Non-Contracted Herbicide Operations TxDOT Office of Internal Audit Objective Evaluate the effectiveness of methods used for vegetation management as it relates

More information

PMP PMBOK 5 th Edition Course Agenda

PMP PMBOK 5 th Edition Course Agenda PMP PMBOK 5 th Edition Course Agenda 1. Introduction to PMP Course Certification What are PMI and PMP Application Requirements for the PMP Exam Guidelines to Fill Up the PMP Application About the PMP Exam

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Travel Information Center Safety TxDOT Internal Audit Division Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously

More information

Appendix A. Simplified Sample Entity-Level Control Matrices

Appendix A. Simplified Sample Entity-Level Control Matrices Control Strategies: A Mid to Small Business Guide By Julie Harrer Copyright 2008 Hamlet ing Corp. Appendix A Simplified Sample Entity-Level Control Matrices Control Environment Possible Controls Integrity

More information

IDENTIFY STAKEHOLDERS BEST PRACTICES 1. Identify Stakeholders Best Practices. Bill Carswell

IDENTIFY STAKEHOLDERS BEST PRACTICES 1. Identify Stakeholders Best Practices. Bill Carswell IDENTIFY STAKEHOLDERS BEST PRACTICES 1 Identify Stakeholders Best Practices Bill Carswell IDENTIFY STAKEHOLDERS BEST PRACTICES 2 Abstract Identifying stakeholders is an enabling activity, leading to development

More information

Project Management Training Brochure

Project Management Training Brochure Project Management Training Brochure We develop project management training sessions by integrating our 40 years of combined practitioner experience with the most current project management knowledgebase

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Rail Project Management TxDOT Internal Audit Division Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated

More information

Project Integration Management

Project Integration Management Project Integration Management Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the Project Management

More information

PMP in the Real World. Scott Bailey, MBA, PMP, SSGB

PMP in the Real World. Scott Bailey, MBA, PMP, SSGB PMP in the Real World Scott Bailey, MBA, PMP, SSGB PMP in the Real World Webinar purpose To understand the relevance of the PMI PMP certification and its influence on the success or failure of projects

More information

Bank Account Creation, Management, and Oversight at University of Wisconsin-Stevens Point. Office of Internal Audit

Bank Account Creation, Management, and Oversight at University of Wisconsin-Stevens Point. Office of Internal Audit Bank Account Creation, Management, and Oversight at University of Wisconsin-Stevens Point Office of Internal Audit Report Control #2018-34 February 28, 2018 TABLE OF CONTENTS OPINION... 1 OBJECTIVES, SCOPE,

More information

Yvette Soliz Rivers PMP, CQA, MBA. PROGRAM MANAGEMENT AND IV&V CONSULTANT

Yvette Soliz Rivers PMP, CQA, MBA. PROGRAM MANAGEMENT AND IV&V CONSULTANT Enlightening program performance. Yvette Soliz Rivers PMP, CQA, MBA PROGRAM MANAGEMENT AND IV&V CONSULTANT 703-498-1319 yrivers@luzent.com SUMMARY. Ms. Rivers is an accomplished management consultant recognized

More information

Joint Operations (JO) Contactor Health Environment and Safety Management (CHESM) Standardized Operational Excellence (OE) Process

Joint Operations (JO) Contactor Health Environment and Safety Management (CHESM) Standardized Operational Excellence (OE) Process Joint Operations (JO) Contactor Health Environment and Safety Management (CHESM) Standardized Operational Excellence (OE) Process Approved 23 May 2007 Reviewed 1 May 2010 Version 1.1 Version 11. Revised

More information

Internal Audit Follow-Up Report. General Controls - IT TxDOT Office of Internal Audit

Internal Audit Follow-Up Report. General Controls - IT TxDOT Office of Internal Audit Internal Audit Follow-Up Report TxDOT Office of Internal Audit Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated in General Controls

More information

Internal Audit Report. Unified Transportation Program TxDOT Office of Internal Audit

Internal Audit Report. Unified Transportation Program TxDOT Office of Internal Audit Internal Audit Report Unified Transportation Program TxDOT Office of Internal Audit Objective To determine if legislative changes to the Unified Transportation Program process have been implemented effectively

More information

Construction Project Management Training Curriculum Integration Map

Construction Project Management Training Curriculum Integration Map Construction Project Management Training Curriculum Integration Map Value of the Project Management is being recognized all over the world. Most businesses manage their business by successfully implementing

More information

Assessment of the Design Effectiveness of Entity Level Controls. Office of the Chief Audit Executive

Assessment of the Design Effectiveness of Entity Level Controls. Office of the Chief Audit Executive Assessment of the Design Effectiveness of Entity Level Controls Office of the Chief Audit Executive February 2017 Cette publication est également disponible en français. This publication is available in

More information

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Quality Assurance Plan v04.02 Prepared by: Approved by: QUALITY ASSURANCE PLAN APPROVALS QA/QC Program

More information

PRIVY COUNCIL OFFICE. Audit of PCO s Accounts Payable Function. Final Report

PRIVY COUNCIL OFFICE. Audit of PCO s Accounts Payable Function. Final Report [*] An asterisk appears where sensitive information has been removed in accordance with the Access to Information Act and Privacy Act. PRIVY COUNCIL OFFICE Audit and Evaluation Division Final Report January

More information

Monthly IV&V Assessment Report (December 1 31, 2015)

Monthly IV&V Assessment Report (December 1 31, 2015) Monthly IV&V Assessment Report (December 1 31, 2015) Department of Financial Services Date: 01/13/2016 Version 1.0 Table of Contents Department of Financial Services Executive Summary... 4 Project... 4

More information

Project Integration Management. For the PMP Exam using PMBOK Guide 5 th Edition

Project Integration Management. For the PMP Exam using PMBOK Guide 5 th Edition Project Integration Management For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. Contacts Name: Khaled El-Nakib, PMP

More information

CENTRAL FLORIDA EXPRESSWAY AUTHORITY

CENTRAL FLORIDA EXPRESSWAY AUTHORITY CENTRAL FLORIDA EXPRESSWAY AUTHORITY Prior Audit Recommendations Follow-Up August 31, 2017 Internal Audit, Risk, Business & Technology Consulting TABLE OF CONTENTS 3 Executive Summary 5 Status of Past

More information

Internal Audit Report. Post Implementation Review PeopleSoft Accounts Payable TxDOT Internal Audit Division

Internal Audit Report. Post Implementation Review PeopleSoft Accounts Payable TxDOT Internal Audit Division Internal Audit Report Post Implementation Review PeopleSoft Accounts Payable TxDOT Internal Audit Division Objective To determine if the Oracle PeopleSoft Accounts Payable system is providing effective

More information

Internal Audit Report. Post Implementation Review PeopleSoft Project Costing TxDOT Internal Audit Division

Internal Audit Report. Post Implementation Review PeopleSoft Project Costing TxDOT Internal Audit Division Internal Audit Report Post Implementation Review PeopleSoft Project Costing TxDOT Internal Audit Division Objective To determine if the implementation for project costing and the control design provides

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Salary Growth Plan TxDOT Internal Audit Division Objective To determine if districts and divisions (D/D) are complying with the annual Salary Growth Plan (SGP) objectives and targets.

More information

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015 Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: April June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Financial

More information

PMP PMBOK Guide Sixth Edition Training Course Agenda

PMP PMBOK Guide Sixth Edition Training Course Agenda PMP PMBOK Guide Sixth Edition Training Course Agenda 1. Introduction What are PMI and PMP Certification Application Requirements for the PMP Exam Guidelines to Complete the PMP Application About the PMP

More information

Internal Audit Report. Contract Administration - Closeout Phase TxDOT Internal Audit Division

Internal Audit Report. Contract Administration - Closeout Phase TxDOT Internal Audit Division Internal Audit Report Contract Administration - Closeout Phase TxDOT Internal Audit Division Objective To evaluate and verify the contract closeout process on selected construction and maintenance contracts

More information

RESPONSE TO THE. Procurement Advisory Panel Recommendations AUGUST (also known as the Procurement Improvement Action Plan)

RESPONSE TO THE. Procurement Advisory Panel Recommendations AUGUST (also known as the Procurement Improvement Action Plan) RESPONSE TO THE Procurement Advisory Panel Recommendations AUGUST 2016 (also known as the Procurement Improvement Action Plan) Foreword I would like to thank the Procurement Advisory Panel for their dedication

More information

General Government and Gainesville Regional Utilities Vendor Master File Audit

General Government and Gainesville Regional Utilities Vendor Master File Audit FINAL AUDIT REPORT A Report to the City Commission General Government and Gainesville Regional Utilities Vendor Master File Audit Mayor Lauren Poe Mayor Pro-Tem Adrian Hayes-Santos Commission Members David

More information

Project Management Advisory Board Deep Dive Study of Program Management

Project Management Advisory Board Deep Dive Study of Program Management Project Management Advisory Board Deep Dive Study of Program Management Purpose The purpose of this study is twofold: 1. Understand how Saint Louis companies are managing programs 2. Study the maturity

More information

A Model for CAS Self Assessment

A Model for CAS Self Assessment Introduction An effective Contractor Assurance System integrates contractor management, supports corporate parent governance and facilitates government oversight systems. The purpose of a CAS is threefold:

More information

ISC: UNRESTRICTED AC Attachment. Utility Billing Audit

ISC: UNRESTRICTED AC Attachment. Utility Billing Audit Utility Billing Audit September 5, 2017 THIS PAGE LEFT INTENTIONALLY BLANK ISC: UNRESTRICTED Table of Contents Executive Summary... 5 1.0 Background... 7 2.0 Audit Objectives, Scope and Approach... 8 2.1

More information

GUIDE TO THE CHANGES IN PMP simpl learn i

GUIDE TO THE CHANGES IN PMP simpl learn i GUIDE TO THE CHANGES IN PMP- 2015 simpl learn i Table of contents Introduction the purpose of this manual 1 New Tasks: Initiating 3 New Tasks: Planning 4 New Tasks: Executing 6 New Tasks: Monitoring and

More information

Internal Controls: Providing an Effective Control Environment. Why This Session Is Needed. Lesson Overview & Module Objectives

Internal Controls: Providing an Effective Control Environment. Why This Session Is Needed. Lesson Overview & Module Objectives Internal Controls: Providing an Effective Control Environment Internal Controls 1 Why This Session Is Needed Uniform Guidance has expanded the requirements and increased the focus on internal controls

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

PMP TRAINING COURSE CONTENT

PMP TRAINING COURSE CONTENT PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Enterprise Risk Management Plan FY Submitted: April 3, 2017

Enterprise Risk Management Plan FY Submitted: April 3, 2017 1 Enterprise Risk Management Plan FY 2018 Submitted: April 3, 2017 2 Enterprise Risk Management Plan, FY 2018 Introduction Enterprise Risk Management (ERM) at the Texas A&M Transportation Institute (TTI)

More information

Quality Management_200_Quality Product Review Procedure

Quality Management_200_Quality Product Review Procedure Quality Management_200_Quality Product Review Procedure Last Updated: 05/15/2017 Audience: CWDS Service Teams, PMO Frequency: As needed After reading this procedure, the audience will be able to understand

More information

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions PMP PMI Project Management Professional Processexam.com Exam Summary Syllabus Questions Table of Contents Keys to success in PMP Exam on PMI Project Management Professional... 2 PMI PMP Certification Details:...

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Revenue Accounting TxDOT Internal Audit Division Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated in

More information

Create Actionable Plans

Create Actionable Plans M2D2 Downtown DC Luncheon Series Create Actionable Plans Matthew J. Weaver, PMP, CSM, ITIL Project Weavers, LLC July 16, 2012 2011-2012, Project Weavers, LLC. All rights reserved. Support@ProjectWeavers.com

More information

Internal Audit Report. Rail Project Management TxDOT Office of Internal Audit

Internal Audit Report. Rail Project Management TxDOT Office of Internal Audit Internal Audit Report Rail Project Management TxDOT Office of Internal Audit Objective To evaluate the contract management and oversight of state wide rail projects and programs, specifically, Railroad

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Career Development Program TxDOT Internal Audit Division Objective To assess program maturity and what impacts are being made through TxDOT s career development program. Control Environment

More information

Project Management Body of Knowledge Chapter 3 Project Processes

Project Management Body of Knowledge Chapter 3 Project Processes Project Management Body of Knowledge Chapter 3 Project Processes PMP Exam Prep PMBOK Chapter 1 - Introduction Chapter 2 - Organizational Influences & Life Cycles Chapter 3 - Project Processes Chapter 3

More information

BRIAN WAWRYK PMP. PROJECT MANAGER

BRIAN WAWRYK PMP. PROJECT MANAGER 52 Duncan Norrie Drive Winnipeg, MB R3P 2K1 BRIAN WAWRYK PMP Brian.Wawryk@WawrykConsultingServices.com Residence: 204-261-5531 Cellular: 204-955-9694 Brian Wawryk is an experienced IT professional with

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project October 2017 Date: 11/13/2017 Version 1.0 Table of Contents Executive

More information

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures PROCEDURE Title: Information Technology (IT) Project Management and Governance Procedures Related Policy: FDJJ 1270 I. DEFINITIONS Agency for State Technology (AST) Rule Rules 74-1.001 through 74-1.009,

More information

ISO 14001:2015. EMS Manual.

ISO 14001:2015. EMS Manual. www.iso-9001-checklist.co.uk Insert your company s name or logo, and address. This EMS manual is the property of Your Company. It must not be reproduced in whole or in part or otherwise disclosed without

More information

Mecklenburg County Department of Internal Audit. Business Support Services Agency Computer and Equipment Disposal Audit Follow-Up Report 1575

Mecklenburg County Department of Internal Audit. Business Support Services Agency Computer and Equipment Disposal Audit Follow-Up Report 1575 Mecklenburg County Department of Internal Audit Business Support Services Agency Computer and Equipment Disposal Audit Follow-Up Report 1575 April 19, 2016 Internal Audit s Mission Internal Audit Contacts

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Post Implementation Review ERP - Inventory TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs)

More information

COUNTY OF SAN BERNARDINO Workforce Investment Board POLICY MANUAL POLICY STATEMENT: Process: Page 1 of 5

COUNTY OF SAN BERNARDINO Workforce Investment Board POLICY MANUAL POLICY STATEMENT: Process: Page 1 of 5 COUNTY OF SAN BERNARDINO Workforce Investment Board POLICY MANUAL SUBJECT Monitoring and Oversight of One Stop Delivery System No. 11 ISSUE 1 PAGE 1 of 5 By EFFECTIVE: 11/5/07 APPROVED Curt Hagman, Chairman

More information

Internal Audit. Audit of Procurement and Contracting

Internal Audit. Audit of Procurement and Contracting Internal Audit Audit of Procurement and Contracting June 2011 Table of Contents EXECUTIVE SUMMARY...5 1. INTRODUCTION...8 1.1 BACKGROUND...8 1.2 OBJECTIVES...9 1.3 SCOPE...9 1.4 METHODOLOGY AND APPROACH...9

More information

IDI Internal Control System

IDI Internal Control System Risk Assessment Monitoring Control Environment Information & Communication Control Activities IDI Internal Control System 2014 Contents Preface... 1 1. Introduction... 2 2. Context and Background... 2

More information

Program Management Procedure. Quality Management System

Program Management Procedure. Quality Management System LACCD Bond Program Program Management Procedure Quality Management System Procedure Number: PM 9.0 Effective Date: Total Pages: 10 Controlled Document No.: SharePoint Copy 1.0 Purpose Quality is an integral

More information

Cancer Prevention & Research Institute of Texas. IA # Internal Audit Report over Communication Report Date: April 30, 2018 Issued: May 25, 2018

Cancer Prevention & Research Institute of Texas. IA # Internal Audit Report over Communication Report Date: April 30, 2018 Issued: May 25, 2018 IA # 04-18 Internal Audit Report over Communication Report Date: Issued: May 25, 2018 C O N T E N T S Page Internal Audit Report Transmittal Letter To The Oversight Committee.... 1 Background... 2 Audit

More information

Audit Report. Audit of Contracting and Procurement Activities

Audit Report. Audit of Contracting and Procurement Activities Audit Report August 2012 Recommended for Approval to the Deputy Minister by the Departmental Audit Committee on October 12, 2012 Approved by the Deputy Minister on October 18, 2012 Table of Contents Table

More information

Quality Assurance Policy and Procedures

Quality Assurance Policy and Procedures 650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance

More information