1 SITE IMPROVEMENTS HILLARD BLOOM SHELLFISH COMPANY 210 Stratford Avenue Bridgeport, CT ADDENDUM No. 5 to BID No. PEB April 21, 2010 The attention of bidders submitting bids for the above project is called to the following Addendum to the Project Manual and Contract Drawings. The items set forth herein, whether of omission, addition or substitution, are to be included in and form a part of the Bid submitted. BID FORM The BID form is replaced by the attached revised BID FORM, dated April 20, TECHNICAL SPECIFICATION SECTION STEEL PIPE PILES (MONOPILES) Technical Specification Section Steel Pipe Piles (Monopiles), is replaced by the enclosed Technical Specification Section 02456A, revised April 20, TECHNICAL SPECIFICATION SECTION 02456A STEEL H-PILES Technical Specification Section 02456A Steel H-Piles, is replaced by the enclosed Technical Specification Section 02456A, revised April 20, Drawing No. WH-6 is amended as follows: NOTES REGARDING PILING DRAWING NO. WH-6 Note 2 is revised to read as follows: The epoxy coating shall extend into the underlying sediments. Given the uncertainty associated with pile length at any given location and the likely need to splice piles from transportable stock, Bidders should assume that excess coating will be necessary and supplemental field coating may be required to achieve the desired result. Bids should be calculated on the basis of a 30-foot coated length per pile, but the Contractor shall be responsible to achieve the desired result; that the epoxy coating shall extend into the underlying sediments. Note 3 is revised to read as follows: Drive to 60 ton capacity, see following notes. Bid on basis of 100 foot average pile length; payment shall be made on the basis of installed pile length. No additional payment shall be made for splicing. Addendum No. 5 April 21, 2010 Page 1 of 6
2 Drawing No. WH-9 is amended as follows: DRAWING NO. WH-9 On Detail 2 Typical Dolphin Elevation, the top elevation should read MLW ( NGVD). REVISED RESPONSE TO PLANHOLDER QUESTION From Addendum No. 3, issued April 14, 2010, Planholder Question 1: How long is the coating on the 48 dia. pipe piles? The initial response was that the upper 20 feet of each pile shall be coated. The response is revised to require that the coating shall extend from the top of the pile a minimum of 10 feet into the underlying sediment. The contractor may conduct probes in the proposed dolphin locations to determine the likely overall pile length based on the required minimum penetration into sandy sediments and submit probe findings to the Engineer for review. In the absence of such probes, and due to the impracticality of extending the coating after pile installation, bids shall be prepared on the basis that the FULL LENGTH of each pipe pile shall be coated prior to installation RESPONSES TO PLANHOLDER QUESTIONS 1. Addendum 1 includes a new specification for Steel H-Piles. 4.1 States no measurements will be made. Payment for Steel H-Piles will be deemed included in the lump sum price bid for the Wharf Contract. I assume that costs for Furnishing and Installing H-Piles should be included in Bid Item Number 21 Concrete Wharf. If my assumption is correct then what is the purpose of Bid Item 19? Should this price be included in the total Base Bid? 4.2 States that an adjustment in payment will be made for additional length of H-Piles. I assume this is for furnishing additional H-Pile material. 4.3 Please explain exactly what 4.3 is stating. I assume that the Unit Price for Bid Item 19 will be used to determine adds or deducts for the adjustment based on the final linear footage of H-Pile Driven. Can you explain what vis-a-vis the 20 units whose cost is to be included in the Lump Sum Bid means? Are my assumptions above correct? See the attached Specification Section 02456A for changes to the measurement and payment of H-Piles. These modifications supersede information on Drawing WH-6. In addition, see above for revisions to the Notes Regarding Piling on Drawing WH Bid Item 22. Steel Pipe Piles. Due to unknown final installed length, would it be appropriate to add a Bid Item for Furnish Pipe Piles? See the attached Specification Section for changes to the measurement and payment of Steel Pipe Piles. Addendum No. 5 April 21, 2010 Page 2 of 6
3 3. More time is required to complete this bid. Can the bid date be extended by 1 week? Per Addendum No. 4 issued April 16, 2010, the bid opening has been changed to May 6, 2010 at 2 p.m. 4. What type of attachment is required for the cover plates for the utility trench to the W8 beams? No attachment is necessary, provided some means of maintaining the proper positioning of the W8 beams within the trench is provided. This might be accomplished, for example, by providing raised tabs on the seat bars in the trench to locate the W8 beams. 5. In the revised H pile spec transmitted in addendum 1, Part 1.6 B (Project Conditions) Test Piles: Report on test Piles (and diver inspection of rip rap, is presented in Section Special Conditions. What is the diver inspection? Are we supposed to perform a dive inspection of the rip rap? No diver inspection was performed, and none is required. 6. Can a different type of half pipe be used over the tie rods? PVC, Steel, RCP? Any type of half-round cover may be used, provided that it is of a non-corroding material and is strong enough to support and transfer the soil load without bearing on the tie rods. 7. The sketch attached to addendum 3 is titled Attachment to Addendum No. 3 Questions 8&9 but seems to refer to questions 9&10, is this the case? That is correct. Sketch SK-1 refers to Questions 9 and 10 on Addendum No To what capacity are the pile load tests? 120 tons. 9. The invitation to bid indicates two sealed bids are to be delivered, Addendum No. 1 says three sealed bids are to be delivered and Question 12 in addendum 1 says two sealed bids. Which is correct? Per Addendum No. 4 issued April 16, 2010, one (1) original and two (2) copies of all bids and supporting documentation must be submitted. All materials shall be submitted in one (1) sealed envelope or package. Addendum No. 5 April 21, 2010 Page 3 of 6
4 10. Zone 5 North end of the concrete cap, is a pile located just off the edge of the cap? See drawing WH2, the bent center line stops. There is a pile at this location. However, the pile will be shifted off the north-south bent alignment to avoid the existing concrete bulkhead cap beam. Accordingly, length of the pile cap on that east-west bent alignment will be field adjusted as necessary. 11. What is the final count of production H piles? I have 70 but the bid form has LF for 72. Are there (2) extra piles? There are seventy (70) production piles. Base bids on a total installed length of 7,000 linear feet, per the revised Bid Form, attached. 12. Drawing WH6 detail 3 says to use existing ramp hinges but the ramp/gangway (same sheet) description includes hinges. Do we have new hinges fabricated? New hinges shall be required for the ramp/gangway. 13. Sheet WH9 What is the weld size for the channel attachments and top plates to the pipe piles? Will the weld need to go below MLW (underwater welding)? In order to install the piles it seems these must be field welds, are they? Welds shall be 5/16-inch size. Welds may be field or shop welds, and may be underwater if field-welded. 14. Is the revision 03/24/10 of WH9 the latest? Addendum 1 says the date should be 03/25/10. The correct revision date for sheet WH-9 is March 24, Addendum No.1 requires three copies of the bid documents. Question 12 of the same Addendum was answered as two. Please clarify how many copies of the bid documents are to be submitted. Please clarify if one original and copies are to be submitted or all originals. Please clarify if each set of bid documents is to be submitted in an individual envelope or all copies of the bid documents will be submitted in one envelope. Per Addendum No. 4 issued April 16, 2010, one (1) original and two (2) copies of all bids and supporting documentation must be submitted. All materials shall be submitted in one (1) sealed envelope or package. Addendum No. 5 April 21, 2010 Page 4 of 6
5 16. In addition, we request an additional week extension for the bid opening. We have received a number of requests from the Subcontractors we have solicited asking for additional time. And time for ourselves due to our previous and current bidding schedule, to receive competitive vendor pricing and to evaluate and offer a competitive bid on our part. Per Addendum No. 4 issued April 16, 2010, the bid opening has been changed to May 6, 2010 at 2 p.m. 17. On the plan WH9 the steel pipe, monotube, material is called out as A252 Grade 50; in the spec for the steel pipe the material is called out as A252 grade 2 which has a 35KSI yield strength. Which is correct? The steel pipe monopoles shall be Grade Plan sheet LP-1, the South end of the wall there is a note Repair Existing Bulkhead (APPROX 140 LF). What is the repair and is it still part of the work to be performed? See Addendum No. 1, response to Question No. 2: The nature of the bulkhead repairs is currently under discussion with the Connecticut Department of Environmental Protection. If a final decision is reached on the nature and extent of repairs prior to the bid date, details and specification will be issued in a future addendum. At this time, no repair work in the area indicated on sheet GD-1 is to be included in the bid. 19. Please provide more info. relating to the pipe trench grating. 1.) What is the thickness of the checkered plate. Steel fabricators do not wish to try to figure this out using design criteria of live loads and point loads. 2.) What is the bar size and spacing for the grating? 3.) Can you be more specific about the retractable lifting devices? What are they, how many, etc. 1. Bidders shall be responsible for detailing the checkered plate as indicated in the plans. 2. There are no gratings required. 3. Each cover plate shall have some means of being lifted; this may be a hole in the plate to accommodate a lifting hook or toggle, a ring-type fitting that rests flush with the plate surface when not in use, or some other device. 20. Is there a spec. available for the coal tar epoxy coating specified? Is a hot dip or painted galvanized coating acceptable instead? A galvanized coating is not acceptable. Provide coating per Specification Section Addendum No. 5 April 21, 2010 Page 5 of 6
6 21. Also, handrails are referenced on Sheet WH-6. Can you provide more details instead of design criteria? What is the post spacing? Is it a 2-line or 3-line or single line rail? Can you provide a detail for the face mounting? The handrail shall be a three-rail design, with uniform post spacing not to exceed six feet (6 ) center-to-center. The face mounting system shall consist of two clamps per post and shall permit periodic removal and reinstallation of the handrail. 22. Can we get the list of attendees who attended the second mandatory pre-bid meeting to other than those who attended the first one? The sign-up sheet for the second site visit is attached. 23. Did you work with any manufacturer in the design, etc. for the precast concrete planks, etc.? If so, can you please let me know who? No manufacturer was involved in the design of the precast concrete planks. Please see the response to Question 13, Addendum No. 1, for additional information. - END OF ADDENDUM NO. 5 - Addendum No. 5 April 21, 2010 Page 6 of 6
7 BID FORM Proposal of (hereinafter call BIDDER), organized and existing under the laws of the State of, doing business as *. (*Insert a corporation, a partnership, or an individual as applicable.) To the City of Bridgeport, 999 Broad Street, Bridgeport, CT (hereinafter called OWNER ). In compliance with your Advertisement for Bids, BIDDER hereby proposes to perform all WORK for the execution of Site Improvements Hillard Bloom Shellfish Company in strict accordance with the CONTRACT DOCUMENTS, within the time set forth therein, and at the price stated below. By submission of this BID, each BIDDER certifies, and in the case of a joint BID each party thereto certifies as to his own organization, that this BID has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this BID with any other BIDDER or with any competitor. BIDDER hereby agrees to perform WORK under this contract as indicated in Special Condition 305, Time for Commencement and Completion. BIDDER acknowledges receipt of the following ADDENDA: Addendum No. Date Bid No. PEB Revised April 20, 2010 Page 1 of 6
8 BIDDER agrees to perform all the work described in the CONTRACT DOCUMENTS for the following prices: BASE BID ITEMS Item No. Description Total Price (figures) 1. Site Clearing, the lump sum price of 2. Erosion and Sedimentation Control Measures, the lump sum price of 3. Site Grading, the lump sum price of 4. Segmental Retaining Wall, the lump sum price of 5. Storm Drainage, the lump sum price of 6. Sanitary Sewerage, the lump sum price of Bid No. PEB Revised April 20, 2010 Page 2 of 6
9 7. Fire Protection System, the lump sum price of 8. Bituminous Concrete Paving and Curbing, the lump sum price of 9. Concrete Sidewalk, 13 square yards at the price per square yard of, for a total price of 10. Concrete Driveway Apron, 40 square yards at the price per square yard of, for a total price of 11. Granite Curb, 30 linear feet at the price per linear foot of, for a total price of Bid No. PEB Revised April 20, 2010 Page 3 of 6
10 12. Pavement Marking and Signage, the lump sum price of 13. Fencing, Gates and Guide Rail, the lump sum price of 14. Landscaping, the lump sum price of 15. Site Lighting, the lump sum price of 16. Parapet Mounted Snow Fence For I-95 Bridge, the lump sum price of 17. Waterfront Water and Electrical Services, the lump sum price of 18. New Bulkhead Anchor System, the lump sum price of Bid No. PEB Revised April 20, 2010 Page 4 of 6
11 19. Steel H- Piles, 7,000 linear feet at the price per linear foot of, for a total price of 20. Drilling Through Obstructions for Pile Installation, 400 linear feet at the unit price per linear foot of, for a total price of 21. Concrete Wharf, the lump sum price of 22. Steel Pipe Piles (Monopiles), 4 each at the price per each of, for a total price of 23. Excavate, Dispose Off-Site and Backfill PCB-Impacted Soil, 100 tons at the unit price per ton of, for a total price of The total amount of the Base Bid, as computed by the undersigned Bidder, is (in words) Dollars and cents (and figures $ ). Bid No. PEB Revised April 20, 2010 Page 5 of 6
12 Item No. ADDITIVE ALTERNATE BID ITEMS Estimated Quantity Description Unit Price Total Price A Tons Excavate, Dispose Off-Site and Backfill PMC Exceedance Soil, the unit price per ton of Dollars and Cents A2. Lump Sum Excavation Dewatering, the lump sum price of Dollars and Cents Respectfully submitted: Signature Address Title Date License Number (if applicable) (SEAL if bid is a corporation) Attest Bid No. PEB Revised April 20, 2010 Page 6 of 6
13 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut SECTION STEEL PIPE PILES (MONOPILES) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. B. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. 1. ASTM A 252 Welded and Seamless Steel Pipe Piles (Grade 50). 1.2 SUMMARY A. Section includes steel pipe piles also called monopiles. Fill with sand, not concrete. B. Related Section: Section 09967, Coating of Steel Waterfront Structures, applies to the work under this Section. 1.3 UNIT PRICES A. The Contract Sum: Base the Contract Bid on installing piles, 80 feet long, measured from tip to cutoff, and on the number of piles indicated. B. Measurement: Using data obtained during pile driving, Engineer will calculate actual total length of piles installed. 1. Additional payment for pile lengths in excess of that indicated, and credit for pile lengths less than that indicated, will be calculated at the unit price stated in the Contract, based on net addition or deduction to total pile length 2. Unit prices to include labor, materials, tools equipment and incidentals for furnishing driving, cutting off, capping, and splicing piles and disposing of cutoffs. 3. Test: None. 4. No payment will be made for rejected piles, including piles driven out of tolerance, defective piles, or piles damaged during handling or driving. 1.4 SUBMITTALS A. Shop Drawings: For splices and shoes. Revised April 20, 2010 Steel Pipe Piles (Monopiles) Section Page 1 of 4
14 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut B. Material Certificates: For steel pipe. C. Pile-Driving Equipment: Include type, make, and rated energy per blow of hammer. D. Pile-Driving Records. 1.5 DELIVERY, STORAGE, AND HANDLING A. Deliver piles to Project site in such quantities and at such times to ensure continuity of installation. Handle and store piles at Project site to prevent physical damage. 1. Protect pile coatings and touch up damage to coatings before driving piles. 1.6 PROJECT CONDITIONS A. Assume that it will not be necessary to clear obstructions. B. Site Information: See Plans for available subsurface information. PART 2 - PRODUCTS 2.1 STEEL PIPE PILES A. Steel Pipe: ASTM A 252, Grade 50; seamless or welded. 2.2 CONCRETE AND DOWEL BARS: See SECTIONS and A. Not used. Fill void in pipe with clean sand. 2.3 PILE ACCESSORIES A. Outside Cutting Shoes: Manufacturer's standard, outside-flanged, open-ended cutting shoe, to provide full bearing of pipe pile tip. Fabricate from steel castings as follows: 1. Carbon-Steel Castings: ASTM A 27/A 27M. 2. High-Strength Steel Castings: ASTM A 148/A 148M. B. Splice Coupling: Manufacturer's standard splice coupling, rolled from ASTM A 36/A 36M, carbon-steel bar or cast from heat-treated carbon steel, ASTM A 27/A 27M, Grade 65-35, with interior stop. C. Wing-Type Fender: See Plans. Revised April 20, 2010 Steel Pipe Piles (Monopiles) Section Page 2 of 4
15 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut D. Cover Plate : See Plans. E. T-Bars: See Plans. 2.4 PAINT: See SECTION PART 3 - EXECUTION 3.1 DRIVING EQUIPMENT A. Pile Hammer: See notes on Plans. B. Hammer Cushions and Driving Caps: Between hammer and top of pile, provide hammer cushion and steel driving cap as recommended by hammer manufacturer for type of pile. C. Leads: Optional. 3.2 PILE TESTS A. None. 3.3 DRIVING PILES A. General: Continuously drive piles to penetration into SAND, indicated on the drawings. B. Driving Tolerances: See Notes on Plan. C. Clean out: Not required. D. Cutting Off: Cut off tops of driven piles square with pile axis and at elevations indicated. E. Pile-Driving Records: Maintain accurate driving records for each pile, compiled and attested to by a qualified professional engineer. Include the following data: 1. Project name and number. 2. Name of Contractor. 3. Pile designation. 4. Elevation of tips after driving. 5. Elevation of splices. 6. Type, make, model and rated energy of hammer. Revised April 20, 2010 Steel Pipe Piles (Monopiles) Section Page 3 of 4
16 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut 3.4 TOUCHUP PAINTING A. Clean field welds, splices, and abraded painted areas and field-apply paint as per SECTION DISPOSAL A. Remove cutoff sections of piles from site and legally dispose of them off Owner's property. PART 4 - METHOD OF MEASUREMENT 4.1 No measurement(s) will be made. Work shall be priced on the basis of piles 80 feet long each, of the appropriate wall thickness for each location as indicated on the plans, coated full length. NOTE: An adjustment may be due to the Owner based on the actual installed pile length and the residual value of uninstalled steel pipe. Revised April 20, 2010 Steel Pipe Piles (Monopiles) Section Page 4 of 4
17 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut SECTION 02456A STEEL H-PILES PART 1. GENERAL 1.1. RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Special Conditions, apply to this Section SUMMARY A. This Section includes driven foundation pilings. (H-piles) SUBMITTALS (Not Used) 1.4. QUALITY ASSURANCE (Not Used) 1.5. DELIVERY, STORAGE, AND HANDLING A. Deliver materials to Project site in such quantities and at such times to ensure continuity of pile driving operations and adherence to project schedule. B. Store piles in orderly group aboveground and blocked to prevent distortion of members and to minimize exposure to corrosion conditions PROJECT CONDITIONS A. Site Information: Data on indicated subsurface conditions are shown on the Plans. They are not intended as representations or warranties of continuity of such conditions. It is expressly understood that Owner will not be responsible for interpretations or conclusions drawn therefrom by Contractor. The data is made available for the convenience of the Contractor. B. Test Piles: Report on test piles is presented on sheet PT-1. It is expressly understood that the Owner will not be responsible for interpretations and conclusions drawn therefrom by Contractor. The data is made available for the convenience of the Contractor. C. Order Length (of Piles): Revised April 20, The order length (length in the leads) of piles will be as stated on the Plans. 2. The CONTRACTOR is invited to make such probings, or additional borings, as he may deem to be desirable, before ordering piles. The cost of such investigation shall be deemed to be included in the lump sum price bid for the Contract. Steel H-Piles Section 02456A Page 1 of 3
18 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut 3. Splicing is permitted. Splices shall develop the full strength of the pile (axial and bending). Field touch-up of damaged coating is required. Splicing of cut-off pieces into full-length sections is permitted. No limit on number of splices/pile. PART 2. PRODUCTS 2.1. STEEL H-SECTION PILES A. Steel: Hot-rolled, carbon steel structural shapes and plates, complying with ASTM A 572 or A 992 (50 Grade). B. Provide pile point reinforcement as indicated on Plans DRIVING EQUIPMENT A. General: Provide pile driving equipment of type generally used in standard pile driving practice, operated at manufacturer s specified rate, to develop required rated energy per blow. B. Hammer: Provide impact hammer of minimum 15,000 ft.-lb/blow rated energy. C. Vibratory Hammer: Similar to, or of greater energy than, was used to drive the test piles described above. PART 3. EXECUTION 3.1. DRIVING PILES A. General: Drive piles, at locations indicated, to the criteria noted on the Plans. B. Probing: It is intended that the initial driving shall be with a vibratory hammer; probing (multiple insertions) to get through the riprap. Once through the riprap, remove the vibratory hammer; let the pile sit ; and finish driving with the impact hammer to the specified resistance. Special note is made of the need for the piles to be located so that the head of the pile will fit into the socket in the pile cap. To this end, if the pile cannot be driven in a location such that this fit can be achieved, the successive probing shall batter the pile so that the head does fit, with available tolerances in casting of the pile cap and in slanting the pile cap (horizontal alignment) DRIVEN PILES (NOTE: Unless the Contractor can demonstrate that it is not needed, a template shall be provided). Revised April 20, 2010 Steel H-Piles Section 02456A Page 2 of 3
19 Envar Services Site Improvements Hillard Bloom Shellfish Company Bridgeport, Connecticut A. Driving Tolerances: See Notes on Plans B. Plumb and batter: See Notes on Plans C. Damaged or Misdriven Piles: Damaged piles and piles driven outside required driving tolerances will not be accepted. 1. Withdraw piles rejected after driving and replace with new piles. Do not abandon in place. D. Cutting-Off: Cut off tops of driven piles horizontal at elevations indicated. Dispose of excess materials off site TEST PILES/LOAD TESTS See notes on plans. PART 4. METHOD OF MEASUREMENT 4.1. Steel H-Piles will be measured per linear foot for piles driven complete and in place Drilling Through Obstructions for Pile Installation will be measured per linear foot for distance drilled. PART 5. BASIS OF PAYMENT 5.1 Steel H-Piles will be paid for at the Contract Unit Price per linear foot complete and in place. 5.2 Drilling Through Obstructions for Pile Installation will be paid for at the Contract Unit Price per linear foot complete. Revised April 20, 2010 Steel H-Piles Section 02456A Page 3 of 3
20
SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers.
SECTION 31 62 16 STEEL H PILES PART 1 - GENERAL 1.01 SCOPE OF WORK A. Section includes steel H piles embedded into drilled concrete piers. B. Furnish all labor, materials, equipment and incidentals required
More informationADDENDUM NUMBER 3 AUGUST 18, Jackson County Utility Authority Project No Pascagoula/Moss Point WWTP Escatawpa WWTP Repairs
ADDENDUM NUMBER 3 AUGUST 18, 2016 Jackson County Utility Authority Project No. 20150619124 Pascagoula/Moss Point WWTP Escatawpa WWTP Repairs FROM: BURK-KLEINPETER, INC. ENGINEERS, ARCHITECTS, PLANNERS,
More informationSECTION SHEET PILES. A. This section covers the contract item Sheet Piles. This work includes:
SECTION 02250 SHEET PILES PART 1 GENERAL 1.01 DESCRIPTION A. This section covers the contract item Sheet Piles. This work includes: 1. Furnishing, coating, and installing steel sheet piles for the working
More informationCITY OF TACOMA Department of Public Utilities Tacoma Power
CITY OF TACOMA Department of Public Utilities Tacoma Power ADDENDUM NO. 1 DATE: August 4, 2017 REVISIONS TO: Request for Bids Specification No. PG17-0130F TPU Eductor Waste Decant Facility NOTICE TO ALL
More informationSTANTEC ARCHITECTURE ARCHITECTS PLANNERS ENGINEERS 3001 Bee Caves Road Suite 300 Austin, TX April 29, 2016
ADDENDUM NUMBER ONE TO PLANS AND SPECIFICATIONS FOR ELGIN HIGH SCHOOL CTE CANOPY ADDITION ELGIN INDEPENDENT SCHOOL DISTRICT STANTEC ARCHITECTURE ARCHITECTS PLANNERS ENGINEERS 3001 Bee Caves Road Suite
More informationJANUARY 25, 2016 ADDENDUM NO. 3 FOR. ORD Baggage Service Road Retaining Wall Repair
JANUARY 25, 2016 ADDENDUM NO. 3 FOR ORD Baggage Service Road Retaining Wall Repair Specifications and Contract Documents Number: 132110 CDA Project Number: H6163.15-02 For which bids are scheduled to be
More informationSECTION STEEL PIPE PILING
SECTION 02460 STEEL PIPE PILING PART 1 GENERAL 1.1 SCOPE A. The work covered by this Section includes the furnishing of all materials, equipment, labor, and incidentals necessary for furnishing and installing
More informationAllegany College of Maryland Softball Field Murphy & Dittenhafer Project No Willowbrook Road, Cumberland, MD 21502
Addendum No. 2 June 12, 2018 Allegany College of Maryland Softball Field Murphy & Dittenhafer Project No. 17118 12401 Willowbrook Road, Cumberland, MD 21502 Abbreviations: ACM: Allegany College of Maryland,
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure
More informationBID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR
BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR Miscellaneous Concrete Repairs 2014 3600-3900 Blocks of Potomac Avenue and Town Hall, 2014 To: The Honorable Mayor and Town Council Town of Highland Park
More informationCITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017
CITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017 ADDENDUM NO. 1 (This Form Must Be Signed and Submitted With Bid Form) Addendum No. 1 addresses the following issues: QUESTIONS
More informationSECTION MINOR CONCRETE
SECTION 03300 - MINOR CONCRETE CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And Payment...
More informationIII. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE
III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the
More informationSECTION DRILLED CONCRETE PIERS AND SHAFTS
1 PART ONE - GENERAL 1.1 COORDINATION SECTION 02466 DRILLED CONCRETE PIERS AND SHAFTS A. The General, Supplementary, and Special Conditions of these specifications shall all be considered as a part of
More information1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.
PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationSECTION BORING AND/OR JACKING PIPE
02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe
More informationSection REINFORCING STEEL
Section 03210 PART 1 GENERAL 1.01 SUMMARY This Section includes the furnishing and subsequent placing of reinforcing steel, deformed and smooth, chairs, ties, splicing devices, and other reinforcing accessory
More informationFlorence County Government
Florence County Government Procurement Department April 29, 2016 ADDENDUM NO.1- CONSTRUCTION OF A BOARDWALK AND FISHING PIERS AT LAKE CITY PARK PROJECT (BID NO. 35-15/16) The following changes shall be
More information***************************************************************************************************************
02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************
More informationSECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.
PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Handrails and guardrails. 1.2 PERFORMANCE REQUIREMENTS A. General: In engineering railings to withstand structural loads indicated, determine
More informationNovember 29, CITY OF PLANT CITY Purchasing Division (813)
November 29, 2018 CITY OF PLANT CITY Purchasing Division (813) 659-4270 IFB 18-014UM-LG 12-inch Water Transmission Main-Franklin St., Hancock St. and Terrace Drive West ADDENDUM No. 3 *Bidders are required
More informationITEM 555 CHAIN LINK FENCING
ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing
More informationJUDD STREET LIFT STATION DEWATERING CONTRACT
JUDD STREET LIFT STATION DEWATERING CONTRACT MONTCALM COUNTY, MICHIGAN MAY 23, 2018 CITY OF GREENVILLE JOB NO. 401-590-975.281 PREPARED BY: CITY OF GREENVILLE ENGINEERING DEPARTMENT 411 S. LAFAYETTE GREENVILLE,
More informationSECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.
SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES
More informationSECTION STORM DRAINAGE
SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation
More informationSPECIAL SPECIFICATION 6664 Level (3) Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,
More informationHARMONY LELAND-CLAY REPLACEMENT ELEMENTARY SCHOOL
ADDENDUM NO. 4 November 26, 2018 Page 1 TO PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF HARMONY LELAND-CLAY REPLACEMENT ELEMENTARY SCHOOL FOR COBB COUNTY SCHOOL DISTRICT COBB COUNTY, GEORGIA DATED: JULY
More informationSECTION BID FORM. Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19
SECTION 00410 BID FORM Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19 THIS BID IS SUBMITTED TO: CITY OF LEBANON AUTHORITY 2311 Ridgeview Road Lebanon, Pennsylvania 17042 1.01
More information2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationSPECIAL SPECIFICATION 6658 Time Warner Communications System
2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable
More informationNOTICE TO BIDDERS. August 24, 2016 ADDENDUM NO. 1. Gosling Road Pedestrian, Bike & Related Improvements
NOTICE TO BIDDERS August 24, 2016 ADDENDUM NO. 1 Gosling Road Pedestrian, Bike & Related Improvements TO ALL FIRMS OF RECORD: This addendum forms a part of and modifies the bidding and contract documents
More informationSECTION BID FORM. Garfield Street Drainage Improvements
SECTION 00410 BID FORM Garfield Street Drainage Improvements ARTICLE 1 - BID RECIPIENT 1.01 This Bid is submitted to: City of Lindsborg, Kansas City Clerk s Office 101 S. Main Street Lindsborg, KS 67456
More informationSECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section
02540-1 of 10 SECTION 02540 STORM DRAIN REHABILITATION 02540.01 GENERAL A. Description Storm drain rehabilitation shall include, but not necessarily be limited to, pipe joint sealing, inlet and manhole
More informationA NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA
McKee and Associates Architecture and Interior Design Addendum No. FOUR Date: 09.24.18 Project: A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION
More informationADDENDUM NO. 1 FOR ROADWAY RECONSTRUCTION RFP # June 7, 2016
ADDENDUM NO. 1 FOR ROADWAY RECONSTRUCTION RFP #2017-01 NOTICE TO PROSPECTIVE BIDDERS June 7, 2016 Prospective bidders are hereby informed of the following corrections, additions, deletions, and/or modifications
More informationPURCHASING DEPARTMENT. Project # Addendum # # of pages Original Issue Date April 24, 2015
PURCHASING DEPARTMENT The bid listed below has had addenda issued. Documents are available over the Internet at http://www.norwalkct.org Adobe Acrobat reader is required to view this document. If you do
More informationSECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL
SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS
More informationITEM 432 TUNNEL CONSTRUCTION
AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.
More informationBID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS
BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS (Easement 6 & 11, 4200 block of Versailles Avenue and Belclaire Avenue and the 4300 block of Westway
More informationADDENDUM #1 AUGUST 25, INTERSECTION IMPROVEMENTS AT SR 434 AND TUSCORA DRIVE Bid # ITB-06/16/BF
ADDENDUM #1 AUGUST 25, 2016 INTERSECTION IMPROVEMENTS AT SR 434 AND TUSCORA DRIVE Bid # ITB-06/16/BF TO: ALL PLAN HOLDERS This Addendum No. 1 to the Contract Documents for City of Winter Springs project
More informationRIVER OAKS PUMP STATION RENOVATIONS/MODIFICATIONS, PHASE II for the LAFAYETTE CONSOLIDATED GOVERNMENT LAFAYETTE, LOUISIANA (DS&A #4628.
ADDENDUM TO CONTRACT DOCUMENTS AND SPECIFICATIONS RIVER OAKS PUMP STATION RENOVATIONS/MODIFICATIONS, PHASE II for the LAFAYETTE CONSOLIDATED GOVERNMENT LAFAYETTE, LOUISIANA (DS&A #4628.02) ADDENDUM NO.
More informationGeneral Water Bid Items Item No.
BID PROPOSAL PROPOSAL OF, a corporation organized and existing under the laws of the State of, a partnership consisting of, an individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationPUBLIC WORKS DEPARTMENT GENERAL NOTES
PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard
More informationADDENDUM NO. 3 February 28, 2017
ADDENDUM NO. 3 February 28, 2017 Project: From: To: Grimsley High School Auditorium Roof Replacement 801 Westover Terrace Greensboro, North Carolina 27408 Terracon Consultants, Inc. 7327-G West Friendly
More informationSTRUCTURAL STEEL FRAMING
SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical
More informationPROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67
August 28, 2018 PROJECT MANUAL for Phantom Canyon Tunnel Repair Project Location On Fremont County Road 67 7.5 miles North of Intersection US Highway 50 with FCR 67 Fremont County, Colorado OWNER: Fremont
More informationSECTION STRUCTURE MOUNT RAILING SYSTEM
SECTION 05520 STRUCTURE MOUNT RAILING SYSTEM Peak Fall Protection specializes in the design, engineering, fabrication, installation, and certification of fall protection safety systems. Our team of safety
More informationDivision IV Section 4100 Measurement and Payment PUBLIC WORKS DEPARTMENT
Division IV Section 4100 Measurement and Payment PUBLIC WORKS DEPARTMENT DIVISION IV CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 4100 MEASUREMENT AND PAYMENT 4100 SCOPE... 2 4101 Clearing and Grubbing...
More informationAnswer 1: The reference to CB 5 is incorrect. The correct reference should be CB 4. Question 2: Have any potential staging areas been identified?
ADDENDUM NO. 1 July 26, 2017 223837 RE: FROM: TO: CITY OF BARRE HMGP STORM DRAIN IMPROVEMENT PROJECTS DuBOIS & KING, INC. P.O. Box 339 Randolph, Vermont 05060 (802) 728-3376 Prospective Bidders This Addendum
More information1 Revised: 2019 Edition
STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with
More informationPRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B
SECTION 05 5213 - PIPE RAILINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationCITY OF FARGO SPECIFICATIONS REMOVALS
REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation
More informationAddendum # 1 Perdue Stadium Seating Bowl Improvements Date of Addendum: 09/07/16
Wicomico County Purchasing 125 N. Division St. Room B-3 Salisbury, MD 21801 Ph. 410-548-4805 Fax 410-334-3130 Email: purchasing@wicomicocounty.org Addendum # 1 Perdue Stadium Seating Bowl Improvements
More informationCITY OF FARGO SPECIFICATIONS REMOVALS
REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation
More informationCITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS
CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. Section Includes furnishing and installing chain-link fabric fence, gate, and appurtenances. 1.02
More informationCW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS
October 1990 CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Testing and Approval...1 5.3 Irrigation Pipe and Fittings...1
More informationFAX TRANSMITTAL. Two (2) NOTICE TO BIDDERS
FAX TRANSMITTAL ADDENDUM TO THE CONTRACT DOCUMENTS Page Number 1 No. of Pages 5 Addendum No. Two (2) Date Addendum Issued: September 28, 2017 Issuing Office Division of Parks and Outdoor Recreation 550
More informationSTATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014
STATE STRUCTION FUND DIRECTIVE 5-1 Issue date: October 2014 STRUCTURAL STEEL 1. General: It is the Fund's policy that the design of the structural steel is the prime responsibility of the project's Structural
More informationSPECIAL SPECIFICATION 6666 Charter Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,
More informationADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1
ADDENDUM No. 6 ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1 Due: June 9, 2016 at 2:00 p.m. (local time) The following changes, additions, and/or deletions
More informationREROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA
McKee and Associates Architecture and Interior Design Addendum No. FOUR Date: 07.17.17 Project: REROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA A4.1 GENERAL
More informationAddendum No. 1 Issue Date: March 29, 2016
Addendum No. 1 Issue Date: Project: Bonson and Short Street Reconstruction Contract: #1-16 Owner: City of Platteville, Wisconsin Engineer: Delta 3 Engineering, Inc. Daniel J. Dreessens, P.E. 875 South
More informationApril 1, CITY OF PORTSMOUTH Public Works Department. Bid # Annual Paving Project ADDENDUM NO. 1 NOTICE TO ALL BIDDERS
April 1, 2009 CITY OF PORTSMOUTH Public Works Department Bid #54-09 2009 Annual Paving Project ADDENDUM NO. 1 NOTICE TO ALL BIDDERS This Addendum forms part of the original document marked Bid #54-09 2009
More informationADDENDUM NO. 1 CITY OF SOUTH PORTLAND, MAINE WATERMAN DRIVE PARKING IMPROVEMENTS BID # August 21, 2014 PREPARED BY:
ADDENDUM NO. TO CITY OF SOUTH PORTLAND, MAINE WATERMAN DRIVE PARKING IMPROVEMENTS BID #04-5 August 2, 204 PREPARED BY: SEBAGO TECHNICS, INC. 75 John Roberts Road Suite A South Portland, ME 0406 3036 Addendum
More informationRevised BID FOR UPGRADES AND REPAIRS TO BULK DOCK 2 MARINE STRUCTURES PORT OF CORPUS CHRISTI AUTHORITY
Revised BID FOR UPGRADES AND REPAIRS TO BULK DOCK 2 MARINE STRUCTURES PORT OF CORPUS CHRISTI AUTHORITY (Company Name) Port Commissioners Port of Corpus Christi Authority P. O. Box 1541 Corpus Christi,
More information707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax
ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n
More informationADVERTISEMENT TO BID PARTIAL
ADVERTISEMENT TO BID The City of Elkton will receive separate, sealed Bids for their East Main Street Lift Station Generator Pad Addition Project until 10:30 a.m. local time, Tuesday, January 8, 2019 at
More informationAddendum 1. Valve & Valve Vault Replacement. Issued June 13, 2018
155 Corey Avenue St. Pete Beach, FL 33706-1839 www.stpetebeach.org Addendum 1 Valve & Valve Vault Replacement Issued June 13, 2018 Note that this Addendum does not change the bid due date and time as stated
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following
More informationSOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.
SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS
More informationUPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04
UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure
More information1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows:
Segments 3, 4, 6 and 7 Pier Repairs Invitation for Bids (IFB) Project/Contract #C4962 Addendum # 1 November 30, 2018 To All Bidders: 1. Instructions to Bidders AIA Document A701, 1997 Section 5.3.1.3 of
More informationSample. Bid Proposal. Not Valid for Use
BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions Invitations to Bidders, the undersigned proposes
More informationSECTION MISCELLANEOUS METALS
PART 1 GENERAL 1.1 WORK OF THIS SECTION A. Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install all miscellaneous metal fabrications
More informationBid Form. Schedule 2 Alternate Bid No. 4: Install gutters and downspouts. (100% Local Funded)
Bid Form TxDOT CSJ No. 17HGRCKPT Project: Aransas County Airport - 2017 Hangar Project Project Description: Schedule 1A Base Bid: Construct TxDOT 360 concrete apron pavement for box hangar. Schedule 1A
More informationThe Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.
ADDENDUM #1 EXTERIOR REPAIRS YOUTH SERVICES BUREAU 63 LINDEN STREET MANCHESTER, CT 06040 BID #15/16-68 S/P+A PROJECT NO. 15.207 DATE: March 15, 2016 The following changes to the Drawings and Project Specifications
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2017.02 Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5 The following changes are made to the Proposal, Specifications and Plans: SPECIFICATIONS:
More informationAddendum No. 1 Page 1 of 2
Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT
More informationSUBJECT: ITB , Oxford Road Complete Street Improvements Project ADDENDUM #1
DATE: May 18, 2016 TO: FROM: All Bidders/Proposers Willie Velez, CPPB Procurement Administrator City of Casselberry Purchasing Division SUBJECT: ITB-2016-0023, Oxford Road Complete Street Improvements
More informationTENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1
TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions
More informationAddendum! Project No: HFX A0 Client Project No: MISC Project: MacAulay Sports Field Project Date: March 23, 2015 Addendum No: 2
Addendum! Project No: HFX-00222868-A0 Client Project No: MISC-14-06 Project: MacAulay Sports Field Project Date: March 23, 2015 Addendum No: 2 The following information supplements and/or supersedes the
More informationWhatcom County Bid ADDENDUM NO. 2 West Badger Road / Bertrand Creek Bridge #50 Replacement CRP Federal Aid BRS-2037(107)
WHATCOM COUNTY ADMINISTRATIVE SERVICES DEPARTMENT FINANCE/ACCOUNTING Whatcom County Courthouse 311 Grand Avenue, Suite #503 Bellingham WA 98225-4082 Brad Bennett, Finance Manager March 19, 2019 Whatcom
More informationextrudesection 00301 BID FORM PROJECT IDENTIFICATION: CONSTRUCTION OF PROPOSED DRAINAGE IMPROVEMENTS THIS BID IS SUBMITTED TO: THE CITY OF FREDERICKSBURG, TEXAS, herein after referred to as OWNER. 1. Enter
More informationJOB BB0414 PORTER RD. HWY. 112/71B WIDENING & INTCHNG. IMPVTS. (S) AUGUST 10, 2016
JOB BB0414 PORTER RD. HWY. 112/71B WIDENING & INTCHNG. IMPVTS. (S) AUGUST 10, 2016 Is it allowable to substitute the WF beams to Plate Girders on Bridge 05692? The substitution of a plate girder with flanges
More informationSECTION A1 EXCAVATION AND BACKFILL GENERAL
SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such
More informationProposer shall make note of and/or incorporate all changes listed below into the requested
Request for Proposal (RFP) Bid No: 18-10-1940LE Addendum No. 4 Date: November 27, 2018 To: All Proposers Subject: Addendum No. 4 Consisting of nine (9) Pages RFP No.: Project Name: Owner: 18-10-1940LE
More informationK. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.
DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:
More informationSECTION STEEL JOIST FRAMING
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 05 21 00 1. Use this section only for NCA projects. 2. Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable
More informationAGENDA PRE-BID CONFERENCE
ATTACHMENT NO. 1 TO ADDENDUM NO. 1 AGENDA PRE-BID CONFERENCE Date: December 13, 2016 Time: 1:00 P.M. Project: Boat Lifts at the Ocean Springs Harbor Contract: Boat Lifts at the Ocean Springs Harbor Location:
More information1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.
SECTION 05500- METAL FABRICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION DECORATIVE METAL FENCES AND GATES
SECTION 32 31 19 SPEC WRITER NOTE: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section
More informationSECTION 2831 ITEM F-162 CHAIN-LINK FENCES
SECTION 2831 ITEM F-162 CHAIN-LINK FENCES PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications and the details
More informationBID FORM (LUMP SUM CONTRACT)
BID FORM (LUMP SUM CONTRACT) Place County of El Paso Purchasing Department Date Project No. 11-016 Proposal of (hereinafter called Bidder), a corporation organized under the laws of the State of /a partnership/an
More informationCITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS DOCUMENT 00085B ADDENDUM ADDENDUM NO. 1
ADDENDUM Date of Addendum: December 30 th, 2015 PROJECT NAME: Fencing for Sportspark PROJECT NO: GO1507 BID DATE: Tuesday, January 5 th, 2016 FROM: City of Friendswood Department of Public Works 1306 Deepwood
More informationPIPE CULVERTS. Construct pipe culverts, beveled ends, pipe aprons, and associated appurtenances.
PIPE CULVERTS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe Culverts B. Pipe Aprons and Beveled Ends C. Footings for Concrete Pipe Aprons D. Pipe Apron Guards 1.02 DESCRIPTION OF WORK Construct pipe culverts,
More information.1 American Institute of Steel Construction (AISC) Specifications for Steel Buildings AISC
05 12 00 STRUCTURAL STEEL FRAMING Page 1 of 3 1 General 1.1 SECTION INCLUDES.1 Structural steel framing and support members 1.2 RELATED SECTIONS.1 Section 05 50 00 Metal Fabrications 1.3 REFERENCES.1 American
More information704 - PILING SECTION 704 PILING
SECTION 704 PILING 704.1 DESCRIPTION Drive the specified types of piles to the penetration and bearing values shown in the Contract Documents. BID ITEMS UNITS Piles (*)(**) Test Piles (*) (**) Test Piles
More informationITEM 442 METALS FOR STRUCTURES
AFTER NOVEMBER 1, 2008 ITEM 442 METALS FOR STRUCTURES 442.1 Description. These specifications shall govern for materials such as structural steel, wrought iron, bronze, and other metals used in structures,