DESIGN-BUILD WASHTO WYDOT

Size: px
Start display at page:

Download "DESIGN-BUILD WASHTO WYDOT"

Transcription

1 DESIGN-BUILD An OVERVIEW for STATE DEPARTMENTS of TRANSPORTATION Prepared for WASHTO (Western Association of State Highway and Transportation Officials) WYDOT by Wyoming Department of Transportation June 2002 DESIGN-BUILD 1

2 DESIGN-BUILD An Overview for STATE DEPARTMENTS of TRANSPORTATION TABLE OF CONTENTS Preface and Acknowledgement... 3 Introduction... 5 Design-Build vs. Design-Bid-Build... 5 Appropriate Project Types... 6 Traditional Design-Bid-Build Process... 8 Newer Design-Build Process... 9 Procurement Methods Developing an RFQ/RFP Owner Concerns Legal Issue: Defective Designs Using Design-Build FHWA Rules and Regulations Conclusion Glossary WASHTO Survey: Design-Build DESIGN-BUILD

3 Preface The following information is provided for state department of transportation officials who are unfamiliar with the Design-Build process but are contemplating its usage. It is intended to serve as an introduction to the process, and accordingly, covers only major points while giving basic definitions. It is recommended that anyone giving serious consideration to proceeding with the Design-Build process first undertake a much more intensive review. More detailed information is available from numerous organizations, including the Federal Highway Administration (FHWA) Rules and Regulations, numerous other state departments of transportation that have successfully employed Design-Build, Design-Build Institute of America (DBIA), Associated General Contractors of America (AGC), Engineering Joint Contract Documents Committee (EJCDC), American Society of Civil Engineers (ASCE), National Society of Professional Engineers (NSPE), the insurance and surety industries, as well as others. Acknowledgement Various documents were used as reference material in the preparation of this overview. These include the course notebook for Successful Design-Build Project Delivery developed by the Design-Build Institute of America, the Construction Contractors Guide to the Design-Build Process published by the Associated General Contractors of America, the FHWA Notice of Proposed Rule Making, Rules and Regulations for Design-Build filed in the Federal Register on Oct. 19, 2001, and the notebook on Design-Build assembled by CH2M Hill. DESIGN-BUILD 3

4 4 DESIGN-BUILD

5 Introduction The term Design-Build is used to describe a process where a project sponsor (often a public sector agency such as a state department of transportation) engages a private contractor to perform both design and construction work under terms of a single contract. This is in contrast to the more traditional Design-Bid-Build process whereby the sponsor is responsible for completing all design work before the project is let to contract using the competitive bidding process. There are a variety of methods the sponsor (usually referred to as the owner ) may use to select a Design- Build firm. Likewise, there are a variety of arrangements that may be used by the firm to accomplish the work. The fundamental aspect of Design-Build is that one firm assumes the responsibility for both design and construction. Design-Build vs. Design-Bid-Build Of the several important differences between Design-Build and Design-Bid-Build, perhaps most notable is the separation of design from construction. With Design-Bid-Build, the owner -- either with inhouse staff or by use of a design consultant -- designs the project and puts together a plans and specifications bid package. Bids to build the project are then submitted by various contractors and the project is awarded to the contractor that submits the lowest responsive, responsible bid. DESIGN-BUILD 5

6 DESIGN-BUILD vs. DESIGN-BID-BUILD (continued) There are a number of reasons for considering the Design-Build process. Chiefly, these are: Faster project completion; Lower staffing needed by owner; Potential for less conflict between owner, designer and construction company; Potential for lower costs and/or higher quality; Often allows for more innovation. A study undertaken by the Construction Industry Institute identified a unit cost reduction of 6 percent and an overall project delivery time of 33 percent faster for Design-Build compared to Design-Bid-Build projects. Project Types Appropriate for Design-Build There is no clearly defined standard for determining which particular projects are most suitable for a Design- Build process. Each project should be looked at to determine its potential. Considerations include whether the project schedule is tight and what degree of control over design details does the owner want. Other factors include how much design has already been accomplished, and how much more design must be done. An additional factor is whether Design-Build is in line with state laws and regulations, and similarly, whether its use meets professional licensing laws and regulations. When federal highway funds are involved, a number of requirements come into play. These include: Compliance with provisions of the National Environmental Policy Act (NEPA); Use of federal procurement documents and contracting provisions; Suitable effort to meet disadvantaged business enterprise (DBE) requirements; Compliance with Buy America requirements, Davis- Bacon requirements and certain auditing requirements. 6 DESIGN-BUILD

7 Additional details can be found in Federal Highway Administration (FHWA) Rules and Regulations. Who Should Assume Risk - Owner or Design- Builder? It s logical to assume that a certain amount of risk must be borne by the Design-Build firm. However, experience shows that some liability must be retained by owner; otherwise, an undue burden would be placed on the Design-Builder, resulting in time delays and additional costs. When pursuing highway and other linear projects, an issue for the owner will be how to determine where to assign risk for NEPA, right-of-way acquisitions, utility relocations, environmental documentation and compliance, archaeological and historical sites, hazardous materials and other related project constraints. More discussion about each of these topics follows. For linear roadway projects, a general rule of thumb is that the owner will typically complete about 25 to 35 percent of the preliminary design work, thus minimizing some risks, and avoiding others altogether, being placed on the Design-Builder. The owner completes this amount of design by using either in-house personnel or a bridging design consultant prior to requesting proposals from Design-Build firms to complete the design and then proceed to construction. NEPA documentation: Preparation of the NEPA document is often very time consuming and may significantly affect design. For this reason, a project owner often takes direct responsibility for completing this phase of the project preparation process prior to involving a Design-Build firm. Right-of-way acquisition: Right-of-way acquisition is also time consuming, thanks in part to the need to meet special federal and state requirements. Given this, it is often desirable for the owner to assume this risk and either have secured the right-of-way, or at least be able DESIGN-BUILD 7

8 to provide the Design-Builder with a definitive schedule for the right-of-way acquisition. Utility relocations: Prior to obtaining proposals from Design-Build firms, it is common for the owner to at least identify conflicting utilities and either relocate them or enter into an agreement with utility companies regarding relocation work. Hazardous material sites: Identification of hazardous material sites is a risk best assumed by the owner even though the Design-Build firm may be assigned responsibility for remediation efforts. Other risk factors: Various other risk factors, such as archaeological, biological, historic and paleontological requirements, vary from project to project, and responsibilities for obtaining necessary clearances need to be considered on a case-by-case basis. In summing up, when it comes to considering risks and responsibilities, the owner must take into account that assigning excessive risk to the Design-Build firm may create disputes as well as result in a higher price and longer completion time for the Design-Build contract. Traditional Design-Bid-Build Process Advantages In a couple of words, the advantage of staying with a Design-Bid-Build process can be described as familiarity and understanding. Design engineers are familiar with the process and contractors are familiar with it as well. Likewise, staff of the owner agency understand how it is done, as do legislators and members of the general public. Another advantage of Design-Bid-Build is its suitability for the competitive bidding process, which may be required in accordance with state statutes. Other advantages are: Having the design engineer working directly for owner; 8 DESIGN-BUILD

9 Adherence with legal precedents that have been established over time; Insurance and bonding mechanisms are well defined; Absence of legal barriers in procurement and professional licensing. Disadvantages Along with the advantages come some disadvantages. For starters, the owner must manage two contracts, with the owner assuming all responsibility for design adequacy and frequently being more involved in disputes. Conflict arises due to the owner, engineer and contractor having different objectives, with disagreements arising when the low bid is not the best value and when problems are created by bids being over budget. Not having the contractor involved in the design process makes it more likely for misunderstandings to arise, and ultimately, slow downs in project completion. Ultimately, Design-Bid-Build is generally more litigious than Design-Build. Newer Design-Build Process Advantages Perhaps the most commonly cited advantage of Design-Build is that it is necessary for the owner to deal with only one firm. Only one Request For Qualifications (RFQ) and one Request For Proposal (RFP) is needed, instead of the two contracts needed when the Design- Bid-Build process is employed with a design consultant and a construction contractor. Another often-cited benefit is having the design engineer and contractor working together from a relatively early stage of the project. The engineer and contractor can be unified when dealing with owner. Other advantages which may be gained include: Provides earliest knowledge of firm costs; DESIGN-BUILD 9

10 Allows for continuous Value Engineering; Provides for faster project delivery; Possibly results in higher quality; Provides clearest assignment of risks; Generally results in fewer claims and less litigation. Disadvantages In contrast to the familiar feel of the traditional Design-Bid-Build process, Design-Build is a newer process which requires participants to negotiate a learning curve. Often, the greatest need for education and buy-in may be with owners personnel. When using Design-Build, owners are faced with having to make earlier and timelier decisions. Further, in some states, barriers to both procurement and professional licensing may be encountered. Some aspects of the Design-Build process may not be allowed unless statutes can be amended. Other disadvantages may include: A need for new insurance and bonding products; Resistance by those unfamiliar with system; A need to educate the public, legislators, local governments, engineering firms, contractors, and bonding and insurance companies. Procurement Methods Various methods of procurement may be used, with procurement in this context meaning how an agency goes about hiring or entering into an agreement with an engineering or construction company. Some of the most well-known methods are: Sole Source: When public-sector projects are involved, this type of procurement usually happens only in emergency situations; Qualification Based Selection: A problem may arise when public-sector agencies attempt to allow construction under same contract as design, without advertising for competititve bidding for at least the construction portion of a project; 10 DESIGN-BUILD

11 Low Bid, or Information For Bid: This is a method whereby a single bid to undertake a project includes at least partial design in addition to all of the construction work; Best Value Procurement: This is the most commonly used procurement method for obtaining Design-Build services. It is usually a two-step process with the owner issuing both an RFQ and an RFP before contract award is made to the Design-Build firm providing the best value. Design-Build - Best Value Procurement Under the traditional Design-Bid-Build model, and when design work is done by the owner (or by a consultant hired by the owner), the designer is selected on qualifications, while the contractor is selected via the low-bid process. However, Design-Build usually integrates the above two into a best value selection, combining technical aspects and price considerations. This method can be weighted towards qualifications, or towards price. Because selection methods can range from sole source to low bid, best value represents a middle of the road procurement method. Experience has also shown that: Selections tend toward price orientation when 30 percent or more of the design work is provided by the owner; Selections are more qualification based when less than 30 percent of the design is provided to the firm; When using Design-Build for the first time, owners tend to provide more design, but as they become more experienced, they tend to provide less design; The national trend is towards more Design-Build contracts, with projects of this type now constituting about 45 percent of the market. Types of Design-Build Firm Organization The organizational makeup of Design-Build firms varies. An integrated firm is one where both design and DESIGN-BUILD 11

12 construction functions can be accomplished. In other cases, a construction company will serve as prime while hiring an engineering consultant as subcontractor, or conversely, an engineering firm will serve as prime while bringing in a construction company subcontractor. Also possible is a joint venture with engineering and construction firms working together. Degree of Advance Design Varies for Design-Build The amount of preliminary design completed by the owner can and does vary significantly with individual Design-Build contracts. In the case of Direct Design- Build, a negligible amount of completed design or design criteria is provided. With Design Criteria/ Design-Build, only design criteria is provided. With Preliminary Design/Design-Build, the owner completes a portion of the design -- generally about 25 to 35 percent of the job -- before turning the remaining work over to the Design-Build firm. Developing an RFQ/RFP for a Design-Build Project When developing an RFQ and an RFP, the owner intent on going with Design-Build should consider needs and program requirements, and should determine what the cost would be to design and construct a similar facility. Also, the owner should consider whether conceptual or bridging design is more appropriate for the project. The latter term refers to the practice of the owner partially completing a design prior to issuing an RFQ/ RFP. The owner must decide whether a bridging design is needed, and if so, how far should it be advanced? Not surprisingly, design professionals generally favor conceptual designs, while Design-Builders believe bridging designs inhibit creativity and innovation. Other perceived frequently mentioned disadvantages of bridging designs are: They tend to stifle competition; 12 DESIGN-BUILD

13 Contractor innovation is not available during the preliminary stage of design; They require significant front-end time and cost; Owner is responsible for conceptual design; Two design teams -- which may have differing ideas -- are involved in overall project development. However, bridging designs do offer some advantages, some of which are: They allow owner input in design decisions; They allow use of standard designs; They reduce design costs for Design-Build firm; They make it easier to select firm based on low bid and reduce the necessity of technical evaluation. Items Included in RFQ/RFP Development Numerous items are typically found in the two-step process of developing an RFQ /RFP. The documents can start with a project description along with a statement of objectives to help define what requirements the successful team will be expected to meet. Other information in RFQ portion includes project location and schedule, as well as the makeup of the selection team (sometimes called a jury ) and a schedule for issuance of the subsequent RFP. Usually, the RFQ document also includes: How selection of the Design-Build firm will be made and what factors will be used; Process for writing the RFP, including an outline of requirements for qualification statement; Requirements of Design-Build contract. Additional items in the RFP portion include requirements of both the proposal and the contract. Usually, these items fall into the following areas: Program and project requirements (often presented in narrative form); Performance requirements (generally favored over perspective specifications); DESIGN-BUILD 13

14 Design and construction requirements (which may include design submittals and review time minimums). Other items include how to handle any addenda to RFP which may be necessary, and how to present any preliminary design information provided by the owner. Also, how will any process of clarification be handled? It is very important that the owner knows and communicates comprehensive and clear program and performance requirements. Design requirements and specifications expected of the Design-Builder should be clearly spelled out. Failure to provide accurate information can lead to disputes and add cost to the contract. How Will the Award be Determined? A number of questions will arise when the time comes to determine how a Design-Build firm will be selected. These include: Who will evaluate proposals? Who will make the award? What factors and weights will be the basis for technical evaluations? How will cost be factored in? Will the selection team (or jury) decide or just make a recommendation? Typical Items in RFP Requirements Numerous decisions will need to be made when setting requirements for RFPs. For example, eligibility standards may need to be set. Stipends or honoraria may be paid; if so, it must be determined how many firms will be paid and how much these payments will be. A schedule for the RFP will need to be determined. If any meetings are to be held prior to the proposal submittal deadline, when and where will they be conducted and how many will be needed. Further items to consider: What form(s) will be used for proposal submittal? Will alternates be allowed, and if so, how will they be handled? 14 DESIGN-BUILD

15 What are the submittal requirements? Will presentations be required or allowed? If addenda become necessary, how will they be issued and when? What will be the selection criteria? Items in Contract General Conditions Delineation of responsibilities of the owner as opposed to those of the Design-Builder is an important item to address. Other notable detail items include the preferred hierarchy of documents, design submittal reviews, the owner s right to use design and how extra work orders will be handled. Requirements may be set for a number of topical areas, including, but not limited to, disadvantaged business enterprise (DBE), quality assurance/quality control (QA/QC), warranties, insurance, bonding and standard of care (for the Design-Builder). Differing site conditions should also be addressed. Standard forms of agreements for Design-Build contracts have been devised by several groups including the Design-Build Institute of America (DBIA), American Institute of Architects (AIA), Associated General Contractors of America (AGC), Engineering Joint Contract Document Committee (EJCDC), American Society of Civil Engineers (ASCE) and the National Society of Professional Engineers (NSPE). Other Items to Consider Several variations are available when it comes to contract pricing. One is the lump sum method, another is the guaranteed maximum price, and yet another is reimbursable costs plus incentives. Whichever method is used, risk sharing between the owner and the Design- Build firm needs to be fair, balancing risk with reward. Likewise, there are various methods of negotiated Design-Build procurement. These include making the selection based solely on qualifications, or based on best value, or based on best and final offer. In any case, it DESIGN-BUILD 15

16 should be remembered that state and federal statutes often restrict the extent of negotiated procurement for public entities, which generally have to use a form of competitive procurement. Varying methods available for making competitive procurement selections are described as follows: Weighted matrix, which establishes weight for both technical aspects as well as cost; Fixed budget with best technical proposal; Adjusted low bid; adjusts offer price based on technical merit; Low bid for equivalent designs; Lowest price for technically acceptable proposals. Owner Concerns Not surprisingly, communicating clearly and effectively is key to undertaking a successful Design-Build effort. Good two-way information flow is necessary right from the start of the process when project announcements and advertisements are prepared. Other areas of concern in this regard include working to ensure the quality and completeness of any RFQs and RFPs which are assembled, as well as conducting productive meetings with individuals or groups. Communications savvy is also important in knowing how to handle and answer questions, deciding whether to make in-person presentations and knowing how to create useful addenda. Design completion and owner review/approval How, and to what degree, the project owner will be involved in completing the design portion of a Design- Build project is also an important concern. One item which hinges on the amount of involvement is what resources must be budgeted for contingencies and changes. Generally, the final design and contract documents are the responsibility of the Design-Builder, with the owner reviewing and approving those products to ensure compliance with the RFP and Design-Build contract. 16 DESIGN-BUILD

17 The owner may accomplish some or all of this quality assurance work by using a peer review process. Regardless of what method is used for checking the quality of the design, the Design-Builder will continue to maintain liability for the design. It will be incumbent upon the owner to review and approve any change orders which may become necessary. Owner provides limited quality assurance Although not responsible for making design decisions, the owner will provide prudent oversight but not detailed inspections. When it comes to specifications, using performance, instead of perspective, is desirable. Further, the owner should plan to perform tests and provide inspections only to confirm design assumptions made by the Design-Builder; otherwise, the performance of in-depth inspection and testing will be one of the requirements of the Design-Builder. Modifications and changes Because changes always carry the potential for increasing costs, it is recommended that the procedure for explaining and defining how the owner can go about making changes be set forth in writing. Unless otherwise specified, the Design-Builder should have the right to make changes with notification to owner. At the same time, the Design-Builder should continually engage in Value Engineering for the project. Legal Issue: Who pays for defective designs? Design-Bid-Build Under the traditional Design-Bid-Build process, the owner typically provides to the contractor an implied warranty of adequacy of plans and specifications, with the contractor in turn warranting the adequacy of plans and specifications to subcontractors. In this scenario: The contractor only has to prove the design was defective and that it cost money; DESIGN-BUILD 17

18 The owner has a much more difficult time proving professional negligence of the design firm; The owner must prove malpractice or professional negligence and that a standard of care was not met; Design professionals usually have limited liability and are often somewhat thinly capitalized, making it impossible to pay for major mistakes. Design-Build One-stop shopping is a term often used when it comes to addressing the issue of responsibility and liability; the Design-Builder is totally responsible to owner for both design and construction. Beyond that, there is the issue of whether there will be warranties, and if so, what they will cover and for how long. Using Design-Build Factors to consider with Design-Build Numerous factors must be considered when undertaking a Design-Build project. These include state procurement statutes, federal procurement requirements (when federal funds are involved), state licensing statutes and regulations, types and amounts of insurance coverage, bid and performance bond requirements, and FHWA rules and regulations. Contract issues with Design-Build Details in Design-Build project contracts typically address items such as performance requirements, warranties for product acceptability, and standards of care. An important issue is assigning responsibilities in case of defective work. If disputes arise, will resolution be attempted using mediation or arbitration? If these measures become necessary, who will pay attorney fees? The contract should also address how termination for convenience will be handled. Generally, the owner retains the right to take this action, but details to be out- 18 DESIGN-BUILD

19 lined include how associated costs will be handled and who owns any design work which has been completed. State professional licensing and contracting statutes In most states, licensing statutes were originally codified to set a strict distinction between design and construction, and generally, have not been updated to reflect increasing usage of Design-Build. Unfortunately, violation of statutes may have criminal implication as well as negate contracts. Due to concerns about the Design-Build philosophy among legislators, members of trade groups, and others, a need for increased public education and awareness exists, as does a need to update applicable laws. State procurement statutes Similarly, procurement laws in most states reflect the competitive sealed bidding process for construction, and conversely, the selection of professional services based solely on qualifications, and not price. As is the case with licensing laws, procurement laws have not kept pace with the increased Design-Build usage, and as a result, contracts which violate these laws may not be enforceable. Again, an identifiable need exists to update applicable laws. Insurance requirements and associated problems When using Design-Build, the overall risk management assessment includes the issue of insurance and bonding requirements and the decisions about risk allocation. Like other sectors, the insurance industry has lagged behind the trend of increased Design-Build usage, although available insurance products are now expanding. The owner still needs to compare benefits against costs. Typically any coverage which may be obtained for errors and omission excludes construction errors. Likewise, commercial general liability coverage exclude DESIGN-BUILD 19

20 design errors, as do performance bonds. In these cases, special coverage or riders may be needed. Types of primary insurance coverage required are: Commercial general liability; Professional liability; and Property damage. It is important to remember that surety bonds do not constitute insurance, and that design firms often lack the capital to secure bonds. Many surety companies are unwilling to bond Design-Build projects. Further, these firms generally do not underwrite bond issues to cover design liability, and they have concerns about the confusion between design and construction claims. Surety companies also: Often require higher premiums and tighter underwriting; Often bond only construction; Require coordination of bonds with insurance coverage for errors and omissions coverage. Observers report that the surety industry is now beginning to respond to usage of Design-Build. An in-depth review of desired insurance coverage, bonds and other products available is needed before Design-Build is used. FHWA Rules and Regulations on Design - Build Docket No. FHWA On Oct. 19, 2001, the FHWA filed a Notice of Proposed Rule Making (NPRM) in the Federal Register for Design-Build Contracting. The final rules will amend 23 CFR Parts 627, 635, 636, 637 and 710. The deadline for written comments to this notice of federal rule making was Dec. 18, The final rule will establish prescribed policies and procedures for utilizing the Design-Build contracting method on federal-aid highway projects, and the final 20 DESIGN-BUILD

21 rule will need to be followed any time federal funds are to be used for state DOT Design-Build contracts. When this publication was produced, the final rule had not yet been published. Items mentioned in the NPRM For starters, the monetary amount of a project is required for Design-Build approval, unless approved under Special Experimental Projects Number 14 (SEP- 14), Innovative Contracting. Design-Build contracts must comply with section 102 of the NEPA of 1969, and must include opportunities for Value Engineering and DBE participation. Standardized changed condition clauses include: Differing site condition; Suspensions of work ordered by the engineer; Significant changes in the character of work; Other sections of the NPRM address procedures for licensing and qualification of contractors, advertising for bids, bid opening and bid tabulations, award of contract and concurrence in award, and subcontracting and contractor responsibilities. Also addressed are participation in progress payments, authorizations, product selection, warranty clauses, quality assurance procedures and right-of-way acquisition. The notice also includes a definition of terms and questions and answers. CONCLUSION Design-Build is a good alternative method of project delivery that deserves consideration but is not necessarily the only valid solution. All available mechanisms deserve consideration and another type of solution may be more appropriate for a particular situation. DESIGN-BUILD 21

22 Glossary Adjusted low bid: A form of best value selection in which qualitative aspects are scored on a 0 to 100 scale expressed as a decimal; cost is then divided by qualitative score to yield an adjusted bid or cost per quality point. Award is made to offeror with the lowest adjusted bid. Best value selection: Any selection process in which proposals contain both cost and qualitative components and award is based upon a combination of cost and qualitative considerations. Clarifications: A written or oral exchange of information which takes place after the receipt of proposals when award without discussions is contemplated. The purpose of clarifications is to address minor or clerical revisions in a proposal. Competitive range: A list of the most highly rated proposals based on the initial proposal rankings. It is based on the rating of each proposal against all evaluation criteria. Communications: Exchanges, between the contracting agency and offerors, after receipt of proposals, which leads to the establishment of the competitive range. Contracting agency: The agency which represents the owner for the Design-Build project. Competitive acquisition: An acquisition process which is designed to foster an impartial and comprehensive evaluation of offerors proposals, leading to the selection of the proposal representing the best value to the contracting agency. Deficiency: A material failure of a proposal to meet a contracting agency requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. Design-Bid-Build: The traditional project delivery method where design and construction are sequential steps in the project development process. Design-Build contract: A single contract which provides for design and construction services. 22 DESIGN-BUILD

23 Glossary (continued) Design-Builder: The entity contractually responsible for delivering the project design and construction. Discussions: Written or oral exchanges that take place after the establishment of the competitive range with the intent of allowing the offeror to revise its proposal. Fixed price/best design: A form of best value selection in which contract price is established by the owner and stated in the Request For Proposals document. Design proposals and management plan are evaluated and scored, with award going to the firm offering the best qualitative proposal for the established price. Modified Design-Build: A variation of Design-Build in which the contracting agency furnishes offerors with partially complete plans (generally 30 to 35 percent complete). The Design Builder s role is generally limited to the completion of the design and construction of the project. Organizational conflict of interest: If due to other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the owner, or the person s objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage. Prequalification: The contracting agency s process for determining whether a firm is fundamentally qualified to compete for a certain project or class of projects. The prequalification process may be based on financial, management and other types of qualitative data. Prequalification should be distinguished from short listing. Price proposal: The price submitted by the offeror to provide the required design and construction services. Proposal modification: A change made to a proposal before the solicitation closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award. Proposal revision: A change to a proposal made after the solicitation closing date, at the request of, or as DESIGN-BUILD 23

24 Glossary (continued) allowed by a contracting officer, as the result of negotiations. Qualified project: Defined by the FHWA. Request For Proposals (RFP): The document that describes the procurement process, forms the basis for the final proposals and may potentially become an element in the contract. Request For Qualification (RFQ): The document issued by the owner in Phase I of the two-phased selection process. It typically describes the project in enough detail to let potential offerors determine if they wish to compete and forms the basis for requesting qualifications submissions from which the most highly qualified firms can be identified. Single-phase selection process: A procurement process where cost and/or technical proposals are submitted in response to an RFP. Short listing is not used. Short listing: The narrowing of the field of offerors through the selection of the most qualified offerors who have responded to an RFQ. Solicitation: A public notification of an owner s need for information qualifications, or proposals related to identified services. Stipend: A monetary amount sometimes paid to the most highly qualified unsuccessful offerors. Technical proposals: The portion of a Design-Build proposal which contains design factors, layout, aesthetics and specifications for materials. Tradeoff: A method of source selection which allows you to select the source which represents the best value. This process permits an exchange between cost and noncost factors and allows you to accept other than the lowest priced proposal. Two-phase selection process: A procurement process in which the first phase consists of short listing (based on qualifications submitted in response to an RFQ) and the second phase consists of the submission of cost and technical proposals in response to an RFP. 24 DESIGN-BUILD

25 Glossary (continued) Weakness: A flaw in the proposal that increases the risk of unsuccessful contract performance. A significant weakness in the proposal is a flaw that appreciably increases the risk of unsuccessful contract performance. Weighted criteria process: A form of best value selection in which maximum point values are preestablished for qualitative and cost components, and award is based upon high total points earned by the offerors. Reference: Terms as defined in FHWA Docket No. FHWA dated Oct.19, DESIGN-BUILD 25

26 26 DESIGN-BUILD

27 SURVEY on DESIGN-BUILD Usage Among WASHTO States During the spring of 2002, a questionnaire on usage of Design- Build was submitted to the 18 WASHTO states. For each state, the questionnaire was directed to the state DOT s representative for the Sub-Committee on Design. Each representative was asked whether his or her state had used Design-Build, and if so, how many times, and what was the total cost of all of the Design-Build contracts to date. The representatives were also asked whether their state was considering using Design- Build in the future, and if so, how many contracts were anticipated, and what was the estimated total cost of the future contracts. A Questionnaire on usage of Design-Build was submitted to all WASHTO State DOT s. The sub-committee on Design Representative, for each State, was used as the initial contract. Responses were received from all 17 States. The questions included were as follows: 1. Number of Design-Build Contracts to date: 2. Total cost of all Design-Build Contracts to date: 3. Number of future Design-Build Contracts being considered: 4. Estimated total cost of future Design-Build contracts being considered: For each individual project, the following information was requested: Project Number Name: Length: miles Type of Work: Contract Amount: $ 5. Percent design completed prior to Design-Build Contract: % 6. Included in Design-Build Contract: a. Environmental: Yes No b. Design-Build Survey In addition, for those states where Design-Build had been used, the representatives were asked to provide details about the individual Design-Build projects, including the project name and number, the length of the project, what type of work was accomplished, and what was the contract amount. Additional details included what percent of the design work was completed prior to the beginning of the Design- Build contract and whether the contract required the Design-Build firm to undertake environmental clearance, utility relocation, right-ofway acquisition, warranties, and quality control/quality assurance work. Respondents were also asked what year the Design-Build contract was issued and what year the ensuing construction was completed. See Page 28 for Summary of Response DESIGN-BUILD 27

28 SUMMARY of RESPONSE WASHTO states were split exactly in terms of whether they had yet undertaken any Design-Build contracts. Nine states (Alaska, Arizona, Colorado, Hawaii, New Mexico, Oregon, South Dakota, Utah and Washington) had used Design- Build at least once. Nine states (California, Idaho, Montana, Nebraska, Nevada, North Dakota, Oklahoma, Texas and Wyoming) had not used Design-Build. Two respondents from two states indicated that although their state had not yet used Design-Build, they intend to do so. Other respondents indicated their state is prohibited statutorily from using Design-Build. In general, the states which have used Design-Build in the past are considering using it again. There is a wide range of dollar amounts anticipated for future Design-Build contracts. The smallest contract reported was worth about $20 million, and the largest surpassing $1.5 billion (in both Utah and Colorado). Respondents indicated the average percent of design completed prior to letting a Design-Build contract was in the percent range. No states included the environmental process in the Design-Build contracts, and in most cases, utility locates were not included in the Design-Build contracts, but the actual relocations were. In addition, right-of-way acquisitions were usually not included in the Design-Build contracts, and slightly more than half of the states have included warranties in their Design-Build contracts. Almost all states included QA/QC (Quality Assurance and Quality Control) in their Design-Build contracts. 28 DESIGN-BUILD 28 DESIGN-BUILD

29 28 DESIGN-BUILD

30 WYOMING Department of Transportation 28 DESIGN-BUILD

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS DEPARTMENT OF TRANSPORTATION Transportation Commission and Office of Transportation Safety REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Design-Build Terminology

Design-Build Terminology Design-Build Terminology This glossary is representative of the terminology used in the design-build community and advocated by the Canadian Design-Build Institute (CDBI). For definitions of contractual

More information

PUBLIC CONTRACT CODE SECTION

PUBLIC CONTRACT CODE SECTION PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD OWNER OWNER OWNER DESIGNER GC DESIGNER DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD Contracts Communications

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Procurement Under the New Requirements 1

Procurement Under the New Requirements 1 Requirements 1 Procurement under the New Requirements 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between

More information

CONSTRUCTION MANAGEMENT CORE COMPETENCIES

CONSTRUCTION MANAGEMENT CORE COMPETENCIES CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011)

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Sec. 153.65. As used in sections 153.65 to 153.73 of the Revised Code: (A)(1)

More information

Commonwealth of Virginia

Commonwealth of Virginia Commonwealth of Virginia Alternative Project Delivery Division April 2017 Virginia Department of Transportation TABLE OF CONTENTS INTRODUCTION... 2 1.0 DEFINITIONS... 3 2.0 PRELIMINARY PROJECT SELECTION...

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE Proposals Solicited by: City of Nanticoke 15 East Ridge Street Nanticoke, PA 18634 C:\Users\jim\Desktop\Nanticoke City\07222013professionalengservices\Engineer

More information

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013 FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

Acadiana Metropolitan Planning Organization (MPO) Consultant Selection Process When Federal Funds Are Utilized

Acadiana Metropolitan Planning Organization (MPO) Consultant Selection Process When Federal Funds Are Utilized Acadiana Metropolitan Planning Organization (MPO) Policy and Procedures Consultant Selection Process When Federal Funds Are Utilized Adopted by TPC 11/2016 Approved: DOTD 03/2013 FHWA 05/2016 CONTENTS

More information

CONSTRUCTION MANAGEMENT SERVICES

CONSTRUCTION MANAGEMENT SERVICES DrAFTDRAFTdd EXHIBIT 1 CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS () SELECTION PROCESS School District of Lee County, Florida TABLE OF CONTENTS 1. INTRODUCTION 1 Lobbying 2 2. REQUEST

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Choosing an External Auditor: A Guide to Making a Sound Decision, Developed by the Mid-America Intergovernmental Audit Forum

Choosing an External Auditor: A Guide to Making a Sound Decision, Developed by the Mid-America Intergovernmental Audit Forum Choosing an External Auditor: A Guide to Making a Sound Decision, Developed by the Mid-America Intergovernmental Audit Forum Introduction Regardless of the type or size of public entity you are affiliated

More information

Complying with Ohio s. Qualifications-Based Selection Law. (Ohio Revised Code ) A Guide for Public Authorities

Complying with Ohio s. Qualifications-Based Selection Law. (Ohio Revised Code ) A Guide for Public Authorities Complying with Ohio s Qualifications-Based Selection Law for Professional Engineers, Architects & Surveyors (Ohio Revised Code 153.65-.73) A Guide for Public Authorities American Council of Engineering

More information

New York City Transit (NYCT) DATE: July 19, 2018 CONSTRUCTION/ARCHITECTURAL & ENGINEERING CONTRACT SOLICITATION NOTICE/PROJECT OVERVIEW MTA-NYCT IS NOW ADVERTISING FOR THE FOLLOWING: SSE #: 0000226381

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

Connoisseur Solutions Project Procurement Management

Connoisseur Solutions Project Procurement Management Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes

More information

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES SEDA-COUNCIL OF GOVERNMENTS REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES ENGINEERING, DESIGN, AND BIDDING 119 SOUTH LOCUST STREET DEMOLITION BOROUGH OF MOUNT CARMEL NORTHUMBERLAND COUNTY,

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

CONSTRUCTION DOCUMENTS Part 1

CONSTRUCTION DOCUMENTS Part 1 Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

Amity School District 4J

Amity School District 4J Amity School District 4J Code: DJCA-AR Adopted: 10/11/00 Revised/Readopted: 06/22/05 Personal Services Contracts I. Personal Services Contracts Defined A. Personal services contracts include, but are not

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES

REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES REQUEST FOR QUALIFICATIONS CITY ENGINEERING SERVICES QUALIFICATION SUBMITTAL DATE: Monday, February 18, 2019 RFQ Number 2019-01 City of McLendon-Chisholm 1371 W. FM 550 McLendon-Chisolm, Texas 75032 972-524-2077

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS PROJECT DELIVERY: AN INTRODUCTION A profound design process eventually makes the patron, the architect, and every occasional visitor in the building a slightly better human being. JUHANI PALLASMAA The

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

Mid-America Intergovernmental Audit Forum. Selecting an External Auditor. Guide for Making a Sound Decision

Mid-America Intergovernmental Audit Forum. Selecting an External Auditor. Guide for Making a Sound Decision Mid-America Intergovernmental Audit Forum Selecting an External Auditor Guide for Making a Sound Decision May 2007 Foreword The benefits of having a high-quality audit of a government's financial statements

More information

Purchasing and Procurement Policy

Purchasing and Procurement Policy Purchasing and Procurement Policy Purpose The purpose of this document is to implement the requirements of state law with regard to procurement and bidding on public contracts for public works, goods,

More information

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 AN OVERVIEW OF DESIGN-BUILD Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 Design-Build Not a New Concept In California: Multiple statutes govern design-build

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for

More information

MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK

MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK DATE ISSUED: January 10, 2018 DEADLINE FOR WRITTEN

More information

NOTICE TO BIDDERS FOR

NOTICE TO BIDDERS FOR CITY OF SAN LEANDRO STATE OF CALIFORNIA ENGINEERING AND TRANSPORTATION DEPARTMENT NOTICE TO BIDDERS FOR MONARCH BAY DRIVE BRIDGE REPAIR PROJECT NO. 12-144-38-324 BID NO. 12-13.013 1. BID OPENING: The bidder

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Meeting the Standard of Care in an Evolving Project Delivery Environment

Meeting the Standard of Care in an Evolving Project Delivery Environment Meeting the Standard of Care in an Evolving Project Delivery Environment Russell Jumper & Tim Fandrey Gray Reed & McGraw Texas Society of Professional Engineers Denton Chapter March 9, 2018 Gray Reed &

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 Request For Qualification (RFQ) Number: 2018-01 Environmental Consultant DATE OF ISSUANCE: Tuesday, January 9, 2018 TYPE

More information

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013) SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead

More information

OWNER S REPRESENTATIVE SELECTION RATING. Rate each firm on each item below according to the following scale:

OWNER S REPRESENTATIVE SELECTION RATING. Rate each firm on each item below according to the following scale: OWNER S REPRESENTATIVE SELECTION RATING Rate each firm on each item below according to the following scale: Superior = 5 Excellent = 4 Good = 3 Fair = 2 Poor = 1 1. Competence to Perform Required Services

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

REQUEST FOR QUALIFICATIONS AND PROPOSALS

REQUEST FOR QUALIFICATIONS AND PROPOSALS REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan

More information

Procurement Policies and Procedures

Procurement Policies and Procedures Center for Economic and Social Development Procurement Policies and Procedures 1. Purpose of procurement standards. The purpose of these standards is to establish procedures for the Center for Economic

More information

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,

More information

Procurement & Contracting

Procurement & Contracting Procurement & Contracting Overview The procurement of goods and services and executing related contracts is a major function of transit management. In addition to seeking to obtain the highest quality

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Albany Unified School District Contractor Prequalification

Albany Unified School District Contractor Prequalification Albany Unified School District Contractor Prequalification The Albany Unified School District ( District ) has determined that contractors providing construction services ( Contractor(s) or Firm(s) ) must

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

Request for Proposals Triennial Performance Audit of Public Transit Systems and The Council of Governments in San Joaquin County

Request for Proposals Triennial Performance Audit of Public Transit Systems and The Council of Governments in San Joaquin County Request for Proposals Triennial Performance Audit of Public Transit Systems and The Council of Governments in San Joaquin County April 09, 2018 Responses Due Date/Time April 30, 2018 before 4:00 PM Pacific

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

EXHIBIT A. 1) General:

EXHIBIT A. 1) General: 1) General: EXHIBIT A FINDINGS OF FACT FOR EXEMPTION FROM COMPETITIVE BIDDING AND USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) METHOD OF CONTRACTING FOR TILLAMOOK PUD OPERATIONS CENTER AND

More information

Ohio Department of Transportation. Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests

Ohio Department of Transportation. Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests June 26, 2017 (rev. 9/29/2017) Ohio Department of Transportation Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests Purpose The purpose of this document

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 REQUEST FOR PROPOSAL (RFP) 2018-10 Lobby Kiosk Services DATE ISSUED: Thursday, May 3, 2018 TYPE OF PROJECT: CONTACT PERSON:

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016 REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for

More information

Legal Issues Related to Design Build

Legal Issues Related to Design Build Legal Issues Related to Design Build Presented by Aaron O. Martin CLARK, MIZE & LINVILLE, CHARTERED 129 S. 8 th, St. Salina, KS 67401 Telephone: (785) 823 6325 Facsimile: (785) 823 1868 aomartin@cml law.com

More information

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA Project No. 4484/A4L-379/964840 LEVEL I PREQUALIFICATION DOCUMENTS for OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North

More information

Terminal D South Expansion - Construction Manager-At-Risk (CMAR)

Terminal D South Expansion - Construction Manager-At-Risk (CMAR) DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 3 FOR Terminal D South Expansion - Construction Manager-At-Risk (CMAR) CONTRACT NO. 9500647 August 30, 2018

More information

BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA OFC FAX

BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA OFC FAX BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA 95132 408-923-1871 OFC 408-926-8329 FAX PREQUALIFICATION PACKAGE INSTRUCTIONS FOR PROSPECTIVE MEP SUBCONTRACTORS FEBRUARY

More information

Doing Business with Public Entities in Arizona

Doing Business with Public Entities in Arizona DOING BUSINESS WITH PUBLIC ENTITIES IN ARIZONA 1 Doing Business with Public Entities in Arizona A Vendor Guide to Understanding Arizona Procurement Practices 2 DOING BUSINESS WITH PUBLIC ENTITIES IN ARIZONA

More information

Procurement Process: Architects & Professional Engineering Services. Procurement.

Procurement Process: Architects & Professional Engineering Services. Procurement. Procurement Process: Architects & Professional Engineering Services Procurement www.novascotia.ca/tenders Updated: February 2017 Table of Contents Contents INTRODUCTION:... 3 APPLICATION:... 3 SCOPE of

More information

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for

More information

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous

More information

448 INNOVATIVE BIDDING TOOLKIT

448 INNOVATIVE BIDDING TOOLKIT Publication 448 INNOVATIVE BIDDING TOOLKIT 2013 Edition, Change 2 Bureau of Project Delivery, Highway Delivery Division Project Schedules, Specifications and Constructability Section PUB 448 (05-16) This

More information

COLLINS COCKREL & COLE A PROFESSIONAL CORPORATION

COLLINS COCKREL & COLE A PROFESSIONAL CORPORATION COLLINS COCKREL & COLE A PROFESSIONAL CORPORATION PAUL R. COCKREL JAMES P. COLLINS ROBERT G. COLE TIMOTHY J. FLYNN EVAN D. ELA LINDA M. GLESNE DAVID A. GREHER ATTORNEYS AT LAW 390 UNION BOULEVARD, SUITE

More information

BID No: 04/17 REQUEST FOR PROPOSALS FOR TRAVEL MANAGEMENT SERVICES FOR THE GENERAL SECRETARIAT OF THE ORGANIZATION OF AMERICAN STATES

BID No: 04/17 REQUEST FOR PROPOSALS FOR TRAVEL MANAGEMENT SERVICES FOR THE GENERAL SECRETARIAT OF THE ORGANIZATION OF AMERICAN STATES BID No: 04/17 REQUEST FOR PROPOSALS FOR TRAVEL MANAGEMENT SERVICES FOR THE GENERAL SECRETARIAT OF THE ORGANIZATION OF AMERICAN STATES SECRETARIAT OF ADMINISTRATION AND FINANCE (SAF) GENERAL SECRETARIAT

More information

CONSTRUCTION MANAGEMENT SERVICES

CONSTRUCTION MANAGEMENT SERVICES DrAFTDRAFTdd EXHIBIT 1 CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) SELECTION PROCESS School District of Lee County, Florida TABLE OF CONTENTS 1. INTRODUCTION 1 Lobbying 2 2. 3 A.

More information

REQUEST FOR PROPOSALS AND STATEMENT OF QUALIFICATIONS IMPACT FEE STUDY

REQUEST FOR PROPOSALS AND STATEMENT OF QUALIFICATIONS IMPACT FEE STUDY REQUEST FOR PROPOSALS AND STATEMENT OF QUALIFICATIONS IMPACT FEE STUDY June 1, 2018 The City of Rhome is now accepting sealed Request for Proposals and Statement of Qualifications (RFQ) for New Water &

More information

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...

More information

Invitation to Negotiate

Invitation to Negotiate Invitation to Negotiate Programming, Design, and Consulting Services Lisa Daws 4/3/2012 CLERKS OF COURT OPERATIONS CORPORATION Table of Contents Agency Background... 3 Statement of Purpose... 3 Scope of

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

Kirk W Buffington, CPFIM, CPPO, C.P.M.,

Kirk W Buffington, CPFIM, CPPO, C.P.M., Kirk W Buffington, CPFIM, CPPO, C.P.M., An Overview We will be talking about: The elements of the RFP process Factors determining the selection of the procurement method The elements of risk and how they

More information

Army Enterprise Resource Planning (ERP) Services

Army Enterprise Resource Planning (ERP) Services Army Enterprise Resource Planning (ERP) Services Army Enterprise Resource Planning (ERP) Services SOLICITATION NUMBER: W52P1J-14-R-0059 Army Contracting Command Rock Island (ACC-RI) 1 Rock Island Arsenal

More information

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

As a state agency, the College administration is required to develop procedures for Construction Manager selection. COLLEGE of CENTRAL FLORIDA ADMINISTRATIVE PROCEDURE Title: Construction Management Selection Process Page 1 of 2 Implementing Procedure For F.S. 1013.45 Date Approved: 09/11/02 Division: Administration

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

BID AND PURCHASING LAWS/BEST PRACTICES

BID AND PURCHASING LAWS/BEST PRACTICES BID AND PURCHASING LAWS/BEST PRACTICES BEFORE YOU DO ANYTHING, ASK YOURSELF THIS QUESTION. Is this purchase or contract for goods or services exempt from the bid laws? Exemptions: Piggy back off a contract

More information

Design-Build Project/Team Awards Submission Details

Design-Build Project/Team Awards Submission Details Design-Build Project/Team Awards Submission Details Deadline: May 22, 2019 Please review this information carefully before beginning your online awards submission and share this document with your team

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

City and County of San Francisco

City and County of San Francisco City and County of San Francisco Office of the Controller CITY SERVICES AUDITOR REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION CONTRACT AUDIT AND PROJECT CONSULTING SERVICES RFQ#CON2013-11 CONTACT: Mary Hom,

More information

REQUEST FOR PROPOSALS: CEO COMPENSATION AND EVALUATION SERVICES. Issue Date: April 30, Due Date: June 6, 2014

REQUEST FOR PROPOSALS: CEO COMPENSATION AND EVALUATION SERVICES. Issue Date: April 30, Due Date: June 6, 2014 REQUEST FOR PROPOSALS: CEO COMPENSATION AND EVALUATION SERVICES Issue Date: April 30, 2014 Due Date: June 6, 2014 In order to be considered, proposals must be signed and returned via email to rwhitmore@wested.org

More information

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &

More information