Breakwater on Soft Subsoil Problems of Design and Execution

Size: px
Start display at page:

Download "Breakwater on Soft Subsoil Problems of Design and Execution"

Transcription

1 Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Breakwater on Soft Subsoil Problems of Design and Execution Siegmund Schlie Heinrich Hirdes GmbH, Rostock Abstract The paper reports about problems in design of the breakwater system of the town Barth in Mecklenburg Vorpommern which is planned as a combination of harbour protection and reducing the risks of storm flood for the town of Barth. The projected breakwater system should consist of rock structures. Several boundary conditions can be identified as most important design factors. The paper shows how small mistakes in decisions of the client and designer will cause problems in execution of the construction works. These can cause problems in the realisation of works. Additional works had to be done, leading to the extension of execution time and the increase of construction cost. The paper presents the used technology and the problems with difficult soft subsoil in this project. Engineers learn mostly a lot of things by mistakes. So for the Barth project there is a chance to find better technical solutions for the second phase of the project. Possible solutions will be exemplified. 1 Introduction The town of Barth (Fig. 1) and the environmental authorities of Mecklenburg Vorpommern made a concept for a combination of harbour protection and reducing the risks of storm flood for the town of Barth. The implementation of the project was divided into two phases, the western and the eastern breakwater system. The western breakwater was partly carried out in The detailed design and the execution of the eastern breakwater are expected in 2008/2009.

2 Barth Rostock Figure 1 Map of the area round Barth ( Google) The continuation of the western breakwater will be combined with the design and execution of the eastern. The harbour of Barth is situated in the inner coastal waters, the so called Bodden. The characteristics of this area are shallow water and difficult hydrological and geological conditions. The planned breakwater system consists of rock structures. 2 General Design Aspects 2-1 Stages in the Life of Rock Breakwaters All projects start with a need: something that is desired, required or lacking the lack of a shelter of a harbour, for example. The project definition stage defines this need by setting project objectives. These objectives will present requirements and restrictions. Clear objectives will assist in establishing the appropriate engineering solution to meet the identified need. This is the starting point for the designer. At the concept design stage broad solutions are developed, such as structure type and feasibility. One of the main activities at this stage tends to be the identification of the functions, constraints and information requirements that will enable the design to go forward. Preliminary design is when many of the investigations and study activities must be carried out, including determination of wave climate or current regime, environmental assessments and economical analysis. This has to be an interactive process, involving many parties, to gain agreement and select a preferred solution. Once the various criteria have been satisfied, detailed design must involve the development of all structural elements, using further in situ investigation and physical and technical data, to produce drawings, specifications and bill of quantities.

3 During the working design phase further design modification may be necessary as a result of on-site difficulties such as unforeseen ground conditions or changes in working approaches. When this happens, the designer should ensure that the original design concepts are fully understood and the design changes do not compromise any other aspect of structure performance. In the operational period the continued performance of the structure is ensured by implementing a monitoring and maintenance programme. 2-2 Technical Considerations for Planning and Design Planning and design of rock breakwaters as well as other constructions demand the attention of different requirements. Economical, environmental and social considerations have to be checked with the same accuracy then technical considerations which are described in Table 1. If the engineer follows strictly these considerations in planning and design, the probability of big mistakes can be reduced. Sometimes the clients try to reduce the research of technical requirements because of financial problems. Mostly these reductions will cause much more financial and time schedule problems during the execution phase. Table 1 Technical considerations for planning and design of rock breakwaters Planning and design considerations Aspect Functional requirements (performance) Considerations - Achievement of functional requirements (e.g. limited overtopping, reducing wave activity in a harbour riverbank erosion) - Acceptable structural stability and residual risk of failure (factors of safety and choice of design conditions) - Changes in acceptable probability of failure over time - Adaptability (e.g. change of use of the structure over time) - In service health and safety requirements - Ground conditions (geotechnical) - Topographic and bathymetric conditions Physical conditions - Hydraulic forces - waves, currents, water levels - Morphological changes - Sediment load and movement - Uncertainties of physical conditions (confidence limits) - Material properties (e.g. rock density, quality, durability and availability) Technical data - Accuracy of design information, including analytical methods used - Structure-specific design methods - Nature of failure (progressive or instantaneous, complete or partial)

4 Construction Maintenance - Ability to build the structure - Contractor experience and resources - Health and safety issues - Conditions during construction (e.g. storm or flood frequency and magnitude) - Access of construction plant - Material quality - Alternative material availability (sources) - Site area for storage of materials and operations - Characteristics of structure response - Frequency and type of intervention - Availability of suitable resources for repair (materials, plant, expertise) - Funding - Accessibility for construction plant 3 Requirements on Subsoil Investigation Structures like rock breakwaters require especially accurate investigations of subsoil. The structure and its foundation must be designed in such a way, during the design life, foundation displacements and movements are kept within the limits that the structure can tolerate without effects on its structural integrity and functional capability. One important aspect of the design of foundation is the stability of the seabed and the possibility of scour and undermining around the structure under wave and current actions. Difficult ground conditions refer generally to the existence of unfavourable subsoil strata at the site. The presence of such conditions, if not properly handled, may lead to both problems during the construction stage and the future use of breakwaters. Guidelines for site investigation are given in different publications, e.g. the "Manual on the use of rock in coastal and shoreline engineering" and "Port Works Design Manual Part 4". The basic geological and geotechnical data requirements are summarised in terms of the physical and mechanical characteristics which need to be investigated. These data are obtained by means of a wide variety of field and laboratory tests, supplemented by detailed descriptions made by a geotechnical engineer or geologist. The values of geotechnical parameters for design should be determined from careful assessment of the range of values of each parameter. Particular attention should be given to the quality of ground investigation and the adequacy of test data with respect to the inherent variability of the materials encountered. For structures founded on silt or clay (low permeability) consolidation needs a long time. The most critical period for stability is during construction and just after completion. The undrained shear strength of the founding strata is the controlling critical factor for overall stability. The designer should determine the appropriate

5 undrained shear strength as well as the long term (drained) parameters, and assess the foundation stability under all conditions. Particular attention must to be paid to place the rock material of the structure when clay or silt deposits remain under the foundation. Rapid fill placement may induce instability on the foundation as the excess pore water pressure due to the fill loading will take some time to dissipate completely. The effect of the filling rate or the stages of loading on stability should be investigated with respect to the shear strength of the underlying soil at the time of construction. The settlement expected during the design life of breakwaters should be assessed to ensure that it is acceptable for the proposed use of the structures. In general, the settlement after completion of construction should be limited, depending on the type, importance, stability and usage of the structure and the site condition. 4 The Conditions at the Barth Area The following boundary conditions were identified in the area of Barth: - Hydraulic boundary conditions Barth is situated on the southern coast of the Western Pomeranian Boddenzone (see Fig. 1) with a very flat coastline. Due to the position of Barth to the Bodden waters the area is endangered by flooding during stormy high waters. The extreme water level was measured in the year 1872 with m about HN gauge. Such remarkable water levels will endanger as well the harbour as the city of Barth. Significant parameters for Barth are: Calculated high water level: Wind direction: Wind speed: Fetch Length: Wave length L: Wave period T: Significant wave height H s : + 1,95 m HN NNE 25 m/s 5,000 m m 2.84 s 0.78 m There are various water depths inside the harbour of Barth with a maximum of 3.00 m below medium water level. The waterways to the harbour are also dredged up to 3.00 m. Outside of the harbour and the fairways water depths between 0.50 m and 2.00 m exist. The last hydrographical survey was executed in These survey results had been used as basis for the design. The calculation of amour unit weights according to the formulas of HUDSON and VAN DER MEER requires smaller rock units compared with the influence of

6 ice pressure. - Ice conditions Ice pressure plays a decisive role in dimensioning of amour unit weight for the breakwater in this area. Ice thickness of 20 cm up to 53 cm can be expected. - Geological and geotechnical boundary conditions Geotechnical experts made some studies on the geological and geotechnical conditions of the planned site area. The geological situation formed following the last ice age. Generally three different layers are typical for this area: a) Holocene silty mud and peat with a low undrained cohesion and layer thickness of 0.3m up to 4.10 m b) Holocene silty sand c)pleistocene sand and bolder clay The detailed results of description of subsoil are presented in Table 2. Table 2 Soil characteristics of the site area Soil characteristic Friction Unit Layer Cohesion Elastic Coefficient of Layer angle weight horizon modulus Permeability Thickness effective undrained of soil in meter φ' c u γ E k [ ] [kn/m²] [kn/m³] [MN/m²] [m/s] -0,8 to -5,6 mud ,5 1*10-11 to ,5 peat ,5-1,0 1*10-8 to ,0 to -9,0 sand *10-5 to ,0 clay 28 5/ *10-5 to 10-4 The geotechnical expert recommended the exchange of the soft subsoil because a displacement of the muddy layers can be expected. - Sedimentation, shore evolution and environmental impacts The "Barther Bodden" can only be considered in connection with the complete system Bodden waters. This system is an ecological high sensitive one. The water exchange with the Baltic Sea influences the quality of water in the Bodden zone. The design of rubble mound breakwaters in this area has to take water exchange aspects into consideration. For this reason water exchange openings have to be arranged in the breakwater system. In several parts of the harbour the removal of organic sedimentation was recommended. - Construction and maintenance considerations The line of the breakwater was determined by functional requirements. The construction should be carried out in combination of floating and land based equipment. There are different experienced contractors for this kind of works available. Rock material can be supplied as well from Scandinavia as from

7 southern Germany. Execution time is only limited by frost conditions because of safety requirements. The size of amour layers of the breakwater was designed for zero maintenance with normal weather conditions. - Cost considerations. During the planning phase a budget for the construction was estimated in the right level. When the designer made the bill of quantity he didn't use any position for unpredictable circumstances. The budget for execution had been settled on basis of the winning offer of tender process without any reserves because of limited aid from the county government and the European Union. 5 The Breakwater System in Barth 5-1 Design of the Western Breakwater The breakwater system for Barth consist of a western part with a length of 830 m, which should be constructed in the first construction period, and an eastern part, that will to be implemented in a second stage respectively. The planned structures of the breakwater system are shown at Figure 2. Figure 2 Top view of the planned breakwater system in Barth The Barth breakwater system consisted of rubble mound breakwaters made of natural rock. For the western part a breakwater with the following main parameters was designed: Top level after settlement: m HN Slope inclination sea side: 1:2.0

8 Slope inclination harbour side: 1:1.5 Slope Inclination of breakwater heads: 1:2.0 Amour layer sea side: Amour layer harbour side: Core material in different layers: > 1.0 t per unit > 0.5 t per unit 0 to 60 kg Blockade against sediment passage to sea side:by non woven geotextile Content of hollow space inside the rock structure:42 % Figure 3 demonstrates a general cross section of the western breakwater. The designer held the opinion that the exchange of the soft subsoil which the geotechnical expert had recommended is not necessary. For foundation on the soft subsoil a woven geotextile with high tensile strength was designed to reduce settlements on a level of 0.45 m on maximum. 5-2 Execution Figure 3 General cross section breakwater We started the execution with hydrographical survey and detected water depth that were 0.3m less then the survey from The placement of the woven geotextile with high tensile strength was the first step of construction of the western Barth breakwater. The single tracks were 5.00 m wide and had to overlap 1.0 m. The start was at the western shore line. On this geotextile a gravel layer of 4 60 mm had to be installed.

9 Figure 4 Displacement of mud in the direction of construction With the placement of gravel a displacement and strong settlement of the soft subsoil started. This process continued and became stronger during the placing of core material. Following the results of our measurements on the settlement gauges the core of the breakwater sunk into the soft subsoil up to the level of the sustainable soil layer. The muddy subsoil was displaced to sea and harbour side as well as to front side, the construction direction (Fig.4). Some additional dredging works had to be done to continue the construction. The general technology was disturbed by some additional works. The new process is demonstrated at Figure 5. Figure 5 Technology influenced by replacement of mud Thus, the displacement of the soft subsoil happened by expensive rock material. The supposition of the designer referring the content of hollow space inside the rock structure was completely wrong. Due to the wide spread size of rock material this content averaged only 28%. These both facts caused a massive increasing of the quantities of rock and the construction costs. The budget of the client was limited because of the missing of reserves for unpredictable circumstances. Then the client had to come to a decision, the construction of the breakwater had to be interrupted about 200 m before the end. The next stages were profiling of the core and placing of the armour layers by hydraulic grab (Fig. 6 and 7).

10 Figure 6 Profiling by hydraulic grab Figure 7 Completely profiled breakwater In spite of all problems we built this part of the western breakwater in a good quality. For continuation there will be a big disadvantage. A water based technology has to be used which is more expensive then the land based in the first stage. 6 Conclusions and Recommendations a) The client and the designer have to find out a budget that is flexible enough for unpredictable circumstances. b) The designer should never use a hydrographical survey which is some years old. That is saving money at the wrong place. c) If the designer hasn't got experience in the field of rock armour works, he must lock to some experts and/or experienced contractors for advice. Then it is possible to choose the right details for the rock structures, e.g. the hollow space inside. d) The designer should never ignore recommendations of geotechnical experts referring to the properties of soil and necessary measures. e) There are various types of improvement of the ground for a foundation of a breakwater in the case of bad soft subsoil, such as - Vertical drainage - Vacuum consolidation - Embankments on different kinds of piles - Geotextile encased columns - Vibrated stone columns - Soil exchange. f) For the relatively thin layers of soft material in the Bodden area soil exchange is the cheapest solution, but there are actual requirements on storage area for the organic soft soil.

11 7 References Ciria, Cur. Manual on the Use of Rock in Coastal and Shoreline Engineering. CIRIA London, CUR Gouda, Ciria, Cur and Cetmef. The Rock Manual. The Use of Rock in Hydraulic Engineering (2 nd edition). CIRIA, London (published in advance in the web), The Government of Hong Kong Special Administrative Region, Civil Engineer Department, Civil Engineer Office,.Port Works Design Manual Part 4. Guide to Design of Seawalls and Breakwater, Pilarczyk, K.W. and R.B. Zeidler. Offshore Breakwaters and Shore Evolution Control. Balkema Rotterdam / Brookfield pp , , Arbeitsausschuss "Ufereinfassungen" der HTG, Recommendations of the Committee for Waterfront Structures Wasserstraßen EAU Ernst & Sohn, Berlin, 2004.

12

CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA)

CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA) CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA) Siegmund Schlie*, Bernd Opfermann** and Torsten Retzlaff*** * Heinrich Hirdes GmbH, Rostock ** b & o - Ingenieure, Hamburg ***

More information

Special Building Method for a Storm Tide Protection Construction on the Baltic Sea Coast

Special Building Method for a Storm Tide Protection Construction on the Baltic Sea Coast Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Special Building Method for a Storm Tide Protection Construction on the

More information

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures Arbeitsausschuß "Ufereinfassungen" der Hafentechnischen Gesellschaft e.v. Recommendations of the Committee for Waterfront Structures Harbours and Waterways 9., completely revised Edition TABLE OF CONTENTS

More information

PIANC Commission Working Group Report Reviews

PIANC Commission Working Group Report Reviews PIANC Commission Working Group Report Reviews EnviCom Working Group report details Initial review: conclusion * If identified as potentially sensitive, please highlight the particular areas of potential

More information

SUBSOIL IMPROVEMENT WORKS AT DVIZ, HAIPHONG, VIETNAM

SUBSOIL IMPROVEMENT WORKS AT DVIZ, HAIPHONG, VIETNAM Subsoil Improvement Works at DVIZ, Haiphong, Vietnam 3 ALICE MONTULET, LUCIEN HALLEUX AND NGUYEN VAN NGOC SUBSOIL IMPROVEMENT WORKS AT DVIZ, HAIPHONG, VIETNAM ABSTRACT This article describes the subsoil

More information

Improving Engineering Properties of Soft Soil Using Preloading and Prefabricated Vertical Drains

Improving Engineering Properties of Soft Soil Using Preloading and Prefabricated Vertical Drains Volume 1, Issue 2, October-December, 2013, pp. 08-12, IASTER 2013 www.iaster.com, Online: 2347-2855, Print: 2347-8284 ABSTRACT Improving Engineering Properties of Soft Soil Using Preloading and Prefabricated

More information

CHAPTER 153 PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS. K.J. Macintosh* and W.F. Baird*

CHAPTER 153 PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS. K.J. Macintosh* and W.F. Baird* CHAPTER 153 ABSTRACT PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS K.J. Macintosh* and W.F. Baird* At the 19th ICE Conference in Houston in 1984 an alternative concept for the design of rubble mound

More information

Rubble-Mound Stability

Rubble-Mound Stability Design of Marine Structures Rubble-Mound Stability Steven A. Hughes. Ph.D., P.E. Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center David R. Basco. Ph.D., P.E. Coastal Engineering

More information

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Module - 3 Lecture - 10 New materials for coastal embankments l

More information

SoilTain Coastal Protection Tubes. Geosynthetic Container System for Coastal and Bank Protection

SoilTain Coastal Protection Tubes. Geosynthetic Container System for Coastal and Bank Protection SoilTain Coastal Protection Tubes Geosynthetic Container System for Coastal and Bank Protection 2 3 Geosynthetic Tube System The All-Rounder for Coastal and Bank Protection The effects of global climate

More information

MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION

MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION MASS STABILIZATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION Juha Forsman, M.Sc.(Civ.Eng.) Ramboll Finland Oy MASS STABILISATION IN INFRASTRUCTURE AND ENVIRONMENTAL CONSTRUCTION 1. GEOTECHNICAL

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

Table 1. Typical Soil Parameters Description Bulk Density, kn/m 3 Liquid Limit, % Plastic limit, % Natural Moisture Content, % Cohesion, kn/m 2 Compre

Table 1. Typical Soil Parameters Description Bulk Density, kn/m 3 Liquid Limit, % Plastic limit, % Natural Moisture Content, % Cohesion, kn/m 2 Compre CASE STUDY CONSTRUCTION OF HIGH ROAD EMBANKMENT OVER THICK SOFT SILTY CLAY- A CASE STUDY Radhakrishnan R, Geo-Enviro Engineers P Ltd, Chennai, Tamil Nadu, India, 044-24483522, geoenviro2012@gmail.com.

More information

THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS

THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS International Conference on Soft Ground Engineering (ICSGE2015) 3-4 December 2015, Singapore THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS JEROEN DIJKSTRA

More information

GROUND IMPROVEMENT SITE INVESTIGATON

GROUND IMPROVEMENT SITE INVESTIGATON GROUND IMPROVEMENT SITE INVESTIGTON November 2009 Lankelma ltd old Harbour arn old Harbour Lane Iden, East Sussex TN31 7UT U.K. T: +44 (0)1797 280050 E: info@lankelma.com www.lankelma.com Gardline Lankelma

More information

Southern African Coastal Vulnerability Assessment. Dr Christo Rautenbach

Southern African Coastal Vulnerability Assessment. Dr Christo Rautenbach Southern African Coastal Vulnerability Assessment Dr Christo Rautenbach 1 Content layout Introduction to coastal vulnerability Climate change Consequences on the coast Vulnerability and risk on coastal

More information

USE OF THE OBSERVATIONAL APPROACH FOR EMBANKMENT CONSTRUCTION ON ORGANIC SOIL DEPOSITS IN SRI LANKA

USE OF THE OBSERVATIONAL APPROACH FOR EMBANKMENT CONSTRUCTION ON ORGANIC SOIL DEPOSITS IN SRI LANKA USE OF THE OBSERVATIONAL APPROACH FOR EMBANKMENT CONSTRUCTION ON ORGANIC SOIL DEPOSITS IN SRI LANKA R.P.D.S.Premalal, B.Sc.Undergraduate, Department of Civil Engineering, University of Moratuwa (email:

More information

8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES. COPEDEC 2012, IIT Madras, Chennai, INDIA Feb.

8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES. COPEDEC 2012, IIT Madras, Chennai, INDIA Feb. 8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES COPEDEC 2012, IIT Madras, Chennai, INDIA. 20-24 Feb. 2012 Case Studies and Lessons Learnt from Applications of Sand

More information

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1 DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE6502 - FOUNDATION ENGINEERING Subject Code: CE6502 UNIT 1 1. What are the informations obtained

More information

Importance of tailings properties for closure

Importance of tailings properties for closure Proceedings of Mine Closure Solutions, 2014 April 26 30, 2014, Ouro Preto, Minas Gerais, Brazil Published by InfoMine, 2014 InfoMine, ISBN: 978-0-9917905-4-8 Importance of tailings properties for closure

More information

Mechanical and Environmental Properties of Plastics-included Landfills with Elastic Behavior

Mechanical and Environmental Properties of Plastics-included Landfills with Elastic Behavior December 21, 2016 3K133011 Mechanical and Environmental Properties of Plastics-included Landfills with Elastic Behavior (Resilient) Atsushi YAMAWAKI 1 Japan Industrial Waste Management Foundation Period

More information

Construction of Embankment with Ground Improvement at By Pass of NH 34. Dilbag Singh Construction Head Transport Vertical HCC Ltd.

Construction of Embankment with Ground Improvement at By Pass of NH 34. Dilbag Singh Construction Head Transport Vertical HCC Ltd. Construction of Embankment with Ground Improvement at By Pass of NH 34 2 0 1 7 Dilbag Singh Construction Head Transport Vertical HCC Ltd. Abstract The Baharampore Farakka corridor of the National Highway

More information

Where the Ocean Meets Land. Coastal Engineering

Where the Ocean Meets Land. Coastal Engineering Where the Ocean Meets Land Coastal Engineering Photo credit : Rio Tinto Alcan Our Expertise MARINAS AND HARBOURS Design and repair of breakwaters Sedimentation and dredging studies Navigation guidelines

More information

A Case Study: Foundation Design in Liquefiable Site

A Case Study: Foundation Design in Liquefiable Site RESEARCH ARTICLE OPEN ACCESS A Case Study: Foundation Design in Liquefiable Site Tahar Ayadat* *(Department of Civil Engineering, College of Engineering, PMU University, P.O. Box 1664, Al-Khobar, 31952,

More information

Numerical Modeling the Behavior of Ground Improvement in Soft Clay

Numerical Modeling the Behavior of Ground Improvement in Soft Clay Numerical Modeling the Behavior of Ground Improvement in Soft Clay Jason Y. Wu Department of Civil Engineering and Engineering Informatics Chung Hua University No.707, Sec. 2, Wufu Rd., Hsinchu City 300,

More information

Finite Element Analysis of Ground Modification Techniques for Improved Stability of Geotubes Reinforced Reclamation Embankments Subjected to Scouring

Finite Element Analysis of Ground Modification Techniques for Improved Stability of Geotubes Reinforced Reclamation Embankments Subjected to Scouring Finite Element Analysis of Ground Modification Techniques for Improved Stability of Geotubes Reinforced Reclamation Embankments Subjected to Scouring Hyeong-Joo Kim 1), *Jay Jamin 2) and Jose Leo Mission

More information

3D ASSET DATA CAPTURE TO EFFECTIVELY INFORM DAMAGE ASSESSMENT AND REPAIR DESIGN OF ROCK ARMOURED BREAKWATERS E Rowe 1, D Dack 1, J Hinschen 2

3D ASSET DATA CAPTURE TO EFFECTIVELY INFORM DAMAGE ASSESSMENT AND REPAIR DESIGN OF ROCK ARMOURED BREAKWATERS E Rowe 1, D Dack 1, J Hinschen 2 3D ASSET DATA CAPTURE TO EFFECTIVELY INFORM DAMAGE ASSESSMENT AND REPAIR DESIGN OF ROCK ARMOURED BREAKWATERS E Rowe 1, D Dack 1, J Hinschen 2 1 Arup, Sydney, NSW 2 North Queensland Bulk Ports, Mackay,

More information

MIKE 21/3 FLOW MODEL HD FM

MIKE 21/3 FLOW MODEL HD FM MIKE 21/3 FLOW MODEL HD FM 2D and 3D hydrodynamic modelling using flexible mesh DHI/Photo Simon Mortensen, DHI-AUK component will teach you the fundamentals of 2D and 3D hydrodynamic modelling (HD) and

More information

GEOTECHNICAL ENGINEERING CHALLENGES ON SOFT GROUND. For Myanmar Engineering Society 2012 CONTENTS

GEOTECHNICAL ENGINEERING CHALLENGES ON SOFT GROUND. For Myanmar Engineering Society 2012 CONTENTS GEOTECHNICAL ENGINEERING CHALLENGES ON SOFT GROUND For Myanmar Engineering Society 2012 G&P Professional Sdn Bhd (www.gnpgroup.com.my) By Engr. Dr. Gue See Sew (P.Eng) Engr. Dr. Wong Shiao Yun (G.Eng)

More information

Compressibility of Soil. Chapter 11

Compressibility of Soil. Chapter 11 Compressibility of Soil Chapter 11 TOPICS INTRODUCTION ELASTIC SETTLEMENT Stress distribution in soil masses CONSOLIDATION SETTLEMENT Fundamentals of consolidation Calculation of 1-D Consolidation Settlement

More information

Widening of Existing Bridge Abutments A Geotechnical Approach

Widening of Existing Bridge Abutments A Geotechnical Approach Widening of Bridge Abutments A Geotechnical Approach Michelle Phillipson, Jacobs, Australia ABSTRACT Widening of existing infrastructure is slowly becoming more commonplace but is not yet routine and requires

More information

Skirted Spudcan Sheet Pile Wall Interaction during Jack- Up Rig Installation and Removal in a Harbour Area

Skirted Spudcan Sheet Pile Wall Interaction during Jack- Up Rig Installation and Removal in a Harbour Area Skirted Spudcan Sheet Pile Wall Interaction during Jack- Up Rig Installation and Removal in a Harbour Area L. Kellezi GEO - Danish Geotechnical Institute 1 Maglebjergvej, DK 2800 Copenhagen, Denmark G.

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent

More information

THE FIRST CORE-LOC BREAKWATER. Anton H Holtzhausen'

THE FIRST CORE-LOC BREAKWATER. Anton H Holtzhausen' THE FIRST CORE-LOC BREAKWATER Anton H Holtzhausen' Abstract The first project in which Core-Locs were used as the main breakwater armour unit, is a small craft harbour on the south east coast of South

More information

BEHAVIOUR OF GEOTEXTILE REINFORCED STONE COLUMNS MANITA DAS, A.K.DEY ABSTRACT

BEHAVIOUR OF GEOTEXTILE REINFORCED STONE COLUMNS MANITA DAS, A.K.DEY ABSTRACT BEHAVIOUR OF GEOTEXTILE REINFORCED STONE COLUMNS MANITA DAS, A.K.DEY ABSTRACT Stone columns are being used to improve the bearing capacity and reduce the settlement of a weak or soft soil. The improvement

More information

Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION

Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION Earth retaining structures are designed to overcome significant variation in ground levels to provide either a sloping or flat ground on the retained

More information

4.6 Lightweight Treated Soil Method

4.6 Lightweight Treated Soil Method TECHNICAL STANDARDS AND COMMENTARIES FOR PORT AND HARBOUR FACILITIES IN JAPAN 4.6 Lightweight Treated Soil Method (1) Definition and Outline of Lightweight Treated Soil Method 1 The provisions in this

More information

B209 - EMBANKMENTS OVER SWAMPS AND COMPRESSIBLE SOILS - OPSS 209. Excavation method means to remove the swamp material mechanically.

B209 - EMBANKMENTS OVER SWAMPS AND COMPRESSIBLE SOILS - OPSS 209. Excavation method means to remove the swamp material mechanically. B209 - - OPSS 209 209.1 GENERAL Embankments over swamps and compressible soils/soft ground can be designed with one or a combination of the following alternatives: 1. Excavation Method 2. Floatation Method

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

SEEPAGE FLOW-STABILITY ANALYSIS OF THE RIVERBANK OF SAIGON RIVER DUE TO RIVER WATER LEVEL FLUCTUATION

SEEPAGE FLOW-STABILITY ANALYSIS OF THE RIVERBANK OF SAIGON RIVER DUE TO RIVER WATER LEVEL FLUCTUATION Geotech., Const. Mat. and Env., ISSN:2186-2982(P), 2186-2990(O), Japan SEEPAGE FLOW-STABILITY ANALYSIS OF THE RIVERBANK OF SAIGON RIVER DUE TO RIVER WATER LEVEL FLUCTUATION A. Oya 1, H.H. Bui 2, N. Hiraoka

More information

15. Coastal Defences. Executive Summary: Chapter 15. Coastal Defences

15. Coastal Defences. Executive Summary: Chapter 15. Coastal Defences 15. Coastal Defences Executive Summary: Chapter 15. Coastal Defences The potential direct and indirect impacts that will arise from the proposed Berth 201/202 works, either through the reconstruction of

More information

A Vacuum Consolidation Method Application Case for Improving Dredging Slurry

A Vacuum Consolidation Method Application Case for Improving Dredging Slurry A Vacuum Consolidation Method Application Case for Improving Dredging Slurry Liu Yu 1 Ph.D, Geoharbour Group, liuyu@geoharbour.com, CHINA Marcello Djunaidy 2 MT, Geotekindo PT, marcello@geotekindo.com,

More information

History of land reclamation using dredged soils at Tokyo Haneda Airport

History of land reclamation using dredged soils at Tokyo Haneda Airport Japanese Geotechnical Society Special Publication The 15th Asian Regional Conference on Soil Mechanics and Geotechnical Engineering History of land reclamation using dredged soils at Tokyo Haneda Airport

More information

American International Journal of Research in Science, Technology, Engineering & Mathematics

American International Journal of Research in Science, Technology, Engineering & Mathematics American International Journal of Research in Science, Technology, Engineering & Mathematics Available online at http://www.iasir.net ISSN (Print): 2328-3491, ISSN (Online): 2328-3580, ISSN (CD-ROM): 2328-3629

More information

Use of DMT for subsurface characterization: strengths and weaknesses

Use of DMT for subsurface characterization: strengths and weaknesses Use of DMT for subsurface characterization: strengths and weaknesses Hai-Ming Lim Burgess Engineering and Testing, Inc., Moore, Oklahoma, USA Musharraf Zaman School of Civil Engineering and Environmental

More information

CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1

CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1 CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1 ABSTRACT From March 2012 until September 2014, the international port of Tanjung Priok in

More information

Geotechnical Solutions for High Speed Track Embankment A Brief Overview

Geotechnical Solutions for High Speed Track Embankment A Brief Overview Geotechnical Solutions for High Speed Track Embankment A Brief Overview Ir. Dr. Gue See Sew Managing Director, Gue & Partners Sdn Bhd & Ir. Tan Yean Chin Associate Director, Gue & Partners Sdn Bhd ABSTRACT:

More information

PVD Ground Improvement System

PVD Ground Improvement System eau eau CeTeau stands for innovative ground improvement technologies with Prefabricated Vertical Drains. Prefabricated Vertical Drains (PVD), also called Wick Drains, are prefabricated drain strips consisting

More information

CHAPTER 5 - RUBBLE-MOUND STRUCTURES SECTION 1. STRUCTURAL COMPONENTS

CHAPTER 5 - RUBBLE-MOUND STRUCTURES SECTION 1. STRUCTURAL COMPONENTS CHAPTER 5 - RUBBLE-MOUND STRUCTURES SECTION 1. STRUCTURAL COMPONENTS 5.1.1 MOUND. A mound is an artificial embankment or ridge composed of sand, gravel, and cobbles, constructed on the oceanic floor by

More information

EFFECT OF SOIL CEMENT COLUMN SPACING AND AREA REPLACEMENT RATIO ON EMBANKMENT BEARING CAPACITY: A QUEENSLAND CASE STUDY

EFFECT OF SOIL CEMENT COLUMN SPACING AND AREA REPLACEMENT RATIO ON EMBANKMENT BEARING CAPACITY: A QUEENSLAND CASE STUDY Geotec., Const. Mat. & Env., ISSN: 2186-2982(Print), 2186-299(Online), Japan EFFECT OF SOIL CEMENT COLUMN SPACING AND AREA REPLACEMENT RATIO ON EMBANKMENT BEARING CAPACITY: A QUEENSLAND CASE STUDY Mark

More information

UNBRACED PIPE TRENCH STIFF FISSURED CLAY LAYER ON SOFT CLAY

UNBRACED PIPE TRENCH STIFF FISSURED CLAY LAYER ON SOFT CLAY UNBRACED PIPE TRENCH STIFF FISSURED CLAY LAYER ON SOFT CLAY Kari Christer Avellan, Helsinki Finland pcs INTRODUCTION year Figure 1. Statistics of deadly accidents in trenches in Finland. Research concerning

More information

Shoreline Erosion. How Erosion Occurs

Shoreline Erosion. How Erosion Occurs How Erosion Occurs Shoreline Erosion When a 3 metre (10 feet) high shoreline bank erodes, it may look as if the entire height of bank is eroding. In reality, it is only the toe of the bank that is, the

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

HRPP 348. Update of the manual on the use of rock in hydraulic engineering ( The Rock Manual ) Kirsty McConnell, Jonathan Simm & Marianne Scott

HRPP 348. Update of the manual on the use of rock in hydraulic engineering ( The Rock Manual ) Kirsty McConnell, Jonathan Simm & Marianne Scott HRPP 348 Update of the manual on the use of rock in hydraulic engineering ( The Rock Manual ) Kirsty McConnell, Jonathan Simm & Marianne Scott Reproduced from a paper published in: Proceedings of the 40th

More information

Investigation of Pile Capacity in Mongla Sub-Soil

Investigation of Pile Capacity in Mongla Sub-Soil Paper ID: GE-22 International Conference on Recent Innovation in Civil Engineering for Sustainable Development () Department of Civil Engineering DUET - Gazipur, Bangladesh 460 Investigation of Pile Capacity

More information

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 9

More information

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment MATEC Web of Conferences 11, 03006 ( 2014) DOI: 10.1051/ matecconf/ 20141103006 C Owned by the authors, published by EDP Sciences, 2014 Study of Various Techniques for Improving Weak and Compressible Clay

More information

Behaviour of a Highway Embankment on Stone Columns Improved Estuarine Clay

Behaviour of a Highway Embankment on Stone Columns Improved Estuarine Clay Behaviour of a Highway Embankment on Stone Columns Improved Estuarine Clay Author Oh, Erwin, Balasubramaniam, Bala, Surarak, Chanaton, Bolton, Mark, Chai, Gary, Huang, Min, Braund, M. Published 27 Conference

More information

EuroGeo4 Paper number 260 INNOVATIVE APPLICATIONS OF GEOGRIDS AS TIE-BACK ANCHORS FOR VERTICAL WALLS

EuroGeo4 Paper number 260 INNOVATIVE APPLICATIONS OF GEOGRIDS AS TIE-BACK ANCHORS FOR VERTICAL WALLS INNOVATIVE APPLICATIONS OF GEOGRIDS AS TIE-BACK ANCHORS FOR VERTICAL WALLS Oliver Detert 1, Edi Wehrli 2 & AlexanderCejka 3 1 Huesker Synthetic GmbH. (e-mail: detert@huesker.de) 2 Schoellkopf AG, Switzerland.

More information

(Refer Slide Time: 04:08)

(Refer Slide Time: 04:08) Soil Mechanics Prof. B.V.S. Viswanathan Department of Civil Engineering Indian Institute of Technology, Bombay Lecture 27 Flow of water through soils-viii Welcome to lecture number eight of flow of water

More information

GEOGRID BASAL REINFORCEMENT FOR CONSTRUCTION OF EMBANKMENT ON SOFT SOIL

GEOGRID BASAL REINFORCEMENT FOR CONSTRUCTION OF EMBANKMENT ON SOFT SOIL GEOGRID BASAL REINFORCEMENT FOR CONSTRUCTION OF EMBANKMENT ON SOFT SOIL Moreno Scotto, International Manager, Geosynthetics Business Unit, Officine Maccaferri s.pa, Italy. ing.mscotto@fastwebnet.it Prashant

More information

Construction and Geotechnical Issues

Construction and Geotechnical Issues AECOM port project images here Original must be proportionate to 25.4cm x 8cm Image here Original must be square Image here Original must be square Image here Original must be square Construction and Geotechnical

More information

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD FOR NCIG CET3 COAL STOCKYARD Charles CH Chua 1, Ming Lai 2, Graeme Hoffmann 2 and Brett Hawkins 1 1 Connell Hatch, Australia, 2 Keller Ground Engineering Pty Ltd ABSTRACT This paper presents an overview

More information

Inclusion Effect on Heterogeneity of Excess Pore Water Pressure Distribution in Composite Clay

Inclusion Effect on Heterogeneity of Excess Pore Water Pressure Distribution in Composite Clay Inclusion Effect on Heterogeneity of Excess Pore Water Pressure Distribution in Composite Clay J. Jalili Payame Noor University, Iran M. K. Jafari & A. Shafiee International Institute of Earthquake Engineering

More information

1 Introduction CIRIA C683 1

1 Introduction CIRIA C683 1 1 Introduction 1 3 5 7 9 CIRIA C3 1 1 Introduction CHAPTER 1 CONTENTS 1.1 Use of rock...................................................... 3 1. Background to the manual.........................................

More information

CROWN-WALL WITH EXTENDED BASE SLAB

CROWN-WALL WITH EXTENDED BASE SLAB CROWN-WALL WITH EXTENDED BASE SLAB Ing. Ineke Vos-Rovers MSc (Eng.) 1, Ir. Bas Reedijk 1, Ing. Sjaak Ekelmans 2 This paper presents the design philosophy and the construction stages of a n6n-standard crown-wall

More information

Lincoln Road Corridor Improvements Geotechnical Assessment Report

Lincoln Road Corridor Improvements Geotechnical Assessment Report Geotechnical Assessment Report Prepared for Auckland Transport December 2015 Status: Draft Project number: Page 1 Our ref: Word - Report Cover This document has been prepared for the benefit of Auckland

More information

The planned conversion of part of the Port of

The planned conversion of part of the Port of South Port of Copenhagen: Clean-up of Contaminated Sediments NIELS LYKKEBERG & HELGE GRAVESEN, Carl Bro a/s, Glostrup, Denmark KAJ HOLM JØRGENSEN, Port of Copenhagen, Denmark A BSTRACT The planned conversion

More information

Estimation of in-situ water content, void ratio, dry unit weight and porosity using CPT for saturated sands

Estimation of in-situ water content, void ratio, dry unit weight and porosity using CPT for saturated sands Barounis, N. & Philpot, J. (217) Estimation of in-situ water content, void ratio, dry unit weight and porosity using CPT for saturated sands Proc. 2 th NZGS Geotechnical Symposium. Eds. GJ Alexander &

More information

Foundation Engineering CE Introduction. Prof. H. Alawaji. Room No. 2A- 47/1, Tel

Foundation Engineering CE Introduction. Prof. H. Alawaji.   Room No. 2A- 47/1, Tel Foundation Engineering CE 483 1. Introduction Prof. H. Alawaji Email: alawaji@ksu.edu.sa Room No. 2A- 47/1, Tel. 01-46- Contents Introduction Course General Information Prior Knowledge required for the

More information

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities Acoustic Decoupling Measures Plan 12 September 2012 Main

More information

Review and Feasibility Assessment of Offshore Ground Improvement Methods

Review and Feasibility Assessment of Offshore Ground Improvement Methods Review and Feasibility Assessment of Renmin Zhang, Postgraduate Student AOG 2017 Background Final semester study project (6 months) Course completion fulfillment Master of Subsea Engineering (MC-SBSENG)

More information

Introduction to Foundations on Fill and Backfilling

Introduction to Foundations on Fill and Backfilling Introduction to Foundations on Fill and Backfilling Course No: G01-003 Credit: 1 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court

More information

Land Subject to Coastal Storm Flowage

Land Subject to Coastal Storm Flowage Land Subject to Coastal Storm Flowage Rebecca Haney Coastal Geologist MCZM Lealdon Langley Wetlands & Waterways MassDEP Definitions/Terminology Land subject to coastal storm flowage: means land subject

More information

Distribution Restriction Statement

Distribution Restriction Statement DEPARTMENT OF THE ARMY CECW-ED U.S. Army Corps of Engineers CECW-EG Washington, DC 20314-1000 ETL 1110-2-352 Technical Letter No. 1110-2-352 31 March 1994 Engineering and Design STABILITY OF GRAVITY WALLS

More information

The Bearing Capacity of Soils. Dr Omar Al Hattamleh

The Bearing Capacity of Soils. Dr Omar Al Hattamleh The Bearing Capacity of Soils Dr Omar Al Hattamleh Example of Bearing Capacity Failure Omar Play the move of bearing Capacity failure The Philippine one Transcona Grain Silos Failure - Canada The Bearing

More information

Uncertainties of Smear Zone Characteristics in the Design of Preloading with Prefabricated Vertical Drains

Uncertainties of Smear Zone Characteristics in the Design of Preloading with Prefabricated Vertical Drains Uncertainties of Smear Zone Characteristics in the Design of Preloading with Prefabricated Vertical Drains A. Parsa Pajouh 1,*, B. Fatahi 1, and H. Khabbaz 1 1- School of Civil and Environmental Engineering,

More information

Suitability of Different Materials for Stone Column Construction

Suitability of Different Materials for Stone Column Construction Suitability of Different Materials for Stone Column Construction Dipty Sarin Isaac and Girish M. S. Department of Civil Engineering College of Engineering, Trivandrum, Kerala diptyisaac@yahoo.com, girishmadhavan@yahoo.com

More information

A successful trial of vacuum consolidation at the Port of Brisbane

A successful trial of vacuum consolidation at the Port of Brisbane A successful trial of vacuum consolidation at the Port of Brisbane Daniel Berthier 1, Peter Boyle 2, J Ameratunga 3, Cynthia De Bok 3 and Philippe Vincent 1 1 Austress-Menard, Macquarie Park, NSW, Australia

More information

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG. MEMORANDUM Levelton Consultants Ltd. 150-12791 Clarke Place Richmond, BC V6V 2H9 Canada Tel: 604 278-1411 Fax: 604 278-1042 E-Mail: rhillaby@levelton.com Web Site: www.levelton.com TO: STUART OLSON DOMINION

More information

Engineering Properties of Soft Organic Soil Underlying Dredge Fill Areas of Dhaka, Bangladesh

Engineering Properties of Soft Organic Soil Underlying Dredge Fill Areas of Dhaka, Bangladesh Engineering Properties of Soft Organic Soil Underlying Dredge Fill Areas of Dhaka, Bangladesh Md. Anisuzzaman, and Arifuzzaman Abstract Over the past 45 years, Dhaka city has experienced a rapid growth

More information

NUMERICAL STUDY OF OFFSHORE SKIRTED FOUNDATIONS SUBJECTED TO COMBINED LOADING

NUMERICAL STUDY OF OFFSHORE SKIRTED FOUNDATIONS SUBJECTED TO COMBINED LOADING NUMERICAL STUDY OF OFFSHORE SKIRTED FOUNDATIONS SUBJECTED TO COMBINED LOADING S.K. NAIK 1, S.M. DASAKA 2, and V.B. CHAUHAN 3 1 Former Post Graduate Student, Department of Civil Engineering, Indian Institute

More information

Land Subject to Coastal Storm Flowage

Land Subject to Coastal Storm Flowage Land Subject to Coastal Storm Flowage Rebecca Haney Coastal Geologist MCZM Lealdon Langley Wetlands & Waterways MassDEP Why do we need these regs? Prevent/reduce flood damage, decrease repetitive loss

More information

TENCATE MIRAFI RSi MULTIFUNCTIONAL WOVEN GEOTEXTILES

TENCATE MIRAFI RSi MULTIFUNCTIONAL WOVEN GEOTEXTILES TENCATE MIRAFI RSi MULTIFUNCTIONAL WOVEN GEOTEXTILES IDEAL FOR TEMPORARY ACCESS ROADS Mirafi RSI is designed to maximise use of site -won materials in temporary roads, haul roads and site access road construction.

More information

GEOGRID REINFORCED RAILWAYS EMBANKMENTS: DESIGN CONCEPTS AND EXPERIMENTAL TEST RESULTS

GEOGRID REINFORCED RAILWAYS EMBANKMENTS: DESIGN CONCEPTS AND EXPERIMENTAL TEST RESULTS GEOGRID REINFORCED RAILWAYS EMBANKMENTS: DESIGN CONCEPTS AND EXPERIMENTAL TEST RESULTS Filippo Montanelli Engineer Sales Director - Geosynthetics Division TENAX Spa, Viganò (Lecco) - Italy Filippo Montanelli,

More information

Back Analyses and Performance of Semi Top-Down Basement Excavation of 11m Deep in Sandy Alluvial Deposits overlying Kenny Hill Formation in Malaysia

Back Analyses and Performance of Semi Top-Down Basement Excavation of 11m Deep in Sandy Alluvial Deposits overlying Kenny Hill Formation in Malaysia Back Analyses and Performance of Semi Top-Down Basement Excavation of 11m Deep in Sandy Alluvial Deposits overlying Kenny Hill Formation in Malaysia S. S. Liew & S. J. Gan G&P Geotechnics Sdn Bhd, Wisma

More information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical

More information

Material properties of Tailings from Swedish mines

Material properties of Tailings from Swedish mines Material properties of Tailings from Swedish mines I. Jantzer Luleå University of Technology, Sweden, Isabel.Jantzer@ltu.se A. Bjelkevik Sweco AB, Sweden, Annika.Bjelkevik@sweco.se K. Pousette Luleå University

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

2012 Soil Mechanics I and Exercises Final Examination

2012 Soil Mechanics I and Exercises Final Examination 2012 Soil Mechanics I and Exercises Final Examination 2013/1/22 (Tue) 13:00-15:00 Kyotsu 155 Kyotsu 1 Kyotsu 3 W2 Lecture room Attention: There are four questions and four answer sheets. Write down your

More information

DAMAGE ON DEEP, MULTI-TIED-BACK EXCAVATION DUE TO DEFORMATION OF THE ANCHOR-SOIL BLOCK SYSTEM

DAMAGE ON DEEP, MULTI-TIED-BACK EXCAVATION DUE TO DEFORMATION OF THE ANCHOR-SOIL BLOCK SYSTEM DAMAGE ON DEEP, MULTI-TIED-BACK EXCAVATION DUE TO DEFORMATION OF THE ANCHOR-SOIL BLOCK SYSTEM H.-G. Kempfert 1, Berhane Gebreselassie 2, M. Raithel 3 ABSTRACT: Despite the knowledge and experiences accumulated,

More information

Evaluation of safe bearing capacity of soil foundation by using numerical analysis method

Evaluation of safe bearing capacity of soil foundation by using numerical analysis method Focussed on: Fracture and Structural Integrity related Issues Evaluation of safe bearing capacity of soil foundation by using numerical analysis method Abdoullah Namdar, Xiong Feng Western China Earthquake

More information

Lecture 7 BALLAST & SUBGRADE. Dr. Charisma Choudhury. April 2011

Lecture 7 BALLAST & SUBGRADE. Dr. Charisma Choudhury. April 2011 Transportation Engineering II: Highway Design & Railways Lecture 7 BALLAST & SUBGRADE Dr. Charisma Choudhury April 2011 Ballast Functions Provide a hard and level bed for sleepers Hold sleepers in place

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad -00 03 CIVIL ENGINEERING QUESTION BANK Course Name : GROUND IMPROVEMENT TECHNIQUES Course Code : A012 Class : III B. Tech IISemester

More information

Numerical Simulation of Liquefaction Deformation of Sand Layer around Bucket Foundations under Dynamic Loadings

Numerical Simulation of Liquefaction Deformation of Sand Layer around Bucket Foundations under Dynamic Loadings The Open Ocean Engineering Journal, 2010, 3, 75-81 75 Open Access Numerical Simulation of Liquefaction Deformation of Sand Layer around Bucket Foundations under Dynamic Loadings Chi Li 1,*, Xiaobing Lu

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01

More information

WORK PROGRAMME on CO-OPERATION IN THE FIELD OF CLIMATE CHANGE VULNERABILITY, RISK ASSESSMENT, ADAPTATION AND MITIGATION Between THE MINISTRY OF

WORK PROGRAMME on CO-OPERATION IN THE FIELD OF CLIMATE CHANGE VULNERABILITY, RISK ASSESSMENT, ADAPTATION AND MITIGATION Between THE MINISTRY OF WORK PROGRAMME on CO-OPERATION IN THE FIELD OF CLIMATE CHANGE VULNERABILITY, RISK ASSESSMENT, ADAPTATION AND MITIGATION Between THE MINISTRY OF SCIENCE, TECHNOLOGY AND ENVIRONMENT OF THE REPUBLIC OF CUBA

More information

ITEM 750 ROCK FILTER DAMS

ITEM 750 ROCK FILTER DAMS AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction

More information

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN STEEL PIPE PILES OF FOUNDATIONS FOR HIGHWAY BRIDGES Kouichi TOMISAWA, Civil Engineering Research Institute of Hokkaido, Japan Satoshi NISHIMOTO,

More information

Reinforced Soil Slopes (RSS)

Reinforced Soil Slopes (RSS) Supplemental Technical Specification for Reinforced Soil Slopes (RSS) SCDOT Designation: SC-M-206-1 (4/16) 1.0 DESCRIPTION 1.1 Construct a reinforced soil slope in accordance with these specifications,

More information