CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA)

Size: px
Start display at page:

Download "CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA)"

Transcription

1 CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA) Siegmund Schlie*, Bernd Opfermann** and Torsten Retzlaff*** * Heinrich Hirdes GmbH, Rostock ** b & o - Ingenieure, Hamburg *** Inros Lackner AG, Rostock Abstract: Near the village Boltenhagen on the German Baltic Sea Coast in 1934 an artificial peninsula was created to make tests with seaplanes. After the Second World War this place became a navy base of the East German Navy until In October 2006 the change of this area started. A modern hotel and holiday apartment combination for at most 930 people has been built, which includes a marina for about 290 boats. This marina will complete the net of boat harbours at the German Baltic Coast. At first an enormous quantity of old concrete structures had to be eliminated and recycled to material for road building. At a length of more than 1000 m the shore line had to be protected by different structures. About 650 m shoreline was secured by a combination of sheet pile wall, revetment and concrete walls for high water protection. The other part of shore line was protected by rock armour in combination with a concrete wall against high water. The space between the revetments and the concrete walls will be used as a promenade. The new marina consists of a water area of 100,000 m² with water depth up to 6.00 m. The sea side has been protected by 2 breakwaters with a total length of about 1000 m. These breakwaters were founded partly on soft subsoil and constructed with different types of geotextile, gravel sand as well as rock armour. Following the requirements for German coastal structures the top of the breakwaters has been carried out at 3.50 m above medium sea level. The different kinds of shore line protection were designed by two consultants. The paper will show the requirements and technical solutions in design and execution of work. The design of breakwaters had been changed by the contractor to find a more economic solution for the client. Design and execution of this project phase will be explained. I. INTRODUCTION Boltenhagen is a village at the Baltic Sea, situated between Wismar and Luebeck. More than 70 years ago an artificial peninsula was built by reclamation works and named Tarnewitz. It had been used for military as a testing field for special airplanes. The shore line protection of this peninsula consisted of sheet pile walls combined with revetments of boulders collected in the Baltic. After the Second World War this area was partly used by the East German Army as a navy base for small fast vessels to observe the border between the eastern and western block during the Cold War Period until This navy base was protected by a concrete wall and small breakwaters made of wooden piles and boulders as well as rock armour. The majority of the military area has not been reconstructed. After the German unification, from 1990 till 2005, the complete peninsula with its bunkers, subsoil tanks, houses and shore protection had been allowed to fall into ruin. A security service had to watch all the time to this dangerous area. One part of the peninsula became a natural reserve, but the former navy base was bought by an investor in This area, about 400,000 m² at the land side and about 100,000 m² at the sea side were taken over completely with all old structures, ammunition and environmental problems. A long permit procedure was needed to reach the goal, installing of a special recreation centre with marina. Such a centre had to be founded at a place where is no danger of high water caused by storm floods in the Baltic Sea. From October 2006 till April 2008 the new recreation complex called "Weisse Wieck" was built. Behind a more then 1000 m new shoreline protection the investors created a hotel with

2 rooms and an apartment hotel especially for families with about 400 beds. Two new breakwaters give the right protection to a marina for about 290 boats, a fishery port for 15 fishing boats and berth pockets for 2 small passenger ships. The location of "Weisse Wieck" recommended special measures of high water protection, because it is situated in front of the dike line. A new structure for coastal protection had to be built and the responsibility of maintenance the owner of that area had to take over. The wish of the owner was it to combine high water protection with a promenade and a marina. Different designers prepared all the necessary documents and drawings to get the building permits and to make a public tender process. There was a requirement for public tendering because the shoreline protection and the breakwaters for the marina were co-financed by the county government of Mecklenburg Vorpommern. In this paper we want to explain something about design and execution of works for the shoreline protection and the breakwaters. Figure 1. Sheet pile wall with anchor, flood protection, and promenade II. SHORELINE PROTECTION A. Design and Execution of Inside Marina Protection The main parts that had to be designed and executed were the follows: High water protection wall made from precast concrete parts Sheet pile wall with anchors and concrete arbor in the area of berth pockets for boats partly in front of an old sheet pile wall Revetment with sheet pile wall Rebuilding of several old concrete structures Retaining wall made by precast concrete elements Two-stage stairways by precast concrete elements Several movements of big soil quantities and preparing the placed soil for other works had to be designed and done as well. The old harbour basin had been existed on water depths of about 6.00 m below medium sea level. This fact was useful for the new marina, but it caused stronger sheet piles and anchors. The special requirements had been the combination of the sheet pile wall with the other elements of the new structure for flood protection and functionally with promenade (see Fig.1). In the other part of the marina and fishery harbour soil has to be dredged up to 3.60 m below medium sea level. Here the sheet pile wall led to 30 cm below the water level and a revetment protects the lower areas under the promenade. Details are shown in Figure 2. Figure 2. Sheet pile wall with revetment, flood protection and promenade The sheet pile wall was driven by vibration and partly by an IHC S-35 hydraulic hammer. The anchoring of this wall was made by drilling anchors pressed with concrete. The revetment was placed at a geotextile filter and consisted of a filter layer of natural rock (density 2.70 kg/dm³, thickness 0.30 m, size 80 mm to 150 mm) and an armour layer of natural rock (same density, thickness 0.65 m, weight 10 kg to 40 kg). The rock had been supplied by self discharging vessels from Norwegian quarries, handled to the land side and placed by hydraulic grabs. The precast concrete elements were placed at a concrete bed. There were particular requirements for the quality of concrete. The joints between the elements were sealed by special synthetic material. All together the following materials had to be built in to the shoreline protection inside the marina: 950 t sheet piles 91 drilled anchors 360 m³ monolithic concrete 2500 t rock 680 pieces precast concrete elements with a medium weight of 5 t. The design was made by b & o Ingenieure Hamburg / Rostock. The works had been executed 97

3 by a Joint Venture of Heinrich Hirdes GmbH Rostock and Colcrete -von Essen GmbH & co. KG Rastede. B. Design and Execution of the Outside Marina Protection The North Eastern part of the shore line protection required a stronger structure, because North East is the most dangerous wind direction combined with the highest water levels and waves in this part of the Baltic Sea. This piece of the area would not be protected by any breakwater. The following parts of the structure and works had to be designed and executed (see Fig. 3): Removal of the old revetment and other constructions New heavy revetment Retaining walls for storm flood protection and stabilization of the revetment made of monolithic concrete Movements of soil for slope profiling and filling. Figure 3. North Eastern shore line protection Revetment with flood protection wall and promenade The old shore protection construction consisted of a sheet pile wall, which was at the top corroded and a revetment of boulders and rock armour. Old destroyed concrete constructions were situated close to the revetment on the land side. The corroded part of the old sheet pile wall had to be cut, boulders and rock armour had to be stored for the new revetment and old concrete had to be recycled for site way improvement and road building. The retaining wall at the land side reduces finally splash water and wave overtopping for all the buildings of the apartment hotel. The top level of this wall had to be built constant at HN m. The design water level had been determined according the general arrangement plan for coastal protection of Mecklenburg Vorpommern at HN m and a medium overtopping quantity of about 5.0 l/s per running meter had been accepted. Significant wave hight was determined at 0.9 m for the Northern protection structure. The surface of the retaining wall had to be carried out as fair faced concrete. There were several requirements for the quality of the concrete and the design of the surface of the concrete. Another retaining wall bordered the promenade to the revetment on the sea side. The top level of this wall was defined at HN m to make dewatering of the promenade possible. Both walls had to be made from monolithic concrete C 30/37. The revetment was placed at a profiled slope and consists of the following elements: Filter layer of natural rock density 2.70 kg/dm³, medium weight 175 kg, layer thickness 0.40 m Armour layer of natural rock same density, medium weight 1750 kg, layer thickness 1.75 m, partly use of the old stored rock material. The geotextile was placed by hydraulic excavator with a long reach stick and special handling equipment. The rock had been supplied by self discharging vessels for small rock and big barges for the armour rock from Norwegian quarries, handled to the land side and placed by hydraulic grabs. For the shoreline protection outside the marina the following materials were built in to the structure: 26,000 t rock 9,000 m² geotextile filter 700 m³ monolithic concrete The design for this part of shoreline protection was made by Inros Lackner AG Rostock. The works were executed by the Joint Venture Hirdes / Colcrete as well. III. BREAKWATER SYSTEM A. Design The main part of marine construction the breakwater system had been. It is a specialty to combine a recreation resort with a marina and a small fishery port. Two breakwaters have to protect the marina, the fishery port as well as the hotel building. They were designed for overtopping and overflowing of the crest and have to reduce wave movements in general in this area. The following waves could be accepted inside the harbour, if there would be a high water level of HN m (according PIANC recommendation 1995): Eastern harbour area for small passenger ships about 0.4 m Western harbour area for sailing boats about 0.2 m. On the crest of the breakwaters no way was planned. Layout and length of the breakwaters had been checked by analysis of diffraction. Design high water level was determined at HN m. The significant wave hights had been estimated at 2.20 m for the Eastern breakwater and 1.60 m for the 98

4 Western. The fairway for the harbour entrance was required with a width of 33 m and medium water depth of 3.50 m. The following parts of the breakwater system had to be designed and executed: Partly demolition and integration of the old wave protection structure into the new Eastern breakwater New Eastern breakwater New Western breakwater Berth pockets for some fishery boats. Rebuilding of on old breakwater and using the rock for different layers of the new structure The breakwaters had been designed in general as conventional rubble mound breakwaters. Fig. 4 shows all the elements and layers of the Eastern breakwater such as: Sinking mattress to lead to evenly settlements of the soft sub soil in some parts of the Eastern breakwater Filling and part of the core made of gravel and sand Core material 0.5 kg to 50 kg natural rock, density 2.7 kg/dm³ Filter layer natural rock, same density, weight 60kg to 300 kg, layer thickness 0.80 m Armour layer natural rock, same density, weight 1 t to 3 t, layer thickness 1.75 m Width of the crest 2.4 m. The loads for the Western breakwater were determined much lower then for the Eastern. The Western Breakwater consists of the following element and layers: Partly core material of gravel and sand Core material natural rock 0.5kg to 50 kg, density 2.7 kg/dm³ Filter layer natural rock, same density, weight 40 kg to 200 kg. layer thickness 0.60 m Armour layer natural rock, same density, weight 0.5 t to 1.5 t, layer thickness 1.35 m Width of the crest 1.9 m. Figure 4. Cross section of Eastern breakwater The original design was made by Inros Lackner AG Rostock. But the contractor, again the Joint Venture Heinrich Hirdes GmbH Rostock / Colcrete von Essen GmbH & Co. KG Rastede, changed the design partly, because the client had some budget problems and had asked the contractor for some practical ideas to save costs. The proposal of the contractor included to substitute some core rock material by gravel and sand and to cover this completely by a geotextile filter (sand mattress). Additional sand slopes in deep water had to be protected by rock furthermore. The client accepted the contractors proposal and had saved more then 1.5 million costs. The adaptation of the execution design had been carried out by designers of the contractor. The main advantage of the gravel and sand had been in the logistics. Marine gravel and sand borrow pits were situated only 30 km from the building site. The sailing distance to the rock quarries in Norway had been more than 800 km. This advantage had led to a shorter construction period for the core as well. B. Execution The execution of all works had started with the partly demolition of the old protection constructions. The old structures had been rebuilt up to 0.3 m under the level of the new filter layer. Boulders and rock armour were stored for the use in the new filter and armour layer. A part of the Eastern breakwater had to be founded at mud layers between 0.6 m and 1.8 m. Special sinking mattresses should lead to evenly settlements of the breakwater. The mud had been replaced mostly by the cheaper gravel and sand material. The sinking mattress was made of a combination of woven and non woven geotextile fitted out with in square placed fasces of pasturage. The prefabricated mattresses had a size up 35 m by 60 m and had been placed by special equipment. The gravel and sand core and filling material had been dredged by a small Trailing Suction Hopper Dredger with about 1,500 m³ hopper volumes, transported to the site and sprayed via a spraying pontoon in to the right place. Later a backhoe dredger had profiled the gravel sand surface. After that the geotextile sand mattress had been placed by a floating cable grab and other special 99

5 equipment. Core rock material covered the geotextile to protect it against the more heavy rock of the filter layer. The core material was supplied by self discharching vessels from Norwegian quarries, which loaded barges for the site transport. Hydraulic grabs based on pontoons had placed this material into the right profiles supported by computer based monitoring systems. The filter and armour layers had been supplied by an 8,000 t barge from Larvik in Norway. Site transport was organised by smaller barges. The under water profile had been carried out by hydraulic grabs based on pontoons. The crest had been profiled by a hydraulic grab based on the breakwaters. All the works required a high accuracy especially because the four different layer profiles and several changing of the water depth, which caused some crossover of the profiles. Totally the following materials had been placed in to the both breakwaters: 45,000 m³ gravel and sand 160,000 t rock 30,000 m² geotextile filter 9,000 m² sinking mattresses 60 pieces wooden piles as a pier construction for the fishery boats 6 steel piles for small passenger ships The very hard time schedule for a winter time project had been implemented in time. Dedicated designers and site managers as well as experienced operators on board of all the used equipment had cooperated with the client very well and all together they made this project to a success. This project is a very good example to change old military constructions into peaceful utilisations. 100

Breakwater on Soft Subsoil Problems of Design and Execution

Breakwater on Soft Subsoil Problems of Design and Execution Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Breakwater on Soft Subsoil Problems of Design and Execution Siegmund Schlie

More information

Special Building Method for a Storm Tide Protection Construction on the Baltic Sea Coast

Special Building Method for a Storm Tide Protection Construction on the Baltic Sea Coast Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Special Building Method for a Storm Tide Protection Construction on the

More information

PIANC Commission Working Group Report Reviews

PIANC Commission Working Group Report Reviews PIANC Commission Working Group Report Reviews EnviCom Working Group report details Initial review: conclusion * If identified as potentially sensitive, please highlight the particular areas of potential

More information

SoilTain Coastal Protection Tubes. Geosynthetic Container System for Coastal and Bank Protection

SoilTain Coastal Protection Tubes. Geosynthetic Container System for Coastal and Bank Protection SoilTain Coastal Protection Tubes Geosynthetic Container System for Coastal and Bank Protection 2 3 Geosynthetic Tube System The All-Rounder for Coastal and Bank Protection The effects of global climate

More information

15. Coastal Defences. Executive Summary: Chapter 15. Coastal Defences

15. Coastal Defences. Executive Summary: Chapter 15. Coastal Defences 15. Coastal Defences Executive Summary: Chapter 15. Coastal Defences The potential direct and indirect impacts that will arise from the proposed Berth 201/202 works, either through the reconstruction of

More information

CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1

CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1 CONSTRUCTION OF THE BREAKWATER USING BAMBOO PILE AND BAMBOO MATTRESS AS FOUNDATION MATERIAL Ryusuke Tsutsumi 1 ABSTRACT From March 2012 until September 2014, the international port of Tanjung Priok in

More information

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment Appendix 8: Best Practicable Environmental Option (BPEO) Assessment ABERDEEN HARBOUR EXPANSION PROJECT BEST PRACTICABLE ENVIRONMENTAL OPTION (BPEO) ASSESSMENT October 2015 Updated April 2016 TABLE OF CONTENTS

More information

8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES. COPEDEC 2012, IIT Madras, Chennai, INDIA Feb.

8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES. COPEDEC 2012, IIT Madras, Chennai, INDIA Feb. 8 th INTERNATIONAL CONFERENCE ON COASTAL AND PORT ENGINEERING IN DEVELOPING COUNTRIES COPEDEC 2012, IIT Madras, Chennai, INDIA. 20-24 Feb. 2012 Case Studies and Lessons Learnt from Applications of Sand

More information

Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring.

Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring. Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring. Ad Stolk and Chris Dijkshoorn Ministry of Transport, Public Works and Water Management Rijkswaterstaat North

More information

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Guidelines for environmental impacts of vessels InCom

More information

Hydraulic engineering

Hydraulic engineering Hydraulic engineering From wet dredging to strengthening the canal bed Hydraulic engineering work is of great international importance to the family-run business Felbermayr. Our rapidly expanding division

More information

Where the Ocean Meets Land. Coastal Engineering

Where the Ocean Meets Land. Coastal Engineering Where the Ocean Meets Land Coastal Engineering Photo credit : Rio Tinto Alcan Our Expertise MARINAS AND HARBOURS Design and repair of breakwaters Sedimentation and dredging studies Navigation guidelines

More information

Harbour & Coastal PART 8 PLANNING REPORT WATERFORD CITY AND COUNTY COUNCIL ARDMORE BEACH COAST PROTECTION FOR. July Malachy Walsh and Partners

Harbour & Coastal PART 8 PLANNING REPORT WATERFORD CITY AND COUNTY COUNCIL ARDMORE BEACH COAST PROTECTION FOR. July Malachy Walsh and Partners Harbour & Coastal Malachy Walsh and Partners Consulting Engineers Cork Tralee Limerick London PART 8 PLANNING REPORT ARDMORE BEACH COAST PROTECTION PART 8 PLANNING REPORT FOR WATERFORD CITY AND COUNTY

More information

PORT OF PORT TOWNSEND. Point Hudson Marina Breakwater Preliminary Design

PORT OF PORT TOWNSEND. Point Hudson Marina Breakwater Preliminary Design PORT OF PORT TOWNSEND Point Hudson Marina Breakwater Preliminary Design December 5, 2014 1 Outline Project Status (Scopes of Work, To-Do List from Conceptual Design) Existing Conditions Alternative Evaluation

More information

Appendix H. Proposed Shoreline Improvements

Appendix H. Proposed Shoreline Improvements Appendix H Proposed Shoreline Improvements This page intentionally left blank. Parcel or Area North Shore East Shore South Shore Location Proposed Use Existing Shoreline Conditions Proposed Improvement

More information

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC MARINE WORKS shafaconstruction.com SHAFA AL NAHDAH SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC Al Manara Tower, ETA Star 23rd Floor, Office no. 2302-04, Business Bay, P.O. Box 252050

More information

SoilTain Bags. Bags for Erosion Control and Scour Protection

SoilTain Bags. Bags for Erosion Control and Scour Protection SoilTain Bags Bags for Erosion Control and Scour Protection Overview of a typical SoilTain Bag construction site The SoilTain Bag system Bags provide an efficient and economic solution for erosion and

More information

THE FIRST CORE-LOC BREAKWATER. Anton H Holtzhausen'

THE FIRST CORE-LOC BREAKWATER. Anton H Holtzhausen' THE FIRST CORE-LOC BREAKWATER Anton H Holtzhausen' Abstract The first project in which Core-Locs were used as the main breakwater armour unit, is a small craft harbour on the south east coast of South

More information

CONSTRUCTION OF A PERIMETER BUND USING THE PRE-MIXED (PM)-CLAY METHOD

CONSTRUCTION OF A PERIMETER BUND USING THE PRE-MIXED (PM)-CLAY METHOD 24 Terra et Aqua Number 133 December 2013 TAKU SAITOH CONSTRUCTION OF A PERIMETER BUND USING THE PRE-MIXED (PM)-CLAY METHOD ABSTRACT Securing disposal fields to receive soft dredged material has become

More information

Policy Research Corporation

Policy Research Corporation Policy Research Corporation SOUND SOLUTIONS BASED ON SCIENTIFIC RESEARCH The role of Maritime Clusters to enhance the strength and development of maritime sectors Country report Lithuania INTRODUCTION

More information

Breakwater Construction Mary s Harbour, NL Environmental Registration Document

Breakwater Construction Mary s Harbour, NL Environmental Registration Document Breakwater Construction Mary s Harbour, NL Environmental Registration Document Submitted to the Government of Newfoundland and Labrador Department of Municipal Affairs and Environment Environmental Assessment

More information

Oil skimming technology "SORBMOP"

Oil skimming technology SORBMOP Oil skimming technology "SORBMOP" B. Koppe 1, E. Kumpf 2, S. Kohlhase 1 1 Institute for Hydraulic and Coastal Engineering, University of Rostock, Germany 2 EKU Entwicklungen, Rostock, Germany Abstract

More information

INVESTOR RELATIONS PRESENTATION 2017/18

INVESTOR RELATIONS PRESENTATION 2017/18 INVESTOR RELATIONS PRESENTATION THE YEAR IN FIGURES REVENUE INVESTMENTS EBIT EBIT MARGIN 12,108M 408M 475M 3.9% Revenue increased by 8.2%, of which 6.2% was organic growth. Revenue increased in all three

More information

MARINE WORKS OPERATIONS AND ENVIRONMENTAL CONSIDERATIONS WHEN BUILDING THE FEHMARNBELT TUNNEL

MARINE WORKS OPERATIONS AND ENVIRONMENTAL CONSIDERATIONS WHEN BUILDING THE FEHMARNBELT TUNNEL 20 Terra et Aqua Number 127 June 2012 JØRGEN ANDERSEN, CLAUS IVERSEN AND EELCO VAN PUTTEN MARINE WORKS OPERATIONS AND ENVIRONMENTAL CONSIDERATIONS WHEN BUILDING THE FEHMARNBELT TUNNEL ABSTRACT The Fehmarnbelt

More information

Failure of Defences. Frontage 1 Long Curtain Moat

Failure of Defences. Frontage 1 Long Curtain Moat Failure of Defences The current defences along Southsea Seafront have a residual life of less than 10 years this is discussed in the Current Standard of Protection resource in the Resources section of

More information

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Module - 3 Lecture - 10 New materials for coastal embankments l

More information

1 Introduction CIRIA C683 1

1 Introduction CIRIA C683 1 1 Introduction 1 3 5 7 9 CIRIA C3 1 1 Introduction CHAPTER 1 CONTENTS 1.1 Use of rock...................................................... 3 1. Background to the manual.........................................

More information

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures Arbeitsausschuß "Ufereinfassungen" der Hafentechnischen Gesellschaft e.v. Recommendations of the Committee for Waterfront Structures Harbours and Waterways 9., completely revised Edition TABLE OF CONTENTS

More information

HYDRAULIC ENGINEERING

HYDRAULIC ENGINEERING hydraulic engineering.. hydraulic engineering. 2 HYDRAULIC ENGINEERING Getting to the bottom of it Hydraulic engineering is counted among the internationally significant fields of activity in which the

More information

Harbour Improvements. St. Lunaire, NL. Environmental Registration Document

Harbour Improvements. St. Lunaire, NL. Environmental Registration Document Harbour Improvements St. Lunaire, NL Environmental Registration Document Submitted to the Government of Newfoundland and Labrador Department of Environment and Conservation Environmental Assessment Division

More information

Hamburg, GERMANY. Predöhlkai extension project Berth 1

Hamburg, GERMANY. Predöhlkai extension project Berth 1 Hamburg, GERMANY Predöhlkai extension project Berth 1 As one of the world s most important ports, Hamburg will handle an expected 14 million TEU by 2010. This represents a major rise from today s 8.5 million

More information

ROTAWN ENERGY AND LOGISTICS CONSTRUCTION PROFILE

ROTAWN ENERGY AND LOGISTICS CONSTRUCTION PROFILE ROTAWN ENERGY AND LOGISTICS CONSTRUCTION PROFILE CONSTRUCTION PROFILE ABOUT US Rotawn Energy and Logistics Services Ltd was established in 2007 as an indigenous Nigerian company offering tailor made solutions

More information

Quality management system. Environmental management system. Occupational health and safety management system.

Quality management system. Environmental management system. Occupational health and safety management system. Company Profile Gulf Rock Engineering Group was started in 1975 as a specialist blasting sub-contractor and has since developed into one of the Gulf regions leading earthworks and underground construction

More information

Beneficial use of mudcrete in reclamations SJ. Priestley Beca Carter Rollings & Ferner Limited, Auckland, New Zealand

Beneficial use of mudcrete in reclamations SJ. Priestley Beca Carter Rollings & Ferner Limited, Auckland, New Zealand Beneficial use of mudcrete in reclamations SJ. Priestley Beca Carter Rollings & Ferner Limited, Auckland, New Zealand Abstract Redevelopment of the eastern section of the Viaduct Basin in downtown Auckland,

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION LSA ASSOCIATES, INC. OCTOBER 2009 DRAFT ENVIRONMENTAL IMPACT REPORT ALAMITOS BAY MARINA REHABILITATION PROJECT CITY OF LONG BEACH 3.0 PROJECT DESCRIPTION 3.1 PROJECT LOCATION AND SITE DESCRIPTION The Alamitos

More information

8. HYDROGRAPHICAL CONDITIONS

8. HYDROGRAPHICAL CONDITIONS 64 state of the seas 8. HYDROGRAPHICAL CONDITIONS Key Messages A substantial proportion of the Northern Ireland coastline has been altered by coastal defence structures. This is particularly prevalent

More information

PENDER HARBOUR DOCK MANAGEMENT PLAN

PENDER HARBOUR DOCK MANAGEMENT PLAN PENDER HARBOUR DOCK MANAGEMENT PLAN 1.0 INTENT OF DOCK MANAGEMENT PLAN The Pender Harbour Dock Management Plan (the DMP) is an instrument of policy that provides guidance in relation to docks authorized

More information

Dilution, A New Technology. at the Pearl River Estuary.

Dilution, A New Technology. at the Pearl River Estuary. Noël Pille Dilution, A New Technology Used at the Pearl River Estuary Pipeline Installation Project Abstract This article explains a new technology, dilution, used for dredging and backfilling works during

More information

Comparison Between Overtopping Discharge in Small and Large Scale Models

Comparison Between Overtopping Discharge in Small and Large Scale Models Downloaded from vbn.aau.dk on: januar 25, 2019 Aalborg Universitet Comparison Between Overtopping Discharge in Small and Large Scale Models Helgason, Einar; Burcharth, Hans Falk Published in: 30th International

More information

WATER AND DRAINAGE. Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A

WATER AND DRAINAGE. Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A WATER AND DRAINAGE Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A H CONSTRUCTION H-1 W A T E R A N D D R A I N A G E DRAINAGE AROUND WALLS Poor drainage is a leading

More information

HDB MARINE. Your Solution for Marina and Dock Design / Construction

HDB MARINE. Your Solution for Marina and Dock Design / Construction HDB MARINE Your Solution for Marina and Dock Design / Construction Commercial Marinas Recreational Marinas Resort Marinas Military Marine Dock Applications Custom Private Docks HDB will build your design

More information

proserve Berth Scour Protection - Using Concrete Mattress MARINE CONSTRUCTION ENGINEERS Berth Scour Aprons

proserve Berth Scour Protection - Using Concrete Mattress   MARINE CONSTRUCTION ENGINEERS Berth Scour Aprons Berth Scour Protection - Using Berth Scour Aprons These provide protection to quay structures against: Propeller Scour Ro Ro Fast Ferry Jet Scour Bow Thrusters Wave and Current Action The System Mattress

More information

U l t i m a t e e f f i c i e n c y D re D ging

U l t i m a t e e f f i c i e n c y D re D ging 1 Ultimate efficiency Dredging We have a deep attitude. 2 Ultimate efficiency 3 Growth of global population, tourism, transportation of people and goods together with increased awareness of the need to

More information

The new Lauenburg lock

The new Lauenburg lock The new Lauenburg lock on the Elbe-Luebeck Canal (ELC) at km 60.15 On 12 May 2006 the new lock Lauenburg on the Elbe-Luebeck Canal was inaugurated. This structure is the third lock at the site Lauenburg

More information

DOCUMENT STATUS. Details of Revision:

DOCUMENT STATUS. Details of Revision: (I) DOCUMENT STATUS Details of Revision: Revision Rev. Date Sections Amendment Source and/or Details A 30 Aug 2013 All Issued for Approval B 23 Sep 2013 All Revised for Approval C 24 Sep 2013 4, 5 D 8

More information

SLOPE PROTECTION UNDER PILED QUAYS M. Hawkswood 1 and M. King 2

SLOPE PROTECTION UNDER PILED QUAYS M. Hawkswood 1 and M. King 2 ASCE COPRI PORTS 16 CONFERENCE 216 SLOPE PROTECTION UNDER PILED QUAYS M. Hawkswood 1 and M. King 2 1 Martin G. Hawkswood, B.Sc. C.Eng. M.I.C.E. M.I.Struct.E. A.M. ASCE. Proserve Ltd, Princes Drive, Kenilworth

More information

ENVIRONMENTAL ASSESSMENT REGISTRATION

ENVIRONMENTAL ASSESSMENT REGISTRATION ENVIRONMENTAL ASSESSMENT REGISTRATION PORT HARMON CHANNEL AND HARBOUR DREDGING Submitted to: Department of Environment Environmental Assessment Division May 2004 ENVIRONMENTAL ASSESSMENT REGISTRATION PORT

More information

CHAPTER 153 PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS. K.J. Macintosh* and W.F. Baird*

CHAPTER 153 PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS. K.J. Macintosh* and W.F. Baird* CHAPTER 153 ABSTRACT PROTOTYPE EXPERIENCE WITH RUBBLE MOUND BREAKWATERS K.J. Macintosh* and W.F. Baird* At the 19th ICE Conference in Houston in 1984 an alternative concept for the design of rubble mound

More information

Initial Construction and Maintenance Costs

Initial Construction and Maintenance Costs VI. Initial Construction and Maintenance Costs This section documents the state of knowledge regarding the initial and maintenance costs associated with terminal groin structures. As part of the cost study,

More information

The Port of Cape Town Latitude S Longitude E

The Port of Cape Town Latitude S Longitude E The Port of Cape Town Latitude 33 54 S Longitude 18 26 E Introduction The Port of Cape Town lies in the shadow of Table Mountain, approximately 120 nautical miles north west of Cape Agulhas strategically

More information

APPENDIX 8-A. Valued Component Selection Rationale

APPENDIX 8-A. Valued Component Selection Rationale APPENDIX 8-A Valued Component Selection Rationale This page is intentionally left blank A list of candidate s was compiled based on issues identified through the scoping process described in Section 8.1.2

More information

4 DESCRIPTION AND METHODOLOGY OF PROPOSED COASTAL WORKS

4 DESCRIPTION AND METHODOLOGY OF PROPOSED COASTAL WORKS 4 DESCRIPTION AND METHODOLOGY OF PROPOSED COASTAL WORKS 4.1 INTRODUCTION Rivière des Galets site is remarkably different from the Mon Choisy site. The critical coastal hazard to be addressed at Rivière

More information

Alcoa Mosjøen Harbor Remediation Project Information and Fender Design

Alcoa Mosjøen Harbor Remediation Project Information and Fender Design Alcoa Mosjøen Harbor Remediation Project Information and Fender Design Trygve Isaksen and Maiken Eng, Norconsult 1 Content Short presentation of Norconsult, Port and Coastal Engineering and Trygve Introduction

More information

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017. Cairns Shipping Development Project Revised Draft Environmental Impact Statement Fact Sheet July 2017 AT A GLANCE > An additional 70 cruise ships into Port of Cairns each year by 2031 > Project design

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies STANDARD FOR RIPRAP Definition A layer of loose rock, aggregate, bagged concrete, gabions, or concrete revetment blocks placed over an erodible soil surface. Purpose The purpose of riprap is to protect

More information

Conversion of Kurnell refinery to a fuel import terminal

Conversion of Kurnell refinery to a fuel import terminal Conversion of Kurnell refinery to a fuel import terminal Dr Jos Kusters 1 May 2014 AGENDA Background Kurnell site conversion Management of environmental and community impacts Operation as a terminal 2

More information

DRAFT. Point Hudson. Marina Breakwater Rehabilitation Task 1 Design Refinement. Port of Port Townsend. August 30, 2017

DRAFT. Point Hudson. Marina Breakwater Rehabilitation Task 1 Design Refinement. Port of Port Townsend. August 30, 2017 DRAFT Point Hudson Marina Breakwater Rehabilitation Task 1 Design Refinement Port of Port Townsend August 30, 2017 Task 1 - Design Refinement Overview Contractor/ Supplier Outreach Information on cost

More information

Study on the Plan of Taipei Port

Study on the Plan of Taipei Port Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Study on the Plan of Taipei Port Chi-Chi Chen UNION-TECH Engineering Consultants

More information

MARINA PHASING AND COSTS

MARINA PHASING AND COSTS WATERFRONT PLACE IMPLEMENTATION STRATEGY Prepared for Port of Everett TEAM Reid Middleton BST Associates RMC Architects MARINA PHASING AND COSTS This section Prepared by: Reid Middleton September 2014

More information

C-POWER PROJECT BELGIUM

C-POWER PROJECT BELGIUM THE BELGIAN COAST C-POWER PROJECT BELGIUM A min 216 max 300 MW windfarm in front of the belgian coast Power@Sea and its shareholders are holding the majority in the C-Power project, a farshore wind farm

More information

Walthamstow Reservoirs No. 4 & No. 5 embankment protection

Walthamstow Reservoirs No. 4 & No. 5 embankment protection Walthamstow Reservoirs No. 4 & No. 5 embankment protection C.B. PECK, Thames Water RWE, UK SYNOPSIS. Walthamstow reservoirs Nos. 2, 3, 4 and 5 are situated in the Lee Valley, north-east London. Reservoirs

More information

CTB3300WCx Introduction to Water and Climate

CTB3300WCx Introduction to Water and Climate CTB3300WCx Introduction to Water and Climate IN3 Delta and Estuary intervention Mark Voorendt Hello my name is Mark Voorendt. I am researcher and lecturer on hydraulics structures at the Delft University

More information

CROWN-WALL WITH EXTENDED BASE SLAB

CROWN-WALL WITH EXTENDED BASE SLAB CROWN-WALL WITH EXTENDED BASE SLAB Ing. Ineke Vos-Rovers MSc (Eng.) 1, Ir. Bas Reedijk 1, Ing. Sjaak Ekelmans 2 This paper presents the design philosophy and the construction stages of a n6n-standard crown-wall

More information

About the company Union Dredgers and Marine Contracting is a dynamic and highly respected company operating out of the UAE since 2007 and is part of the Union Group of companies. During this period we

More information

Southern African Coastal Vulnerability Assessment. Dr Christo Rautenbach

Southern African Coastal Vulnerability Assessment. Dr Christo Rautenbach Southern African Coastal Vulnerability Assessment Dr Christo Rautenbach 1 Content layout Introduction to coastal vulnerability Climate change Consequences on the coast Vulnerability and risk on coastal

More information

Port of Long Beach Port Master Plan Overview December 22, 2008

Port of Long Beach Port Master Plan Overview December 22, 2008 Port of Long Beach Port Master Plan Overview December 22, 2008 PORT OF LONG BEACH PORT MASTER PLAN OVERVIEW INTRODUCTION In 1978 the California Coastal Commission certified the Port of Long Beach Port

More information

Statement of evidence of Stephen Lee (wharf design and construction methods)

Statement of evidence of Stephen Lee (wharf design and construction methods) Before Hearing Commissioners at Christchurch under: the Resource Management Act 1991 in the matter of: applications CRC175507, CRC176030, CRC175508, CRC175509, CRC175510 to reclaim land and construct a

More information

POWER HUB AS AN ISLAND 17 NOVEMBER 2017

POWER HUB AS AN ISLAND 17 NOVEMBER 2017 POWER HUB AS AN ISLAND 17 NOVEMBER 2017 Executive Summary Reduction of the total system cost is essential to facilitate large scale offshore wind and interconnection capacity deployment and all options

More information

About Viadukt. Our vision. Our mission

About Viadukt. Our vision. Our mission About Viadukt Viadukt d.d. is the largest construction company in Croatia and in the South East Europe. It was founded in 1947, it employs more than 1 800 employees and is specialized in the execution

More information

Onshore terminal plants

Onshore terminal plants Onshore terminal plants Norconsult experience covers engineering consultancy services within development of new facilities (Green plants) and live plant modifications (Brown plants) For Green terminal

More information

CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE

CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE S.Y. CHEW Manager, Building and Development Division, Housing and Development Board, Singapore and J. WEI Principal Civil Engineer, Building

More information

Experiences from Union of Baltic Cities. Jarkko Virtanen

Experiences from Union of Baltic Cities. Jarkko Virtanen 20 years of regional cooperation! Experiences from Union of Baltic Cities Jarkko Virtanen Deputy Mayor, City of Turku Vice President, Unio on of the Baltic Cities Union of the Baltic Cities UBC Founded

More information

Developing the second holistic assessment of ecosystem health in the Baltic Sea (HOLAS II) and HELCOM Data management plans

Developing the second holistic assessment of ecosystem health in the Baltic Sea (HOLAS II) and HELCOM Data management plans Developing the second holistic assessment of ecosystem health in the Baltic Sea (HOLAS II) and HELCOM Data management plans Joni Kaitaranta, Data Coordinator joni.kaitaranta@helcom.fi 12.4.2016 First HELCOM

More information

Measured environmental impacts of dredging operations S.J. Priestley

Measured environmental impacts of dredging operations S.J. Priestley Measured environmental impacts of dredging operations S.J. Priestley Abstract Recent dredging operations in the port of Auckland, New Zealand were preceded by detailed environmental impact assessments.

More information

The effectiveness of sustainable floating structures in the Gulf Region (Middle East)

The effectiveness of sustainable floating structures in the Gulf Region (Middle East) High Performance and Optimum Design of Structures and Materials 653 The effectiveness of sustainable floating structures in the Gulf Region (Middle East) A. Ghafooripour 1, E. Nezamifar 1, O. Ogwuda 1

More information

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement DEVELOPMENT

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement DEVELOPMENT ABERDEEN HARBOUR EXPANSION PROJECT November 2015 Volume 2: Environmental Statement Chapter 3: DESCRIPTION OF THE DEVELOPMENT 3. DESCRIPTION OF THE DEVELOPMENT 3.1 Introduction This chapter describes the

More information

ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE

ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE DREDGING PROFILE ABOUT US Rotawn Energy and Logistics Services Ltd was established in 2007 as an indigenous Nigerian company offering tailor made solutions

More information

1 Small Hydro Power Plants Wetzmann

1 Small Hydro Power Plants Wetzmann 5 th Bulgarian-Austrian Seminar SMALL DAMS AND HPP 30 March 2012, Sofia R.9 REFURBISHMENT OF TWO SMALL HYDRO POWER PLANTS IN AUSTRIA P. Tschernutter Abstract: A weir at the River Gail, which was used for

More information

Construction of Container Terminal 4 Port of Bremerhaven, Germany

Construction of Container Terminal 4 Port of Bremerhaven, Germany Third Chinese-German Joint Symposium on Coastal and Ocean Engineering National Cheng Kung University, Tainan November 8-16, 2006 Construction of Container Terminal 4 Port of Bremerhaven, Germany Birgitt

More information

World. Yearbook MARITIME REPORTER. The 2015 AND ENGINEERING NEWS. June 2015 M A R I N E L I N K. C O M

World. Yearbook MARITIME REPORTER. The 2015 AND ENGINEERING NEWS. June 2015 M A R I N E L I N K. C O M The World s Largest Circulation Marine Industry Publication The Information Authority for the Global Marine Industry since 1939 MARITIME June 2015 REPORTER AND ENGINEERING NEWS M A R I N E L I N K. C O

More information

Quantifying the carbon footprint of coastal construction a new tool HRCAT

Quantifying the carbon footprint of coastal construction a new tool HRCAT Quantifying the carbon footprint of coastal construction a new tool HRCAT Rudi Broekens 1, Manuela Escarameia 1, Clemente Cantelmo 1 and George Woolhouse 1 1 HR Wallingford, Wallingford, United Kingdom

More information

Critical-phase sea dike construction of NCICD program in Jakarta as national capital city

Critical-phase sea dike construction of NCICD program in Jakarta as national capital city IOP Conference Series: Earth and Environmental Science PAPER OPEN ACCESS Critical-phase sea dike construction of NCICD program in Jakarta as national capital city To cite this article: H Suprayogi et al

More information

Media Release # 4. Melville Bay East Arnhem Land Mud Wharf Community Project Stages 7c & 7d

Media Release # 4. Melville Bay East Arnhem Land Mud Wharf Community Project Stages 7c & 7d Media Release # 4. Melville Bay East Arnhem Land Mud Wharf Community Project Stages 7c & 7d. 10.07.2016 Work is now underway on the next Stage of the Community Boat Ramp works as part of the $500,000 commitment

More information

The Construction of JadeWeserPort A Deepwater Container Terminal in Wilhelmshaven

The Construction of JadeWeserPort A Deepwater Container Terminal in Wilhelmshaven 411 The Construction of JadeWeserPort A Deepwater Container Terminal in Wilhelmshaven By JADEWESERPORT REALISIERUNGSGESELLSCHAFT Contents 1. A Terminal for Next Generation Container Ships.....................

More information

Product Guide. Fabric-formed Concrete Erosion Control and Armoring Systems. Filter Point. Filter Band. Uniform Section. Enviromat. Articulating Block

Product Guide. Fabric-formed Concrete Erosion Control and Armoring Systems. Filter Point. Filter Band. Uniform Section. Enviromat. Articulating Block Filter Point Filter Band Uniform Section Enviromat Articulating Block Hydrocast Armor Units Fabric-formed Concrete Erosion Control and Armoring Systems Product Guide Filter Point (FP) Linings Filter Band

More information

Marine Portfolio

Marine Portfolio Page 2 & 3 Contents 2 & 3 4 & 5 6 & 7 8 & 9 Contents Introduction D1 Belfast Harbour Seaforth Passage 10 & 11 12 & 13 14 & 15 16 & 17 Heysham Cooling Water Outfall Granton Harbour Wall Montrose Deep Water

More information

River Restoration in Japan

River Restoration in Japan River Restoration in Japan Keigo Nakamura, Ph.D Water Environment Research Group Public Works Research Institute Contents What is restoration? History of river restoration in Japan Basics for river restoration

More information

HANDBOOK OF PORT AND HARBOR ENGINEERING

HANDBOOK OF PORT AND HARBOR ENGINEERING HANDBOOK OF PORT AND HARBOR ENGINEERING GEOTECHNCAL AND STRUCTURAL ASPECTS Gregory P. Tsinker, Ph.D., RE. E3 CHAPMAN & HALL International Thomson Publishing New \ork Albany Bonn ^Boston Cincinnati Detroit

More information

SOLUTIONS SOLUTIONS BROCHUREPORT

SOLUTIONS SOLUTIONS BROCHUREPORT SOLUTIONS SOLUTIONS BROCHUREPORT 2 BOSKALIS IS A LEADING GLOBAL DREDGING AND MARINE EXPERT A PROVEN NAME IN THE PORTS MARKET 3 A PROVEN NAME IN THE PORTS MARKET With safety as our core value we provide

More information

CONSTRUCTING MODERN PORTS WITHOUT STEPPING ON WATER by

CONSTRUCTING MODERN PORTS WITHOUT STEPPING ON WATER by CONSTRUCTING MODERN PORTS WITHOUT STEPPING ON WATER by Sabino, Leandro Mendes 1 and Filho, Rubens da Costa Sabino 2 ABSTRACT When the decision for the construction of a new port is taken, investors and

More information

Environmental Sustainability of Constructing the Newquay Artificial Surfing Reef

Environmental Sustainability of Constructing the Newquay Artificial Surfing Reef Environmental Sustainability of Constructing the Newquay Artificial Surfing Reef S. L. Challinor 1 and A. Weight 2 1 Chestnut Mews, Feniton, Honiton, Devon, UK EX14 3BA. wislon22@yahoo.co.uk 2 Newquay

More information

Marine Portfolio

Marine Portfolio Page 2 & 3 Contents 2 & 3 4 & 5 6 & 7 8 & 9 Contents Introduction D1 Belfast Harbour Seaforth Passage 10 & 11 12 & 13 14 & 15 16 & 17 Heysham Cooling Water Outfall Granton Harbour Wall Montrose Deep Water

More information

Policy Research Corporation

Policy Research Corporation Policy Research Corporation SOUND SOLUTIONS BASED ON SCIENTIFIC RESEARCH The role of Maritime Clusters to enhance the strength and development of maritime sectors Country report Belgium INTRODUCTION TO

More information

Harbour Constructions

Harbour Constructions Harbour Constructions River and Coastal morphology: They provide morphological services based on one-, two- and threedimensional computer models. These models are used to answer the questions of clients

More information

IHC TRAINING INSTITUTE DREDGE TRAINING ROYALIHC.COM /SERVICES/TRAINING

IHC TRAINING INSTITUTE DREDGE TRAINING ROYALIHC.COM /SERVICES/TRAINING ROYALIHC.COM /SERVICES/ IHC INSTITUTE DREDGE IHC INSTITUTE LOOK BEYOND YOUR HORIZON Educating your crew to open up the full potential of your vessel and equipment trainers with extensive experience in

More information

PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1

PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1 PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1 PREPARED FOR PORT OF NAPIER LTD NOVEMBER 2017 PROPOSED WHARF AND

More information

NEW YORK / NEW JERSEY HARBOR DEEPENING PROJECT

NEW YORK / NEW JERSEY HARBOR DEEPENING PROJECT NEW YORK / NEW JERSEY HARBOR DEEPENING PROJECT Using Synergy to Successfully Execute A Mega Water Resource Project Joseph J. Seebode Deputy District Engineer U.S. Army Corps of Engineers New York District

More information

FINDINGS, CONCLUSIONS AND DECISION

FINDINGS, CONCLUSIONS AND DECISION FINDINGS, CONCLUSIONS AND DECISION Applicant: Agent: File No: Request: Location: Parcel No.s: Shoreline Designation: Summary of Proposal: Public Hearing: Decision: Walla Walla University Rosario Beach

More information