A BIM-based solution to support Earned Value Management in Construction. Extended Abstract. Civil Engineering

Size: px
Start display at page:

Download "A BIM-based solution to support Earned Value Management in Construction. Extended Abstract. Civil Engineering"

Transcription

1 A BIM-based solution to support Earned Value Management in Construction Anne-Marie Nsimire Mushamalirwa Extended Abstract Thesis to obtain the Master of Science Degree in Civil Engineering Supervisor: Professor António Morais Aguiar da Costa Jury: Chairperson: Professor Augusto Martins Gomes Supervisor: Professor António Morais Aguiar da Costa Members of the Committee: Professor Nuno Gonçalo Cordeiro Marques de Almeida July 2016

2 1. Introduction Building Information Modelling (BIM) technology has significantly impacted the Architecture, Engineering, and Construction (AEC) /Facility Management (FM) industry in the past few years. It has accelerated the response to different pressures such as the increasing projects complexity or the need for achieving higher levels of sustainability while reducing cost and time of design and construction [1]. BIM has changed the approach of planning, designing, building and operating building construction projects [2] and has allowed a more efficient collaboration between all the stakeholders of the project during the lifecycle of the building [1]. One of the phases that can truly benefit from BIM is the execution phase. This phase is one of the most challenging and has always faced in-situ problems such as the discovery of design changes or errors, delays etc. In addition, the response time from onsite supervisors always have to be prompt to meet the schedule dates and allocated budget. The implementation of BIM can greatly reduce the above mentioned constraints and be a useful tool for construction managers. The objective of this paper is to present an innovative BIM-based tool to support managers during this delicate and complex phase. This tool is based on a synergy between BIM and Earned Value Management (EVM) knowledge and uses two well-known tools, Microsoft (MS) Excel and Autodesk Revit, to show the cost and time performance of a construction site at a specific point in time and using a 3 Dimensional (3D) BIM model. For this, the user must provide the required input data with the use of mobile devices such as laptops or tablets. This paper is divided into four parts. The first part presents a literature review that was conducted to understand the concepts and the application of BIM and EVM. The second part explains the methodology used in the study. The third part describes how the EVM/BIM tool is developed and implemented, and finally the last part presents the results obtained on a pilot case made on a residential house. 2. Literature Review 2.1 BIM and Construction Management Building Information Modelling allows creating a 3D model of a construction project which might gather all the information produced during its entire lifecycle [1]. Thus, it is a powerful instrument that helps optimizing the project regarding cost and time. For example, it improves the efficiency of quantity takeoffs which are especially important during the bid phase to estimate the cost [1]. This aspect was highlighted by Manning & Messner [3] as one of the major benefits of BIM, when they implemented BIM in two construction projects: a medical research laboratory and an expeditionary hospital facility in the United States. With regards to the construction analysis and planning, the traditional methods present some disadvantages. Besides being a tedious manual task, they are time-consuming and prone to error [4], mainly due to the lack of software applications which supports it [5]. However, an efficient exploitation of BIM data can help achieving significant time reductions, for example generating automated 2

3 construction schedules [6] [7]. BIM is also changing the approach regarding safety, which constitutes an important issue in construction sites. For instance, the State Technical Research Centre of Finland developed a manual procedure using BIM technology to visualize safety railing for fall/edge protection [8]. Zhang et al [9] also developed an automated rule-based safety checking system for fall protection based on BIM software, focusing on potential fall hazards such as openings like unprotected windows, or holes in slabs. 2.2 EVM concept The Earned Value Management (EVM) is a management technique used in different areas such as Information Technology (IT) or construction, which aims to monitor cost, schedule and technical performance of a project [10]. One of its main uses is to forecast project cost and time through the use of performance indices [11]. It also constitutes an early warning of performance problems when properly applied [12]. The concept is based on the interpretation of three parameters that allow the computation of those performance indices. The first parameter is the Planned Value (PV), which is the planned cost of the project work that is supposed to be done at any given time [13]. The highest and last value of PV is the Budget At Completion (BAC) corresponding to the total budget baseline for the activity [14]. The second parameter is the Actual Cost (AC) which represents how much resources have been used to reach the actual work performed at a certain point in time. To obtain this value, the user needs to have a system of tracking costs over time and by project component. The last parameter is the Earned Value (EV) which represents the amount of work accomplished to date or in a given period. There are different ways of evaluating the EV. However, the easiest and simplest technique is based on the determination of the percentage completed i.e. the percentage of the work achieved is determined at each measurement period by the responsible manager [13]. 2.3 BIM and EVM synergies Individually, EVM and BIM represent two of the most prevalent project control methodologies for the purpose of productivity improvement according to a survey made on 50 international construction project controls professionals [11]. Several researches prove the potential of combining the two in construction management. For example, in Poland, Foremny, Kluczuk & Nicał [15] developed a Mobile Earned Value Management System (MEVMS) aiming to increase the speed and quality of monitoring schedule and cost in-situ with a MS Excel interface. Marzouk & Icham [16] also tried to implement EVM in Bridge Information Modelling (BrIM) an application of the BIM concept on bridges. They presented a BIM-based cost estimate application which integrates the EV concept to control cost and time during the execution phase of the project. With a different approach, the combination of 3D Laser scanning and EVM can efficiently evaluate the performance of a project execution. Laser scanning has been considered as the best available technology in the AEC/FM industry to capture 3D information on a project with speed and accuracy [17] and allows the reconstruction of as-built 3D BIM models from acquired 3D point clouds [18]. A comparison between those models and the expected state planned in a BIM model allows to perform 3

4 an EVM analysis and thus obtain the cost and time performance of construction works. This principle has been applied to Mechanical, Electrical and Plumbing works [18], steel structures and reinforced concrete structures [19]. 3. Research method The objective of this study was to create an EVM/BIM tool able to support construction managers during the execution phase by showing the cost and time performance on a BIM model. To reach this goal, a conceptual model of the tool was designed to outline the context of its use, the different actors, the technology used, and the operational mode. Secondly, an Excel table was created where all the necessary input data for all tasks of the project schedule have to be inserted. Computation for the different EVM indicators was implemented in an automatic way and so the EVM status is given per task first, and then for all elements that constitute the BIM model, assuming that all of those elements are known. Thirdly, a Dynamo programming code was developed to implement the connection between the Excel file and the BIM software. Dynamo is a visual programming add-in of Autodesk Revit that enables to automate several operations based on the BIM model. In this case it was used to perform an information exchange from Revit to Excel, by the extraction of a list all elements and their properties from the Revit model to the table, and from Excel to Revit, by collecting the performance information of all elements. Afterwards, based on these performance indicators, Dynamo was also used to colour the elements in the BIM model according to their status. In this sense, 9 statuses were defined, each one of them being associated to a specific colour. Finally, several simulations were conducted to test the prototype tool, based on a Revit model of a residential house. 4. EVM/BIM Tool Development 4.1 Conceptual model Figure 1. Theoretical model of the EVM/BIM tool. Figure 1 presents the theoretical model of the EVM/BIM tool. Firstly, the manager fills an Excel sheet with the list of the construction tasks and their respective EVM inputs, which can be made using computer or a mobile interface such as a tablet. The EVM indices and the global graph are computed, and based on those indices the performance is obtained per task and also for the entire project. The next step is to extract a list of elements from the BIM model, which can be achieved by using Dynamo. 4

5 The list of tasks and the list of elements are pre-connected on the Excel file, so that when a performance is attributed to a task, all the related elements get their corresponding performance. Thus, each element is credited of an EVM performance and is coloured in the BIM model using Dynamo, following the colours code system established. 4.2 Creation of the Excel interface The Excel file comprises of 7 different sheets. The first sheet contains the terms of use of the interface. It describes the colours code used and presents the operational mode, namely what the user has to do in each sheet. The three next sheets are for the Planned Value, the Actual Cost and the Earned Value which are to be completed by the user with the EVM input data at the moment considered. Finally, the three last sheets give the performance of the project per activity, per element, and the global one. The fifth sheet called Performance per Activity is the most important. Indeed, it gathers for each activity the accumulated PV, AC and EV so that the Schedule Variance (SV) and Cost Variance (CV) are computed with the following formulas: SV = EV - PV CV = EV - AC The Schedule Variance allows one to know if the project is ahead, on or behind schedule; the Cost Variance if the project is under, on or over budget. So after calculating those indicators, the EVM performance is obtained for each task. For each performance is attributed a number and a colour (Table 1). Then, in the sixth sheet Performance per Element a performance number is attributed to each element of the 3D model, obtained from the previous sheet. Finally, the last sheet, Global Performance, gathers all the inputs to obtain a graph with PV, AC and EV evolutions along the time to present the general EVM performance of the entire project. Table 1. Colours code system SV CV Performance and Colour / / 0 Element/Task not started SV > 0 CV > 0 1 Ahead of Schedule and Under Budget SV > 0 CV = 0 2 Ahead of Schedule and On Budget SV > 0 CV < 0 3 Ahead of Schedule and Over Budget SV = 0 CV > 0 4 On Schedule and Under Budget SV = 0 CV = 0 5 On Schedule and On Budget SV = 0 CV < 0 6 On Schedule and Over Budget SV < 0 CV > 0 7 Behind Schedule and Under Budget SV < 0 CV = 0 8 Behind Schedule and On Budget SV < 0 CV < 0 9 Behind Schedule and Over Budget (1) 4.3 Interoperability between Excel and Revit Visual scripting interfaces have become an important tool for the design and construction areas. They provide an alternative to computer programming, by replacing the conventional elaborate coding with a visual metaphor of connecting small blocks of independent functionalities into o whole system or procedure [20]. Dynamo is one of those visual scripting interfaces that works as a plugin to Autodesk Revit. It is designed to extend Revit s parametric modelling capabilities. The user interacts with 5

6 Dynamo using elements called nodes. Each node has a number of ports to enable communication between nodes along connectors. Ports can only be connected to other ports whose output type matches the port s input type (Figure 2). All of those connected elements create the workflow [21]. Node Port Figure 2. Extract of a Dynamo code. In this study, an information exchange is required from the BIM model to Excel and vice versa. Dynamo is the interface chosen to perform this bidirectional interoperability, while Excel is used to compute the performance per element after receiving Revit information. Dynamo has 4 functions that are presented in Table 2. Table 2. Functions of Dynamo Function Main nodes used Description All Elements of Category 1. Extraction of information (element identification number and Task number ) 2. Send information to Excel 3. Read Excel data 4. Update the BIM model Select Model Elements Element.GetParameterByName Element.Id Live Write Excel Excel.ReadFromFile. List.FilterByBoolMask Element.OverrideColorInView Element.TemporarilyIsolateInView Connector The elements from which the information are extracted have to be selected. This selection is made by category. The node allows getting all the elements in the model that belong to it. The selection can be done manually, by selecting directly in the Revit file. Once the elements list is obtained, Dynamo allows to get the value of any parameter implemented in the Revit file through the node. It is just required to enter as an input a string with the exact name of the parameter. Here it is Task number, see paragraph 4.4. The ID number is directly obtained with the node. The objective is to insert the lists obtained previously in the table of the sheet Performance per Element. The node allows to write the input data in the current active Excel file. At this stage, in the Excel file, to every element identified by the ID number is attributed a performance number from 0 to 9. So firstly, the performance values are extracted with the node. The objective is to filter this list according to the performance value, that is to mean to separate the group of elements in 10 groups, each group corresponding to an EVM status. Then, the elements that belong to a group are coloured with the corresponding colour (Table 1). The node colours the element in the current active view of the Revit file. The node allows to isolate the coloured elements, which are in fact the elements whose the execution has started. 6

7 4.4 Challenges The biggest challenge is the connection between the list of activities and the list of elements. Until the present day, the interaction between objects and tasks is made manually [1] as there is no automated process to link objects to the tasks [7]. In the tool, this connection is required because when the performance per task is obtained, the elements have also to be credited of a performance value. Usually, a planning is under the following format or, if not, it is easy to convert into the following format: 1. Footings 1.1. Formwork, etc. This requires each task to be allocated a hierarchic number such as "1.1.2.". Therefore, the solution for this is to create in the Revit project a shared parameter called Task number. The task number of an element corresponds to the number of the task in which it is involved. This attribution can be done manually directly in Revit or using Dynamo which is less time-consuming. It implies that the connection between elements and tasks is univocal i.e. to each element corresponds only one task. The next step involves transferring the list of elements with their respective identification (ID) number and task number to the Excel sheet titled Performance per element. The column in the spreadsheet corresponding to the performance has a pre-defined formula in the cells. This formula allows the cell to take the value of the performance of a task only if its task number is equal to the task number of the element concerned. 5. Results The prototype has been tested on a Revit model of a residential house with a 3 room typology. It has 2 floors and an area of 325 m 2. This model was created for experimental reasons. Before starting the simulations, a construction schedule was built in order to enter the task numbers in the Revit file from the foundation construction until the installation of residential furniture. The entering of this data was made using a Dynamo code with the node Element.SetParameterByName that changes the current value of the parameter considered by a given input value. Then the simulations were done considering as variable the performance for activities. They are presented in Table 3. There are two scenarios. In the first one, the works start well but end critically and in the second one it is the contrary. Table 3. Presentation of the simulations Simulation Construction state Scenario/Assumptions 1.a Part 1: Optimistic 1.b Part 2: Pessimistic 2.a Part 1: Pessimistic 2.b Part 2: Optimistic The foundations elements are done. In the ground floor, the slab, columns and walls are done. In the first floor, the slab, the beams, the columns and walls are done. Everything is done (structural and nonstructural). Same as 1.a Part 1 Same as 1.b Part 2 7 The tasks are done with a performance inferior or equal to 5 (except from 3), that is to mean that nothing is over budget neither behind schedule. All the remaining tasks have a performance superior or equal to 5 (or equal to 3) that is to mean that the corresponding works are over budget and/or behind schedule. The tasks accomplished have a performance superior or equal to 5 (or equal to 3). All the remaining tasks have a performance inferior or equal to 5 (except from 3).

8 1.a 1.b 2.a 2.b Figure 3. Results obtained. Figure 3 illustrates the results obtained in temporary views for the four simulations representing the outline of the house. However, if the objective is to visualize the non-structural part of the house such as plumbing equipment or partition walls, other views should be provided. In this case, it is more appropriate to make a section view of the house. The presented views show that the transposition of performance from tasks to Revit elements is successful, since the colours reflect the assumptions made. Moreover, with the colour code opted, it is easy to identify which are the sensitive areas of the project. The cool colours e.g. blue and green are indicative that there are no specific issues whilst the warm colours e.g. red and yellow warn that there is a critical aspect. Furthermore since the ID numbers are available on the Excel sheet Performance per Element, the user has an access to any element he wants to have more information if needed. However, the use of the tool during this pilot case underlined several drawbacks. Firstly, the manual entry of task numbers in the Revit file is inconvenient because it is mainly prone to error. Moreover, the non-automated connection between tasks and elements requires that the schedule, or more specifically the order of tasks, does not change. Otherwise, the entry of task numbers has to be repeated, and for big projects it can be time-consuming. Secondly, since Revit is object-oriented, the level of detail of the schedule cannot always be transposed in the model. For example, considering the task Walls finishing is irrelevant because the element wall includes in the software all the materials, from the core material to the finishing layer. Besides, the connection element/task is not necessarily univocal. So the efficiency of the transposition task to element is limited by the element approach of Revit. 8

9 6. Conclusions The EVM/BIM tool created showed that EVM is a powerful management technique that enables the user to easily visualize the cost and time performance of a project construction execution with the help of a colour code system. The pilot study is globally positive. It provided a successful snapshot of the financial and time status of the construction works. However, the simulations presented two extreme situations: optimistic and pessimistic ones. Usually the reality is more complex, so in order to check its real efficiency, as a further development, the tool should be tested in real in-situ conditions. A real case study would also allow us to have some feedback from the construction managers, in order to check if the tool is useful to alert them when a situation becomes critical in terms of time and/or cost, and assisted them to make prompt and efficient decisions. Finally, the tool has a good potential that can be deeply utilised for a more automated use. 7. References [1] C. Eastman, P. Teicholz, R. Sack and K. Liston, BIM Handbook, A Guide for Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors, 2nd ed., New Jersey: John Wiley & Sons, Inc., [2] B. Hardin, BIM and Construction Management, Indianapolis: Wiley Publishing, [3] R. Manning and J. Messner, Case studies in BIM implementation for programming of healthcare facilities, ITcon, vol. 13, pp , [4] N. Chevallier and A. Russel, Automated schedule generation, Canadian Journal of Civil Engineering, vol. 26, no. 6, pp , [5] E. Tauscher, E. Mikulakova, E. Beucke and M. König, Automated generation of construction schedules based on the IFC object model, Computing in Civil Engineering 2009, pp , [6] M. Kataoka, Automated generation of construction plans from primitive geometries, Journal of Construction Engineering and Management, vol. 134, no. 8, pp , [7] H. Kim, K. Anderson, L. SangHyun and J. Hildreth, Generating construction schedules through automatic data extraction using open BIM (building information modeling) technology, Automation in Construction, vol. 35, pp , [8] K. Sulankivi, K. Kähkönen, T. Mäkelä and M. Kiviniemi, 4D-BIM for Construction Safety Planning, [Online]. Available: [Accessed 11 November 2015]. [9] S. Zhang, J. Teizer, J.-K. Lee, C. M. Eastman and M. Venugopal, Building Information Modeling (BIM) and Safety: Automatic Safety Checking of Construction Models and Schedules, 9

10 Automation in Construction, vol. 29, pp , [10] Q. Fleming and J. Koppelman, Earned value project management, 4th ed., Newtowns Square: Project Management Institute, [11] R. Kenley and T. Harfield, Construction Project Control Methodologies and Productivity Improvement: EVM, BIM, LBM, in Engineering, Project, and Production Management Conference, Gold Coast, Australia, September 2-5, [12] W. Abba, How Earned Value Got to Prime Time: A Short Look Back and Glance Ahead, [Online]. Available: Glance%20Ahead.abba.pdf. [Accessed 28 October 2015]. [13] Project Management Institute, Practical Standard for Earned Value Management, Newtowns Square: Project Management Institute, [14] F. Anbari, Earned Value Project Management Methods and Extensions, Project Management Journal, vol. 34, no. 4, pp , [15] A. Foremny, P. Kluczuk and A. Nicał, Design and implementation of automated, mobile construction projects monitoring system (MEVMS) based on Earned Value Management as an element of BIM in the execution stage, in Creative Construction Conference 2014, Prague, Czech Republic, June 21-24, [16] M. Marzouk and M. Hisham, Implementing Earned Value Management using Bridge Information Modeling, KSCE Journal of Civil Engineering, pp , 20 May [17] G. Jacobs, 3D scanning: Using multiple laser scanners on projects, Professional Surveyor Magazine, vol. 28, [18] F. N. Bosche, A. Guillemet, Y. Turkan, C. T. Haas and R. Haas, Tracking the built status of MEP works: Assessing the value of a Scan-vs-BIM system, Journal of Computing in Civil Engineering, pp. 1-28, July/August [19] Y. Turkan, F. N. Bosche, C. Haas and R. Haas, Toward automated earned value tracking using 3D imaging tools, Journal of Construction Engineering and Management, [20] S. Boeyckens and H. Neuckermans, Visual Programming in Architecture: Should Architects Be Trained as Programmers?, T. Tidafi and T. Dorta (eds) Joining Languages Cultures and Visions: CAADFutures 2009 CD-Rom, [21] I. Keough, Dynamo: designing a visual scripting interface for the Revit API (notes), See also for more information about coding Dynamo,

A BIM-based solution to support Earned Value Management in Construction

A BIM-based solution to support Earned Value Management in Construction A BIM-based solution to support Earned Value Management in Construction Anne-Marie Nsimire Mushamalirwa Thesis to obtain the Master of Science Degree in Civil Engineering Supervisor: Professor António

More information

Enhance Construction Visual As-Built Schedule Management Using BIM Technology

Enhance Construction Visual As-Built Schedule Management Using BIM Technology Enhance Construction Visual As-Built Schedule Management Using BIM Technology Shu-Hui Jan, Hui-Ping Tserng, Shih-Ping Ho Abstract Construction project control attempts to obtain real-time as-built schedule

More information

GA2016 XIX Generative Art Conference

GA2016 XIX Generative Art Conference THE INTRODUCTION OF BIM METHODOLOGY IN EDUCATION (Paper) Topic: Architecture, Advanced Teaching Author(s): Alcinia Zita Sampaio Portugal, University of Lisbon, Department of Civil Engineering and Architecture

More information

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models Neo Chan The Hong Kong Polytechnic University, Hong Kong (email: neo.kychan@polyu.edu.hk)

More information

TEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL

TEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL F. Madeo and M. A. Schnabel (eds.), Across: Architectural Research through to Practice: 48 th International Conference of the Architectural Science Association 2014, pp. 421 432. 2014, The Architectural

More information

Application of Building Information Modelling (BIM) in Construction Planning Process

Application of Building Information Modelling (BIM) in Construction Planning Process Application of Building Information Modelling (BIM) in Construction Planning Process Amala Merlin Jose 1, Jeevan Jacob 2 1Pursuing Masters in Civil Engg. from APJ Abdul Kalam Technological University,

More information

Keywords: BIM; Building Information Modelling; RFID; Information System; Facility Management, Maintenance Management

Keywords: BIM; Building Information Modelling; RFID; Information System; Facility Management, Maintenance Management INTEGRATED BIM/RFID-BASED FACILITY MANAGEMENT SYSTEM 1 YU-CHENG LIN, 2 YEN-PEI CHEN, 3 YU-CHIH SU 1,2,3 Department of Civil Engineering, National Taipei University of Technology, Taipei, Taiwan Email:

More information

STUDY ON BIM-BASED STRUCTURAL WORKING DRAWING DESIGN SYSTEM

STUDY ON BIM-BASED STRUCTURAL WORKING DRAWING DESIGN SYSTEM STUD O BIM-BASED STRUCTURAL WORKIG DRAWIG DESIG SSTEM ong Wang, PhD, PMP, wangyong_tj@126.com Beijing Urban Construction Group Co. Ltd., Beijing, China Department of Civil Engineering, Tsinghua University,

More information

A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1

A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1 A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1 Yi-Wen Chen & Shang-Hsien Hsieh Department of Civil Engineering, National Taiwan University, Taipei, Taiwan ABSTRACT: Since the

More information

Utilization of BIM-based Automated Safety Checking in Construction Planning

Utilization of BIM-based Automated Safety Checking in Construction Planning Utilization of BIM-based Automated Safety Checking in Construction Planning Kristiina Sulankivi 1, Sijie Zhang 2, Jochen Teizer 3, Charles M. Eastman 4, Markku Kiviniemi 5, Ilkka Romo 6, Leif Granholm

More information

A Framework for Collaboration Management of BIM Model Creation in Architectural Projects

A Framework for Collaboration Management of BIM Model Creation in Architectural Projects A Framework for Collaboration Management of BIM Model Creation in Architectural Projects Yu-Cheng Lin* 1 and Hui-Hsuan Yang 2 1 Professor, Department of Civil Engineering, National Taipei University of

More information

CONSTRUCTION SITE BIM REQUIREMENTS

CONSTRUCTION SITE BIM REQUIREMENTS CONSTRUCTION SITE BIM REQUIREMENTS Marco L. Trani 1, Manuele Cassano, Massimo Minotti and Davide Todaro Department of Architecture, Built Environment and Construction Engineering, Politecnico di Milano

More information

The Development of BIM Model-based Construction Project Performance Evaluation Mechanism

The Development of BIM Model-based Construction Project Performance Evaluation Mechanism Civil Engineering and Architecture 3(5): 128-135, 2015 DOI: 10.13189/cea.2015.030505 http://www.hrpub.org The Development of BIM Model-based Construction Project Performance Evaluation Mechanism Yi-Jao

More information

Field BIM and Supply Chain Management in Construction: an On-going Monitoring System

Field BIM and Supply Chain Management in Construction: an On-going Monitoring System Creative Construction Conference 2016 Field BIM and Supply Chain Management in Construction: an On-going Monitoring System Vito Getuli 1, Silvia Mastrolembo Ventura 2, 3,*, Pietro Capone 1, Angelo L. C.

More information

QUALITY BEYOND CONSTRUCTION IN AN ITALIAN HOSPITAL

QUALITY BEYOND CONSTRUCTION IN AN ITALIAN HOSPITAL QUALITY BEYOND CONSTRUCTION IN AN ITALIAN HOSPITAL By BIM manager Elisa Spallarossa SOLIBRI.COM 2 This case study focuses on how Solibri Model Checker can be utilized in a hospital and other asset projects

More information

Experiencing Interoperability of BIM in a Stadium Project in China

Experiencing Interoperability of BIM in a Stadium Project in China Experiencing Interoperability of BIM in a Stadium Project in China Cheng Zhang 1, Bo Liu 2, Guobin Gong 3 1) Lecturer, Department of Civil Engineering, Xi an Jiaotong-Liverpool University, Suzhou, Jiangsu,

More information

Application of BIM on Documenting Construction Defects

Application of BIM on Documenting Construction Defects Application of BIM on Documenting Construction Defects Ying-Mei Cheng Abstract This study aims to establish a system prototype using Autodesk Revit API to code the add-ins which display 3D elements with

More information

A Web-based Framework of Project Performance and Control System

A Web-based Framework of Project Performance and Control System A Web-based Framework of Project Performance and Control System Jui-Sheng Chou* National Taiwan University of Science and Technology, Department of Construction Engineering Taipei, Taiwan jschou@mail.ntust.edu.tw

More information

Development of a sub building information model for 4D structural safety analysis during construction

Development of a sub building information model for 4D structural safety analysis during construction icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) Development of a sub building information model for

More information

IDES-EDU. WP2 Workshop. Building Information Modelling and Interoperability. Anna Osello & Carlo Caldera 4/17/2013. About BIM

IDES-EDU. WP2 Workshop. Building Information Modelling and Interoperability. Anna Osello & Carlo Caldera 4/17/2013. About BIM WP2 Workshop Building Information Modelling and Interoperability Anna Osello & Carlo Caldera About BIM Building Information Modelling (BIM) is the process of generating and managing digital data about

More information

BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF. Extended Abstract Master s Degree in Civil Engineering

BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF. Extended Abstract Master s Degree in Civil Engineering BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF Bernardo Ferreira e Silva Extended Abstract Master s Degree in Civil Engineering Supervisors Profª. Alcínia Zita de Almeida Sampaio Jury President:

More information

BIM and Concrete Formwork Repository

BIM and Concrete Formwork Repository BIM and Concrete Formwork Repository Pavan Meadati, Ph.D., LEED AP Southern Polytechnic State University Marietta, Georgia Javier Irizarry, Ph.D., PE. Georgia Institute of Technology Atlanta, Georgia Amin

More information

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES Mohamed Marzouk, Associate Professor, mm_marzouk@yahoo.com Mohamed Hisham, Graduate Student, mohamed1984_h@hotmail.com Construction

More information

Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste

Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste Daniel Santos da Silva DECivil, Instituto Superior Técnico, Universidade de

More information

Model Interoperability in Building Information Modelling

Model Interoperability in Building Information Modelling Model Interoperability in Building Information Modelling Jim Steel, Robin Drogemuller Queensland University of Technology/ CRC for Construction Innovation Alternate First Page Only Summary Problem Domain:

More information

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D

More information

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction 1666 An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction Hexu LIU 1, Zhen LEI 2, Hong Xian LI 3, Mohamed AL-HUSSEIN 4 1 Hole School of Construction

More information

Effective Application of Building Information Modeling in Construction

Effective Application of Building Information Modeling in Construction Volume-7, Issue-2, March-April- 2017 International Journal of Engineering and Management Research Page Number: 52-57 Effective Application of Building Information Modeling in Construction Akhilasree D

More information

Automated Cost Analysis of Concept Design BIM Models

Automated Cost Analysis of Concept Design BIM Models Automated Cost Analysis of Concept Design BIM Models ABDELMOHSEN Sherif, LEE Jinkook and EASTMAN Chuck College of Architecture, Georgia Institute of Technology, Atlanta, GA, USA sherif.morad@gatech.edu,

More information

MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems

MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems Alan Espinoza MMC Contractors Jake Olsen, PE DEWALT Learning Objectives Learn how Revit can be used to efficiently

More information

Stepping into Variable Height Retaining Walls

Stepping into Variable Height Retaining Walls Stepping into Variable Height Retaining Walls Eric Cylwik Sundt Construction, Inc. CR 2499 - Mechanically-stabilized earth (MSE) walls are inherently complex shapes; smoothly curving in all 3 dimensions

More information

TUTORIALS. BIM Workflow in Advance Design

TUTORIALS. BIM Workflow in Advance Design TUTORIALS BIM Workflow in Advance Design About GRAITEC Tutorials GRAITEC technology evolution is driven by years of practical experience and combined with user feedback to provide the most intelligent

More information

Technion Graduate BIM Course

Technion Graduate BIM Course Technion Graduate BIM Course Advanced Building Information Modeling for Students of Architecture, Engineering and Construction 019627 for CEE Students 209XXX for Arch students Goals and Outline Design

More information

Advance Concrete. PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES

Advance Concrete. PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES ADAGP Franck Hammoutène Architecte / photo : Luc Boegly Advance Concrete PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES www.graitec.com

More information

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Abstract Considering the significant amount of material wasted in the construction

More information

A Building Information Modelling-Based Tool for Heuristically Assessing Façade Manufacturability

A Building Information Modelling-Based Tool for Heuristically Assessing Façade Manufacturability A Building Information Modelling-Based Tool for Heuristically Assessing Façade Manufacturability Eleanor VOSS 1, Mauro OVEREND 2, and Will STEVENS 3 1 Glass and Façade Technology Research Group, Department

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

Building Information Models as the Basis of Business Strategy: A Case Study of an Integrated BIM-Based System for Construction Management

Building Information Models as the Basis of Business Strategy: A Case Study of an Integrated BIM-Based System for Construction Management Building Information Models as the Basis of Business Strategy: A Case Study of an Integrated BIM-Based System for Construction Management Ligia D. Trindade, ligiatrindade@usp.br Polytechnic School of the

More information

Applications of Building Information Modeling (BIM) in Knowledge Sharing and Management in Construction

Applications of Building Information Modeling (BIM) in Knowledge Sharing and Management in Construction Applications of Building Information Modeling (BIM) in Sharing and Management in Construction Shu-Hui Jan, Shih-Ping Ho, Hui-Ping Tserng Abstract Construction knowledge can be referred to and reused among

More information

Development of an Efficient Tapered Slip-Form System Applying BIM Technology

Development of an Efficient Tapered Slip-Form System Applying BIM Technology Engineering, 2013, 5, 693-699 http://dx.doi.org/10.4236/eng.2013.59082 Published Online September 2013 (http://www.scirp.org/journal/eng) Development of an Efficient Tapered Slip-Form System Applying BIM

More information

Saurabh Gangwar 2018 Project Management Symposium

Saurabh Gangwar 2018 Project Management Symposium Name UMD Project Management Symposium May 10-11, 2018 Slide 1 FROM PEOPLE MANAGEMENT TO INFORMATION MANAGEMENT Impact of technology on project management in the design and construction industry Saurabh

More information

Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models

Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models ICT Enhanced Buildings Potentials Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models Cand. Scient. Bygningsinformatik. Semester 1, 2010. CONTENT

More information

A New Approach for Construction Engineering Design Management Research Based on BIM LIU Qing 1, a

A New Approach for Construction Engineering Design Management Research Based on BIM LIU Qing 1, a International Conference on Education Technology, Management and Humanities Science (ETMHS 2015) A New Approach for Construction Engineering Design Management Research Based on BIM LIU Qing 1, a 1 Qinghai

More information

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia JUNE 2017 BIM FOR SURVEYORS Survey Economics State of recovery Tracking Wildlife With a total station Measuring a Meridian Time in 1700s Philadelphia A NEW MODEL FOR SURVEYORS As BIM moves into more projects

More information

On Application of BIM Technology in Building Design Stage

On Application of BIM Technology in Building Design Stage Abstract On Application of BIM Technology in Building Design Stage Juan Wang Zhengzhou Institute of Technology, Zhengzhou 450044, China Rapid development of modern information technology has intensified

More information

Application of Building Information Modeling Tool for Building Project

Application of Building Information Modeling Tool for Building Project Application of Building Information Modeling Tool for Building Project Amol A. Metkari 1, Dr. A. C. Attar 2 1 PG Student, Department of Civil Engineering, Rajarambapu Institute of Technology, Sangli-415

More information

Modelling structures using BIM

Modelling structures using BIM VŠB Technical University of Ostrava Faculty of Civil Engineering Department of Building Structures SUPPORTING MATERIAL Subject aims expressed by acquired skills and competences After completing this subject,

More information

The Long and Foster Headquarters Building: A Building Information Modeling Case Study

The Long and Foster Headquarters Building: A Building Information Modeling Case Study The Long and Foster Headquarters Building: A Building Information Modeling Case Study By: Megan Wortman, Robert M. Leicht, Nevena Zikic, John I. Messner Technical Report No. 55 Copyright April 2008 Computer

More information

Building Information Modeling to Facilities Information Management and Beyond

Building Information Modeling to Facilities Information Management and Beyond Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas

More information

Autodesk MEP Engineering Solutions. Engineer for energy efficiency.

Autodesk MEP Engineering Solutions. Engineer for energy efficiency. Autodesk MEP Engineering Solutions Engineer for energy efficiency. Deliver Sustainable Building Systems More Quickly and Economically Autodesk MEP Engineering Solutions help MEP engineers, designers, and

More information

SENIOR THESIS FINAL PROPOSAL

SENIOR THESIS FINAL PROPOSAL Submitted 12/10/2010 Construction Management Advisor: Dr. Robert Leicht [The following report presents a detailed overview of the research topics to be done on the Office Renovation Building. A series

More information

EcoDomus, Inc

EcoDomus, Inc www.ecodomus.com Introduction BIM Data Requirements & Guidelines COBie: Data Entry and Responsibility Matrix COBie: Quality Control BIM and BAS Integration: Use Cases Mobile BIM and Work Orders Asset View

More information

APPLYING CLIMATE-BASED DAYLIGHT MODELING (CBDM) FOR A MACRO SCALE MASTER PLAN DESIGN CASE STUDY: THE GREAT CITY IN CHINA

APPLYING CLIMATE-BASED DAYLIGHT MODELING (CBDM) FOR A MACRO SCALE MASTER PLAN DESIGN CASE STUDY: THE GREAT CITY IN CHINA APPLYING CLIMATE-BASED DAYLIGHT MODELING (CBDM) FOR A MACRO SCALE MASTER PLAN DESIGN CASE STUDY: THE GREAT CITY IN CHINA M. Sadeghipour Roudsari 1,*, Y. Yi 2 and C. R. Drew 3 1 Architect, Adrian Smith

More information

Cost Optimization of Construction Projects using Building Information Modelling

Cost Optimization of Construction Projects using Building Information Modelling IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 05, 2016 ISSN (online): 2321-0613 Cost Optimization of Construction Projects using Building Information Modelling Abstract

More information

A Real-time Building HVAC Model Implemented as a Plug-in for Trimble SketchUp Zaker A. Syed 1 and Thomas H. Bradley 2

A Real-time Building HVAC Model Implemented as a Plug-in for Trimble SketchUp Zaker A. Syed 1 and Thomas H. Bradley 2 A Real-time Building HVAC Model Implemented as a Plug-in for Trimble SketchUp Zaker A. Syed 1 and Thomas H. Bradley 2 1 Graduate Research Assistant, Department of Mechanical Engineering, Colorado State

More information

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study 89 Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3

More information

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE

More information

Approach for Automated Planning Using 5D-BIM

Approach for Automated Planning Using 5D-BIM Approach for Automated Planning Using 5D-BIM Jani Mukkavaara, jani.mukkavaara@ltu.se Luleå University of Technology, Sweden Gustav Jansson, gustav.jansson@ltu.se Luleå University of Technology, Sweden

More information

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal PTI Journal Technical Session Paper USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS By FLORIAN AALAMI Authorized reprint from: December 2018 issue of the PTI Journal Copyrighted 2018, Post Tensioning

More information

A BIM-based tool to support time risk management. in construction projects. Civil Engineering

A BIM-based tool to support time risk management. in construction projects. Civil Engineering A BIM-based tool to support time risk management in construction projects Marco Petrus Adrianus van Rijn Thesis to obtain the Master of Science degree in Civil Engineering Supervisor: Professor António

More information

UNIVERSITY COLLEGE CORK

UNIVERSITY COLLEGE CORK UNIVERSITY COLLEGE CORK MASTERS IN IT IN AEC CE6014 COMPUTER Mediated Construction The Benefits of BIM Tools to the Design Engineer By Sandra McSwiney (104492617) Date: November 2014 Module Leader: Dr.

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

BIM Support for the Construction Project from a Suppliers POV

BIM Support for the Construction Project from a Suppliers POV CS10324 BIM Support for the Construction Project from a Suppliers POV Dr. Nils Krönert Hilti AG, Schaan, Liechtenstein Connor Christian Lead Designer, Kiewit Learning Objectives The possibilities of project

More information

ACSE AWARDS Large Project Parliament Square, Hobart

ACSE AWARDS Large Project Parliament Square, Hobart ACSE AWARDS 2018 Large Project Parliament Square, Hobart Project Credit Client Citta Property Group Architect FJMT Structural Engineer Taylor Thomson Whitting Contractor Hansen Yuncken Other Consultants

More information

CS21793 Transition to Operations with Building Ops: The (Eye) in BIM

CS21793 Transition to Operations with Building Ops: The (Eye) in BIM CS21793 Transition to Operations with Building Ops: The (Eye) in BIM Mark Mergenschroer Bernhard TME Learning Objectives Learn how to track maintenance data before taking ownership Learn how to increase

More information

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer PROJECT NAME By signature below, this Execution Plan is herewith adopted and incorporated into the Agreement, dated, for Professional Design Services between and Duke University. Duke University Architect

More information

Research Article An Integrated BIM System to Track the Time and Cost of Construction Projects: A Case Study

Research Article An Integrated BIM System to Track the Time and Cost of Construction Projects: A Case Study Journal of Construction Engineering Volume 2015, Article ID 579486, 10 pages http://dx.doi.org/10.1155/2015/579486 Research Article An Integrated BIM System to Track the Time and Cost of Construction Projects:

More information

BIM model management in the design of structures

BIM model management in the design of structures BIM model management in the design of structures João Pedro Diniz Flor de Oliveira Instituto Superior Técnico University of Lisbon, Av. Rovisco Pais 1, 1049-001 Lisbon, Portugal ABSTRACT Building Information

More information

DYNAMIC PROTOTYPE BIM MANUAL FOR A FITNESS CENTER V1.0 November 21, 2011

DYNAMIC PROTOTYPE BIM MANUAL FOR A FITNESS CENTER V1.0 November 21, 2011 DYNAMIC PROTOTYPE BIM MANUAL FOR A FITNESS CENTER V1.0 November 21, 2011 Developed by: Air Force Center for Engineering and the Environment Ralph Rick Sinkfield, YD-03, DAF Project Manager Email: ralph.sinkfield@us.af.mil

More information

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING Baltimore, Maryland Dan Weiger Architectural Engineering, 5th Year Construction Management Option Thesis Proposal Advisor: Dr. John I. Messner December 12,

More information

From BIM Requirements to Facility Management

From BIM Requirements to Facility Management From BIM Requirements to Facility Management BIM based scenario in a large-scale public building A. Ciribini, Università degli Studi di Brescia A. Vanossi, Politecnico di Milano A. Tegon, CMB Carpi G.

More information

A BIM Based Approach for Quality Supervision of Construction Projects

A BIM Based Approach for Quality Supervision of Construction Projects Creative Construction Conference 2016 A BIM Based Approach for Quality Supervision of Construction Projects Zhiliang Ma*, Na Mao and Qiliang Yang Department of Civil Engineering,Tsinghua University, Beijing,100084,China

More information

CHAPTER 7 Building Information Modeling

CHAPTER 7 Building Information Modeling CHAPTER 7 Building Information Modeling Dr Nabil Elsawalhi Associate Professor of Construction Management 1 Information and Communication Technology/ Building Information Modeling New approaches to construction

More information

5D BIM: Shaping the Future of the Construction Industry. Gain insights into how you can leverage tools to work smarter in this era

5D BIM: Shaping the Future of the Construction Industry. Gain insights into how you can leverage tools to work smarter in this era 5D BIM: Shaping the Future of the Construction Industry Gain insights into how you can leverage tools to work smarter in this era Industry Overview The architecture, engineering and construction (AEC)

More information

Implementation of Virtual Design Reviews in the Generation of As-Built Information

Implementation of Virtual Design Reviews in the Generation of As-Built Information Construction Research Congress 2018 285 Implementation of Virtual Design Reviews in the Generation of As-Built Information Fadi Castronovo 1 ; Bassam Awad 2 ; and Reza Akhavian 3 1 School of Engineering,

More information

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent 8353 University Boulevard, Moon Township, PA 15108 Thesis Proposal THIRD REVISION 3/19/2010 Table of Contents Executive

More information

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING Baltimore, Maryland Dan Weiger Architectural Engineering, 5th Year Construction Management Option Thesis Proposal Advisor: Dr. John I. Messner January 26, 2009

More information

Durability evaluation software system of concrete structure based on BIM and 4D technology

Durability evaluation software system of concrete structure based on BIM and 4D technology icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) Durability evaluation software system of concrete structure

More information

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER PROJECT NAME BIM EXECUTION PLAN PROJECT INFORMATION CLIENT PROJECT NAME PROJECT NUMBER XX XXXXX XX XXXXX XXXXXXXXXXXXXXXXXXXXXXXXX DATE XXXXXXXX 2016 PROJECT LOCATION & ADDRESS XXXXX, XXXXX. INTRODUCTION...

More information

7 Steps to Data Blending for Predictive Analytics

7 Steps to Data Blending for Predictive Analytics 7 Steps to Data Blending for Predictive Analytics Evolution of Analytics Just as the volume and variety of data has grown significantly in recent years, so too has the expectations for analytics. No longer

More information

Information Fusion Harnessing the I for Lifecycle Data Management

Information Fusion Harnessing the I for Lifecycle Data Management Brent Mauti Global Director Design Technology, Board of Directors CANBIM Treasurer Toronto BIM Community Information Fusion Harnessing the I for Lifecycle Data Management Name of Presentation Agenda BIM

More information

SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS

SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS 1 SAGAR M MALSANE, 2 AMEY Z SHETH 1 Assistant Professor, National Institute of Construction Management & Research, India 2 phd

More information

BIM 5D model. Ir. Dr. Sam C. M. Hui Faculty of Science and Technology

BIM 5D model. Ir. Dr. Sam C. M. Hui Faculty of Science and Technology SBS5322 Basics of Building Information Modelling http://ibse.hk/sbs5322/ BIM 5D model Ir. Dr. Sam C. M. Hui Faculty of Science and Technology E-mail: cmhui@vtc.edu.hk Jan 2018 Contents The 5th dimension

More information

A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects

A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects Jonathan W. Elliott, Ph.D., Svetlana Olbina, Ph.D., and Manikandan Natesan Colorado State University

More information

ARIZONA STATE UNIVERSITY UNIVERSITY SERVICES ADMINISTRATIVE SERVICES GOALS TRACKING APPLICATION

ARIZONA STATE UNIVERSITY UNIVERSITY SERVICES ADMINISTRATIVE SERVICES GOALS TRACKING APPLICATION ARIZONA STATE UNIVERSITY UNIVERSITY SERVICES ADMINISTRATIVE SERVICES GOALS TRACKING APPLICATION STATEMENT OF PROGRAM OR PRACTICE University Services designed a new innovative Goals Program which was launched

More information

Oracle Hyperion Planning for Interactive Users

Oracle Hyperion Planning for Interactive Users Oracle University Contact Us: 1.800.529.0165 Oracle Hyperion Planning 11.1.2 for Interactive Users Duration: 0 Days What you will learn This course is designed to teach you how to use Planning. It includes

More information

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM Mounir El Asmar, Ph.D., Assistant Professor, asmar@asu.edu School of Sustainable Engineering and the Built Environment,

More information

Building Management System to support building renovation

Building Management System to support building renovation Snapshots of Doctoral Research at University College Cork 2010 Building Management System to support building renovation Hang Yin Department of Civil and Environmental Engineering, UCC Introduction Many

More information

Cracking the Vault: Implementing Autodesk Vault Collaboration AEC into Civil/Survey Firms

Cracking the Vault: Implementing Autodesk Vault Collaboration AEC into Civil/Survey Firms Cracking the Vault: Implementing Autodesk Vault Collaboration AEC into Civil/Survey Firms Joe Hedrick, LS, EIT IMAGINiT Technologies CI4980-V Do you have challenges managing data while working in project

More information

Tekla Software in practice BIM and precast concrete fabrication. Loe Betongelementer, norway. Copyright: LPO Architects

Tekla Software in practice BIM and precast concrete fabrication. Loe Betongelementer, norway. Copyright: LPO Architects Tekla Software in practice BIM and precast concrete fabrication Loe Betongelementer, norway Copyright: LPO Architects Loe Betongelementer integrates Tekla to their workflow s Loe Betongelementer has used

More information

VIRTUAL CONSTRUCTION: ADVANTAGES AND EXECUTION. By Carl Veillette

VIRTUAL CONSTRUCTION: ADVANTAGES AND EXECUTION. By Carl Veillette VIRTUAL CONSTRUCTION: ADVANTAGES AND EXECUTION By Carl Veillette December 2012 TABLE OF CONTENTS Virtual construction Advantages of building information modeling (BIM) Three phases of migration BIM 1.0

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

Table of contents. EC3 Steel Design - Class 4 calculation of effective characteristics... 5

Table of contents. EC3 Steel Design - Class 4 calculation of effective characteristics... 5 What's New 2018 R2 Table of contents NEW OPTIONS & IMPROVEMENTS... 5 EC3 Steel Design - Class 4 calculation of effective characteristics... 5 Optimization of theoretical reinforcement according to EC2

More information

Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA

Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA M. Mangal a, Q. Wang a and J.C.P. Cheng a a Department of Civil and Environmental Engineering, The Hong Kong University

More information

ORACLE HYPERION PLANNING

ORACLE HYPERION PLANNING ORACLE HYPERION PLANNING KEY FEATURES AND BENEFITS KEY FEATURES: Multi-dimensional / multi user planning with a powerful business rules engine Flexible workflow and plan management capabilities Comprehensive

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation NEW PICKIE REQUIRED Course Objectives This course objectives are to teach participants: Introduction to the user interface, How to plan projects without resources, Filters, layouts and printing, Baselines,

More information

Tekla Structures for Precast Concrete Industry TRANSFORMING THE WAY THE WORLD WORKS

Tekla Structures for Precast Concrete Industry TRANSFORMING THE WAY THE WORLD WORKS Tekla Structures for Precast Concrete Industry Model, Fabricate and Erect all Precast Structures Faster and with Better Quality Working with the constructible Tekla models minimizes costly surprises and

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Strategic Revit MEP Object Organization From BIM to Asset Management

Strategic Revit MEP Object Organization From BIM to Asset Management MEP20732 Strategic Revit MEP Object Organization From BIM to Asset Management Jorge Quiroz Director DCV Consultores Sebastian Zaje Senior Technical Specialist - LATAM Autodesk George Broadbent Director

More information