1 Commissioning Under the Influence Redefining the Traditional Role of the Commissioning Agent in the Design and Construction of the Building Envelope National Conference on Building Commissioning: May 2-4, 2007 Presented by: Fiona Aldous Daniel J. Lemieux, AIA

2 Defining the Building Envelope any enclosing covering, membrane, or structure. "The envelope has to respond both to natural forces and human values. The natural forces include rain, snow, wind and sun. Human concerns include safety, security, and task success. The envelope provides protection by enclosure and by balancing internal and external environmental forces. To achieve protection it allows for careful control of penetrations. A symbol of the envelope might be a large bubble that would keep the weather out and the interior climate in." Richard Rush, The Building Systems Integration Handbook

3 Influences on Building Envelope: Geography and Climate -Regional geography including orientation, slope, adjacent buildings, proximity to large bodies of water (fresh and salt) - Temperature impact on expansion and contraction of materials -Radiation and UV light impact varies with elevation - Biological attack resulting from local pests

4 Wind Loads and Precipitation roof -Water -Ice/ Snow - Vapor (in the form of moist air and vapor diffusion) impacting the manner of moisture entry to interior: - Penetration of liquid moisture, typically rain wall -Migration of moisture through capillary action wp - Air movement and wind results in pressure differentials: bgwp -wind effect -stack effect -HVAC effects -Combined effects

5 Moisture-Laden Airflow and Vapor Drive -Condensation resulting from vapor in air, relative humidity and surface temperature differentials. HVAC & IAQ - Vapor diffusion - the movement of vapor from an area of high pressure to an area of low pressure through materials independent of air flow. Building envelopes are complex systems.. subjected to numerous influences and risk Exterior envelope interface areas prone to failure how commissioning can help.

6 Why Commission Under the Influence? Uncontrolled rainwater penetration and moisture ingress are two of the most common threats to the structural integrity and performance of the building envelope. Together, they represent up to 80% of all construction-related claims in the United States. 80% Errors and omissions in the design and installation of the façade interfaces, rather than in the façade materials, components and systems themselves, are the primary (and most frequently overlooked) sources of uncontrolled rainwater penetration through the building envelope. It starts with technical competence and good design

7 Conveying Proper Design Intent From Architect To GC / Subcontractor To Dispute $6M Lawsuit on a $12.5M project

8 Design Intent Lost Misdiagnosis Rush to Judgment Missing end-dam at masonry wall beyond

9 The Rescue Bulk Rainwater Penetration As-Built Construction Repair

10 The Rescue Bulk Rainwater Penetration As-Built Construction Repair

11 The Rescue Bulk Rainwater Penetration As-Built Construction Repair

12 The Rescue Bulk Rainwater Penetration As-Built Construction Repair

13 The Rescue Bulk Rainwater Penetration Repair As-Built Construction

14 Substantially Complete? 06_ RCI

15 Failing (by Design) From Architect To Subcontractor 06_ RCI To Rescue

16 The Rescue...

17 Veterinary Exterior Wall Permeability Problems... High moisture storing masonry cladding materials and un-vented sheet metal roof in combination with interior high levels of RH and vinyl wall coverings, combined to result in a wall and roof assembly that could not breathe, the development of microbial growth and deterioration of exterior wall components.

18 Natatorium Air Barrier Deficiencies igh interior moisture conditions and lack of ontinuous air barrier combined to allow arm, moisture-laden air to migrate into the xterior envelope, resulting in condensation nd deterioration of exterior envelope aterials

19 NIBS Guideline 3 3 A Call for Change "We cannot solve the problems that we have created with the same thinking that created them." -Albert Einstein

20 Commissioning Begins with Good Design The pre and design development phase has the greatest possibilities for creating coordinated and detailed envelope assemblies to facilitate a quality installation. If left to the field installation phase, the building envelope commissioning process will serve only to document, rather than complement the overall design development and commissioning processes. NIBS Guideline 3 provides an overview for the Building Envelope Commissioning Process and implementation, however it must be adapted to suit the specific project and goals

21 NIBS Guideline 3 Exterior Enclosure Technical Requirements for the Commissioning Process From Design Phase: Design Development Project Objectives Meeting Design Phase: Construction Documents Participate in Project Review Meeting ( ) Update Cx Team ( 6.2.1) Identify Outstanding Enclosure Issues Prepare Construction Documents Cx Reviews of Design Docs. ( 6.2.8) Update OPR ( ) Update Basis of Design (BOD) ( ) Update Cx Plan ( (b )) Develop Cx Process Requirements for Construction Documents Phase ( 6.2.4) Constructi on Checklists ( 6.2.5) Update Systems Manual ( 6.2.6) 20% of systems re BOD ( ) Develop Cx Requirements for Construction Documents ( 6.4) Acceptance Requiremen ts ( 6.3) Training Requirement s ( 6.2.7) & ( 6.5) Project Objectives Meeting Owner Acceptance of Constr. Documents Products Final Objectives Meeting for Phase ( ) Owner Acceptance of Cx Products ( 6.3) To Construction Phase ( 7)

22 Project Design Phases and Commissioning Design Phases: Commissioning Process: Pre-Design Phase: Pre-Design is a preparatory phase of the project delivery process in which the Owner s Project Requirements are developed and defined. See Part 5 of this Guideline. Design Phase: During the Design Phase of the project delivery process the Owner s Project Requirements are translated into construction documents. 1. Establish Performance requirements 2. Develop Commissioning plan 3. Validation and documentation Design Sub-Phases: The Design Phase is typically broken into three subphases; with each being about 1/3 of the total design phase. These subphases have a variety of names but for this document the following terms will be used. Schematic Design, Design Development and Construction Documentation. Schematic Design: (Also referred to as 35% Design ). A phase of building design that produces documents that establish the conceptual design of a project, illustrating the scale and relationship of the Project components including preliminary selections of major building systems and construction materials. Design Development: (Also referred to as 65% Design ). A phase of building design that produces documents that illustrate and describe the refinement of the design of a Project, establishing the scope, relationships, forms, size and appearance of the Project and identifying major materials and systems and establishing their quality levels. Construction Documentation: (Also referred to as 100% Design ) A phase of building design that produces documents that (1) set forth in detail the requirements for the construction of a Project and (2) establish in detail the quality of materials and systems required for the Project. Final Construction Documents are prepared as required to solicit, procure and construct the project and include drawings, specifications, contract forms and conditions, bidding requirements and resource documents. NIBS Commissioning Guideline 3, 2006

23 NIBS Guideline 3 Commissioning-Focused Review of Design Documents (c) Building Exterior Enclosure System-Specific Review. The Commissioning Authority should verify that, within the areas selected for review, the design complies with the Owner s Project Requirements. The intent of this review is to determine if there are systematic errors for exterior enclosure materials and interface coordination, not to fully check the drawings. The responsibility for complete checking of the drawings for coordination, appropriateness, and accuracy remains with the Design Team (d) Building Exterior Enclosure Specification Review. The Commissioning Authority should ensure that a review of the specifications is performed to determine completeness and applicability to the project. A review of 10-20% of the building exterior enclosure specification is performed in detail for verification of compliance with the Owner s Project Requirements. Items checked include applicability of the section to the project, Commissioning Process requirements, submittal requirements, applicability of sub-systems and materials, training requirements, coordination with other sections, and coordination with the drawings.

24 Testing and Validation Lab Testing (ASTM E2099) Air Infiltration: ASTM E283 (Air Infiltration/Static) Water Infiltration: ASTM E 331 (Water Penetration/Static) ASTM E 547 (Water Penetration/Cyclic) AAMA E (Water Penetration/Dynamic) Structural: ASTM E330 (Uniform Static) ASTM E1233 (Cyclic Static) Thermal: AAMA 1503 and Field Testing Air Infiltration: AAMA Ref: ASTM E 783 (Chamber) Water Infiltration: AAMA Ref: ASTM E 1105 (Chamber) Ref: AAMA (Nozzle Test)

25 Field Certification Testing Air Infiltration ASTM E-783: Field Measurement of Air Leakage through Installed Exterior Windows and Doors Water Penetration Resistance ASTM E-1105: Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Curtain Walls, and Doors by Uniform or Cyclic Static Air Pressure Differential AAMA : Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls, and Sloped Glazing Systems Understand and Properly Apply the Standards Define Performance Standards (ASCE 7) AAMA Performance Class and the 2/3 Rule Define Scope of Testing and Failure (ASTM v. AAMA)

26 A Case Study in Commissioning (1998) Phase I: Phase II: Phase III: Phase IV: Design Period Services Schematic Design Design Development Construction Documents Pre-Construction Services Value Engineering Shop Drawing Review (Design Refinement ) Laboratory Mock-Up and Performance Testing Plant Visits Construction Period Services QA/QC Coordination Meeting (GC/CM and All Trades) Pre-Installation Meetings (Individual Trades) Bi-Monthly Skin Meetings Bi-Weekly Construction Observation (Field Sketches/Design Refinement ) Field Air and Water Penetration Resistance Testing Project Close-Out Final Open/Closed Issue Log Copies of All Field Reports, Photos, and Sketches Building Envelope Maintenance Manual

27 A Case Study In Commissioning (1998) Detailing Fig. 1: typical generic sill detail Fig. 2: revised baseline sill detail for CDs Fig. 3: development of an as-built detail Fig. 4: final interface detail at sill

28 Design Intent Realized Detailing

29 Looking Ahead The complexities that initiate the development of the building envelope commissioning plan are varied; the changing roles of the architect and contractor in the traditional design and construction process; or the management of risk; or the overriding concern for quality and performance. Yet without question; the result of a commissioning plan is to provide a documented, quality performing, reliably operating and efficient built resource for the shelter of the inhabitants needs and activities. The building envelope commissioning agent and the building envelope specialist are the opportunities for the future; to partner and produce a comprehensive, fully-documented, technically sound and verifiable building envelope commissioning plan that is both cost-effective in the near term and beneficial to the long-term durability and performance of the project.

30 Questions? Reconciliation of contractual requirements between the architect and the commissioning agent? Defining the role of building envelope consultant and building envelope commissioning agent? Joining the traditional building envelope commissioning team?

Performance Testing for Quality Assurance and Commissioning

Performance Testing for Quality Assurance and Commissioning BEST 4 Conference: April 13, 2015, Kansas City, MO Performance Testing for Quality Assurance and Commissioning Fiona Aldous Principal The most benefit to a project is obtained during the Design Phase -

More information

Guideline for Building Envelope Commissioning: New Buildings

Guideline for Building Envelope Commissioning: New Buildings Guideline for Building Envelope Commissioning: New Buildings Introduction Building envelope failures may arise from inadequacies in the design, construction and operation of buildings and appear to be

More information

Introduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1

Introduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1 Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:

More information

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap

More information

Enclosure Commissioning a crash course in reality

Enclosure Commissioning a crash course in reality Enclosure Commissioning a crash course in reality BUILD. CONNECT. ACHIEVE. Denali Jones, Building Science Engineer (EIT) RDH Building Science 0 AIA Quality Assurance The Building Commissioning Association

More information

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group

More information

Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera

Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera Walter Sebastian BMT Building Enviroment Consultants Ltd., Doktor Neergaards Vej 15, DK-2970 Hoersholm, Denmark

More information

Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning

Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning NFMT 2016 T. Stephen Kisielnicki, RWC, LEED AP, BECxP March 24, 2016 About Gale Building Envelope Technology Roof, walls,

More information

Finding Value in Building Enclosure Commissioning

Finding Value in Building Enclosure Commissioning Finding Value in Building Enclosure Commissioning Brian S. Rose, P.E. Technical Staff Jeffrey D. Kerr, P.E. Senior Project Manager 12 March 2015 www.sgh.com Course Description This presentation will outline

More information

Why test a system that has already been tested? Typical Manufacturers information for window to wall interface and basis for reported test results.

Why test a system that has already been tested? Typical Manufacturers information for window to wall interface and basis for reported test results. 1 Pre-Construction Phase, & the Laboratory or Field Mock-Up Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by Fiona Aldous Why test a system

More information

Guideline Exterior Enclosure Technical Requirements for The Commissioning Process

Guideline Exterior Enclosure Technical Requirements for The Commissioning Process Guideline 3-2006 Exterior Enclosure Technical Requirements for The Commissioning Process Joseph Deringer The Deringer Group Inc David Altenhofen Hiller Architecture Wagdy Anis Shepley Bulfinch Richardson

More information

Building Performance Testing Services

Building Performance Testing Services Building Performance Testing Services Laboratory Testing NAFS Testing: AAMA/WDMA/CSA 101/I.S. 2/A440-05: Standard/Specification for Windows, Doors and Unit Skylights AAMA/WDMA/CSA 101/I.S. 2/A440-08: North

More information

Building Enclosure Commissioning of a Student Athletic Facility

Building Enclosure Commissioning of a Student Athletic Facility Building Enclosure Commissioning of a Student Athletic Facility Presented by: Paul Totten, PE, Senior Project Manager BEST3 Conference Atlanta, Georgia 3 April 2012 www.sgh.com Presentation Outline Section

More information

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.

More information

Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment

Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment Explain the differences between waterproof, weatherproof, and water repellent. Identify a laboratory test method used for determining

More information

Efficiently Produced Construction Documents are Quality Construction Documents

Efficiently Produced Construction Documents are Quality Construction Documents Efficiently Produced Construction Documents are Quality Construction Documents Creative Disruption - AIA Minnesota November 13, 2015; 10:15 am 11:45 am Micheal J. Lough Good design makes a difference CES

More information

Building Enclosure Commissioning A review of commissioning under the influence

Building Enclosure Commissioning A review of commissioning under the influence Building Enclosure Commissioning A review of commissioning under the influence Fiona Aldous Senior Associate Wiss, Janney, Elstner Associates, Inc. Joseph J. Godfryt, AIA Principal Wiss, Janney, Elstner

More information

Technical Update: Airtightness and Water Penetration Testing for Residential Buildings

Technical Update: Airtightness and Water Penetration Testing for Residential Buildings GREEN BUILDING PROGRAM Technical Update: 2017-07-11 Airtightness and Water Penetration for Technical Update 2017-07-11 Airtightness and Water Penetration for Guideline 1 GREEN BUILDING PROGRAM GUIDELINES

More information

Field Testing and Forensic Analysis for Manufacturers

Field Testing and Forensic Analysis for Manufacturers AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION Field Testing and Forensic Analysis for Manufacturers AAMA Special Event Webinar April 28, 2015 Welcome AAMA Members Licensees Other manufacturers Industry

More information

Building Enclosure Commissioning

Building Enclosure Commissioning Building Enclosure Commissioning John Runkle, P.E. Vice President Building Sciences October 5, 2016 Program Outline Defining the Enclosure Building Science Concepts Façade Design State of the Practice

More information

Building Enclosure Performance for Existing and New Buildings

Building Enclosure Performance for Existing and New Buildings Building Enclosure Performance for Existing and New Buildings 2015 HESNI Annual Conference Rick Ziegler, PE Industry Construction Defect Claims Building Envelope - 70% Plumbing - 12% Freezing - 4% Fire

More information

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED Ministry of Municipal Affairs PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED CHANGE NUMBER: SOURCE: B-05-10-03 Ontario-mNBC CODE REFERENCE: Division B / 5.10.3. DESCRIPTION OF THE

More information

New Opportunities For Spray Polyurethane Foam

New Opportunities For Spray Polyurethane Foam New Opportunities For Spray Polyurethane Foam Presented by: Len Anastasi EXO-TEC Consulting, Inc. www.exo-tec.biz len@exo-tec.biz Recent Building Code Changes 2006 International Energy Code Increases insulation

More information

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P Provider Number:404108121 Darek Brandt, PE Chief Engineer, Building Science Solutions AIA CES DISCLAIMER Credit(s) earned on completion

More information

Building Enclosure Commissioning Process

Building Enclosure Commissioning Process Building Enclosure Commissioning Process Paul E. Totten, PE ABSTRACT The building enclosure is comprised of various sub-assemblies that, in combination, must achieve the proper balance in an interacting

More information

NIBS Guideline

NIBS Guideline National Institute of BUILDING SCIENCES NIBS Guideline 3-2012 Building Enclosure Commissioning Process BECx This Guideline is for Use with ASHRAE Guideline 0-2005: The Commissioning Process An Authoritative

More information

SECTION ALUMINUM WINDOWS

SECTION ALUMINUM WINDOWS SECTION 08520 ALUMINUM WINDOWS PART 1 GENERAL 1.1 SECTION INCLUDES A. Projected windows. B. Fixed windows. 1.2 RELATED SECTIONS A. Section 07900: Joint Sealers. B. Section 08400: Entrances and Storefronts.

More information

Corium Brick Rainscreen System Specifications

Corium Brick Rainscreen System Specifications CORIUM BRICK RAINSCREEN SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Work Included: The Work of this Section shall include but not be limited to the following: 1. Corium brick plates 2. Galvanized and coated

More information

Building Enclosure Commissioning: Who, What, When, Why, and How?

Building Enclosure Commissioning: Who, What, When, Why, and How? Building Bridges to Net Zero Building Enclosure Commissioning: Who, What, When, Why, and How? Thomas J. McMullan III, PE Wiss, Janney, Elstner Associates, Inc. Associate Principal Philadelphia, PA 1 Learning

More information

How-to: Commissioning Design Reviews for the Building Envelope

How-to: Commissioning Design Reviews for the Building Envelope AABC Commissioning Group AIA Provider Number 50111116 How-to: Commissioning Design Reviews for the Building Envelope Course Number: CXENERGY1625 Stevan Vinci, BECxP, LEED AP, Morrison Hershfield Maurya

More information

RFP for Building Enclosure Consulting Services Proposal Request No Answers to Questions Asked as of 11/01/2017

RFP for Building Enclosure Consulting Services Proposal Request No Answers to Questions Asked as of 11/01/2017 RFP for Building Enclosure Consulting Services Proposal Request No. 17-0137 Answers to Questions Asked as of 11/01/2017 1. What extent of project documents will be available for the building enclosure

More information

Energy-Efficient Facilities: Building Envelope Design. Wall Systems. Copyright Materials. Course Description

Energy-Efficient Facilities: Building Envelope Design. Wall Systems. Copyright Materials. Course Description Energy-Efficient Facilities: Building Envelope Design Steve Easley steve@steveeasley.com Wall Systems www.steveeasley.com Copyright Materials This presentation is protected by US and International Copyright

More information

Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series.

Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series. Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series. 1 3 6 7 8 An enclosure s basic function is to separate the outside from the inside.

More information

Architectural Building Envelope Consulting Group

Architectural Building Envelope Consulting Group Architectural Building Envelope Consulting Group Pre-Construction Engineering Quality Assurance The greatest opportunity to affect the cost, value, aesthetics, quality and sustainability of a building

More information

Quality Control of Air Barriers During Construction

Quality Control of Air Barriers During Construction Quality Control of Air Barriers During Construction BEST III Conference Brandon S. Buchberg, P.E. Senior Staff II Jason S. Der Ananian, P.E. Senior Staff II Simpson Gumpertz & Heger Inc. 3 April 2012 www.sgh.com

More information

SECTION STAINLESS STEEL WALL PANELS

SECTION STAINLESS STEEL WALL PANELS SECTION 07400 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Dry joint, Rainscreen stainless steel wall panel system. 2. Accessories including attachments, clips, sub girts, shims, and fasteners 3.

More information

Commissioning: What Architects Need to Know

Commissioning: What Architects Need to Know Commissioning: What Architects Need to Know Rino Zan P.Eng., Morrison Hershfield Ltd. rzan@morrisonhershfield.com Ontario Association of Architects May 12 & 13, 2016 Commissioning: What Architects need

More information

Commissioning the Building Envelope

Commissioning the Building Envelope Thank you to our Conference Sponsors! Silver Sponsors Bronze Sponsor Commissioning the Building Envelope Brian H. Neely, AIA, NCARB, CDT March 27,2014 Gale Associates, Inc. E n g i n e e r s a n d P l

More information

SSG. Fundamentals of Structural Sealant Glazing. Introduction

SSG. Fundamentals of Structural Sealant Glazing. Introduction SSG Fundamentals of Structural Sealant Glazing Photos Courtesy of SmithGroup Introduction This presentation is about the use of silicone sealants for structural sealant glazing (SSG) Information on sealants

More information

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants.

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. Section 07 42 13 Page 1 PART 1 GENERAL 1.1 SECTION INCLUDES A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. 1.2 RELATED SECTIONS A. Section 06112 - Framing

More information

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1 ABSTRACT Innovating Continuous Exterior Insulation Theresa A. Weston, PhD. 1 As the need to reduce energy usage and carbon consumption has increased, the need for energy efficient building envelopes has

More information

BEYOND DIAGNOSTIC TESTING: An Interpretation of Home Performance

BEYOND DIAGNOSTIC TESTING: An Interpretation of Home Performance BEYOND DIAGNOSTIC TESTING: An Interpretation of Home Performance 2016 Energy Design Conference & Expo Tessa Murry B.S. Residential Building Science BPI Building Analyst Certified In accordance with the

More information

NAFS Labeling and Part 5 Compliance for Commercial Glazing Products. A Guide for Architects

NAFS Labeling and Part 5 Compliance for Commercial Glazing Products. A Guide for Architects NAFS Labeling and Part 5 Compliance for Commercial Glazing Products A Guide for Architects An informational resource from the Fenestration Association of BC Executive summary NAFS labeling requirements

More information

Thermal Patterns Created By Moisture Accumulation Within Exterior Masonry Walls by A. Colantonio* and G. Desroches ** * Public Works And Government Services Canada, Ottawa, Canada ** Public Works And Government

More information

Architectural Testing, Inc. 849 Western Avenue North Saint Paul, Minnesota Dan Johnson, Director - Regional Operations

Architectural Testing, Inc. 849 Western Avenue North Saint Paul, Minnesota Dan Johnson, Director - Regional Operations IAS Accreditation Number Company Name Address Contact Name Telephone (651) 636-3835 Effective Date of Scope August 12, 2016 Accreditation Standard ISO/IEC 17025:2005 Conformity Specifications TL-285 849

More information

Commissioning the Building Envelope: Surviving Hurricanes Charley, Frances, and Jeanne

Commissioning the Building Envelope: Surviving Hurricanes Charley, Frances, and Jeanne Commissioning the Building Envelope: Surviving Hurricanes Charley, Frances, and Jeanne R. Bruce Parzych U.S. Army Community and Family Support Center David MacPhaul, PE CH2M HILL Synopsis In March 2004,

More information

We met at the parapet and it was transition at first sight. Christine Cronin, Building Science Corporation

We met at the parapet and it was transition at first sight. Christine Cronin, Building Science Corporation We met at the parapet and it was transition at first sight Christine Cronin, Building Science Corporation Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute

More information

SECTION METAL WALL PANEL SYSTEM

SECTION METAL WALL PANEL SYSTEM CSI Format for Metal Wall Panel System Specification SECTION 07410 METAL WALL PANEL SYSTEM PART 1 GENERAL 1.1 SECTION INCLUDES A. Exterior Metal Plate Wall Panels B. Substructure and Framing C. Structural

More information

FL200 13/4 x41/2 GUIDE SPECIFICATION. Non-Thermal Storefront

FL200 13/4 x41/2 GUIDE SPECIFICATION. Non-Thermal Storefront Manufacturer: Coral Architectural Products 3010 Rice Mine Road Tuscaloosa, AL. 35406 Voice: (800) 772-7737 Fax: (800) 443-6261 SECTION 08410 ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS This suggested guide

More information

2. Representatives of the facility user and operation and maintenance personnel.

2. Representatives of the facility user and operation and maintenance personnel. PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according

More information

The Air Barrier Pre-Installation Meeting

The Air Barrier Pre-Installation Meeting The Air Barrier Pre-Installation Meeting Corey S Zussman, AIA, NCARB, ALA, REWC, RWC, RRO, CDT, CQM, LEED AP BD+C Pepper Construction Company Air Barrier Association of America (ABAA) is a Registered Provider

More information

Success Via Vigilance Breaks

Success Via Vigilance Breaks National Institute of Building Sciences Provider Number: G168 BECx, Construction, and the Kick-Off Meeting Success Via Vigilance Breaks Alex Connor, David Meyers, & Nick Thornsbury Course Number Date Credit(s)

More information

AIR BARRIER SYSTEMS VAPOR-PERMEABLE AND NON-PERMEABLE. Sealed, Smart, and Sustainable WATERPROOFING & BUILDING PRODUCTS COMMERCIAL PRODUCT

AIR BARRIER SYSTEMS VAPOR-PERMEABLE AND NON-PERMEABLE. Sealed, Smart, and Sustainable WATERPROOFING & BUILDING PRODUCTS COMMERCIAL PRODUCT WATERPROOFING & BUILDING PRODUCTS COMMERCIAL PRODUCT VAPOR-PERMEABLE AND NON-PERMEABLE AIR BARRIER SYSTEMS Sealed, Smart, and Sustainable Environmentally friendly and ecologically sound Effective, efficient

More information

Practices for Installing

Practices for Installing Quality Management Best Practices for Installing Self-Adhering Sheet Air Barriers Chris Bubser, AIA, LEED AP BD+C Mortenson Construction Air Barrier Association of America (ABAA) is a Registered Provider

More information

BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE

BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE 200-4010 Regent Street Burnaby BC V5C 6N2 Canada Telephone: (604) 430-8035 Toll Free Canada-wide: 1-888-430-8035 Facsimile: (604) 430-8085 BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL

More information

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance www.epa.gov/iaq/moisture Foundations Issue Building foundations are vulnerable to moisture problems for a number of reasons, including: Water from rain and from plumbing leaks is drawn by gravity to foundations,

More information

Mark Lawton, P.Eng., FEC. Airtightness in Buildings A Canadian History June 2017

Mark Lawton, P.Eng., FEC. Airtightness in Buildings A Canadian History June 2017 Mark Lawton, P.Eng., FEC Airtightness in Buildings A Canadian History June 2017 History of What? Understanding Measurement Implementation Air in Buildings Carries moisture to cold surfaces where condensation

More information

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1 Fitness Facility Addition Page 1 PART 1 GENERAL 1.1 SECTION INCLUDES.1 Extruded aluminum windows with fixed sash..2 Factory glazed..3 Perimeter sealant. 1.2 RELATED SECTIONS.1 Section 05500 - Metal Fabrications.2

More information

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program

More information

The Role of Control Layers in Building Enclosure Design

The Role of Control Layers in Building Enclosure Design The Role of Control Layers in Building Enclosure Design COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER OCTOBER 13, 2016 Disclaimer: This presentation was developed by a third party and is

More information

Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls

Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls Robert Kudder, PhD, S.E., FASTM Raths, Raths & Johnson, Inc BEC Detroit, October 14, 2014 Background! 1986 Alan Yorkdale and James

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

It s not what you expect, it s what you inspect! Inspections

It s not what you expect, it s what you inspect! Inspections It s not what you expect, it s what you inspect! John Runkle, P.E. Architectural Testing, Inc. Inspections Testing Code/regulations Consulting Component Removal Visual Observation Interviews/ Communication

More information

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS SECTION 074233 EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS PART 1 - GENERAL 1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Cardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS

Cardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS Cardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION 08410 ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS This suggested guide specification has been developed using

More information

[Project Name] Section [ ]

[Project Name] Section [ ] Page 1 PART 1 - GENERAL 1.1 SECTION INCLUDES 1.1.1 Design, labor, products, equipment and services necessary for interior/exterior Aluminum Facade System (AFS) work, in accordance with the Contract Documents.

More information

Welcome to this continuing education seminar. This is the first of three parts of the Building Enclosure Fundamentals series.

Welcome to this continuing education seminar. This is the first of three parts of the Building Enclosure Fundamentals series. Welcome to this continuing education seminar. This is the first of three parts of the Building Enclosure Fundamentals series. 1 3 6 7 8 The primary reasons to build airtight buildings are to avoid drafts

More information

Series B450 Guide Specification

Series B450 Guide Specification Boyd Aluminum Manufacturing Company P.O. Box 1565 3248 E. Division Street Springfield, MO 65801-1565 800-737-2800 417-862-1232 fax boydaluminum.com STOREFRONT SERIES B450 Shear Block Air Infiltration:

More information

6. Moisture Design. Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration

6. Moisture Design. Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration 6. Moisture Design Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration Vapor Condensation More new bldgs are susciptable to vapor condensation because of: 2. 1. 2.

More information

MOCK-UP TEST REPORT. Report No: NCTL Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10

MOCK-UP TEST REPORT. Report No: NCTL Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10 MOCK-UP TEST REPORT Report No: NCTL-110-11828-3 Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10 Client: Alumil N.A. Corporation 4401 21 st. Street, Suite 203 Long Island City,

More information

SECTION ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

SECTION ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS SECTION 08 4113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Aluminum entrance doors and frames. 2. Glass infill panels. 3. Door hardware. B. Related Sections:

More information

Guide Specification for the OSI QUAD Window and Door Flashing System

Guide Specification for the OSI QUAD Window and Door Flashing System Henkel Corporation 26235 First Avenue Westlake, OH 1-866-591-2178 www.ositough.com Guide Specification for the OSI QUAD Window and Door Flashing System Specifier Note: The purpose of this guide specification

More information

Considerations in the Repair and Replacement of Historic Windows

Considerations in the Repair and Replacement of Historic Windows Considerations in the Repair and Replacement of Historic Windows Carolyn L. Searls, PE, LEED AP BD+C Senior Principal Taryn N. Williams, SE Senior Staff II Simpson Gumpertz & Heger California Preservation

More information

Interaction Between the Building Envelope and Fenestration Products

Interaction Between the Building Envelope and Fenestration Products Interaction Between the Building Envelope and Fenestration Products Dave Stammen Robert Jutras Underwriters Laboratories (UL) Air Barrier Association of America (ABAA) is a Registered Provider with The

More information

Building Envelope Enclosures That Work, What Owners Want!

Building Envelope Enclosures That Work, What Owners Want! WEBINAR February 23, 2017 Building Envelope Enclosures That Work, What Owners Want! Will Ikerd, P.E. (TX), LEED AP Webinar Speakers Karl Strand President of Vertical Solutions Consulting Will Ikerd, PE

More information

BASIC VENTILATION REQUIREMENTS

BASIC VENTILATION REQUIREMENTS ATTIC VENTILATION BUILDING DEPARTMENT 952-446-1660 WWW.CITYOFMINNETRISTA.COM This handout is intended only as a guide and is based in part on the 2015 Minnesota Residential Code, Minnetrista City ordinances,

More information

Avoiding Air Barrier Pitfalls When sub-trade activities are not in sync with air barrier requirements, installation can go poorly.

Avoiding Air Barrier Pitfalls When sub-trade activities are not in sync with air barrier requirements, installation can go poorly. 48 D+D NOVEMBER 2013 Building Envelope Avoiding Air Barrier Pitfalls When sub-trade activities are not in sync with air barrier requirements, installation can go poorly. By Brian H. Neely, AIA, CDT, CBST,

More information

2001 National Workshop on State Building Energy Codes July th, 2001 Burlington, Vermont

2001 National Workshop on State Building Energy Codes July th, 2001 Burlington, Vermont 2001 National Workshop on State Building Energy Codes July 16-19 th, 2001 Burlington, Vermont A Systems Engineering Approach to the Design of Energy and Resource Efficient Homes Presented By: Mark LaLiberte

More information

SECTION FLUID-APPLIED WEATHER AND AIR BARRIER SYSTEM FOR VENTILATED CAVITY

SECTION FLUID-APPLIED WEATHER AND AIR BARRIER SYSTEM FOR VENTILATED CAVITY SECTION 07 27 27 FLUID-APPLIED WEATHER AND AIR BARRIER SYSTEM FOR VENTILATED CAVITY SPECIFIER NOTE: THIS SECTION IS INTENDED FOR A COMPLETE BUILDING ENVELOPE BARRIER APPLICATION, INCLUDING VENTILLATED

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

PROJECT LOCATION SECTION COPPER METAL PLATE WALL PANELS

PROJECT LOCATION SECTION COPPER METAL PLATE WALL PANELS SECTION 07 4213.25 PART 1- GENERAL 1.01 SECTION INCLUDES A. Copper metal plate wall panels. 1.02 RELATED REQUIREMENTS A. Section 05 4000 Cold-Formed Metal Framing: Wall panel substrates support framing.

More information

BECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process

BECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process BECx Design Phase Specification Review Workshop Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by William R. Nash Design Phase Pre Design

More information

Low-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity

Low-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity Low-cost Construction for High-energy Savings Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity construction@rahh.org Objectives: 1. Control air & moisture in high-performance, low-cost

More information

Windows and Doors: How to Do It Right and Still Get It Wrong

Windows and Doors: How to Do It Right and Still Get It Wrong Windows and Doors: How to Do It Right and Still Get It Wrong Steve Gleason, PE, and Charles Allen Jr., AIA Liberty Building Forensics Group 3700 Dohnavur Drive, Zellwood, Florida 32798 Phone: 407-703-1300

More information

The Building Envelope Defined

The Building Envelope Defined Learning Objectives 1. The purpose of the building envelope 2. The energy code s definition of the building envelope 3. The exterior forces that act on the building envelope 4. The interior forces that

More information

Designing and Constructing a High-Performance Building Envelope for Multi-Unit Affordable Housing

Designing and Constructing a High-Performance Building Envelope for Multi-Unit Affordable Housing Designing and Constructing a High-Performance Building Envelope for Multi-Unit Affordable Housing Jeffrey Davis, AIA, LEED AP FortyEighty Architecture Debbie Clark, NCARB, LEED AP FortyEighty Architecture

More information

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE PART 1 - GENERAL 1.1 SUMMARY SECTION 07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit

More information

BUILDING ENVELOPE HEAT FLOW. Building Envelope

BUILDING ENVELOPE HEAT FLOW. Building Envelope BUILDING ENVELOPE HEAT FLOW stuff lots of stuff happens when a building meets a climate Ball State Architecture ENVIRONMENTAL SYSTEMS 1 Grondzik 1 Building Envelope A general term that describes the various

More information

SECTION ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS

SECTION ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS PART 1 GENERAL SECTION 08 1116 ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS 1.01 SECTION INCLUDES A. Aluminum-framed storefront, with vision glass. B. Infill panels of glass. C. Aluminum doors

More information

SECTION TERRA COTTA CLAY TILE RAINSCREEN SYSTEM

SECTION TERRA COTTA CLAY TILE RAINSCREEN SYSTEM SECTION 07400 TERRA COTTA CLAY TILE RAINSCREEN SYSTEM PART 1 GENERAL 1.01 WORK INCLUDED A. The terra cotta clay tile elements and aluminum support system shall be manufactured by NBK Keramik GmbH as represented

More information

Demystifying Testing Standards C t B ildi F d. Common to Building Facades. John Runkle, P.E. Architectural Testing, Inc. Learning Objectives

Demystifying Testing Standards C t B ildi F d. Common to Building Facades. John Runkle, P.E. Architectural Testing, Inc. Learning Objectives Demystifying Testing Standards C t B ildi F d Common to Building Facades John Runkle, P.E. Director, Forensic Services Architectural Testing, Inc. Architectural Testing Learning Objectives Understand laboratory

More information

STRUCTURAL DESIGN CRITERIA

STRUCTURAL DESIGN CRITERIA CHAPTER 3 STRUCTURAL DESIGN CRITERIA SECTION 301 GENERAL 301.1 Scope. Loads and load combinations shall be determined in accordance with ASCE 7 unless otherwise noted. Structural elements of the storm

More information

North Hanover Township School District North Hanover Township, New Jersey

North Hanover Township School District North Hanover Township, New Jersey SECTION 084413 - GLAZED ALUMINUM CURTAIN WALLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

Building Envelope Systems Exam Learning Objectives

Building Envelope Systems Exam Learning Objectives Building Envelope Systems Exam Learning Objectives Roofing Nomenclature 1. Define the following roofing terms: low, flat, sloped, conventional, protected/inverted, hybrid, BUR, modified bitumen, PVC, TPO,

More information

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system.

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. SECTION 08625 METAL FRAMED SKYLIGHT PART 1 GENERAL 1.01 SECTION INCLUDES: A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. B. Fabrication

More information

5/12/2014. CSA S478 Guideline on Durability in Buildings. The Durability Process. Take a deep breath' Durability

5/12/2014. CSA S478 Guideline on Durability in Buildings. The Durability Process. Take a deep breath' Durability 5/2/204 CSA S478 Guideline on Durability in Buildings The Durability Process David Kayll, FMA, P.Eng. Principal, Building Science Specialist MORRISON HERSHFIELD, Ottawa May 8, 204 Take a deep breath' 2

More information

Mario D. Gonçalves, Patenaude-Trempe 1 Pierre Gendron, Patenaude-Trempe 2 Tony Colantonio, PWGSC 3. Abstract

Mario D. Gonçalves, Patenaude-Trempe 1 Pierre Gendron, Patenaude-Trempe 2 Tony Colantonio, PWGSC 3. Abstract Commissioning of Exterior Building Envelopes of Large Buildings for Air Leakage and Resultant Moisture Accumulation using Infrared Thermography and Other Diagnostic Tools Mario D. Gonçalves, Patenaude-Trempe

More information

Insulating Basements: Part 1 Fundamentals

Insulating Basements: Part 1 Fundamentals The Pennsylvania Housing Research Center Insulating Basements: Part 1 Fundamentals Builder Brief: BB0510 Brian Wolfgang, PHRC Fellow INTRODUCTION The perception of a basement has changed significantly

More information

CSI Boston Technical Paper No. 1: Specifying Air Barriers Air Barriers

CSI Boston Technical Paper No. 1: Specifying Air Barriers Air Barriers CSI Boston Technical Paper No. 1: Specifying Air Barriers 07 27 00 - Air Barriers CSI BOSTON TECHNICAL PAPER NO. 1: SPECIFYING AIR BARRIERS JULY 2014 1 TABLE OF CONTENTS Click on any heading below to be

More information

COMMERCIAL FENESTRATION FUNDAMENTALS & DESIGN CONSIDERATIONS

COMMERCIAL FENESTRATION FUNDAMENTALS & DESIGN CONSIDERATIONS COMMERCIAL FENESTRATION FUNDAMENTALS & DESIGN CONSIDERATIONS INTRODUCTION Pace Representatives is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned

More information