1 Building Enclosure Performance for Existing and New Buildings 2015 HESNI Annual Conference Rick Ziegler, PE

2 Industry Construction Defect Claims Building Envelope - 70% Plumbing - 12% Freezing - 4% Fire Sprinklers - 3% Building Envelope 70% HVAC/Electric - 3% Structure - 1.5% Concrete - 1.5% Flooring - 0.8% FoundaJon - 0.8% *Per data from the American Contractor s Insurance Group

3 Agenda Building Enclosure Fundamentals Existing Buildings New Construction Discussion/Questions

4 Environmental Separation Control heat flow Control air flow Control vapor flow Control rain Control groundwater Control light and solar radiation Control noise and vibration Control insects, rodents, and vermin Control fire Provide strength and rigidity Provide blast resistance Be durable

5 Fundamentals Water/Drainage Air Control Durability Vapor Control Thermal ProtecJon

6 Water/Air Control Fluid Applied Felt Sheet Mechanically Applied Attached Roof Below Grade Waterproofing Mechanically Attached

7 Air Barrier Materials Materials with air permeability psf air pressure differenjal Plywood Oriented Strand Board Extruded InsulaJon Board Foil- back InsulaJon Board Closed Cell Spray Foam Open Cell Spray Foam Exterior/Interior Gypsum Board Cement Board Fully Adhered Roof Membrane Portland cement or gypsum plaster Concrete Fully Grouted Concrete Block Sheet Steel or Aluminum Built- up Roofing Membrane Mod- bit Roofing Membrane

8 Air Barrier Materials Not All Air Barriers are Equal Stucco Air barrier per IECC C Must be flashed per IBC

9 ASHREA 1478 RP Roof to wall intersection Exterior soffits, wings, and canopies connected to buildings Fenestration connections to opaque walls and roof Separation of building and vented attics Structural beam penetrations of the enclosure Double facades Weatherstripping

10 Barrier and Cavity Walls Barrier Assembly Mechanically Attached Roof Cavity/Drainage Assembly

11 Vapor Control Layers per the Code Vapor Retarders per the 2012 IBC: Class I Perm rajng less than.1 Class II Perm rajng between.1 and 1 Class III Perm rajng greater than 1 Class I or II required on interior side of walls in climate zones 5, 6, 7, 8 and marine 4

12 Vapor Diffusion Vs. Air Leakage * At 40% RH over course of winter in Canada

13 Agenda Building Enclosure Fundamentals Existing Buildings New Construction Discussion/Questions

14 Existing Buildings - Failures - Maintenance - Energy Performance

15 Moisture Problems Condensation Water Leakage

16 Failures Biological growth Leakage into wall cavity

17 Repairs Sealant applied incorrectly

18 Investigations

19 Investigations

20 Investigations Project History Occupant interviews Maintenance logs Conditions during failure - Wind speed/direction - Precipitation - Building pressures - Temperatures - Failure descriptions

21 Investigations Document Reviews

22 On-site Observations and Testing

23 On-site Observations and Testing

24 Repair Plans Options 1) Isolated repairs 2) Proactive/comprehensive repairs 3) Removal and replacement

25 Maintenance Programs Understand the fundamentals Identify a schedule Develop maintenance logs Know where to look

26 Maintenance Failed Sealants Fasteners on roof membrane

27 Maintenance Infrared Scans Debris blocking roof drain

28 Energy Performance Energy Cost Savings ($/yr) $45,000 $40,000 $35,000 $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $0 Energy Savings Based on Total Building Air Leakage 0.40 cfm/sf 0.25 cfm/sf 0.10 cfm/sf

29 Energy Performance Building pressures Infrared Thermography Smoke testing

30 Whole Building Air Leakage Testing Spray Rack Testing (Chamber) Spray Nozzle Testing

31 Modifications Verify with WUFI Wärme und Feuchte InstaJonär

32 Modifications Verify with THERM

33 Agenda Building Enclosure Fundamentals Existing Buildings New Construction Discussion/Questions

34 New Construction

35 Envelope Failures Curling of spray foam Self- adhered flashing pulling away from drip edge

36 Envelope Failures Comprehensive flashing repairs

37 Commissioning HVAC Electrical Plumbing Fire Protection Security Medical Gas Building Automation Controls Building Envelope

38 Enclosure Commissioning (BECx) Building Enclosure Systems Fenestration Air barriers Vapor barriers Roofing Below grade Claddings Waterproofing Sealants Insulation

39 BECx Phases Pre-Design Design Pre-Construction Construction Operations and Maintenance

40 Pre-Design Phase Owner s Project Requirements Selection of enclosure systems Basis of Design Energy Modeling

41 Pre-Design Energy Modeling and OPR

42 Design Phase

43

44

45

46

47 Test Protocols Testing Considerations OPR and difficulty in achieving Mock-up and field testing budget Complexity of design Quantity of systems Trade expectations Most realistic testing building will experience

48 Test Protocols ASTM E1105: 3.2.3: Penetration of water beyond a plane parallel to the glazing (the vertical plane) intersecting the innermost projection of the test specimen

49

50 Pre-Construction Phase Typical Shop Drawing Detail Coordinated Shop Drawing Detail

51 Pre-Construction Phase Laboratory Mock-up On-site Stand Alone Mock-up

52 Mock-up Air Leakage Testing Prior to Cladding Installation Mock-up Water Leakage Testing Prior to Cladding Installation

53 Mock-up Testing Mock-up Air Leakage Testing Prior to Cladding Installation

54 Construction Phase Finalize field functional performance test plan Review contractor s quality control Field functional performance testing Construction observations/inspections BECx meetings

55

56

57

58

59

60

61 Qualitative Air Barrier Testing Quantitative Air Barrier Testing

62 ASTM D 4541 Air Barrier Adhesion Testing Air Barrier Adhesion Testing

63 Spray Rack Testing (Chamber) Spray Nozzle Testing

64 Operations and Maintenance Phase Warranty Documentation Maintenance Plan Final BECx Report Post Occupancy Site Visit

65 THANK YOU QUESTIONS? COMMENTS? Rick Ziegler, PE

Building Enclosure Commissioning

Building Enclosure Commissioning Building Enclosure Commissioning John Runkle, P.E. Vice President Building Sciences October 5, 2016 Program Outline Defining the Enclosure Building Science Concepts Façade Design State of the Practice

More information

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P Provider Number:404108121 Darek Brandt, PE Chief Engineer, Building Science Solutions AIA CES DISCLAIMER Credit(s) earned on completion

More information

Design Phase Building Envelope Commissioning

Design Phase Building Envelope Commissioning Design Phase Building Envelope Commissioning John A. Runkle, P.E. Vice President, Building Sciences October 14, 2016 Learning Objectives Understand the key attributes that dictate proper design based on

More information

Quality Control of Air Barriers During Construction

Quality Control of Air Barriers During Construction Quality Control of Air Barriers During Construction BEST III Conference Brandon S. Buchberg, P.E. Senior Staff II Jason S. Der Ananian, P.E. Senior Staff II Simpson Gumpertz & Heger Inc. 3 April 2012 www.sgh.com

More information

Understanding Energy Codes

Understanding Energy Codes NRCA University Webinar October 17, 2013 Understanding Energy Codes presented by Mark S. Graham Associate Executive Director, Technical Services National Roofing Contractors Association Some background

More information

Approaches to Efficient Envelope Design Air Barrier for High-Performance Buildings Alex Boetzel, Director of Sustainability and Operations

Approaches to Efficient Envelope Design Air Barrier for High-Performance Buildings Alex Boetzel, Director of Sustainability and Operations Approaches to Efficient Envelope Design Air Barrier for High-Performance Buildings Alex Boetzel, Director of Sustainability and Operations Why Airtight Comfort Better control over indoor environment Health

More information

COMMERCIAL ENERGY EFFICIENCY

COMMERCIAL ENERGY EFFICIENCY COMMERCIAL ENERGY EFFICIENCY Commercial buildings are all buildings that are not detached one- or two-family dwellings, multiple single-family dwellings (townhouses), or Group R-2, R-3 or R-4 buildings

More information

Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning

Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning NFMT 2016 T. Stephen Kisielnicki, RWC, LEED AP, BECxP March 24, 2016 About Gale Building Envelope Technology Roof, walls,

More information

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap

More information

How-to: Commissioning Design Reviews for the Building Envelope

How-to: Commissioning Design Reviews for the Building Envelope AABC Commissioning Group AIA Provider Number 50111116 How-to: Commissioning Design Reviews for the Building Envelope Course Number: CXENERGY1625 Stevan Vinci, BECxP, LEED AP, Morrison Hershfield Maurya

More information

Building Enclosure Detailing for Walls and Low-Sloped Roofs

Building Enclosure Detailing for Walls and Low-Sloped Roofs Building Enclosure Detailing for Walls and Low-Sloped Roofs COLIN SHANE M.ENG., P.ENG., P.E. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. AUGUST 2016 Disclaimer: This presentation was developed

More information

Thermal Bridging in Residential Construction

Thermal Bridging in Residential Construction PHRC Webinar Series Tuesday, May 12, 2015 @ 1pm Thermal Bridging in Residential Construction Brian Wolfgang Housing Systems Specialist Pennsylvania Housing Research Center 219 Sackett Building University

More information

NIBS AIR BARRIERS. Washington, DC October 26, 2010 Update on Standards Wagdy Anis, FAIA, LEED AP Wiss, Janney, Elstner, Assoc., Inc.

NIBS AIR BARRIERS. Washington, DC October 26, 2010 Update on Standards Wagdy Anis, FAIA, LEED AP Wiss, Janney, Elstner, Assoc., Inc. NIBS AIR BARRIERS Washington, DC October 26, 2010 Update on Standards, FAIA, LEED AP wanis@wje.com ASHRAE 1478 RP LEED PLATINUM 0.8 cfm/ft2 @ 75 Pa PEN TEST Continuity of barriers Air Leakage Air Barrier

More information

2006 INTERNATIONAL ENERGY CONSERVATION CODE

2006 INTERNATIONAL ENERGY CONSERVATION CODE 2006 INTERNATIONAL ENERGY CONSERVATION CODE DOCUMENTATION Code Change No: EC28-06/07 Original Proposal Sections: IECC: 202, 402.5, 402.5.1 (New), Table 402.5.1 (New), 402.5.2 (New), 402.5.3 (New), 402.2.8,

More information

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1 ABSTRACT Innovating Continuous Exterior Insulation Theresa A. Weston, PhD. 1 As the need to reduce energy usage and carbon consumption has increased, the need for energy efficient building envelopes has

More information

Demystifying Testing Standards C t B ildi F d. Common to Building Facades. John Runkle, P.E. Architectural Testing, Inc. Learning Objectives

Demystifying Testing Standards C t B ildi F d. Common to Building Facades. John Runkle, P.E. Architectural Testing, Inc. Learning Objectives Demystifying Testing Standards C t B ildi F d Common to Building Facades John Runkle, P.E. Director, Forensic Services Architectural Testing, Inc. Architectural Testing Learning Objectives Understand laboratory

More information

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used. It is far more important than often appreciated to use precise, unambiguous, clear definitions when describing aspects of buildings, building enclosures, and building science performance. The following

More information

Guideline for Building Envelope Commissioning: New Buildings

Guideline for Building Envelope Commissioning: New Buildings Guideline for Building Envelope Commissioning: New Buildings Introduction Building envelope failures may arise from inadequacies in the design, construction and operation of buildings and appear to be

More information

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group

More information

Enclosure Commissioning a crash course in reality

Enclosure Commissioning a crash course in reality Enclosure Commissioning a crash course in reality BUILD. CONNECT. ACHIEVE. Denali Jones, Building Science Engineer (EIT) RDH Building Science 0 AIA Quality Assurance The Building Commissioning Association

More information

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE PART 1 - GENERAL 1.1 SUMMARY SECTION 07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit

More information

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS Insulation First Revison October 2016 DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS 1. General Information This Guide describes the use of Kingspan GreenGuard DC14 Drainage

More information

Moisture Considerations for Insulated Building Assemblies

Moisture Considerations for Insulated Building Assemblies PHRC Webinar Series Tuesday, November 10, 2015 @ 1pm Description Moisture Considerations for Insulated Building Assemblies Brian Wolfgang Housing Systems Specialist One critical design consideration in

More information

Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure

Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure Peter Baker, Building Science Corporation ABSTRACT With rising utility cost, concerns

More information

Finding Value in Building Enclosure Commissioning

Finding Value in Building Enclosure Commissioning Finding Value in Building Enclosure Commissioning Brian S. Rose, P.E. Technical Staff Jeffrey D. Kerr, P.E. Senior Project Manager 12 March 2015 www.sgh.com Course Description This presentation will outline

More information

8/14/2015. Course Description. Course Objectives AIR, WATER, AND MOISTURE MANAGEMENT IN LIGHT COMMERCIAL BUILDING ENVELOPES

8/14/2015. Course Description. Course Objectives AIR, WATER, AND MOISTURE MANAGEMENT IN LIGHT COMMERCIAL BUILDING ENVELOPES AIR, WATER, AND MOISTURE MANAGEMENT IN LIGHT COMMERCIAL BUILDING ENVELOPES Traditional and Next Generation Solutions New England Building Officials Education Association Conference October 5-7, 2015 Course

More information

SECTION THERMAL INSULATION

SECTION THERMAL INSULATION Pactiv Building Products 2100 RiverEdge Parkway Suite 175 Atlanta, GA 30328 Toll Free: (800) 241-4402 Web Site: www.green-guard.com SECTION 07210 THERMAL INSULATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

More information

Performance Testing for Quality Assurance and Commissioning

Performance Testing for Quality Assurance and Commissioning BEST 4 Conference: April 13, 2015, Kansas City, MO Performance Testing for Quality Assurance and Commissioning Fiona Aldous Principal The most benefit to a project is obtained during the Design Phase -

More information

The Disclaimer located on the reverse side of the title page of the OAA Rain Penetration Practice Guide applies to each section of the Guide.

The Disclaimer located on the reverse side of the title page of the OAA Rain Penetration Practice Guide applies to each section of the Guide. Note: This document has been divided into several sections in order to suit the limitations of the website. The Disclaimer located on the reverse side of the title page of the OAA Rain Penetration Practice

More information

Impact of NFPA 285 on Air Barrier Specification and Design

Impact of NFPA 285 on Air Barrier Specification and Design Impact of NFPA 285 on Air Barrier Specification and Design Charlotte Metzler Amanda Stacy, LEED Green Associate WSP Building Enclosures Air Barrier Association of America (ABAA) is a Registered Provider

More information

Improving the Energy Performance of Mass Masonry Enclosures

Improving the Energy Performance of Mass Masonry Enclosures Improving the Energy Performance of Mass Masonry Enclosures APT DC Symposium Energy Efficiency of Historic Sites Chrissie Parker, P.E. Simpson Gumpertz & Heger www.sgh.com Presentation Outline Background

More information

Effective Envelope Design Mitigating Risk with High Performance Panels and Acrylic Flashing Systems

Effective Envelope Design Mitigating Risk with High Performance Panels and Acrylic Flashing Systems Effective Envelope Design Mitigating Risk with High Performance Panels and Acrylic Flashing Systems Presented by: Cale Kids & Sean Smith Huber Engineered Woods Disclaimer: This presentation was developed

More information

GA APPLICATION OF GYPSUM SHEATHING

GA APPLICATION OF GYPSUM SHEATHING 1. Scope 1.1 This specification describes the minimum requirements for, and the methods of handling, storage, and application of, gypsum sheathing for use as a substrate for exterior claddings. 1.1.1 Exterior

More information

2009 IECC Chapter 1 Additions, alterations, renovations or repairs.

2009 IECC Chapter 1 Additions, alterations, renovations or repairs. 2009 IECC Chapter 1 Additions, alterations, renovations or repairs. Additions, alterations, renovations or repairs to an existing building, building system or portion thereof shall conform to the provisions

More information

BUILDING ENVELOPE By Sabrina D Ambra

BUILDING ENVELOPE By Sabrina D Ambra BUILDING ENVELOPE 2014-01-15 By Sabrina D Ambra 2 OUTLINE Workplan Objectives Chp 6 Building enclosure design: Highlights Structural system Rainscreen system Prescriptive Path Results Design of Wall Design

More information

6. Moisture Design. Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration

6. Moisture Design. Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration 6. Moisture Design Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration Vapor Condensation More new bldgs are susciptable to vapor condensation because of: 2. 1. 2.

More information

INSIDE WHY SPRAY POLYURETHANE FOAM INSULATION?

INSIDE WHY SPRAY POLYURETHANE FOAM INSULATION? INSIDE WHY SPRAY POLYURETHANE FOAM INSULATION? SUSTAIN THROUGH KNOWLEDGE BOOK 1: WHY SPRAY POLYURETHANE FOAM INSULATION BOOK 2: SPF & THERMAL BARRIER SPF & SAFETY PERSONAL PROTECTIVE EQUIPMENT BOOK 3:

More information

The Role of Control Layers in Building Enclosure Design

The Role of Control Layers in Building Enclosure Design The Role of Control Layers in Building Enclosure Design COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER OCTOBER 13, 2016 Disclaimer: This presentation was developed by a third party and is

More information

Technicalbulletin #16

Technicalbulletin #16 air barriers Technicalbulletin #16 Introduction The movement of moisture 1 can cause problems with the performance of the building envelope through two mechanisms; condensation of water vapor and bulk

More information

Adding Air Barrier and Thermal Improvements to Existing Facilities

Adding Air Barrier and Thermal Improvements to Existing Facilities Adding Air Barrier and Thermal Improvements to Existing Facilities Brian H. Neely, AIA, CDT, BECx PSM Gale Associates, Inc. 163 Libbey Parkway, Weymouth, Massachusetts 02189 Phone: 800-659-4753 e-mail:

More information

Compliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know

Compliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know Compliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know www.dryvit.com 800-556-7752 1 AIA / CES Dryvit Systems, Inc. is a Registered Provider with The American Institute

More information

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance www.epa.gov/iaq/moisture Foundations Issue Building foundations are vulnerable to moisture problems for a number of reasons, including: Water from rain and from plumbing leaks is drawn by gravity to foundations,

More information

Air Barrier Considerations for Roof/Wall Intersections. Presented by Laverne Dalgleish Air Barrier Association of America

Air Barrier Considerations for Roof/Wall Intersections. Presented by Laverne Dalgleish Air Barrier Association of America Air Barrier Considerations for Roof/Wall Intersections Presented by Laverne Dalgleish Air Barrier Association of America Credit(s) earned on completion of this course will be reported to AIA CES for AIA

More information

Building Enclosure Design Fundamentals, Components, and Assemblies

Building Enclosure Design Fundamentals, Components, and Assemblies Building Enclosure Design Fundamentals, Components, and Assemblies COLIN SHANE M.ENG., P.ENG., P.E. PRINCIPAL, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. JULY 11, 2018 Disclaimer: This presentation

More information

Doorways to the Future

Doorways to the Future Air Barriers: Walls Meet Roofs Wagdy Anis, AIA, LEED AP Shepley Bulfinch Richardson and Abbott William Waterston, RRC, AIA Wiss, Janney, Elstner Associates Boston, Massachusetts Doorways to the Future

More information

Energy-Efficient Facilities: Building Envelope Design. Wall Systems. Copyright Materials. Course Description

Energy-Efficient Facilities: Building Envelope Design. Wall Systems. Copyright Materials. Course Description Energy-Efficient Facilities: Building Envelope Design Steve Easley steve@steveeasley.com Wall Systems www.steveeasley.com Copyright Materials This presentation is protected by US and International Copyright

More information

FirstEnergy Program Overview

FirstEnergy Program Overview FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio

More information

BASIC VENTILATION REQUIREMENTS

BASIC VENTILATION REQUIREMENTS ATTIC VENTILATION BUILDING DEPARTMENT 952-446-1660 WWW.CITYOFMINNETRISTA.COM This handout is intended only as a guide and is based in part on the 2015 Minnesota Residential Code, Minnetrista City ordinances,

More information

The Building Envelope Defined

The Building Envelope Defined Learning Objectives 1. The purpose of the building envelope 2. The energy code s definition of the building envelope 3. The exterior forces that act on the building envelope 4. The interior forces that

More information

United States Army Corp of Engineers Requirements for Air Barrier Systems in Buildings

United States Army Corp of Engineers Requirements for Air Barrier Systems in Buildings United States Army Corp of Engineers Requirements for Air Barrier Systems in Buildings Timothy R. Posey, MBC, Scott W. Kramer, Ph.D. and Mark C. Tatum, P.E. Auburn University Auburn, Alabama This study

More information

Building Envelope

Building Envelope 9.36.2. Building Envelope Module 2 BCBC 9.36. 2014 1 Richard Kadulski Architect 9.36.2. Building Envelope Focus is on total building performance, not just thermal insulation Heat transfer and air leakage

More information

GAF EnergyGuard Polyiso Wall Sheathing

GAF EnergyGuard Polyiso Wall Sheathing From: Technical Services May 15, 2013 GAF EnergyGuard Polyiso Wall Sheathing GAF s EnergyGuard Polyiso Wall Sheathing is intended to be installed on residential construction only. Application types include:

More information

CSI Boston Technical Paper No. 1: Specifying Air Barriers Air Barriers

CSI Boston Technical Paper No. 1: Specifying Air Barriers Air Barriers CSI Boston Technical Paper No. 1: Specifying Air Barriers 07 27 00 - Air Barriers CSI BOSTON TECHNICAL PAPER NO. 1: SPECIFYING AIR BARRIERS JULY 2014 1 TABLE OF CONTENTS Click on any heading below to be

More information

Thermal Patterns Created By Moisture Accumulation Within Exterior Masonry Walls by A. Colantonio* and G. Desroches ** * Public Works And Government Services Canada, Ottawa, Canada ** Public Works And Government

More information

2. The building envelope shall comply with all applicable requirements in Section of ANSI/ASHRAE/USGBC/IES Standard

2. The building envelope shall comply with all applicable requirements in Section of ANSI/ASHRAE/USGBC/IES Standard 5.2 Exterior Wall Systems 5.2.1 General Requirements for All Exterior Wall Systems 1. The design and detailing of exterior wall systems and assemblies will require significant input from U of C FM&D in

More information

WeatherSmart Air Barrier Installation Guide

WeatherSmart Air Barrier Installation Guide WeatherSmart Air Barrier Installation Guide 1 The intent of this document is to provide a guide for the installation of WeatherSmart as both a Weather Resistive Barrier (W.R.B.) and an Air Barrier Material

More information

Continuous Insulation and Air Barriers for High Performance Walls

Continuous Insulation and Air Barriers for High Performance Walls Continuous Insulation and Air Barriers for High Performance Walls www.dryvit.com 800-556-7752 1 AIA / CES Dryvit Systems, Inc. is a Registered Provider with The American Institute of Architects Continuing

More information

NOVAWRAP ASPIRE Q & A

NOVAWRAP ASPIRE Q & A TM NOVAWRAP ASPIRE i build with What is building wrap and why should I use NovaWrap Aspire? A building wrap like NovaWrap Aspire is a critical element in the building envelope system which is the physical

More information

Commissioning Under the Influence

Commissioning Under the Influence Commissioning Under the Influence Redefining the Traditional Role of the Commissioning Agent in the Design and Construction of the Building Envelope National Conference on Building Commissioning: May 2-4,

More information

REScheck Software Version Compliance Certificate

REScheck Software Version Compliance Certificate REScheck Software Version 4.3.1 Compliance Certificate Project Title: Chow Residence Renovation Energy Code: 2009 IECC Location: Boston, Massachusetts Construction Type: Single Family Project Type: Addition/Alteration

More information

INTERNATIONAL CODE COUNCIL 2009/2010 CODE DEVELOPMENT CYCLE

INTERNATIONAL CODE COUNCIL 2009/2010 CODE DEVELOPMENT CYCLE INTENATIONAL CODE COUNCIL 09/10 CODE DEVELOPMENT CYCLE 09/10 FINAL ACTION AGENDA UPDATE #2 INTENATIONAL ENEGY CONSEVATION CODE Updated 10-22-10 October 25. 27-31, 10 CHALOTTE CONVENTION CENTE CHALOTTE,

More information

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING INSTALLING WATER-RESISTIVE BARRIERS & FLASHING IN A TWO-LAYER STUCCO APPLICATION Fortifiber Building Systems Group provides this guide to assist installers by demonstrating a two-layer installation of

More information

Building Enclosure Concept Design Checklist

Building Enclosure Concept Design Checklist Building Enclosure Concept Design Checklist SUPPORT. Support mechanical loads Sufficient strength and stiffness (from structural engineer) CONTROL. Heat Flow Control (Temperature and Energy) avoid thermal

More information

Integrated Air & Water Barrier Systems

Integrated Air & Water Barrier Systems Integrated Air & Water Barrier Systems Presented by [ Jeff Presenter s Key, Georgia-Pacific Name ] Wood Products AIA Course: GP-FF-WRBAB Credit Designation: LU HSW Please add relevant logo here Disclaimer:

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

SECTION AIR AND VAPOR BARRIERS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION AIR AND VAPOR BARRIERS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 071326 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Advanced technologies for enhancing the building envelope. 3M Building and Construction Market

Advanced technologies for enhancing the building envelope. 3M Building and Construction Market Advanced technologies for enhancing the building envelope 3M Building and Construction Market Controlling air is crucial for the health & energy efficiency of buildings Ensuring you have the right air

More information

Air Barrier Requirements for Low-Slope Roof Assemblies Myths vs. Facts

Air Barrier Requirements for Low-Slope Roof Assemblies Myths vs. Facts Air Barrier Requirements for Low-Slope Roof Assemblies Myths vs. Facts Peter Kalinger Canadian Roofing Contractors Association Dr. B. Baskaran National Research Council of Canada 1 Air Leakage Controlling

More information

Our sophisticated knowledge base and innovative product line promote quality green building methods, energy efficiency, comfort and health.

Our sophisticated knowledge base and innovative product line promote quality green building methods, energy efficiency, comfort and health. We provide specialized building supplies, expert guidance, and advanced education to architects, contractors, building owners, and construction industry professionals. Our sophisticated knowledge base

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

A Guide to Cold Storage Roof System Design Prepared by GAF Technical Services February, 2019

A Guide to Cold Storage Roof System Design Prepared by GAF Technical Services February, 2019 A Guide to Cold Storage Roof System Design Prepared by GAF Technical Services February, 2019 Table of Contents Page Introduction About GAF 2 About Cold Storage Buildings 2 Important Considerations 3 Guarantee

More information

Goals of Session. Building a Better Thermal Envelope. Thermal Envelope Priorities. Disclaimer. Insulation performance (Real World)

Goals of Session. Building a Better Thermal Envelope. Thermal Envelope Priorities. Disclaimer. Insulation performance (Real World) Goals of Session Building a Better Thermal Envelope RESNET Conference ACI RES 4 February 20, 2007 Bruce Harley, Technical Director Conservation Services Group Understand the key roles in building performance

More information

New Air and Vapor Barrier Technologies

New Air and Vapor Barrier Technologies New Air and Vapor Barrier Technologies Dr John Straube Dupont Young Professor Associate Professor of Building Science Civil Engineering Dept and School of Architecture University of Waterloo Waterloo,

More information

Pre-WWII Buildings. Performance? Environmental Separation. Mold, Rot, Corrosion, Decay, Recladding

Pre-WWII Buildings. Performance? Environmental Separation. Mold, Rot, Corrosion, Decay, Recladding Pre-WWII Buildings John Straube, Ph.D., P.Eng 2013 Environmental Separation No added insulation (or very little) Heating systems and some natural ventilation No air conditioning No vapor barriers Few explicit

More information

SECTION Blown Insulation THERMAL INSULATION

SECTION Blown Insulation THERMAL INSULATION SECTION 07 21 26 - Blown Insulation THERMAL INSULATION PART 1 GENERAL 1.1 SECTION INCLUDES A. Spray-in-place rigid closed-cell polyurethane foam insulation in assemblies indicated on the Drawings, to provide

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series.

Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series. Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series. 1 3 6 7 8 An enclosure s basic function is to separate the outside from the inside.

More information

Building Enclosure Detailing for Balconies

Building Enclosure Detailing for Balconies Building Enclosure Detailing for Balconies COLIN SHANE M.ENG., P.ENG., P.E. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. AUGUST 2016 Disclaimer: This presentation was developed by a third

More information

FINAL July 10, 2012 CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS

FINAL July 10, 2012 CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS FINAL July 10, 2012 CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS Executive Summary: In Chicagoland there are two codes in roofing and reroofing. The International Family of Codes and the

More information

in the industry that highly permeable membranes are superior to less-permeable alternatives. This is not always the case.

in the industry that highly permeable membranes are superior to less-permeable alternatives. This is not always the case. Editor s Note: A modified version of this paper was originally presented at the RCI, Inc. 31st International Convention & Trade Show in Orlando, Florida, in March 2016. introduction Vapor diffusion is

More information

Building Envelope Systems Exam Learning Objectives

Building Envelope Systems Exam Learning Objectives Building Envelope Systems Exam Learning Objectives Roofing Nomenclature 1. Define the following roofing terms: low, flat, sloped, conventional, protected/inverted, hybrid, BUR, modified bitumen, PVC, TPO,

More information

1 Exam Prep Prov Module: Thermal and Moisture Protection Questions and Answers

1 Exam Prep Prov Module: Thermal and Moisture Protection Questions and Answers 1 Exam Prep Prov Module: 27203-13 Thermal and Moisture Protection Questions and Answers 1. The R-value is a measure of the ability of a material to. A. Resist the passage of moisture B. Resist heat conduction

More information

DuPont Tyvek Wall Underlay Install Guide

DuPont Tyvek Wall Underlay Install Guide DuPont Tyvek Wall Underlay Install Guide (For Residential & Light Commercial Buildings) Acceptable Solution to NZBC E2/AS1 New Zealand As at 1/4/15 Version 2 Subject to change without notice DuPont Tyvek

More information

BUILDING EXTERIOR SHELL TRAINING

BUILDING EXTERIOR SHELL TRAINING BUILDING EXTERIOR SHELL TRAINING Course Handout Part 1 Background and Insurance Issues (19min) Causes of Building Exterior Shell Problems Bad Design Poor Planning Failure to Follow Manufacturer s Recommendations

More information

MOISTURE VAPOR MOVEMENT AND VAPOR PERMEANCE

MOISTURE VAPOR MOVEMENT AND VAPOR PERMEANCE HOW VAPOR RESISTANCE PROPERTIES OF COATINGS AFFECT EXTERIOR WALL MOISTURE PERFORMANCE Garth D. Hall, Senior Architect, AIA, Kenneth M. Lies, Principal, AIA, and Sarah K. Flock, Architect III Raths, Raths,

More information

A. Section includes fluid applied, vapor permeable membrane air barriers.

A. Section includes fluid applied, vapor permeable membrane air barriers. Master Construction Specifications Insert Project Name SECTION 072726 FLUID APPLIED MEMBRANE AIR BARRIERS PART 1 GENERAL 1.1 SUMMARY A. Section includes fluid applied, vapor permeable membrane air barriers.

More information

PROJECT DIRECTIVE # FOR KALISPELL PUBLIC SCHOOLS

PROJECT DIRECTIVE # FOR KALISPELL PUBLIC SCHOOLS PROJECT DIRECTIVE #1 2010-11 FOR KALISPELL PUBLIC SCHOOLS GLACIER HIGH SCHOOL SITE INVESTIGATION SECOND FLOOR CLASSROOM PODS INSULATION AND VAPOR BARRIER INSPECTION TECHNICAL MEMORANDUM NO. 1.1 April 1,

More information

Boundaries and Barriers

Boundaries and Barriers Overview of Presentation Boundaries and Barriers High Performance Enclosures Dr John F. Straube Dupont Young Professor School of Architecture & Dept of Civil Engineering University of Waterloo Ontario,

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab.

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab. Willow Glen Housing Repairs Project #9-59 Addendum Item. Change to bid date The bid date will be extended to March 8, 09, :00pm at the Housing Authority of Columbus Central Office,000 Wynnton Road Columbus,

More information

Zero Energy Ready Home Training

Zero Energy Ready Home Training DOE Zero Energy Ready Home Zero Energy Ready Home Training Kiere DeGrandchamp High Performance Homes AIA Provider # 409119425 Date: September 20, 2016 1 INNOVATION & INTEGRATION: Transforming the Energy

More information

Managing Condensation and Thermal Performance with Continuous Insulation

Managing Condensation and Thermal Performance with Continuous Insulation Managing Condensation and Thermal Performance with Continuous Insulation Presented by Brian Shores, Don Simon Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks

More information

The Role of Control Layers in Building Enclosure Design

The Role of Control Layers in Building Enclosure Design The Role of Control Layers in Building Enclosure Design COLIN SHANE M.ENG., P.ENG., P.E. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. SEPTEMBER 14, 2016 Disclaimer: This presentation was

More information

ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services

ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services Addenda Dated: 01/16/2018 PURPOSE: The purpose of this Addenda #5 is to provide a

More information

Air Barrier Systems Designed to Perform

Air Barrier Systems Designed to Perform Air Barrier Systems Designed to Perform A Broad Range of PROVEN, CONTINUOUS Solutions Sheet-applied membranes Roller-applied membranes COMPREHENSIVE AIR & MOISTURE MANAGEMENT SOLUTIONS Vapor permeable

More information

SECTION FLUID-APPLIED VAPOR PERMEABLE MEMBRANE AIR BARRIER SYSTEM ASSEMBLY (August 2013)

SECTION FLUID-APPLIED VAPOR PERMEABLE MEMBRANE AIR BARRIER SYSTEM ASSEMBLY (August 2013) SECTION 07 27 20 FLUID-APPLIED VAPOR PERMEABLE MEMBRANE AIR BARRIER SYSTEM ASSEMBLY (August 2013) PART 1 GENERAL 1.01 SECTION INCLUDES A. Materials and installation methods supplementing a one-component

More information

Insulating Exterior Assemblies : Batt, Blown / Spray, Board and Beyond

Insulating Exterior Assemblies : Batt, Blown / Spray, Board and Beyond Insulating Exterior Assemblies : Batt, Blown / Spray, Board and Beyond Batt Fiberglass Mineral Wool Cotton Wool Blown, Sprayed Fiberglass Spray Foam Cellulose Wool Board Polystyrene (XPS, EPS) Polyisocyanurate

More information

Building Enclosure Details and Assemblies for Wood-Frame Buildings

Building Enclosure Details and Assemblies for Wood-Frame Buildings Building Enclosure Details and Assemblies for Wood-Frame Buildings COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCES INC. NOVEMBER 19, 2015 Disclaimer: This presentation

More information

Inside Why Spray polyurethane Foam insulation? All About Spray polyurethane Foam Book 1

Inside Why Spray polyurethane Foam insulation? All About Spray polyurethane Foam Book 1 Foam Book Inside Why Spray polyurethane Foam insulation? All About Spray polyurethane Foam Book 1 SUSTAIN THROUGH KNOWLEDGE Book 1: Why Spray Polyurethane Foam Insulation Book 2: SPF & Thermal Barrier

More information

IECC - RESIDENTIAL - ENERGY TAC

IECC - RESIDENTIAL - ENERGY TAC IECC - RESIDENTIAL - ENERGY TAC W A R N I N G Copyright Notice: This document has been reproduced solely for considering proposed changes to the Florida Building Code with the permission of the International

More information