1 MANITOWOC PUBLIC UTILITIES CONSTRUCTION SPECIFICATIONS for the MPU WATER DISTRIBUTION SYSTEM Revised July 2015

2 INTRODUCTION The purpose of these Specifications is to establish basic water distribution system standards. In the interest of providing the best possible service with the least possible cost, the Manitowoc Public Utilities Water Department (MPU) requests mutual cooperation between all parties involved. Both the written and drawing sections of the Specifications are meant to better communicate the current requirements of the MPU. Construction of domestic water pipelines and appurtenances shall be in accordance with the requirements of these Specifications. These Specifications are not intended to cover all situations. More detailed specifications may be required for some projects. These detailed Specifications shall be prepared on an as-needed basis. The Specifications shall also include by reference the following: State of Wisconsin Public Service Commission, Chapter PCS 185, Standards for Water Public Utility Service. Chapter NR 114 Wisconsin Administrative Code Specification Requirements. Department of Natural Resources, Chapter NR SAFE DRINKING WATER, Chapter NR REQUIREMENTS FOR THE OPERATION AND MAINTENANCE OF PUBLIC WATER SYSTEMS, and Chapter NR REQUIREMENTS FOR THE OPERATION AND DESIGN OF COMMUNITY WATER SYSTEMS. Standard Specifications for Sewer and Water Construction in Wisconsin-latest edition. City of Manitowoc Plumbing Code. City of Manitowoc Municipal Code Chapter 29, Construction Site Erosion Control. Manitowoc Public Utility Water Utility Rules. Customers, suppliers, developers, contractors and engineers are advised to obtain prior approval of any proposed work so that specific requirements are understood. All materials shall be purchased and/or approved by the Water Distribution Manager. Robert Michaelson, P.E. Water Systems Manager CS-1

3 MATERIALS 1.01 General: The MPU will furnish all materials unless specifically noted on the plans or contract documents, with the exception of water service piping. The Contractor shall provide all water service piping. All materials shall be picked up by the Contractor from the MPU material storage areas, unless other arrangements have been approved. Any materials damaged or lost during the course of construction will be replaced at Contractor s expense Ductile Iron Pipe: All ductile iron pipe shall conform to the latest edition of AWWA C- 150 and C-151. a. Class: The minimum ANSI class for all pipe shall be Class 52. b. Pressure Rating: 350 psi c. Coatings/Linings: All ductile iron pipe shall have an asphaltic coating at least 1 mil thick, with the interior having a cement mortar lining in accordance with the latest edition of AWWA C-104. d. Gaskets: All gaskets shall be in conformance with the latest edition of AWWA C Areas of soil contamination (petroleum or petroleum by-products) shall require the use of nitrile gaskets if the pipe will be above groundwater, and fluorocarbon gaskets if the main will be below groundwater. e. Joints: All underground joints shall be push-on. Exceptions include pipe joints with fittings and valves shall be mechanical joint, and river crossings shall be ball and socket joints. Other joint types may be used as conditions require, with approval of the Water Systems Manager. Specifications for these joints will be developed for each special use. f. Wrapping: All ductile iron pipe shall be encased with polyethylene in accordance with the latest edition of AWWA C Polyvinyl Chloride (PVC) Pipe: All PVC pipe shall conform to the latest edition of AWWA C-900 (4-12 diameters) and C-905 (14-36 diameters). a. Prohibited Use: PVC pipe is not to be used in areas of soil contamination (petroleum or petroleum by-products). b. Pressure Rating: The pipe shall have a minimum pressure class of 235 PSI and a dimension ratio of 18 (i.e. DR 18). c. Gaskets: All gaskets shall be elastomeric, meeting the requirements of ASTM F477. d. Joints: All joints shall be push-on and conform with ASTM D3139. Other joint types may be used as conditions require, with approval of the Water Systems Manager. Specifications for these joints will be developed for each special use Fittings: All fittings shall be ductile iron and shall conform to the latest edition of AWWA C-110 (ductile iron or gray iron) or AWWA C-153 (ductile iron compact fittings). The fittings shall be mechanical joint with mortar lining. Fittings shall be installed with CS-2

4 COR BLUE Bolts Hydrants: Fire hydrants shall be Waterous Pacer WB-67, conforming to AWWA C a. Hydrants shall have a six inch (6 ) mechanical joint connection, a break-away flange at ground level, a sixteen inch (16 ) break-away section above ground, with two (2) 2½ inch and one (1) 4½ inch National Standard Thread hose connections. b. All fire hydrants shall be painted RED Mechanical Joint Restaints: All mechanical joint restraints shall be EBAA Iron Inc. MEGALUG Series 1100 or equal. All bolts shall be COR-BLUE Valves: a. Valves four (4 ) inch thru twelve (12 ) inch in diameter shall be resilient wedge gate valves. Valves larger than twelve (12 ) inch in diameter shall be butterfly valves unless otherwise specified. b. Resilient Wedge Gate Valves (R/W): Resilient wedge type gate valves shall be in accordance with the latest edition of AWWA C-509 and shall be supplied with external epoxy coating and mechanical joints. Unless otherwise specified, gate valves shall be American Flow Control Series 2500 Resilient Wedge Gate Valves, Clow series F6100, or equal. c. Butterfly Valves: Butterfly valves shall be in accordance with the latest edition of AWWA C-504 for buried services and provided with O-ring shaft seals and rubber seats. The minimum class shall be Class 150B of short-bodied mechanical joint configuration. Butterfly valves shall be equipped with manual operators with an operator nut. Unless otherwise specified, butterfly valves shall be Mueller series B or equal. d. Valve Features: i. Valves to have non-rising stem. ii. Provided with an arrow externally cast on the operating nut showing direction of closing. iii. All gate valves 6 and larger shall be designed for an input torque of 400 foot-pounds without distortion of any kind. iv. All bonnet bolts shall be 304 stainless steel. v. 2 square operating nut. vi. The operating nut attaching nut or bolt shall be 304 stainless steel Valve Boxes: Valve boxes shall be three (3) piece screw type made of plastic or cast iron construction and have a minimum shaft diameter of 5 ¼ inch. Plastic boxes shall have a cast iron ring to hold iron cap and be suitable for magnetic detection. Valve boxes, caps, bases, and adaptors shall be incidental to the installation of the valve. a. Valve Box Caps: Valve box caps shall be made of heavy cast iron construction, CS-3

5 shall fit snugly within valve box top section, and have the structural capability to withstand nominal truck traffic loads. Water shall be clearly printed on the cap. b. Valve Box Bases: Oversized valve box bases shall be used on all valves. c. Valve Box Adaptor: Valve box adaptor shall be installed on all valves to ensure the valve box will be centered and remain centered over the valve operating nut. Unless otherwise specified, the valve box adaptor shall be Adaptor style, as manufactured by Adaptor Inc., or equal. d. Manholes: Generally, manholes shall not be used for valve installation. However, for river crossings and other specific uses, they may be used as necessary Water Services: a. All water laterals shall be a minimum of 1 in diameter for Type K Copper or a minimum of 1¼ Polyethylene (PE) Pressure Pipe and Tubing, CTS (Copper Tubing Size) rated for 200 PSI. A larger diameter may be required. b. Type K Copper Tubing service laterals, 1 to 2 in size, shall conform to ASTM B88 Standard Specification for Seamless Copper Water Tube, suitable for underground installation, in sizes and length specified on the design plans. c. Polyethylene (PE 3408) Pressure Pipe and Tubing, CTS (Copper Tubing Size) rated for 200 PSI service laterals, 1¼ to 2 in size, shall conform to ANSI/AWWA C901 Latest Revision in sizes and length specified on the design plans. Polyethylene tubing shall conform to the outside diameter dimensions of Type K Copper. The PE tubing shall be homogeneous throughout and free of visible cracks, holes, foreign inclusions or other defects. It shall be uniform in color, opacity, density and other physical properties. Surfaces of the product shall be free from scratches, gouges, bloom and color imperfections. The PE tubing shall be permanently identified as PE 3408 water service tubing and the markings shall also include manufacturer s brand name or trademark and production record code, nominal size, NSF logo, pressure class (PC 200), AWWA designation number (AWWA C901-02) and date of manufacture. DR PSI tubing (CTS-OD) will be color coded with a blue stripe and marked with the word Tubing and the dimension ratio. A stainless steel stiffener is required on the inside of the PE tubing at all connections. d. All service laterals 4 and larger required for fire protection shall be rated for a Pressure Class 200 PSI and use either Polyvinyl Chloride (PVC) (DR-14) conforming to ANSI/AWWA C900 Latest Revision or Ductile Iron Pipe (Class 52) Service Saddles: On all PVC pipe, service saddles shall be provided. On all ductile iron pipe, service saddles shall be provided for a tap lager than one (1 ) inch. All service saddles for taps two (2 ) inch diameter and less shall have a single stainless steel band, AWWA tapered threads and a ductile iron body, similar to Ford 202 S 7.50 x CC 6. All larger taps shall use a solid stainless steel tapping sleeve with flanged outlet for the tapping valve Corporation Stops: Corporation stops shall be bronze, with the inlet AWWA tapered CS-4

6 threads, compression type outlet similar to Ford F-1000 up to one (1 ) inch and Ford FB-1000 for 1 ½ and two (2 ) inch taps. Larger taps shall use a resilient wedge tapping valve with flanged inlet, mechanical joint outlet and epoxy coating Curb Stops: Curb stops shall be bronze, compression type similar to Ford Z44-444M with threaded top, or equal. For services larger than two (2 ) inch, the tapping valve shall have a valve box to the surface and serve as the curb stop Curb Boxes: a. Approved Manufacturers: Ford, Mueller, AY McDonald b. Extension type curb box with arch pattern base for ½ through 2 curb valves and stops. c. 72 when fully extended, Cast iron box, Upper section 1, 27 long stationary rod d. Curb boxes on copper water services shall have a 2-hole cast iron cap. e. Curb boxes on PE (plastic) water services shall have a cast iron cap with brass pentagon plug, with tracer wire attachment point Tracer Wire: The tracer wire shall be a minimum of twelve (12) gauge solid core copper electric wire with blue PVC coating and rated for wet conditions. Stranded tracer wire is unacceptable. a. If a tracer wire box is specified to be provided, the tracer wire access box casting shall conform to ASTM specification A-48 Class Tapping Sleeves: a. Approved Manufacturers: Smith-Blair, Rockwell, Romac Ford, Cascade b. Body: Full circumference band. Type 304 stainless steel c. Flange: AWWA C207 Class D ANSI 150 lb drilling. Fusion bonded Flexi-Blue coated finish or stainless steel. d. Test Plug: Provide ¾ NPT stainless steel per ASTM A 240, type 304, with standard square head for pressure testing before tap is made. e. Gasket: Nitrile ( Buna N) compounded to resist oil, hydrocarbon fluids and water. Temperatures up to180f. f. Bolts and Nuts: Type 304 stainless steel heavy hex nuts, stud bolts & washers. Nuts and stud shall have factory applied anti galling coating Tapping Saddles: a. Approved Manufacturers: Ford, Rockwell, Cascade b. Body: All type 304 Stainless Steel double bolts c. Gasket: Grade 60 Buna N compounded to resist oil, acids, hydrocarbon fluids, and water. d. Bolts and Nuts: Type 304 stainless steel heavy hex nuts, stud bolts & washers. CS-5

7 Nuts and studs shall have factory applied anti galling coating Pipe Repair Clamps: a. Approved Manufacturers: Romac, Ford, Smith Blair, Cascade b. Body: All Stainless Steel CS-6

8 2. CONSTRUCTION OF WATER MAIN AND APPURTENANCES 2.01 Location of Existing Water Mains: Before excavation of trenches is begun, the Contractor shall uncover the end of existing water main to which the new main is to be connected. This will permit adjustments in line and grade to avoid the use of extra fittings. The exposed end of an existing main must be protected and blocked by the Contractor to prevent the blowing out of the plug or cap at the end of the main Excavation: a. For water main construction, the width of the trench shall be such as to leave a clear space of not less than six (6) inches nor more than twelve (12) inches between the earth wall or the supporting sheeting or bracing where such is used and the sides of the pipe. The trench width established by this pipe clearance, measured at the spring line, shall be applicable to that portion of the trench from one (1) foot above the top of the pipe to the bottom of the trench. b. On streets opened to traffic, on restricted easements and in such other locations as noted by the Engineer, the width of the trench at the ground surface shall be limited to the outside diameter of the pipe plus two (2) feet, plus the amount necessary for sheeting or bracing. The Engineer reserves the right to limit the extent of excavation depending on the nature of the soil and other conditions. c. In general, the minimum depth of installation shall be six feet (6 ). In no circumstances shall main be installed less than five (5 ) feet unless otherwise approved by the Engineer. d. Surplus material shall be considered to include vegetation from the trench line, excavated rock or cobbles and boulders larger than six (6) inches in diameter, and all other material from excavation not needed or suitable for backfilling trenches. Unless otherwise specified, surplus material shall be the property of the Contractor, and shall be disposed of at no additional cost to the Utility. e. Unsuitable Soils: If, in the opinion of the Engineer, an artificial foundation is necessary because of the nature of the excavated material, the Contractor shall excavate to a point a minimum of six (6) inches below the bottom of the pipe. Any work involved in forming a satisfactory foundation at depths of six (6) inches or less below the bottom of pipe will be considered as incidental to the work. Excavate to such depth as directed by the Engineer. Refill this portion of the trench with select fill and mechanically compact the select fill prior to laying the pipe. Limit the width of the trench excavation to the outside diameter of the pipe plus two (2) feet, plus the amount necessary for sheeting and/or bracing Handling of Pipe, Fittings, Etc.: The Contractor shall have sufficient and adequate equipment on the site of work for unloading and lowering pipe and fittings into the trench. Extreme care shall be exercised by the Contractor in handling all pipe, fittings, and special castings so as to prevent breakage and coating damage. Any significant damage to coating or lining shall be repaired or replaced by the CS-7

9 Contractor before installation. Under no circumstances shall pipe or fittings be dropped into the trench or so handled as to receive hard blows or jolts. All mud or concentration of dirt shall be removed prior to installation Field Inspection of Materials: All materials used in the construction of water mains must pass field MPU inspection before installation Direction of Laying: Unless otherwise ordered, pipe shall be laid with the bell ends facing the direction of installation. When the grade exceeds two (2 ) feet of rise per one hundred (100 ) feet of trench, the bells shall face upgrade and the pipe shall be laid uphill Joining Pipe: a. Every precaution shall be taken to prevent foreign material from entering the pipe while it is being placed in the line. MPU may require that before lowering the pipe into the trench, a heavy, tightly woven canvas bag of suitable size shall be placed over each end and left there until the connection is to be made to the adjacent pipe. During the laying operations, no debris, tools, clothing, or other materials shall be placed in the pipe. b. After placing a length of pipe in the trench, the spigot end shall be centered in the bell and the pipe forced home and brought to correct line and grade. Precautions shall be taken to prevent foreign materials from entering the joint space and the joint recess shall be carefully checked for foreign material before the gasket is installed. c. The pipe shall be secured in place with bedding material, placed by hand or equally careful means, keeping the bell end open Bedding of Ductile Iron Pipe: If not in the roadway, and unless otherwise specified, no special or imported bedding material will be required, however, the pipe shall be laid on an even undisturbed bottom and in accordance with the manufacturer s recommendations. The weight of the pipe shall not rest on the pipe bell. The bedding material immediately below the bell shall be carefully excavated so as to allow the full length of the pipe to lay evenly on the bottom of the trench. Under no circumstances will the pipe be laid on soft spoil piles in the trench. Backfill shall be tamped in layers to adequately support and protect the pipe. Initial backfilling shall be done in six (6 ) inch stages to a point twelve (12 ) inches over the top of pipe with sand or crushed stone. Each stage shall be compacted to 95% Standard Proctor Density. Care should be taken to prevent movement of pipe during backfill Bedding of PVC Pipe: The trench bottom shall be relatively smooth and free of rocks and debris, and the trench bottom shall be leveled with crushed stone or coarse sand. The material shall be compacted to a minimum 90% Standard Proctor Density. The pipe shall be uniformly supported for the entire length except at the joint. For unstable soil, use crushed stone for bedding material. Initial backfilling shall be done in six (6 ) inch stages to a point twelve (12 ) inches CS-8

10 over the top of pipe with sand or crushed stone. Each stage shall be compacted to 95% Standard Proctor Density. Care should be taken to prevent movement of pipe during backfill Tie-in of new main to an existing main: When tying-in a new main to an existing main, a tee is to be cut into the existing main. A valve and the new main are to be connected to the tee branch. After all services have been connected to the new main, the old main is to be cut and plugged as close to the new tee as possible Protection of Open Pipe: At all times when pipe laying is not in progress, the open ends of pipe shall be closed by a water-tight plug or other means. This provision shall apply during the noon hour as well as overnight. If there is water in the trench, the seal shall remain in place until the water level in the trench is pumped out to the Owner s satisfaction. No pipe shall be laid in water or when trench conditions are unsuitable. The interior and exterior of all pipe and fittings shall be clean and free from all foreign material before being installed. The Contractor shall provide the necessary means to wipe, brush, swab or air blast or remove any foreign material from the interior of the pipe and fittings Installation of Push-On Joint Pipe: The water main shall be joined by means of a compression type push-on rubber gasket. The bell and spigot of each pipe shall be wiped clean and dry. The gasket shall be inserted, large round end first, into the gasket seat inside of the bell. A thin film of food grade NSF 60/61 lubricant shall be applied to the inside surface of that portion of the gasket which comes in contact with the entering pipe. The only type of lubricant used shall be that recommended by the pipe manufacturer. Extreme care shall be exercised when lowering the pipe into place to avoid foreign material from adhering to the spigot, bell, or gasket. The entering pipe shall be placed in approximate alignment with the receiving bell and inserted until it just makes contact with the gasket. Sufficient pressure shall be accomplished by use of a leverage bar or other approved method for pipe twelve (12 ) inches in diameter or smaller. A jack and two (2) choker-slings, or other approved method, shall be used on pipe larger then twelve (12 ) inches in diameter. Whenever it is necessary to deflect pipe from a straight line, either in the vertical or horizontal plane, the amount of deflection shall not exceed that recommended by the manufacturer. All deflecting shall be done after the joint is pushed home Installation of Mechanical Joint Pipe: Where specified the water main shall be joined by means of a mechanical joint assembly. The last eight (8 ) inches of the outside of the spigot and inside of the bell shall be thoroughly cleaned of all foreign matter and painted with a soap solution. The cast iron gland shall then be slipped on the spigot end with the lip extension toward the socket or bell end. The rubber gasket shall be painted with the soap solution and placed on the spigot end with the thick edge toward the gland. Nuts and bolts used in the joint assembly shall be Cor-Blue or an approved equal. The entire section of the pipe shall be pushed forward to send the spigot end in the bell. Care shall be taken to locate the gasket evenly around the entire joint. All CS-9

11 nuts shall be tightened with a suitable wrench. Care should be taken not to exceed torque limits on the bolts. Nuts shall be tightened alternately in order to produce an equal pressure on all parts of the gland. After a joint is assembled and securely tightened, the nuts and bolts shall be completely coated. Whenever it is necessary to deflect pipe from a straight line, either in the vertical or horizontal plane, the amount of deflection shall not exceed that recommended by the manufacturer.. All nuts and bolts must comply with AWWA C111/A Latest Revision. Bolts shall be of sufficient length such that a minimum of ½ of threads are exposed beyond the end of the nut when tightened. Tighten the bolts to the normal range of bolt torque in accordance with AWWA C600 Latest Revision Polyethylene Encasement: Wrap all below ground metal in accordance with AWWA C105, including: ductile iron pipe, fittings, valves and valve boxes, corporations, curb stops and curb boxes (their entire length), all portions of hydrants below grade, copper water services, and all metal restraining devices Installation of Tracer Wire: For all pipe materials and services, a twelve (12) gauge, solid coated copper wire tracer wire is to be installed with the pipe. The wire is to be placed on the top of the pipe and taped in place. Tracer wire shall be run along pipe from hydrant to hydrant. Wire shall be taped to each length of pipe at a minimum of two points. A maximum of one splice will be allowed between each hydrant. All tracer wire ends must be grounded. Run tracer wire along polyethylene (plastic) laterals to and up/down all curb boxes and along remaining lateral length into property. Copper laterals do not require tracer wire, but the tracer wire shall be attached to the copper lateral by connecting to the thaw wire type copper tube nut at outlet end of corporation stop, or using a bronze ground clamp. For transmission water mains, or other placed when there is not a practical location to bring the tracer wire to the surface, a valve box top section may be used at approximately 500 intervals for access to the tracer wire. The valve box top section should be filled with sand to a maximum of one foot from the top. The tracer wire should not be spliced. Bring the tracer wire to the surface with a minimum of 18 of excess wire at each valve box. Wire splices shall be soldered with a self-flux rosin core solder and tightly wrapped with electrical tape so no copper wire is exposed. After the Contractor has completed all the underground installation on the project, the Contractor shall test the electrical continuity of all the tracer wire installations on the project with the Engineer. The Contractor shall be responsible for any costs of any repairs that may be required Final Backfilling: The Contractor shall be responsible for proper compaction using mechanical compaction. Water jetting is not permitted, unless otherwise approved by the Engineer. CS-10

12 Final backfilling shall be completed by returning excavated material into the trench. However, the final backfill may not contain large stones, frozen clumps or logs. If excavated material is unacceptable by MPU, granular material compacted to 95% Standard Proctor Density shall be placed in twelve (12 ) inch stages to the top of the trench. In lieu of granular material for final backfilling, a 0 bag slurry or road gravel may be used. Slurry is considered a cement-free 50:50 mix of sand and gravel, with water to make it flowable. The final twelve (12) inches shall be ¾ crushed aggregate with no greater than 25% fines, unless otherwise specified. All trenches within pavement areas shall be compacted to ninety-five (95%) percent modified proctor density. All other trenches shall be compacted to ninety (90%) percent standard proctor density Surplus Excavated Material: All excavated material not needed or not suitable for backfill purposes shall be disposed of by the Contractor, at his expense Underground Casing: The Contractor shall furnish all materials required to jack casing under highways or railroads. The casing shall be steel as sized on the drawings with a minimum yield strength of 35,000 PSI. The casing shall have a bituminous coating on the inside. The Contractor is responsible for providing adequate notice to railroad and highway authorities before jacking starts. The ends of the casing shall be sealed with concrete Drawings: Only approved drawings shall be used for the construction of actual improvements Modifications to Drawings: Field conditions often require adjustments to locations and/or grade of pipeline and appurtenances. Adjustments may be made in the field with MPU approval. At the conclusion of the work, the Contractor is to submit a set of drawings showing all adjustments made VALVES a. Installation: All valves and their installation shall conform to all appropriate requirements of Part IV of the Standard Specifications for Sewer and Water Construction in Wisconsin. Prior to installation, inspect all valves for cracks, handling damages, direction of opening, number of turns to open, freedom of operation and cleanliness of valve ports, especially seating surfaces. Check all nuts and bolts on the valve bonnet and packing gland to be tightened to manufacturer s specifications, before the valve is lowered into the ditch. All perpendicular valve joints shall be made with an approved MEGALUG restraining device. To prevent foreign material from entering the valve and causing damage, always install valves in the closed position. Adjust valves following installation so they will work easily and properly. CS-11

13 All valves shall be wrapped with polyethylene wrap. Any valve nut that needs to be placed deeper than seven feet (7.0 ) below finished grade, the Contractor shall install a valve extension on the nut. The top of the valve nut extension shall be between 4 and 6 from the finished grade. A three-piece valve box and valve box adapter is required for every valve. The valve box shall not transmit shock or stress to the valve and shall be centered over the operating nut of the valve. The valve box cover shall be set ½ below the binder grade for asphalt and shall be flush with the surface of the final asphalt lift or concrete pavements. No ramping will be allowed. Reset any valve boxes that have shifted at any time throughout construction until formal acceptance of the project by the Water Utility so they are plumb and centered over the valve at final acceptance; thus, allowing the proper operation and functionality of every valve. b. Operation: Only MPU crews shall operate valves. If needed, this shall be arranged through the MPU inspector FIRE HYDRANTS a. General: All hydrants and their installation shall conform to all appropriate requirements of Part IV of the Standard Specifications for Sewer and Water Construction in Wisconsin. The Water Utility Inspector shall be present when all hydrants are set, when any hydrant extension is installed and when hydrants are disassembled for adjustment or maintenance. The Water Utility Inspector shall inspect the hydrant setting before backfilling. The Contractor shall be responsible for the proper operation of all hydrants on the project until the Water Utility formally accepts the water mains and the warranty period has expired. b. Location: Install hydrants at the locations and grade shown on the drawings. The Water Utility Inspector must authorize in writing any variation from the locations or grades shown on the drawings. An anchoring tee shall be used to attach the hydrant lead to all water mains. The auxiliary valve shall be directly attached to the anchoring tee. c. Installation: An anchoring tee shall be used to attach the hydrant lead to all water mains. The auxiliary valve shall be directly attached to the anchoring tee. Install a 4-IN x 8-IN x 16-IN solid concrete masonry unit, laid flat, in the excavation to provide a firm base for the hydrant. Set the hydrant in a truly vertical position and securely brace it until backfilling is complete. With the three-nozzle hydrant, the small nozzles shall be parallel with the curb and the pumper nozzle shall be perpendicular to the curb. The hydrant nozzle elevations shall be located 18 to 24 above finished grade or top of curb. Break away flange and break away shaft coupling shall be positioned just CS-12

14 above finished grade. Restrain the full length of all hydrant leads from the tee on the water main to the hydrant, including the hydrant valve and any associated fittings, with mechanical joint restraints MEGALUG Series 1100 or equal. Install the required MEGALUG restraints and concrete thrust blocking to fully secure the hydrant. A concrete thrust block shall be used to restrain both the tee and the hydrant. The space around the lower portion of the hydrant from below the hydrant to six inches above the drain holes shall be backfilled with a minimum of one cubic yard of #2 washed stone. When placing the stone, special care shall be taken to have the drain holes open for drainage. Cover the washed stone with six (6)-mil polyethylene or suitable geotextile fabric to prevent loose dirt from filling in the voids in the stones. Place a wooden block or a brick under the hydrant lead to prevent the hydrant from leaning after being set. Fill the remainder of the excavation with the excavated material and compact it evenly in 12-inch lifts, so that the pressure of the backfill on the stem is equally distributed. All ductile iron pipe and fittings shall be wrapped with polyethylene wrap. The wrap shall also be cut at the drain holes. d. Operating: Only MPU crews shall operate hydrants and flush mains. This shall be arranged through the MPU inspector SERVICES a. General: The Contractor shall provide all water service piping and/or tubing. The service shall include the corporation stop, stop box, service line, shut-off valves and meter. The MPU shall make all taps on water mains and provide all materials, except for the service line and shut-off valves, at the expense of the applicant. The Contractor shall provide all excavation, backfilling materials, road and other repairs. In general, no tap smaller than one (1 ) inch shall be made unless approved by MPU. Services shall terminate at the property line. Unions and/or couplings may not be used unless approved by MPU. b. Installation: All services connected to PVC water main shall require a tapping saddle. All services 1¼ and larger connected to Ductile Iron Pipe shall require a tapping saddle. A direct tap for 1 services connected to Ductile Iron Pipe will be allowed with a proper tap machine. A tapping saddle for 1 services would also be allowed on Ductile Iron Pipe. A minimum of 6 of cover shall be maintained on all water laterals, including any area crossing a drainage ditch. Services with inadequate cover, or within 24 of a crossing storm sewer, shall be insulated. The corporation stop shall be tapped at a 45 angle on the upper half of the main and located on the side of main to which the service is to be extended. A gooseneck shall be installed to minimize the potential for pulling the service CS-13

15 line from the corporation stop. Lay service laterals perpendicular to the water main. All copper service lines shall have sand for bedding and cover material. c. PE Services: Polyethylene (PE) Pressure Pipe and Tubing shall include a straight coupling and a one foot (1 ) section of PE pipe or tubing beyond straight coupling and tape the end of pipe. Prior to installation, all Polyethylene (PE) Pressure Pipe and Tubing shall be inspected for cuts, punctures or excessive abrasion which may have resulted from shipping, storage or handling damage. If tubing is cut to a depth greater than 10% of its wall thickness or kinked, the damaged portion shall be removed, discarded and replaced. Pipe cutters designed for cutting plastic pipes are recommended. Avoid dragging pipe over rough terrain or having it come in contact with sharp objects which may cut or puncture the product. Never allow PE pipe to come in contact with fire, excessive heat or chemicals harmful to the pipe. Trench bottoms shall be free of rocks or sharp objects. The bedding and cover for PE pipe shall be sand, crushed stone chips or crushed stone screening conforming to the requirements in Section and of the current Standard Specifications for Sewer and Water Construction in Wisconsin. Backfill shall be uniform and free of rocks, sharp or heavy objects. PE pipe or tubing may be curved to avoid obstacles; however bends in PE pipe/tubing should not occur closer than 10 diameters from any fitting or valve. Minimum radius of curvature for any bends shall be no less than 30 diameters or the coil radius when bending with the coil. Bending of coiled pipe against the coil shall not go beyond straight. PE pipe expands and contracts when exposed to temperature changes. Allowances for this should be made during installation. Normally PE pipe will snake itself in the trench enough to provide sufficient slack. An extra six inches (6 ) per 100 feet of pipe per 45 F temperature change will compensate for thermal contraction in normal underground installations. To aid in fitting installation, the pipe may be softened by immersing in hot water. Do not heat the pipe with other types of heat sources. Do not use any lubricants other than water. The use of pipe joint compounds, pipe sealing compounds, pipe dope and detergent type lubricants is not acceptable. CAUTION: Potable water service PE pipe or tubing installation is prohibited in areas of known chemical contamination of the soil or where there is a high risk of potential chemical spills. PE pipe should not be used in areas known to be contaminated with organic solvents or petroleum distillates. PE pipe or tubing should not be used in soil near hazardous waste disposal sites or underground chemical or petroleum storage tanks. A stainless steel stiffener is required on the inside of the PE tubing at all connections. CS-14

16 Following installation of service lateral, open the corporation stop and the curb stop and flush out the service lateral. Once flushed out, close the curb stop and peen over the end of a copper service lateral or tape the end of the PE tubing. Any existing water lateral to be removed shall be removed at the water main. d. Large Services: An anchoring tee shall be used to attach all 6 and 8 service laterals to all water mains. The auxiliary valve shall be directly attached to the anchoring tee. e. Curb Box Setting: All curb boxes shall be installed in the approximate middle of each lot. They shall be set to final grade. If they are installed in the sidewalk or driveway, a curb box receptacle shall be supplied by the MPU at applicant s cost and must be used. f. Wrapping: Copper service lines shall be wrapped and taped in polyethylene from the water main to the curb stop, entirely covering any exposed copper. The curb stop and curb box shall also be wrapped and taped in polyethylene. g. Installation of Tracer Wire on Services: Run tracer wire along polyethylene (plastic) laterals to and up/down all curb boxes and along remaining lateral length into property. Copper laterals do not require tracer wire. Wire splices shall be soldered with a self-flux rosin core solder and tightly wrapped with electrical tape so no copper wire is exposed. After the Contractor has completed all the underground installation on the project, the Contractor shall test the electrical continuity of all the tracer wire installations on the project with the Engineer. The Contractor shall be responsible for any costs of any repairs that may be required THRUST DEVICES a. General: A thrust device shall be provided on valves, fittings, dead ends and fine hydrants. b. Materials: For ductile iron pipe, the devices may be mechanical joint restraints, concrete to transmit load to undisturbed soil, steel rod typing the pipe together or when undisturbed soil is not available, as mass of concrete may be used to offset loads. For PVC pipe, only one of the concrete methods may be used. In no case should soft wood be used. c. Concrete Thrust Devices: Concrete thrust devices shall be made of Class E concrete as described in Chapter of the Standard Specifications for Sewer and Water Construction in Wisconsin. d. Size: Thrust blocks shall be designed to have sufficient bearing area and shall be so placed as to safely transmit to the surrounding earth, the maximum forces which may occur in the pipeline at that point. The MPU will approve all thrust device sizes and placement. e. Installation of Concrete Thrust Devices: Concrete thrust blocks shall be placed between fitting and trench wall or trench bottom, as may be applicable. The CS-15

17 bearing faces of the concrete thrust block shall be placed against freshly cut and undisturbed trench wall or bottom of sound material. Formwork shall be constructed whenever necessary to confine the concrete to the prescribed dimension for the block. Form lumber shall be removed prior to testing. f. Upward Thrust: At vertical bends were upward thrust will occur, concrete thrust blocks utilizing reinforced steel bar collars shall be installed below the bend. As an alternate, the fitting may be buried in concrete. g. Curing: Concrete thrust blocks shall be allowed to cure for at least forty eight (48) hours prior to pressure tests on the pipelines. h. Mechanical Joint Restraints: Mechanical joint restraints meeting the applicable requirements of ANSI/AWWA C110/A21.10 may be used in lieu of concrete backing. Components of dissimilar metal shall be protected against corrosion by encasement of the entire assembly with 10-mil thick, loose polyethylene film in accordance with AWWA C105. Mechanical joint restraints shall be MEGALUG or equal. i. Excavation, Bedding and Backfill: Excavation, bedding and backfill for thrust devices shall be in accordance with Section 3, Construction of Water Main and Appurtenances, of these specifications. j. Field Tests: After completion of the installation of the thrust device and before acceptance thereof, the Contractor shall perform such tests as may be necessary to assure proper functioning of the thrust device. Defects disclosed by such testing shall be repaired to the satisfaction of the MPU representative, AND AT THE EXPENSE OF THE CONTRACTOR HYDROSTATIC TESTS a. General: All new mains shall be tested, under the supervision of the MPU representative, by the Contractor, and shall successfully pass the pressure and leakage tests. b. Pressure Test: After the test connections are made, air is removed and the main filled with water, the test section shall be subjected to water pressure normal to the area. After examination of exposed parts of the system, the test pressure will be increased to 150 pounds per square inch. The main shall be examined and if any defects are found, the Contractor shall immediately make the necessary repairs at his expense. The pressure test shall be repeated until no defects can be found. THE DURATION OF THE FINAL PRESSURE TEST SHALL BE ONE (1) HOUR AND THE PRESSURE SHALL NOT VARY BY MORE THAN +/-5 PSI. c. Leakage Test: The leakage test shall be conducted simultaneously with the pressure test and at the same pressure as the pressure test. Leakage is defined as the quantity of water to be supplied into the newly laid pipe, or any valved section of it, necessary to maintain the specified leakage test pressure after the main has been filled with water and the air expelled. CS-16

18 Leakage shall not exceed the number of gallons per hour as determined by the following formula for rubber-sealed joints: From AWWA C600-05: In case the section under test contains joints of various diameters, the allowable leakage will be the sum of the computed leakage for each size joint. Should any test section fail to meet the leakage test, the Contractor shall immediately make the necessary repairs at his own expense. THE DURATION OF THE FINAL LEAKAGE TEST SHALL BE ONE (1) CONTINUOUS HOUR DISINFECTION AND FLUSHING OF MAINS AND APPURTENANCES a. General: After pressure testing and prior to acceptance of work, the entire main including, but not limited to, valves, fittings, fire hydrants, service lines, and other appurtenances shall be disinfected in accordance with the latest edition of Department of Natural Resources NR809, NR811, AWWA C-601, and AWWA C-651 specifications. b. Applications of Chlorine: Either the continuous flow method or placing of HTH tablets method shall be used. HTH tablets shall be installed during the pipe installation process by gluing tablets inside each pipe joint and each fire hydrant. The continuous flow method shall incorporate all materials required to inject a solution of 50 mg/l chlorine throughout the portion to be disinfected. In no case, regardless of application method, shall the disinfection solution be less than 50 mg/l. c. Tablet Method: Because the preliminary flushing step must be eliminated to use tablets, this method shall be used only when scrupulous cleanliness has been exercised. It shall not be used if trench water or foreign material has entered the main or if water is below 5 degrees C (41 degrees F). i. Fillings and Contact: The main to be filled (tablet method) shall be filled with water at a velocity less than one (1 ) foot per second. This water CS-17

19 shall remain in the main for twenty four (24) hours. d. Chlorine Residual: The chlorine residual shall not be less than twenty five (25) mg/l after twenty four (24) hours for either method used. e. Rechlorination: In the event the chlorine residual is less than required, the distribution system being disinfected shall be rechlorinated using the continuous flow method by and AT THE EXPENSE OF THE CONTRACTOR. Rechlorination will be preceded by flushing as required by these specifications. f. Flushing: After disinfection in accordance with the latest edition of AWWA C- 601 and C-651, the main shall be flushed with a flushing velocity of not less than 2.5 fps and sustained for a period of time not less than twice the minimum theoretical time necessary to flush the entire length of the main. If so directed by the MPU representative, portions of certain appurtenances may be required to be temporarily reconfigured for flushing purposes. In the event of possible adverse effects of flushing on system operation, flushing shall be conducted during the hours of least demand or as directed by the MPU representative. The MPU shall not be responsible for loss or damage to grading and landscaping resulting from the flushing operations. g. Safe Bacteriological Sample: In accordance with NR809.10(4), at least one bacteriologically safe sample shall be obtained before waterworks are placed into service. When new distribution systems or extensions on a number of streets are installed, bacteriological samples shall be taken at representative locations to establish that all of the improvements are free of contamination. h. Sampling Instructions (by MPU staff only): i. Avoid plastic, swing, goose-neck, leaky, chrome and outside faucets. ii. Remove any faucet aerator, gasket, screen or hose and run the water until cold. iii. Sterilize the faucet using a propane or butane torch. Hold the flame beneath the faucet opening for 20 seconds. Move the flame continuously to prevent damage to the faucet. Plastic or chrome faucets will melt when heated. iv. Run the cold water at medium force for at least 5 minutes before collecting samples. Do not change the flow rate or wash or wipe the tap before collecting the sample. v. Remove the security seal, and then remove the sample bottle cap without touching the inside of the cap or bottle. Hold onto the cap while sampling. vi. Fill bottle to within one inch of the top or to the fill line. Replace cap securely. Write name on the side of the bottle. vii. Send the water sample and this completed form to the MPU Water laboratory, which is certified under the Safe Drinking Water Act for the CS-18

20 3. INSULATION viii. testing of total coliform and fecal coliform/e. Coli bacteria by an enzyme substrate method. MPU will report the results electronically to the Department. 3.1 General: Water mains shall be insulated over the watermain wherever the depth of cover is less than five (5 ) feet. Water mains shall be insulated under the watermain wherever the watermain crosses a storm sewer, gas main, or other similar conductor of cold temperature. 3.2 Materials: Insulation shall be with polystyrene boards with a minimum thickness of four (4 ) inches. If only two (2 ) inch material is available, multiple layers shall be used. 3.3 Placement: Prior to placement of these polystyrene boards, bedding material shall be placed to a height of six (6 ) inches over the top of the pipe, leveled and compacted. The insulating boards shall be placed on the cover material with the long side parallel to the centerline of the water main for a minimum width of O.D. + twenty four (24 ) inches. The boards shall be placed in a staggered arrangement so as to eliminate continuous transverse joints. If two (2) or more layers of insulation boards are used, each layer should be placed so as to cover the joints of the layer immediately below. The first lift of backfill material shall consist of six (6 ) inches of bedding material which shall be end or side dumped onto the insulation board and spread in such a manner that construction equipment does not operate directly on the insulation. This layer shall be compacted with equipment that exerts a contract stress of 70 to 80 PSI. Once this layer has been compacted to the specified density, the remaining layers of backfill may be constructed utilizing conventional procedures. 4. ABANDONMENT OF EXISTING FACTILITIES 4.1 Water Main: Unless otherwise indicated on drawings, where water mains are abandoned, they shall be disconnected and left in place. All appropriate valves shall be closed and the valve box removed. If the valve is in a manhole, the top ring of the manhole shall be removed and the manhole shall be filled with a slurry of granular material. The end of the pipe shall be plugged with concrete. 4.2 Valves: When only a valve is abandoned in place, it shall be left in an open position, and the valve box or manhole abandoned as in Section If the valve is broken closed, it shall not be abandoned in place, but must be removed. All existing water valve manholes are to have the top ring removed and the manhole filled with "0" bag slurry. If construction warrants, the manhole could be removed completely and the hole backfilled as appropriate. CS-19

21 Existing valves and valve manholes shall not be abandoned until existing mains are abandoned Services: When services are permanently abandoned, they must be shut-off at the corporation stop and disconnected. If the service is to be reused, it may be shut-off at the curb stop. (Peening shut the end of the service and closing the curb stop is not an acceptable method to permanently abandon a service.) Curb boxes shall be removed or cut-off and abandoned below grade Reuse of Service: Old lead and galvanized steel services shall not be reused. A new service may not be created through the Siamese connection of two (2) or more existing services with a wye or tee Hydrants: All existing hydrants that are to be abandoned are to be disconnected at the lead elbow, removed and transported to the Manitowoc Public Utilities storage facilities. The hole is to be backfilled as appropriate. 5. BARRICADES, WARNING SIGNS AND FLAGMEN 5.1 General: Erecting and maintaining traffic signs, barricades, lights and signals, flagging and guidance of traffic is the responsibility of the Contractor. It shall be carried forth in accordance with the latest revision of Manual of Uniform Traffic Control Devices. Sign sizes smaller than the standard sizes described in the manual shall not be used. 6. TRAFFIC 6.1 General: If it is necessary to close down sections of the street for short periods while installing water main and appurtenances, the Contractor shall request permission from the City of Manitowoc, Department of Engineering, or the Police Department. If approved, the Contractor shall provide all detour signs and alternate route signs for the convenience of the public. No driveway shall remain inaccessible at the end of any working day unless agreed to by the property owner. 7. PERMITS, APPROVALS, EASEMENTS AND LOCATIONS 7.1 General: All permits, approvals and easements shall be acquired by MPU before construction begins. Any specific requirements of these documents shall be made known to the Contractor. 7.2 Locations: Locations for all utilities shall be the responsibility of the Contractor. 7.3 Staking: Staking of the route for construction shall be the responsibility of the MPU. However, any measurements required for field adjustments shall be the responsibility of the Contractor. CS-20

SECTION 2100 WATER MAIN

SECTION 2100 WATER MAIN SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

SUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611

SUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611 Revised October 10, 2014 SUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611 Water Main and Service Line Installation shall be in accordance with

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Engineer. 812.2 MATERIALS: The

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860)

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860) City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT 06457 TEL: (860) 638-3500 FAX: (860) 343-8091 GENERAL REQUIREMENTS WATER MAIN AND SERVICE INSTALLATION JANUARY 2017 WATER MAINS:

More information

CALAVERAS COUNTY WATER DISTRICT Ebbetts Pass Water System Reach 3A Pipeline Replacement Project CCWD CIP No ADDENDUM 2

CALAVERAS COUNTY WATER DISTRICT Ebbetts Pass Water System Reach 3A Pipeline Replacement Project CCWD CIP No ADDENDUM 2 CALAVERAS COUNTY WATER DISTRICT Ebbetts Pass Water System Reach 3A Pipeline Replacement Project CCWD CIP No. 11078 ADDENDUM 2 Date Issued: December 2, 2015 **** Receipt of addenda must be acknowledged

More information

SECTION WATER DISTRIBUTION

SECTION WATER DISTRIBUTION SECTION 33 10 00 WATER DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY 1.02 CODES A. Section Includes: 1. Underground water service piping, watermains and appurtenances. A. All work shall comply with the most

More information

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE PART 1 - GENERAL 1.1 DESCRIPTION A. This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, pressure pipe. 1.2 RELATED WORK SPECIFIED ELSEWHERE

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE SECTION 02622 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE PART 1 - GENERAL 1.1 SCOPE A. The work covered by this section includes furnishing all labor, equipment, and materials required to install and test

More information

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID:

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID: TECHNICAL SPECIAL PROVISION FOR 1001 WATER DISTRIBUTION SYSTEM FINANCIAL PROJECT ID: 200105-7-52-01 The official record of this Technical Special Provision is the electronic file signed and sealed under

More information

Copper-Type K soft Drawn 40, 50 HDPE 100 and larger

Copper-Type K soft Drawn 40, 50 HDPE 100 and larger 1.0 GENERAL 1.1 Scope 1.1.1 The work covered by this section involves the installation of water and sewer service connections and all other associated work. 1.2 Authorization 1.2.1 Do not install service

More information

SECTION PIPE INSTALLATION

SECTION PIPE INSTALLATION SECTION 02232 PIPE INSTALLATION A. General The pipe shall be Ductile Iron pipe with Tyton push-on joints and cement lined as described and manufactured in accordance with ANSI/AWWA C151/A21.51. Gaskets

More information

YAKIMA COUNTY, WASHINGTON. Special Provisions For Water Main Construction

YAKIMA COUNTY, WASHINGTON. Special Provisions For Water Main Construction YAKIMA COUNTY, WASHINGTON Special Provisions For Water Main Construction The 2014 Standard Specifications for Road, Bridge, and Municipal Construction as prepared by the Washington State Department of

More information

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,

More information

***************************************************************************************************************

*************************************************************************************************************** 02732 SANITARY FORCE MAIN *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 34 00. ***************************************************************************************************************

More information

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS SECTION 401 PIPE AND FITTINGS PART 2 MATERIALS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS A. PVC Pressure Pipe sizes 4 inch through 12 inch: ANSI/AWWA C 900 1. DR18 B. PVC Pressure Pipe sizes 14 inch

More information

CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER

CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER WATER MAIN 1. All open cut water main shall be polyvinyl chloride plastic (PVC) pressure pipe per AWWA specification

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 02080 FIRE HYDRANTS PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, material, equipment, tools, services and incidentals necessary to furnish and

More information

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01

More information

SECTION WATER UTILITIES

SECTION WATER UTILITIES SECTION 33 10 00 PART 1 - GENERAL 1.1 DESCRIPTION: Underground water distribution system complete, ready for operation, including all appurtenant structures, and connections to both new building service

More information

1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections.

1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections. Issued 2005/06/01 Section 02511 Water Mains Page 1 of 10 PART 1 GENERAL 1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service

More information

CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING

CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING 1.1 HANDLING Pipe, fittings and accessories shall be handled with care and shall not be dropped or bumped against pipe or appurtenances already or against any other

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

1. Required Minimum Flow:

1. Required Minimum Flow: SECTION 6 6. 6.01 General The City of Castle Rock Water System Minimum Standards and Specifications are minimum base level performance, design, and construction standards used to maintain uniformity of

More information

SECTION LAYING AND JOINTING BURIED PIPELINES

SECTION LAYING AND JOINTING BURIED PIPELINES SECTION 02650 LINES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Installation of all underground pipelines. Provide pipeline materials, coatings and linings as specified and pipe of the types, sizes

More information

SECTION WATER DISTRIBUTION SYSTEM

SECTION WATER DISTRIBUTION SYSTEM Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development

More information

CITY OF FARGO SPECIFICATIONS SEWER AND WATER SERVICE CONNECTIONS

CITY OF FARGO SPECIFICATIONS SEWER AND WATER SERVICE CONNECTIONS SEWER AND WATER SERVICE CONNECTIONS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of the furnishing of all labor, material,

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Davis and Weber Counties Canal Company

Davis and Weber Counties Canal Company PRESSURIZED SECONDARY WATER CONSTRUCTION SPECIFICATIONS For Davis and Weber Counties Canal Company January 2016 1 SECTION 1: GENERAL QUALITY CONTROL REQUIREMENTS 1.1 SCOPE: This section defines the general

More information

DETAILED WATER MAIN SPECIFICATONS INDEX. Sec. No. Items Page Nos.

DETAILED WATER MAIN SPECIFICATONS INDEX. Sec. No. Items Page Nos. INDEX Sec. No. Items Page Nos. 1. Ductile Iron Pipe............... DWM 2 thru DWM 5 2. Reinforced Concrete Water Main............... DWM 5 thru DWM 6 3. Hydrants............... DWM 7 4. Gate Valves and

More information

Exhibit A FOX CHAPEL AUTHORITY STANDARD SPECIFICATIONS FOR MATERIALS AND INSTALLATION OF WATER MAINS

Exhibit A FOX CHAPEL AUTHORITY STANDARD SPECIFICATIONS FOR MATERIALS AND INSTALLATION OF WATER MAINS Exhibit A FOX CHAPEL AUTHORITY STANDARD SPECIFICATIONS FOR MATERIALS AND INSTALLATION OF WATER MAINS Requests for extensions to Authority water mains shall be made in writing by the owner or owners of

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.24 POLYETHYLENE PRESSURE PIPE PART 1 GENERAL... 2 1.1 Description... 2 1.2 Reference Specification... 2 1.3

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD SPECIFICATIONS Establishing Minimum Standards for as Related To Fire Protection STANDARD # 103 REVISED 04/01/19 PAGES 7 SCOPE: These specifications shall

More information

REGIONAL CONSTRUCTION STANDARDS

REGIONAL CONSTRUCTION STANDARDS REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.1 (Full Committee Approved Proposed Revision 6.1 Ductile Iron Pipe Protections - Section 200 As Publication Update 6.1) March 27, 2018

More information

SECTION GRAVITY WASTEWATER LINES

SECTION GRAVITY WASTEWATER LINES SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS

More information

All definitions are defined according to ANSI/AWWA C

All definitions are defined according to ANSI/AWWA C SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR REDUCED-WALL, RESILIENT-SEATED GATE AND TAPPING VALVES FOR WATER SUPPLY SERVICE 4 IN. THROUGH 48 IN. ANSI/AWWA C515-01 July 2017 1. SCOPE This product specification

More information

PART 2 SECTION 9 WATERLINES

PART 2 SECTION 9 WATERLINES PART 2 SECTION 9 WATERLINES 9-1 General - All pipe, pipeline installations and facilities related thereto, shall be as specified herein. All pipe installation shall be in accordance with the manufacturers

More information

WATER TRANSMISSION AND DISTRIBUTION LINES

WATER TRANSMISSION AND DISTRIBUTION LINES SECTION 2300 WATER TRANSMISSION AND DISTRIBUTION LINES 1.00 GENERAL 1.01 Scope. Work under this Section shall include furnishing all materials, labor, equipment and miscellaneous items necessary to install,

More information

KENNEBUNK, KENNEBUNKPORT & WELLS WATER DISTRICT MATERIAL SPECIFICATIONS 10/11/2018

KENNEBUNK, KENNEBUNKPORT & WELLS WATER DISTRICT MATERIAL SPECIFICATIONS 10/11/2018 KENNEBUNK, KENNEBUNKPORT & WELLS WATER DISTRICT MATERIAL SPECIFICATIONS 10/11/2018 The following material specifications section is intended to apply to ALL new construction, both public and private. For

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

SECTION PIPING SPECIALTIES AND ACCESSORIES

SECTION PIPING SPECIALTIES AND ACCESSORIES SECTION 15120 PIPING SPECIALTIES AND ACCESSORIES PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified 1. CONTRACTOR shall provide all labor, materials, equipment, tools, services, and incidentals necessary

More information

THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR WATERMAINS

THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR WATERMAINS THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR WATERMAINS INDEX Page No. W.1. GENERAL...1 W.2 SCOPE...2 W.3 MATERIALS...2 W.3.1 General... 2 W.3.2 Concrete... 2 W.3.3 Pipe Bedding and Backfill

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.

More information

MATERIAL/MANUFACTURER SPECIFICATIONS FOR DISTRIBUTION WATER MAINS AND APPURTENANCES

MATERIAL/MANUFACTURER SPECIFICATIONS FOR DISTRIBUTION WATER MAINS AND APPURTENANCES MATERIAL/MANUFACTURER SPECIFICATIONS FOR DISTRIBUTION WATER MAINS AND APPURTENANCES REVISION April 2008 1 MATERIAL SPECIFICATIONS T.S. 1 GENERAL Materials incorporated in the finished work and used during

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION DUCTILE IRON PIPE, FITTINGS AND SPECIAL ITEMS

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION DUCTILE IRON PIPE, FITTINGS AND SPECIAL ITEMS SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.13 DUCTILE IRON PIPE, FITTINGS AND SPECIAL ITEMS PART 1 GENERAL... 3 1.1 Description... 3 1.2 Reference Specifications,

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

CHAPTER 3 - PRESSURE IRRIGATION

CHAPTER 3 - PRESSURE IRRIGATION CHAPTER 3 - PRESSURE IRRIGATION 3.1 GENERAL This division covers furnishing and installing pressure pipe as shown on the Drawings or established in the field, and all flushing, testing, repairing, as required

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

PIPE AND FITTINGS. Submit product information sheet for joint restraint system to be used.

PIPE AND FITTINGS. Submit product information sheet for joint restraint system to be used. PIPE AND FITTINGS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe B. Fittings C. Special Fittings D. Pipeline Accessories 1.02 DESCRIPTION OF WORK Construct water mains and building service pipes. 1.03

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

All definitions are defined according to ANSI/AWWA C b. Flanged Joint: The flanged and bolted joint as described in ANSI/AWWA C110/A21.10.

All definitions are defined according to ANSI/AWWA C b. Flanged Joint: The flanged and bolted joint as described in ANSI/AWWA C110/A21.10. 21-02 SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR RESILIENT-SEATED GATE AND TAPPING VALVES FOR WATER SUPPLY SERVICE ANSI/AWWA C509-01 3 IN., 4 IN., 6 IN., 8 IN., 10 IN., 12 IN., 16 IN., & 20 IN. Revised

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005 Subdivision Requirements Manual Page 1 of 5 PART I - GENERAL 1.1 Related Work.1 Rough Grading: Section 02211 1.2 Scope of Work.1 This section includes the supply and installation of all labour and materials

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 33 11 00 Water Utility Distribution Piping 1. Introduction A. Duke University owns and operates the water distribution system throughout the campus boundaries; however, water is supplied by the City

More information

CHAPTER 4 - CULINARY WATER

CHAPTER 4 - CULINARY WATER CHAPTER 4 - CULINARY WATER 4.1 GENERAL This Division covers furnishing and installing pressure pipe to the lines and grades shown on the drawings and/or established in the field, and all flushing, testing,

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

Water & Industrial Products Catalog

Water & Industrial Products Catalog Water & Industrial Products Catalog www.smith-blair.com info@smith-blair.com Phone: 800..9705 or 870.77.527 After Hours Number: 90.277.998 Fax: 800.8.792 or 870.77.52 EMERGENCY PHONE 90.277.998 In the

More information

SECTION VI SANITARY SEWERS

SECTION VI SANITARY SEWERS SECTION VI SANITARY SEWERS VI-1. DESIGN GUIDELINES Sewer collection lines and appurtenant structures within the jurisdiction of City of Paso Robles shall be constructed in accordance with plans prepared

More information

B. This section includes the furnishing and installation of a water distribution system.

B. This section includes the furnishing and installation of a water distribution system. PAGE 331000-1 SECTION 331000 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa). SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION 027 SPECIFICATIONS - PIPE MATERIALS FOR SEWERS

SECTION 027 SPECIFICATIONS - PIPE MATERIALS FOR SEWERS SECTION 027 SPECIFICATIONS - PIPE MATERIALS FOR SEWERS Pipe material used to construct, repair or modify sewers shall conform to the specifications within this Section. 1.0 Clay Pipe Construction of clay

More information

University of Central Florida Main Campus. Domestic Water. Service and Meter Installations Requirements. Issued January 26 th, 2017.

University of Central Florida Main Campus. Domestic Water. Service and Meter Installations Requirements. Issued January 26 th, 2017. University of Central Florida Main Campus Domestic Water Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS...

More information

CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING

CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING 1.1 HANDLING Pipe, fittings and accessories shall be handled with care and shall not be dropped or bumped against pipe or appurtenances already or against any other

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

PART 5 WATER SYSTEMS

PART 5 WATER SYSTEMS PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete

More information

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS SECTION 02530 - SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Inspector. 812.2 SUBMITTALS: Contractor

More information

SECTION PUBLIC WATER SERVICE CONNECTIONS

SECTION PUBLIC WATER SERVICE CONNECTIONS SECTION 33 14 14 PUBLIC WATER SERVICE CONNECTIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe and fittings for water service connections to small commercial, light industrial, and residential

More information

PVC PRESSURE FITTINGS

PVC PRESSURE FITTINGS GUIDE FOR PVC PRESSURE FITTINGS TABLE OF CONTENTS Introduction 3 Standards and Specifications 3 Products 4 Manufacturing Methods 8 Fabricated Fittings 8 Injection-Molded Fittings 9 Machined Couplings 9

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections. SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity

More information

SECTION 5 INSTALLATION OF DUCTILE IRON AND PVC PIPE, VALVES, FITTINGS, FIRE HYDRANTS, AND APPURTENANCES

SECTION 5 INSTALLATION OF DUCTILE IRON AND PVC PIPE, VALVES, FITTINGS, FIRE HYDRANTS, AND APPURTENANCES SECTION 5 INSTALLATION OF DUCTILE IRON AND PVC PIPE, VALVES, FITTINGS, FIRE HYDRANTS, AND APPURTENANCES 5-01 GENERAL Unless specified differently on the plans or as supplemented herein, installation of

More information

TECHNICAL SPECIFICATIONS WATER MAINS & MATERIALS

TECHNICAL SPECIFICATIONS WATER MAINS & MATERIALS WATER MAINS & MATERIALS Scope of Work Work to be performed under this contract shall consist of furnishing and installing, complete and ready for service, the water mains with various appurtenances as

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

SERVICE LINES, METERS AND APPURTENANCES

SERVICE LINES, METERS AND APPURTENANCES AUGUST02 SECTION 02646 SERVICE LINES, METERS AND APPURTENANCES PART 1 - GENERAL 1.1 DESCRIPTION A. This section concerns materials and installation of corporation stops, curb stops, service lines, meters,

More information

DIVISION 2 SITE WORK SECTION SYSTEM WATER LINES

DIVISION 2 SITE WORK SECTION SYSTEM WATER LINES DIVISION 2 SITE WORK SECTION 02667 SYSTEM WATER LINES PART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Pipe and fittings for water lines including, HDPE sludge mains. 2. Gate valves and appurtenances.

More information

STANDARD SPECIFICATION SECTION POLYVINYL CHLORIDE (PVC) DISTRIBUTION PIPE (AWWA C905)

STANDARD SPECIFICATION SECTION POLYVINYL CHLORIDE (PVC) DISTRIBUTION PIPE (AWWA C905) STANDARD SPECIFICATION SECTION 15293 POLYVINYL CHLORIDE (PVC) DISTRIBUTION PIPE (AWWA C905) PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, installation, and testing of PVC distribution

More information

CHAPTER 3 - PRESSURE IRRIGATION

CHAPTER 3 - PRESSURE IRRIGATION CHAPTER 3 - PRESSURE IRRIGATION 3.1 GENERAL This division covers furnishing and installing pressure pipe as shown on the Drawings or established in the field, and all flushing, testing, repairing, as required

More information

UBC OKANAGAN UBC Technical Guidelines Section Edition Water Utilities Page 1 of 11

UBC OKANAGAN UBC Technical Guidelines Section Edition Water Utilities Page 1 of 11 Page 1 of 11 1.0 GENERAL 1.1 This Section refers to those portions of work related to supply and installation of geothermal mains, valves and valve boxes, fittings, service connections and related appurtenances.

More information

CHAPTER 8 WATER SUPPLY SYSTEM

CHAPTER 8 WATER SUPPLY SYSTEM CHAPTER 8 WATER SUPPLY SYSTEM 8-1 INTRODUCTION These improvement standards shall govern the engineering design of all domestic water systems intended for operation and maintenance by the County of Sutter

More information

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS Rev: 3/26/18 Pipe and fittings used in sanitary sewer construction shall

More information

SECTION SEWER PIPE

SECTION SEWER PIPE SECTION 02530 SEWER PIPE PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: Furnish and install all piping as shown on the Drawings, described in the Specifications and as required for a complete and operable

More information

SECTION VII WATER. Concrete anchor and thrust blocks shall be provided at all discontinuities in accordance with Standard Details G-7.1 and G-7.2.

SECTION VII WATER. Concrete anchor and thrust blocks shall be provided at all discontinuities in accordance with Standard Details G-7.1 and G-7.2. SECTION VII WATER VII-1. DESIGN GUIDELINES Water pipelines and appurtenant structures within the jurisdiction of the City of Paso Robles shall be constructed in accordance with plans prepared by a Professional

More information

CVO/169897A OCTOBER 29, CONVEYANCE PIPING GENERAL

CVO/169897A OCTOBER 29, CONVEYANCE PIPING GENERAL SECTION 02500 CONVEYANCE PIPING - GENERAL PART 1 GENERAL 1.1 REFERENCES A. The following is a list of standards which may be referenced in this section: 1. American Concrete Institute (ACI): 301, Standard

More information

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES B-1 General Notes: SACWSD Standard Construction Drawing Notes 1. No work shall begin on any water or wastewater construction project until the construction

More information

Section FORCE MAINS. This specification provides the requirements for force mains construction for the project.

Section FORCE MAINS. This specification provides the requirements for force mains construction for the project. CCU STANDARD SPECIFICATIONS Section 002325 FORCE MAINS Effective Date: Nov. 1, 2011 Rev#02 Page 1 of 11 PART 1 - GENERAL The following specification is intended for use for the design, selection of materials,

More information