Property of Cooks Plumbing Supplies

Size: px
Start display at page:

Download "Property of Cooks Plumbing Supplies"

Transcription

1 ASSESSMENT REPORT Assessment of the fire resistance performance of various diameter EZIPEX and pipes protected with Fireban One mastic or Hilti Firestop Intumescent sealant CP611A in wall systems when tested in accordance with AS EWFA Report No: Report Sponsor: Boone & Willard Plumbing Pty Ltd Unit 13, 5 Meridian Place Bella Vista, NSW 2153 And Cooks Plumbing Supplies 27 Loyalty Road North Rocks, NSW 2151

2 Page 2 of 25 DOCUMENT REVISION STATUS Date Issued Issue No Description 2/11/ Initial Issue CONTACT INFORMATION Exova Warringtonfire Aus Pty Ltd - ABN NATA Registered Laboratory Unit 2, Hammond Road Dandenong Victoria 3175 Australia T: +61 (0) F: +61 (0) New South Wales Suite 2002a Level 20, 44 Market Street Sydney NSW 2000 Australia T: +61 (0) F: +61 (0) Victoria Unit 2, Hammond Road Dandenong Victoria 3175 Australia T :+61 (0) F:+61 (0) Queensland Northpoint, Unit 29, Level North Quay Brisbane QLD 4000 Australia T: +61 (0) F: +61 (0)

3 Page 3 of 25 CONTENTS 1 INTRODUCTION 4 2 TESTED PROTOTYPES 4 3 VARIATION TO TESTED PROTOTYPES 4 4 REFERENCED TEST PROCEDURES 14 5 FORMAL ASSESSMENT SUMMARY 15 6 DIRECT FIELD OF APPLICATION 16 7 REQUIREMENTS 16 8 VALIDITY 16 9 AUTHORITY Applicant Undertakings and Conditions of Use General Conditions of Use Authorisation on Behalf of Exova Warringtonfire Aus Pty Ltd Date of Issue Expiry Date 17 APPENDIX A - SUMMARY OF SUPPORTING DATA 18 A.1 Test Report EWFA APPENDIX B - ASSESSMENT OF SPECIFIC VARIATIONS 20 B.1 Penetrations on Single, Staggered Single or Double Stud Wall Systems B.2 Penetrations on Various Double Stud Wall Systems Only 20 24

4 Page 4 of 25 1 INTRODUCTION This report presents an assessment of the fire resistance performance of various diameters EZIPEX and pipes protected with Fireban One mastic or Hilti Firestop Intumescent sealant CP611A in wall systems when tested in accordance with AS The tested systems are described in Section 2 if tested in accordance with the referenced test method described in Section 3. The conclusions of the report are summarised in Section 4. The validity of this assessment is conditional on compliance with Sections 6, 7 and 8 of this report. Summaries of the test data on which this assessment is based are provided in the Appendices together with a summary of the critical issues leading to the assessment conclusions including the main points of argument. 2 TESTED PROTOTYPES This assessment makes reference to test report EWFA Test describes a full scale test of a 130mm thick fire rated plasterboard lined wall system with EZIPEX and pipes penetrated on the exposed and unexposed side in accordance with AS The test was undertaken by Exova Warringtonfire Aus Pty Ltd and was sponsored by Boone & Willard Plumbing Pty Ltd and Cooks Plumbing Supplies. Refer to Appendix A for a detailed summary of the reference test data. 3 VARIATION TO TESTED PROTOTYPES The proposed construction for products named EZIPEX and pipes in plasterboard lined walls shall be as tested in EWFA , subject to the following variations; The wall systems shall be single stud, single staggered stud or double studs with same or greater depth than tested and the wall linings are summarised in Table 2. Wall cavity includes Glasswool insulation with a minimum density of 10.5kg/m3. The minimum wall thickness shall be 130mm. Wall systems shall be exposed to exposure from either direction. Penetration installation refers to Table 1. The general arrangement of services is shown in figure 1.

5 Page 5 of 25 Services installed in and out on the fire side wall lining Figure 1 - General arrangement of services Table 1 Penetrations in Wall Systems Listed in Table 2 and 3 ID A B C D E F G H I J K L M N O P Q R S T U V Pipe Ø16mm GAS Ø16mm GAS Ø16mm GAS Ø16mm Additional Fitting Max. height from floor none 1.2m none 0.3m none 2.8m Brass 19bp 1m Services installed in and out on the nonfire side wall lining Sealant around pipe Bostik Fireban One Max. gap around pipe 15mm Max. gap around pipe GAS GAS none 2.8m GAS none 0.3m Hilti CP 611A 10mm 10mm Ø16mm none 1.2m 5mm

6 Page 6 of 25 Table 2 Single and Staggered Steel Stud Systems Construction Details Framing Arrangement and cavity insulation System Number Linings Side One Side Two 1 13mm Fire Rated Plasterboard 1 16mm Fire Rated Plasterboard 1 10mm or 13mm Non Fire grade Plasterboard 2 13mm Fire Rated Plasterboard 2 16mm Fire Rated Plasterboard 1 13mm Fire Rated Plasterboard 1 16mm Fire Rated Plasterboard 1 10mm or 13mm Non Fire grade Plasterboard 2 13mm Fire Rated Plasterboard 2 16mm Fire Rated Plasterboard Table 3 Double Steel Stud Systems Linings Side One Side Two Construction Details 1 13mm Fire Rated Plasterboard 1 16mm Fire Rated Plasterboard 1 10mm or 13mm Non Fire grade Plasterboard 2 13mm Fire Rated Plasterboard 2 16mm Fire Rated Plasterboard 1 13mm Fire Rated Plasterboard 1 16mm Fire Rated Plasterboard 1 10mm or 13mm Non Fire grade Plasterboard Glasswool insulation with a minimum density of 10.5kg/m 3 Bradford Insulation Batts Gold Wall R2.0 with a density of 10.5kg/m3. Framing Arrangement and cavity insulation Bradford Insulation Glasswool Batts Gold Wall R2.0 insulation with a minimum with a density density of of 10.5kg/m 10.5kg/m3. 3 System Number mm Fire Rated Plasterboard 2 16mm Fire Rated Plasterboard

7 Page 7 of 25 Table 4 Schedule of Components Name Description Wall Lining Wall Framing Wall Insulation Bostik Fireban One Sealant Hilti Firestop Intumescent Sealant CP 611A Pipe Pipe Material 13mm or 16mm thick fire grade plasterboard and 10mm and 13mm non-fire grade plasterboard based on design Installation Refer to Table 2 and Table 3 Material Size Spacing Material Steel framing designed in accordance with AS4600 The studs shall be installed as single stud, single staggered stud or double studs to have a minimum wall cavity of 90mm wide. Maximum 500mm centres. Glasswool insulation Density A minimum density of 10.5kg/m 3 Installation Installation Installation Fully installed in the cavity of the wall system. Sealant is applied to: Product EZIPEX PE-X 80 Material Pipe Size Fitting Around the perimeter of wall specimen The annular gap between penetration and wall lining(s) to the full depth of wall lining. Applied to the gap between penetration and wall lining(s) to the full depth of wall lining(s). PEX Ø16.3mm (OD) 2.4mm pipe wall thickness For pipe with no addition fitting: 2 19mm diecast Elbow connectors 6 18mm Copper crimped joint 2 16mm Brass end cap and For pipe fitted with additional Brass 19bp : 2 19mm diecast Elbow connectors 6 18mm Copper crimped joint 1 16mm Brass end cap 1 16mm Brass screw end cap 1 Brass 19bp Product EZIPEX PE-X 80 Material Penetrated through wall linings on either fire side or non-fire side at various height listed in Table 1. PEX Pipe Size Fitting Ø20.2mm (OD) 3.2mm pipe wall thickness For pipe with no addition fitting: 2 24mm diecast Elbow connectors 6 22mm Copper crimped joint 2 Brass end cap and

8 Page 8 of 25 Name Description GAS Pipe GAS Pipe Product Material Pipe Size Fitting Product Material Pipe Size Fitting For pipe fitted with additional Brass 19bp : 2 24mm diecast Elbow connectors 6 Copper crimped joint 2 18mm Copper crimped joint 1 to 16mm reducer 1 Brass end cap 1 Brass screw end cap 1 Brass 19bp Penetrated through wall linings on either fire side or non-fire side at various height listed in Table 1. HDPE/AL/PEX Natural gas/lpg pipe PEX-AL Ø16.1mm (OD) 2.45mm pipe wall thickness For pipe with no addition fitting: 2 19mm diecast Elbow connectors 6 18mm Copper crimped joint 2 16mm Brass end cap and For pipe with additional Brass 19bp ; 2 19mm diecast Elbow connectors 6 18mm Copper crimped joint 1 16mm Brass end cap 1 16mm Brass screw end cap 1 Brass 19bp Penetrated through wall linings on either fire side or non-fire side at various height listed in Table 1. HDPE/AL/PEX Natural gas/lpg pipe PEX-AL Ø (OD) 2.2mm pipe wall thickness For pipe with no addition fitting: 2 24mm diecast Elbow connectors 6 22mm Copper crimped joint 2 Brass end cap and For pipe fitted with additional Brass 19bp : 2 24mm diecast Elbow connectors 6 Copper crimped joint 2 18mm Copper crimped joint 1 to 16mm reducer 1 Brass end cap 1 Brass screw end cap 1 Brass 19bp

9 Page 9 of 25 Name Description 16mm EZIPEX Elbow System 16mm EZIPEX GAS Elbow System 16mm EZIPEX Stopper System Dimension Dimension Penetrated through wall linings on either fire side or non-fire side at various height listed in Table 1. 1 EZIPEX Elbow 16mm 2 EZIPEX Compression Sleeve 16mm 90 degree joint of all 16mm EZIPEX pipes EZIPEX Elbow 16mm: long wide 12mm diameter with 19mm edge diameter EZIPEX Compression Sleeve 16mm: 18mm diameter long 1mm thick 90 degree joint of all 16mm pipes Elbow part: long wide 12mm diameter with 19mm edge diameter Compression Sleeve part: 18mm diameter long 1mm thick Compression Sleeve Elbow connector Compression Sleeve Stopper 1 EZIPEX Elbow 16mm 1 EZIPEX Compression Sleeve 16mm At the end of the 16mm EZIPEX pipe

10 Page 10 of 25 Name Description Dimension EZIPEX Stopper 16mm: End: 17.9mm diameter 3.6mm thick Edge: 19.4mm diameter 2.4mm thick Overall: 6mm thick EZIPEX Compression Sleeve 16mm: 18mm diameter long 1mm thick 16mm EZIPEX GAS Stopper System EZIPEX Elbow System Dimension Dimension At the end of the 16mm pipe Stopper part: End: 17.9mm diameter 3.6mm thick Edge: 19.4mm diameter 2.4mm thick Overall: 6mm thick Compression Sleeve part: 18mm diameter long 1mm thick 90 degree joint of all EZIPEX pipes EZIPEX Elbow : long wide 12mm diameter with 23mm diameter edge. EZIPEX Compression Sleeve : 21.6mm diameter 22mm long 0.8mm thick Compression Sleeve Elbow connector

11 Page 11 of 25 Name Description EZIPEX GAS Elbow System Dimension Brass end cap EZIPEX Stopper System Dimension 90 degree joint of all pipes Elbow part: long wide 12mm diameter with 23mm diameter edge. Compression Sleeve part: 21.6mm diameter 22mm long 0.8mm thick 1 EZIPEX Stopper 1 EZIPEX Compression Sleeve At the end of the EZIPEX pipe EZIPEX Stopper: End: 22mm diameter 3.9mm thick Edge: 23.3mm diameter 2.9mm thick Overall: 6.8mm thick EZIPEX Compression Sleeve : Compression Sleeve Stopper 21.6mm diameter 22mm long 0.8mm thick Dimension At the end of the pipe Stopper part:

12 Page 12 of 25 Name Description End: 22mm diameter 3.9mm thick Edge: 23.3mm diameter 2.9mm thick Overall: 6.8mm thick Compression Sleeve: 21.6mm diameter 22mm long 0.8mm thick Brass screw end cap EZIPEX 19BP Elbow 16mm ½ BSPM 65mm long system At the end of the /EZIPEX 19BP Elbow 16mm ½ BSPM 65mm long Dimension Dimension Installation 25.2mm long 15.1mm wide 3.4mm thick 1 EZIPEX 19BP Elbow 16mm ½ BSPM 65mm long 1 EZIPEX Compression Sleeve 16mm At the end of the pipe EZIPEX 19BP Elbow 16mm ½ BSPM 65mm long: 20.9mm diameter 90mm long EZIPEX Compression Sleeve 16mm: 19BP Elbow Compression Sleeve 18mm diameter long 1mm thick The flange is fixed to the timber nogging with three screws. One end is connected to the pipe and the other end protruded through the separating element and is capped with a brass screw end cap.

13 Page 13 of 25 Name Description 19BP Elbow 16mm ½ BSPM 65mm long system EZIPEX Reducing Coupling 20-16mm system Reducing Coupling 20-16mm system Dimension Installation Dimension Installation Dimension At the end of the pipe at bottom penetration 19BP Elbow part: 20.9mm diameter 90mm long Compression Sleeve: 18mm diameter long 1mm thick The flange is fixed to the timber nogging with three screws. One end is connected to the pipe and the other end protruded through the separating element and is capped with a brass screw end cap. compression sleeve Joints between Ø and pipe before the pipe connecting EZIPEX 19BP Elbow 16mm ½ BSPM 65mm long system EZIPEX Reducing Coupling: 23.2mm diameter on the pipe side and 19mm diameter on the 16mm pipe side EZIPEX Compression Sleeve 16mm: 18mm diameter long 1mm thick EZIPEX Compression Sleeve : 21.6mm diameter 22mm long 0.8mm thick The reducer is inserted over the pipes and secured mechanically via crimping. Joints between Ø and Ø16mm pipe before the pipe connecting 19BP Elbow 16mm ½ BSPM 65mm long system EZIPEX Reducing Coupling part: 23.2mm diameter on the pipe side and 19mm diameter on the 16mm pipe side EZIPEX Compression Sleeve 16mm part: Reducing Coupling 16mm compression sleeve

14 Page 14 of 25 Name Timber Nogging Open clip with metal screw Installation Material Installation Installation Description 18mm diameter long 1mm thick EZIPEX Compression Sleeve part: 21.6mm diameter 22mm long 0.8mm thick The reducer is inserted over the pipes and secured mechanically via crimping the sleeve. Dressing pine, minimum 90mm deep 4 REFERENCED TEST PROCEDURES The timber noggings are installed in staggered configuration and fixed to the metal studs with two screws on each side. Securing the EZIPEX and pipe to the timber noggings in the wall cavity This report is prepared with reference to the requirements of AS and assessed in accordance with AS

15 Page 15 of 25 5 FORMAL ASSESSMENT SUMMARY Based on the discussion presented in this report, it is the opinion of this testing authority that if the specimen described in section 2 had been modified within the scope of section 3, it will achieve the performances as stated below when tested in accordance with the test method referenced in Section 4 and subject to the requirements of Section 7: Table 5.1 Pipe Penetrations in Single and Staggered Wall Systems (Refer Table 2 and Figure 1) Pipe Ø16mm GAS Ø16mm GAS Ø16mm GAS Ø16mm GAS GAS GAS Ø16mm Fitting through lining Max. height from floor none 1.2m Sealant around pipe Bostik Fireban One Gap between Service and Lining 5mm- 15mm Wall system 1, 2, 3 or 4 FRL - Wall system 5, 6, 7 or 8 -/60/60 -/90/90 none 0.3m -/60/60 -/90/90 none 2.8m -/60/60 -/90/60 Brass 19bp none 2.8m 1m -/60/60 -/90/60 -/60/60 -/90/60 Hilti CP none 0.3m 10-15mm -/60/60 -/90/90 611A none 1.2m -/60/60 -/90/90

16 Page 16 of 25 Table 5.2 Pipe Penetrations in Double Stud Wall Systems (Refer Table 3 and Figure 1) Pipe Ø16mm GAS Ø16mm GAS GAS Addition Fitting Max. height from floor none 2.8m Brass 19bp none 2.8m 6 DIRECT FIELD OF APPLICATION Sealant around pipe Bostik Fireban One Gap Between Service and Lining 5mm- 15mm Wall system 9, 10, 11 or 12 FRL Wall system 13, 14, 15 or 16 -/60/60 -/90/90 1m -/60/60 -/90/90 Hilti CP 611A 10-15mm -/60/60 -/90/90 The results of this assessment are applicable to penetrations in walls exposed to fire from either side. 7 REQUIREMENTS This report details the methods of construction, test conditions and assessed results that would have been expected had the specific elements of construction described herein been tested in accordance with AS Any further variations with respect to size, constructional details, loads, stresses, edge or end conditions, other than those identified in this report, may invalidate the conclusions drawn in this report. It is required that the supporting construction be otherwise tested or assessed to achieve the required FRL of the penetration seal in accordance with AS VALIDITY This assessment report does not provide an endorsement by Exova Warringtonfire Aus Pty Ltd of the actual products supplied. The conclusions of this assessment may be used to directly assess the fire resistance performance under such conditions, but it should be recognised that a single test method will not provide a full assessment of the fire hazard under all fire conditions. Because of the nature of fire resistance testing, and the consequent difficulty in quantifying the uncertainty of measurement, it is not possible to provide a stated degree of accuracy. The inherent variability in test procedures, materials and methods of construction, and installation may lead to variations in performance between elements of similar construction.

17 Page 17 of 25 The assessment can therefore only relate only to the actual prototype test specimens, testing conditions and methodology described in the supporting data, and does not imply any performance abilities of constructions of subsequent manufacture. This assessment is based on information and experience available at the time of preparation. The published procedures for the conduct of tests and the assessment of test results are the subject of constant review and improvement and it is recommended that this report be reviewed on or, before, the stated expiry date. The information contained in this report shall not be used for the assessment of variations other than those stated in the conclusions above. The assessment is valid provided no modifications are made to the systems detailed in this report. All details of construction should be consistent with the requirements stated in the relevant test reports and all referenced documents. 9 AUTHORITY 9.1 APPLICANT UNDERTAKINGS AND CONDITIONS OF USE By using this report as evidence of compliance or performance, the applicant(s) confirms that: to their knowledge the component or element of structure, which is the subject of this assessment, has not been subjected to a fire test to the Standard against which this assessment is being made, and they agree to withdraw this assessment from circulation should the component or element of structure be the subject of a fire test by a test authority in accordance with the Standard against which this assessment is being made and the results are not in agreement with this assessment, and they are not aware of any information that could adversely affect the conclusions of this assessment and if they subsequently become aware of any such information, agree to ask the assessing authority to withdraw the assessment. 9.2 GENERAL CONDITIONS OF USE This report may only be reproduced in full without modifications by the report sponsor. Copies, extracts or abridgments of this report in any form shall not be published by other organisations or individuals without the permission of Exova Warringtonfire Aus Pty Ltd. 9.3 AUTHORISATION ON BEHALF OF EXOVA WARRINGTONFIRE AUS PTY LTD Prepared by: Reviewed by: S. Hu K. Nicholls 9.4 DATE OF ISSUE 02/11/ EXPIRY DATE 30/11/2020

18 Page 18 of 25 APPENDIX A - SUMMARY OF SUPPORTING DATA A.1 TEST REPORT EWFA A.1.1 A Report Sponsor Boone & Willard Plumbing Pty Ltd, Unit 13, 5 Meridian Place, Bella Vista, NSW 2153, and A Cooks Plumbing Supplies, 27 Loyalty Road, North Rocks, NSW A.1.2 A A.1.3 Test Laboratory Exova Warringtonfire Aus Pty Ltd, Unit 2, Hammond Road, Dandenong, Victoria 3175, Australia. Test Date A The test was conducted on 25 th May A.1.4 A A.1.5 A A A.1.6 A A.1.7 A A A A A ID Test Standards prescribed AS Section 2 and 10 as appropriate for a wall system penetrated by services. General description of tested specimens The test assembly comprised a nominal 3000mm wide x 3000mm high x 130mm thick wall system with EZIPEX and pipes penetrated on the exposed and unexposed side. The wall specimen comprised 91mm thick steel stud framing clad with two different boards setting on the north and south side of the wall system. On the south side, the wall framing was clad with a single layer of 13mm Fyrchek on the exposed side and double layer on the unexposed side. On the north side, the framing was clad with a double layer of 13mm Fyrchek on the exposed side and single layer on the unexposed side. The wall system was penetrated by 24-off different EZIPEX and pipe penetrations which were protected by Bostik Fireban One mastic or Hilti Firestop Intumescent Sealant CP 611A. The EZIPEX pipes were supported with the timber noggings inside the wall cavity, Instrumentation The test instrumentation was in accordance with AS Test Results The ambient temperature was approximately 17 C at the start of the test and did not vary significantly during the test, The test duration was 90, At 78, a hole had become evident on top of the pipe penetration K located on the top section of the south side of separating element. At 78, it had become evident that the pipe K located at the bottom section of the north side of the separating element had sagged. Pipe material Performance of Services through plasterboard wall system Fitting (Bottom opening only) Wall lining layer Fire Non- Fire Wall penetrated Integrity Insulation A B C 16mm EZIPEX EZIPEX 16mm none 1 2 Fire side only none 1 2 Fire side only none 1 2 Fire side only

19 Page 19 of 25 ID D E F G H I J K L M N O P Q R S T U V W Pipe material 16mm EZIPEX EZIPEX 16mm 16mm 16mm EZIPEX EZIPEX 16mm EZIPEX 16mm EZIPEX EZIPEX 16mm 16mm Fitting (Bottom opening only) Wall lining layer Fire Non- Fire Wall penetrated none 1 2 Fire side only none 1 2 Fire side only ½ brass 1 2 Fire side only ½ brass 1 2 Fire side only ½ brass 1 2 Fire side only ½ brass 1 2 Fire side only ½ brass 1 2 Fire side only none 1 2 ½ brass 1 2 Non fire side only Non fire side only none 2 1 Fire side only none 2 1 Fire side only none 2 1 Fire side only none 2 1 Fire side only none 2 1 Fire side only ½ brass 2 1 Fire side only ½ brass 2 1 Fire side only ½ brass 2 1 Fire side only ½ brass 2 1 Fire side only ½ brass 2 1 Fire side only none 2 1 Non fire side only Integrity Insulation Failed at 88 on wall lining Failed at 85 on wall lining Failed at 71 on wall lining Failed at 86 on wall lining X ½ brass 2 1 Non fire side only

20 Page 20 of 25 APPENDIX B - ASSESSMENT OF SPECIFIC VARIATIONS B.1 PENETRATIONS ON SINGLE, STAGGERED SINGLE OR DOUBLE STUD WALL SYSTEMS B.1.1 B B.1.2 B B B B B Proposal The proposed construction for EZIPEX and pipes in plasterboard lined walls shall be as tested in EWFA , subject to the following variations; The wall systems shall be single stud, single staggered stud or double studs with same or greater depth than tested and the wall linings are summarised in Table 2. Wall cavity shall be fully insulated with Glasswool insulation with a minimum density of 10.5kg/m3. The minimum wall thickness shall be 130mm. Wall systems shall be exposed to exposure from either direction. The wall material can also be hollow core masonry wall with wall thickness of 130mm or greater. Penetration installation refers to Figure 1. Discussion Tested Specimens The test assembly tested in a full scaled test EWFA comprised a 130mm thick steel framing wall system with EZIPEX and pipes penetrated through either exposed side wall lining(s) or unexposed side wall lining(s) of tested wall specimen. The tested wall specimen clad with two different boards setting on the north and south side of the wall system. With reference to the test configuration in test EWFA , pipe services A to J were installed on the exposed side of south part of wall specimen whereas services K and L were installed on the unexposed side of south part of wall specimen. The south part wall framing was clad with single layer of 13mm Fyrchek on the exposed side and double layer of 13mm Fyrchek on the unexposed side. With reference to the test configuration in test EWFA , pipe services M to V were installed on the exposed side of north part of wall specimen whereas services W and X were installed on the unexposed side of north part of wall specimen. The north part wall framing was clad with double layer of 13mm Fyrchek on the exposed side and single layer of 13mm Fyrchek on the unexposed side. The above 24 pipe services consisted of Ø16mm and pipes and Ø16mm and GAS pipes installed at 0.3m, 1m, 1.2m and 2.8m respectively from the floor level and protected with either Bostik Fireban One sealant or Hilti Firestop Intumescent sealant CP 611 in the annular gap between pipe and aperture. Additional brass 19bp fittings were fitted to the pipes which were installed at 1m from floor level. The proposed penetrations are identical to the services that tested in EWFA and installed in a similar manner. The key variations of proposed penetrations by comparison with the tested 24 pipe penetrations in EWFA , are summarised below; Inclusion of EZIPEX pipes and with or without brass fitting entering non-fire side wall lining(s) only at different heights. Applicability of Hilti Firestop Intumescent sealant CP 611A to Ø16mm and Ø EZIPEX pipes. Inclusion various steel stud framed wall systems as summarised in Table 2.

21 Page 21 of 25 B B B B B B B B B B B B B Services at Different Heights entering Either Side of Wall System The proposed Ø16mm and pipes and Ø16mm and GAS pipes were all tested at 0.3m, 1.2m and 2.8m high and entered either single layer of 13mm Fyrchek plasterboard on fire side of south part of wall specimen or double layer of 13mm Fyrchek plasterboard on fire side of north part of wall specimen tested in EWFA When tested, the services all maintained integrity performance of 90 without cracks, fissures or gap formation during the test duration. With reference to EWFA , EZIPEX and pipes installed at 0.3m and 1.2 high on fire side of both south part and north part of wall specimen maintained insulation performance of 90. With reference to EWFA , EZIPEX and pipes installed at 2.8m high on fire side of south part maintain insulation performance of 90 whereas 16mm and PEX pipes installed at 2.8m high on fire side of north part failed insulation at 85 and 71 respectively. The 16mm and pipes on fire side of north part wall though maintained insulation performance of 90. Upon inspection of the temperature measurements on unexposed side wall lining of service M and N, it was considered the sharply raise of temperature on the unexposed wall lining was occurred after the fire side lining(s) became parts and fell off, the wall cavity insulation started to catch on fire. In addition, the pressure at the penetrations located at 2.8m from floor was more than twice higher than the ones at 0.3m and 1.2m, hence the hot gases in the furnace is likely to convey more heat by convection to the top section of wall hence fail the insulation performance earlier. Service K and L comprised pipes which were installed on the non-fire side of south wall part, 0.3m, 1.2m and 2.8m away from floor level. Service W and X comprised pipes which were installed on the non-fire side of north wall part, 0.3m, 1.2m and 2.8m away from floor level. When tested, the four services all maintain integrity performance of 90 without cracks, fissures or gap formation during the test duration, the pipes exclude the one with additional brass fitting also maintain insulation performance of 90. The above test results demonstrate the Fireban One sealant seal around the pipe penetration is cable to maintain the integrity performance for at least 90. By comparison with the temperature measurements on the unexposed side wall lining of pipe on fire side and temperature measurements on unexposed side wall lining and pipe penetration of pipe on non-fire side, it is observed, the temperature raise of unexposed side wall lining followed similar trend during the test duration, and the temperature on the pipe on the unexposed side was lower than the plasterboard lining until the time when fire side linings fell off from framing. The significance of above test results demonstrates the presence of pipes on the unexposed side of wall specimen is unlikely to introduce any weakness to the integrity and insulation performance for at least 90. The proposed Ø16mm and Ø16mm and pipe though are not tested entering the non-fire side wall lining of wall system, based on the performance of pipe tested, it is reasonable expected the proposed pipes on non-fire side of wall system would at least maintain the similar performance to the ones installed on the fire side for up to 90. B The proposed wall systems 5 and 6 are as tested in EWFA , which clad with single layer of 13mm thick fire grade plasterboard on each and double layer of 13mm thick fire grade plasterboard on the other side. In light of the above, it is considered the proposed pipe penetration will maintain integrity performance and insulation performance summarised in table 5.1 when installed on wall systems 5 and 6 when tested in accordance with AS

22 Page 22 of 25 B B B B B B B B B B B B B Services with Brass Fitting entering Either Side of Wall System The proposed Ø16m and pipes and Ø16mm and GAS pipes were all tested with additional brass fitting 19bp at 1m high entered either single layer of 13mm Fyrchek plasterboard on fire side of south part of wall specimen or double layer of 13mm Fyrchek plasterboard on fire side of north part of wall specimen tested in EWFA When tested, the services all maintained integrity performance of 90 without cracks, fissures or gap formation during the test duration. The services all maintain insulation performance of 90. Service L and X comprised pipes fitted with additional brass 19bp were installed on the non-fire side of south and north part of wall system. When tested, the service L maintained integrity performance of 90 and failed insulation performance at 88 when the maximum temperature measured on pipe penetration exceed the maximum temperature rise limit of 180K. When tested, service X maintained integrity and insulation performance of 90 with no sign of impending integrity and insulation failure during the test duration. Upon inspection of the temperature measurements on unexposed side wall lining and pipe of Service L, it was considered the sharply raise of temperature on pipe was occurred after the fire side lining(s) became parts and fell off, the wall cavity insulation started to catch on fire. The presence of 26mm deep Fireban One sealant though prevented gap formation around pipe penetration is likely to close the opening formed by the brass fitting. The significance of above test results demonstrates the presence of pipes on the unexposed side of wall specimen is unlikely to introduce any weakness to the integrity performance up to 90 though insulation performance up to 60 The proposed Ø16mm and Ø16mm and pipe though are not tested entering the non-fire side wall lining of wall system, based on the behaviour of pipe with brass fitting tested, it is reasonable expected the proposed pipes on non-fire side of wall system would at least maintain the similar integrity performance to the ones installed on the fire side for up to 90 whereas lower the insulation performance to be 60. The proposed wall systems 5 and 6 are as tested in EWFA , which clad with single layer of 13mm thick fire grade plasterboard on each and double layer of 13mm thick fire grade plasterboard on the other side. In light of the above, it is considered the proposed pipe penetration with additional brass fitting shall maintain integrity performance and insulation performance summarised in table 5.1 when installed on wall system 5 and 6 when tested in accordance with AS Services sealed with Hilti Firestop Intumescent Sealant CP 611A Service E and Q comprised pipes installed on the fire side of south and north part of wall system and the annular gap between pipe and aperture was sealed with Hilti Firestop Intumescent sealant CP 611A. When tested, the service E maintained integrity performance of 90 and insulation performance of 90. When tested, the service Q maintained integrity performance of 90 and failed insulation performance at 86 when the maximum temperature measured on the unexposed wall lining exceed the maximum temperature rise limit 180K. B By comparison with the temperature measurements on the unexposed side wall lining of pipes sealed with Fireban One sealant and Hilti Intumescent sealant CP 611A (Service D and E on south wall section, and Service P and Q on north wall section) respectively, it was observed the cavity temperature and temperature measured on the unexposed side wall lining of services with different sealant followed a very similar trend and the unexposed.

23 Page 23 of 25 B B B B B B B B B B B B The significance of above test results demonstrates the substitution of annular gap sealant Fireban One sealant with proposed Hilti Firestop Intumescent sealant CP 611A is unlikely to introduce any weakness to the integrity and insulation performance up to 90. The proposed Ø16mm and Ø16mm and pipe though are not tested protected with Hilti Firestop Intumescent sealant CP 611A, based on the behaviour of pipe with Hilti CP 611A sealant tested, it is reasonable expected the proposed pipes with Hilti CP 611A would at least maintain the similar integrity performance to the ones protected with Fireban One sealant on either side of wall system. The proposed wall systems 5 and 6 are as tested in EWFA , which clad with single layer of 13mm thick fire grade plasterboard on each and double layer of 13mm thick fire grade plasterboard on the other side. In light of the above, it is considered the proposed pipe penetration with Hilti Firestop Intumescent sealant CP 611A shall maintain integrity performance and insulation performance summarised in table 5.1 when installed on either side of wall system 5 and 6 when tested in accordance with AS Performance of Services in Various Steel Stud framed Wall Systems Wall System 1, 2, 3 and 4 The proposed wall system 1 comprises single layer of 13mm thick fire grade plasterboard on each side of steel framing with minimum wall thickness of 130mm thick. When the construction is exposed to heating, the exposure to the seal around the pipe penetration on fire side would be similar to the south part of wall specimen tested in EWFA With reference to the south part of wall specimen tested in EWFA which the wall framing clad with single layer of 13mm thick fire grade plasterboard on the fire side and double layer of 13mm fire grade plasterboard on the non-fire side. Upon inspection of the cavity temperature measurements, it was observed the fire side 13mm fire grade plasterboard started to fall off around 30 and the temperature raise recorded on the unexposed side of non-fire side wall lining did increase dramatically between 30 and 60 due to the presence of wall cavity insulation material. It is therefore expected the insulation performance of pipe penetration is governed by the falloff time of fire side plasterboard lining and the conduction of heat through the wall cavity insulation. Reducing the non-fire side wall lining to be single layer of 13mm thick fire grade plasterboard would tend to increase the unexposed side temperature of non-fire side lining. Hence it is reasonable and conservative expected the unexposed side temperature would increase twice if the non-fire side wall lining is reduced from double layer of 13mm thick to be single layer. With reference to all the penetrations on the south part of wall specimen tested in EWFA , apart from the pipe with brass fitting on the non-fire side wall lining that the failure of insulation performance was occurred on pipe and was due to the unclose pipe penetration. The maximum temperatures measured any other locations were below 100 C at 60. Based on the above, it is considered the proposed penetrations will maintain integrity performance of 60 and insulation performance of 60 if installed on either side of wall system 1. The proposed wall systems 2 and 3 comprises single layer of 13mm thick fire grade plasterboard on one side and one layer of 13mm thick fire grade plasterboard and one layer of 10mm or 13mm non-fire grade plasterboard on the other side. B It is expected the 10mm standard core would remain in place for 5 to 10 and with reference to the discussion for wall system 1, the integrity and insulation performance of proposed penetrations are not considered to be detrimentally affected by including additionally layer of 10mm or 13mm non-fire grade plasterboard on either unexposed side or unexposed side.

24 Page 24 of 25 B B B B B B B B B Based on the discussion presented for wall system 1, it is considered the performance for proposed penetrations on either side of wall system 2 and 3 would be at least the same as the performance for on System 1. The proposed wall system 4 comprises single layer of 16mm thick fire grade plasterboard on each side of wall framing. It is expected the 16mm thick fire grade plasterboard is likely to stay in place on the fire side longer than that tested 13mm thick fire grade plasterboard and hence will not introduce any foreseeable integrity and insulation weakness to the performance of pipe penetrations installed of at least 60. Based on the discussion presented for wall system 1, it is considered the performance for proposed penetrations on either side of wall system 4 would be at least the same as the performance for on System 1. In light of the above, the proposed construction is therefore expected to maintain integrity and insulation performance of 60 when tested in accordance with AS Wall System 7 and 8 The type of lining will determine how much shielding the penetration will receive. The proposed wall systems 7 and 8 comprises double layers of 13mm thick or 16mm fire grade plasterboard on each side of wall framing. With reference to the discussion presented for wall system 4 and 5, it is expected the integrity and insulation performance of proposed penetrations are not considered to be detrimentally affected by including additional layer of 13mm thick fire grade plasterboard nor increasing the wall lining thickness. In light of the above, it is considered the proposed pipe penetration will maintain integrity performance and insulation performance summarised in table 5.1 when installed on either side of wall system 7 and 8 when tested in accordance with AS B.2 PENETRATIONS ON VARIOUS DOUBLE STUD WALL SYSTEMS ONLY B.2.1 B B.2.2 B B Proposal The proposed construction for PEX and PEX-AL pipes in plasterboard lined walls shall be as tested in EWFA , subject to the following variations; The wall systems shall be double studs only and each steel stud depth shall be minimum 90mm. The wall linings are summarised in Table 2. Wall cavity shall be fully insulated with Glasswool insulation with a minimum density of 10.5kg/m3. The minimum wall thickness shall be 164mm. Wall systems shall be exposed to exposure from either direction. Penetration installation refers to Figure 1. Discussion The insulation performance of the penetration is governed by the fall-off time of fire side plasterboard lining and the conduction of heat through the cavity insulation. With reference to test EWFA , it is observed the earliest failure of insulation performance of penetration (Service N) was occurred at 71 and the unexposed side temperature measured on the non-fire side wall lining at 90 was 271 C. B B B The proposed wall system comprises double stud wall framing and hence the wall cavity insulation thickness is double as well. There will be a significantly improved insulation performance due to the increased cavity insulation thickness compares to the tested configuration in EWFA As discussed, the dramatic raise of temperature on the unexposed wall lining was occurred after the fire side lining(s) became parts and fell off, the wall cavity insulation started to catch

25 Page 25 of 25 B B on fire. Upon inspection of the unexposed temperature measurement chart of Service N, it was noted before the wall cavity insulation burned away at 60, the unexposed side temperature recorded on the non-fire wall lining was only 102 C Based on the above observation, it is considered the double the cavity insulation material is likely to delay the dramatic raise of temperature on the unexposed side for another 15 minute margin. Based on the above, it is considered the proposed pipe penetration will maintain integrity performance and insulation performance summarised in table 5.2 when installed on either side of double stud wall systems when tested in accordance with AS

Title: The Fire Resistance Performance of PRT and PRC, Side and Centre-Opening Lift Landing Doorsets. WF Assessment Report No: Prepared for: Klefer SA

Title: The Fire Resistance Performance of PRT and PRC, Side and Centre-Opening Lift Landing Doorsets. WF Assessment Report No: Prepared for: Klefer SA Exova Warringtonfire Holmesfield Road Warrington WA1 2DS United Kingdom T : +44 (0) 1925 655 116 F : +44 (0) 1925 655 419 E : warrington@exova.com W: www.exova.com Title: The Fire Resistance Performance

More information

BRE Global Assessment Report

BRE Global Assessment Report BRE Global Assessment Report An assessment of the fire performance of Suresnap Fire Collars fitted around plastic pipes penetrating concrete floors against the adopted criteria of BS 476: Part 20: 1987

More information

SECTION D Masonry Wall Systems. Contents. Introduction. Design Considerations. Installation. Components. System Specifications.

SECTION D Masonry Wall Systems. Contents. Introduction. Design Considerations. Installation. Components. System Specifications. SECTION D Wall Systems. Contents. SUBJECT Introduction Design Considerations Installation Components PAGE D2 D2 D4 D5 System Specifications Stud One Side Stud Both Sides Stud and Furring Channel Resilient

More information

Title: The Fire Resistance Performance of PRT and PRC, Side and Centre-Opening, Vandal Resistant, Lift Landing Doorsets. WF Assessment Report No:

Title: The Fire Resistance Performance of PRT and PRC, Side and Centre-Opening, Vandal Resistant, Lift Landing Doorsets. WF Assessment Report No: assessment report Title: The Fire Resistance Performance of PRT and PRC, Side and Centre-Opening, Vandal Resistant, Lift Landing Doorsets WF Assessment Report No: 183968A Prepared for: Klefer SA Kilkis

More information

CERTIFICATE OF APPROVAL No CF 816 BIP GMBH

CERTIFICATE OF APPROVAL No CF 816 BIP GMBH CERTIFICATE OF APPROVAL No CF 816 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of St Peter Straβe 25 (Chemiepark

More information

PASSIVE FIRE PROTECTION PRODUCTS

PASSIVE FIRE PROTECTION PRODUCTS OCTOBER 2016 PASSIVE FIRE PROTECTION PRODUCTS www.allproof.com CONTENTS FIRE TESTING 1 ADVANCED INTUMESCENT 2 ALLPROOF INTUMESCENT TECHNOLOGY: 2 LOW PROFILE S 3 CONCRETE SLAB TEST RESULTS: 4 FLOOR WASTE

More information

BS 476: Part 7: Method For Classification Of The Surface Spread Of Flame Of Products. A Report To: Thermaflex International Holding B.V.

BS 476: Part 7: Method For Classification Of The Surface Spread Of Flame Of Products. A Report To: Thermaflex International Holding B.V. Exova Warringtonfire Holmesfield Road Warrington WA1 2DS United Kingdom T : +44 (0 1925 655116 F : +44 (0) 1925 655419 E : warrington@exova.com W: www.exova.com BS 476: Part 7: 1997 Method For Classification

More information

Part E robustdetails. robustdetails. January 2017 Update Pack. Dear Colleague,

Part E robustdetails. robustdetails. January 2017 Update Pack. Dear Colleague, Part E Pack Dear Colleague, This is the first 2017 update to the Part E Robust Details Handbook. In this update pack, we have focussed on clarifying the situation on incorporating underfloor heating (UFH)

More information

CERTIFICATE OF APPROVAL No CF 154 J B KIND LIMITED & IRMADE- INDÚSTRIAS DE REVESTIMENTO DE MADEIRAS, S.A.

CERTIFICATE OF APPROVAL No CF 154 J B KIND LIMITED & IRMADE- INDÚSTRIAS DE REVESTIMENTO DE MADEIRAS, S.A. CERTIFICATE OF APPROVAL No CF 154 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of J B KIND LIMITED & IRMADE-

More information

Tehnical Data Sheet Astro Intu Mastic. UIC of product-type: INTUM CPR-JA5015

Tehnical Data Sheet Astro Intu Mastic. UIC of product-type: INTUM CPR-JA5015 1121 Astroflame Fireseals Ltd Unit 8 The I O Centre 14 1121-CPR-JA5015 ETA-14/0049 ETA-14/0050 ETAG 026-Part 1 ETAG 026-Part 2 ETAG 026-Part 3 MASTIC see ETA-14/0049 & ETA- 14/0050 for relevant characteristics

More information

DD CEN/TS 1187: 2012 Test 4

DD CEN/TS 1187: 2012 Test 4 Exova Warringtonfire Holmesfield Road Warrington WA1 2DS United Kingdom T : +44 (0 1925 655116 F : +44 (0) 1925 655419 E : warrington@exova.com W: www.exova.com DD CEN/TS 1187: 2012 Test 4 Incorporating

More information

FIREPRO FIRESTOP PIPE COLLARS. Firestop solution for plastic pipework penetrations

FIREPRO FIRESTOP PIPE COLLARS. Firestop solution for plastic pipework penetrations FIREPRO FIRESTOP PIPE COLLARS Firestop solution for plastic pipework penetrations FIREPRO FIRESTOP PIPE COLLARS Firestop solution for plastic pipework penetrations. ROCKWOOL Firestop Pipe s provide a simple

More information

Technical Data Sheet. Hilti Firestop cable collar CFS-CC. European technical approval ETA N o 13 / Issue 10 / 2013

Technical Data Sheet. Hilti Firestop cable collar CFS-CC. European technical approval ETA N o 13 / Issue 10 / 2013 Technical Data Sheet Hilti Firestop cable collar CFS-CC Hilti Firestop cable collar CFS-CC European technical approval ETA N o 13 / 0704 Issue 10 / 2013 Hilti Firestop cable collar CFS-CC Issue 10 / 2013

More information

BRE Global Assessment Report

BRE Global Assessment Report BRE Global Assessment Report An assessment of the fire performance of the Gebrik Insulating Brick Cladding System against BR 135, Third Edition Prepared for: Date: 13 April 2016 Aquarian Cladding Systems

More information

Page No 1 Introduction... 3

Page No 1 Introduction... 3 Contents Page No 1 Introduction... 3 2 Details of classified element... 3 2.1 Type of function... 3 2.2 Description... 3 3 Test reports and test results in support of classification... 3 3.1 Summary of

More information

Thermal Performance of Plasterboard Lined Steel Stud Walls

Thermal Performance of Plasterboard Lined Steel Stud Walls Missouri University of Science and Technology Scholars' Mine International Specialty Conference on Cold- Formed Steel Structures (28) - 19th International Specialty Conference on Cold-Formed Steel Structures

More information

This classification report consists of five pages and may only be used or reproduced in its entirety.

This classification report consists of five pages and may only be used or reproduced in its entirety. Title: Classification of Fire Resistance Performance In Accordance With EN 0-2: 200 Notified Body No: 08 Product Name: Pyrobelite 2 Report No: WF 9 Issue No: Prepared for: Glaverbel S. A. BU Industrial

More information

USGBORAL.COM SYSTEMS+ INTRODUCTION OUTRWALL BRICK VENEER WALLS EXTERNAL WALLS INNOVATIVE SYSTEMS SOLUTIONS

USGBORAL.COM SYSTEMS+ INTRODUCTION OUTRWALL BRICK VENEER WALLS EXTERNAL WALLS INNOVATIVE SYSTEMS SOLUTIONS USGBORAL.COM S+ E 2 E 5 E 9 E 10 INTRODUCTION OUTRWALL WALLS FIRECLAD E EXTERNAL WALLS INNOVATIVE S SOLUTIONS E EXTERNAL WALLS INTRODUCTION The following USG Boral external wall systems are outlined in

More information

HILTI CP 674 Cavity Closure For Rainscreen / Cladding Systems

HILTI CP 674 Cavity Closure For Rainscreen / Cladding Systems Data Sheet HILTI CP 674 Cavity Closure For Rainscreen / Cladding Systems The enclosed pages are taken from the Hilti Firestop Systems Manual Edition April 2011 Supported by additional standard details

More information

SPECIFICATION DIVISION 7 NUMBER SECTION DESCRIPTION DIVISION 07 THERMAL AND MOISTURE PROTECTION SECTION THROUGH-PENETRATION FIRESTOP SYSTEMS

SPECIFICATION DIVISION 7 NUMBER SECTION DESCRIPTION DIVISION 07 THERMAL AND MOISTURE PROTECTION SECTION THROUGH-PENETRATION FIRESTOP SYSTEMS BuildingName The Description of the Project P00000000 0000 DOCUMENTS Title Page Table of Contents Instruction to Bidders Form of Proposal Equal Opportunity Statement Form of Guarantee Supplemental General

More information

Crimp-ON Pex Plumbing System

Crimp-ON Pex Plumbing System WATER & GAS DR BRASS stainless steel sleeve witness opening double o Ring Crimp-ON Pex Plumbing System August 2011 09 Oschin Bush O-Ring Crimp DL brochure.indd 1 2/08/11 4:56 PM ELSON proudly presents

More information

FIRE PROTECTION. GTEC Shaftwall systems 244 GTEC Shaftwall Stairwell systems 248 GTEC Horizontal Shaftwall systems 249 GTEC Encasement systems 250

FIRE PROTECTION. GTEC Shaftwall systems 244 GTEC Shaftwall Stairwell systems 248 GTEC Horizontal Shaftwall systems 249 GTEC Encasement systems 250 FIRE PROTECTION GTEC Shaftwall range uses a specially designed system to protect voids and shafts in buildings. It resists pressure changes and enables installation from one side of the shaft only. GTEC

More information

QUALITY CONTROL TESTING OF PLASTERBOARD FOR BRACING APPLICATIONS. Y L Liew Vicroads Victoria, Australia

QUALITY CONTROL TESTING OF PLASTERBOARD FOR BRACING APPLICATIONS. Y L Liew Vicroads Victoria, Australia Int. Journal for Housing Science, Vol.32, No.1 pp. 51-60, 2008 Published in the United States QUALITY CONTROL TESTING OF PLASTERBOARD FOR BRACING APPLICATIONS Y L Liew Vicroads Victoria, Australia E F

More information

BRE Global Ltd Watford, Herts WD25 9XX. d+b facades (UK) Ltd. The Packway, Larkhill, Salisbury, SP4 8PY. Customer Services

BRE Global Ltd Watford, Herts WD25 9XX. d+b facades (UK) Ltd. The Packway, Larkhill, Salisbury, SP4 8PY. Customer Services BRE Global Test Report BS 8414-1:2015 + A1:2017 test on d+b facades rain screen cladding system with 100mm-thick Rockwool insulation and aluminium cassette panels. Prepared for: d+b facades (UK) Ltd. Date:

More information

FIRESTOP SUBMITTAL PACKAGE

FIRESTOP SUBMITTAL PACKAGE FIRESTOP SUBMITTAL PACKAGE PLUMBING Materials FS-ONE Intumesent Caulk Includes: Technical and Installation Data UL Certificate of Compliance LEED information MSDS UL Details Gypsum Wall Assemblies W-L-1054

More information

CERTIFICATE OF APPROVAL No CF 5497 AL HUDA INTERIORS FACTORY LLC

CERTIFICATE OF APPROVAL No CF 5497 AL HUDA INTERIORS FACTORY LLC CERTIFICATE OF APPROVAL No CF 5497 1 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of Abu Dhabi Musaffah

More information

AS/NZS 2280:2012 AS/NZS

AS/NZS 2280:2012 AS/NZS AS/NZS 2280:2014 Incorporating Amendment No. 1 and 2 Australian/New Zealand Standard Ductile iron pipes and fittings Superseding AS/NZS 2280:2012 AS/NZS 2280:2014 AS/NZS 2280:2014 This joint Australian/New

More information

This European technical approval

This European technical approval Authorised and notified according to Article 10 of the Council Directive 89/ 106/EEC of 21 December 1988 on the approximation of laws, regulations and administrative provisions of Member States relating

More information

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION BASIC ELECTRICAL MATERIALS AND METHODS SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:

More information

Rondo steel stud. Framing Systems Installation Manual. revised: october 2008

Rondo steel stud. Framing Systems Installation Manual. revised: october 2008 Rondo steel stud Framing Systems Installation Manual revised: october 2008 design considerations general information The Rondo Steel Stud and Track sections detailed in this installation manual will provide

More information

TECHNICAL GUIDANCE XXXX 2015 EXXON QUESTION ANSWER. page 1 of 9

TECHNICAL GUIDANCE XXXX 2015 EXXON QUESTION ANSWER. page 1 of 9 MARKINGWALLING OF SAFETY GLASS SPANDREL CURTAIN PANELS FORMED TO COLDFROM ROOFS STACKED WINDOW 7.2 /25 January ARRANGEMENTS (First Issue) XXXX EXXON QUESTION Which factors should be taken into account

More information

Internal Applications

Internal Applications Internal Applications Technical Manual ANY BUILDING ANY SURFACE ANYWHERE INEX BOARDS 2 INEX BOARDS Decking Internal Applications Technical Manual Contents INEX>WALLBOARD Product Information 6 INEX>PARTYWALL

More information

SECTION Domestic Water Piping. A. American National Standards Institute (ANSI)/American Water Works Association (AWWA)

SECTION Domestic Water Piping. A. American National Standards Institute (ANSI)/American Water Works Association (AWWA) SECTION 22 11 16 Domestic Water Piping PART 1 GENERAL 1.1 SECTION INCLUDES A. PEX a tubing and fittings for domestic water piping. 1.2 REFERENCES A. American National Standards Institute (ANSI)/American

More information

Rondo panther Acoustic and Fire-Tested Wall & Ceiling Access Panels. revised: october 2008

Rondo panther Acoustic and Fire-Tested Wall & Ceiling Access Panels. revised: october 2008 Rondo panther Acoustic and Fire-Tested Wall & Ceiling Access Panels revised: october 2008 design considerations introduction The Rondo Panther range of Acoustic and Fire rated Access Panel Systems have

More information

Section Domestic Water Piping (Hot and Cold Water Potable Water Distribution)

Section Domestic Water Piping (Hot and Cold Water Potable Water Distribution) Domestic Water Piping 22 11 16 Uponor, Inc. 5925 148th Street West Apple Valley, MN 55124 Toll Free: (800) 321-4739 Phone: (952) 891-2000 Fax: (952) 891-2008 www.uponor-usa.com This specification is a

More information

BRE Global Assessment Report

BRE Global Assessment Report RE Global Assessment Report An assessment of the fire performance of the IDE servery rolling shutter doorset, for opening sizes Prepared for: Date: 07 July 2014 Industrial Door Engineering Limited RE Global

More information

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS SECTION 270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Communications equipment coordination and installation. 2. Sleeves for pathways and cables. 3. Raceway

More information

HILTI CP 606 Flexible Firestop Sealant

HILTI CP 606 Flexible Firestop Sealant Data Sheet HILTI CP 606 Flexible Firestop Sealant The enclosed pages are taken from the Hilti Firestop Systems Manual Edition April 2011 Supported by additional standard details For Material Safety data

More information

Building Design Data

Building Design Data Building Design Data.. 1. Building Design The KORE ICF System is designed to meet the requirements of the Building Regulations 1997-2006, in the case of two storeys, single occupancy dwellings. If the

More information

CERTIFICATE OF APPROVAL No CF 820 ZMR LTD TRADING AS MILLENNIUM DOOR SYSTEMS

CERTIFICATE OF APPROVAL No CF 820 ZMR LTD TRADING AS MILLENNIUM DOOR SYSTEMS CERTIFICATE OF APPROVAL No CF 820 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of ZMR LTD TRADING AS MILLENNIUM

More information

Kent, DA1 4FT. appended hereto:

Kent, DA1 4FT. appended hereto: CERTIFICATE OF APPROVALL No CF 583 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection s The undermentioned products of FIRETHERM INTUM MESCENT &

More information

FIRESTOP SUBMITTAL PACKAGE

FIRESTOP SUBMITTAL PACKAGE FIRESTOP SUBMITTAL PACKAGE HVAC Materials FS-ONE Intumesent Caulk CP 606 Acrylic Includes: Technical and Installation Data UL Certificate of Compliance LEED information MSDS UL Details Concrete Assemblies

More information

ASSEMBLY INSTRUCTION.

ASSEMBLY INSTRUCTION. INSTALLATION OF BUILT-IN BOX brickwork plastering sealing tape built-in box with flange height adjustment sealing tile adhesive tiles LED technology cover silicon joints aluminium profiles The built-in

More information

Xtratherm Thin-R Thermal Liner (XT/TL Grade)

Xtratherm Thin-R Thermal Liner (XT/TL Grade) CERTIFICATE NO. 03/0183 DETAIL SHEET 4 Xtratherm Thin-R Thermal Liner (XT/TL Grade) PRODUCT DESCRIPTION: This Detail Sheet relates to Xtratherm Thin-R Thermal Liner, as defined in NSAI Agrément Certificate

More information

HILTI CP 617 Intumescent acoustic putty pad

HILTI CP 617 Intumescent acoustic putty pad Data Sheet HILTI CP 617 Intumescent acoustic putty pad The enclosed pages are taken from the Hilti Firestop Systems Manual Edition April 2011 Supported by additional standard details For Material Safety

More information

Site check The timber frame pocket guide

Site check The timber frame pocket guide PREVIEW PAGES Site check The timber frame pocket guide Sample pages 2 Frame erection ISBN 978-1-909594-65-4 First published in 2018 This is a technical publication for professionals in the built environment

More information

EXCEL Medical Waste - Equipment Installation Section SECTION GYPSUM BOARD

EXCEL Medical Waste - Equipment Installation Section SECTION GYPSUM BOARD SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board. 1.2 RELATED WORK A. Installation of steel framing members for walls, partitions,

More information

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018 Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018 TK Products A Division of Sierra Corporation TK-HYDROMAX 2001 SB DAMPPROOF COATING, TK-HYDROMAX 2002 SB FOUNDATION WATERPROOF

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

3M Fire Protection Products. Confidence. Even Under Fire. Principal Products Ltd I Ph: I

3M Fire Protection Products. Confidence. Even Under Fire. Principal Products Ltd I Ph: I 3M Fire Protection Products Confidence Even Under Fire 1 Principal Products Ltd I Ph: +64 9 483 4000 I www.3mfire.co.nz Protecting Lives for More Than 30 Years In 1974, the movie Towering Inferno sparked

More information

P.O. Box ZN Bleiswijk Brandpuntlaan Zuid NZ Bleiswijk The Netherlands

P.O. Box ZN Bleiswijk Brandpuntlaan Zuid NZ Bleiswijk The Netherlands P.O. Box 554 2665 ZN Bleiswijk Brandpuntlaan Zuid 16 2665 NZ Bleiswijk The Netherlands +31 88 3473 723 nederland@efectis.com Determination of the fire resistance according to EN 1364-1:1999 and FprEN 1364-1:2014

More information

REPORT HOLDER: THE DOW CHEMICAL COMPANY 1501 LARKIN CENTER DRIVE MIDLAND, MICHIGAN EVALUATION SUBJECT:

REPORT HOLDER: THE DOW CHEMICAL COMPANY 1501 LARKIN CENTER DRIVE MIDLAND, MICHIGAN EVALUATION SUBJECT: 0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3089 Reissued 07/2016 This report is subject to renewal 07/2018. DIVISION: 07 00

More information

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE.

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE. The Steel Strong-Wall is a corrugated steel panel which is designed to be fixed directly to the concrete foundations of a building, within the external or internal wall, via a bolted connection. FEATURES

More information

SECTION THROUGH-PENETRATION FIRE STOP SYSTEMS

SECTION THROUGH-PENETRATION FIRE STOP SYSTEMS SECTION 07841 THROUGH-PENETRATION FIRE STOP SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. Section includes firestopping and through-penetration system materials and accessories; firestopping tops of

More information

U L - E U C E R T I F I C A T E

U L - E U C E R T I F I C A T E U L - U C R T I F I C A T Page 1/8 Date of Issue 15-07-02 Certificate Holder Manufacturer Certified Product Type Product Trade Name Trademark Rating/Classification ASTROFLAM FIRSALS LIMITD UNIT 8 TH IO

More information

CERTIFICATE OF APPROVAL No CF 663 HILTI AG

CERTIFICATE OF APPROVAL No CF 663 HILTI AG CERTIFICATE OF APPROVAL No CF 663 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of BU Chemicals, Feldkircherstrasse

More information

BS EN ISO : 1999

BS EN ISO : 1999 Exova Warringtonfire Holmesfield Road Warrington WA1 2DS United Kingdom T : +44 (0 1925 655116 F : +44 (0) 1925 655419 E : warrington@exova.com W: www.exova.com BS EN ISO 4589-2: 1999 Determination of

More information

Jean Vaillancourt Fire Protection Specialist Hilti (Canada) Corp.

Jean Vaillancourt Fire Protection Specialist Hilti (Canada) Corp. Cable Management Firestop Jean Vaillancourt Fire Protection Specialist Hilti (Canada) Corp. FIRESTOPPING KNOWLEDGE FOR BETTER SPECIFICATION AND DESIGN OF FIRE-RATED CONSTRUCTION Presentation Topics and

More information

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: COMPOSITE WALL PANELS REPORT HOLDER: PARKLEX USA

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: COMPOSITE WALL PANELS REPORT HOLDER: PARKLEX USA 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3462 Reissued 09/2017 This report is subject to renewal 09/2018. DIVISION: 07 00

More information

Annex C Cavity Closures

Annex C Cavity Closures Annex C Cavity Closures Introduction The objective of this study was to investigate the effectiveness of different types of window frame constructions at mitigating the entry of fire into a timber frame

More information

NATIONAL GYPSUM COMPANY Wood Frame Walls And Ceilings Single- And Double-Layer Construction

NATIONAL GYPSUM COMPANY Wood Frame Walls And Ceilings Single- And Double-Layer Construction Walls And Ceilings Single- And Double-Layer Construction 09 9 00/NGC Single-Layer Construction The single-layer construction system consists of a single layer of Gold Bond brand Gypsum Board applied to

More information

HILTI CP 657 Firestop Brick

HILTI CP 657 Firestop Brick Data Sheet HILTI CP 657 Firestop Brick The enclosed pages are taken from the Hilti Firestop Systems Manual Edition April 2011 Supported by additional standard details For Material Safety data sheets visit

More information

BRE Global Test Report

BRE Global Test Report BRE Global Test Report Classification of fire performance in accordance with BR 135: 2013 Annex B. Prepared for: Date: 02 July 2014 Report Number: 287129 Iso Systems and Aquarian Cladding Systems BRE Global

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1208: Issue 2.2 This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for information purposes only. Its use for testing, assessment,

More information

Australian Standard. Pipelines Gas and liquid petroleum. Part 0: General requirements AS AS

Australian Standard. Pipelines Gas and liquid petroleum. Part 0: General requirements AS AS AS 2885.0 2008 AS 2885.0 2008 Australian Standard Pipelines Gas and liquid petroleum Part 0: General requirements This Australian Standard was prepared by Committee ME-038, Petroleum Pipelines. It was

More information

A better way to build a better home. Permanent Insulated Concrete Formwork

A better way to build a better home. Permanent Insulated Concrete Formwork POLYWALL by Polyfoam A better way to build a better home Permanent Insulated Concrete Formwork VICTORIA TASMANIA QUEENSLAND NEW SOUTH WALES 32 Dandenong Street 113 Cove Hill Road 43 Proprietary Street

More information

Structural vs Nonstructural Members. Roger LaBoube, Ph.D., P.E. Wei-Wen Yu Center for Cold-Formed Steel Structures

Structural vs Nonstructural Members. Roger LaBoube, Ph.D., P.E. Wei-Wen Yu Center for Cold-Formed Steel Structures Structural vs Nonstructural Members Roger LaBoube, Ph.D., P.E. Wei-Wen Yu Center for Cold-Formed Steel Structures Behavior of Cold-Formed Steel Members STEEL DESIGN SPECIFICATIONS Type of steel Specification

More information

BRE Global Test Report

BRE Global Test Report BRE Global Test Report BS 476: Part 3: 2004 + A1: 2006 + A2: 2007 External fire exposure to roofs test on SolFit Top Loader. Prepared for: SolFiT Ltd Date: 19 November 2016 Report Number: P105772-1000

More information

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: MINERAL FIBER FIREPROOFING REPORT HOLDER: UNIFRAX I LLC

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: MINERAL FIBER FIREPROOFING REPORT HOLDER: UNIFRAX I LLC 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2224 Reissued 08/2017 This report is subject to renewal 08/2018. DIVISION: 07 00

More information

Johns Manville MinWool Water & Fire Block Mineral Wool Insulation

Johns Manville MinWool Water & Fire Block Mineral Wool Insulation Johns Manville MinWool Water & Fire Block Mineral Wool Insulation Johns Manville s MinWool Water & Fire Block mineral wool insulation provides a vapor-permeable continuous layer of insulation. Along with

More information

SSS009: Substrate Specification Sheet 9 - Render Board

SSS009: Substrate Specification Sheet 9 - Render Board SSS009: Substrate Specification Sheet 9 - Render Board Page 1 of 8 Document: 9993.48 Collection: 116: Substrate Specification Sheets (SSS) Modified: 08/12/2017 11:34 Created: 20/06/2016 12:09 Armourcoat

More information

SOUND INSULATION TESTING IN DWELLINGS

SOUND INSULATION TESTING IN DWELLINGS SOUND INSULATION TESTING IN DWELLINGS Chris Dilworth, AWN Consulting This Presentation Discusses the standards by which we judge sound insulation performance. Presents the results of sound insulation tests

More information

ROOFING APPLICATION STANDARD (TAS) No. 102(A)-95

ROOFING APPLICATION STANDARD (TAS) No. 102(A)-95 ROOFING APPLICATION STANDARD (TAS) No. 102(A)-95 TEST PROCEDURE FOR STATIC UPLIFT RESISTANCE OF MECHANICALLY ATTACHED, CLIPPED, RIGID, ROOF SYSTEMS (For Methods of Mechanical Attachment Excluding Clips,

More information

Fire Door Installation

Fire Door Installation FA LCON PANEL PRODUCTS LTD 14.1 It is vital that performance doorset are installed by competent tradesmen and It is strongly recommended that the installer is a member of a recognised quality assurance

More information

EVALUATION SUBJECT: WATTS RADIANTPEX, WATTS RADIANTPEX+, WATTS HEATINGPEX, AND RADIANTFLOW

EVALUATION SUBJECT: WATTS RADIANTPEX, WATTS RADIANTPEX+, WATTS HEATINGPEX, AND RADIANTFLOW ICC-ES Report PMG-1008 Reissued 12/2017 This report is subject to renewal 12/2018 EVALUATION SUBJECT: WATTS RADIANTPEX, WATTS RADIANTPEX+, WATTS HEATINGPEX, AND RADIANTFLOW DIVISION: 23 00 00 HEATING,

More information

EVALUATION OF DIZAL INC

EVALUATION OF DIZAL INC EVALUATION OF DIZAL INC., PRINTED ALUMINUM SIDING SYSTEM IDENTIFIED AS DIGITALLY PRINTED ALUMINUM SIDING / 6 FOR IMPACT RESISTANCE IN ACCORDANCE WITH ISO 7895 Report to: DiZal Inc. 1020 Bouvier, Suite

More information

The Passive Fire Protection Handbook. Chapter 3: Structural Steel

The Passive Fire Protection Handbook. Chapter 3: Structural Steel Chapter 3: Structural Steel 43 Chapter 3: Structural Steel - Introduction The amount of fire protection required to achieve this depends on the following: Duration of fire resistance specified Type of

More information

HILTI CP 643N Firestop collar

HILTI CP 643N Firestop collar Data Sheet HILTI CP 643N Firestop collar The enclosed pages are taken from the Hilti Firestop Systems Manual Edition April 2011 Supported by additional standard details For Material Safety data sheets

More information

Australian Standard. Design and installation of sheet roof and wall cladding. Part 3: Plastic AS AS

Australian Standard. Design and installation of sheet roof and wall cladding. Part 3: Plastic AS AS AS 1562.3 2006 AS 1562.3 2006 Australian Standard Design and installation of sheet roof and wall cladding Part 3: Plastic This Australian Standard was prepared by Committee PL-022, Plastic Building Sheets.

More information

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: THERMAL INSULATION REPORT HOLDER: DEMILEC (USA) INC.

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: THERMAL INSULATION REPORT HOLDER: DEMILEC (USA) INC. 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 4073 Issued 08/2017 This report is subject to renewal 08/2018. DIVISION: 07 00 00

More information

PinkWood Ltd. Revised September 29, 2017

PinkWood Ltd. Revised September 29, 2017 Fire-Rated Assemblies PR-S315 PinkWood Ltd. Revised September 29, 2017 Products: Series I-Joists PinkWood Ltd., 5929 6 th St. NE, Calgary, Alberta, Canada T2K 5R5 (403) 279-3700 www.pinkwood.ca 1. Basis

More information

Roof Replacement. Notes: T-1 (Title Sheet) Roof Key Plan Russell House Student Union 1400 Greene Street Columbia, South Carolina 29208

Roof Replacement. Notes: T-1 (Title Sheet) Roof Key Plan Russell House Student Union 1400 Greene Street Columbia, South Carolina 29208 Notes: Drawing Index T-1 Title R-1 Roof Plan - Existing Conditions R-2 Roof Plan - New D-1 Roof Details D-2 Roof Details D-3 Roof Details M-1 Mechanical - Roof Plan M-2 Mechanical - Details Roof Key Plan

More information

HALFEN HLB LOOP BOX Z-HLB-M50 13-E CONCRETE

HALFEN HLB LOOP BOX Z-HLB-M50 13-E CONCRETE HALFEN HLB LOOP BOX Z-HLB-M50 13-E CONCRETE Translation of the General Certificate of Approval Approval Office: German Institute for Construction Engineering (Deutsches Institut für Bautechnik DIBt) Kolonnenstrasse

More information

GIB Quiet Clip GIB CBI March Features and Benefits

GIB Quiet Clip GIB CBI March Features and Benefits CBI - 5113 March 2002 GIB Quiet Clip Features and Benefits No special flooring systems required Easy fit Installation Significantly improves low frequency sound transmission Significantly improves low

More information

duo installation guide DUO Exposed Grid Ceiling System

duo installation guide DUO Exposed Grid Ceiling System duo installation guide DUO Exposed Grid Ceiling System rondo duo EXPOSED GRID CEILING SYSTEM GENERAL INFORMATION This brochure provides details of the Rondo DUO Exposed Grid Ceiling System, which allows

More information

Originally Issued: 05/20/2013 Revised: 07/07/2017 Valid Through: 05/31/ Design

Originally Issued: 05/20/2013 Revised: 07/07/2017 Valid Through: 05/31/ Design BRADY INNOVATIONS, LLC. PROX HEADER SYSTEM CSI Section: 05 05 23 Metal Fastenings 05 40 00 Cold-formed Metal Framing 1.0 RECOGNITION Brady Innovations, LLC s ProX Header System recognized in this report

More information

OutRWALL. Exterior Wall Systems for Residential Construction. 314DC Issue 1

OutRWALL. Exterior Wall Systems for Residential Construction. 314DC Issue 1 OutRWALL Exterior Wall Systems for Residential Construction 314DC Issue 1 2 Introduction Contents Introduction... 2 Benefits... 2 Description... 2 Applications... 2 Design and Specifications Design Notes...

More information

GOWANDA, NEW YORK SEPTEMBER 18, 2008 ARCH PROJECT NO

GOWANDA, NEW YORK SEPTEMBER 18, 2008 ARCH PROJECT NO SECTION 07210 BUILDING INSULATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

June Non - Residential Refurbishment Internal lining walls

June Non - Residential Refurbishment Internal lining walls June 2010 Non - Residential Refurbishment 5.3.4 Internal lining walls Non-residential refurbishment 5.0 Non-residential Refurbishment Internal Lining Walls Contents Introduction find online page Solution

More information

PMG-1039 Effective Date: April 1, 2014 This listing is subject to re-examination in one year.

PMG-1039 Effective Date: April 1, 2014 This listing is subject to re-examination in one year. ICC-ES PMG Listing PMG-1039 Effective Date: April 1, 2014 This listing is subject to re-examination in one year. www.icc-es-pmg.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code

More information

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows: SECTION 16130 (Master Template Final-05) ELECTRICAL BOXES PART 1 GENERAL 1.01 SECTION INCLUDES A. Provide boxes for electrical equipment and wiring devices as follows: 1. Wall and ceiling outlet boxes.

More information

Suspension System Data Center Ceiling Solutions

Suspension System Data Center Ceiling Solutions Hardware That Needs to be Purchased Separately Screws are fine listed as shown: Min 1-1/4" or longer #8 Truss head self-tapping screws for attaching structural wall angle, lateral support bar 16" or 4"

More information

Australian Standard. Cement mortar lining of steel pipes and fittings AS AS 1281

Australian Standard. Cement mortar lining of steel pipes and fittings AS AS 1281 AS 1281 2001 AS 1281 Australian Standard Cement mortar lining of steel pipes and fittings This Australian Standard was prepared by Committee WS-009, Rolled and Welded Steel Pipes. It was approved on behalf

More information

Managing the geotechnical aspects of longwall face recovery

Managing the geotechnical aspects of longwall face recovery University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2010 Managing the geotechnical aspects of longwall face recovery David Hill Strata Engineering

More information

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued January 1, Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued January 1, Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued January 1, 2000 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900 Montclair

More information

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF WELDED SYSTEM PART 1 GENERAL 1.1 SECTION

More information

Evaluation Report. for. Empire West, Inc Graton Road Post Office Box 511 Graton, California 95444

Evaluation Report. for. Empire West, Inc Graton Road Post Office Box 511 Graton, California 95444 for Empire West, Inc. 9270 Graton Road Post Office Box 511 Graton, California 95444 CertMark International Pty Ltd (CMI) has awarded this Certification to the company named above for the Product/system

More information

GypLyner UNIVERSAL Metal framed wall lining system

GypLyner UNIVERSAL Metal framed wall lining system Metal framed wall lining system Pizza Express, York 30 Metal framed wall lining system wall lining system is a cost-effective, virtually independent metal frame drylining. It is a general purpose system

More information