1 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4. STORMWATER DRAINAGE MINIMUM REQUIREMENTS 4.A General 4.A.1 Most developments will modify the predevelopment drainage pattern and a stormwater drainage system is typically designed and constructed to adequately manage this situation. The primary goals of a stormwater system are to minimize nuisance flooding and flows and to minimize affects on the pre-development. 4.A.2 Affects on the pre-development environment are becoming more important as time goes on. Various methods are available to limit such affects. Auckland Regional Council publication TP124 Low Impact Design Manual is a useful document that gives consideration to the relevant issues and offers various techniques an solutions. Designers are encouraged to use this document where appropriate to minimize affects on the environment. 4.A.3 The stormwater drainage system shall be capable of serving the entire natural catchment to provide adequate protection against flooding. C.1 TP124 is a document for the Auckland Region. While this limits its strict applicability in the Bay of Plenty the majority of the document is relevant to the issues in this Region. C.2 The economic life of any piped system shall not be less than 50 years. C3 Designer shall describe the affect of the proposed development on the upstream, downstream and neighbouring properties. The potential of the entire natural catchment is defined as the full development of the area as zoned under the current District Plan at time of consent. 4.A.4 The consent holder shall design and construct a stormwater drainage system that will provide an adequate gravity method of disposing of the flow from each allotment or intended building site, including all hardstand areas. Note that in the case of 4.C.1(d) and (e) the system need not be constructed but it must be demonstrated that it can be successfully constructed. 4.A.5 Where a stormwater drainage system has been or is to be installed by the Council to serve the natural catchment, contributions on an area basis shall be made in terms of the development impact fees or other agreed cost sharing arrangement. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-1

2 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage MEANS OF COMPLIANCE 4.B Design Standard 4.B.1 Unless otherwise required, the design of the stormwater system shall be in accordance with the IPENZ Procedure for Hydrological Design of Urban Stormwater Systems, December B.2 The design storm, Annual Exceedance Probability (AEP) return period shall be as follows: Overall system (primary and secondary) in all urban areas 50 year storm (2% AEP). Primary piped system in all urban areas minimum 10 year storm (10% AEP). Bridge structures 100 year storm (1% AEP). 4.B.3 Secondary Flows C4 Stormwater calculations shall demonstrate the performance of the overall system and the primary piped system. C4a Temporal rainfall distributions for applications such as computer modelling are available upon application from the Stormwater Asset Manager Flows generated by events that exceed the capacity of the primary system shall be conveyed by a secondary system. The secondary system will typically consist of ground shaping to manage surface flows along flowpaths. Such secondary flowpaths are typically protected by easement. Piped secondary systems are discouraged due to the risk of blockage. Piped secondary systems may be permitted if a totally separate and adequate entry system is provided. 4.B.4 Freeboard Freeboard above design stormwater levels shall be provided as shown. C5 Floor levels may be imposed by Consent Notice to achieve minimum freeboards Type of building Non habitable residential buildings, garage floors. Commercial and Industrial. Dwellings (habitable floors) Major Facilities 50 yr Return Period 200mm 300 mm 500mm 500mm C6 Inundation information is used to update GIS records identifying land within the City that is prone to inundation or potentially prone to inundation. 4.B.5 Drawing D1 details rainfall intensities to be used for the drainage element being designed. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-2

3 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.B.6 Designer must identify areas that will be prone to inundation. This includes ponding areas and secondary flow paths. 4.B.7 The piped system shall be designed to cater for the design flow, without surcharge, based on a Colebrook - White pipe roughness co-efficient Ks=1.50 for pipes up to and including 450 mm diameter and Ks=0.60 for larger concrete pipes. K values for other materials are to be approved by the Director of City Services. 4.B.8 The secondary stormwater system shall safely convey stormwater without undue nuisance. Acceptable solutions include: Temporary ponding on local and collector roads Temporary flow along local and collector roads. Flow across private property. Flow must be in a defined channel or swale, clear of existing or future building sites and protected by an easement in favour of Council and/or Consent Notice which prohibits ground reshaping and the erection of any barriers. 4.B.9 Where the design full pipe velocity is less than 1.3m/s, then measures shall be taken to allow for silt collection. This shall typically take the form of unbenched manhole sumps below lowest invert level. The extra depth required is half the line diameter or as otherwise approved. 4.C Primary System C7 Diameters quoted refer to nominal internal diameters in millimetres C8 Temporary means of the same order as the critical storm s time of concentration C9 Removal of silt from flat lines costs a significant amount. Removal from sumps reduces costs dramatically. It is acknowledged that this velocity is greater than that in NZS4404 but this is because full pipe velocities are only achieved in a 20% AEP event. 4.C.1 Stormwater Connection Destination The following destinations are possible for stormwater collected on a lot. Any destinations must be approved by Council: (a) A piped system: The first choice in most situations. (b) An open drain: Generally permitted, but only where there is an existing open public drain within or beside the lot and a piped system is not available, or desirable, subject to Regional Council general authorisation and in accordance with all other requirements. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-3

4 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage (c) A road sump: Not encouraged. Prior approval from the Director of City Services required. (d) A public roadside channel: Not encouraged except where the lot is remote from a piped drainage system and Council does not consider that a piped system is likely or desirable [refer Drawing D2 (a)] (e) Soakage: Generally not permitted in any area except Papamoa & Mt Maunganui. In these areas generally permitted if soil and groundwater characteristics are favourable and no adverse effects are caused. Design, construction and maintenance to be in accordance with Guidelines for use of soakage in Tauranga District. 4.C.2 The primary piped stormwater reticulation system shall consist of 200mm diameter and larger pipelines laid to a true grade and line between access manholes located at each change of direction and grade. Manholes are also required at the upper end of all primary, piped stormwater reticulation. Manhole spacings shall not exceed 100m for pipe lines up to 1000mm diameter, above which spacings may extend to 200m. Each branch line shall join the main line at a manhole junction, except: - 225mm diameter sump leads may be saddled into 600mm diameter pipes or larger, using a factory made fitting. - Branch lines 300mm diameter or smaller may be saddled onto pipes 1200mm diameter or larger provided a manhole is supplied on the branch line within 50 m of the main line, using a factory made fitting. 4.C.3 Secondary flowpaths shall generally be along the road network. Where such flowpaths are required to cross private property an appropriate easement in favour of Council shall be provided to ensure its protection. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-4

5 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.C.4 Subdivision 4 lots or more Minimum pipe sizes are 150mm diameter for reticulation and 100mm diameter for laterals. In addition, the following shall apply: (a) Lateral with single connection (out of manhole). 100mm diameter up to 50m. Above 50m normal reticulation standards apply, (ie 150mm minimum diameter pipeline with terminating manhole). 150mm diameter pipes must be used under all streets. C10 Clause 4.C.4 relates to the provision of connection for house lots to be public system. It is not intended to be used for general infill reticulation. However, there will be occasions when infill subdivision may need to adhere to those requirements. (b) (c) Lateral with two or three connections (out of manhole). 150mm diameter lengths up to 50m. Above 50m normal reticulation standards apply. Lateral out of line servicing one allotment. 100mm diameter up to 24m. 150mm diameter pipes must be used under all streets. 4.C.5 Infill Subdivision 3 lots and less (includes existing Lot) Reticulation of infill subdivisions shall comply with the following criteria: Drainage within the parent lot is to remain private and be protected by an appropriate easement. Drainage lines are to be separated at the point of connections to the Council s reticulation system and remain separate for each lot unless specific approval is gained from the Group Manager of Environmental Services. Infill subdivisions are to be reticulated on a site by site basis to the approval of the Group Manager of Environmental Services. All private drainage works to be constructed in accordance with Building Code regulations. All private drainage works to be constructed by a Registered Drainlayer. Should the consent holder upgrade and construct the drainage reticulation in accordance with the Code of Practise requirements for servicing (other than 4.C.5) then the drains will be declared public. C11 It is recognised that infill subdivisions require flexibility in their reticulation layout. However, normal trade practises and standards still apply to ensure that the desired service life is still achieved. Common private drains are not encouraged so as to alleviate the friction that sometimes occurs between neighbours when shared services are involved. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-5

6 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.C.6 Where practicable and where connection is to be within 6m of the manhole the connection shall be to the manhole. 4.C.7 Where the main line is within 5m of the property boundary a separate connection shall be provided to each allotment. 4.D Service Connections 4.D.1 To provide a service connection to each allotment, a minimum 100mm diameter line shall be extended from the main reticulation system to terminate at a minimum distance of 1.0m within each site, whether created by cross lease, unit title or fee simple subdivision. In all cases service connections shall serve as much of the site as practically possible, but at least the possible building site. Above diameter and 225mm diameter connection can connect to 600mm diameter line or greater. 300mm diameter connection can connect to 1200mm line or greater. 4.D.2 Service connections shall be brought to within 1.2m of the final ground surface and be constructed in accordance with Drawing D2 or D3 (for pipe depths greater than 2.5m). 4.D.3 All service connections to the site boundary shall form part of the public system. 4.D.4 Each Connection shall be marked by a 50mm x 50mm ground treated timber stake with the top painted blue extending from below invert level to 300mm above ground level. The location shall be shown on the As built plan. The As built plans shall also show the distance of the Y junction from the nearest downstream manhole. 4.D.5 All connections to existing main stormwater shall be made by an approved contractor with the consent of the Group Manager of City Services at the consent holder s expense. 4.D.6 The following size connections can be connected directly to the line. Any combinations outside this list connect via a manhole. 100mm diameter connection can connect to 100mm diameter line or greater. Above diameter and 150mm diameter connection can connect to 150mm diameter line or greater. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-6

7 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.D.7 To differentiate between sewer and stormwater, the stormwater end cap is to be wrapped or painted with blue tape/blue paint. This is to be in conjunction with an approved marker peg. connection point, of 1.2m from the lowest point in the building site. 4.E Manholes 4.E.1 Standard Stormwater manholes shall be constructed as detailed on Drawings D4 to D11. For Manholes of greater depth than 5m refer to D12. Shallow manholes (Drawing D5) may be used in certain circumstances with the approval of the Group Manager City Services. 4.E.2 Standard 1050mm manhole risers are not suitable where either pipes are larger that 675mm diameter or where multiple pipes enter a manhole causing loss of manhole wall. Designers shall upsize manholes in these cases to maintain wall integrity. 4.E.3 (a) The fall through a manhole is either: The invert of the outlet pipe from a manhole shall be 20mm plus 0.5mm per degree of horizontal angle change between the two lines lower than the lowest incoming line invert. C12 For large diameter manhole risers the lid may be lowered to 2.0m or more above invert with a 1050mm throat above, provided that the lid is of suitable strength. (b) (c) The soffit of the outlet pipe shall be level with or below the lowest incoming line s soffit. The extension of the grade of the steepest pipe whichever is the greatest. 4.E.4 All stormwater manhole covers to be painted blue (with road marking paint). 4.F Layout 4.F.1 Reticulation lines shall be sited, where possible on the low side of the proposed sites having more than 1.5m cross fall and in areas that will not reduce the building area available, ie within front, side and rear yard areas. 4.F.2 The minimum desirable cover to all pipes from finished ground level shall generally be 600mm in private land and 1.2m for road crossings, (other than sump leads) provided there is generally a minimum depth to invert, at the service TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-7

8 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.F.3 Pipelines within private property shall generally run parallel to lot boundaries. Where the centreline of a pipeline is further than 1.5m from a lot boundary or not parallel to a lot boundary an easement in favour of Council and/or Consent notices shall be provided to ensure its protection. 4.G Pipe Materials 4.G.1 Stormwater drainage systems constructed of the following materials will be accepted: Polyethylene in accordance with AS4130. PVC in accordance with AS/NZS 1260:1996. DN 100mm and 150mm to have minimum wall thickness of 4.1mm and 6.3mm respectively, defined as grade SN 16 for up to 5m depth. DN175 mm and larger to be grade SN 8 minimum or equivalent. Pipe type to be either plain wall or sandwich construction (refer Tauranga Distict Council approved products). Reinforced concrete in accordance with NZS Other pipes, arches and box structures on a specific design basis only. 4.G.2 All joints shall be: Polyethylene. Butt fusion welding to AS2033 with flanged end gibault joints allowable at endpoints. PVC. Factory made spigot and socket, rubber ring jointed to NZS Flush joints are permitted on 1050mm diameter and larger pipes, provided no ground water or geotechnical requirements dictate the need for fully sealed joints. Joints are to be RRJ or steel banded, to manufacturers specifications. 4.H.1 All drainage lines shall be thoroughly bedded haunched and surrounded as in the Drawing D13 unless installed by no-dig technology as per Drawing D4. C13 (i) SN 16 is the recommended equivalent of SEH C in DN 100 and 150 (ii) SN 8 is the recommended equivalent of SEH in DN 175 or larger. (iii) Stiffness, NOT wall section,is the controlling feature in AS/NZS 1260:1999. The actual ID (and therefore flow rate) of plain wall pipe is likely to be greater than the same size / SN of sandwich construction pipe. 4.G.3 All fittings and service connections to pipes shall be factory fabricated of compatible material to the proposed system chosen and comply with the relevant standards. PVC fittings and service connections to be in accordance with AS/NZS 1260:1996. DN 100mm and 150mm injection moulded fitting to be the closest grade currently available to the specified grade. DN 175mm and larger factory fabricated fitting to be made of same grade materials as specified for the pipeline. 4.H Bedding And Protection TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-8

9 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.H.2 All drainage lines shall be designed and constructed to withstand al the likely loads they will be subject to during the life of the system. The load carrying capacity in relation to their installation conditions shall be calculated in accordance with AS/NZS 3725:1989 Loads on Buried Concrete Pipes and AS2566:1982 Plastics Pipe laying Design where appropriate. 4.H.3 For drainage pipelines laid at grades steeper than 20% in grade, anti-scour blocks located at pipe joints, not exceeding 6m spacing, are required, as shown on Drawing D15 or as otherwise approved. 4.H.4 Where the minimum cover as outlined in Section 4.F.2 cannot be achieved, specific design of pipe and cover is required to achieve manufacturers requirements. Concrete capping will be designed on a site by site basis taking into account not just pipe protection but roading integrity requirements. C14 The manufacturer s specification for bedding shall take precedence. 4.H.5 Where public drains are located within rights of way or private access legs all other utility services such as power, telephone and gas shall be located 300mm horizontally clear of the pipe. 4.I Testing And Acceptance 4.I.1 Prior to acceptance of the completed stormwater drainage system, the subdivider s representative shall have supplied the Council with As Built drawings of the work, including any secondary flowpaths, open channel systems and areas prone to inundation, together with certification and a certificate of subdivision construction (Drawing D16). All testing shall be carried out when backfilling is completed and prior to carriageway surfacing. 4.J Close Proximity Rules 4.J.1 No building shall be built over a stormwater pipeline or closer than the greater of: 1.5m from the outside edge of the pipeline. The depth to the centre line of the pipeline from the existing/proposed ground surface, plus the diameter of the pipeline. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-9

10 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.J.2 Dispensation Dispensation may be approved to site the building down to 800mm off the pipeline centreline subject to the following conditions: The depth of the pipeline is less than 3.0m deep from the existing/proposed ground surface; Specifically designed footing/piles must be installed to 200mm below the pipeline invert; That all connections be a minimum of 1.0m outside the building; That all buildings be at least 0.5m off the outside wall of manhole structures. 4.J.3 Ancillary buildings may be exempt: Garages (single and double, maximum 7.2m), provided they are detached and do not form an integral part of the house shall be allowed to be built over pipelines, subject to the following conditions: Corner foundations are a minimum of 800m off the pipeline centre line. Additional foundation requirements of piles are to be installed 200mm below the pipeline invert, a minimum of 800mm either side of the pipeline where it enters and exits the building. The Director of City Services must be satisfied with the location of the building. No buildings will be allowed over the pipeline if there is a connection closer than 1.0m to the buildings, unless the connection is relocated to the satisfaction of the Director of City Services. 4.J.4 Carports/Decks/Sunrooms These structures may be sited over pipelines provided: There is no connection point closer than 1.0m to the building; The structure is designed such that it can be dismantled easily in sections (bolting is the preferred method of construction); 4.K Resource Consents TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-10

11 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.K.1 Where resource consents from the Regional Council are required for the diversion and or discharge of stormwater, the consent holder is responsible for making the necessary application and obtaining such resource consents before physical work commences on site. 4.K.2 Developers will typically wish to transfer resource consents (and any associated conditions) to the Tauranga Distict Council when assets are vested. Reserves the right to not accept consents if doing so would be detrimental to the Council s interests. Generally however the Council is prepared to accept consents provided that: The conditions are considered to be fair and reasonable. The required works have been completed. Full documentation is supplied including the original application, drawings and compliance certification from the Regional Council. C15 In parallel with the EBOP application, subdividers are encouraged to submit copies of stormwater discharge consent applications to Tauranga Distict Council to assist future transfer. 4.L Open Stream Systems 4.L.1 Where natural open stream systems or formed channels are to be incorporated in the stormwater drainage system, they shall generally be located within a drainage reserve of sufficient width to contain the full design flood flow together with a freeboard. Such reserves shall generally have a batter of 20% (1 in 5) and where access for maintenance is required shall include a 4m wide access berm for the full length. 4.L.2 The flow characteristics of natural open stream systems shall be based on the likely long term stream conditions. C16 Open streams, drains and channels through subdivisions can create maintenance and safety misunderstandings and difficulties. Designers need to carefully consider and describe proposed ownership/maintenance arrangements including easements and consent notices etc. 4.L.3 To encourage the best use of the open stream systems the drainage reserves shall be linked with other reserves and open spaces such as school sites, to accommodate off road pedestrian and cycle access. Access points for public use and maintenance shall provided at regular intervals along the system together with footpath and pedestrian bridges, as may be defined in the resource consent. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-11

12 Code of Practice for Development TAURANGA CITY COUNCIL SECTION 4 Stormwater Drainage 4.L.4 Where natural open stream areas form part of the stormwater drainage system they shall be cleared of all unsuitable plant growth and replanted to an appropriately approved landscape design. These works shall include protection of the low flow channel against scour and erosion of the stream bed where necessary. Access shall be provided for maintenance purposes. 4.M Detention Ponds 4.M.1 Stormwater detention ponds are an accepted method of improving stormwater quality and reducing downstream flow rates. 4.M.2 Pond design shall follow the guidance of Auckland Regional Council Technical Publication Number 10. Specific points to focus on are: Side slopes with safety considerations. Ease of maintenance including mowing and silt cleanout. Shape and contour for amenity value. An effective outlet structure. Overflow. C 17 Cost of cleaning these ponds is significant hence Council has decided to charge a development contribution bases on 2 cleans in first 5 years 4.N Pumpstations Stormwater Pumpstations are generally not permitted. Any use of pumpstations will be considered only in exceptional circumstances and then only by specific Council approval. TCC Ref: Print Date: Feb 2006 VERSION 1 R2 Page 4-12

13 Code of Practice for Development TAURANGA DISTRICT COUNCIL SECTION 4 Stormwater Drainage 4.L.4 Where natural open stream areas form part of the stormwater drainage system they shall be cleared of all unsuitable plant growth and replanted to an appropriately approved landscape design. These works shall include protection of the low flow channel against scour and erosion of the stream bed where necessary. Access shall be provided for maintenance purposes. 4.M Detention Ponds 4.M.1 Stormwater detention ponds are an accepted method of improving stormwater quality and reducing downstream flow rates. 4.M.2 Pond design shall follow the guidance of Auckland Regional Council Technical Publication Number 10. Specific points to focus on are: Side slopes with safety considerations. Ease of maintenance including mowing and silt cleanout. Shape and contour for amenity value. An effective outlet structure. Overflow. C 17 Cost of cleaning these ponds is significant hence Council has decided to charge a development contribution bases on 2 cleans in first 5 years 4.N Pumpstations Stormwater Pumpstations are generally not permitted. Any use of pumpstations will be considered only in exceptional circumstances and then only by specific Council approval Print Date: May 2002 VERSION 1 R1 Page 4-13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

DESIGN STANDARD TABLE OF CONTENTS

DESIGN STANDARD TABLE OF CONTENTS DESIGN STANDARD DS-5 STORMWATER TABLE OF CONTENTS DS-5.1 General...1 DS-5.2 Minimum Requirements...1 DS-5.3 Regional Council Requirements...1 DS-5.4 Design...2 DS-5.5 Conveyance - Primary and Secondary

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

CONTENTS. Section 6 Stormwater and Land Drainage CODE OF PRACTICE FOR SUBDIVISION AND DEVELOPMENT 6.1 SCOPE... 2

CONTENTS. Section 6 Stormwater and Land Drainage CODE OF PRACTICE FOR SUBDIVISION AND DEVELOPMENT 6.1 SCOPE... 2 CONTENTS 6.1 SCOPE... 2 6.2 PERFORMANCE STANDARDS... 2 6.2.1 General... 2 6.3 MEANS OF COMPLIANCE... 4 6.3.1 General... 4 6.3.2 Resource Consents... 6 6.3.3 Gravity Mains Reticulation Layout... 6 6.3.4

More information

5.1 INTRODUCTION OBJECTIVES PERFORMANCE CRITERIA KEY REFERENCES... 2

5.1 INTRODUCTION OBJECTIVES PERFORMANCE CRITERIA KEY REFERENCES... 2 CONTENTS SECTION 5 - STORMWATER 5.1 INTRODUCTION... 1 5.2 OBJECTIVES... 1 5.3 PERFORMANCE CRITERIA... 1 5.4 KEY REFERENCES... 2 5.5 GENERAL DESIGN REQUIREMENTS... 3 5.5.1 Design Methodology... 3 5.5.2

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

7 STORMWATER AND DRAINAGE

7 STORMWATER AND DRAINAGE 7 STORMWATER AND DRAINAGE 7.1 Introduction The purpose of Council s stormwater engineering standards is to provide design guidance and minimum standards for the design and construction of stormwater management

More information

STORMWATER BUBBLE UP PIT

STORMWATER BUBBLE UP PIT Cast iron swing grate in cast iron frame A Nominal 90 mm inlet SECTION A x ID concrete chamber. Available chamber depths 400mm or 600mm deep CHAMBER PLAN Stormwater pipe House Chamber location in vehicle

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies...

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies... Section Contents Rural-Residential... 2 16. Rural-Residential... 2 Explanatory Statement... 2 16.1 Significant Issues... 2 16.2 Objectives and Policies... 3 16.3 Activity Lists... 3 16.4 Activity Performance

More information

Part 5: Stormwater and Land Drainage

Part 5: Stormwater and Land Drainage Part 5: Stormwater and Land Drainage Part 5: Stormwater and Land Drainage Contents 5.1 Referenced Documents...5-3 5.1.1 Source documents... 5-4 5.2 Introduction... 5-4 5.2.1 Philosophy... 5-4 5.2.2 Objectives...

More information

STORMWATER AND EROSION CONTROL PERMIT

STORMWATER AND EROSION CONTROL PERMIT STORMWATER MANAGEMENT AND EROSION CONTROL PERMIT INSTRUCTIONS AND INFORMATION Any project that involves the disturbance of ANY quantity of land requires the applicant to receive approval for the project

More information

WATER 6.1 GUIDELINES

WATER 6.1 GUIDELINES 6-1 6.0 WATER 6.1 GUIDELINES The requirements of the Queensland Water Resources Commission Guidelines for Planning and Design of Urban Water Supply Schemes shall be followed in general. The requirements

More information

DIVISION 3: SEWER. Improvement Design Standards City of Dundee Oregon. Division 3 : Sewer Page 1

DIVISION 3: SEWER. Improvement Design Standards City of Dundee Oregon. Division 3 : Sewer Page 1 DIVISION 3: SEWER 3.1 DESIGN CRITERIA A. APPLICABILITY 1. These Design Standards shall govern all construction and upgrading of public sanitary sewer facilities in the City of Dundee and applicable work

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

LOT GRADING GUIDELINES

LOT GRADING GUIDELINES LOT GRADING GUIDELINES RESIDENTIAL PROPERTIES The Drainage Bylaw 16200 came into effect on June 1, 2013 replacing previous versions of the Surface Drainage Bylaw 11501. This Bylaw requires that all single

More information

The Proposed Auckland Unitary Plan (notified 30 September 2013)

The Proposed Auckland Unitary Plan (notified 30 September 2013) ART 3 REGIONAL AND DISTRICT RULES»Chapter H: Auckland wide rules»4 Natural resources» 4.14 Stormwater management Introduction The roposed Auckland Unitary lan (notified 30 September 2013) This section

More information

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects 2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD

More information

DIVISION 5 STORM DRAINAGE CRITERIA

DIVISION 5 STORM DRAINAGE CRITERIA DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer Place holder image thameswater.co.uk/developerservices Building over or close to a public sewer Did you know Thames Water is legally responsible for more than 100,000

More information

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections. Village of Vernon Hills Community Development Department 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http:// www.vernonhills.org FENCES This hand out is for REFERENCE

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Learning objectives. Upon successful completion of this lecture, the participants will be able to: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design

More information

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY Section Includes: 1. Pipe and fittings. 2. Drain Basin. 3. De-chlorination tablet feeder. 4. Non-pressure transition couplings.

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater.

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater. Background The City of rth Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of a

More information

Summary of the 2011 Changes

Summary of the 2011 Changes The following is a list of amendments to the Residential Site Improvement s, N.J.A.C. 5:21, adopted in 2011. The Notice of Adoption of these changes appeared in the New Jersey Register on May 16, 2011.

More information

Storm. Section. B. General Design and Drawing Standards Design

Storm. Section. B. General Design and Drawing Standards Design Section Storm 5 General Plans for the existing stormwater system are maintained in digital and printed form by the City. Copies may be obtained from the Utility Division of the Public Works Department.

More information

Design Guidelines. pegasus-town.co.nz

Design Guidelines. pegasus-town.co.nz Design Guidelines pegasus-town.co.nz Welcome to Pegasus Town These guidelines have been developed to help make your home-building process as easy as possible. The contents provide you, or your designer

More information

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit

More information

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

Drainage By-law. WM-4 Consolidated as of April 18, 2011

Drainage By-law. WM-4 Consolidated as of April 18, 2011 Drainage By-law WM-4 Consolidated as of April 18, 2011 As Amended by By-law No. Date Passed at Council WM-4 September 20, 1993 WM-4-95001 September 18, 1995 WM-4-96002 August 6, 1996 WM-4-97003 May 5,

More information

Design Guidelines. 1. INTRODUCTION 2. SECTION SPECIFICATIONS 3. HOUSE DESIGN RULES

Design Guidelines. 1. INTRODUCTION 2. SECTION SPECIFICATIONS 3. HOUSE DESIGN RULES Design Guidelines. 1. INTRODUCTION Waimakariri District Council (WDC) and Ravenswood Developments Ltd (Ravenswood) have in place a number of rules and covenants that effect the development of sections

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CHAPTER 6. Sanitary Sewer

CHAPTER 6. Sanitary Sewer CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide

More information

FLOOD PLAIN STANDARDS AND REQUIREMENTS. Adopted by City Council on September 16, 2014 Effective January 1, 2015

FLOOD PLAIN STANDARDS AND REQUIREMENTS. Adopted by City Council on September 16, 2014 Effective January 1, 2015 City of Vancouver Land Use and Development Policies and Guidelines Planning and Development Services, 453 W. 12th Ave Vancouver, BC V5Y 1V4 tel 604.873.7000 fax 604.873.7060 planning@vancouver.ca FLOOD

More information

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts 2.7 C Culverts 1. General Culverts are intended to safely pass flow under road crossings. Criteria are designed to protect, maintain, and enhance public health, safety, and the environment. Where culverts

More information

7.00 MANHOLES AND INSPECTION CHAMBERS. Hunter Underground Systems

7.00 MANHOLES AND INSPECTION CHAMBERS. Hunter Underground Systems 7.00 MANHOLES AND INSPECTION CHAMBERS Hunter Underground Systems 7.01 Access to drains 7.02 preformed plastic Inspection Chambers 7.03 Manholes 7.04 450mm diameter inspection chambers Equal 110mm inspection

More information

Initial Construction Costs For Various Pavement and Drainage Options

Initial Construction Costs For Various Pavement and Drainage Options Interpave Initial Construction Costs For Various Pavement and Drainage Options Final Prepared For Interpave Scott Wilson Ltd Interpave Pavement Design CONTENTS 1. Overview 2. Summary of Pavement Types

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

Article 20: Erosion Control and Stormwater Management

Article 20: Erosion Control and Stormwater Management Article 20: Erosion Control and Stormwater Management Section 360: Purpose, Scope of Authority, Performance Guarantee and Approvals A. Purpose. The purpose of this document is to set forth minimum requirements

More information

Concrete pipe reference manual Issue 1

Concrete pipe reference manual Issue 1 Strength. Performance. Passion. Concrete pipe reference manual Issue 1 Contents 1. Introduction 3 Manufacturing 3 Joint types 3 Durability 4 Hydraulics 4 Size class (DN) 4 Load class 5 6. Pipes for pressure

More information

BLOCK, LOT ; Section Requirement Status of Permit Review Status of C.O. Review The first 6 items are relevant to the principal building (house):

BLOCK, LOT ; Section Requirement Status of Permit Review Status of C.O. Review The first 6 items are relevant to the principal building (house): R-1A - ZONING REVIEW WORKSHEET Note: The items below must be reviewed and found in compliance prior to issuance of a zoning permit. Therefore, the appropriate data must be shown on the survey/lot development

More information

Landscaping and Fencing

Landscaping and Fencing Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007: LOT GRADING DEFINITION Lot grading is the reshaping or sloping of the land in such a way that surface drainage from rain runoff is directed away from the buildings and is controlled in a manner that eliminates

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS

CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS Section 1 Intent. 49 Section 2 Floodplain Requirements 49 Section 3 Water-Oriented Accessory Structures 50 Section 4 Stairways,

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

Underground Piping for Private Hydrants & Sprinkler Supply Line

Underground Piping for Private Hydrants & Sprinkler Supply Line City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies

More information

3.1 Introduction: Design Responsibility and Applicability of Requirements

3.1 Introduction: Design Responsibility and Applicability of Requirements SECTION 3 Sewer Design and Construction 3.1 Introduction: Design Responsibility and Applicability of Requirements The design and construction requirements for sewer collection systems included in this

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1300 CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1301 SECTION 13.01 STATEMENT OF PURPOSE To provide for manufactured home park development, of long-term duration of stay, in

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds Section 8: Amended Soil Mounds 8. Amended Soil Mounds 8. Amended Soil Mounds 8.1 Design...95 8.2 Installation...96 8.3 Inspection...101 8.4 Operation...101 8.5 Common technical issues...105 8.6 Case study...105

More information

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA SECTION 6900 - WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA 6901 DESIGN CRITERIA A. General 1. The design standards presented in the City of Lee's Summit Design Criteria are the minimum standards

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

PALMERSTON NORTH CITY PALMERSTON NORTH STORMWATER DRAINAGE BYLAW. Administration Manual

PALMERSTON NORTH CITY PALMERSTON NORTH STORMWATER DRAINAGE BYLAW. Administration Manual PALMERSTON NORTH CITY PALMERSTON NORTH STORMWATER DRAINAGE BYLAW 2015 Administration Manual 1 Contents Part One Introduction... 4 Part Two Standard Conditions For Stormwater Connections... 5 Appendix 1

More information

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

S.O.P. No. HMD

S.O.P. No. HMD Page: 1 of 9 PURPOSE: To establish (SOP) for submission requirements, review process and approval of applications for Non-vehicular Access Permits for the purpose of connection or discharge to any MassDOT

More information

JEFFERSON COUNTY STORM WATER MANAGEMENT

JEFFERSON COUNTY STORM WATER MANAGEMENT JEFFERSON COUNTY STORM WATER MANAGEMENT B-210 Courthouse, Birmingham, Alabama 35203 Telephone: (205) 325-8741 Erosion and Sedimentation Control Measures for Commercial Projects (Plans Requirements) -All

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

ENGINEERED SOLUTIONS. Terre Arch Concrete Detention/Infiltration. Solutions Guide

ENGINEERED SOLUTIONS. Terre Arch Concrete Detention/Infiltration. Solutions Guide ENGINEERED SOLUTIONS Terre Arch Concrete Detention/Infiltration Solutions Guide Stormwater Solutions from Contech Selecting the Right Stormwater Solution Just Got Easier... It s simple to choose the right

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

Method of Measurement for Road Works Series MM Earthworks

Method of Measurement for Road Works Series MM Earthworks Method of Measurement for Road Works Series MM 600 - CC-RMP-00600 March 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

THE ADVANTAGES HDPE MANHOLES

THE ADVANTAGES HDPE MANHOLES NIC HDPE manholes are custom fabricated for many varied applications including municipal and industrial manholes, sewer and storm water manholes, leach ate collection, sewer lift stations, siphon structures,

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

SEPTIC TANK CONSTRUCTION GUIDELINES

SEPTIC TANK CONSTRUCTION GUIDELINES SEPTIC TANK CONSTRUCTION GUIDELINES Septic tank for this airport will be designed/ built by the general contractor of the building facilities. At the time of the project design, availability of a septic

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. SECTION 33 05 13 MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. B. Related Sections: 1. Section 03 20 00 - Concrete

More information

***************************************************************************************************************

*************************************************************************************************************** 02735 WASTE WATER DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 22 14 00 ***************************************************************************************************************

More information

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements General Information Site Card. Before starting construction, post the site card (issued by the City) in a front window visible from the street. Miss Dig. Before you dig, call Miss Dig at 800.482.7171 This

More information

Hydrological and Hydraulic Guidelines

Hydrological and Hydraulic Guidelines Hydrological and Hydraulic Guidelines Prepared by Environmental Hazards Group Bay of Plenty Regional Council Guideline 2012/02 5 Quay Street PO Box 364 Whakatane NEW ZEALAND ISSN: 1179-9595 (Print) ISSN:

More information

INTRODUCTION. PVC PRESSURE PIPE SPECIFICATIONS The SANS 966 is a two-part specification.

INTRODUCTION. PVC PRESSURE PIPE SPECIFICATIONS The SANS 966 is a two-part specification. 1 INTRODUCTION DPI Plastics (Pty) Ltd is a leading manufacturer of PVC and HDPE water reticulation and drainage pipe and fitting systems with two ISO 9001 certified South African factories based in Johannesburg

More information

COMMUNICATIONS ALLIANCE LTD INDUSTRY GUIDELINE G645:2017 FIBRE-READY PIT AND PIPE SPECIFICATION FOR REAL ESTATE DEVELOPMENT PROJECTS

COMMUNICATIONS ALLIANCE LTD INDUSTRY GUIDELINE G645:2017 FIBRE-READY PIT AND PIPE SPECIFICATION FOR REAL ESTATE DEVELOPMENT PROJECTS COMMUNICATIONS ALLIANCE LTD INDUSTRY GUIDELINE FIBRE-READY PIT AND PIPE SPECIFICATION FOR REAL ESTATE DEVELOPMENT PROJECTS Industry Guideline Fibre-Ready Pit and Pipe Specification for Real Estate Development

More information

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections. SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity

More information

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS 14.1 GENERAL USE REGULATIONS 14.1.1 PERMITTED USES No land, building, or structures shall be used or erected in the General Industrial Zone (M2) unless

More information