DIVISION 5 STORM DRAINAGE CRITERIA
|
|
- Buck Archibald Adams
- 6 years ago
- Views:
Transcription
1 DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the Standard Drawings. The minimum allowed pipe size and material inside the City rightof-way is fifteen-inch (15 ) diameter reinforced concrete. Section 5.02 INLET BOXES AND MANHOLES Sub-Section A. Storm Water Inlets: Curb face inlets (or an acceptable alternative) must be constructed at all low lying areas. Curb face inlet boxes will serve tributary piping and shall not be used as junction boxes or manholes. If multiple piping is required in a structure using a curb face inlet, a combination box shall be constructed which must include a manhole for access. No inlets shall be allowed at the bottom of an ADA ramp structure or in a designated pedestrian path. Inlets at drive cuts are discouraged and may only be used with approval of the City Engineer. Manholes: Minimum manhole interior diameter is four (4) foot for manholes with one inlet and one outlet pipe. Manholes with two or more inlet pipes and one outlet pipe shall be a minimum of five (5) foot in diameter. Spacing between manholes shall be no more than four hundred (400) feet unless special approval is granted by the City Engineer. Sub-Section C. Storm Water Treatment: All new land development will require provisions for storm water treatment before the water is allowed to discharge into the existing City system. A design that will separate oils and particulates from the discharged water will have to be approved by the City Engineer. The treatment facility must be easily accessible and maintainable without unreasonable effort. Section 5.03 MULTIPLE-LOT STORM DRAINAGE CALCULATIONS The following information shall be included in the storm drainage calculations for multiple-lot development. Sub-Section A. Hydrologic (Flow) Calculations: 1) A map showing drainage sub-basins and the piping system. 2) Cumulative peak flow calculations for each sub-basin (submit all input data, calculations and results). Hydraulic (Inlet and Pipe) Calculations: 1) Capacity calculations for each segment of the pipe system. 2) Calculations demonstrating that flow rates in streets do not exceed maximums before being caught in storm drain inlets. Section 5.07, Sub-Section C: Inlet Spacing dictates the criteria required for allowable water spread. 3) Calculations demonstrating that inlets are sufficiently long to capture peak design flows. 4) Slopes shall be designed to have a two (2) foot pre second velocity. Minimum slopes for different size pipes are as follows: 3-8
2 Sub-Section C. Detention Calculations: MINIMUM STORM DRAIN MAIN SLOPES Pipe Size Min Slope (ft/ft) ) Detention volume requirement which includes an analysis that identifies the storm whose duration creates the greatest detention volume requirement, given storm duration and stage storage curve and outlet discharge curve. 2) Orifice calculations illustrating that the maximum release rate is not exceeded. Section 5.04 COMMERCIAL SITE STORM DRAINAGE CALCULATIONS The following information shall be included in the storm drainage calculations for commercial site property development. Sub-Section A. Hydrologic (Flow) Calculations: 1) Peak flow calculations for the site (submit all input data, calculations and results). Hydraulic (Inlet and Pipe) Calculations: 1) Capacity calculations for each segment of the pipe system. Sub-Section C. Detention Calculations: 1) Detention volume requirement-an analysis that identifies the storm whose duration creates the greatest detention volume requirement, given storm duration and stage storage curve and outlet discharge curve. 2) Stage storage curve - generally required only on large detention basins. 3) Outlet discharge curve - generally required only on large detention basins. 4) Orifice calculations illustrating that the maximum release rate is not exceeded. Section 5.05 LANDSCAPED STORM DETENTION BASIN REQUIREMENTS Storm water must be detained such that the peak flow rate released from the site does not exceed 0.15 cubic feet per second per acre of development (cfs/acre). Detention basins must have vehicular access for maintenance and will not be allowed in the backyards of single family residences. The following limitations apply to detention basins: a) The side slopes of the basin may not be steeper than 3:1 unless special circumstances warrant a change. Any change must be approved by the City Engineer. The bottom of the detention basin must slope toward the drain. b) Within 10 feet of the outlet, the slope of the basin bottom must not be flatter than 5% unless a concrete apron is constructed around the outlet. c) Excluding areas within 10 feet of the outlet, the maximum allowable depth of water in the basin is 3 feet. An additional one (1) foot of freeboard must be constructed on all basins. 3-9
3 d) Storm drain pipes are to be continuous through detention areas to allow low flows to proceed through the storm drainage system without having to come to the surface. These flows must still pass through the outlet restriction that limits runoff rates. e) Basins are to be designed such that water does not run into them after storm water reaches a maximum depth (unless a free flowing overflow is provided) this can usually be controlled by the elevation of an inlet box in the street adjacent to the basin. f) Basins are to be designed such that when runoff exceeds design values or when restrictions plug, excess storm water will be directed to the street system or bypass the restriction by entering the piped system via a free flowing overflow. g) A basin may be designed for dual use, but uses other than the detention of storm water must be approved by the City Engineer. h) In cases where the basin detains water from, and is part of a project controlled by, a Home Owners Association (HOA), the HOA will be responsible to maintain the operation, landscaping and irrigation sprinkling of the basin. Section 5.06 HARD SURFACE STORM DETENTION STORAGE REQUIREMENTS Storm water may not be detained above ground on hard surface areas. If property is not available for a landscaped detention basin, storm water may be detained underground in an approved underground system. Storm water must be detained such that the peak flow rate released from the site does not exceed 0.15 cubic feet per second per acre of development (cfs/acre). Underground storage designs should be discussed with the City Engineer before submittal and will be approved on a case by case basis. The following limitations apply to underground detention storage: a) Basins are to be designed such that when runoff exceeds design values or when restrictions plug, excess storm water will be directed to the street system or bypass the restriction by entering the piped system via a free flowing overflow. b) The private property owner benefiting from the underground detention storage will be responsible to maintain the operation of the system. Section 5.07 STORM WATER QUANTITY CRITERIA AND DESIGN GUDELINES The following storm drainage criteria and design guidelines apply to all storm drainage plans in Springville and shall be used in storm drainage calculations. The City Engineer has authority to modify the criteria and guidelines as needed to meet changing or unusual needs or conditions. Sub-Section A. Design Storm: 1) Frequency i. Design the piping system for a 10-year storm ii. Design detention for a 25-year storm with a 0.15 cfs/acre release rate. iii. Control the point of discharge and the flooding hazard of a 100-year storm 2) Intensity per the following table: Duration Rainfall Intensities (inches/hour) min min min min min
4 2 hours hours hours hours hours Runoff Coefficients: Springville City requires the design engineer to calculate a composite runoff coefficient based on surface type and associated runoff coefficient, weighted by the area of each surface type. Sub-Section C. Inlet Spacing: Two criteria must be met. 1) Spread of water in the street: Storm water must be delivered from the street into an underground piped system when the spread of water in the street covers the outside 8 feet of asphalt. This will leave one 12-foot traffic lane in local streets (that have 28 feet of asphalt), two 10-foot lanes in minor collector streets (that have 36 feet of asphalt) and three 12-foot lanes in major collector streets (that have 52 feet of asphalt) that are not submerged. 2) Gutter velocity: Water must be delivered from the street into an underground piped system when the velocity of water in the deepest part of the gutter reaches 10 feet per second (as a safety consideration). Both of these requirements are a function of street slope and storm water flow rate. Storm water must be delivered from the street to storm drains when flows reach amounts shown in the following graph. This means that for a given longitudinal street slope, flows on the street surface must be delivered into the underground piped system when they reach the amount indicated on the graph by the solid line. 3-11
5 Note: The spread of water in the street is calculated using the Manning equation in the form developed by Izzard, with a roughness coefficient of and the standard street cross section. The velocity criteria is based on the velocity at the deepest part of the gutter with the Manning Equation, with a roughness coefficient of 0.013, and using a depth at a point six inches from the face of the curb as the hydraulic radius. Sub-Section D. Inlet Capacity: The designer is to assume 50% blockage of inlets when considering storm drain inlet capacity. 3-12
PART 3 STORM WATER TECHNICAL MANUAL
PART 3 STORM WATER TECHNICAL MANUAL A. INTRODUCTION The Storm Water Technical Manual contains requirements for land development and construction activities, as well as design criteria and guidelines for
More informationDESIGN CRITERIA FOR PUBLIC IMPROVEMENTS TABLE OF CONTENTS
DESIGN CRITERIA FOR PUBLIC IMPROVEMENTS CHAPTER 3, TABLE OF CONTENTS DESIGN CRITERIA FOR PUBLIC IMPROVEMENTS TABLE OF CONTENTS DIVISION 1 - GENERAL REQUIREMENTS... 3-1 Section 1.01 PURPOSE OF DOCUMENTS...
More informationTABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method
More informationChapter 8. Inlets. 8.0 Introduction. 8.1 General
. Introduction This chapter provides criteria and design guides for evaluating and designing storm sewer inlets in the City of Centennial. The review of all planning submittals will be based on the criteria
More informationSTORM DRAINS AND IRRIGATION
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 STORM DRAINS AND IRRIGATION 105.1. STORM DRAINS... 105.1 105.2. METHODS OF ANALYSIS... 105.1 105.2.1. Rational Method... 105.1 105.2.2.
More informationCHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN
CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW7 September 2017 SW7.01 Purpose The purpose of this Chapter is to establish a basis for inlet design utilizing City of Fort Wayne standard inlets and
More informationStorm Water System Improvements
IV Storm Water System Improvements A. General The purpose of this Section is to establish standard principles and practices for the design and construction of storm drainage facilities within the City
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationRETENTION BASIN EXAMPLE
-7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary
More informationHydrologic Study Report for Single Lot Detention Basin Analysis
Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page
More informationCUYAHOGA COUNTY ENGINEER
CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted
More informationSTORM DRAINAGE DESIGN MANUAL
Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated
More informationSECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1
CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1
More informationIntroduction to Storm Sewer Design
A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream
More informationFORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview
Chapter 5: Hydrology Standards Contents 1.0 Overview... 1 1.1 Storm Runoff Determination... 1 1.2 Design Storm Frequencies... 1 1.3 Water Quality Storm Provisions... 2 1.4 Design Storm Return Periods...
More informationLAKE COUNTY HYDROLOGY DESIGN STANDARDS
LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide
More informationCACHE VALLEY STORM WATER DESIGN STANDARDS. As Amended by Logan City November 2010
CACHE VALLEY STORM WATER DESIGN STANDARDS As Amended by Logan City November 2010 Updated November 2010 Table of Contents A. Definitions... 3 B. Design Requirements... 5 1. Storm Event... 5 2. Allowable
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More informationChapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification
7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street
More informationChapter 9 STORMWATER DESIGN. Table 9-1 Hydrology Design Methods
www.knoxvilletn.gov/engineering/ 9.1 Hydrology Methods Chapter 9 STORMWATER DESIGN Table 9-1 shows the various hydrologic computation methods that can be used to compute peak flows in the City of Knoxville.
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More informationT a b l e o f C o n t e n t s
C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General
More information3.3 Acceptable Downstream Conditions
iswm TM Criteria Manual - = Not typically used or able to meet design criterion. 1 = The application and performance of proprietary commercial devices and systems must be provided by the manufacturer and
More informationAPPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary
APPENDIX J-3 Orcem Stormwater Management and Treatment Facilities Design Summary Stormwater Management & Treatment Facilities Design Summary INTRODUCTION KPFF Consulting Engineers has compiled this report
More informationSTORM DRAINAGE IMPROVEMENTS
STORM DRAINAGE IMPROVEMENTS I. Storm drain size determination A. The minimum pipe line size for the public storm drain systems shall be 15 inch for the main line, (12 inch allowed for one inlet box at
More informationPRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY
PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established
More informationSubmittal requirements are discussed in this Manual in Section Development Review Team (DRT).
SECTION 7 7.0 DRAINAGE SECTION 7.1 GENERAL This section provides stormwater design information for local agencies, engineers, developers, or others whose activities affect stormwater management within
More informationSubmittal requirements are discussed in this Manual in Section Development Review Team (DRT).
SECTION 7 7.0 DRAINAGE SECTION 7.1 GENERAL This section provides stormwater design information for local agencies, engineers, developers, or others whose activities affect stormwater management within
More informationPART A4 STORM DRAINAGE SYSTEM
PART A4 STORM DRAINAGE SYSTEM DECEMBER 2015 PART A4 - STORM DRAINAGE SYSTEM Page 1 1 GENERAL... 2 2 DEFINITIONS... 2 3 SUBMISSIONS AND APPROVALS... 2 MASTER DRAINAGE PLAN... 2 SITE DRAINAGE PLAN... 3 4
More informationSTORM DRAINAGE DESIGN CRITERIA. Department of Engineering. Town of Windsor, Colorado
STORM DRAINAGE DESIGN CRITERIA Department of Engineering Town of Windsor, Colorado Revised July 21, 2006 STORM DRAINAGE DESIGN CRITERIA TOWN OF WINDSOR, COLORADO TABLE OF CONTENTS SECTION 1 - DRAINAGE
More informationPRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS
PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS 39 AUGUST 2005 TABLE OF CONTENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PAGE SECTION 1 DESIGN CRITERIA 41 SECTION 2 SUBMITTAL 44 SECTION 3 STRUCTURES
More informationChapter 11 Drainage Improvements
Chapter 11 Drainage Improvements U30011.docx 04/14/17 Chapter 11 Drainage Improvements 11.1 Requirements for Storm Drainage Plans... 1 11.1.1 General... 1 11.1.2 Minor and Major Design Storms... 2 11.1.3
More informationSECTION 4 STORM DRAINAGE
4.01 GENERAL SECTION 4 STORM DRAINAGE These standards shall provide minimum requirements for the design of Storm Drainage and related appurtenances within the City of West Sacramento rights of way and
More informationPRELIMINARY DRAINAGE STUDY
PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,
More informationCatch Basin Inserts: Method to Determine CB Inserts Act as Full Capture Devices
WATERSHED PROTECTION DIVISION DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION CITY OF LOS ANGELES Catch Basin Inserts: Method to Determine CB Inserts Act as Full Capture Devices Catch Basin Inserts: Method
More informationCHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
More informationHY-12 User Manual. Aquaveo. Contents
Y-12 User Manual Aquaveo Contents Overview...2 Watershed Parameters...3 Channel Parameters...3 Storm Drain Parameters...3 Design of new systems...4 Analysis of existing systems...4 Steady flow...4 ydrographic
More informationDawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228
Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:
More informationSTORMWATER DESIGN CRITERIA. PUBLIC WORKS DEPARTMENT City of Hudson Oaks, Texas
STORMWATER DESIGN CRITERIA PUBLIC WORKS DEPARTMENT City of Hudson Oaks, Texas REVISED JANUARY 23, 2014 TABLE OF CONTENTS Foreword.... 3 Storm Water Management Policy.... 4 Definitions.... 5 1. Preliminary
More informationAPPENDIX F RATIONAL METHOD
7-F-1 APPENDIX F RATIONAL METHOD 1.0 Introduction One of the most commonly used procedures for calculating peak flows from small drainages less than 200 acres is the Rational Method. This method is most
More informationContents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek
Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Contents SITE LOCATION / DESCRIPTION... 3 WESTPOINTE STORMWATER MANAGEMENT PLAN... 3 THE ENCLAVE AT WESTPOINTE DETENTION POND... 3 Table
More information10.0 Storm Sewer Systems
October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and
More informationCITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS
CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE
More informationReport. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationCity of Lawton Public Works. Stormwater Drainage Policy
City of Lawton Public Works Stormwater Drainage Policy July 2007 TABLE OF CONTENTS SECTION I GENERAL DRAINAGE POLICY FOR THE CITY OF LAWTON 1 Goal Purpose Performance Requirements Minimum Surface Drainage
More informationWinSLAMM v Program Modifications Final, 3/16/19
WinSLAMM v 10.4.1 Program Modifications Final, 3/16/19 1. Printing Set up a printing option for.pdf files for input data and output summary data. 2. Added the Pipe input data to the printing input data
More informationArticle 20: Erosion Control and Stormwater Management
Article 20: Erosion Control and Stormwater Management Section 360: Purpose, Scope of Authority, Performance Guarantee and Approvals A. Purpose. The purpose of this document is to set forth minimum requirements
More informationAPPENDIX F DESIGN CRITERIA FOR STORM WATER DRAINAGE FACILITIES (1.10 of Appendix A)
APPENDIX F 1.10 DESIGN CRITERIA FOR STORM WATER DRAINAGE FACILITIES (1.10 of Appendix A) SECTION 1 INTRODUCTION 1.01 Purpose The purpose of this manual is to establish standard methods and principals for
More informationPRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN
PRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN April 5, 2015 Wayne W. Chang, MS, PE 46548 Chang Civil Engineering Hydrology Hydraulics Sedimentation P.O. Box 9496 Rancho Santa Fe, CA 92067 (858) 692-0760
More informationPRELIMINARY HYDROLOGY STUDY
PRELIMINARY HYDROLOGY STUDY FOR Tentative Tract Map West Side of Loma Alta Drive City of Oceanside, CA Prepared For: EMERALD HILLS LLC 4272 Dogwood Avenue Seal Beach, CA 90740 Contact: Mr. Jimmy Chen Ph:
More informationDRAINAGE BASICS Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements
DRAINAGE BASICS 1 Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements 2 Common Terminology & Useful Tools CFS= Cubic Feet per Second-
More informationStormwater Management Criteria
FOR OFFICE USE ONLY Stormwater Management Criteria Form #PWU005 (rev. 11/16) Approving Agency Performance Standards Applicability for Control of Stormwater Pollution Applicability for Control of Peak Runoff
More informationCity of Orem STORM DRAINAGE SYSTEMS DESIGN AND MANAGEMENT MANUAL
City of Orem STORM DRAINAGE SYSTEMS DESIGN AND MANAGEMENT MANUAL TABLE OF CONTENTS Page No. Section 1 Purpose...1 Section 2 Drainage Submittal Requirements...2 2.1 Introduction...2 2.2 Storm Water Pollution
More informationAPPENDIX G HYDRAULIC GRADE LINE
Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm
More informationDecember 6, Nate Hatleback Project Manager City of Thornton 9500 Civic Center Drive Thornton, CO 80229
December 6, 2016 Nate Hatleback Project Manager City of Thornton 9500 Civic Center Drive Thornton, CO 80229 RE: Drainage Conformance Letter Hilton Garden Inn @ The Grove The Grove Filing No 1, lot 5E Thornton,
More informationLearn how to design inlet grates, detention basins, channels, and riprap using the FHWA Hydraulic Toolbox and WMS
v. 11.0 WMS 11.0 Tutorial Learn how to design inlet grates, detention basins, channels, and riprap using the FHWA Hydraulic Toolbox and WMS Objectives Learn how to use several Hydraulic Toolbox calculators
More informationCITY OF WAXAHACHIE, TEXAS MANUAL FOR THE DESIGN OF STORM DRAINAGE SYSTEMS
CITY OF WAXAHACHIE, TEXAS MANUAL FOR THE DESIGN OF STORM DRAINAGE SYSTEMS MAY, 2001 TABLE OF CONTENTS Page No. SECTION I: INTRODUCTION 1.1 General... I-1 1.2 Scope... I-1 1.3 Organization of Manual...
More information2. DEFINITIONS. American Association of State Highway and Transportation Officials.
2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:
More informationPART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS
PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm
More informationHYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS
HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review
More informationOverview of NRCS (SCS) TR-20 By Dr. R.M. Ragan
Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability
More informationSECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements
SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature
More informationCITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390
CITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390 ENGINEERING DESIGN STANDARDS Prepared by: Boss Engineering Howell, Michigan October 5, 2016 TABLE OF CONTENTS PART I. INTRODUCTION SECTION 1.0
More information3. STORM DRAINAGE FACILITIES
3. STORM DRAINAGE FACILITIES 3.1 Introduction: Drainage facilities shall be designed and constructed at such locations and of such size and dimensions to adequately serve the development and the contributing
More informationState Standard. for. Stormwater Detention/Retention
ARIZONA DEPARTMENT OF WATER RESOURCES FLOOD MITIGATION SECTION State Standard for Stormwater Detention/Retention Under the authority outlined in ARS 48-3605(a) the Director of the Arizona Department of
More informationCUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL
CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 July 29, 2011 Revisions
More information6.5 Extended Detention Basin
6.5 Extended Detention Basin Figure 6-22: Extended Detention Basin. Photograph courtesy of Bill Southard (DES Architects and Engineers) Best uses Detain low flows Can be expanded to detain peak flows Sedimentation
More information12 DRAINAGE General Administrative Requirements Standards
12 DRAINAGE 12.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with drainage, including culverts, bridge hydraulics, roadway ditches, and closed storm
More informationChapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall
6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures
More informationSubmittal Requirements. Post Construction Verification Document Plan Requirements
Submittal Requirements Post Construction Verification Document survey plan in accordance with the items of this Checklist Supporting calculations in accordance with the items of this Checklist A copy of
More informationENGN.4010 ENGINEERING CAPSTONE DESIGN Watershed Analysis. CiA
RATIONAL METHOD Q CiA Where: Q = Maximum Rate of Runoff (cfs) C = Runoff Coefficient i = Average Rainfall Intensity (in/hr) A = Drainage Area (in acres) RATIONAL METHOD Assumptions and Limitations: Watershed
More informationCity of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development
City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit
More informationReport. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationCITY OF BIXBY STORMWATER DRAINAGE CRITERIA
CITY OF BIXBY STORMWATER DRAINAGE CRITERIA August 27, 2001 PREPARED BY MESHEK & ASSOCIATES, INC. P.O. BOX 636 20 W. 2 ND ST., SUITE 200 SAND SPRINGS, OK 74063 918-241-2803 1 E.1.1 Master Drainage Plans
More informationWinSLAMM v Program Modifications Final, 12/12/17
WinSLAMM v 10.3.4 Program Modifications Final, 12/12/17 1. Corrected an error in the Biofilter caused by an improperly defined variable that caused an overflow during very long model runs. 2. Corrected
More informationCONSTRUCTION PLAN CHECKLIST
CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted
More informationDICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON
DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON May 25, 2006 INTRODUCTION The Dickinson Bayou Watershed covers approximately 95.5 square miles and stretches from western Brazoria
More informationDrainage Analysis. Appendix E
Drainage Analysis Appendix E The existing and proposed storm drainage systems have been modeled with Bentley CivilStorm V8 computer modeling software. The peak stormwater discharge was determined for
More informationCITY OF CALDWELL ENGINEERING DEPARTMENT CALDWELL MUNICIPAL STORMWATER MANAGEMENT MANUAL
CITY OF CALDWELL ENGINEERING DEPARTMENT CALDWELL MUNICIPAL STORMWATER MANAGEMENT MANUAL July 2009 1 Table of Contents 100 STORMWATER MANAGEMENT... 5 100.1 GENERAL OVERVIEW... 5 100.2 MANAGEMENT GOALS...
More informationSump Pumps Office procedures for the Drainage & Grading section
County of Los Angeles Department of Public Works Building and Safety Division Grading and Drainage Section Sump Pumps Office procedures for the Drainage & Grading section Introduction This manual provides
More informationThe City of Bristol, Tennessee. Infrastructure Design Standards
The City of Bristol, Tennessee Infrastructure Design Standards October 2017 GENERAL PROVISIONS Adoption These Infrastructure Design Standards (the Standards ) are adopted pursuant to Section 62-8 of the
More informationDesign Example Handouts. DURANGO DETENTION WORKBOOK LUNCH AND LEARN CITY OF DURANGO Meeting Date: February 7, 2017
Design Example Handouts DURANGO DETENTION WORKBOOK LUNCH AND LEARN CITY OF DURANGO Meeting Date: February 7, 2017 Design Example 1 Residential Infill Development Durango Detention Sheet: Basin Structure
More informationWASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS
GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Community Services Department (CSD) standards for: INDEX Designing Gravity Sewer Collection Facilities ( Sewer Design
More informationMODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation
Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed
More informationDESIGN GRADING AND EROSION CONTROL A. Slope Criteria
Section 5. DESIGN GRADING AND EROSION CONTROL A. Slope Criteria Earthen slopes shall conform to the following: Maximum slope should not be steeper than 6:1 (horizontal to vertical) unless protected from
More informationCUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL
CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 November 18, 2013
More informationAppendix J: Storm Conveyance Design Parameters
Appendix J: Storm Conveyance Design Parameters Drain Commissioner 39 February 2005 STORM DRAINAGE DESIGN CRITERIA A. STORM SEWERS 1. The required discharge capacity shall be determined by the Rational
More informationTechnical Memorandum
Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:
More informationDRAINAGE SUBMITTAL CHECKLIST
Project Name: Firm Name: Map ID: Engineer: Address: City: State: Zip: Phone Number: Fax Number: Property Owner: Address: City: State: Zip: Reviewed By: Date Received: Date Accepted for Review: The following
More informationFINAL DRAINAGE REPORT FALLBROOK FILING NO. 3 Thornton, CO
FINAL DRAINAGE REPORT FALLBROOK FILING NO. 3 Thornton, CO May 6, 2016 JN: 14053 Prepared for: Carlson Associates CalAtlantic Homes PO Box 247 6161 S. Syracuse Way, Suite 200 Eastlake, CO 80614 Greenwood
More informationA Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.
Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts
More informationEngineering Division 701 Laurel Street Menlo Park, CA Phone: (650) Fax: (650)
Engineering Division 701 Laurel Street Menlo Park, CA 94025 Phone: (650) 330-6740 Fax: (650) 327-5497 GRADING AND DRAINAGE GUIDELINES FOR SINGLE FAMILY HOME PROJECTS It is the responsibility of the property
More informationLDS Technical Guidance
May 21, 2008 The following was provided to County staff as internal guidance for reviewers in applying the adequate outfall requirements of the Public Facilities Manual (PFM). A number of private sector
More informationLAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA
LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA FEBRUARY 1996 CITY OF LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA TABLE OF CONTENTS Pg 1.0 GENERAL 1.1 Introduction... 1 1.2 Applicability... 1 1.3 General
More information