PROVING OUR PROFESSIONALISM

Size: px
Start display at page:

Download "PROVING OUR PROFESSIONALISM"

Transcription

1 PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB

2 TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods The Nitty Gritty, CCNA & Design-Build Solicitation Strategies

3 PROJECT DELIVERY OVERVIEW

4 PROJECT DELIVERY OVERVIEW A COMPREHENSIVE PROCESS NECESSARY FOR ORGANIZING, EXECUTING AND COMPLETING A BUILDING, FACILITY OR PROJECT. Design-Bid-Build Construction Manager at Risk (CM@R or CMAR) Design-Build

5 DESIGN-BID-BUILD Traditional Construction Project Delivery Low Bid Two contracts Linear Sequential Responsive & Responsible

6 PROJECT DELIVERY SYSTEMS I. Design-Bid-Build A/E prepares plans and specifications Low dollar bid from general contractor Separate contracts for design and construction OWNER ARCHITECT/ ENGINEER DESIGN SUBS BUILDER/GC SUBS & SUPPLIERS

7 PROJECT DELIVERY SYSTEMS CONSTRUCTION MANAGER AT RISK Competitive Selection Negotiated Contract Two contracts Design Construction GMP Contingencies Possible fast track Spearin Doctrine

8 PROJECT DELIVERY SYSTEMS II. Construction Management Select Designer Select CM Based on Qualifications Two separate Companies under Contract CM Responsible for Delivery of Construction Services OWNER ARCHITECT/ ENGINEER DESIGN SUBS CM SUBS & SUPPLIERS

9 PROJECT DELIVERY SYSTEMS DESIGN-BUILD Negotiated Contract One contract Single point of responsibility Faster to Contract Award Concurrent Design/Construction Fast track Total Cost Known earlier No Spearin Doctrine (if done right!)

10 PROJECT DELIVERY SYSTEMS Design-Build Design and construction under a single contract Project may begin before design is complete OWNER DESIGN-BUILDER ARCHITECT/ ENGINEER BUILDER/GC

11 COMPARING PROJECT DELIVERY METHODS

12 COMPARING PROJECT DELIVERY METHODS Design-Bid-Build Owner Selects Designer Design by A/E Owner Warrant Plans Construction Bid after Plans Complete Construction Starts after Construction Contract Awarded Design-Build Owner Selects DB Designer Part of DB Team Design by DB DB Warrants Plans RFP for Design and Construction Construction may Start upon Contract Award

13 COMPARING PROJECT DELIVERY METHODS Construction Manager at Risk Owner Selects Designer 2 Contracts Design by A/E Owner Warrants Plans CM Input GMP may be Negotiated Before Plans Complete Construction Starts after CM@R Contract Awarded Design-Build Owner Selects DB Designer Part of DB Team 1 Contract=Single Responsibility Design by DB DB Warrants Plans Builder input Design + Construction Cost Proposed & Negotiated Construction may Start upon Contract Award

14 DESIGN-BID-BUILD Determine Need Define Scope of Work Solicit Designer Award Designer Design Project Solicit Contractor Award Contractor Construct Project Project Completion

15 DESIGN-BUILD Determine Need Develop Design Criteria Solicit Design- Builder Award Design- Build Complete Design Construct Project Project Completion

16 DESIGN-BID-BUILD Advantages Familiar process, established procedure Suitable for many projects Checks & balances Legal precedent No legal barriers to procurement & licensing Insurance and Bonding Disadvantages Lowest bidder not always most qualified Owner is referee Spearin Doctrine Slower No innovation Total cost known at end of project

17 DESIGN-BUILD Advantages Single point of responsibility Faster to award Less conflict No Spearin Doctrine (if done right!) Quality & Innovation Cost savings potential Schedule Early knowledge of cost Fast Track Construction Disadvantages New territory, different roles & risks Complex process Designer not under owner s control Design-Criteria Package Best value vs. Lowest price

18 CONSTRUCTION INDUSTRY INSTITUTE STUDY 351 Projects Various types/industry sectors Compared performance between D-B-B, CM at Risk, and D-B Performance evaluated Cost, Schedule, Quality areas

19 CONSTRUCTION INDUSTRY INSTITUTE STUDY Design-Build Performance compared to Design-Bid-Build Unit Cost - 6% less Construction Time - 12% faster Project Time (design and construction) - 33% faster

20 CONSTRUCTION INDUSTRY INSTITUTE STUDY Quality on a 10-point scale - Start-up; Call Backs; O&M; Exterior and Structure; Interior; Environmental; Equipment D-B outperformed D-B-B in every category

21 THE NITTY-GRITTY CCNA FS

22 CCNA AND DESIGN-BUILD CCNA FS Competitive Proposals (Best Value) Qualification-Based Selection (Progressive Designbuild) Defines: design-build firm design-build contract design criteria package design criteria professional design-build

23 CCNA DEFINITIONS Design Build Firm Certified or Registered General Contractor, OR Certified or Registered Building Contractor, OR Engineering firm, OR Architecture firm, OR Landscape Architecture firm.

24 CCNA DEFINITIONS Design-Build Contract One contract for design AND construction of public project Design Criteria Professional Architect, LA, or Engineer Employed by or under contract with agency Prepares Design Criteria Package

25 CCNA DEFINITIONS Design Criteria Package Concise Performance-oriented drawings Performance-oriented specifications Sufficient to permit DB firms to submit a proposal, OR Sufficient to permit negotiations with a DB Not specifications!

26 CCNA - APPLICABILITY TO DESIGN-BUILD CONTRACTS Design Criteria package prepared by Design Criteria Professional Design Criteria Professional not eligible to render services under the design-build contract Non-State agencies must adopt own rules for award of Design-Build contracts

27 CCNA - APPLICABILITY TO DESIGN-BUILD CONTRACTS 2 Selection Processes Competitive Proposal Selection aka Best Value Qualifications Based Selection aka Progressive Design-Build

28 COMPETITIVE PROPOSALS/BEST VALUE Design Criteria Package Short listing based on qualifications Weighted Evaluation Criteria published Competitive technical & price proposals from short listed firms Evaluation of technical and price proposals by design criteria professional

29 COMPETITIVE PROPOSALS/BEST VALUE 3 proposals from each firm Qualifications Statement Technical Proposal Price Proposal

30 SOLICITATION STRATEGIES

31 COMPETITIVE PROPOSALS - OPTIONS One Step Qualifications, Technical & Price Proposal from each firm Two Step Qualifications proposals received and firms short listed Short listed firms submit Technical and Price Proposals

32 COMPETITIVE PROPOSALS A WAR STORY Temporary Jail Housing One Step Design Criteria limiting Form follows Function

33 QUALIFICATION-BASED SELECTION Same announcement and qualifications procedures as A/E selection Same competitive selection as A/E Same Competitive Negotiation requirements as A/E Owner must retain or employ licensed designer to serve as Owner s rep Design criteria package required to negotiate GMP & guaranteed completion time

34 QUALIFICATION-BASED SELECTION/PROGRESSIVE DESIGN-BUILD Evaluation Criteria Specific to Project Capabilities Adequacy of Personnel Past Record Experience of Firm Experience of Key personnel Design of similar projects Construction of similar projects Prior Design-Build experience Same team? Project Approach MWBE standing / participation

35 QUALIFICATION-BASED SELECTION Negotiate Contract Bids from Trades Use of contingency; Owner s/design-builder s Owner Direct Purchases Award Contract Negotiate GMP Open Book Pre-GMP Costs General Conditions Design Cost Cost of the Work Contingencies Negotiate Guaranteed Completion Date

36 SUMMARY

37 DESIGN-BUILD SUMMARY Review of 3 Project Delivery Methods Each has advantages/disadvantages Design-Build CII Study Faster Cheaper Better Quality CCNA Application to Design-Build Solicitation Strategies Best Value Selection Progressive Design-Build

38 QUESTIONS??

39 THANK YOU ALL! Joanne Flick, CPPO, CPPB Purchasing Agent City of Daytona Beach

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

Integrated Project Delivery

Integrated Project Delivery 2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM

More information

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR Moderator: Praful Kulkarni, AIA President/CEO of gkkworks National Chairman of DBIA Presenters: Geoffrey Neumayr, SE Chief Development Officer

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services B-Series B- S E R I E S The documents in the B Series relate to various forms of agreement between an owner and an architect for professional services. B141 Standard Form of Agreement Between Owner and

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

Two Parts of our Discussion

Two Parts of our Discussion Two Parts of our Discussion Part One: The basics (what, why, how, when, etc) An overview of process By no means comprehensive (not enough time) Part Two: From the trenches stuff Not contained in statute

More information

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together This document printed Friday, 04/15/2016 Contracting Opportunity Title:

More information

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous

More information

Department of Public Works Division of Engineering. Nassau County, New York

Department of Public Works Division of Engineering. Nassau County, New York TOWN OF OYSTER BAY Department of Public Works Division of Engineering Nassau County, New York REQUEST FOR PROPOSALS FOR CONSULTANT SERVICES SOLICITATION NO. 2017-12 NOTES: 1. ISSUANCE DATE: Thursday, October

More information

CM AT RISK VS. DESIGN BID BUILD

CM AT RISK VS. DESIGN BID BUILD CM AT RISK VS. DESIGN BID BUILD A TEXAS CASE STUDY ON PROCUREMENT AND IMPLEMENTATION September 28, 2010 Acknowledgement Mike Adams, P.E Executive Director of Engineering and Utilities City of Midlothian

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

Tampa Bay Water is a wholesale water

Tampa Bay Water is a wholesale water FWRJ Utilizing The Engineer-Procure-Construction Management Procurement Process To Get A Bang Without Going Bust Suzannah Folsom, Jonathan Kennedy, Jerry Russell, and Eric Peters Tampa Bay Water is a wholesale

More information

The documents in the A-Series relate to various forms of agreement between an owner and a contractor.

The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A-Series A- S E R I E S The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A101 Owner-Contractor Agreement Form Stipulated Sum Basis of payment is a stipulated

More information

Strategic Management and Project Selection

Strategic Management and Project Selection Strategic Management and Project Selection Strategic Management and Project Selection Maturity of Project Management Overview Criteria for PS Models Nature of PS Models Types of PS Models Uncertainty Analysis

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

BID AND PURCHASING LAWS/BEST PRACTICES

BID AND PURCHASING LAWS/BEST PRACTICES BID AND PURCHASING LAWS/BEST PRACTICES BEFORE YOU DO ANYTHING, ASK YOURSELF THIS QUESTION. Is this purchase or contract for goods or services exempt from the bid laws? Exemptions: Piggy back off a contract

More information

FEMA PA Match Training

FEMA PA Match Training FEMA PA Match Training PROCUREMENT REQUIREMENTS USING CDBG-DR FUNDS Regulatory/Statutory Citations Selection Procedures - (2 CFR 200.319) Conflict of Interest - (2 CFR 200.318) Contract Administration

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

Tsawwassen First Nation Procurement Policy. February, 2010

Tsawwassen First Nation Procurement Policy. February, 2010 Tsawwassen First Nation Procurement Policy February, 2010 TFN Procurement Policy Page 0 of 10 Table of Contents 1. Authority... 2 2. Purpose and Scope... 2 3. Principles... 2 4. Purchasing authority and

More information

How to Prepare a Request for Qualifications (RFQ) Response for A/E & CMR Solicitations

How to Prepare a Request for Qualifications (RFQ) Response for A/E & CMR Solicitations How to Prepare a Request for Qualifications (RFQ) Response for A/E & CMR Solicitations September 29, 2014 at 9:00 am School Board Administrative Building (Auditorium) 1 Who We Are: THE SCHOOL BOARD OF

More information

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005 CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS August 2005 Projects Requiring Licensed Architect / Engineer: *Project Cost Threshold New Construction or Additions $135,000 + Major Repairs

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California. REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE SPARTAN COMPLEX SEISMIC UPGRADE PROJECT SAN JOSE STATE UNIVERSITY ONE WASHINGTON SQUARE, SAN JOSE, CA 95192-0010 The Trustees of

More information

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM Contracting for Architectural and Engineering (A/E) Services Webinar August 30, 2011 10 AM to 11:30 AM 1 Where We're Going Today Webinar Operation - Fred Ward 5 minutes (+/-) Topic Introduction - John

More information

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop SAN DIEGO COMMUNITY COLLEGE DISTRICT SDCCD Design/Build Subcontracting Plan Preparation Workshop April 7, 2015 Welcome Chris Manis Vice Chancellor, Facilities Management Purpose To share information useful

More information

BoardDocs Pro http://www.boarddocs.com/fla/leon/board.nsf/public 1 of 2 3/9/2015 12:39 PM Agenda Item Details Meeting Mar 10, 2015 - Business Meeting Category Subject Type Budget Source 18. Items for Consideration

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Design-Build Highway Projects: A Review of Practices and Experiences Final Report PRC F

Design-Build Highway Projects: A Review of Practices and Experiences Final Report PRC F Design-Build Highway Projects: A Review of Practices and Experiences Final Report PRC 15-53 F Design-Build Highway Projects: A Review of Practices and Experiences Texas A&M Transportation Institute PRC

More information

Project Procurement Considerations in This Market. October 14, 2016

Project Procurement Considerations in This Market. October 14, 2016 Project Procurement Considerations in This Market October 14, 2016 Overview Thank you for being here! Introduction About QBS Colorado Project Delivery Methods Market Information Federal & State Information

More information

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

More information

Office. RdM s confidence and apparent interest in our business operation proved to be real. They became knowledgable

Office. RdM s confidence and apparent interest in our business operation proved to be real. They became knowledgable RdM s confidence and apparent interest in our business operation proved to be real. Office They became knowledgable about how our people interacted internally and made educated alternative suggestions

More information

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build

More information

Jackson Miracle Building Plan Outreach Roundtable. February 14, 2017

Jackson Miracle Building Plan Outreach Roundtable. February 14, 2017 Jackson Miracle Building Plan Outreach Roundtable February 14, 2017 $1.8 billion Expanded Footprint Improved Patient Experience World-Class Facilities Innovative, Leading-Edge Care A Stronger, More Competitive

More information

Operational Procedures Supplementing the JEA Procurement Code

Operational Procedures Supplementing the JEA Procurement Code Operational Procedures Supplementing the JEA Procurement Code Revised: June 2006 April 2011 June 2017 Approved By: Date: Table of Contents PART A: INTRODUCTION... 6 1.0 Intent of Operational Procedures...

More information

Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL

Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL Purchasing Month Jeopardy Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL This game helps individuals learn about Purchasing. We actually pass out the questions prior to the

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

Selection of Contractor Step 5. June 2013

Selection of Contractor Step 5. June 2013 Selection of Contractor Step 5 June 2013 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement of Contractor

More information

Invitation to Negotiate

Invitation to Negotiate Invitation to Negotiate Programming, Design, and Consulting Services Lisa Daws 4/3/2012 CLERKS OF COURT OPERATIONS CORPORATION Table of Contents Agency Background... 3 Statement of Purpose... 3 Scope of

More information

Progressive Design-Build

Progressive Design-Build Progressive Design-Build Progressive Design-Build Design-Build Procured with a Progressive Design & Price A Design-Build Done RightTM Primer 1 Design-Build Progressive Design-build Design-Build Procured

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

February Procurement Overview

February Procurement Overview February 2017 Procurement Overview The Strategic Procurement objective TCHC Strategic Procurement team is committed to open, fair and transparent procurement practices to achieve best value for money in

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS DEPARTMENT SUITE 209S - LOGAN OFFICE CENTER ONE HARBORSIDE DRIVE EAST BOSTON, MASSACHUSETTS 02128-2909 REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT

More information

UNDP Procurement. UNDP Angola Procurement

UNDP Procurement. UNDP Angola Procurement UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Workforce Innovation and Opportunity Act of 2014, Public Law , Sections 107(d)(10)(A), 107(g)(2), and 121(d),

Workforce Innovation and Opportunity Act of 2014, Public Law , Sections 107(d)(10)(A), 107(g)(2), and 121(d), Administrative Policy POLICY NUMBER 097 Title: Program: One-Stop Operator Procurement Workforce Innovation and Opportunity Act (WIOA) Adopted: September 25, 2017 Effective: September 25, 2017 I. PURPOSE

More information

Construction Manager at Risk Delivery Method

Construction Manager at Risk Delivery Method County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing

More information

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &

More information

ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY?

ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY? ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY? Gordon Culp Smith Culp Consulting SmithCulp.com INTRODUCTION Are there alternative methods for delivering water and wastewater treatment

More information

Request for Proposal (RFP) Medical and Dental Supplies RFP No MD-S ADDENDUM NO. 1. July 12, 2016

Request for Proposal (RFP) Medical and Dental Supplies RFP No MD-S ADDENDUM NO. 1. July 12, 2016 Request for Proposal (RFP) ADDENDUM NO. 1 July 12, 2016 Contained herein are the answers to the questions submitted to the Department of Management Services (Department). The Department hereby amends as

More information

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program?

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program? What is the Architectural Experience Program? The Architectural Experience Program (AXP ) is an essential step in the path to becoming an architect. Through the AXP, you will learn about the daily realities

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

OBJECTIVES, SCOPE, AND METHODOLOGY

OBJECTIVES, SCOPE, AND METHODOLOGY OBJECTIVES, SCOPE, AND METHODOLOGY Pursuant to our approved annual plan, we have completed an audit of the University Major Construction Project, specifically Student Academic Success Center Capital Project.

More information

International Airport Expansion Project. Terms of Reference for Legal Advisor

International Airport Expansion Project. Terms of Reference for Legal Advisor A. Background International Airport Expansion Project Terms of Reference for Legal Advisor 1. [ ] International Airport (IA) is a medium size airport with a total passenger per year volume of [ ]. IA has

More information

Kirk W Buffington, CPFIM, CPPO, C.P.M.,

Kirk W Buffington, CPFIM, CPPO, C.P.M., Kirk W Buffington, CPFIM, CPPO, C.P.M., An Overview We will be talking about: The elements of the RFP process Factors determining the selection of the procurement method The elements of risk and how they

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

BID PROPOSAL. For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES. Page Article 1 Bid Recipient...

BID PROPOSAL. For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES. Page Article 1 Bid Recipient... BID PROPOSAL For the Construction of: JEMEZ SPRINGS WATER TANK REHABILITATION TABLE OF ARTICLES Page Article 1 Bid Recipient... 1 Article 2 Bidder s Acknowledgements... 1 Article 3 Bidder s Representations...

More information

REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements

REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements Page 1 of 16 University of Washington REQUEST FOR QUALIFICATIONS FOR Design-Build Services for the University of Washington Seismic Improvements Project No. 205729 Submittal Deadline Date: No later than

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS

More information

Trinity Well Field and Production Facilities Project Management Using CMAR

Trinity Well Field and Production Facilities Project Management Using CMAR Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,

More information

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center Construction 101 C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center This training is provided for educational, compliance and loss-prevention purposes only and, absent the

More information

March 6, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Addendum No. 1/RFP Y15-1023-CH DISASTER DEBRIS MONITORING SERVICES Proposal Opening Date: March 17, 2015 This addendum is hereby incorporated

More information

ADDENDUM NUMBER ONE Clarifications

ADDENDUM NUMBER ONE Clarifications August 25, 2017 ADDENDUM NUMBER ONE Clarifications RE: Interdisciplinary Science and Technology Building VII (ISTB 7) Request for Qualifications No. CMAR 11976 Total pages in this addendum: Five (5) The

More information

Role of Procurement / Purchasing Within the Authority

Role of Procurement / Purchasing Within the Authority Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.

More information

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately $1.2 million a year.

1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately $1.2 million a year. RFP for Information Technology Services- Questions Due: 8/11, 3pm, Answers due 8/16 Questions/Answers 1) Please share the last years expenditure under this contract. Answers: LIPA expects to spend approximately

More information

Ethical Issues in Design-Build (Live Webinar)

Ethical Issues in Design-Build (Live Webinar) PDHonline Course R136W (2 PDH) Ethical Issues in Design-Build (Live Webinar) Instructor: J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax,

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

Subject: Statement of Qualifications for Public Safety Building Design

Subject: Statement of Qualifications for Public Safety Building Design March 5, 2010 Subject: Statement of Qualifications for Public Safety Building Design The City of Porterville seeks Statements of Qualification (SOQ) from qualified architectural and engineering firms for

More information

PROFESSIONAL TECHNICAL ADVISORY BOARD

PROFESSIONAL TECHNICAL ADVISORY BOARD Introduction Design professionals should be selected on specialized experience and qualifications. The Owner needs to utilize a qualification-based selection process to obtain the best firm at the least

More information

REQUEST FOR QUALIFICATIONS DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA REPLACEMENT SCHOOL PROJECT NO

REQUEST FOR QUALIFICATIONS DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA REPLACEMENT SCHOOL PROJECT NO REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA 32725 REPLACEMENT SCHOOL PROJECT NO. 184620 Facilities Planning and Business Services 3750 Olson Drive,

More information

SEATTLE S NEW WMBE INCLUSION PLAN

SEATTLE S NEW WMBE INCLUSION PLAN SEATTLE S NEW WMBE INCLUSION PLAN This past summer Seattle Mayor Mike McGinn announced a new WMBE program for Seattle public works contracts he called an Inclusion Plan to increase women and minority owned

More information

RFQ WEB Advertisement

RFQ WEB Advertisement 165 Capitol Avenue, Hartford, CT 06106 Selection Type: Request for Qualifications (RFQ) Web Advertisement Construction Manager at Risk Adv. No.: Web Advertisement Date: July 18, 2008 General Statement:

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

A Decision Support System for Project Delivery Method Selection in the Transit Industry

A Decision Support System for Project Delivery Method Selection in the Transit Industry A Decision Support System for Project Delivery Method Selection in the Transit Industry A Dissertation Presented by Kamran Ghavamifar To The Department of Civil and Environmental Engineering in partial

More information

DESIGN-BUILD WASHTO WYDOT

DESIGN-BUILD WASHTO WYDOT DESIGN-BUILD An OVERVIEW for STATE DEPARTMENTS of TRANSPORTATION Prepared for WASHTO (Western Association of State Highway and Transportation Officials) WYDOT by Wyoming Department of Transportation June

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Understanding Public Bid Law La. R.S. 38:

Understanding Public Bid Law La. R.S. 38: Understanding Public Bid Law La. R.S. 38:2211-2293 E R I N D A Y, A S S I S T A N T A T T O R N E Y G E N E R A L L O U I S I A N A D E P A R T M E N T O F J U S T I C E Application All Political Subdivisions

More information

PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017

PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017 Michigan Department Of Transportation 3182 (03/17) PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017 Page 1 of 28 PURPOSE The purpose of these guidelines is

More information