Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel

Size: px
Start display at page:

Download "Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel"

Transcription

1 Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel Stephanie Fekete McMillen Jacobs Associates Steve Skelhorn McNally Construction Inc. Tim Langmaid Hatch Mott MacDonald Allen Mitchell Metro Vancouver Abstract. The Port Mann Main Water Supply Tunnel project provides a critical water main crossing of the Fraser River for the owner, Greater Vancouver Water District (Metro Vancouver). The project consists of two 60-metre-deep slurry panel shafts and a 1-kilometre-long, 3.5-metre excavated diameter tunnel located near Vancouver, British Columbia, Canada. The initial tunnel lining is a precast steel fiber reinforced segmental lining. The final lining is a 2.1-metre-diameter welded steel pipe. This paper describes the challenges encountered during tunnel construction and the solutions implemented. Key challenges include earth pressure balance tunnelling at up to 6 bar pressure the highest to date in Canada a water-crossing without surface access for the majority of the tunnel drive, ground freezing from a river platform for a critical TBM intervention, and boring through cobbles and boulders in dense glacial till. INTRODUCTION Metro Vancouver supplies drinking water to 18 municipalities, one electoral district and one treaty first nation, serving a population of more than 2.4 million residents. Water is collected in three mountainous watersheds to the north of the Greater Vancouver area, in southwestern British Columbia, Canada. To supply the growing demands of Metro Vancouver s customers, treated water must be conveyed across two significant water bodies: the Burrard Inlet and the Fraser River. The existing Port Mann water main is one of several key links between the watersheds north of Vancouver and the municipalities south of the Fraser River. The Port Mann Main Water Supply Tunnel (PMMWST) is the first of a series of upgrades, to increase capacity, enhance scour protection, and improve seismic resilience. The new tunnel is 3.5 metres (11.5 ft) in diameter and 1 kilometre (0.6 mi) long. When completed, it will contain a new 2.1 metre (7 ft) diameter steel water main that will help ensure the continued, reliable delivery of drinking water to these municipalities, and will more than double the capacity of the existing 1.2 metre diameter main. Construction of the PMMWST began in the spring of 2011, with ground being broken for the construction of the south shaft. A significant milestone was achieved on June 26, 2015, when Squirrel, 1

2 an earth pressure balance tunnel boring machine (EPB TBM), completed the final advance of the tunnel drive. This paper focuses on the tunnel portion of the work and highlights some of the unique challenges that had to be addressed during design and construction. Project Team The PMMWST project is being constructed by the McNally Construction Inc. Aecon Constructors Joint Venture (MAJV). Construction management is being provided by Hatch Mott MacDonald. The design for the permanent structures as well as engineering services during construction are provided by the Fraser River Tunnel Group (FRTG), a team comprising Ausenco, McMillen Jacobs Associates, and Golder Associates. Project Overview The tunnel was driven between shafts sunk on either bank of the Fraser River, see Figure 1. The launch shaft on the south bank in Surrey is 11 metres internal diameter; the reception shaft in Coquitlam has a 5 metre internal diameter. The two 60 metres deep shafts were constructed using unreinforced slurry diaphragm walls for temporary support. A tremie slab plug was placed before the permanent, cast-inplace, reinforced concrete liners were installed. At both the North and South sites, a valve chamber was constructed integral to the shafts to control water flows through the tunnel pipe. The tunnel is 1 kilometre long with a 3.5 m excavated diameter. The tunnel is located approximately 30 m below the bottom of the Fraser River. The initial tunnel support (precast concrete segments) provided ground support during mining and steel pipe installation. The final lining consists of a 2.1 m diameter steel pipe, which will be the final conduit for drinking water. The tunnel is located below the depth of riverbed scour and is designed to remain functional following a major earthquake. The annulus around the steel pipe is backfilled with cellular (foamed) concrete. Figure 1. Project location. Left: Geographic location; Right: Tunnel alignment 2

3 PROJECT GEOLOGY The tunnel alignment intersects two primary geologic units, as shown in Figure 2, a simplified geologic profile. The geology is typical of the Fraser Valley, with overconsolidated glacial units at depth and overlying normally consolidated fluvial and marine deposits. Tunnel Soil Group 1 (TSG1), a till-like unit, consists of dense glacial material, including silty sand, sand and gravel, and silty clay with some cobbles and boulders. This unit is quite variable with zones of predominantly fined grained materials as well as sand and gravel zones. In general, this unit has low permeability, although this varies in the more granular subunits. TSG2 consists of silty clay, with limited granular materials. TSG2 is a more uniform unit and proved to be an excellent tunnelling medium. Seventy percent (70%) of the tunnelling was in TSG2 (silty clay), with the remaining 30% in TSG1 (till-like soil). The interface between TSG1 and TSG2 was encountered at both the north and south sides of the river. This interface was known to have the potential for nested cobbles and boulders. A Geotechnical Baseline Report was developed during project design, incorporated into the contract documents, and was a valuable tool throughout construction. TUNNEL DESIGN Figure 2. Simplified geologic cross section for the 1 km long Port Mann Tunnel Initial Lining The initial tunnel lining is a universal gasketed ring consisting of six segments (5 + 1 key), each 1 m long and 250 mm thick. The steel fibre-reinforced segments were designed for MAJV by Aecom. To facilitate the installation of a tunnel air lock in the event of a hyperbaric intervention, the segment design incorporated a deep caulking groove around each circumferential joint. The segment moulds were fabricated by Herrenknecht in Germany, before being shipped to Vancouver, where Armtec fabricated the segments a short distance from site. They are designed to have a compressive strength of 50 MPa, and provide temporary support for the installation of the steel water main pipe. Final Lining The final tunnel lining consists of 9.1 metre long sections of welded steel pipe, 2.1 m in diameter and 25 mm wall thickness. Each stick of pipe was installed with a rail-mounted pipe carrier and then circumferentially butt-welded. Once all of the pipe was installed, the tunnel annulus was backfilled with a low strength cellular concrete mix installed via grout ports in the steel pipes. Because of the tunnel grade, several bulkheads were used to divide the tunnel into backfill reaches. 3

4 During design, it was determined that there was a risk of lateral spreading, which could cause permanent ground deformation along both riverbanks towards the river, resulting in significant structural demands on the steel final lining. An extensive geotechnical drilling program combined with seismic analyses and structural modelling were undertaken to complete the design. The results indicated that the tunnel and the steel lining could potentially see large compressive and tensile strains. Special welding and steel material requirements were specified to accommodate these strains. TUNNEL CONSTRUCTION: OVERVIEW Tunnelling was completed on a slight downward vertical alignment, with the 3.5 m diameter Caterpillar EPB TBM working its way from the South Shaft toward the North Shaft on the other side of the Fraser River. The TBM was designed to handle high groundwater pressures, with a 6 bar pressure anticipated. Tunnelling began in February 2014 and was completed in June TBM Launch Both shafts utilized ground replacement to facilitate TBM launch and reception. A rectangular block of concrete panels at break-out and break-in zones was constructed using a hydromill and backfilled with low-strength concrete. To ensure adequate protection from high groundwater pressure, a steel launch can, from which to launch the TBM, was installed with three inflatable Bullflex seals as well as a rubber gasket (or wiper seal) (Figure 3). A steel jacking frame was set up at the base of the shaft and used to advance the TBM until enough segmental lining had been installed to resist the full thrust of the machine. Figure 3. TBM launch: approach to manage high groundwater pressures. Left- South Shaft configuration for launch. Right- Launch can lowered by crane for installation. TBM Design Because of the risks associated with a cutterhead entry under the anticipated conditions (6 bar), the primary machine design requirement was to mitigate or eliminate the need for a compressed air intervention during the 1 kilometre drive. The following measures were incorporated into the machine s design: 4

5 1. A combination of rippers, scrapers, and discs were included in the cutterhead design to maximize the possibility of performing the drive without having to change tools. A total of 36 rippers were installed on the head and 4 disc cutters were added to the periphery. Figure 4 shows the ripper design; Figure 5 shows the TBM cutterhead configuration. Adapter boxes allowed for the interchange of rippers with disc cutters along two spokes; however, this alternative configuration was not used. 2. Tool wear indicators were also installed and monitored from within the machine. All tools were back-loading to enable tool changes from within the plenum if necessary. 3. Robust grizzly bars were welded in place to prevent oversized material from entering the head and jamming the screw. 4. Flood gates were not to be used; this was deliberate to minimize the potential for mechanical related failures. 5. Hard wearing plates were welded to the face of the machine. 6. A TBM mounted airlock was eliminated to maximize clearance in the TBM for a larger screw conveyor. A tunnel airlock was to be utilized if a compressed air intervention was needed. Figure 4. Ripper teeth with state-of-the-art wear protection Figure 5. Squirrel cutterhead configuration 5

6 Notwithstanding the above, the TBM was designed to allow safe hyperbaric entry should it be necessary. Compressed air dive crews worked with the TBM manufacturer through the design phase to ensure alignment with all components. The TBM gantry was designed to be easily removable to facilitate installation of an in-tunnel airlock as close to the face as practical. The rippers were generally effective in breaking up the ground so that soil and rock fragments could pass through the grizzly bars into the excavation chamber. In the first 800 m, tool wear was minimal with the tools showing only 10% wear. The following 200 m saw increased wear, with some rippers displaying very significant wear and others minimal wear. Based on the results of the inspections, the cutterhead tools were partially replaced on two occasions and fully replaced on a third. Tunnel Progress and Statistics Tunnelling began February 24, 2014, and was completed June 26, Progress for the first 100 m was slow because of the combination of difficult ground conditions, progressive installation of the TBM equipment at the base of the South Shaft, and some mechanical issues. This segment took 4 months to complete. There was a strong contrast between the TBM progress under the most favorable and least favorable tunnelling conditions. The interface of TSG1 and TSG2, with its concentration of cobbles and boulders, made for the most challenging. Advance rates in TSG1 (till-like soil) were typically slow, with an average of 5 m per day (or 2 to 3 m per 12-hour shift). When the TBM encountered greater resistance (typically cobbles or boulders), advance rates further reduced to 0 to 5 mm/min, with several 1-metre shoves taking 3 hours each to complete. Tunnelling in full-face TSG2 (silty clay), on the other hand, was excellent and resulted in high advance rates. A typical day in TSG2 saw 18 metres of tunnelling completed (9 m per 12 hour shift) with advance rates of 100 mm/min on average and up to 200 mm/min. Tunnel Breakthrough Although highly anticipated, the TBM breakthrough was less visually dramatic than is typical. In order to balance the significant chamber pressure, the North Shaft was backfilled to above the tunnelling horizon and filled with water. This allowed the machine to enter the shaft with minimal change in external pressures. The tunnel eye was heavily reinforced with rebar, which meant that missing the 70 mm alignment tolerance could have had catastrophic consequences. The as-built tunnel alignment was verified continually using the tacs guidance system and was also confirmed with a gyro-theodolite survey on three occasions by the MAJV and another two times by the Owner s third-party consultant. The backfill was removed and the shaft dewatered to reveal that Squirrel had in fact reached its destination. The cutterhead and forward shell were removed by crane via the North Shaft (with just enough room) while the sacrificial skin around the stationary shield was grouted in place. The remainder of the TBM was disassembled and removed via the South Shaft. Figure 6 shows a schematic of the TBM entering the backfilled North Shaft and then beginning disassembly. 6

7 Figure 6. TBM Breakthrough and disassembly PROJECT-SPECIFIC CHALLENGES AND SOLUTIONS Shaft Launch Several TBM launch challenges had to be overcome because of the tunnel depth as well as limited workspace at the base of the South Shaft. Worker access to the base of the shaft was typically via a scaffolding stair tower, complemented by a crane and man-basket. At only 11 m in diameter, the launch shaft made for a very constrained work site. Typically in shaft launches, a starter tunnel is excavated to provide extra room for equipment. However, because of the seismic requirements of the project as well as the high groundwater level, a starter tunnel could not be constructed. Therefore, the TBM had to be assembled one gantry car at a time as the machine advanced and more space became available. This assembly process was lengthy as each time a new section of the TBM backup was lowered down to tunnel elevation, new temporary configurations had to be implemented for the utility connections and various tunnel operations, such as muck handling. The TBM umbilicals consisted of electrical and hydraulic connections, which allowed the launch of the TBM while retaining some of the systems, such as the grouting and bentonite systems on the surface. Additionally, the launch through the headwall into the 5.5 bar ground presented its own challenge. The TBM was designed with a double screw conveyor to allow the pressures to be reduced before discharging; however, on launch there was insufficient clearance for the double screw. To allow a full pressure launch, a Putzmeister pump was utilized. This was bolted to the outlet of the first half of the screw conveyor and acted as a pressure reducing valve. The system was successful, and the launch under pressure was achieved with no ground loss. The system did have some issues in that clearance was reduced for installing the segments, and two TBM operators were required for the launch one on the TBM and one on the pump (see Figure 7). The pump also reduced the effective advance of the TBM. Large cobbles could not pass through the pump and were collected in a screen box at the screw discharge. With the number of cobbles encountered, this resulted in the screen requiring cleaning out every 200 mm or so. 7

8 Figure 7. Initial TBM configuration. No TBM backup installed. First part of screw conveyor in place with Putzmeister pump for use during launch. Small-diameter EPB TBM Tunnelling with a small-diameter EPB TBM at high pressure certainly has its challenges. The 3.5 m excavated diameter TBM is significantly smaller than what is used for transportation tunnels (typically 5 to 7 m diameter). Additionally on the PMMWST project, clearances were further reduced by the thicker than normal segments (250 mm) and the large screw size. From the launch, it became obvious that working in such a confined space makes every task more difficult (Figure 8), be it lack of access or difficult access, limitations on number of construction activities that could occur simultaneously (often allowing only one at a time), number of workers, or equipment size. Other limitations of smaller TBMs, such as reduced thrust and torque capabilities and reduced ability to handle larger cobbles and rock fragments, make tunnelling in glacial soils even more challenging than typical. 55cm Figure 8. View inside the TBM gantry a tight working space. High External Pressures To balance the external soil and groundwater pressures, the TBM had to be operated at high chamber pressures. TBM excavation chamber pressures up to 6 bar occurred during tunnel excavation where the 8

9 full hydrostatic pressure was realized. For a portion of the drive in the clay-rich TSG2 material, the TBM was operated typically in the 3 to 4 bar range because of slower groundwater recharge. In the TSG1 material, recharge was generally rapid and the TBM had to be operated at the full EPB pressures with a target of 0.3 bar above ambient, typically around 5.6 bar. This was very challenging, with the nature of the ground, cobbles and boulders combined with the high pressures. Large spikes in pressures were common and very rapid drops in pressures were observed when clearing cobbles through the screw conveyor. Ground conditioning was utilized throughout the zone with polymer injection used in TSG1. The high hydrostatic pressures also affected the TBM design. The sealing systems needed to cope with the high pressures and needed to be fail-safe to lock pressures in the event of a power failure. This presented some challenges in the initial part of the drive with potential over pressurization of the seals during mining. Additional seal pressure monitoring systems were installed along with safeguards to trip grease pumping systems should pressure spikes be observed. Tunnelling through Difficult Geologic Interfaces The TBM saw considerably lower advance rates in the more challenging geologic conditions. The interface of TSG1 and TSG2, with its concentration of cobbles and boulders, made for the most challenging. The first time the interface was encountered (near the South Shaft, as the TBM was driving from TSG1 into overlying TSG2 unit), the TBM was able to pass through with minor delays. More significant delays occurred closer to the North Shaft, where the TBM returned from TSG2 back into TSG1. Because of the near flat geologic contact, the length of tunnel intercepting the contact was much greater than at the southern contact. A number of free-air interventions were performed at the TSG1/TSG2 interface, with the majority of these occurring in the last 200 m of tunnelling. The interventions were required for various reasons, including TBM repair, replacing cutterhead tools, breaking up boulders/cobbles ahead of the face, and unclogging the grizzly bars/cutterhead openings. During project planning, it was not assumed that the ground behaviour would be favorable enough (i.e., firm ground with minimal water inflow) to perform free-air interventions, so preparation had been made for a hyperbaric intervention. In the end, no hyperbaric interventions were performed. An intervention occurred at Ring 793 that was an exception to the others. Here, a combination of less favourable geology and machine condition would not allow for a free-air intervention. The project team evaluated the benefits and risks associated with each of the alternatives. In the end, ground improvement by ground freezing from an in-river platform was selected as the best method to undertake the critical repairs needed. The river platform was constructed to conduct the ground freeze, and boreholes were drilled to below tunnel depth. Moretrench, a subcontractor to MAJV, performed the design and implementation of the ground-freezing scheme. A liquid nitrogen system was implemented with barges of liquid nitrogen regularly replenishing the on-platform tanks. Once the ground freeze was established, the intervention was conducted to perform repairs, unclog the screw conveyor, and change the cutterhead tools. This intervention was the most significant delay during tunnelling and lasted 6 months. Grouting Annulus grouting (between the segmental lining and the ground) was initially conducted via the tail shield. Because of issues with grout line blockages, and the risk in cleaning these out at high groundwater pressures, this was soon aborted and annulus grouting was completed by injection 9

10 through the precast segments for the majority of the tunnel drive. For each advance, ball valves were installed, approximately at the spring line on either side of the tunnel, and drilled out. Grout holes were added to every segment, but these were blind holes and required drilling at the TBM once the selected ports were identified. A two-part cementitious grout (2 MPa design strength) was injected at pressure. Hydrophilic O-rings were installed into the drilled-out grout ports at a later date. These were highly effective in reducing any leakage occurring from the grout ports and greatly reduced tunnel water inflow. CONCLUSIONS This paper outlines some of the practical engineering solutions developed to tunnel through complex geology at exceptional depths and high hydrostatic pressure. Numerous innovative approaches were taken in customization of TBM and tunnelling systems to suit the aforementioned conditions. The design of the TBM, emergency systems, procedures for high-pressure compressed air interventions, and specialized launch and removal procedures are just some of the details that were analyzed in detail. Lessons Learned The Port Mann tunnel project provides a wealth of knowledge and experience for tunnelling in challenging ground conditions, which will be invaluable for other tunnel crossings of the Fraser River and the Burrard Inlet that are currently in the planning or design stage. The Port Mann experience has provided a number of key learning points: It is worthwhile to invest time and resources in risk management measures to reduce the likelihood of interventions. Despite this effort, the need for interventions can never be fully eliminated and should be allowed for. Launching the TBM from a small shaft without a starter tunnel is challenging and time consuming, but with thoughtful TBM design and configuration, the challenge can be overcome. When planning to tunnel at high pressures, it is prudent to prepare for high pressure compressed air interventions. However, there are alternatives, which should also be considered at the design and planning stages. The possibility of safe, free-air interventions should not be discounted, even with potential pressures of up to 6 bar. The tunnelling fraternity must work to educate owners and designers of the benefits of a larger tunnel during construction tunnels should be sized to enable safe and efficient construction, not just for their intended final purpose. While the project did encounter challenges during tunnelling, the diligence given to these technical aspects certainly paid off and resulted in the successful execution of a tunnel under the Fraser River at the highest EPB pressure seen to date in Canada. Acknowledgments The authors would like to thank Metro Vancouver for its permission to publish this paper and for providing its support. 10

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

TBM Selection and Specification

TBM Selection and Specification By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements

More information

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc. Pipejacking Tunnel Boring Machines TBMs Michael Frenke, LOVAT Inc. Pipejacking Tunnel Boring Machines (TBMs( TBMs) Introduction Pipejacking Sequence TBM Design Features Types of Jacking Pipe Pipejacking

More information

Liquid Waste Coordination Committee

Liquid Waste Coordination Committee Annacis Island Wastewater Treatment Plant Outfall Project Liquid Waste Coordination Committee FOR LWCC BY KEN MASSÉ. 19 JANUARY 2017 Ken Massé, P.Eng. METRO VANCOUVER April 3, 2017 CONTRACTOR INFORMATION

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

TBM rescue projects using shafts and ground freezing

TBM rescue projects using shafts and ground freezing TBM rescue projects using shafts and ground freezing Dipl.-Ing. Michael Löffler, Dipl.-Ing. Helmut Haß (CDM Consult GmbH, Germany) Dipl.-Ing. Thomas Ahlbrecht (Deilmann-Haniel Shaft Sinking GmbH, Germany)

More information

From Colonia Jardín to Cuatro Vientos

From Colonia Jardín to Cuatro Vientos 60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was

More information

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY CROSSRAIL INFORMATION PAPER TUNNEL CONSTRUCTON METHODOLOGY This paper sets out the proposed Crossrail tunnel construction strategy and methodology. It will be of particular relevance to those in the vicinity

More information

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout Brendan P. Harkins 1, E.I.T.; Dominic M. Parmantier 2, M. ASCE, P.E. 1 Project Engineer, Condon-Johnson & Associates,

More information

Tel: Neil: Tony: Website:

Tel: Neil: Tony: Website: Australian Tunnelling Services are a consortium that has been formed to offer specialist underground services to both clients and contractors in the Civil Engineering, Mining & Building Industries. The

More information

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City

More information

Shield TBM risk model based on Bayesian networks applicable in design stage

Shield TBM risk model based on Bayesian networks applicable in design stage Shield TBM risk model based on Bayesian networks applicable in design stage *Heeyoung Chung 1), In-Mo Lee 2) and Jeongjun Park 3) 1), 2) School of Civil, Environmental and Architectural Engineering, Korea

More information

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore

More information

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA Miranda Roman D. *, LaFaso Edward Iseki, Inc. 7518 Carroll Road, San Diego, Calif. 92121-2402 USA This paper will discuss the

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

D7: TUNNEL CONSTRUCTION AND METHODOLOGY HIGH SPEED TWO INFORMATION PAPER D7: TUNNEL CONSTRUCTION AND METHODOLOGY This paper outlines the proposed tunnelling methodology. It will be of particular interest to those potentially affected by the

More information

EOSC 547: Tunnelling & Underground Design

EOSC 547: Tunnelling & Underground Design EOSC 547: Tunnelling & Underground Design Topic 4: Tunnelling Methods Soft Ground TBMs 1 of 41 Tunnelling Grad Class (2017) Dr. Erik Eberhardt Excavation Methods Selection of a tunnelling system (i.e.

More information

CPM Concrete Drainage Systems

CPM Concrete Drainage Systems CPM Group Ltd offer a complete range of precast concrete manhole units from DN 900 to DN 4000 in varying depths with tongue and groove joints. A djusting units Ductile iron cover & frame Cover slab DN1200

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) Topic 5 Tunnelling 1. Introduction Tunnels can be defined as underground passages constructed for the purpose of transportation connection between two points. 2. Type of Tunnels There are many types of

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

is a possibility of the existence of permafrost as a result

is a possibility of the existence of permafrost as a result 111.2 CERTAIN ASPECTS OF ALASKA DISTRICT ENGINEERS EXPERIENCE IN AREAS OF MARGINAL PERMAFROST E. L. Long In nearly twenty years of engineering and construction experience in Alaska, the Alaska District

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

Hardrock Tunnel Boring Machines

Hardrock Tunnel Boring Machines Bernhard Maidl, Leonhard Schmid, Willy Ritz, Martin Herrenknecht Hardrock Tunnel Boring Machines In co-operation with Gerhard Wehrmeyer and Marcus Derbort -=rnst & Sohn '-A Wiley Company Contents 1 Historical

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Evergreen Line Rapid Transit Project

Evergreen Line Rapid Transit Project Evergreen Line Rapid Transit Project Burnaby, Port Moody, and Coquitlam, BC Completed in December 2016 Canadian Consulting Engineering Awards 2017 Project Category: B. Transportation Canadian Consulting

More information

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria

More information

STANDARD SPECIFICATIONS SECTION JACKED CASING

STANDARD SPECIFICATIONS SECTION JACKED CASING STANDARD SPECIFICATIONS SECTION 02315 JACKED CASING PART 1 - GENERAL A. Description Tunneling method by jacked casing, directional drilling, or a tunnel boring machine, for highway, railroad, creek, and

More information

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure Tunnels content of the lecture 1st Hour Tunnels Immersed tunnels Comparison Bored Tunnels (short) Land tunnels 2nd Hour Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield

More information

Design Data 4M. Jacking Concrete Pipe

Design Data 4M. Jacking Concrete Pipe Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Risk Management based Ground deformation monitoring during Queens Bored Tunnels project

Risk Management based Ground deformation monitoring during Queens Bored Tunnels project Risk Management based Ground deformation monitoring during Queens Bored Tunnels project Michael MOONEY a, Jacob GRASMICK a, Eric PRANTIL b, Andrew THOMPSON b a Civil and Environmental Engineering, Colorado

More information

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei

More information

Design Data 4. Jacking Concrete Pipe

Design Data 4. Jacking Concrete Pipe Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.2 MICRO TUNNELING 7.2.1 General Where indicated on the Drawings, or where field

More information

Tunnel Boring Machines

Tunnel Boring Machines Tunnel Boring Machines IMIA WGP 60 Michael Spencer, Zurich London (Chairman) Alessandro Stolfa Generali Heiko Wannick Munich Re Ronan Gallagher Allianz John Forder Willis Beat Guggisberg Allianz Eric Bentz

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Combined Pile Foundation System for a Residential Complex

Combined Pile Foundation System for a Residential Complex Combined Pile Foundation System for a Residential Complex Alvin K.M. Lam, Geotechnical Engineer, Ove Arup & Partners Hong Kong Limited, Hong Kong, China; email: alvin.lam@arup.com Daman D.M. Lee, Civil

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

Pipe Jacking Association An introduction to pipe jacking and microtunnelling Pipe Jacking Association An introduction to pipe jacking and microtunnelling Copyright Pipe Jacking Association ISBN 978-1-5272-0341-9 All rights reserved. No part of this publication may be reproduced,

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

Texas-Sized Challenges

Texas-Sized Challenges Aerial view of the City of Austin s Water Treatment Plant No. 4 in northwest Austin near the intersection of RM 620 and Bullick Hollow Road. cover story Delivering Water Provides Texas-Sized Challenges

More information

P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer

P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer 2. Field Program 2.1 Health and Safety Plan Prior to beginning the field program, CH2M HILL developed a health and safety plan (H&SP). The H&SP provided a summary of potential physical hazards that could

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

Underground Construction Technology

Underground Construction Technology Underground Construction Technology Course Lectures Part 4.2 Permanent support Dr Ákos TÓTH 1 Segmental Lining in TBM Tunnelling Segmental lining is the support system for shield TBM excavated tunnels.

More information

SECTION XXXX POLYMER CONCRETE PUMP STATIONS

SECTION XXXX POLYMER CONCRETE PUMP STATIONS SECTION XXXX POLYMER CONCRETE PUMP STATIONS PART 1 GENERAL 1.1 SUMMARY A. This specification shall govern for the furnishing of all work necessary for installation of polymer concrete pump stations to

More information

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK or our breadth of capability. Of all the storage tank manufacturers doing business today, no other offers Caldwell s range of capability. We are the only manufacturer

More information

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective Purdue Geotechnical Society Workshop Digging Deep April 8, 2011 Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective David Chapman, P.E. Lachel & Associates, Inc. Morristown, NJ Hudson

More information

Description Unit Quantity Rate Kshs. Amount Kshs.

Description Unit Quantity Rate Kshs. Amount Kshs. BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling Glen Frank, JayDee Contractors, Inc., Seattle, WA Ehsan Alavi Gharahbagh, The Pennsylvania State University, University Park, PA Michael

More information

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar Advances in Hollow Thread Bar Micro Pile Installation Techniques, Equipment, Materials, Testing and Monitoring ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems

More information

Performance review of a pipe jacking project in Hong Kong

Performance review of a pipe jacking project in Hong Kong Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte

More information

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Joseph Donohue 1, R. Greg Eberhardt 2 and Ildiko Juhasz 3 1 Associate, Arup 2

More information

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul Proceedings of the 2 nd World Congress on Mechanical, Chemical, and Material Engineering (MCM'16) Budapest, Hungary August 22 23, 2016 Paper No. MMME 113 DOI: 10.11159/mmme16.113 Analysis of the EPB-TBM

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

Monitoring Earth Pressure Balance Tunnels in Los Angeles

Monitoring Earth Pressure Balance Tunnels in Los Angeles Monitoring Earth Pressure Balance Tunnels in Los Angeles Thomas M. Saczynski 1, M ASCE P.E., Michael Pearce 2, M ASCE, P.E., G.E., and Amanda Elioff 3, M ASCE, P.E. 1 Sr. Manager, KBR,790 Colorado Blvd

More information

CONSTRUCTION OF TWO MICROTUNNEL ACCESS SHAFTS USING THE CUTTER SOIL MIX (CSM) METHOD IN THE SAN JOAQUIN DELTA, CALIFORNIA

CONSTRUCTION OF TWO MICROTUNNEL ACCESS SHAFTS USING THE CUTTER SOIL MIX (CSM) METHOD IN THE SAN JOAQUIN DELTA, CALIFORNIA CONSTRUCTION OF TWO MICROTUNNEL ACCESS SHAFTS USING THE CUTTER SOIL MIX (CSM) METHOD IN THE SAN JOAQUIN DELTA, CALIFORNIA Eric S. Lindquist, Berti-Lindquist Consulting Engineers, Moraga, CA, USA John Morgan,

More information

Section 401. PIPE CULVERTS

Section 401. PIPE CULVERTS 401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials

More information

Previous Tunnel News

Previous Tunnel News Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE TUNNEL LINER PLATE FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE SAFE ECONOMICAL VERSATILE SIMPLE EASY TO HANDLE READILY AVAILABLE All underground work can be undertaken from within the assembled shell.

More information

Prof. Eng. Daniele PEILA

Prof. Eng. Daniele PEILA Course in Tunnelling and Tunnel Boring Machine Kurs w zakresie drążenia tuneli oraz maszyny drążącej TUNNEL FACE STABILITY WITH MECHANIZED TUNNELING GENERAL CONCEPTS Prof. Eng. Daniele PEILA 0 When tunneling

More information

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project Noah Johnson The Robbins Company ABSTRACT: The San Francisco Central Subway project is a challenging modern

More information

16. Design of Pipeline Structures.

16. Design of Pipeline Structures. 16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.

More information

Principles for Tunnel Design. 20th to 21st April 2017 Kuala Lumpur

Principles for Tunnel Design. 20th to 21st April 2017 Kuala Lumpur 20th to 21st April 2017 Kuala Lumpur Mechanized Tunneling (TBM and Support Systems) Thorsten Tatzki Herrenknecht Asia Headquarters Pte. Ltd. Introduction: General Overview Shield Machines and Tunnel Boring

More information

Steel screw settlement reduction piles for a raft foundation on soft soil

Steel screw settlement reduction piles for a raft foundation on soft soil Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Alexei Murashev Opus International Consultants Limited, Wellington, New Zealand. Keywords: piled raft, settlement

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 Alberta Transportation Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 17.0 MAIN CANAL CONVEYANCE STRUCTURES 17.1 General Conveyance structures typically employed on main

More information

EPB TBM UNDER THE CITY CENTRE OF VANCOUVER: RISK MANAGEMENT AND SETTLEMENT CONTROL

EPB TBM UNDER THE CITY CENTRE OF VANCOUVER: RISK MANAGEMENT AND SETTLEMENT CONTROL EPB TBM UNDER THE CITY CENTRE OF VANCOUVER: RISK MANAGEMENT AND SETTLEMENT CONTROL Andrea Ciamei and M arco M occichino S.E.L.I., Società Esecuzione Lavori Idraulici Spa Piazza G. Marconi 26/c 00144 Rome

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

Foundation Innovations Ensure Successful Bridge Replacement

Foundation Innovations Ensure Successful Bridge Replacement COVER STORY Foundation Innovations Ensure Successful Bridge Replacement Rhode Island s new $163.7 million, 2,265 ft (690 m) long, fourlane Sakonnet River Bridge sits just south of the existing bridge in

More information

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION TUNNELING & UNDERGROUND CONSTRUCTION THE OFFICIAL PUBLICATION OF UCA OF SME WWW.TUCMAGAZINE.COM VOLUME 1 NO 2 JUNE 2007 SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM Tunnel Demand Forecast Ground

More information

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Qing-Long Cui, Ph.D. student Co-authors: Ye-Shuang Xu, Shui-Long Shen*, Huai-Na

More information

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur

More information

A.2.a Random Riprap... Table

A.2.a Random Riprap... Table 3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide

More information

A case study of twin bored tunnelling under mixed-face soil - Bendemeer MRT station project (Downtown Line 3), Singapore

A case study of twin bored tunnelling under mixed-face soil - Bendemeer MRT station project (Downtown Line 3), Singapore Japanese Geotechnical Society Special Publication The 15th Asian Regional Conference on Soil Mechanics and Geotechnical Engineering A case study of twin bored tunnelling under mixed-face soil - Bendemeer

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield tunnelling

Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield tunnelling 2do Congreso Latinoamericano de Túneles y Espacios Subterráneos LAT 2015 28 de septiembre de 2015 Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield

More information

Take Me to the Other Side:

Take Me to the Other Side: Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional

More information

Solutions for tunneling and mining TBM. Expanding Horizons Underground

Solutions for tunneling and mining TBM. Expanding Horizons Underground Solutions for tunneling and mining TBM Expanding Horizons Underground Cost Effective Solutions Partnership MEYCO Global Underground Construction (MEYCO) is a world leader in the provision of reliable,

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Geo-Strata. Urban Geotechnical ALSO. Building Careers and Developing Leadership. May/June 2014

Geo-Strata. Urban Geotechnical ALSO. Building Careers and Developing Leadership. May/June 2014 Geo-Strata May/June 2014 Urban Geotechnical ALSO Building Careers and Developing Leadership Ground Freezing in a Congested Urban Area By Paul C. Schmall, PhD, PE, D.GE, F.ASCE, and Joseph A. Sopko, PhD,

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

Drilled Shaft. Inspection. HQ Construction Office HQ Geotechnical Division

Drilled Shaft. Inspection. HQ Construction Office HQ Geotechnical Division Drilled Shaft Inspection HQ Construction Office HQ Geotechnical Division Drilled Shafts: What are Drilled Shafts Drilled Shaft Construction Challenges of Drilled Shaft Construction The WSDOT SHAFT Special

More information

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel. Rock Tunnel Engineering INTRODUCTION Tunnel a hole in the ground to provide for desired movement or as mobility channel. Serves as highway, railroad, pedestrian passageway, water conveyance, waste water

More information

Water Well Decommissioning Guidelines

Water Well Decommissioning Guidelines Water Well Decommissioning Guidelines Approval Date: June 1, 2007 Effective Date: September 10, 2007 Approved By: Gerard MacLellan Version Control: This is a new guideline I. Introduction The Water Well

More information

Pipetron Tunnel Construction Issues

Pipetron Tunnel Construction Issues Pipetron Tunnel Construction Issues James E. Friant Colorado School of Mines and Excavation Engineering Associates, Inc., 1352 SW 175th St., Seattle, WA 98166 Robert A. Bauer and David L. Gross Illinois

More information

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine. Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine. Alan Naismith 1, Dr Graham Howell 2, Howard Marsden 3. 1 SRK; 2 SRK; 3 Petra Diamonds (previously,

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5 Turbine Foundation Construction Method Statement Copyright ESB International Limited, all rights reserved. Farm Contents 1 Introduction

More information

Relining Project in Turkey proves successful By Hans Juergen Koenig and Jens Kirste

Relining Project in Turkey proves successful By Hans Juergen Koenig and Jens Kirste Relining Project in Turkey proves successful By Hans Juergen Koenig and Jens Kirste The Trolining process for no-dig pipe renovation has proven successful for decades. Lately, the grouted-in-place pipe

More information

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11 CHAPTER 11 INTRODUCTION The open-trench method of placing underground conduits is commonly used on new construction of culverts, sewers and underpasses. Interference with traffic, as well as inconvenience

More information