Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

Size: px
Start display at page:

Download "Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines"

Transcription

1 Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Joseph Donohue 1, R. Greg Eberhardt 2 and Ildiko Juhasz 3 1 Associate, Arup 2 Senior Engineer, Arup 3 Principal Engineer, Parsons Brinckerhoff Abstract: The Tunnel Boring Machine (TBM) launch box for the Brisbane AirportlinkM7 consists of diaphragm walls with the use of both steel and reinforced concrete for the various levels of temporary and permanent props and whalers. The launch box was constructed in a top-down sequence to a depth of approximately 23m, which resulted in the 1.2m thick concrete sections being heavily reinforced. Glassfibre reinforcement was required in the soft-eyes to allow for the launching of the two TBMs through the headwall. Under lateral loading predominately arising from soil and water pressure, the glass-fibre reinforcement needed to resist the short-term loading until the TBM s were launched. The permanent regions of the diaphragm wall above and below the soft-eyes required steel reinforcement to satisfy the long-term loadings and to meet the 100 year design-life requirements. The use of the glass-fibre reinforcement entailed several design issues that had to be dealt with, including: a low modulus of elasticity and shear strength of the material, creep effects and limited ligature shapes. Three-dimensional analysis was undertaken to optimise the headwall design in both the short and long-term conditions. The quantity of reinforcement, which was required to withstand the temporary loading, has led to significant construction constraints, especially with congestion of the GFRP and steel reinforcing at the interfaces between the soft-eyes and the permanent headwall. Careful detailing, a close working relationship with the contractor and a strong, engineering site-presence during construction, allowed for the successful integration of the design and constructability requirements. Keywords: AirportlinkM7, Soft-Eye, Headwall, GFRP 1. Introduction This paper discusses the soft-eye headwall for Brisbane AirportLinkM7 Tunnel the largest infrastructure project in Australia. The detailed design of the soft-eye headwall had to incorporate many considerations including the construction sequence, which had numerous load-combination cases under both short and long-term conditions. The construction sequencing incorporated ground improvement behind the headwall, in the upper layers of soil strata, which reduced the lateral loading and assisted with launching the TBMs. Another important consideration was accounting for the design issues which were specific to the glassfibre reinforcement. The quantity of reinforcement, which was required to withstand the temporary loading, resulted in the need for careful detailing of the GFRP and steel reinforcing at the interfaces between the soft-eyes and the permanent headwall. 2. Project description AirportlinkM7 Tunnel, Brisbane, QLD The AirportlinkM7 Tunnel is a 6.7km, multi-lane road connecting Brisbane s inner-northern suburbs and the north-south CBD bypass tunnel with the airport and the north-south Gateway Motorway. The tunnel has three connections to the existing surface-road network. Thiess-John Holland JV were appointed as principle contractors in May 2008 following the successful tender-bid; Parsons Brinckerhoff-Arup JV were the design team. The project s completion date was set at June These tight timelines meant that the design was required to progress in an accelerated schedule to keep pace with construction. Major design inputs and issues such as: design criteria, soil testing, construction loads and sequencing etc had to be developed and updated without any delay to the construction schedule. The authors were structural engineers and design lot leaders for cut and cover structures on the Toombul or Eastern Connection of this project. These structures were on the critical path due to their temporary use

2 as the launch box for the tunnel boring-machines (TBMs), and also served as the receiving pit for two large, reinforced-concrete culverts that were jacked under the North Coast Rail Line and airport rail link. 3. TBM Launch Box The focus of this discussion is on the headwall of the TBM launch box, which consisted of reinforcedconcrete diaphragm walls with in-situ roof, base and intermediate slabs. It was constructed by a top-down construction technique utilising two layers of temporary steel props and whalers between the intermediate and base slabs. The roof and intermediate slabs featured large temporary voids to allow segments of the TBM to be lowered into position. In cross-section, the TBM launch box incorporated a haunched base-slab to accommodate the TBM outline. The road level is at a higher elevation than the TBM invert, and the haunched profile of the base slab reduced the vertical span-length of the typical, diaphragm wall-panels. The diaphragm wall at the headwall needed, however, to span to below the invert of the TBM. Figure 1 shows a section through the portal wall with two layers of temporary props and whalers between the intermediate level slab and base slab. Figure 1. Section through headwall with two layers of temporary support. After the TBM launch, a non-structural infill was provided in the base slab up to the underside of pavement level. The upper layers of soil strata, to a depth of 12m at the headwall, were soft silty-clays with clayey-gravels and very stiff-to-hard silty-clays below. Low to medium strength siltstone was present towards the bottom of the soft-eye region at close to the final road level. The typical, diaphragm wall-panels for the TBM launch box were 1200mm thick. The objective to maintain the same thickness of diaphragm wall-panels at the headwall to span the extra length, even for the shortterm design-life, was a challenge during the design phase.

3 3.1 Soft-eye Headwall In the soft-eye regions of the headwall, glass-fibre reinforced polymer (GFRP) bars were used to provide zones without steel reinforcement to allow the TBMs to break-through. The soft-eyes were centred about the TBMs and had a clear diameter of 13.10m. This provided construction tolerance and clearance between the steel reinforcement and the 12.48m diameter TBM cutter-head. To reduce the lateral loading and the corresponding bending effects on the portal wall and, to assist with launching the TBMs, ground improvement was carried out behind the portal wall. See Figure 1. The extent of this ground improvement had, however, to be limited due to the proximity of property boundaries and a newly-diverted sewer line. 3.2 Factors Affecting Construction Sequence The timing of the works meant that the ground improvement behind the portal wall could not be completed until after the sewer line had been installed; this sewer diversion was required to enable the TBM launch box diaphragm-walls to be constructed. A further input into the construction sequence was the need for a permanent overland water-flow path diversion, which was incorporated into the roof slab of the TBM launch box at the opposite end to the headwall. This was required to be operational to enable the commencement of early works for the jacked box under the North Coast Rail Line and airport rail link. Another significant factor on the construction sequence was the lead times for the GFRP bars and, especially, for large diameter bars and bent bars. These factors contributed to the headwall diaphragmwall panels being constructed last for the TBM launch box, although the design was undertaken in parallel with the TBM launch box diaphragm-wall and roof slab. 4. Design Criteria Over the extent of the soft-eyes, the glass-fibre reinforcement had to satisfy the short-term loading until the TBM s were launched. Steel reinforcement was utilised in the permanent regions above and below the soft-eyes to satisfy the long-term loadings and to meet the 100 year design-life requirements. The design life of the GFRP is an important design consideration for it is subject to creep effects. Based on the projected schedule for construction and excavation of the launch box and for the assembly and launching of the two TBM s, the design life of the GFRP reinforcing was established at six months. The design of the GFRP was based on the American Concrete Institute (ACI) Guide for the Design and Construction of Structural Concrete Reinforced with Fibre Reinforced Polymer Bars, ACI 440.1R-06. Though there are other international codes, the ACI method had a separate check against creep rupture using unfactored loads. This was critical, since creep rupture can be the governing failure mechanism under sustained loadings such as under earth and water pressure (1). The design parameters for the GFRP bars were verified by tests; these were undertaken to ACI test method B5 as described in ACI Analysis The analysis showed that the construction sequence and ground improvement were critical. The governing locations for bending were positive moment at mid-span of the soft-eye and negative bending at the intermediate slab-level, which is largely locked-in during the excavation sequence. For the chosen construction sequence, the extent and strength of the ground improvement influenced the profile of the bending in the headwall. The extent of the ground improvement was largely determined by the sewer location and by the TBM launching requirements. The strength of the adopted ground improvement was chosen to balance the peak positive and negative bending, since both these regions needed to be resisted with concrete reinforced with GFRP bars. It was thus important that the analysis considered both upper and lower values for strength of ground improvement. A number of soil-structure interaction-models were created for the headwall with the intent to model the 3D-effects of the headwall and adjoining diaphragm wall-corner panels, with the intent being to reduce the vertical bending by accounting for load spanning in both directions. This was used to accurately determine

4 the both vertical and transverse bending in the soft-eyes. Both 2D and 3D Plaxis models were created along with corresponding structural stiffness matrix models. The 2D model assisted with the calibration of the 3D model, especially, with the seepage modelling which was more readily modelled in 2D Plaxis. Since the water pressure during construction was based on the seepage modelling, a sensitivity analysis was carried out on the horizontal permeability of the soil and rock layers. The structural stiffness matrix models considered the locked-in effects from the Plaxis model in conjunction with the numerous load combination cases for both the short and long-term loading conditions (2). The transverse bending was limited due to the vertical joints in the diaphragm wall-panels. The design accounted for transverse bending with co-existing axial compression, which was induced from the lateral earth and water pressure on the corner diaphragm wall-panels. It was, however, sufficient to provide a working solution for the 1200mm thick diaphragm wall-panels. Analysis showed, after the TBM break-through, that there was an increase in negative moment above the soft-eye when combined with the long-term effects and other loading such as fill on the roof slab and longterm lateral loading, which was applied after the TBM launch. 6. Design The design was required to consider the induced tension in the GFRP bars during the time taken for each excavation stage; this time included allowing for casting the reinforced concrete slabs and for installing the temporary props and whalers. Following the completion of the excavation to the underside of the base slab, the GFRP bars had a six-month design-life to allow for the casting of the base slab, de-stressing and removal of the temporary supports and for the assembly and the launch of the TBMs. There was, approximately, a two-month lag between the launch of the first and the second TBM, although the excavations on each side of the launch box were done concurrently. An internal ring beam was cast against the excavated face of the headwall, which extended from the underside of the intermediate slab to the top of the base slab in height, and between the internal faces of the corner diaphragm wall-panels in width. This was cast after the temporary steel props and whalers were removed. The ring beam was used to connect the seal ring of the TBM, which seals the TBM and launch box from water during the TBM break-through into soil and rock. See Figure 2. Figure 2. Photograph of headwall showing ring beam prior to TBM assembly.

5 The L-shaped corner-panels were stiffer than the adjoining diaphragm wall-panels with GFRP. As a result, the analytical model indicated a deflection differential between these panels. The ring beam was designed to act in shear to reduce the deflection of the panel with GFRP and, thus, to prevent local failure of the diaphragm wall panel joints. Since the ring beam did not extend over the full extent of the soft-eye, the 1200mm thick panels with GFRP were still spanning vertically. The design of shear reinforcement was also affected by the anisotropic characteristics of glass fibre. When used for ligatures, the GFRP bars were required to be manufactured with bends. A strength reduction of 14 to 23% compared with the tensile strength of a straight bar was used for the ligatures to account for fibre bending and for stress concentrations in the bend. The values used for the reduction in tensile strength due to bending were based on test results, which had been provided by the manufacturer, that were performed in accordance with test methodologies cited in ACI 440.3R. The durability of GFRP reinforcement is influenced by its exposure to the environment; the creep rupture endurance time can irreversibly decrease under adverse environmental conditions. Following the ACI recommendations, we used an environmental reduction factor of C E = 0.7 for concrete exposed to earth and weather. 7. Detailing Special consideration had to be given to the detailing for a number of reasons. The GFRP bars have a significantly-lower modulus of elasticity of 40.8 GPa in comparison with steel reinforcement, which is approximately five times larger. A much greater cross-sectional area of these are thus required to give the same bending capacity as that of steel reinforcement. This resulted in the need for five GFRP bars to be arranged in two bundles of two and three reinforcement bars respectively. See Figure 3. This arrangement was comparable in bending capacity to a single bundle of two N40 bars, which were adopted outside the soft-eye region. Figure 3. Section showing GFRP bar arrangement. The splice region between the GFRP and the steel bars required significant attention. The design of the launch-box diaphragm-walls was optimised by positioning the intermediate slab and the base slab with a minimum clearance to the TBM. This, however, involved having haunches in the underside of the intermediate slab and on the top of the base slab to provide assembly access around the perimeter of the TBMs.

6 This resulted in the diaphragm wall-panels, which required reinforcement couplers for these slabs, being positioned immediately adjacent to the soft-eye regions. The maximum negative bending occurs at the intermediate slab-level; this was also the splice zone from steel to GFRP, so the region was locally congested. Special detailing was carried out to minimise this congestion. This included having the diaphragm-wall steel reinforcement end with a coupler at the intermediate level slab and staggering the length of other steel bars to match the circular profile (in elevation) of the soft-eyes. A 10mm concrete mix was specified for these diaphragm wall-panels to allow for better consolidation in the congested areas. The reinforcement in the panels was detailed with 600mm clear zones to allow concrete placement using tremmie pipes. In addition, bending of GFRP bars is not possible on site; the factory bending results in the bent portion having a considerably lower tension-capacity. A further limitation of GFRP bars is that they can only have a maximum bend of 90 rather than a hook. This resulted in a reduced capacity of the shear ligatures. Detailing of these followed ACI 440-1R recommendations, that is, the use of 90-degree cogs with a minimum r b /d b ratio of 3, and a minimum tail length of 12 d b. This required lapping the bent bar with a horizontal spacer bar, in order to provide sufficient rigidity for lifting the reinforcement cage during construction. See Figure Construction Most diaphragm wall-panels for the TBM launch box had reinforcement-cage splice locations between the intermediate and the base slab levels. This location was not, however, suitable for the splice location in the soft-eye and, instead, the splice was located at the base slab level. This resulted in a longer panel length with these panels being assembled near the launch box. Prior to excavation, instrumentation that included inclinometers and prisms were installed and calibrated. These were recorded and compared against predicted values at each excavation stage. The 3D Plaxis model correlated reasonably well with the site-measured deflections, which were 24mm and 20mm respectively, for the stage after the removal of the temporary supports, and correlations at the other construction stages were similar. 9. Conclusions The break-through of the TBM required the use of GFRP bars, which greatly affected the design of the headwall in several aspects. The soil and pore water pressures, ground improvement extents and the construction sequence varied the peak bending moment positions on the headwall. Haunch beams on the underside of the intermediate slab and on top of the base slab were adopted to reduce the effective length of the headwall panels. The diaphragm wall headwall panels were subject to greater deflection than the adjacent corner-panels, which were inherently stiffer due to their L-shape. This effect was modeled by using 3D models and by calibrating them against the 2D models. The differential deflection created shear forces across the diaphragm wall panel joints; the shear forces were greater than the joint s capacity. These panels thus needed additional restraint; this was provided by utilising the internal ring beam to span over the joint and to effectively connect the panels together. GFRP bars are susceptible to creep effects, with creep rupture being one of their critical failure mechanisms. The adopted design life for the soft-eye was six months; when combined with the exposure classification, this established the design parameters for the reinforcement. The GFRP bars had approximately 20% of the modulus of elasticity of steel reinforcement, which meant that more bars were required to resist the bending moments. To substitute the typical steel reinforcing of two N40 bars at 180mm centres, in the soft-eye regions five 32mm GFRP bars at 180mm centres were arranged in two bundles of three and two bars. This caused congestion, which was amplified at the splice region between the steel and GFRP zones. The congestion of the reinforcement was mitigated by using concrete with 10mm aggregate to allow for better consolidation in the these areas.

7 Bends in the shear ligatures were limited to a 90, and reduced their strength by 14 to 24%. The use of GFRP bars was further complicated by long lead-times for fabrication, and the necessity for bends to be made by the manufacturer. The need for replacement bars was eliminated by careful detailing in close liaison with the contractor s construction team. The 1200mm diaphragm wall was designed and detailed without the need to widen the wall in the GFRP zone. The recorded on-site maximum deflection at mid-span, immediately after the removal of the temporary supports, for the diaphragm wall-panel measured 20mm. It compared closely to the predicted 24mm from the 3D Plaxis model. This provided greater confidence in the methods used for the design and detailing of the diaphragm wall soft-eyes using a combination of steel and GFRP reinforcing bars. 10. Acknowledgement The authors would like to thank Thiess-John Holland and Parsons Brinckerhoff-Arup for their support. 11. References 1. American Concrete Institute, Guide for the Design and Construction of Concrete Reinforced with FRP Bars, (ACI 440.1R-06) ACI Committee 440, 2006, Michigan. 2. Donohue, J,. Eberhardt, R. G., Kuhn, M., The adoption of soil co-efficients from FEA (Finite Element Analysis) models for use in stiffness matrix models to allow for multiple load cases generating large numbers of load combinations, Proceedings, World Tunnel Congress 2013, Geneva, Switzerland.

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Bridge articulation No. 1.04

Bridge articulation No. 1.04 Bridge articulation Scope This Guidance Note gives advice on the selection of the articulation arrangements, the choice of bearing types and dispositions of bearings, for bridges where relative movement

More information

Northport Berth 3 design and construction monitoring

Northport Berth 3 design and construction monitoring Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Lucy Coe, Nicola Ridgley, Do Van Toan Beca Infrastructure Limited, Auckland, NZ Keywords: retaining wall, deflections,

More information

APPENDIX B ABC STRUCTURES DESIGN GUIDE

APPENDIX B ABC STRUCTURES DESIGN GUIDE APPENDIX B ABC STRUCTURES DESIGN GUIDE The Cohos Evamy Partners TABLE OF CONTENTS Page No. DISCLAIMER... I 1. STRUCTURAL DESIGN GUIDELINES... 1 2. GENERAL REQUIREMENTS (FIGURE B.2, STEP 1)... 1 3. GENERAL

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 2016 MOMENT REDISTRIBUTION OF GFRP-RC CONTINUOUS T-BEAMS S. M. Hasanur Rahman M.Sc. Student, University of Manitoba, Canada Ehab El-Salakawy Professor and CRC in Durability

More information

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures CFA Technical Note: 008-2010 A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures CFA Technical This CFA Technical Note is intended to serve as a guide to assist

More information

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte

More information

Wood-based beams strengthened with FRP laminates Improved performance with pre-stressed systems

Wood-based beams strengthened with FRP laminates Improved performance with pre-stressed systems COST Action FP1004 Final Meeting 15 April 17 April 2015 Lisbon, Portugal Wood-based beams strengthened with FRP laminates Improved performance with pre-stressed systems Robert Kliger and Reza Haghani -

More information

JULY 2014 LRFD BRIDGE DESIGN 5-1

JULY 2014 LRFD BRIDGE DESIGN 5-1 JULY 014 LRFD BRIDGE DESIGN 5-1 5. CONCRETE STRUCTURES Reinforced and prestressed concrete are used extensively in bridge projects. In addition to general design guidance and information on detailing practices,

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Ultimate strength prediction for reinforced concrete slabs externally strengthened by fiber reinforced polymer (FRP)

Ultimate strength prediction for reinforced concrete slabs externally strengthened by fiber reinforced polymer (FRP) Ultimate strength prediction for reinforced concrete slabs externally strengthened by fiber reinforced polymer (FRP) Abstract This paper presents the potential use of externally bonded fiber reinforced

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway

Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway Michael D. McDonagh, P.E., P.Eng., WSP Parsons Brinckerhoff Andrew J. Foden, Ph.D., P.E., WSP Parsons Brinckerhoff

More information

Section A A: Slab & Beam Elevation

Section A A: Slab & Beam Elevation CE 331, Spring 2011 Flexure Strength of Reinforced Concrete s 1 / 5 A typical reinforced concrete floor system is shown in the sketches below. The floor is supported by the beams, which in turn are supported

More information

CHAPTER 11: PRESTRESSED CONCRETE

CHAPTER 11: PRESTRESSED CONCRETE CHAPTER 11: PRESTRESSED CONCRETE 11.1 GENERAL (1) This chapter gives general guidelines required for the design of prestressed concrete structures or members with CFRM tendons or CFRM tendons in conjunction

More information

Design Data 4M. Jacking Concrete Pipe

Design Data 4M. Jacking Concrete Pipe Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Bridge Beams/Girders

Bridge Beams/Girders Bridge Beams/Girders Introduction Simplifying Concrete Construction Insteel Wire Products is the nation s largest manufacturer of steel wire reinforcing products for concrete construction applications.

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11 CHAPTER 11 INTRODUCTION The open-trench method of placing underground conduits is commonly used on new construction of culverts, sewers and underpasses. Interference with traffic, as well as inconvenience

More information

BEHAVIOR OF INFILL MASONRY WALLS STRENGTHENED WITH FRP MATERIALS

BEHAVIOR OF INFILL MASONRY WALLS STRENGTHENED WITH FRP MATERIALS BEHAVIOR OF INFILL MASONRY WALLS STRENGTHENED WITH FRP MATERIALS D.S. Lunn 1,2, V. Hariharan 1, G. Lucier 1, S.H. Rizkalla 1, and Z. Smith 3 1 North Carolina State University, Constructed Facilities Laboratory,

More information

Design Data 4. Jacking Concrete Pipe

Design Data 4. Jacking Concrete Pipe Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

ACCEPTANCE CRITERIA FOR THREADED HIGH-STRENGTH STEEL BARS FOR CONCRETE REINFORCEMENT PREFACE

ACCEPTANCE CRITERIA FOR THREADED HIGH-STRENGTH STEEL BARS FOR CONCRETE REINFORCEMENT PREFACE www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council ACCEPTANCE CRITERIA FOR THREADED HIGH-STRENGTH STEEL BARS FOR CONCRETE REINFORCEMENT AC237 Approved June 2009

More information

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE If you want to put a photo on the title slide use this layout with colour photos (delete this box) Michael Wei, Jawad Zeerak & David Barton 8 th

More information

PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140)

PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140) PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140) *A. Ahmed 1, K. H. Tan 1 1 Department of Civil and Environmental Engineering National University of Singapore, Singapore,

More information

16. Design of Pipeline Structures.

16. Design of Pipeline Structures. 16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.

More information

GFRP systems for. for diaphragm walls and piles

GFRP systems for. for diaphragm walls and piles GFRP systems for for diaphragm walls and piles 0 U n d e r g r o u n d & C i v i l W o r k s d i v i s i o n ATP is present in the FRP market for more than thirty years and it is today one of the leading

More information

ST7008 PRESTRESSED CONCRETE

ST7008 PRESTRESSED CONCRETE ST7008 PRESTRESSED CONCRETE QUESTION BANK UNIT-I PRINCIPLES OF PRESTRESSING PART-A 1. Define modular ratio. 2. What is meant by creep coefficient? 3. Is the deflection control essential? Discuss. 4. Give

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

Finite Element Analysis of RC Beams Strengthened with FRP Sheets under Bending

Finite Element Analysis of RC Beams Strengthened with FRP Sheets under Bending Australian Journal of Basic and Applied Sciences, 4(5): 773-778, 2010 ISSN 1991-8178 Finite Element Analysis of RC Beams Strengthened with FRP Sheets under Bending 1 2 Reza Mahjoub, Seyed Hamid Hashemi

More information

Contents. 1.1 Introduction 1

Contents. 1.1 Introduction 1 Contents PREFACE 1 ANCIENT MASONRY 1 1.1 Introduction 1 1.2 History of Masonry Materials 1 1.2.1 Stone 2 1.2.2 Clay Units 2 1.2.3 Calcium Silicate Units 4 1.2.4 Concrete Masonry Units 4 1.2.5 Mortars 5

More information

Interaction between ductile RC perimeter frames and floor slabs containing precast units

Interaction between ductile RC perimeter frames and floor slabs containing precast units Interaction between ductile RC perimeter frames and floor slabs containing precast units R. C Fenwick,. J. Davidson and D.. N. Lau Department of Civil and Environmental Engineering, University of uckland.

More information

FE MODELING OF CFRP STRENGTHENED CONCRETE BEAM EXPOSED TO CYCLIC TEMPERATURE, HUMIDITY AND SUSTAINED LOADING

FE MODELING OF CFRP STRENGTHENED CONCRETE BEAM EXPOSED TO CYCLIC TEMPERATURE, HUMIDITY AND SUSTAINED LOADING FE MODELING OF STRENGTHENED CONCRETE BEAM EXPOSED TO CYCLIC TEMPERATURE, HUMIDITY AND SUSTAINED LOADING H. R. C. S. Bandara (Email: chinthanasandun@yahoo.com) J. C. P. H. Gamage (Email: kgamage@uom.lk)

More information

Seismic Behaviour of RC Shear Walls

Seismic Behaviour of RC Shear Walls Ductile Detailing of RC Structures :: IS:13920-1993 1993 Short Course on Seismic Design of RC Structures Durgesh C. Rai Department of Civil Engineering, IIT Kanpur The material contained in this lecture

More information

Bijan Khaleghi, Ph, D. P.E., S.E.

Bijan Khaleghi, Ph, D. P.E., S.E. 0 Submission date: July, 0 Word count: 0 Author Name: Bijan Khaleghi Affiliations: Washington State D.O.T. Address: Linderson Way SW, Tumwater WA 0 INTEGRAL BENT CAP FOR CONTINUOUS PRECAST PRESTRESSED

More information

Lintel Tables Design Notes and Limitations

Lintel Tables Design Notes and Limitations LINTEL TABLES Lintel Tables Design Notes and Limitations 1. These tables apply to one and two family residential structures only that conform to the requirements of the 2006, 2009 or 2012 International

More information

Combined Pile Foundation System for a Residential Complex

Combined Pile Foundation System for a Residential Complex Combined Pile Foundation System for a Residential Complex Alvin K.M. Lam, Geotechnical Engineer, Ove Arup & Partners Hong Kong Limited, Hong Kong, China; email: alvin.lam@arup.com Daman D.M. Lee, Civil

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Underground Construction Technology

Underground Construction Technology Underground Construction Technology Course Lectures Part 4.2 Permanent support Dr Ákos TÓTH 1 Segmental Lining in TBM Tunnelling Segmental lining is the support system for shield TBM excavated tunnels.

More information

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system. APPENDIX B. LOAD FRAME This Appendix will describe the philosophy in the design and operation of the loading system. LOAD FRAME The large-scale gusset plate testing required a unique loading fixture. A

More information

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore

More information

4D grouting pressure model of a bored tunnel in 3D Tunnel

4D grouting pressure model of a bored tunnel in 3D Tunnel 4D grouting pressure model of a bored tunnel in 3D Tunnel F.J.M. Hoefsloot & A. Verweij, Fugro Ingenieursbureau B.V., The Netherlands INTRODUCTION For some ten years TBM-techniques have been used to construct

More information

with Fillers Department of Civil Engineering, National Taipei University of Technology, Taiwan, R.O.C

with Fillers Department of Civil Engineering, National Taipei University of Technology, Taiwan, R.O.C A Study on the Mechanical Behaviour of the BFRP Decks with Fillers Yeou-Fong Li 1* and Chia-Hou Wu 1 1 Department of Civil Engineering, National Taipei University of Technology, Taiwan, R.O.C * 1, Sec.

More information

Design of Semi gravity Retaining Walls

Design of Semi gravity Retaining Walls Design of Semi gravity Retaining Walls Example 13.1 A semi gravity retaining wall consisting of plain concrete (weight = 145 lb/ft³) is shown in Figure 13.9. The bank of supported earth is assumed to weigh

More information

Analysis of a Severely Skewed Prestressed Concrete Beam Bridge

Analysis of a Severely Skewed Prestressed Concrete Beam Bridge Analysis of a Severely Skewed Prestressed Concrete Beam Bridge Gary L. Gardner, Jr., P.E. Bridge Technical Service Manager ms consultants, inc. August 19 th, 2015 MIDAS Special Elite Engineers Webinar

More information

4D grouting pressure model PLAXIS

4D grouting pressure model PLAXIS 4D grouting pressure model PLAXIS F.J.M. Hoefsloot & A. Verweij Fugro Ingenieursbureau B.V., Leidschendam, The Netherlands ABSTRACT: Bored tunnels are about to be constructed in the urban areas of Amsterdam

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Development of Steel Diaphragm Wall with Soil Cement

Development of Steel Diaphragm Wall with Soil Cement Technical Report Development of Steel Diaphragm Wall with Soil Cement UDC 624. 154 Naoya NAGAO* Masakazu TAKENO Takuzo KUZU Noriyoshi HARATA Abstract The steel diaphragm wall had one method, called Steel

More information

GFRP-STEEL HYBRID REINFORCED CONCRETE BRIDGE DECK SLABS IN QUEBEC, CANADA

GFRP-STEEL HYBRID REINFORCED CONCRETE BRIDGE DECK SLABS IN QUEBEC, CANADA Fourth Asia-Pacific Conference on FRP in Structures (APFIS 213) 11-13 December 213, Melbourne, Australia 213 International Institute for FRP in Construction GFRP-STEEL HYBRID REINFORCED CONCRETE BRIDGE

More information

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

More information

Tension and compression testing of fibre reinforced polymer (FRP) bars

Tension and compression testing of fibre reinforced polymer (FRP) bars University of Wollongong Research Online Faculty of Engineering and Information Sciences - Papers: Part A Faculty of Engineering and Information Sciences 2015 Tension and compression testing of fibre reinforced

More information

A PRODUCT FROM KANTAFLEX (INDIA) PVT LIMITED

A PRODUCT FROM KANTAFLEX (INDIA) PVT LIMITED ELASTOMERIC BRIDGE BEARING TO LATEST IRC: 83-015 (PART - II) Kanta System of Elastomeric bridge bearing is made out of Poly chloroprene rubber having low crystallization rates and adequate shelf life,

More information

Effect of Bar-cutoff and Bent-point Locations on Debonding Loads in RC Beams Strengthened with CFRP Plates

Effect of Bar-cutoff and Bent-point Locations on Debonding Loads in RC Beams Strengthened with CFRP Plates CICE 2010 - The 5th International Conference on FRP Composites in Civil Engineering September 27-29, 2010 Beijing, China Effect of Bar-cutoff and Bent-point Locations on Debonding Loads in RC Beams Strengthened

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Concrete Pipe Association of Australasia ACN 007 067 656 TECHNICAL BULLETIN CONTENTS ABSTRACT 1 INTRODUCTION 2 METHOD OF INSTALLATION 3 CONCRETE PIPE DESIGN 4 CONCRETE PIPE JOINT

More information

Continuous for Live Load: A Texas Historical Perspective

Continuous for Live Load: A Texas Historical Perspective Continuous for Live Load: A Texas Historical Perspective Scott Walton, M.S.C.E., E.I.T. 1, and Timothy E. Bradberry, M.S.E., P.E. 2 Abstract A significant number of engineers in the United States have

More information

Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems

Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems Mohamad J. Terro Associate Professor. Civil Engineering Department, Kuwait University. Sameer

More information

CVEN 483. Structural System Overview

CVEN 483. Structural System Overview CVEN 483 Structural System Overview Dr. J. Bracci Fall 2001 Semester Presentation Overview 1. Building system primary function 2. Types of load 3. Building materials 4. Structural members 5. Structural

More information

PUNCHING SHEAR STRENGTH OF GFRP REINFORCED DECK SLABS IN SLAB- GIRDER BRIDGES

PUNCHING SHEAR STRENGTH OF GFRP REINFORCED DECK SLABS IN SLAB- GIRDER BRIDGES IV ACMBS MCAPC 4 th International Conference on Advanced Composite Materials in Bridges and Structures 4 ième Conférence Internationale sur les matériaux composites d avant-garde pour ponts et charpentes

More information

HRC T-Headed Bars Advantages for the user

HRC T-Headed Bars Advantages for the user HIGH PERFORMANCE REINFORCEMENT PRODUCTS HRC T-Headed Bars Advantages for the user HRC T-headed bars have some special characteristics which distinguish them from conventional reinforcement. HRC T-heads

More information

Inverted Double T BEAMS and SLABS Applications

Inverted Double T BEAMS and SLABS Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Inverted Double T BEAMS and SLABS Applications Inverted Double T Beams U Panels Inverted Double T Slabs Inverted Triple

More information

ArmourWall T2B Construction PRODUCT BROCHURE. ArmourWall T2B SHEET PILE TECHNOLOGY

ArmourWall T2B Construction PRODUCT BROCHURE. ArmourWall T2B SHEET PILE TECHNOLOGY PRODUCT BROCHURE ArmourWall T2B SHEET PILE TECHNOLOGY What Is Top To Bottom Construction If we consider that bottom-up is the conventional way that a structure is built, then as the name suggests, top-bottom

More information

HIGHWAY STRUCTURES: DESIGN (SUBSTRUCTURES AND SPECIAL STRUCTURES) COMPONENTS PART 7 BA 82/00 FORMATION OF CONTINUITY JOINTS IN BRIDGE DECKS SUMMARY

HIGHWAY STRUCTURES: DESIGN (SUBSTRUCTURES AND SPECIAL STRUCTURES) COMPONENTS PART 7 BA 82/00 FORMATION OF CONTINUITY JOINTS IN BRIDGE DECKS SUMMARY DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 2 SECTION 3 HIGHWAY STRUCTURES: DESIGN (SUBSTRUCTURES AND SPECIAL STRUCTURES) MATERIALS AND COMPONENTS PART 7 BA 82/00 FORMATION OF CONTINUITY JOINTS IN BRIDGE

More information

mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE

mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE SECTION 1. mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE 1.1 Overview of AS 3600:2009 AS 3600:2009 is the latest Australian

More information

EARTHQUAKE DESIGN CONSIDERATIONS OF BUILDINGS. By Ir. Heng Tang Hai

EARTHQUAKE DESIGN CONSIDERATIONS OF BUILDINGS. By Ir. Heng Tang Hai EARTHQUAKE DESIGN CONSIDERATIONS OF BUILDINGS By Ir. Heng Tang Hai SYPNOSIS 1. Earthquake-Induced Motions 2. Building Configurations 3. Effectiveness Of Shear Walls 4. Enhancement Of Ductility In Buildings

More information

PORTAL FRAMES 1.0 INTRODUCTION

PORTAL FRAMES 1.0 INTRODUCTION 36 PORTAL FRAMES 1.0 INTRODUCTION The basic structural form of portal frames was developed during the Second World War, driven by the need to achieve the low - cost building envelope. Now they are the

More information

BEHAVIOR OF REINFORCED CONCRETE BEAM WITH OPENING

BEHAVIOR OF REINFORCED CONCRETE BEAM WITH OPENING International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 7, July 2017, pp. 581 593, Article ID: IJCIET_08_07_062 Available online at http:// http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=7

More information

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

D7: TUNNEL CONSTRUCTION AND METHODOLOGY HIGH SPEED TWO INFORMATION PAPER D7: TUNNEL CONSTRUCTION AND METHODOLOGY This paper outlines the proposed tunnelling methodology. It will be of particular interest to those potentially affected by the

More information

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 905 APRIL 2007 CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE TABLE OF CONTENTS 905.01 SCOPE 905.02 REFERENCES 905.03 DEFINITIONS

More information

Design of Steel-Concrete Composite Bridges

Design of Steel-Concrete Composite Bridges Design of Steel-Concrete Composite Bridges to Eurocodes Ioannis Vayas and Aristidis Iliopoulos CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What

More information

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E. BRIDGE DESIGN MANUAL UPDATES Jamie F. Farris, P.E. October 2015 Table of Contents 1 BDM Chapter 2 Limit States and Loads 2 BDM Chapter 3 Superstructure Design 3 BDM Chapter 4 Substructure Design 4 Questions

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan

More information

SEISMIC PERFORMANCE OF CONCRETE TILT-UP BUILDINGS: CURRENT WALL-TO-SLAB CONNECTIONS

SEISMIC PERFORMANCE OF CONCRETE TILT-UP BUILDINGS: CURRENT WALL-TO-SLAB CONNECTIONS SEISMIC PERFORMANCE OF CONCRETE TILT-UP BUILDINGS: CURRENT WALL-TO-SLAB CONNECTIONS Frank Devine, 1 Omri Olund, 2 Ken Elwood 3 and Perry Adebar 4 1 Graduate Student, Dept. of Civil Engineering, University

More information

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority SYNOPSIS In recent years, there has been heightened concern over the performance of half joints

More information

SHEAR PERFORMANCE OF RC MEMBERS STRENGTHENED WITH EXTERNALLY BONDED FRP WRAPS

SHEAR PERFORMANCE OF RC MEMBERS STRENGTHENED WITH EXTERNALLY BONDED FRP WRAPS Proc., 12th World Conference on Earthquake Engineering, Jan 3- Feb 4, 2, Auckland, New Zealand, paper 35,1 pp SHEAR PERFORMANCE OF RC MEMBERS STRENGTHENED WITH EXTERNALLY BONDED FRP WRAPS AHMED KHALIFA,

More information

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights 1 Exam Prep Placing Reinforcing Bars Tabs and s These 1 Exam Prep Tabs are based on the CRSI Placing Reinforcing Bars Recommended Practices, 9 th Edition. Each 1 Exam Prep tabs sheet has five rows of tabs.

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper F-1-04 A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES Sherif Kamel

More information

Development of New H-Section Steel Shape with Inner Rib, J-grip H, and Its Application to Steel Concrete Composite Diaphragm Wall

Development of New H-Section Steel Shape with Inner Rib, J-grip H, and Its Application to Steel Concrete Composite Diaphragm Wall JFE TECHNICAL REPORT No. 16 (Mar. 2011) Development of New H-Section Steel Shape with Inner, J-grip H, and Its Application to Steel Concrete Composite Diaphragm Wall ONDA Kunihiko *1 KOJO Rinya *2 AOKI

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge.

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge. The Design and Construction of Alfords Point Bridge Mark Bennett, Senior Bridge Engineer (New Design) RTA Harry Cheung, Project Engineer, RTA Trung Doan Project Engineer, RTA Synopsis The bridge over the

More information

Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment

Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment 8th Australian Small Bridges Conference 2017 Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment Level Crossing Removal Project 1 Burke Road, North Road, McKinnon Road and Centre

More information

Table of Contents. July

Table of Contents. July Table of Contents 36.1 General... 3 36.1.1 Bridge or Culvert... 3 36.1.2 Box Culvert Size Restrictions... 4 36.1.3 Stage Construction for Box Culverts... 4 36.2 Dead Loads and Earth Pressure... 5 36.3

More information

> 0. 1 f, they are treated as beam-columns.

> 0. 1 f, they are treated as beam-columns. 223 A- Flexural Members (Beams) of Special Moment Frames Requirements of ACI 21.5 are applicable for special moment frame members proportioned primarily to resist flexure with factored axial forces 0.

More information

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2) Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction

More information

Reinforced Concrete Design. A Fundamental Approach - Fifth Edition

Reinforced Concrete Design. A Fundamental Approach - Fifth Edition CHAPTER REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition Fifth Edition REINFORCED CONCRETE A. J. Clark School of Engineering Department of Civil and Environmental Engineering

More information

Eurocode 8 Timber and Masonry structures

Eurocode 8 Timber and Masonry structures Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 8 Timber and Masonry structures E C Carvalho, Chairman TC250/SC8 Brussels, 18-20 February 2008 Dissemination of information

More information

NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS

NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS AHMAD RAHIMIAN, PhD, PE, SE Dr. Ahmad Rahimian., PE, SE is President of Cantor Seinuk Structural Engineers in New York City. An expert in the behaviour of steel

More information

Design and construction of an immersed concrete tunnel using an integrated dock facility

Design and construction of an immersed concrete tunnel using an integrated dock facility Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Design and construction of an immersed concrete tunnel using an integrated dock facility

More information

Modelling of RC moment resisting frames with precast-prestressed flooring system

Modelling of RC moment resisting frames with precast-prestressed flooring system Modelling of RC moment resisting frames with precast-prestressed flooring system B.H.H. Peng, R.P. Dhakal, R.C. Fenwick & A.J. Carr Department of Civil Engineering, University of Canterbury, Christchurch.

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete

More information

ADAPT-PTRC 2016 Getting Started Tutorial ADAPT-PT mode

ADAPT-PTRC 2016 Getting Started Tutorial ADAPT-PT mode ADAPT-PTRC 2016 Getting Started Tutorial ADAPT-PT mode Update: August 2016 Copyright ADAPT Corporation all rights reserved ADAPT-PT/RC 2016-Tutorial- 1 This ADAPT-PTRC 2016 Getting Started Tutorial is

More information

Deflection Assessment of an FRP-Reinforced Concrete Bridge. By Danielle K. Stone, Andrea Prota, and Antonio Nanni

Deflection Assessment of an FRP-Reinforced Concrete Bridge. By Danielle K. Stone, Andrea Prota, and Antonio Nanni Deflection Assessment of an FRP-Reinforced Concrete Bridge By Danielle K. Stone, Andrea Prota, and Antonio Nanni Synopsis: Serviceability of FRP-reinforced concrete structures remains a highly relevant

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information