INO: West Kalimantan Power Grid Strengthening Project

Size: px
Start display at page:

Download "INO: West Kalimantan Power Grid Strengthening Project"

Transcription

1 Environmental Monitoring Report # Semiannual Report July-December 2016 INO: West Kalimantan Power Grid Strengthening Project Prepared by Joint Venture of Tractebel Engineering Ltd and Powergrid International Limited (Thailand) for the PT PLN and the Asian Development Bank.

2 CURRENCY EQUIVALENTS (as of 31 December 2016) Currency unit Indonesian rupiah (Rp) Rp1.00 = $ $1.00 = Rp13,492 NOTE (i) In this report, "$" refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

3 PT PLN (PERSERO) UIP KALIMANTAN BAGIAN BARAT Jl. Letjend Suprapto No. 50 G, Pontianak Kalimantan Barat Environmental Monitoring Semi Annual Report July - December 2016 Indonesia: Project Implementation Strengthening of West Kalimantan Power Grid Prepared by PT PLN (Persero) for The Government of The Republic of Indonesia and the Asian Development Bank Page a of 76

4 ABBREVIATIONS ADB - Asian Development Bank AFD - Agence Française de Développment AMDAL - analisis mengenai dampak lingkungan (environmental assessment under Indonesian Government requirements) BAPEDAL - Environmental Impact Management Agency (Government of Indonesia) BAPPEDA - Badan Perencanaan Pembangunan Daerah (Regional Planning Agency) EMP - environmental management plan GI - gardu induk (substation) HVTL - high voltage transmission line HIV/ AIDS - human immunodeficiency virus/ acquired immunodeficiency syndrome IEE - initial environmental examination (ADB terminology) No - number OPGW - optical ground wire or optical fiber composite overhead ground wire OSH - occupational safety and health PIC - project implementation consultant PLN - PT Perusahaan Listrik Negara (Persero) (State Electricity Company) PT - perusahaan terbatas (company limited) RKL - rencana pengelolaan lingkungan or environmental management plan SMCF - steel mortar composite foundations ROW - right of way SUTT - saluran udara tegangan tinggi or high voltage transmission line SUTET - saluran udara tegangan ekstra tinggi or extra high voltage transmission line TE - Tractebel Engineering T - tower UKL -UPL - upaya pengelolaan lingkungan and upaya pemantauan lingkungan (environmental management and monitoring effort) UPK - PT PLN (Persero) Unit Pelaksana Kerja 5 is the old name of PLN UPP of Kalbagbar 3 UPP - PT PLN (Persero) Unit Pelaksana Proyek UIP - PT PLN (Persero) Unit Induk Pembangunan (UIP) X is the old name of PLN UIP Kalimantan Bagian Barat WEIGHTS AND MEASURES ha - hectare km - kilometer kv - kilovolt m - meter MVA - megavolt ampere Page i of 76

5 Table of Contents 1. INTRODUCTION SUMMARY OF CONSTRUCTION PROGRESS 2.1. Summary of Construction Progress of Package 1: 275 kv Bengkayang Jagoibabang Transmission Line Summary of Construction Progress of Package 2: 275/150 kv Bengkayang Substation Summary of Construction Progress of Package 3: 150 kv Bengkayang - Ngabang Tayan Transmission Lines Summary of Construction Progress of Package 4: 150/20 kv Ngabang Substation and Tayan Substation Extension SUMMARY OF ENVIRONMENTAL PROGRESS Summary Environmental Progress of Package 1: 275 kv Bengkayang Jagoibabang Transmission Line Summary Environmental Progress of Package 2: 275/150/20 kv Bengkayang Substation Summary Environmental Progress of Package 3: 150 kv Bengkayang - Ngabang Tayan Transmission Lines Summary Environmental Progress of Package 4: 150/20 kv Ngabang and Tayan substations ENVIRONMENTAL MITIGATIONS AND LAND ACQUISITION IMPLEMENTED Environmental Mitigations Land Acquisition SUMMARY OF ENVIRONMENTAL COMPLIANCE MONITORING Summary of Inspection Activities Mitigation Compliance Mitigation Effectiveness KEY ENVIRONMENTAL ISSUES Environmental key Issues Identified Action to be taken CONCLUSION Overall Progress of Implementation of Environmental Management Measures Problems Identified and Actions Recommended Updated EMP...20 LIST OF TABLES Table 1. Summary of Completion Status of Land Acquisition/Compensation of Package 1: 275 kv Bengkayang Jagoibabang Transmission Lines Table 2. Summary of Completion Status of Land Acquisition/Compensation of Package 2: 275/150 kv Bengkayang Ngabang Substations Page ii of 76

6 Table 3. Summary of Completion Status of Land Acquisition/Compensation Status of Package 3: 150 kv Bengkayang Ngabang Tayan Transmission Lines and Package 4: 150/20 kv Ngabang & Tayan Substations..15 LIST OF MAPS Map 1. Project Location on the Map of Indonesia... 2 Map 2. West Kalimantan Power Grid Strengthening Project... 3 LIST OF APPENDIX A-1. SITE INSPECTION / MONITORING REPORTS...22 A-1.1. Summary of Construction Progress and Environmental Performance...23 A Summary of Construction Progress and Environmental Performance of 275 kv Bengkayang Jagoibabang Transmission Line (Completed) A Summary of Environmental Performance of 275/150 kv Bengkayang substation (Completed) A Summary of Construction Progress and Environmental Performance of 150 kv Bengkayang Ngabang Tayan Transmission Lines A Summary of Environmental Performance of 150 kv Ngabang and Tayan Substations (Completed) A-1.2. Mitigation Compliance Inspection Monitoring ()...39 A Site Environmental Compliance Inspection and Monitoring of Package 1 (Completed).. 39 A Site Environmental Compliance Inspection and Monitoring of Package 2 (Completed).. 42 A Site Environmental Compliance Inspection and Monitoring of Package A Site Environmental Compliance Inspection and Monitoring of Package 4 (Completed).. 49 A-2. PHOTOGRAPHS...52 A-2.1. Package 1: 275 kv Bengkayang Jagoibabang Transmission Lines (Completed)...52 A-2.2. Package 2: 275/150 kv Bengkayang Substation (Completed)...49 A-2.3. Package 3: 150 kv Bengkayang - Ngabang-Tayan transmission Lines...53 A-2.4. Package 4: 150/20 kv Ngabang and Tayan substations (Completed)...56 A-3. CONTRACTUAL ENVIRONMENTAL REQUIREMENTS OF EACH PACKAGE...57 A-3.1. Package 1: 275 kv Bengkayang Jagoibabang Transmission Line ()...57 A-3.2. Package 2: 275/150 kv Bengkayang Substation ()...58 A-3.3. Package 3: 150 kv Bengkayang Ngabang Tayan Transmission Line ()...60 A-3.4. Package 4: 150/20 kv Substation at Ngabang and Tayan () A-4. LIST OF SUBMITTED ENVIRONMENTAL REPORTS...63 A-5. STATUS OF THE TOWER CHANGES AND ENVIRONMENTAL REVIEW...64 A-6. UPDATED ENVIRONMENTAL MANAGEMENT PLAN...72 Page iii of 76

7 1. INTRODUCTION In accordance with the Project Administration Manual of the loan agreements with ADB and AFD of July 2013 of West Kalimantan Power Grid Strengthening Project of Item D. Consultant's Terms of Reference sub item 1. Scope of Services for Project Implementation Consultants (Firm) paragraph 62, that the consultant shall prepare the Quarterly progress reports to be submitted to PLN. This report also corresponds with the IEE, Appendix F Sample Mitigation Compliance Inspection Monitoring Form, and Appendix G Sample Project Environmental Progress and Monitoring Report. PT PLN (Persero) has assigned the Joint Venture of Tractebel Engineering Ltd. and Power Grid International Limited (Thailand), Contract No PJ/041/DIR/2013 of 30th July, 2013, to carry out the monitoring of the project works. The project comprises of design, supply, installation, testing, and commissioning of the works as follows: Package 1: 275 kv Transmission Line between Bengkayang substation and the border with Sarawak, East Malaysia (80.26 km). Package 2: 275/150 kv Substation at Bengkayang. Package 3: 150 kv Transmission Lines from Bengkayang substation to the new Ngabang substation (93.34 km), and from there to the existing Tayan substation (46.64 km). Package 4: 150/20 kv Substation at Ngabang and Tayan Substation extension. The location of the project is presented on Map 1 and the West Kalimantan Power Grid Strengthening Project is presented on Map 2. The monitoring of the environmental works is carried out for all four packages of the works as mentioned above. The report on occupational health and safety (OHS) is presented separately. Compared to the original schedule mentioned in IEE, there are some route changes due to the relocation of the planned sites for 275/150/20 kv Bengkayang substation and 150/20 kv Ngabang substation. The status report concerning the route changes is presented in Appendix 5. According to the original plan of the 275 kv Bengkayang Jagoibabang Transmission Line (Sarawak border) that comprises of 199 towers (extended from Tower No 1 in Bengkayang to Tower No. 199 in Jagoibabang). Six towers from No. 1 to 6 had been eliminated; instead of new 4 towers had been added. Besides, there are more addition of 4 inserted towers resulted 201 towers in total. The original plan of 150 kv Bengkayang - Ngabang and 150 kv Tayan - Ngabang transmission lines comprise of 393 towers in total (260 towers and 133 towers respectively). There are several modifications have been made to the total number of towers of the Bengkayang Ngabang and Tayan - Ngabang transmission lines. The total towers finally increase to 408 towers (there are 280 towers and 128 towers respectively). The detail is as follows: Bengkayang Ngabang route a) The shifting of 275/150 kv Bengkayang Substation position to north-eastern direction resulted in the elimination of 3 towers and addition of 7 new towers. b) Due to site relocation of 150/20 kv Ngabang Substation to south of Ngabang and thus closer to Tayan direction, a number of towers will be relocated and added: Page 1 of 76

8 Relocation: 7 towers (T.253 up to T.259) Addition: o 3 additional towers (T.260 up to T.262) to connect with the former Ngabang - Tayan route at tower T.128 o o 13 additional towers as relocated towers from former Ngabang - Tayan route of towers T. 128 up to T additional towers to connect with tower T.116 of former Tayan - Ngabang route with the (New) Ngabang substation. c) There are two towers (T.157 and T.159) to be eliminated due to span condition and one additionally inserted tower (T.24A). Ngabang Tayan route The Tayan - Ngabang route has been modified as follows: 5 eliminated towers of former Ngabang - Tayan route at towers T.129 up to T.133, because the Bengkayang Ngabang route will be connected with T eliminated towers which formerly belonged to the Ngabang - Tayan route from towers T. 128 up to T.116 but are now part of the Bengkayang-Ngabang route. Two additional towers (T.114B and T.114C) are required to connect with the remaining planned towers from Tayan direction. The original tower T.115 will be shifted from previous planned location (the number will become T.114A). 9 towers are required to connect to Tayan substation which had been shifted about 2.5 km southward during the planning of 150 kv Tayan-Siantan (Pontianak) transmission line. This route has not been mentioned in the original tower schedule of 150 kv Tayan-Ngabang transmission line. In June 2016 PLN had acquired the land for eight locations. Two additional towers as insert tower at T.04A and 73/1. Thereby the Bengkayang Ngabang - Tayan transmission lines will comprise of 408 towers, i.e. 280 towers for the Bengkayang Ngabang section and 128 towers for the Tayan - Ngabang section. Detailed information concerning the environmental review on relocation of the substations and towers is elaborated in detail in Appendix 5. Map 1. Project location on the Map of Indonesia Page 2 of 76

9 Map 2. West Kalimantan Power Grid Strengthening Project 2. SUMMARY OF THE PROGRESS OF THE PROJECT WORKS UP TO THE END OF DECEMBER Summary of Construction Progress of Package 1: 275 kv Bengkayang Jagoibabang Transmission Line (Completed). A total of 201 towers has been completely constructed extending along the km transmission lines. The works progress is currently summarized in the following table below. No Type of works Progress of works 1 Tower foundations: a Soil works b Concrete works Completed Completed 2 Tower erection Completed 3 Stringing a. Fisrt circuit : 29 December 2015 b. Second circuit: Mid of March Energizing a. First circuit: 20 January 2016 b. Second circuit: 19 May Summary of Construction Progress of Package 2: 275/150 kv Bengkayang Substation (Completed) The 275/150 kv Bengkayang Substation has been finally finished for the two major works, repectively, Fedeer 1 of Mambong 275 Transmission Lines and Mambong Line 2 & 50 MVA Reactor. The final works such as pre commissioning test and energizing have been completely done for them. However, several minor works need to be rectified such Page 3 of 76

10 as Fire Prevention Equipment on One Phase IBT and Repairing Online Monitoring System for IBT Transformer. The overall works progress is finally summarized below. No Type of works Progress of works 1 Civil works: a Cut and fill b Concrete works 2 Electro-Mechanical works: a Mechanical (Metal) works b Electrical works Feeder 1 Mambong 275 KV Transmision Lines Mambong Line 2 & 50 MVA Reactor Completed Completed Completed Completed a. Pre commissioning test: January 2016 b. Energizing: 20 January 2016 a. Pre commissioning test: 19 May 2016 b. Energizing: 19 May Summary of Construction Progress of Package 3: 150 kv Bengkayang - Ngabang Tayan Transmission Lines (In progress) The updated Package 3 comprises of 408 Towers in total. This package is divided into two sections, as follows: i. Section 1 : the 150 KV Bengkayang - Ngabang Transmission Lines, included 280 Towers. ii. Section 2: the 150 KV Ngabang Tayan Transmission lines, included 128 Towers. The total works progess of the Package 3 (included Section 1 and 2) is as follows: Previous period (January June 2016): Total tower foundation : 351 Towers (86.03%) Total tower erection : 343 Towers (84.07%) Total Tower stringing : 0 Towers This period (July December 2016): Total tower foundation : 394 Towers (96.86%) Total tower erection : 385 Towers (94.36%) Total tower stringing : 14 Towers (5%) Page 4 of 76

11 The summary of individual progress of each section is as follows: No Type of works Progress of works I Section 1: 150 KV Bengkayang Ngabang Transmission Lines (280 Towers) 1 Tower foundations a Soil works Previous semester: 243 tower sites (86.78%) Up to end of this semester: 279 Tower sites (99.64%) b Concrete works Previous semester: 243 tower sites (86.78%) Up to end of this semester: 279 Tower sites (99.64%) 2 Tower erection Previous semester: 240 towers (85.71%) Up to end of this semester: 275 Towers (98.21%) 3 Stringing Previous: 0 Towers Up to end of this semester : 14 Towers (5%) II Section 2: 150 KV Ngabang Tayan Transmission Lines (128 Tower sites) 1 Tower foundations a Soil works Previous semester: 108 Tower sites (84.37%) Up to end of this semester: 115 Tower sites (89.84%) b Concrete works Previous semester: 108 Tower sites (84.37%) Up to end of this semester: 115 Tower sites (89.84%) 2 Tower erection Previous semester: 103 Towers erected (80.46%) 3 Stringing Not yet started Up to end of this semester: 110 Towers (85.93%) 2.4. Summary of Construction Progress of Package 4: 150/20 kv Ngabang Substation and Tayan Substation Extension (Completed) The final construction progress of Package 4 is as the following: No Type of works Progress of works I 150/20 kv Ngabang Substation 1 Civil works a Cut and fill Completed in April b Main civil and infrastructure works 2 Electro-Mechanical works: II Completed: Main buildings, in August 2016; a Mechanical (Metal) works Completed: on May 2016 b Electrical works Completed: Testing, on September 27, /20 kv Tayan Substation 1 Civil works Page 5 of 76

12 No Type of works Progress of works a Cut and fill Completed: Land preparation, December b Main civil and infrastructure works 2 Electro-Mechanical works a Mechanical (Metal) works Completed: May 2016 b Electrical works Completed: Main civil works, in August 2016; In progress: Acces road (additional works) Completed: September 2016; Testing: not run yet 3. SUMMARY OF ENVIRONMENTAL PROGRESS The environmental monitoring progress at the end of December 2016 is as follows: 3.1. Summary Environmental Progress of Package 1: 275 kv Bengkayang Jagoibabang Transmission Line (Completed) There are currently no any environmental monitoring progress was made on the Package 1 since the transmission lines of the pakacge 1 has been completely energized on last May The completion of environment monitoring status of Package 1 is previously resumed as follows: No Concern Environment Impact 1 Land Compensation Completed Mitigation Implementation progress Notes 2 Vegetation clearing Good Vegetation clearing has been done by manual equipment/no heavy equipment used (incl. chain saw) 3 Soil erosion Fair to good Levelling the site to reduce runoff and decreasing the slope. Most tower sites have been naturally covered by grass and shrub 4 Drainage Fair No need special drainage constructed. 5 Water quality Fair No significant impact on water quality 6 Air quality Fair to good Impact of the machine used on air quality assumed minimal; Mostly small engines used 7 Construction waste Fair Removal of remaining construction wastes such as plastic, hemp sack need to be done in some locations. 8 Domestic waste Fair Several locations, domestic wastes still remained; They need to be removed. Mostly plastic bottle or food wraps. 9 Roads and infrastructure 10 Community health and safety Good Fair to good No impact. Most concern on food hygiene that consumed by workers during tower construction and stringing activities. See: Occupational Safety and Health Page 6 of 76

13 No Concern Environment Impact 11 Employment opportunities Mitigation Implementation progress Fair to good report. Notes Subcontractors and local people were hired for tower construction Summary Environmental Progress of Package 2: 275/150/20 kv Bengkayang Substation (Completed) There are currently no any environmental monitoring progress was made during this period on the Package 2 since the whole works has been completed on last May In exception is the additional works of access road which the reconstruction is in progress. The completion of environment monitoring status of Package 2 at the end of previous period (June 2016) is resumed as follows: No Concern Environment Impacts 1 Land Compensation Completed Mitigation Implementation progress Note 2 Soil erosion Fair Soil erosion considered minimal: 1. Retaining wall for all areas was completed. 2. The parking area was paved. 3. The switch yard area covered by gravel; 4. Some heap of soil still remained; 5. Some holes are not backfilled yet 3 Drainage Good A main drainage has been constructed. 4 Water quality Good No significant impact on water quality 5 Air quality Fair Impact of the machine used on air quality assumed minimal 6 Construction waste Fair to good 7 Domestic waste Fair to good 8 Roads and infrastructure 9 Community health and safety 10 Employment opportunities Fair Fair Fair to good Reconstruction (asphalt pavement) of the access road is not completely finished yet (additional works) No special concern observed. See: Occupational Safety and Health report. Local peoples were hired by local subcontractor 3.3. Summary of Environmental Progress of Package 3: 150 kv Bengkayang - Ngabang Tayan Transmission Lines (In progress) The updated Package 3 comprises of 408 Towers in total. This package is divided into two sections, as follows: Page 7 of 76

14 a. Section 1 : the 150 KV Bengkayang - Ngabang Transmission Lines, included 280 Towers. b. Section 2: the 150 KV Ngabang Tayan Transmission lines, included 128 Towers. The several works of Package 3 are still in progress such as tower foundation, tower erection, tree cutting and stringing. The total works progess of the Package 3 during this end of December 2016 (included both of Section 1 and 2) is as follows: Total tower foundation : 394 Towers (96.86%) Total towers erection : 385 Towers (94.36%) Total tower stringing : 14 Towers (5%) The environmental monitoring review of Package 3 is as follows: No Environment Impact / Concern Mitigation Implementation progress Note I Bengkayang Ngabang Transmission Line route 1 Land Compensation 208 Tower sites have been compensated See social report for details. 2 Vegetation clearing Fair. Tree cutting followed the ROW alignment; Chain saw used in tree cutting; No chemicals or burning applied; Some tree cutting were posponded due to delay in compesation 3 Soil erosion Fair Final soil works referred to the design. Levelling the ground to reduce runoff, decreasing the slope and developing retaining wall to protect tower ground from land sliding 4 Drainage Fair No need for special drainage. 5 Water quality Fair No significant impact 6 Air quality Fair to good No significant impact 7 Construction waste Fair Some construction wastes remained scattered, such as plastic, hemp sack in some locations. Need to be cleaned. 8 Domestic waste Fair Mostly plastic of food wraps/plastic bottles are remained scattered. Need to be cleaned. 9 Roads and infrastructure impact 10 Community health and safety 11 Employment opportunities Good Fair to good Fair to good II Ngabang Tayan Transmission Line route No significant impact. Attention for: food hygiene that consumed by workers. See: Occupational Safety and Health report. The subcontractor hired local people. Page 8 of 76

15 No Environment Impact / Concern Mitigation Implementation progress 1 Land Compensation 128 tower sites have been compensated. Note See social report for details. 2 Vegetation clearing Fair Tree cutting followed the ROW alignment; Chain saw used in tree cutting; No chemicals or burning applied; Some tree cutting were posponded due to delay in compesation 3 Soil erosion Fair Final soil works referred to the design. Levelling the ground to reduce runoff, decreasing the slope and developing retaining wall to protect tower ground from land sliding 4 Drainage Fair No need for special drainage. 5 Water quality Fair No significant impact 6 Air quality Fair to good No significant impact 7 Construction waste Fair Some construction wastes remained scattered, such as plastic, hemp sack in some locations. Need to be cleaned. 8 Domestic waste Fair Removal of domestic waste remained to be done in some locations. Mostly plastic bottles or food wraps. 9 Roads and infrastructure impact 10 Community health and safety 11 Employment opportunities Good Fair to good Fair to good No impact. Attention for: food hygiene that consumed by workers. See: Occupational Safety and Health report. The subcontractor hired local people Summary Environmental Progress of Package 4: 150/20 kv Ngabang and Tayan substations (Completed) This package consists of Ngabang substation and Tayan substation constructions works. The construction works of those plants has been completely on August Running test of Ngabang plant has been commenced in September However, the test of the function of the Tayan plant was not run yet. The environmental works implementation progress of Package 4 is as follows: No Environment Impact / Concern I Ngabang Substation Mitigation Implementation progress Note 1 Land Compensation Completed Page 9 of 76

16 No Environment Impact / Concern Mitigation Implementation progress Note 2 Soil erosion Good Retaining wall had been constructed along the surrounded border; Inside roads were paved; Gravel was applied on the ground of switch yards 3 Drainage Good Inside and surrounding drainages were completely developed; 4 Water quality Fair No serious impact on surrounding water body 5 Air quality Fair Emission of machine used causing air pollution assumed minimum 6 Construction waste Fair to good Small parts of unused material were left 7 Domestic waste Fair to good No domestic wastes left 8 Roads and infrastructure impact 9 Community health and safety 10 Employment opportunities II Tayan Substation Good Fair Fair to good 1 Land Compensation Completed No access road works at Ngabang plants See: Occupational Safety and Health report. Local subcontractors employed local people as labour 2 Soil erosion Fair to good Retaining wall has been constructed along the surrounding border; But some of soil heaps remain at outside of the Tayan plant, they may be eroded by storm water; 3 Drainage Fair Drainage system has been completed. 4 Water quality Fair 5 Air quality Fair Emission pollution from machinery assumed minimum 6 Construction waste Fair to good Small parts of unused material were left 7 Domestic waste Fair to good No domestic wastes left 8 Roads and infrastructure impact 9 Community health and safety 10 Employment opportunities Good Fair Fair to good The access road of Tayan plants is additional works that being in progress now. A little ponding during rain at road side but drain off quickly See: Occupational Safety and Health report. Local subcontractors employed local people as labour Page 10 of 76

17 4. ENVIRONMENTAL MITIGATIONS AND LAND ACQUISITION IMPLEMENTED 4.1. Environmental Mitigations a) Air Quality: Air quality deterioration could be caused by exhaust gas of construction machines (truck, car, motor cycle), operation of concrete mixer, drilling/pilling machineries and heavy vehicles for land preparation (these are mostly utilized for substation works; rarely for tower works). Concrete mixer Concreate mixer equipped with small diesel engines used intermittently about 8 hours a day for pouring concrete at each tower pad. This machine is considered producing few emission then assumed no air pollution occurred. In addition, there are no people affected since the locations are away from villages. Drilling and excavation Man power are mostly used in excavation works. There are two method in soil excavation works depends on the soil condition. At a low bearing soil capacity (soft soil), holes were excavated by a drilling machine. While at a better soil condition (hard soil), either the foundation holes dig manualy or drilled by pile driver machine. The use of drilling machine assumed to generate more air pollution but not significant. Erection of towers No machinery used, so there is no air pollution. Transportation of material. Construction material was transported in two ways from store house. First, material transported directly to the site if the location can be accessed by truck (i.e. substation or tower sites that located just at roadside). Second, if the tower site is far from main road or cannot be accessed by truck, then the material carried to the roadside that closest point from the tower site. From this point the material transported manualy by labour or motorcycle to the tower sites. No significant air pollution assumed from this activity. Land preparation of the substations. The land preparation works is to clear and levelling the undulated ground of the Ngabang substation. But this works is not for the Tayan substation since the land has been ready for construction. The higher ground level in the site was cut to fill lower ground using bulldozer and backhoe. No outside quarry needed to produce soil embankment. Further, there is no transporting soil from outside, then generated dust can be minimized. b) Water Quality Water quality deterioration may be caused by soil works, concrete works, spilled diesel/oil. Soil works may generate turbid water and sedimentation in water body. Concrete works usually produce alkaline water and turbid water due to the cement deposit. In addition, spilled diesel/oil could be occured due to negligence, misconduct and or accident, further it may pollute into soil and water. Water pollution may be also from acid soil encountered during the excavation works. It may produce acid water that pollute the water body. Page 11 of 76

18 So far there was no water pollution indicated significantly at the sites; So there is no need specific measures applied. There are several sources of impact predicted to cause water pollution, as follows: Drillings and excavations. If soft soil indicated in a tower pad area, foundation holes shall be dig by manual drill equipment to locate concrete piles. But some drilling machine may be limited used at some specific locations. Where the soil was considered harder (better condition), no drilling method was applied. Instead of this, manual excavation was conducted in all tower pads. Both of drillings and excavations generated heap of soil and bare surface. Once the concreating finished, the soils were backfilled to the foundation holes. Further, the bare land and soil heaps may be sensitive to be washed away by storm water when it rains. The strom water that containing much soil sediment will be drained and pollute into water body surrounding areas. The soil heaps will be backfilled to the fondoution holes. Fortunately, most towers are surrounded by natural grass, bushes and litter of foliage. These will screen naturaly the soil sediment carried by storm water. So far, these activities generated insignificant soil erosion. Land preparation. Substations of Ngabang and Tayan The land preparation of Ngabang and Tayan substations cover an area of about 1 ha each. The clearing and levelling the ground surface, done prior to civil works begun. Acces roads in the substations are paved by asphalt, and ground surface at the switch yards covered by gravel to prevent from soil erosion. Also, surround retaining walls were constructed at substations to protect soil from erosion and land sliding. Open ditches were constructed inside of the plant area and between main/access road and the substations to control run-off water from in-beetwen area that may cause a local flooding. Tower Pads of Bengkayang Ngabang - Tayan Transmission Lines Final contour of tower pads were carried out following the each tower designs. Levelling the ground of the tower pads was done to reduce run off. Decreassing the slope is necessary to prevent soil erosion. In particular, the tower pads locate at steep slope need to develop retaining wall to protect tower pads from land slide. Concrete works. The concreate works wastes such as spilled cement liquid and alkaline/turbid waters from equipment cleaning were assumed a little amount that generated insignificantly impacts to the soil and water surrounding project sites. Oil uses. The contractor used diesel oil for powering the concrete mixer only. It is contained in jerry cans securely, and no signiificant oil spill was indicated during the works. c) Noise Pollution Page 12 of 76

19 The noise sources are mainly from concrete mixer, drilling and excavator or bulldozer machines. But the most equipment used during construction works was concrete mixer. While, the drilling machine, excavator and bulldozer are temporarily used in sub station works. Drilling pile machine and rock breaker also used but in limited time under specific circumstances at some tower sites. The rock breaker machine Steel Mortar Composite Foundations (SMCF) was previously used approximately 4-6 days for four towers of the 275 kv Bengkayang transmission lines and at 150 kv Bengkayang - Ngabang transmission line at towers no. 172 and 174. But, the noise impact was considered minimum since the tower sites were located away from inhabitant area, and the works were conducted during day time. d) Pollution Prevention Air Pollution See the review of item a) Water Pollution and Soil Pollution See the review of item b) Land Pollution Sources of this impact are the construction and domestic wastes. In most cases, the contractor have removed the large size of the construction and domestic wastes but some smaller pieces found scattered at many tower sites. The construction wastes of paper cement containers, broken hemp sacks, plastic wraps and chunks of wood is found in development areas of most towers. The domestic wastes produced by the construction workers who throw the garbage (plastic bottles, plastic wrap) carelessly to the surrounding environment. The woods for pouring concreate were reused in further concreate works. e) Biodiversity and Natural Resources The project passes some forest lands, that not categorized into the conservation/protected forest. It means, there are no protected or endangered plants affected by project. The most vegetations affected by project are plantation crops such as rubber, palm oil, seasonal crops and bushes. There are several public forest lands (but the lands owned by government) affected by project but they are mostly not well maintained which grown by shrubs and bushes. The workers were allowed to use woods resulting from clearing for construction purposes in limited amount. But entering into the forest out of the ROW cutting area for personal purposes is prohibited. f) Physical Cultural Resources Until now, the cultural heritage resources was not indicated during surveillance monitoring. g) Employment opportunities Local subcontractors with local labours have been hired to do project works such as substations works, tower works, tree cutting and stringing. These works have provided benefits for local peoples. h) Capacity Building Page 13 of 76

20 There is no any capacity building taken place during this period. Previously, a workshop on capacity building of environment, health & safety, and social issues in Bengkayang was commenced on 16 th October 2014 which attended by : The contractors of four packages works as follows: o PT. Bukaka Teknik Utama on Package 1. o CG Consortium on Package 2. o Consortium of KEC International Ltd. and Mitsubishi Corporation on Package 3. o PT. Siemens Indonesia on Package 4. PT. PLN (Persero) who the project owner: o PT. PLN (Persero) Unit Induk Pembangunan (UIP) Kalbagbar as the Principal project management unit in West Kalimantan o PT. PLN (Persero) Unit Pelaksana Proyek (UPP) Kalbagbar 3 as the project implementation management unit of the Implementation Strengthening of West Kalimantan Power Grid. Tractebel Engineering (TE) and Power Grid International Limited in association with PT. Catur Bina Persada who organized the workshop Land Acquisition a) Package 1: The 275 kv Bengkayang Jagoibabang Transmission Lines (Completed) All of 201 tower sites of the 275 kv Bengkayang - Jagoibabang transmission line have been totally compensated, including 4 locations as re-route towers and 4 locations as additional towers. Table 1. Summary of the completion status of land acquisition and compensation of the Package 1 : 275 kv Bengkayang Jagoibabang Transmission Lines NO ROUTES AND LOCATION TOTAL COMPENSATION STATUS 1 Towers on private land: A, B, C, D, and Compensated 2 Towers on Forestry land: Compensated 3 Towers on private land: including Inserted towers 76A, 99A, 110A, 158A 147 Compensated 4 Towers on Forestry land: Compensated Total on Forestry land 39 Total on Private land 162 Total number of Towers 201 Total of Compensated Land for towers 201 Total of not yet compensated land 0 b) Package 2: 275/150 KV Bengkayang substation (Completed) The Bengkayang substation area of about 6.6 ha that has been fully compensated prior to construction commencement in January The plant unit has been energized in May Page 14 of 76

21 Table 2. Summary of the completion status of land acquisition and compensation of the Package 2 : 275/150 kv Bengkayang Substation NO LOCATION TOTAL COMPENSATION STATUS 1 275/150 KV Bengkayang substation 1 Compensated c) Package 3: The 150 kv Bengkayang Ngabang - Tayan Transmission Lines There are totally 408 tower sites for the 150 kv Bengkayang Ngabang - Tayan Transmission Line which comprises of 280 tower located along the Bengkayang - Ngabang sites (Section 1), and 128 towers extend through the Ngabang - Tayan sites (Section 2). The 87 towers of them indicated crossing forestry lands, that they are 64 towers of Bengkayang - Ngabang alignment (Towers: 1A to 7A; 4 to 32; 82 to 103; and 144 to 151) and 23 towers of Tayan - Ngabang alignment (Towers: 35 to 43; 53 to 54 and 57 to 68). The total tower sites of section 1 and section 2 have been completely compensated. d) Package 4: The 150/20 kv Ngabang and Tayan Substations The Package 4 comprises two substatios that are: the 150/20 KV Ngabang substations and the 150/20 KV Tayan substations. Both of the them have been completely contructed during previous periods. Table 3. Summary of Completion Status of Land Acquisition and Compensation of The Package 3: 150 kv Bengkayang Ngabang Tayan Transmission Line, and The Package 4: 150/20 kv Ngabang and Tayan Substations. NO LOCATION TOTAL Unit COMPENSATION STATUS I Package 3: The 150 KV BENGKAYANG NGABANG TRANSMISSION LINE (Section 1) 1 Towers on private land: 33 to 81, 91, 104 to 128 to 143; 152 to 168, 170 to 221, 224 to 244, 251 to 254 and 264 to 273 (ex Ngabang-Tayan of 118 to 127), 2 Towers on Forestry land: 1A to 32, 82 to 92 to 103 and 144 to Compensated 64 Compensated 3 Total Towers 280 Compensated II Package 3: The 150 KV TAYAN NGABANG TRANSMISSON LINE (Section 2) 1 Towers on private land: 1/0, 1A/0, 1B/0, 1C/0, 1C/1, 1D/0, 1D/1, 1E/0, 1F/0, 1G/0, 1 to 34, 44 to 52, 55, 56, 69 to94, 96 to Towers on Forestry land: 35 to 43, 53, 54 and 57 to Compensated 23 Compensated 3 Total Towers 128 Compensated Page 15 of 76

22 NO III LOCATION TOTAL Unit Package 4: The 150/20 kv NGABANG and TAYAN Substations COMPENSATION STATUS 1 Ngabang Substation (New Location) 1 Compensated 2 Tayan substation extension 1 Compensated 5. SUMMARY OF ENVIRONMENTAL COMPLIANCE MONITORING The Environmental Management Plan (EMP) has been updated on June 2015 to consider the national and local standards. This updated EMP is enclosed on the Appendix A-6 of the report. The following environmental management reviews, therefore, refer to the updated EMP Summary of Inspection Activities a) Vegetation clearing Vegetation clearing was done by local sub contractors after the compensation completed. Clearences area followed the designed drawings of tower sites and routes of ROW of Bekayang Ngabang Tayan Transmission Lines. All tree cutting and clearances were used hand tools (including chain saw) without any heavy machines used as well as no burning applied. Tree cutting in particular addressed to the trees that higher than 3 m. All dry vegetation cut were left at the sites along the ROW lines. There were no any woods collected from the clearing sites for personal uses except for the construction purposes, such as temporary retaining wall, scaffolding works, temporary hut etc. Making fire in the clearing sites is strictly prohibited since the dried cut easily burned. But limited fires for cooking may be made by workers. b) Soil erosion Soil erosion might be generated from foundation works at substations and towers sites. The foundation holes resulted from excavation works were backfilled by the dig soil during finalization of the works. To control soil erosion, area of the sites of substations and towers have been levelled following the designs. In particular, the substation sites have been facilitated by drainages to drain off the storm water and reducing soil erosion. However, at the tower sites, the uses of drainange depend on the need of the sites. The uses of retaining walls, especially at steep sites is necessary to retain soil erosion and land sliding. c) Drainage Most of tower sites were not facilitated by drainages, except in certain area where it is considered required. But drainages have been constructed at the substations sites to drain off the storm water. d) Acid sulphate soils. No such soil was observed. No action required to be done. Page 16 of 76

23 e) Water quality impacts Source of impacts are run-off water and oil/diesel spill. The run-off water has been controlled by drainages construction at the substations sites. But there is no drainage made at tower sites. The spill diesel from machines uses are considered minimal and no significant impact on water quality. During tower foundation works, the water for drilling and concrete works may generate waste water. But this is considered small amount and will be absorbed by soil surrounding tower sites. f) Air quality impacts The machine are very limited used in the construction process. Thus air quality are not significantly affected. g) Construction waste management The construction wastes were cleaned by contractors. But some still remained there such as small portion chunk of woods, broken hemp sacks and cement paper containers. h) Domestic waste management The garbages (plastic bottles, plastic wrap) produced by the construction workers thrown carelessly to the surrounding environment. The wastes were scattered within the tower sites, surrounding their huts/temporary shelters and along the temporary access/footpath. i) Roads and infrastructure impacts No impact was observed in such facilities. j) Encroachment into protected forests, hunting, wood collection No encroachment was observed. Some transmission lines passed the public state forest lands, but most lands are grown by bushes or grasses. No firewood collection from the forest was observed. Also, no hunting activity by the workers indicated. k) Community health and safety Prevention of HIV/AIDS. o The contractor have campaigned the awareness of the sexually transmitted diseases to the their workers. Safety line and notice. o Safety lines and notices were not apllied by the contractor to prevent the people entering unsafe zones during unloading the steel materials at roadsides and or storehouse area. The mobilization of materials. o The use of front loader equipment to load and unload the materials at both of Page 17 of 76

24 roadsides and warehouse is considered unsafe for people passing by. Neen more sufficient safety notices and lines applied. The stringing of conductors. o Scaffoldings are used during stringing activities for the 150 kv Bengkayang Ngabang - Tayan transmission lines which crossing public utilities. The affected public utilities such as road, electric lines etc were protected by scaffoldings made of bamboo or woods to prevent the community affected by the stringing process. l) Employment opportunities The contractor hired local subcontractors that also employed local people to execute the construction works such as foundation, tower erection, tree cutting and stringing etc. Surrounding people also had benefit by selling meals or foods or other daily needs to the workers. m) Physical cultural resources. Until now no physical cultural resources were found and observed Mitigation Compliance a) Vegetation clearing In general, the clearing process can be handled adequately by the contractor. There are no serious impacts that considered to endanger the environment. Also, there are no protected plants affected by the cutting. But, it must be concerned that the dried cut likes woods, branches, leaves remained at the location must be protected from fire. b) Soil erosion Measures in soil protection have been made by the contractor to reduce soil erosion such as paving the substasion roads, finalizing the ground surface referring to the designs, decreasing the slope of tower pads, backfilling the foundation holes, establishing retaining walls surrounding the substations, gravel covering on the swith yards area. c) Drainage Most tower sites do not need to construct a rigid drainage system. Open drain may be necessary for some towers, especially located at concave sites to drain off storm water. All substations have been facilitated by open drains to control storm water. d) Acid sulphate soils Up to now, this type of soil was not found. e) Water quality impacts There is no special measures provided to control water quality. The construction Page 18 of 76

25 works did not significantly generate pollution to affect the surrounding water body. f) Air quality impacts Contractor complied with the requirement. g) Construction waste management In general the contractor clean the construction wastes after the works completed. But some construction wastes likes woods, cement sacs, plastic bags are still remained. The cleaning works need to be improved. h) Domestic waste management Similarly with the point (g) above, the workers did not adequately manage their wastes after finishing the construction. The wastes such as plastic bags, papers are scattered at some towers sites. i) Roads and infrastructure impacts Contractor complied with the requirements. j) Encroachment into protected forests, hunting, wood collection Contractor complied with the requirements. k) Community health and safety During the stringing works, contractor installed scaffolding that passing at the public sites to protect communities from dangerous activities. Unfortunately, there are no warning signs included. l) Employment opportunities Contractor complied with the requirement. The local people were hired to transport the materials from roadside to the tower locations. m) Physical cultural resources Up to now, there are no physical cultural resources indicated Mitigation Effectiveness Some notes in the mitigation review are as follows: In general environmental mitigation measures have been fairly done; but some are still insufficient applied sush as in managing of construction and domestic wastes; Eventhough the environment/osh officer has been hired by KEC but the final inspection of wastes cleaning after the construction finished was not adequately controled; Lack of monthly environmental monitoring report from the contractor submitted to the PLN causing insufficient control in environmental mitigation compliance. Page 19 of 76

26 6. KEY ENVIRONMENTAL ISSUES 6.1. Environmental key Issues Identified To increase in imposing of the EMP by the contractor to their subcontractor and their workers Action to be taken The contractor (KEC Int. consorcium) shall commit with the EMP and OSH requirements to enforce the EMP to both of the contractor employees and the sub contractors as well as their workers. The tasks must be concerned as follows: The environmental mitigation measures should be imposed following the EMP to whole involved personnels; To control adequately the apllied environmental mitigation measures during the construction works; To provide monthly environmental monitoring reports that submitted to the PLN and copied to the consultant; 7. CONCLUSION 7.1. Overall Progress of Implementation of Environmental Management Measures In general, the environmental management measures are fairly applied. However, some mitigation measures that insufficient applied are as follows: The wastes of construction and trashes cleaning were not adequately carried out after the works finished. The unused woodens, paper cement bags, plastic bags, plastic food wraps scattered surrounding the sites; The soil heaps located at outsite of sub station area (Tayan) was not managed well. The storm water washed the soils away and may generate polluted water coming into the surrounding water body; Fire for cooking made by workers around their hut must be concerned well, since it be able to burn easily the dry leaves and woods; 7.2. Problems Identified and Actions Recommended a. The main contractors should assign the Environmental and OSH personnel to be more active in controlling environmental works; b. The main contractor shall adequately imposing the EMP and OSH requirements to the sub contractors and their employees c. The main contractors shall establish routine monthly environmental monitoring report to be submitted to the PLN and the consultant Updated EMP The EMP has been updated to adapt the local and national regulations aswell as the conditions prevailing at the construction sites. This updated EMP has been submitted to PLN on 30 June The updated EMP is shown in Appendix A-6. Page 20 of 76

27 REFERENCES 1. Asian Development Bank Initial Environment Examination: 275 kv Regional Interconnection HVTL Mambong (Sarawak) to Bengkayang and 150 kv HVTLs Bengkayang to Tayan (West Kalimantan). Prepared by SOFRECO. July TA 6441-REG. Efficiency Improvement and Connectivity Strengthening in Archipelagic Southeast Asia Project. Final Report, Part G. 2. Bukaka Teknik Utama, Approved Foundation Schedule for Bengkayang Jagoibabang Transmission lines for Tower 50 up to PLN Kalimantan Principal Project of Generation and Transmission Lines Environmental Management Plan and Environmental Monitoring Plan (UKL-UPL) of High Voltage Transmission Line of Bengkayang-Ngabang West Kalimantan. PT PLN (Persero) Proyek Induk Pembangkit dan Jaringan Kalimantan. Printed document of translated document. 4. PLN Kalimantan Principal Project of Generation and Transmission Lines Environmental Management Plan and Environmental Monitoring Plan (UKL-UPL) of High Voltage Transmission Line of Ngabang-Tayan West Kalimantan. PT PLN (Persero) Proyek Induk Pembangkit dan Jaringan Kalimantan. Printed document of translated document. 5. PLN Kalimantan Principal Project of Generation and Transmission Lines Environmental Assessment, Environmental Management Plan and Environmental Monitoring Plan of Extra High Voltage Transmission Line of Bengkayang-Sarawak borderline and Bengkayang substation. West Kalimantan. PT PLN (Persero) Proyek Induk Pembangkit dan Jaringan Kalimantan. Soft file of translated document. 6. PLN, Contract document No 001.PJ/611/DIR/2013 dated April 12th, 2013 between PT Perusahaan Umum Listrik Negara (Persero) and PT Bukaka Teknik Utama. Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 1: Design, Supply, Installation, Testing, and Commissioning of 275 kv Overhead Transmission Lines Bengkayang Substation Jagoibabang Volume I IV. 7. PLN, Contract Document No PJ/611/DIR/2013, Dated April 30th, 2013, between PT. Perusahaan Listrik Negara (PERSERO) and CG Consortium for Strengthening West Kalimantan Power Grid Project LOAN ADB + AFD Package 2 : Design, Supply, Installation, Testing, and Commissioning of 275/150 kv Bengkayang Substation. Volume 1 III. 8. PLN, Contract document No 0009.PJ/611/DIR/2013 dated April 30th, 2013 between PT Perusahaan Umum Listrik Negara (Persero) and Consortium of KEC International Limited and Mitsubishi Corporation. Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 3: Design, Supply, Installation, Testing, and Commissioning of 150 kv Overhead Transmission Lines Bengkayang Ngabang-Tayan. Volume I IV. 9. PLN, Contract Agreement No PJ/041/DIR/2013, Dated: August 1st, 2013 Between: PT. PLN (Persero) and PT. Siemens Indonesia for Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 4: Design, Supply, Installation, Testing, and Commissioning of 150/20 kv Substation at Ngabang and Tayan. Book PLN, Contract document No 0107.PJ/611/DIR/2013 dated July 30th, 2013 between PT Perusahaan Umum Listrik Negara (Persero) and Joint Venture of Tractebel Engineering Ltd and Powergrid International Limited (Thailand), Sub-Consultant PT Caturbina Guna Persada for Consulting Services for Project Implementation Strengthening West Kalimantan Power Grid (Loan No 3015-INO) 11. PLN UPK V, Bengkayang. Various data such as: a) Maps of re-routes tower of 150 kv Bengkayang Ngabang Tayan Transmission lines and Ngabang substations. b) Maps of re-routes tower of 275 kv Bengkayang Jagoibabang Transmission line (Sarawak Border) c) Land Compensation which has been conducted for Bengkayang Jagoibabang Transmission lines and Bengkayang Ngabang-Tayan Transmission lines. Page 21 of 76

28 APPENDICES A-1. SITE INSPECTION / MONITORING REPORTS A-1.1. Summary of Environmental Performance. A Summary of Environmental Performance of 275 kv Bengkayang-Jagoibabang Transmission Lines (Completed); A Summary of Environmental Performance of 275/150 kv Bengkayang Substation (Completed); A Summary of Environmental Performance of 150 kv Bengkayang-Ngabang- Tayan Transmission Lines; A Summary of Environmental Performance of 150 kv Ngabang and Tayan Substations (Completed). A-1.2. Mitigation Compliance Inspection Monitoring A Site Environmental Compliance Inspection and Monitoring of Package 1 (Completed); A Site Environmental Compliance Inspection and Monitoring of Package 2 (Completed); A Site Environmental Compliance Inspection and Monitoring of Package 3; A Site Environmental Compliance Inspection and Monitoring of Package 4 (Completed). Page 22 of 76

29 Appendix: A-1.1. Summary of Construction Progress and Environmental Performance A Summary of Construction Progress and Environmental performance of 275 kv Bengkayang Jagoibabang Transmission Lines (Completed) Compens Payment Construction Environmental Mitigation Public Safety & Health Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install Stringing 1 A B C D Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment Foundation Erection Stringing Page 23 of 76

30 Compens Payment Construction Environmental Mitigation Public Safety & Health Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install Stringing A A Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment Foundation Erection Stringing Page 24 of 76

31 Compens Payment Construction Environmental Mitigation Public Safety & Health Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install Stringing A Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment Foundation Erection Stringing Page 25 of 76

32 Compens Payment Construction Environmental Mitigation Public Safety & Health Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install Stringing A SCORE NOTE For Compensation & Construction: Blank = Not started yet Highlight = On going; 1 = done Air quality Water quality For Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. Soil protection Trash & Debris NOTE Biodiversity Loc. Employment Foundation Erection The towers number with yellow highlight is the new site (it differs comparing with the sites of original tower schedule) Stringing Page 26 of 76

33 Note: Scoring Note refers to the IEE West Kalimantan Power Grid Strengthening Project, July, 2011, p Appendix: A Summary of Environmental Performance of 275/150 kv Bengkayang Substation (Completed) No Project works category Air quality Water quality Environmental Mitigation Soil protection Trash & Debris Biodiversity Loc. Employment Public Safety Health 1 Land clearing Land preparation Foundation and subsoil structure works Metal works Installation Testing and commissioning Score for Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. Appendix: A Summary of Construction Progress, Environmental performance of 150 kv Bengkayang Ngabang -Tayan Transmission Lines A. Bengkayang Ngabang (Section 1) Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Page 27 of 76 Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment 1 1A A A A A A A Foundation Erection Stringing Notes

34 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Page 28 of 76 Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment A Foundation Erection Stringing Notes

35 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment Foundation Erection Stringing Notes Page 29 of 76

36 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment VOID TOWER VOID TOWER Foundation Erection Stringing Notes Page 30 of 76

37 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment Foundation Erection Stringing Notes Page 31 of 76

38 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Loc. Employment A B SCORE NOTE NOTE Foundation Erection Stringing Notes ex Tayan-Ngabang towers Page 32 of 76

39 For Compensation & Construction: Blank = Not started yet Highlight = On going; 1 = done For Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. The towers number with yellow highlight is the new site (it differs comparing with the sites of original tower schedule) Note: Scoring Note refers to the IEE West Kalimantan Power Grid Stengthening Project, July, 2011, p Page 33 of 76

40 B. Ngabang-Tayan (Section 2) Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Page 34 of 76 Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Local Employment 1 1G/ F/ E/ D/ D/ C/ C/ B/ A/ A Foundation Erection Stringing

41 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Local Employment / Foundation Erection Stringing Page 35 of 76

42 Compens. Payment Construction Environmental Mitigation Public H&S Tower No. Working No. Tower site ROW Soil works Concreting Erection Insulator install. Stringing Air quality Water quality Soil protection Trash & Debris Biodiversity Local Employment A B C Foundation Erection Stringing Page 36 of 76

43 Compens. Payment Construction Environmental Mitigation Public H&S 128 Tower No. Working No. SCORE NOTE Tower site ROW For Compensation & Construction: Blank = Not started yet Highlight = On going; 1 = done Soil works Concreting Erection Insulator install. Stringing Air quality Water quality For Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. Soil protection Trash & Debris NOTE Biodiversity Local Employment Foundation Erection Stringing The towers number with yellow highlight is the new site (it differs comparing with the sites of original tower schedule) Note: Scoring Note refers to the IEE West Kalimantan Power Grid Stengthening Project, July, 2011, p Appendix: A Summary of Environmental Performance of 150 kv Ngabang and Tayan Substations (Completed) A. 150/20 kv NGABANG SUBSTATION No Project works category Air quality Water quality Environmental Mitigation Soil protection Trash & Debris Biodiversity Local Employment 1 Land clearing Land preparation Foundation and subsoil Public S & H structure works 4 Metal works Installation Testing and commissioning Score for Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. B. 150 kv TAYAN SUBSTATION EXTENSION No Project works category Air quality Water quality Environmental Mitigation Soil protection Trash & Debris Biodiversity Loc. Employment Public safety & Health 1 Land clearing Land preparation Foundation and subsoil structure works Page 37 of 76

44 No Project works category Air quality Water quality Environmental Mitigation Soil protection Trash & Debris Biodiversity Loc. Employment Public safety & Health 4 Metal works Installation Testing and commissioning Score for Environmental Mitigation & OSH: 5=Very Good; 4=Good; 3=Fair; 2=Poor; 1=Very poor. Page 38 of 76

45 Appendix: A-1.2. Mitigation Compliance Inspection Monitoring (1) Appendix: A Site Environmental Compliance Inspection and Monitoring of Package 1 (Completed) Project : West Kalimantan Power Grid Strengthening Project (RRP INO 41074) Sub-Project : 275 kv Bengkayang Jagoibabang Transmission Line Implementing Agency Monitoring Agency : PLN UPK 5, UIP X : PLN UIP X Location Monitoring Period : Districts of Lumar, Ledo, Sanggau Ledo, Seluas : 1 July September 2016 (Previous Period) Enforcement Agency Contractor(s) Date : End of September 2016 Implementation Phase : Ministry of Environment; Bapedalda West Kalimantan : Bukaka Teknik Utama : Construction (Completed) (1). Contractor(s) Contractor(s) Environmental Awareness Contractor(s) aware of mitigation requirements? Contractor(s) have a copy of EMP? Yes / No Yes Yes Actions Required Contractor Response / Comment Bukaka to provide continued awareness of EMP during maintenance and demobilization to the subcontractors and the labourers Bukaka to provide Simple Works Instruction Procedure to the labourers 1 Refer to APPENDIX F. Initial Environmental Examination, July West Kalimantan Power Grid Strengthening Project (RRP INO 41074). Page 39 of 76

46 (2). Mitigation Compliance Inspection No Impact / Mitigation Measure (From EMP) Mitigations Implemented (Yes, No) Mitigations Effective? (1 to 5)* Impact Observed / Location 1 Vegetation clearing Yes and No 4 TA T199 Action Required All vegetation clearing has been completed Contractor Response / Comment Endorsed by: Implementing Agency Monitoring Agency 2 Soil erosion Yes and No 4 TA T199 3 Drainage Yes and No 4 TA T199 4 Acid sulphate soils - - TA T199 5 Water quality impacts Yes and No 4 TA T199 6 Air quality impacts Yes 4 TA T199 7 Construction waste management Yes and No 4 TA T199 All backfilling in each leg has been finished There is no acid sulphate soils observed All construction works has been finished All construction works has been finished 8 Domestic waste management Yes and No 4 TA T Roads and infrastructure impacts Encroachment into protected forests, hunting, wood collection Yes 4 TA T TA T199 There is no protected forest area 11 Community health and safety Yes and No 4 TA T Employment opportunities Yes 4 TA T Physical cultural resources - - TA T199 There is no PCR observed/ affected *) Mitigation Effectiveness Rating Criteria: (5). Very Good (all required mitigations implemented); (4) Good (the majority of required mitigations implemented); (3). Fair (some mitigations implemented); (2). Poor (few mitigations implemented); (1). Very Poor (very few mitigations implemented) Page 40 of 76

47 (3). Environmental Incidents during Reporting Period (if relevant) Environmental Incidents (accidents, spills, complaints) None Date / Location Reported by Description/ Location Action Taken Further Action Required Endorsed by: Implementing Agency Monitoring Agency (4). Summary of Actions Required and Follow-up (if relevant) Action Required Timeframe (e.g. within one week) Responsible Parties Follow-up (to be completed if inspection/monitoring indicates actions are required) None Required Action Taken: Effectiveness: Further Action Required?: Prepared by: Date: Inspection Completed by: Attachments: (e.g. notes, photographs) Date: Signature:. Page 41 of 76

48 Appendix: A Site Environmental Compliance Inspection and Monitoring of Package 2 (Completed) Project : West Kalimantan Power Grid Strengthening Project (RRP INO 41074) Implementing Agency : PLN UPK 5, UIP X Sub-Project : 275/150/20 kv Bengkayang Substation Monitoring Agency : PLN UIP X Location : Magmagan, Bengkayang Enforcement Agency : Ministry of Environment; Bapedalda West Kalimantan Monitoring Period : 1 July 30 September 2016 (Previous Period) Contractor(s) : CG Consortium Date : End of September 2016 Implementation Phase : Construction (Completed) (1). Contractor(s) Contractor(s) Environmental Awareness Contractor(s) aware of mitigation requirements? Contractor(s) have a copy of EMP? Yes / No Yes Yes Actions Required Contractor Response / Comment CG Consortium to provide continued awareness of EMP to the subcontractors and the labourers CG Consortium to provide Simple Works Instruction Procedure to the labourers Page 42 of 76

49 (2). Mitigation Compliance Inspection No Impact / Mitigation Measure (From EMP) Mitigations Implemented (Yes, No) Mitigations Effective? (1 to 5)* Impact Observed / Location Action Required Contractor Response / Comment Endorsed by: Implementing Agency Monitoring Agency 1 Vegetation clearing Yes Yes 2 Soil erosion Yes/No 4 Levelling the remaining excavated soil. 3 Drainage Yes/No 4 4 Acid sulphate soils - - None 5 Water quality impacts Yes and No 4 Bengkayang Substation 6 Air quality impacts Yes 4 Maintenance of the machinery used 7 Construction waste management Yes and No 3 8 Domestic waste management Yes and No 4 9 Roads and infrastructure impacts Yes 4 10 Encroachment into protected forests, hunting, wood collection 11 Community health and safety Yes and No 4 12 Employment opportunities Yes and No 3 Small fraction of construction waste to be removed The village/access road has been improved. Pouring asphalt on the road surface - - No forest affected. Not applied. 13 Physical cultural resources - - None Awareness for workers and supervisors Always encourage the usage of local labourers *) Mitigation Effectiveness Rating Criteria: (5). Very Good (all required mitigations implemented); (4) Good (the majority of required mitigations implemented); (3). Fair (some mitigations implemented) ; (2). Poor (few mitigations implemented) ; (1). Very Poor (very few mitigations implemented) Page 43 of 76

50 (3). Environmental Incidents during Reporting Period (if relevant) Environmental Incidents (accidents, spills, complaints) None Date / Location Reported by Description/ Location Action Taken Further Action Required Endorsed by: Implementing Agency Monitoring Agency (4). Summary of Actions Required and Follow-up (if relevant) Action Required Timeframe (e.g. within one week) Responsible Parties Follow-up (to be completed if inspection/monitoring indicates actions are required) None Required Action Taken: Effectiveness: Further Action Required?: Prepared by: Date: Inspection Completed by: Attachments: (e.g. notes, photographs) Date: Signature:. Page 44 of 76

51 Appendix: A Site Environmental Compliance Inspection and Monitoring of Package 3. Project : West Kalimantan Power Grid Strengthening Project (RRP INO 41074) Sub-Project : 150 kv Bengkayang-Ngabang- Tayan Transmission Line Location Monitoring Period : Bengkayang, Landak and Sanggau Regencies : July - December 2016 Implementing Agency Monitoring Agency Enforcement Agency Contractor(s) Date : End of December 2016 Implementation Phase : PLN UPK 5, UIP X : PLN UIP X : Bapedalda of West Kalimantan Bapedalda of Bengkayang Bapedalda of Landak Bapedalda of Sanggau : Consortium of KEC International Limited and Mitsubishi Corporation : Construction (in Progress) (1). Contractor(s) Contractor(s) Environmental Awareness Contractor(s) aware of mitigation requirements? Yes / No Yes Actions Required Contractor Response / Comment KEC & Mitsubishi Consortium need to provide continued awareness of EMP to the subcontractors and the labourers - Contractor(s) have a copy of EMP? Yes KEC & Mitsubishi Consortium need to provide Simple Works Instruction Procedure to the labourers - Page 45 of 76

52 (2). Mitigation Compliance Inspection No Impact / Mitigation Measure (From EMP) Mitigations Implemented (Yes, No) Mitigations Effective? (1 to 5)* 1 Vegetation Clearing Yes Yes 2 Soil Erosion Yes/No 3 3 Drainage Yes/No 3 4 Acid Sulphate Soils Water Quality Impacts Yes and No 3 6 Air Quality Impacts Yes 4 7 Construction Waste Management Yes and No 3 8 Domestic Waste Management Yes and No Roads and Infrastructure Impacts Encroachment into Protected Forests, Hunting, Wood Collection Yes Community Health and Safety Yes and No 3 12 Employment Opportunities Yes and No 4 13 Physical Cultural Resources - - Impact Observed / Location Bengkayang- Ngabang T 1A T116B Ngabang - Tayan T1G/0 T114C Action Required Keep the dried cut away from fire Levelize the tower site and reducing the steep slope To conduct backfilling for each leg as soon as it is finished There is no acid sulphate soils observed Prevent the water pollution (concrete waste water and oily water) Maintenance of the machinery used Improve in construction waste management Improve in domestic waste management No significant impact There is no protected forest area Awareness for workers and supervisors Encourage the usage of local labour There is no PCR observed/ affected Contractor Response / Comment Implementing Agency Endorsed by: Monitoring Agency *) Mitigation Effectiveness Rating Criteria (5). Very Good (all required mitigations implemented); (4) Good (the majority of required mitigations implemented); (3). Fair (some mitigations implemented); (2). Poor (few mitigations implemented); (1). Very Poor (very few mitigations implemented) Page 46 of 76

53 Page 47 of 76

54 (3). Environmental Incidents during Reporting Period (if relevant) Environmental Incidents (accidents, spills, complaints) None Date / Location Reported by Description/ Location Action Taken Further Action Required Endorsed by: Implementing Agency Monitoring Agency (4). Summary of Actions Required and Follow-up (if relevant) Action Required Timeframe (e.g. within one week) Responsible Parties Follow-up (to be completed if inspection/monitoring indicates actions are required) None Required Action Taken: Effectiveness: Further Action Required?: Prepared by: Date: Inspection Completed by: Attachments: (e.g. notes, photographs) Date: Signature:. Page 48 of 76

55 Appendix: A Site Environmental Compliance Inspection and Monitoring of Package 4 (Completed) Project : West Kalimantan Power Grid Strengthening Project (RRP INO 41074) Sub-Project : 150/20 kv Ngabang & Tayan Substation Implementing Agency Monitoring Agency Location : Ngabang and Tayan Enforcement Agency : PLN UPK 5, UIP X : PLN UIP X : Bapedalda of West Kalimantan Bapedalda of Landak Bapedalda of Sanggau Monitoring Period : 1 July 30 September 2016 (Previous Period) Contractor(s) : PT. Siemens Indonesia Date : End of September 2016 Implementation Phase : Construction (Completed) (1). Contractor(s) Contractor(s) Environmental Awareness Contractor(s) aware of mitigation requirements? Contractor(s) have a copy of EMP? Yes / No Yes Yes Actions Required Contractor Response / Comment PT. Siemens Indonesia to provide continued awareness of EMP to the subcontractors and the labourers PT. Siemens Indonesia to provide Simple Works Instruction Procedure to the labourers Page 49 of 76

56 No (2). Mitigation Compliance Inspection Impact / Mitigation Measure (From EMP) Mitigations Implemented (Yes, No) Mitigations Effective? (1 to 5)* 1 Vegetation clearing Yes Yes 2 Soil erosion Yes/No 3 3 Drainage Yes 4 Impact Observed / Location 4 Acid sulphate soils - - None 5 Water quality impacts Yes and No 3 6 Air quality impacts Yes 4 7 Construction waste management Yes and No 4 Ngabang & Tayan Substations Action Required Continue to construct retaining wall at the rear border and right side (viewed from main road) to protect land slide and erosion. Maintain the drainage siphon adjacent to the road side area at Ngabang Substation. Prevent the water pollution (concrete waste water and oily water) Maintenance of the machinery used Removing whole construction waste 8 Domestic waste management Yes and No 3 Removing whole domestic waste 9 10 Roads and infrastructure impacts Encroachment into protected forests, hunting, wood collection Yes 4 11 Community health and safety Yes and No 3 12 Employment opportunities Yes and No 3 13 Physical cultural resources No forest affected. Not applied. Awareness for workers and supervisors Always encourage the usage of local labour None Contractor Response / Comment Endorsed by: Implementing Agency Monitoring Agency *) Mitigation Effectiveness Rating Criteria : (5). Very Good (all required mitigations implemented); (4) Good (the majority of required mitigations implemented); (3). Fair (some mitigations implemented) ; (2). Poor (few mitigations implemented) ; (1). Very Poor (very few mitigations implemented) Page 50 of 76

57 (3). Environmental Incidents During Reporting Period (if relevant) Environmental Incidents (accidents, spills, complaints) None Date / Location Reported by Description/ Location Action Taken Further Action Required Endorsed by: Implementing Agency Monitoring Agency (4). Summary of Actions Required and Follow-up (if relevant) Action Required Timeframe (e.g. within one week) Responsible Parties Follow-up (to be completed if inspection/monitoring indicates actions are required) None Required Action Taken: Effectiveness: Further Action Required?: Prepared by: Date: Inspection Completed by: Signature:. Attachments: (e.g. notes, photographs) Page 51 of 76

58 APPENDIX: A-2. PHOTOGRAPHS A-2.1. Package 1: 275 kv Bengkayang Jagoibabang Transmission lines (Completed) No of Picture: 1 and 2 Route: 275 kv Bengkayang - Jagoibabang Tower: T.115 andt.116 Picture taken: September (Completed) Note: Left: Retaining Wall at Tower T201 Right: Retaining Wall at Tower T191 No of Picture: 3 and 4 Route: 275 kv Bengkayang - Jagoibabang Tower: T.50 (T52 working no.) Picture taken: July 2016 (Completed) Note: Retaining Wall at Tower T50. A-2.2. Package 2: Bengkayang Substation (Completed) No of Picture: 5 and 6 Area: 275/150/20 kv Bengkayang Substation Status: Completed Picture taken: October 2016 Note: Left: Completed Works of Switch Yards Page 52 of 76

59 Right: PLN Engineers Training Note: Left: Bengkayang substation Right: PLN Engineers Training for Bengayang Substation No of Picture: 7 and 8 Area: 275/150/20 kv Bengkayang Substation Status: Completed works Note: Left: Completed Works of Switch Yards Right: Completed Works of Switch Yards Picture taken: September 2016 No of Picture: 9 and 10 Area: 275/150/20 kv Bengkayang Substation Status: Completion Works Picture taken: September 2016 Note: Left: Rehabiltation/asphalt paving on access road was in progress Right: Finalization of Gravel Covering on Switch Yards area Page 53 of 76

60 A-2.3. Package 3: 150 kv Bengkayang - Ngabang-Tayan transmission line Section 1: Bengkayang Ngabang Transmission Lines No of Picture: 11 and 12 Route: 150 kv Bengkayang Ngabang No of Tower: T 85 and T 09 Status: Tower Stringing and Tower erection works Picture taken: Left: November 2016 Right: December 2016 Note: Left: Roller Hoisting T85 Right: Tower Erection T09 No of Picture: 13 and 14 Route: 150 kv Bengkayang Ngabang No of Tower: T and T.116A Status: Tree cutting and Tower foundation construction Picture taken: Left November 2016 Right November 2016 Note: Left: Tree Cutting at Span T85-86 Right: Bore Pilling Foundation at Tower T116A No of Picture: 15 and 16 Route: 150 kv Bengkayang Ngabang No of Tower: T.194 and T126 Status: Tower stringing and foundation construction Note: Left: Stringing at Tower 194, a Pulling Tensioner Machine Picture taken: Left: November Right: December 2016 Page 54 of 76

61 Right: Foundation concreting at Tower T126 Section 2: Ngabang Tayan Transmission Lines No of Picture: 17 and 18 Route: 150 kv Ngabang - Tayan No of Tower: T.116B and T.73/1 Status: Foundation construction Note: Left: Foundation concreting at Tower T116B Right: Excavation for Foundation at Tower 73/1 Picture taken: Left: December 2016 Right: December 2016 No of Picture: 19 and 20 Route: 150 kv Ngabang - Tayan No of Tower: T.1A/0 and T.1/0 Status: Foundation construction Picture taken: Left: December 2016 Right: December 2016 Note: Left: Excavation works at tower T1/0 Right: Excavation work at tower T1/0, blocking the rear drain No of Picture: 21 and 22 Route: 150 kv Ngabang - Tayan No of Tower: T.1A/0 and T.1/0 Status: Foundation construction Picture taken: Left: November 2016 Right: December 2016 Note: Left: Bore pile work at tower T1A/0 Right: Excavation work at tower T1/0 Page 55 of 76

62 A-2.4. Package 4: 150/20 kv Ngabang and Tayan substations (Completed) No of Picture: 23 and 24 Area: 150/20 kv Ngabang substation Status: Completed Pictures taken: December 2016 Note: Left: Ngabang Substation (Front view) Right: Ngabang substation (Side view) No of Picture: 25 and 26 Area: 150/20 kv Ngabang substation Status: Completed Pictures taken: October 2016 Note: Left: Final Lanscaping works Right: Control Building, Finishing works No of Picture: 27 and 28 Area: 150/20 kv Ngabang substation Status: Completed Pictures taken: October 2016 Note: Left: ADB Visit, Joint Review Mission Page 56 of 76

63 Right: Training for PLN Engineers APPENDIX: A-3. CONTRACTUAL ENVIRONMENTAL REQUIREMENTS OF EACH PACKAGE. A-3.1. Package 1: 275 kv Bengkayang Jagoibabang Transmission Line (2) Section VII Special Section 8 - Special Conditions of Contract Conditions Special Conditions of Contract (SCC) shall supplement the General Conditions of Contract (GCC). Whenever there is a conflict, the provisions herein shall prevail over those in the GCC. The clause number of the SCC is the corresponding clause number of the GCC (Page 8-1). Clause 46. Protection of the Environment (Page 8-6) The Contractor shall comply with all applicable national, provincial, and local environmental laws and regulations. The Contractor shall: a. establish an operational system for managing environmental impacts, b. carry out all of the monitoring and mitigation measure set forth in the Initial Environmental Examination (lee) or Environmental Management Plan (EMP), and c. allocate the budget required to ensure such measures are carried out. The Contractor shall submit semi-annual reports on the carrying out of such measure to the Employer. More particularly, the Contractor shall comply with: (i) the measures and requirements set forth in the initial environmental examination and the environmental management plan attached hereto as Appendix 9; and (ii) any corrective or preventive actions set out in safeguards monitoring reports that the Employer will prepare from time to time to monitor implementation of the initial environmental examination and the environmental management plan. The Contractor shall allocate a budget for compliance with these measures, requirements and actions Addendum No. 1 of Bidding Document Package 1: 275 kv Bengkayang - Jagoibabang Transmission Line (September 2012) Section 8: Special Conditions of Contract (Page R1) Clause 35. Unforeseen Conditions Clause 35.3 (added at end of 35.3) 2 Contract document No 001.PJ/611/DIR/2013 dated April 12 th, 2013 between PT Perusahaan Umum Listrik Negara (Persero) and PT Bukaka Teknik Utama. Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 1: Design, Supply, Installation, Testing, and Commissioning of 275 kv Overhead Transmission Lines Bengkayang Substation Jagoibabang Volume I IV. Page 57 of 76

64 o In addition to notice of any Unforeseeable physical conditions, the Contractor shall provide the Project Manager with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the Plant or Permanent Works, which were not considered in the initial environmental examination, the environmental management plan or the resettlement plan attached hereto as Appendix 9 through Appendix 10 (not attached in this report) A-3.2. Package 2: 275/150 kv Bengkayang Substation (3) VOLUME I of III, BOOK 2 of 2, April GENERAL TECHNICAL REQUIREMENT: 2.4 Environmental Considerations The contractor shall comply with the following acts and regulations a follows: - Act of Republic of Indonesia no. 23/1997, regarding Environmental Management - Act of Republic of Indonesia no. 24/1992, regarding Spatial Use Management - Degree of the Minister for Environmental of Republic of Indonesia No. KEP- 28/MENLH/11/1996, regarding Noise Level Standards - The following are other environmental considerations for which the Contractor shall take due considerations. Local Employment The contractor shall make every endeavour to maximize the employment of people from the local villages of the site. Earthworks The Contractor shall ensure that stripped topsoil is stored for later use for landscaping and re-vegetation. The Contractor shall ensure that adequate and appropriate temporary silt ponds, site drainage and silt traps are constructed during earth works, especially in the rainy season to minimize the impact of silt/mud run off into local streams. The Contractor shall minimize the extent of vegetation stripping during earth works. At the completion of the main earth works the Contractor shall spread topsoil in open areas inside the site and re-vegetate such areas as appropriate. Construction Traffic The road to the site is narrow and passes through a village. There are a number of residents houses and a school near the road. Therefore, in order to minimize construction traffic impact and ensure the safety of local people - in particular children - the Contractor shall schedule as best as practical the construction traffic through the village so as to minimize impacts. Construction traffic shall be during the day except for large transportation items. The contractor shall install traffic signs around the village and impose and strictly enforce a 20km/h speed limit for construction traffic in the vicinity of the site and village. All construction vehicles shall be maintained as to minimize their noise and exhaust pollution levels. The road in the vicinity of the site and the local village which is used for construction 3 Contract Document No PJ/611/DIR/2013, Dated April 30th, 2013, between PT. Perusahaan Listrik Negara (PERSERO) and CG Consortium for Strengthening West Kalimantan Power Grid Project LOAN ADB + AFD Package 2 : Design, Supply, Installation, Testing, and Commissioning of 275/150 kv Bengkayang Substation Page 58 of 76

65 traffic shall be regularly water sprinkled by water truck to minimize the level of dust in the air around local villages. Site Noise Control All works shall be carried out without unreasonable noise. Welding generator, concrete mixers, drilling equipment and stringing motors used at site shall be silenced either by using only full silenced models fitted with effective exhaust silencers and properly lined and sealed acoustic covers or by the use of effective acoustic screen to enclose the noise source. Such equipment shall be maintained in good and efficient working order. Public Morality The Contractor shall be responsible for keeping discipline at the site and in this regard the Contractor shall pay attention to the public morality of his staff and labourers both on and off the site. In the interests of good community relations, the Contractor and his personnel shall be circumspect in their dealing with people residing in the neighbourhood of the works and take steps to minimize any disturbance to them. The Contractor shall arbitrate any dispute arising between his personnel and persons in the neighbourhood of the works. Interference with Existing Water Courses The Contractor shall not interfere with damage, contaminate and/or pollute any existing significant streams or rivers. The Contactor shall take all precautions not to affect the original condition. Direct discharge of construction waste water or contaminated water into the stream or river is not permitted. The Contractor shall provide adequate setting basins for construction works. VOLUME I of III, BOOK 1 of 2, April 2013 SECTION 8. SPECIAL CONDITIONS OF CONTRACT (SCC) 46. Environmental Protection (page 8-6) The Contractor shall comply with all applicable national, provincial, and local environmental laws and regulations. The Contactor shall: (a) establish an operational system for managing environmental impacts, (b) carry out all the monitoring and mitigation measure set forth in the Initial Environmental Examination (IEE) or Environmental Management Plan (EMP), and (c) allocate the budget required to ensure such measures are carried out. The Contractor shall submit semi-annual reports on the carrying out of such measures to the Employer. More particularly, the Contractor shall comply with (i) the measures and requirements set forth in the initial environmental examination and the environmental management plan attached hereto as Appendix 9; and (ii) any corrective or preventive actions set out in the safeguards monitoring reports that the Employer will prepare from time to time to monitor implementation of the initial environmental examination and environmental management plan. The Contractor shall allocate a budget for compliance with these measures, requirements and actions ADDENDUM NO Unforeseen Conditions Page 59 of 76

66 35.3 (added to end of 35.3) In addition to notice of any unforeseeable physical conditions, the Contractor shall provide the Project Manager with a written notice of any unanticipated environmental or resettlement risks or impact that arise during construction, implementation or operation of the Plant or Permanent Works, which were not considered in the initial environmental examination, the environmental management plan or the resettlement plan attached hereto as Appendix 9 through Appendix 10 (not added to this report). A-3.3. Package 3: 150 kv Bengkayang Ngabang Tayan Transmission Line (4) Section VI Addendum No. 1 of Bidding Document (September 2012) Section 8 - Special Conditions of Contract (Page 8-5-R1) Section VII: Special Conditions Section 8 - Special Conditions of Contract Special Conditions of Contract (SCC) shall supplement the General Conditions of Contract (GCC). Whenever there is a conflict, the provisions herein shall prevail over those in the GCC. The clause number of the SCC is the corresponding clause number of the GCC (Page 8-1). Section 8 - Special Conditions of Contract (Page 8-5) Clause 35. Unforeseen Conditions Clause (added at end of 35.3) In addition to notice to any unforeseen physical conditions, the Contractor shall provide the Engineer with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the Plant or Permanent Works, which were not considered in the initial environmental examination, the environmental management plan or the resettlement plan attached hereto as Appendix [B] through Appendix [D]. Clause 46. Protection of the Environment (Page 8-5 and 8-6) The Contractor shall comply with all applicable national, provincial, and local environmental laws and regulations. The Contractor shall: a. establish an operational system for managing environmental impacts, b. carry out all of the monitoring and mitigation measure set forth in the Initial Environmental Examination (lee) or Environmental Management Plan (EMP), and c. allocate the budget required to ensure such measures are carried out. The Contractor shall submit semi-annual reports on the carrying out of such measure to the Employer. More particularly, the Contractor shall comply with: (i) the measures and requirements set forth in the initial environmental examination and the environmental management plan attached hereto as Appendix [B and D]; and 4 Contract document No 0009.PJ/611/DIR/2013 dated April 30 th, 2013 between PT Perusahaan Umum Listrik Negara (Persero) and Consortium of KEC International Limited and Mitsubishi Corporation. Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 3: Design, Supply, Installation, Testing, and Commissioning of 150 kv Overhead Transmission Lines Bengkayang Ngabang-Tayan. Volume I III. Page 60 of 76

67 (ii) any corrective or preventive actions set out in safeguards monitoring reports that the Employer will prepare from time to time to monitor implementation of the initial environmental examination and the environmental management plan. The Contractor shall allocate a budget for compliance with these measures, requirements and actions Page 61 of 76

68 A-3.4. Package 4: 150/20 kv Substation at Ngabang and Tayan (5) BOOK I (1 of 8) Section 8. Special Conditions of Contract (SCC) and Addendum No. 1 September, Environmental Protection The Contractor shall comply with all applicable national, provincial, and local environmental laws and regulations. The Contactor shall: (a) establish and operational system for managing environmental impacts, (b) carry out all the monitoring and mitigation measure set forth in the Initial Environmental Examination (IEE) or Environmental Management Plan (EMP), and (c) allocate the budget required to ensure such measures are carried out. The Contractor shall submit semi-annual reports on the carrying out of such measure to the Employer. More particularly, the Contractor shall comply with: (i) the measures and requirements set forth in the initial environmental examination and the environmental management plan attached hereto as Appendix 9; and (ii) any corrective or preventive actions set out in the safeguards monitoring reports that the Employer will prepare from the time to time to monitor implementation of the initial environmental examination and environmental management plan. The Contractor shall allocate a budget for compliance with these measures, requirements and actions. 5 Contract Agreement No PJ/041/DIR/2013, Dated : August 1st, 2013 Between: PT. PLN (Persero) and PT. Siemens Indonesia FOR Strengthening West Kalimantan Power Grid Project Loan ADB + AFD. Package 4 : Design, Supply, Installation, Testing, and Commissioning of 150/20 kv Substation at Ngabang and Tayan Page 62 of 76

69 APPENDIX: A-4. LIST OF SUBMITTED ENVIRONMENTAL REPORTS a. Inception Report/First Quarterly Report (1 book): 1. Quarterly Report on Evironmental Issue, April 2016 b. Quarterly Environmental Monitoring Reports (11 books): 1. Period: May 2014; 2. Period: July - September 2014; 3. Period: October - December 2014; 4. Period: January - March 2015; 5. Period: April - June 2015; 6. Period: July September 2015; 7. Period: October - December 2015; 8. Period: January - March 2016; 9. Period: April - June 2016; 10. Period: July September 2016; 11. Period: October - December 2016 c. Semi Annual Reports (6 books): 1. Period: January June 2015; 2. Period: July December 2014; 3. Period: January June 2015; 4. Period: July December 2015; 5. Period: January June 2016; 6. Period: July December 2016; d. PIC Monthly Progress and Activity Reports (36 books): 1. Period: January 2014 December Page 63 of 76

70 APPENDIX: A-5. STATUS OF THE TOWER CHANGES AND ENVIRONMENTAL REVIEW Comparing with the original schedule mentioned in IEE, there are some route changes due to relocation of the planned sites for 275/150kV Bengkayang substation and 150/20 kv Ngabang substation. The routes location are highlighted in the Map A-1 and the addition or elimination of towers as consequence of the site changes of both substations are discussed in the following paragraphs: Map A-1 Situation map of re-routing of 275 kv Bengkayang Jagoibabang and 150 kv Bengkayang Ngabang Tayan Transmission Lines a) Tower reroutes and changes of tower locations of 275 kv Bengkayang Jagoibabang Transmission Line According to the original planning, this route comprised of 199 towers (Tower No 1 in Bengkayang to Tower No 199 in Jagoibabang). For the sake of synchronizing with the route of the 150 kv Singkawang-Bengkayang transmission line, the planned 275/150kV Bengkayang substation which was originally located at the left side of road into direction to Jagoibabang, had been shifted to north-eastern direction at right hand side of the road, located adjacent to the 150/20 kv Bengkayang substation which is under construction and where the 150 kv Singkawang - Bengkayang Transmission Line will be terminated. Now this line comprises of 201 towers as described below: a.1) Six towers from No.1 to 6 had been eliminated, and replaced through four towers of No. A, B, C, D which had been erected to connect the 275 kv Bengkayang Substation (see Map A-1) with tower No. 7 (Coordinate X= , Y= ). For the sake of mitigating of insufficient ground clearance of conductors, there are an additional four intermediate/insertion towers of No. 76A, Page 64 of 76

71 99A, 110A, and 158A had been constructed. So in total, there will be 201 towers, or more two additional towers on the 275 kv Bengkayang-Jagoibabang route. Table A.1.1 Tower Changes of 275 kv Bengkayang Jagoibabang Transmission Line TOWER NUMBERS A B C D A A A A Tower inserted The 275/150kV Bengkayang substation has been shifted to North-Eastern direction at right hand side of the road, located adjacent to 150/20 kv Bengkayang substation to connect with Singkawang. The towers connecting to it were relocated (4 sites) and eliminated 2 sites. Map A-2 Tower re-routing of 275 kv Bengkayang Jagoibabang and 150 kv Bengkayang - Ngabang Transmission Lines Environmental review: The route to the new substation location at Bengkayang had less impact on forest land due to shorter distance of the Right of Way (ROW) but slightly more impact on rubber and palm oil plantation, and it also added one more crossing of the main National Road of Bengkayang - Jagoibabang and electricity medium voltage lines. No major impact and no special environmental management measures were encountered. During the construction of towers and stringing activities the environmental standard protection measures had been applied and thereby eliminated the expected associated impact. Page 65 of 76 Regarding land use of the alignment which was rubber and palm oil plantation, in general, the potential impacts to be experienced by affected households due to the permanent land acquisition for the tower bases were minor. The towers in West Kalimantan have been constructed higher than those of International standard, so the farmers may cultivate along the ROW area with the annual or perennial crops with its canopy up to 3 m in height.

72 The impact on traffic due to main road crossing could be neglected because no traffic congestion had been encountered caused by stringing activities. Scaffolding as temporary protection made of bamboo at both sides of the road eliminated the traffic disturbance. a.2) The new 275/150 kv Bengkayang substation is being developed adjacent to the new 150/20 kv substation of Bengkayang where it will connect with the 150 kv Bengkayang - Singkawang Transmission Line, but its construction was very slow due to financial matters. The landuse of the substation area was rubber plantation. The planned area was undulating and so it needed soil works to level the site. The higher soil level had been excavated to fill the lower level. No quarry from outside was needed for the embankment, all soil for embankment came from the same area. The 275/150 kv Bengkayang substation has been operated for receiving electric energy from Mambong substation in Sarawak. The energy is transmitted using 150 kv Ngabang bay (as temporary service) to Singkawang transmission lines. This temporary solution had to be taken because the 150 kv Bengkayang- Ngabang transmission line is not completed yet and at the time being the construction works for the 150 kv Bengkayang switchyard for the 150 kv Bengkayang-Singkawang transmission line is still ongoing. Environmental review: Impact on erosion and polluting the water body was minimal because there was no significant creek or river in that area. No embankment for land preparation using soil/material from other location outside, thus no hauling truck going in/out carrying soil that might cause an impact on air quality such as fugitive dust and exhaust gas. No wild animal affected, since the area was rubber plantation and bushes. Close to the substation area at approximately 100 to 300 m, there is an elementary school, but without impact on children since there is no access for them to go to the site. The substation area have been fenced to prevent anybody from entering the site without permission. b) Tower re-routes of 150 kv Bengkayang - Ngabang Transmission Line According to the original plan, this route would comprise of 260 towers (Tower No 1 in Bengkayang to Tower 260 in Ngabang). The total tower will become 280 after several modifications to the number of the towers: Due to 275/150/20 kv Bengkayang Substation shifted north-eastern, it had been decided to eliminate three towers (number 1 to 3) and add seven new towers (1A, 2A, 3A, 4A, 5A, 6A, and 7A), see Map A-2. According to recalculation of the design regarding the conductor ground clearance, it had been decided to eliminate two towers (Tower No. 157 and 158), but in addition one insert tower (Tower No. 24A) will be required. Seven towers to be shifted due to relocation of 150/20 kv Ngabang Substation (see Map A-3.1). It is planned that nine towers will be added to connect T.1 to Tayan substation. Page 66 of 76

73 Table A.1.2. TOWER CHANGES OF 150 KV BENGKAYANG NGABANG TRANSMISSION LINE TOWER NUMBERS 1A 2A 3A 4A 5A 6A 7A A Note: Tower Changes Due to landuse problem on previously proposed Ngabang Substation, the towers connecting to it have been planned to be relocated. (The new route survey and design had been completed). As the new Ngabang substation is now closer to Tayan direction, tower No. 117 up to 133 of Tayan - Ngabang Transmission Line has been added to Bengkayang - Ngabang Transmission Line. Accordingly, the total number of towers of Bengkayang - Ngabang will become 280. b.1) Re-routes and addition of 7 new towers (1A, 2A, 3A, 4A, 5A, 6A, and 7A). Environmental review: Of the seven new additional tower sites of 150 kv Bengkayang Ngabang Transmission Line, there are four towers which will be constructed in parallel route to the completed 150 kv Bengkayang - Singkawang Transmission Line. The latter route is on the western side and the Bengkayang - Ngabang Transmission Line route is on the eastern side. The landuse of the new alignment is palm oil, rubber plant and bushes. There is no protected wild animal, so the impact on flora and fauna is considered insignificant. The new route is far from the river and other water bodies, impact on sedimentation and water quality caused by new alignment can be neglected. b.2) Re-routes due to relocation of originally proposed Ngabang substation. Nine new towers will be constructed due to the relocation of the originally planned Ngabang substation site, out of which seven towers will belong to the previous Bengkayang-Ngabang alignment and two towers belong to the previous Ngabang - Tayan alignment. The footprint of the proposed tower sites has been surveyed and the tower types have been designed. Page 67 of 76

74 Map A-3.1 Tower re-routes of 150 kv Bengkayang - Ngabang Transmission Line at originally proposed Ngabang substation Note: The green mark (T.259) was planned for Ngabang substation, but now it is used as dwelling area, so it had been decided to relocate the substation to the South-East of Ngabang (see Map No. A-3.2) Tower of Tayan Ngabang shifted to become Bengkayang-Ngabang Ngabang SS Tayan Ngabang route shifted to Bengkayang- Relocated Bengkayang Ngabang Connected Ngabang route route to 116B 116A Page 68 of 76 Due to (New) Ngabang substation shifted southward, towers (yellow mark) are to be relocated. Environmental review: The new alignment of the 150 kv transmission line passes through gentle area with landuse of rubber plantation and mixed garden. The area is far from the water body, so erosion and sedimentation will be insignificant. There is no protected wild animal, so the impact on flora and fauna is considered insignificant. Tower T.252 toward tower T.259 as the end tower of 150 kv Bengkayang - Ngabang route had been decided to be shifted by approximately 700 m southern of original route to connect with the tower of the Ngabang Tayan Transmission Line. It will overpass the regency road and the green area along the creek in between the highly growing residential area. No significant impact is anticipated along this relocated route. c) Tower re-routing of 150 kv Ngabang Tayan Transmission Line The planned number of towers of the original plan for 150 kv Tayan Ngabang Transmission Line was 133, counting starts from Tayan substation. The total number of towers will become 128 due to relocation of Ngabang and Tayan substations. c.1) Tower changes to connect 150 kv Ngabang substation. The new 150/20 kv Ngabang Substation is under construction near to the previous tower No T.116 of the 150 kv Tayan - Ngabang Transmission Line (x= ; y= ). This tower was located adjacent with and on the right hand side of the main road of Pontianak Tayan - Ngabang in the village of Tebedak, Ngabang Subdistrict, Landak Regency (see Map A-3.2).

75 Map A-3.2 Tower re-routes of 150 kv Bengkayang - Ngabang Transmission Line Environmental review: The area of the New Ngabang substation is approximately 1 ha. The topography was undulating and the level of the area at about 1 to 4 m higher than the main road. There is no major settlement close to the area. To level the site, soil works had been conducted in March - April No quarry was needed for embankment and no excess soil to be moved in/out from the site, so there was no major impact on traffic caused by the land preparation. Impact on water quality during the land preparation was insignificant, since the river is about 1.5 km away. The landuse of the proposed new substation was mixed vegetation that consisted of bamboo, rubber trees and other wood trees. No protected fauna was found in that area. The Tayan - Ngabang transmission line will be relocated from T.114 up to T115. In the alignment of those towers are palm oil plantations for which no significant environmental impact is expected. c.2) Tower additions to connect with 150 kv Tayan substation In the original tower schedule, the first tower (T.01) of Tayan is not adjacent to the existing Tayan substation, because the previous planned Tayan substation was relocated about 2.5 km southward due to land acquisition and other consideration of the Siantan-Tayan transmission line route. The Tayan-Ngabang transmission line needed nine additional towers (1A, 1B, 1C, 1C1 1D, 1D1, 1E, 1F and 1G). Environmental review: The direct route will cross the national road that connects Pontianak with several regencies in eastern part of West Kalimantan and in the future to southern part of West Kalimantan after the Kapuas (1.5 km length) bridge has been completed. The crossing point of the transmission lines with that important road will be in the area which is very close to the cross junction road connecting Tayan Sosok. That area is a new high value commercial area where several buildings (some of them with two storey floors) have been built along those road, leaving relatively very narrow corridors that could be used as the route for the transmission line. Page 69 of 76

INO: West Kalimantan Power Grid Strengthening Project

INO: West Kalimantan Power Grid Strengthening Project Environment Monitoring Report # Quarterly Report March 2016 INO: West Kalimantan Power Grid Strengthening Project Prepared by Joint Venture Of Tractebel Engineering Ltd and Powergrid International Limited

More information

WEST KALIMANTAN POWER GRID STRENGTHENING PROJECT Reducing Indonesia s Oil Dependency While Fostering Regional Cooperation

WEST KALIMANTAN POWER GRID STRENGTHENING PROJECT Reducing Indonesia s Oil Dependency While Fostering Regional Cooperation WEST KALIMANTAN POWER GRID STRENGTHENING PROJECT Reducing Indonesia s Oil Dependency While Fostering Regional Cooperation Construction of the Bengkayang Substation Sohail Hasnie Oil fuels all power generation

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

POWER GRID IMPROVEMENT PROJECT

POWER GRID IMPROVEMENT PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Draft Environmental Code of Practices POWER GRID IMPROVEMENT PROJECT (Project ID: P149599)

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER EDUCATION 3835 East Thousand Oaks Boulevard, #365 Westlake Village, California 91362 Telephone: (805) 494-0444 Facsimile: (805) 494-0441

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

Japanese ODA Loan. Ex-Ante evaluation

Japanese ODA Loan. Ex-Ante evaluation Japanese ODA Loan Ex-Ante evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Matarbari Ultra Super Critical Coal-Fired Power Project (I) Loan Agreement: June 16, 2014 Loan

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Lumut Balai Geothermal Power Plant Project Loan Agreement: March 30, 2011 Loan Amount: 26,966 million

More information

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) PROJECT DESCRIPTION: (Enter Type of Project Planning Cost Estimate as Title)

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES PART I GENERAL 1.02 The objective of this section is to reduce the negative impacts of construction on trees. Tree protection

More information

TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK

TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK TOWN OF OCEAN RIDGE CONSTRUCTION SITE MANAGEMENT HANDBOOK I, swear (affirm) that I have read the Town of Ocean Ridge s Construction Site Management Handbook in its entirety and do hereby agree to comply

More information

Cranes and Derricks Standard Summary. April, 2010

Cranes and Derricks Standard Summary. April, 2010 Cranes and Derricks Standard Summary April, 2010 New Crane Regulations Federal OSHA proposed Crane and Derrick Standard in October, 2008. Expected final Federal regulation: June 2010?? In effect now in

More information

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions) Adams Co. Conservation District 670 Old Harrisburg Road, Suite 201 Gettysburg, PA 17325 Telephone: 334-0636 Fax: 337-0730 www.adamscounty.us Erosion and Sediment Pollution Control Guidelines for Residential

More information

Review Zone Application for D&R Canal Commission Decision

Review Zone Application for D&R Canal Commission Decision Review Zone Application for D&R Canal Commission Decision MEETING DATE: December 21, 2016 DRCC #: 16-4345 Latest Submission Received: December 7, 2016 Applicant: Robert McCarthy, PE PSE&G 4000 Hadley Road,

More information

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10 Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors Northeast Utilities Safety 12/10 How Electric Utilities Work Plan the Work & Work the Plan! Agenda Introduction

More information

TEMPORARY FACILITIES

TEMPORARY FACILITIES 04.A GENERAL SECTION 4 TEMPORARY FACILITIES 04.A.01 Plans for the layout of temporary construction buildings, facilities, fencing, and access routes and anchoring systems for temporary structures shall

More information

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections. Village of Vernon Hills Community Development Department 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http:// www.vernonhills.org FENCES This hand out is for REFERENCE

More information

LIST OF SUSTAINABILITY POLICY

LIST OF SUSTAINABILITY POLICY LIST OF SUSTAINABILITY POLICY 1. Sustainability Palm Oil Production Policy in FGV Group 2. Equal Opportunities Policy 3. Communications Policy 4. Steep Slope and Riparian Reserved Protection Policy 5.

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Environmental Assessment Matrix

Environmental Assessment Matrix For FCC Use Only Date: Customer Name: Environmental Assessment Matrix Loan Number: Please complete each question. Some answers may require additional information. Attach additional documentation where

More information

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri Operating Procedure SOP # Date: Page 1 of 10 Classifications: OCC Rail Dispatchers Maintenance of Way - Contractors Other Departments: Real Estate Operation Safety - Risk Management - Engineering & New

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers 4.1-a PERVIOUS PAVEMENT Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers DESCRIPTION Pervious pavement is any system comprised of a load bearing surface that allows for movement of

More information

Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi

Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi Shimamura, Mitsubishi UFJ Research and Consulting Co.,

More information

Planning & Building Department. Requirements for Erosion and Sediment Control

Planning & Building Department. Requirements for Erosion and Sediment Control Planning & Building Department 455 County Center, 2nd Floor Redwood City, California 94063 Tel: 540/863-4161/Fax: 650/363-4849 Mail Drop PLN122 plngbldg@smcgov.org http://planning.smcgov.org Requirements

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Audit Approach to FAC Transmission Vegetation Management FRCC Webinar

Audit Approach to FAC Transmission Vegetation Management FRCC Webinar Audit Approach to FAC-003-2 Transmission Vegetation Management FRCC Webinar September 2013 Ground Rules All participants will be muted upon sign-on Please keep your phone on mute unless asking a question

More information

Town of Fortville Utility Street Standards

Town of Fortville Utility Street Standards Town of Fortville Utility Street Standards SECTION 02101 - TEMPORARY EROSION AND DUST CONTROL PART 1 - GENERAL 1.1 DESCRIPTION A. Temporary Erosion and Dust Control measures must meet the current Town

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

City of Tacoma Surface Water Management Manual

City of Tacoma Surface Water Management Manual City of Tacoma Surface Water Management Manual Volume IV Source Control BMPs Prepared by: Tacoma Public Works Environmental Services January 2003 Table of Contents Chapter 1 Introduction to Volume IV...

More information

CAL/OSHA ELECTRICAL HIGH VOLTAGE

CAL/OSHA ELECTRICAL HIGH VOLTAGE Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to electrical exposure to high voltage for employees and contractors

More information

Worksite Safety Update Promoting safety in road construction

Worksite Safety Update Promoting safety in road construction Worksite Safety Update Promoting safety in road construction No 122 August 2012 In this Edition: Work Near Overhead and Underground Utility Services Page 1 The Regional Rail Link Experience Page 9 This

More information

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes. 1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined

More information

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Handling and Storage of Materials...1 5.3 Testing and Approval...1 5.4

More information

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 The United States Forest Service (USFS), Shawnee National Forest (SNF), is analyzing a request from Ameren Services (Ameren), a group

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities

EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities OSHAcademy Course 500 Study Guide EM 385 SAFETY AND HEALTH CERTIFICATION COURSE SECTION 4 Edited by: Steven Geigle,

More information

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction 2.7 Generic Mitigation Measures 2.7.1 Avifauna CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction Vehicles and machinery can impact on natural vegetation

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan EMP for the Stage 1 Construction and Operation of the Trainers Allotment Area at the Pakenham Racecourse located at Nar Nar Goon / Longwarry Road, Tynong Pty Ltd abn: 44 706

More information

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No. d/b/a National Grid and Clear River Energy LLC (Burrillville Interconnection Project) RIPUC Dkt. No. Testimony of David J. Beron, P.E., P.M.P. November, 0 0-v R.I.P.U.C. Dkt. No. 0 0 INTRODUCTION Q. Please

More information

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei

More information

SECTORAL ENVIRONMENTAL ASSESSMENT

SECTORAL ENVIRONMENTAL ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF MACEDONIA Regional and Roads Program Support Project SECTORAL ENVIRONMENTAL

More information

Section: TABLE OF CONTENTS Temporary Facilities. 04.A General B Access and Haul Roads

Section: TABLE OF CONTENTS Temporary Facilities. 04.A General B Access and Haul Roads Section 4 TABLE OF CONTENTS Temporary Facilities Section: Page 04.A General... 4-1 04.B Access and Haul Roads... 4-3 4-i SECTION 4 Temporary Facilities 04.A General. 04.A.01 Plans for the layout of temporary

More information

Constraints on how the Contractor Provides the Works

Constraints on how the Contractor Provides the Works Constraints on how the Contractor Provides the Works [DELETE AS APPROPRIATE: WHERE NOTIFIABLE CDM APPLIES:] CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2007 In line with the requirements of the above

More information

DISTRIBUTION OPERATIONS AND MAINTENANCE

DISTRIBUTION OPERATIONS AND MAINTENANCE EB-00-0 Exhibit F Schedule Page of 0 DISTRIBUTION OPERATIONS AND MAINTENANCE PREVENTIVE MAINTENANCE Preventive Maintenance is intended to maintain or improve customer service reliability, extend equipment

More information

Chapter 13 Management and Implementation

Chapter 13 Management and Implementation Chapter 13 Management and Implementation TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Overview of AGT Region Operating Management System... 13-1 13.3 Construction

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

Bhutan: Rural Renewable Energy Development Project (Part D Biogas Plants)

Bhutan: Rural Renewable Energy Development Project (Part D Biogas Plants) Environmental Monitoring Report Annual Report November 2016 Bhutan: Rural Renewable Energy Development Project (Part D Biogas Plants) Prepared by the Department of Renewable Energy, Royal Government of

More information

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan

ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan Marine Corps Base Hawaii NPDES Permit No. HI 000007 Prepared by: Marine Corps Base Hawaii August 2015 Table

More information

5.0 SURFACE WATER CONTROL MEASURES

5.0 SURFACE WATER CONTROL MEASURES 5.0 SURFACE WATER CONTROL MEASURES After performing the analysis summarized above, Burns & McDonnell civil engineers, construction personnel, and environmental personnel walked both Newgate/Phelps Road

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification 1. A project preparatory technical assistance (PPTA) is required to prepare all documents for the sector project framework and core

More information

Sherman Library Maintenance Handbook for Porous Asphalt

Sherman Library Maintenance Handbook for Porous Asphalt Sherman Library Maintenance Handbook for Porous Asphalt Porous asphalt systems are an effective means of stormwater management. Unlike traditional pavements, rainfall drains through the pavement surface

More information

MALAYSIA. Soil Resource Management

MALAYSIA. Soil Resource Management Paper presented in the Asian Soil Partnership Consultation Workshop on Sustainable Management and Protection of Soil Resources 12 14 th May 2015; Bangkok,Thailand MALAYSIA Soil Resource Management Presented

More information

What kinds of pollution are there?

What kinds of pollution are there? 1 What kinds of pollution are there? Water Pollution Solid Waste Air 2 What type of pollution? 3 What type of pollution? 4 What type of pollution? 5 Effects of Air Pollution Health problems Damage to the

More information

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY 1. PURPOSE: SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY The purpose of this policy is to establish procedures to facilitate compliance with federal, state and local stormwater regulations

More information

4. GENERAL REQUIREMENTS

4. GENERAL REQUIREMENTS 4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

New York Community Solar Facility Decommissioning Plan

New York Community Solar Facility Decommissioning Plan New York Community Solar Facility Decommissioning Plan July 2017 Prepared For: Town of Dryden, NY Delaware River Solar 33 Irving Place, Suite 1090 New York, NY 10003 Table of Contents Page 1. Introduction

More information

DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS. Wireline Occupancies

DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS. Wireline Occupancies DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS Wireline Occupancies OFFICE OF: VICE PRESIDENT ENGINEERING JACKSONVILLE, FLORIDA ISSUED: September 15, 2003 REVISED: December 16, 2016 THIS PAGE BLANK DESIGN

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 - ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads,

More information

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018)

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018) ADOPTED BY CHOCTAW LAKE BOARD OF TRUSTEES ORIGINAL APPROVAL SEPTEMBER 20, 1990 REVISED AND APPROVED AUGUST 10, 2004, JANUARY 9, 2018 THIS DOCUMENT IS A PART OF THE CLPOA BUILDING CODE CHANGES TO THIS DOCUMENT

More information

Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines

Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines 1910.269(p) and (q) of Electric Power Generation, Transmission, and Distribution Note: The below information applies only

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Sector: AGRICULTURE Sub-Sector: IRRIGATION Activity: Maintenance and Rehabilitation of Irrigation projects. Qty. in unit

Sector: AGRICULTURE Sub-Sector: IRRIGATION Activity: Maintenance and Rehabilitation of Irrigation projects. Qty. in unit ANNEX AGR I - 7 Sector: AGRICULTURE Sub-Sector: IRRIGATION Activity: Maintenance and Rehabilitation of Irrigation projects Priority within the Sector: First Total requested fund : Code Item Description

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

Indonesia - Lahendong II Geothermal Power Project (P096677) Environmental and Social Due Diligence

Indonesia - Lahendong II Geothermal Power Project (P096677) Environmental and Social Due Diligence Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Indonesia - Lahendong II Geothermal Power Project (P096677) and Social Due Diligence

More information

BOZEMAN YELLOWSTONE INTERNATIONAL AIRPORT GALLATIN AIRPORT AUTHORITY 850 GALLATIN FIELD ROAD, SUITE 6 BELGRADE, MT HANGAR INFORMATION

BOZEMAN YELLOWSTONE INTERNATIONAL AIRPORT GALLATIN AIRPORT AUTHORITY 850 GALLATIN FIELD ROAD, SUITE 6 BELGRADE, MT HANGAR INFORMATION BOZEMAN YELLOWSTONE INTERNATIONAL AIRPORT GALLATIN AIRPORT AUTHORITY 850 GALLATIN FIELD ROAD, SUITE 6 BELGRADE, MT 59714 HANGAR INFORMATION Thank you for inquiring about building a hangar at Bozeman Yellowstone

More information

STANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018

STANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018 STANDARD CONSTRUCTION DETAILS REVISED - JANUARY 2018 TABLE OF CONTENTS STORM WATER POLLUTION PLAN NOTES - - - - - - - - - - - - - - - - - - - - - - - - - SD-EC01 SILT FENCE NOTES - - - - - - - - - - -

More information

REPORT STATUS: DATE: Report n :

REPORT STATUS: DATE: Report n : REPORT: Expanded clay LWA in CEA Lightweight fill and thermal insulation products for civil engineering applications. Installation and structural quality control on site. STATUS: Technical report DATE:

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty

More information

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

City of Aliso Viejo Stormwater Program 2017 ANNUAL WATER QUALITY MANAGEMENT PLAN FOR HOMEOWNER ASSOCIATIONS AND PROPERTY MANAGEMENT COMPANIES

City of Aliso Viejo Stormwater Program 2017 ANNUAL WATER QUALITY MANAGEMENT PLAN FOR HOMEOWNER ASSOCIATIONS AND PROPERTY MANAGEMENT COMPANIES City of Aliso Viejo Stormwater Program 2017 ANNUAL WATER QUALITY MANAGEMENT PLAN FOR HOMEOWNER ASSOCIATIONS AND PROPERTY MANAGEMENT COMPANIES ANNUAL SUBMITTAL FORM DEADLINE: 5:00 PM ON FEBRUARY 15, 2017

More information