1 DIVISION 3 CONCRETE - SECTION GENERAL 1.1 Description.1 The Work of this Section as indicated in the Drawings or Specifications includes Bonded Concrete Topping over core slab and all other of Concrete s..2 Related Work Specified Elsewhere:.1 Section Substitutions.2 Section Cast-In-Place Concrete.3 Division 9 - Finishes (Various ing Sections).4 All other Sections and Drawings to be reviewed 1.2 Quality Assurance.1 The Company performing the Work of this Section must have a minimum of five (5) years recent experience in similar installations..2 Workers must be skilled and each have a minimum of five (5) years experience. 1.3 Reference Standards.1 ASTM C309, Specification for Liquid Membrane Forming Compounds for Curing Concrete..2 CAN/CSA-A23.1-M90/A23.2-M90, Concrete Materials and Methods of Concrete Construction, Specification for Liquid Membrane Forming Compounds for Curing Concrete. 1.4 Tolerances.1 Levels of finished concrete floors and floors under finished flooring applications shall be within 1/4 (6mm) of established elevations in any 20-0 (6000mm) square area and sufficiently even to contact a 10-0 (3000mm) long straightedge with a tolerance of 1/4" (6mm). RAA Township of South Frontenac Fire & Rescue Station No
2 1. GENERAL - Continued 1.5 Co-Operation 1.6 Job Conditions 2. PRODUCTS 2.1 Materials.1 Ensure that concrete supplied for slabs does not contain admixtures which will be incompatible with floor hardener materials..1 Perform the Work only when environmental conditions are as specified in CAN/CSA-A23.1-M90/A23.2-M90..2 Ensure that adequate temporary heating is provided as required to perform the Work in cold weather..3 Provide adequate moisture, sun shades and wind barriers to prevent too rapid drying of concrete during hot weather..4 Ensure that finished concrete floor areas are protected from abrasion from foot or wheeled traffic and from damage caused by spillage of oil or other harmful materials..1 Concrete Materials: In accordance with Section Cast-In-Place Concrete..2 Hardener Aggregate: Emery grit, Durafax No. 1, or approved alternate..3 Curing Sheet: 2 mil. Polyethylene or waterproof paper..4 Sealing Compound: Excel Clear Waterproofing. For use only where concrete floor is not to be painted..5 Curing Compound: Where concrete floors are to be left exposed, unpainted and concrete cannot be water cured; use only non-volatile curing compounds conforming to ASTM C309 such as 'Planicure 65' by Mapei or approved alternate..6 Grout: Non-shrink grout In-Pakt by Sternson Limited or approved alternate..7 Stain: Use Chromax integral stain (or apporved alternate) added to concrete mix by concrete supplier. Colour to Architect s Later Selection. RAA Township of South Frontenac Fire & Rescue Station No
3 3. EXECUTION 3.1 Examination.1 Before commencing the Work of this Section, ensure that surfaces are acceptable to receive and maintain concrete finishing and that specified installation will be achieved..2 Commencement of the Work will denote acceptance of conditions and surfaces. 3.2 Bonded Concrete Topping.1 Conform to CAN/CSA-A Strength of concrete and mix to be in accordance with CAN/CSA-A Roughen concrete slab surface before placing topping. Use mechanical means to roughen slab, as may be required to ensure a bond with topping..4 Place each section in one operation..5 Take special precautions against plastic shrinkage cracking, in accordance with /CSA-A23.1, Clause 21, whenever rapid drying of topping may occur..6 Provide control joints in topping directly over control joints in slabs, with 3/16" (5mm) saw to depth of 2/3 topping thickness no later than 24 hours after placing. After 24 hours clean and install filler in joint. 3.3 Concrete.1 Immediately after placing, screed and darby concrete before any water has bled to the surface..2 Strike off concrete level to screeds leaving no low spots. If vibrators are used on straightedge ensure that concrete is not over vibrated causing segregation and collection of water and fines over the surface..3 Smooth concrete to an even plane with a darby or bull float and leave until bleed water and water sheen has disappeared. RAA Township of South Frontenac Fire & Rescue Station No
4 3. EXECUTION 3.3 Concrete - Continued.4 Proceed with finishings only when concrete has hardened sufficiently to support a worker with only slight footprint left on the surface..5 Finish concrete surface with power float or with metal hand floats in areas inaccessible to power floats. Floating shall embed large aggregate below the surface, consolidate mortar at the surface, provide even planes with no bumps or depressions, remove marks from edging and prepare the surface for further specified finishing. Do not bring water and fine material to the surface by overworking..6 Steel trowel floated surface with power trowels or hand trowels in areas inaccessible to power trowels. Proceed with trowelling only when there is no sheen on the surface. Repeat trowelling until the surface is brought to approved finish. Allow sufficient time between trowellings for additional set of concrete..7 Draw a soft bristled brush over steel trowelled surfaces to provide a very light broom surface where a non-skid floor is required..8 Finish floor surfaces shall be level dense with minimal aggregate showing and free of blemishes. 3.4 Hardened s.1 Apply hardener aggregate to floor surfaces as indicated in the Drawings or Specifications in two shakes, half of the aggregate for each shake..2 Apply the first shake when the concrete is firm enough to support worker and equipment and when standing water is present. Mechanically float aggregate into the surface..3 Apply the second shake and mechanically float as specified above for finishing..4 Apply total amount of aggregate at a rate of 26 ounces per square foot (3kg/sq m) of floor area. RAA Township of South Frontenac Fire & Rescue Station No
5 3. EXECUTION - Continued 3.5 Curing 3.6 Patching & Refinishing.1 Cure Concrete as specified in CAN/CSA-A23.1-M90/A23.2-M90 and by methods specified in 3.7 Concrete Schedule. Ensure that no curing compound is used which is detrimental to the bond of bedding for finish flooring or finish flooring materials. Where concrete curing compounds are used, sandblast floor finish after concrete is fully cured..1 Before the completion of project, patch and refinish defective surfaces to match surrounding areas with no discernable variation in appearance. 3.7 Concrete Schedule.1 Rough and Similar Horizontal Surfaces: Screed surfaces to an even, level or sloped surface to elevations as indicated in the Drawings or Specifications..2 : Ensure that the floor finishes are provided as indicated in the Drawings or Specifications. Verify with those performing the Work of applicable Sections that the proposed finishing is satisfactory for the Work they apply to the floors..3 Steel Trowel Finish: Smooth finish by hand and machine float, free from laitence, excessive water, trowel marks, blemishes and ridges for the Work of Section Ceramic Tile, Section Terrazzo, Section Slate ing, Section Resilient Sheet ing, Section Carpeting or Section Painting..4 Exposed s: Give floors exposed to view a steel trowel finish to provide a hard, smooth, dense surface free from laitence, excessive water, trowel marks, blemishes and discolouration. s to be sealed with one (1) coat of sealing compound. END OF SECTION RAA Township of South Frontenac Fire & Rescue Station No
A. Submittal Procedures: See Article 13 of the General Conditions.
SECTION 321313 - CONCRETE PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Driveways. 2. Roadways. 3. Parking lots. 4. Curbs and gutters. 5. Walks. B. Proposed Substitutions: See Article 2,
More informationDIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340
DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340 PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. The General provisions of the contract, including GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS AND
More informationB. Related Sections: 1. Division 07 Section "Joint Sealants" for sealing of expansion, contraction, control, and isolation joints in tile surfaces.
SECTION 093000 - CERAMIC TILE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More information***************************************************************************************************************
09330 QUARRY TILE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 09 30 16 ***************************************************************************************************************
More informationSECTION CONCRETE PAVING FOR PEDESTRIAN AREAS. A. This Section includes exterior cement concrete pavement for the following:
SECTION 321313 CONCRETE PAVING FOR PEDESTRIAN AREAS PART 1 GENERAL 1.1 SUMMARY A. This Section includes exterior cement concrete pavement for the following: 1. Walkways. 2. Courtyards. 3. Plazas. 4. Pedestrian
More informationKolorines Glass Mosaic Tiles Project Specification
Kolorines Glass Mosaic Tiles Project Specification SUGGESTED SPECIFICATION Glass Mosaic Tile Installation for Swimming Pools NOTES TO SPECIFIER: 1. Specify PremiumPlus Thin-Set mixed with CustomFlex Additive
More informationConcrete Framing: Slab on Grade
Concrete Framing: Slab on Grade Casting a Concrete Slab on Grade Concrete Slabs Subgrade Preparation Drainage Layer Slab Edges Vapor Retarder (Moisture Barrier) Reinforcing Pouring the Concrete Finishing
More informationSECTION SITE CONCRETE
SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationMay 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building
May 8, 2017 ADDENDUM #1 IFB 17-082 Resin Floor System For Highway Department Central District Building Addendum #1 is being issued to offer an alternate resin flooring system. 096700 FLUID-APPLIED FLOORING
More informationSECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES
GUIDE SPECIFICATION SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES PART 1 - SCOPE 1.01 WORK INCLUDED: 1.1.1 This guide covers the
More informationSECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION
ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00
More informationARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE
ARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE MANNINGTON COLORFIELDS SHEET RUBBER FLOORING Section 09 65 16 Sheet rubber Flooring (Thermoset Rubber) Created May 2012 Mannington Mills, Inc. P. O. Box
More informationCity of Brandon Division 2 Standard Construction Specifications Section January 2007 (Revision 2) Page 1 of 21 CONCRETE CONSTRUCTION
January 2007 (Revision 2) Page 1 of 21 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 STANDARDS 1.05 QUALITY ASSURANCE The General Conditions of the Contract,
More informationSuggested Specification for Tri-Patch Versatile Concrete Patching Compound
Suggested Specification for Tri-Patch Versatile Concrete Patching Compound SURFACE PREPARATION for Interior and Exterior Floor-Covering Installations. (Vinyl Composition Tiles, Sheet Vinyl, Rubber, Indoor
More informationSECTION CONCRETE PAVING SLABS SET IN MORTAR
SECTION 32 14 13.16 CONCRETE PAVING SLABS SET IN MORTAR (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs mortared to a concrete base and grouted joints
More informationSECTION 11 - REINFORCED AND PLAIN CONCRETE WORKS CONTENTS
CONTENTS SPECIFICATIONS SECTION NO. Scope 11.20 Codes and Standards 11.21 Form Release Agent 11.22 Supports, Chairs and Spacers 11.23 Reinforcement 11.24 Forms 11.25 Premoulded Joint Filler 11.26 Cement
More informationPPC Cement TUTORIAL. how to screed a floor
PPC Cement TUTORIAL how to screed a floor Pre-build: TOOLs & Materials ITEM Quantity Check. Builders bucket. Wheelbarrow 3. Shovel 4. Builder s line 5. 50mm steel pegs 6. Rigid timber forms 7. Flexible
More informationCustom Polishing Systems
Custom Polishing Systems VitraFlor by Bomanite Guideline Specification Standard Application PART 1 GENERAL SECTION 033000 CAST-IN-PLACE CONCRETE 1.1 RELATED DOCUMENTS A. Drawings and general provisions
More informationMANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade.
MANUFACTURER S SPECIFICATIONS Section 03330 LIME CONCRETE ST. ASTIER NATURAL HYDRAULIC LIME CONCRETE PART 1 GENERAL 1.01 General A. This section describes the requirements for floors and slabs on grade.
More informationEditing notes to assist users are included within bordered boxes. Delete these notes prior to final printing.
03360 CONCRETE FLOOR FINISHES This guide specification has been prepared by Dayton Superior Corporation to assist design professionals in the preparation of a specification section covering curing, sealing,
More informationSECTION EPOXY FLOORING SYSTEMS
SECTION 09800 EPOXY FLOORING SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationBITUMEN-SET PRECAST CONCRETE PAVING SLABS
SECTION 32 14 13.16 BITUMEN-SET PRECAST CONCRETE PAVING SLABS (1995 MasterFormat Section 02784) NOTE: This guide specification is the U.S. for concrete paving slabs adhered with a neoprene mastic to a
More informationCONCRETE POLISHING SPECIFICATION NEW OR EXISTING CONCRETE
CONCRETE POLISHING SPECIFICATION NEW OR EXISTING CONCRETE PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division
More informationFloor Preparation Recommendations. Best Practices to Prepare Concrete for Polishing
Floor Preparation Recommendations Best Practices to Prepare Concrete for Polishing Polishing Basics FACT #1 Poorly finished concrete WILL result in a substandard polishing process. Finished concrete is
More informationCTIOA Field Report
CERAMIC TILE INSTITUTE OF AMERICA, INC. 12061 Jefferson Blvd., Culver City, CA 90230-6219 CTIOA Field Report 84-2-2 SUBJECT: WORKING WITH PORTLAND CEMENT CONCRETE I. INTRODUCTION A. Concrete, like many
More informationTECHNICAL INFORMATION CEMSCREED 5
TECHNICAL DATA SHEET CEMSCREED 5 Ver May 2016 TECHNICAL INFORMATION CEMSCREED 5 Product Data Sheet No. 110/03 INTRODUCTION Tarmac Cemscreed 5 is a rapid drying floor screed developed by Tarmac to fulfil
More informationSECTION COMMON WORK RESULTS FOR CONCRETE SSPECIALTY COATINGS
SECTION 03 05 00 COMMON WORK RESULTS FOR CONCRETE 09 97 00 SSPECIALTY COATINGS Weld Crete ************************************************************************************************************************
More informationSpecial Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:
FAST TRACK FULL DEPTH CONCRETE REPAIR Item No. FULL DEPTH CONCRETE REPAIR Item No. PARTIAL DEPTH CONCRETE REPAIR Item No. FAST TRACK PARTIAL DEPTH CONCRETE REPAIR Item No. Special Provision No. 399S43
More informationPROJECT NAME: PROJECT ADDRESS: Farmers Market Structural Repairs 4-6 Gordon Street Guelph, Ontario DATE: November, 2010 I N D E X Page(s) Index... 1 to 1 Introduction... 1 to 1 DIVISION 04 - MASONRY Section
More information1. Division 09 Section "Rough Carpentry."
GREENSPOINT AND LAUDER RD. EC/PRE-KlK PAGE 1 SECTION 096400 - WOOD FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
More information1. Decks, balconies, and sun porches 2. Walkways, ramps, and stairways 3. Patios and courtyards
SECTION 07185 TRAFFIC MEMBRANE PART 1 GENERAL 1.1 SECTION INCLUDES A. Traffic membrane, consisting of welded seam PVC waterproofing, over f following surfaces: 1. Decks, balconies, and sun porches 2. Walkways,
More informationTILE TILE
09300 - TILE 09300-1 PART ONE: GENERAL 1.1 Description TILE 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance with the requirements
More informationSECTION EPOXY TERRAZZO
SECTION 09402 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to
More informationITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS
ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown
More informationB. American Concrete Institute 1. ACI 302, 1R-89 Guide for Concrete Floor and Slab Construction
SECTION 03360- CONCRETE FINISHES SPECIALIZED TERR-CON FLOORING SYSTEM PART 1-GENERAL 1.01 SUMMARY A. This section includes the following: 1. Standard placement of concrete and Terr-Con Aggregate 2. Grinding
More informationUFGS (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-07 16 19 (January 2007) ---------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-07 16 19 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-03 35 00.00 10 (May 2014) ----------------------------------- Preparing Activity: USACE Superseding UFGS-03 35 00.00 10 (November 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationRESILIENT FLOORING: Hot and Heavy - Secoya
160 South Industrial Blvd. Calhoun, GA 30701 Section 096519 RESILIENT FLOORING: Hot and Heavy - Secoya This document is intended as a suggested guide for editing your architectural guide specification.
More informationGUIDE SPECIFICATION
GUIDE SPECIFICATION 09 64 33.01 940 Centre Circle, Suite 1000 Altamonte Springs, FL 32714 Telephone: 407-260-9910 Fax: 407-260-9933 Toll Free: 800-800-5247 Web Site: http://www.kahrs.com This Guide Specification
More informationSECTION 3300 CAST-IN-PLACE CONCRETE
SECTION 3300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 DESCRIPTION A. This Section includes furnishing materials and installation of cast-in-place concrete as indicated on the Drawings and/or specified
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-03 01 30.71 (April 2006) ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-03930 (September 1999) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationSECTION CONCRETE. B. ACI 318 Building Code Requirements for Structural Concrete and Commentary
SECTION 03300 CONCRETE PART 1 GENERAL 1.01 SCOPE OF WORK Concrete foundation walls, sanitary structures, pipe encasements, thrust blocking and slabs on grade. 1.02 REFERENCES A. ACI 301 Specification for
More informationJoint Free Slabs On Grade Website:
Joint Free Slabs On Grade Website: www.jointfreeslabs.com Specification Revised March 2014 Warwick Colefax Robert Colefax Phone (02) 9999 6688 Phone (07) 4051 9466 Fax (02) 9999 6680 Fax (07) 4051 9477
More informationSECTION MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS
SECTION 09699 MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS PART 1 GENERAL 1.1 SECTION INCLUDES A. Testing and application of systems for the reduction of moisture resistant or water-proof
More informationSemstone Construction Details
Semstone Construction Details SP01-94 Treatment for Expansion Joints, Control Joints, and Structural Cracks, Vertical and Horizontal, for Non-Vehicular Traffic 1. Maintain joint/crack through coating.
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE STRUCTURES
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 904 JANUARY 1995 CONSTRUCTION SPECIFICATION FOR CONCRETE STRUCTURES 904.01 SCOPE 904.02 REFERENCES 904.03 DEFINITIONS TABLE OF CONTENTS 904.04 SUBMISSION
More informationINDUSTRY RECOMMENDATION EXTERIOR CONCRETE FLATWORK
INDUSTRY RECOMMENDATION for EXTERIOR CONCRETE FLATWORK Prepared by Ohio Concrete Inquires regarding this document may be addressed to: Ohio Concrete 2600 Corporate Exchange Dr., Ste. 165 Columbus, OH 43231
More informationSECTION FLEXIBLE PAVING
SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications
More informationCHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10
CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES 283 Chapter 10 FUNCTIONAL REQUIREMENTS FUNCTIONAL REQUIREMENTS 10.1 PLASTERWORK Workmanship i. All workmanship must be within the tolerances
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3
CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3
More informationGUIDE SPECIFICATION
GUIDE SPECIFICATION 09 64 33.01 Kährs Canvas Collection 940 Centre Circle, Suite 1000 Altamonte Springs, FL 32714 Tim Colgan Telephone: 407-492-2441 Fax: 407-260-9933 Tim.colgan@kahrs.com Web Site: http://www.kahrs.com
More informationEditing notes to assist users are separated from specification text by rows of asterisks. Delete these notes prior to final printing.
SECTION 09635 LIMESTONE FLOORING This guide specification has been prepared by TexaStone Quarries LLC to assist design professionals in the preparation of a specification section covering cut limestone
More informationCSI SECTION MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials
CSI SECTION 03 01 00 MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials EDITOR NOTE: The following guideline specification
More informationSECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS
SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint
More informationSECTION TILING
SECTION 093000 TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More information1.02 RELATED WORK: Refer to the following sections for related work:
SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete
More informationprospec.com Concrete Repair & Restoration
prospec.com Concrete Repair & Restoration Table of Contents Product Portfolio 3 Product Enhancements 4 Product Selection Matrices 5 Construction Grout & Precast Non-shrink grouts C-1107 Construction Grout
More informationA. This Section includes resinous flooring systems with epoxy body coat(s).
SECTION 096723 - RESINOUS FLOORING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes resinous flooring systems with epoxy body coat(s). 1. Application Method: Troweled (Slurry, Seeded or Broadcast
More informationSECTION INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING
SECTION 04210 INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING PART I GENERAL 1.1 SUMMARY A. Provide installation of new or replacement of masonry units and/or repointing of masonry units
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 096623 - RESINOUS MATRIX TERRAZZO FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationSECTION EPOXY TERRAZZO TILE WITH RECYCLED GLASS MATRIX
GlassPLANK GUIDE SPECIFICATION Manufacturer: GLASS RECYCLED LLC 2939 Irving Blvd Suite 305 Dallas TX 75247 (888) 523-7894 toll free voice www.glassrecycled.com SECTION 09 66 18 EPOXY TERRAZZO TILE WITH
More informationB. All work of the section shall comply with the conditions of the contract, the drawings and any special conditions forming a part of the contract.
SPECIFICATIONS PART ONE - GENERAL ------------------------------------------------------------------------ 1.01 General Description A. The Cementitious capillary waterproofing materials specified herein
More informationHI-TEK POLYMERS T-Poxy Terrazzo Arch Data
HI-TEK POLYMERS T-Poxy Terrazzo Arch Data PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationConstruction. SikaTop 111 Plus. Application Instructions. Sika Corporation
SikaTop 111 Plus Application Instructions SikaTop 111 Plus Two-component, polymer-modified, portland cement based. Fast-setting, screed mortar. Performance repair mortar for horizontal repairs and form
More informationInternational Polished Concrete Institute November 2006 Toll Free (866) Website
International Polished Concrete Institute November 2006 Toll Free (866) 421-9550 Website www.ipcionline.org E-mail info@ipcionline.org SECTION 03365 POLISHED CONCRETE FLOOR SYSTEM PART 1 GENERAL 1.1 SECTION
More informationTECHNICAL DATA SHEET AUS-FLEX MULTI
FLEXIBLE TILE & STONE ADHESIVE POLYMER & RUBBER REINFORCED INTERNAL & EXTERNAL USE SUITABLE FOR: PORCELAIN TILE ALL MASONRY SURFACES CERAMIC TILE CONCRETE QUARRY TILE RENDER, BRICK & BLOCK WORK MOSAIC
More information1.3 Work shall include all reinforcement and accessories necessary to complete installation.
CERAMIC TILING GENERAL INFORMATION 1.1 Ceramic mosaic tile floors and bases, glazed wall tile wainscots and walls, and marble thresholds. 1.2 Installation will typically be with latex-portland cement mortar
More informationWOOD ATHLETIC FLOORING
ROBBINS FLOATING ECLIPSE Page 1 of 7 Specification Note: The following specifications call out the material and default installation requirements necessary for the floor as recommended by Robbins Sports
More informationSpecifications. Specifications (Architectual) Metallic System. Metallic System
(Architectual) Metallic System Architectual NeverStrip Floor Coatings, 6-15 Mils Master Format Section 096700 Fluid Applied Flooring 1 of 6 NeverStrip Metallic High-Build Decorative Epoxy/Urethane Coating
More informationAdjusting approach to suit material leads to success. Silica Fume. for Concrete Bridge Decks By Tarif M. Jaber
Adjusting approach to suit material leads to success Silica Fume for Concrete Bridge Decks By Tarif M. Jaber lacing and consolidating concrete containing silica fume is P essentially the same as for concrete
More informationAdvantages: Advantages include:
Elgin, Illinois Hi-Tek Polymers Floor Description: Hi-Tek Polymers Floor is a decorative thin-set epoxy system of 1/4" (6,3mm) to 3/8 (MM) which meets all the standards set by the NTMA (National Terrazzo
More informationA. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements.
TECHNICAL SPECIFICATIONS SEWER MANHOLE REHABILITATION SYSTEM WITH A PROTECTIVE CEMENT LINER AND HIGH BUILD EPOXY COATING (As Provided by Standard Cement Materials) FOREWORD The following specification
More informationFLUID APPLIED WATERPROOFING
SECTION 07120 FLUID APPLIED WATERPROOFING PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03300 - Cast-In-Place Concrete. 2. 09200 - Metal Studs, Metal Lath, Suspension Ceilings, Plaster, and Stucco.
More informationSECTION mil thickness COLD FLUID-APPLIED WATERPROOFING
SECTION 07 14 16 CCW-MIRASEAL @ 120 mil thickness COLD FLUID-APPLIED WATERPROOFING PART 1 - GENERAL 1.1 SECTION INCLUDES: Installation of waterproofing membrane on surfaces indicated on drawings, consisting
More informationTILING SPECIFICATIONS
TILING SPECIFICATIONS SPECIFICATION NUMBER: NR204-16 PREPARED BY: Mike Cubley PREPARED FOR: Porcelain Plus ATTENTION: Kirk Pollock INSTALLATION: 712 Turner Floor and Wall Tiling Specification. M40 STONE/
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing
More informationSECTION TILING
SECTION 09 30 00 TILING PART 1 - GENERAL 1.1 SUMMARY A. Section includes tile as indicated on new surfaces and as specified. 1.2 SUBMITTALS A. Samples: 1. Submit samples of colors and sizes of tile. B.
More information.1 Formwork for cast-in-place concrete with shoring, bracing, and anchorage.
03 10 00 CONCRETE FORMING AND ACCESSORIES Page 1 of 4 1 General 1.1 SECTION INCLUDES.1 Formwork for cast-in-place concrete with shoring, bracing, and anchorage..2 Form accessories..3 Form stripping. 1.2
More informationAppendix F. Checklist for Concrete Pre-Construction Conference. Best Practices Guidelines for Concrete Construction
Appendix F Checklist for Concrete Pre-Construction Conference 45 Introduction Pre-construction meetings are of prime importance in planning concrete construction work because many potential problems can
More informationPAVING SLABS ON A CONCRETE BASE
SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.
More informationSECTION EPOXY RESIN FLOORING WITH INTEGRAL COVE BASE
SECTION 09730 EPOXY RESIN FLOORING WITH INTEGRAL COVE BASE PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03300 - Cast-in-Place Concrete. 2. 09000 - Patching and Finishes. 3. 09900 - Painting. 4.
More informationConstruction Specification
PART 1 - GENERAL 1.01 SUMMARY A. Furnish all labor, materials, tools and equipment required for completing tile work and related items indicated on the drawings and herein specified. B. Related work specified
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 093000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationContents. SUPPORTING PRODUCTS UL-Primer 24 Moisture Seal 24 Megalastic 25
Floor Levelling 2 Contents Bostik Green Commitment 4 Pictograms 7 Cementitous Floor Levelling Compounds 8 Floor Levelling Characteristics, Specifications And Technical Support 9 Application Instructions
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as
More informationConcrete. Chapter 10 Properties of Fresh Concrete. Materials of Construction-Concrete 1. Wikipedia.org
Wikipedia.org Concrete Chapter 10 Properties of Fresh Concrete Materials of Construction-Concrete 1 What is Concrete? Concrete is a composite material that consists of a cement paste within which various
More informationB. Store products in dry spaces protected from the weather, with ambient temperatures maintained between 50 and 90 deg F (10 and 32 deg C).
SECTION 09651 - RESILIENT TILE FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationRESILIENT FLOORING: Select Step Wood
160 S. Industrial Blvd Calhoun, GA 30701 Section 096519 RESILIENT FLOORING: Select Step Wood This document is intended as a suggested guide for editing your architectural guide specification. Mohawk Group
More information1. Rapid Set Cement. 2. Methods of preparation. 3. How to stage a job site. 4. Installation Mix, place, finish. 5. Coloring the TRU.
1. Rapid Set Cement 2. Methods of preparation 3. How to stage a job site 4. Installation Mix, place, finish 5. Coloring the TRU natural TRU Rapid Set is NOT Portland Cement Rapid Set is a Calcium Sulfoaluminate
More informationCaparol System PRO Data sheet
System features Expanded polystyrene insulation Cost effective solution Excellent detailing options Proven technology Wide variety of colours Reliable protection and crack resistance Proven track record
More informationALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JULY 2017 SPECIFICATION FOR CONCRETE PATCHING MATERIALS
ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JULY 2017 SPECIFICATION FOR CONCRETE PATCHING MATERIALS SCOPE - This specification contains approval procedures and requirements necessary for qualifying
More informationSECTION TERRAZZO FLOOR TILE
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 09 66 16 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // ----- // if not applicable to project. Also delete any other item or
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as
More informationARDEX GUIDE SPECIFICATION ARDEX MRF Moisture-Resistant, Rapid-Drying, Skimcoat Patching Underlayment
ARDEX GUIDE SPECIFICATION ARDEX MRF Moisture-Resistant, Rapid-Drying, Skimcoat Patching Underlayment SECTION 03 01 30 Maintenance of Cast-In-Place Concrete PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings,
More informationThe American Society of Concrete Contractors Concrete Polishing Council SECTION BONDED ABRASIVE POLISHED CONCRETE FLOORS
SECTION 033543 - BONDED ABRASIVE POLISHED CONCRETE FLOORS PART 1 GENERAL 1.1 SUMMARY RETAIN THE BRACKETED OPTION IN THE FOLLOWING SUB-PARAGRAPH WHEN SPECIFYING COLORED FINISH. A. Section Includes: Products
More informationSECTION BRICK MASONRY ASSEMBLIES
PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Face brick. 2. Mortar and grout. 3. Ties and anchors. 4. Miscellaneous masonry accessories. 1.2 SUBMITTALS A. Product Data: For each type
More informationTEX COTE 600 TEXTURED COATING MASONRY PROTECTIVE COATING
SECTION 09960 - TEXTURED COATINGS Coating System Submittals Guide Specification TEX COTE 600 TEXTURED COATING MASONRY PROTECTIVE COATING (SPLIT FACE OR SAND FINISH BLOCK) 1. TEX COTE 600, Textured Coating
More informationSECTION TILE CARPETING
SECTION 096813 TILE CARPETING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationNarrow Modular Pavers (NMP) for Mortar-Set Concrete Tiling Installations
The following specification refers to the Stepstone, Inc. product known as: Narrow Modular Pavers (NMP) for Mortar-Set Concrete Tiling Installations Narrow Modular Pavers are part of the California Architectural
More information