B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.
|
|
- Bryan Cross
- 5 years ago
- Views:
Transcription
1 SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section includes the following: 1. Preparing subgrades for pavements. 2. Subbase course for asphalt paving. 3. Grading for lawn repair B. Related Sections include the following: 1. Division 32 Section "Lawns and Grasses" for finish grading, including placing and preparing topsoil for lawns and plantings. 1.3 DEFINITIONS Backfill: Soil materials used to fill an excavation. B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. C. Excavation: Removal of material encountered above sub grade elevations. 1. Additional Excavation: Excavation below subgrade elevations as directed by Engineer. Additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work. 2. Bulk Excavation: Excavations more than 10 feet in width and pits more than 30 feet in either length or width. 3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated dimensions without direction by Engineer. Unauthorized excavation, as well as remedial work directed by Engineer, shall be without additional compensation. D. E. F. G. Fill: Soil materials used to raise existing grades. Aggregate Base Course: Layer placed between the subgrade and black base course for asphalt paving. Sub grade: Surface or elevation remaining after completing excavation, or top surface of a fill or backfill immediately below subbase, drainage fill, or topsoil materials. Utilities include on-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings. 1.4 SUBMITTALS Material Test Reports: From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated: SECTION EARTHWORK -1-
2 1. Laboratory compaction curve according to ASTM D 1557 for each on-site or borrow soil material proposed for fill and backfill. B. Material Data: Sieve analysis for specified aggregate. 1.5 QUALITY ASSURANCE Applicable Standards: 1. American Society for Testing and Materials as referenced. 2. Missouri Department of Transportation (MoDOT), Missouri Standard Specification for Highway Construction as referenced. B. Geotechnical Testing Agency Qualifications: An independent testing agency qualified according to ASTM E 329 to conduct soil materials and rock-definition testing, as documented according to ASTM D 3740 and ASTM E PROJECT CONDITIONS Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted in writing by Engineer and then only after arranging to provide temporary utility services according to requirements indicated: 1. Do not proceed with utility interruptions without Engineer's written permission. 2. Contact utility-locator service for area where Project is located before excavating. PART 2 -PRODUCTS 2.1 SOIL MATERIALS General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations. B. Satisfactory Soils: ASTM D 2487 soil classification groups GW, GP, GM, SW, SP, and SM, or a combination of these group symbols; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter. C. Unsatisfactory Soils: ASTM D 2487 soil classification groups GC, SC, ML, MH, CL, CH, OL, OH, and PT, or a combination of these group symbols. 1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction. D. Backfill and Fill: Satisfactory soil materials. E. Aggregate Base: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1/2- inch sieve and not more than 35 percent passing a No. 30 sieve per MoDOT Specification Section , Type 1. F. 1/2-inch Clean Aggregate: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone; ASTM D 2940; with 100 percent passing a 1- inch sieve and 95% retained on a 1/2-inch sieve. SECTION EARTHWORK -2-
3 PART 3 -EXECUTION 3.1 PREPARATION Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations. B. Protect subgrades and foundation soils against freezing temperatures or frost. Provide protective insulating materials as necessary. c. Provide erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing; water runoff or airborne dust to adjacent properties and walkways. 3.2 DEWATERING B. Prevent surface water and ground water from entering excavations, from ponding on prepared sub grades, and from flooding Project site and surrounding area. Protect subgrades from softening, undermining, washout, and damage by ram or water accumulation. 1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches. 2. Install a dewatering system to keep subgrades dry and convey ground water away from excavations. Maintain until dewatering is no longer required EXPLOSIVES Explosives: Do not use explosives. EXCAVATION, GENERAL Unclassified Excavation: Excavation to subgrade elevations regardless of the character of surface and subsurface conditions encountered, including rock, soil materials, and obstructions. 1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials. 3.5 EXCAVATION FOR WALKS AND PAVEMENTS Excavate surfaces under walks and pavements to indicated cross sections, elevations, and grades. 3.6 APPROVAL OF SUBGRADE Notify Engineer when excavations have reached required subgrade. B. If Engineer determines that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed. 1. Additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work. SECTION EARTHWORK -3-
4 C. Proof roll sub grade with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding. Do not proof roll wet or saturated sub grades. D. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Engineer. 3.7 UNAUTHORIZED EXCAVATION Fill unauthorized excavation under pavements and trenches by extending bottom elevation of subbase to excavation bottom, without altering top elevation. Lean concrete fill may be used when approved by Engineer. 3.8 STORAGE OF SOIL MATERIALS Stockpile borrow materials and satisfactory excavated soil materials. Stockpile soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees. 3.9 BACKFILL Place and compact backfill in excavations promptly, but not before completing the following: 1. Surveying locations of underground utilities for record documents. 2. Inspecting and testing underground utilities. 3. Removing trash and debris. 4. Removing temporary shoring and bracing, and sheeting B. c. FILL Preparation: Remove vegetation, topsoil, debris, unsatisfactory soil materials, obstructions, and deleterious materials from ground surface before placing fills. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material. Place and compact fill material in layers to required elevations as follows: 1. Under grass and planted areas, use satisfactory soil material. 2. Under walks and pavements, use satisfactory soil material MOISTURE CONTROL Uniformly moisten or aerate subgrade and each subsequent fill or backfill layer before compaction to within 2 percent of optimum moisture content. 1. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain frost or ice. 2. Remove and replace, or scarify and air-dry, otherwise satisfactory soil material that exceeds optimum moisture content by 2 percent and is too wet to compact to specified dry unit weight. SECTION EARTHWORK -4-
5 3.12 COMPACTION OF BACKFILLS AND FILLS Place backfill and fill materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers. 1. Place backfill and fill materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure. B. Compact soil to not less than the following percentages of maximum dry unit weight according to ASTM D 698: 1. Under structures, building slabs, steps, and pavements, scarify and recompact top 12 inches of existing sub grade and each layer of backfill or fill material at 95 percent. 2. Under lawn or unpaved areas, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill material at 85 percent GRADING General: Uniformly grade areas to a smooth surface, free from irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated. 1. Provide a smooth transition between adjacent existing grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances. B. Site Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances: 1. Lawn or Unpaved Areas: Plus or minus 1 inch. 2. Walks: Plus or minus 1 inch. 3. Pavements: Plus or minus 1/2 inch SUBBASE AND BASE COURSES Under pavements and walks, place subbase course on prepared sub grade and as follows: 1. Place base course material over subbase. 2. Compact subbase and base courses at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight according to ASTM D Shape subbase and base to required crown elevations and cross-slope grades. 4. When thickness of compacted subbase or base course is 6 inches or less, place materials in a single layer. 5. When thickness of compacted subbase or base course exceeds 6 inches, place materials in equal layers, with no layer more than 6 inches thick or less than 3 inches thick when compacted FIELD QUALITY CONTROL Testing Agency: Owner may engage a qualified independent geotechnical engineering testing agency to perform field quality-control testing. SECTION EARTHWORK -5-
6 B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earthwork only after test results for previously completed work comply with requirements. C. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the following locations and frequencies: 1. Paved Areas: At subgrade and at each compacted fill and backfill layer, at least one test for every 2000 sq. ft. or less of paved area, but in no case fewer than three tests. D B. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil to depth required; recompact and retest until specified compaction is obtained. PROTECTION Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions. 1. Scarify or remove and replace soil material to depth as directed by Engineer; reshape and recompact. C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing. 1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to the greatest extent possible DISPOSAL OF SURPLUS AND WASTE MATERIALS Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Owner's property. END OF SECTION SECTION EARTHWORK -6-
B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.
SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.
More informationA. Backfill: Soil material or controlled low-strength material used to fill an excavation.
GSA Project No.: GS-P-03-14-AZ-5044 SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Preparing subgrades for walks. 2. Excavating and backfilling for structures. 3. Subbase
More informationDesign and Construction Standards SECTION EARTHWORK
SECTION 02310 EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationA. Work of this Section is affected by unit prices for earth moving specified in Section "Unit Prices."
SECTION 312000 EARTH MOVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION EXCAVATION, BACKFILLING AND COMPACTING
PART 1 GENERAL 1.01 SCOPE Work of this Section shall include all labor, materials, equipment, plant and incidentals required to complete all excavation, backfilling and compacting as indicated on the Drawings
More informationA. Excavation consists of the removal of material encountered to subgrade elevations and the reuse or disposal of materials removed.
SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationSection SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.
Section 02110 SITE CLEARING 1.00 General: A. Related Documents: The general provisions of the Contract including General and Supplementary Conditions and General Requirements, apply to the work specified
More informationSECTION EARTH MOVING
SECTION 312000 -EARTH MOVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Section,
More informationSECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING
PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels
More informationSECTION EXCAVATION AND FILL
SECTION 312300 EXCAVATION AND FILL PART 1 - GENERAL 1.1 SUMMARY A. Excavate, backfill, compact, and grade the site to the elevations shown on the Drawings, as specified herein, and as needed to meet the
More informationBidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.
McKee and Associates Architecture and Interior Design Addendum No. ONE Date: 2.27.19 Project: New Home Side Bleachers at Verbena High School Football Stadium for the Chilton County Board of Education Clanton,
More informationSECTION FILL AND BACKFILL
PART 1 GENERAL 1.1 SECTION INCLUDES A. Filling, backfilling, and compacting for building volume below grade, footings, slabs-on-grade, paving, site structures, and utilities within the building. B. Backfilling
More informationB. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.
SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution
More information1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.
31 20 00 EXCAVATION, TRENCHING AND BACKFILLING SECTION 1 - GENERAL 1.1 SUMMARY A. This section includes grading, excavation trenching, dewatering and backfilling for pipeline installation, roadways, walkways,
More informationEXCAVATION AND BACKF1LL
S E C T I O N 2 3 1 5 EXCAVATION AND BACKF1LL PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: Excavation, trenching, complete and continual dewatering of excavation, sheeting, bracing and shoring of
More informationSITE CLEARING OF 3
SECTION 311000 SITE CLEARING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More information1.1 RELATED DOCUMENTS
SECTION 311000- SITE CLEARING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION EARTHWORK
SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 WORK INVOLVED A. Provide all labor, materials and equipment as required for all excavation, grading, providing borrow materials, hauling, placing and compacting
More informationSECTION TRENCHING & BACKFILLING
SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications
More informationSECTION 10 - TRENCHING AND BACKFILLING
SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements
More informationSECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...
SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...
More informationSECTION TRENCHING
SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.
More informationA. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.
SECTION 311000 SITE CLEARING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION FINISH GRADING
SECTION 02220 - FINISH GRADING PART 1 - GENERAL 1.01 Related Documents A. Drawings and general provisions of the Contract, including General Conditions and Division 1 Specification Sections, apply to work
More information2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationSECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING
32.1 GENERAL SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING This Section covers excavation, backfill, fill and grading associated with utility trench and structural construction. All such WORK
More informationSECTION UNCLASSIFIED EXCAVATION AND GRADING
SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on
More informationB. Subsurface data is available from the *Owner. Contractor is urged to carefully analyze the site conditions.
SECTION 31 22 13 SITE GRADING PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the earthwork generally consisting of excavation, filling, backfilling and subgrade preparation as required for
More informationSECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES
SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.
More information1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods
SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include
More informationEXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.
CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related
More informationSECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.
SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction
More informationSECTION EMBANKMENT
02260-1 of 8 SECTION 02260 EMBANKMENT 02260.01 GENERAL A. Description 1. Embankment shall be formed of suitable material obtained from General, Structure, Borrow, Trench, and other excavations included
More informationSECTION UTILITY BACKFILL MATERIALS
SECTION 31 23 23 UTILITY BACKFILL MATERIALS PART 1: GENERAL 1.01 SECTION INCLUDES A. Material Classifications B. : 1. Concrete sand 2. Gem sand 3. Pea gravel 4. Crushed stone 5. Crushed concrete 6. Bank
More information1.1 RELATED DOCUMENTS A. The provisions of the Contract Documents apply to the work of this Section.
SECTION 01 0200 GENERAL SITEWORK REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The provisions of the Contract Documents apply to the work of this Section. 1.2 SITEWORK LAYOUT A. Monuments and
More informationTABLE OF CONTENTS (ISSUE FOR BID) MISCELLANEOUS CAST-IN-PLACE CONCRETE (OTHER THAN PAVEMENT)
PROJECT SPECIFICATIONS TABLE OF CONTENTS (ISSUE FOR BID) 033053 MISCELLANEOUS CAST-IN-PLACE CONCRETE (OTHER THAN PAVEMENT) 311000 SITE CLEARING 312000 EARTH MOVING 312319 DEWATERING 312333 TRENCHING AND
More informationTRENCH EXCAVATION AND BACKFILL
TRENCH EXCAVATION AND BACKFILL PART 1 - GENERAL 1.01 SECTION INCLUDES A. Trench Excavation for Pipe Systems B. Trench Foundation Stabilization C. Pipe Bedding and Backfill 1.02 DESCRIPTION OF WORK A. Excavate
More informationTECHNOLOGY CENTER WAREHOUSE ADDITION ADMINISTRATIVE SERVICE CENTER MOORE PUBLIC SCHOOLS 1500 S.E. 4 th Street Moore, Oklahoma
10-2-2017 October 2, 2017 ADDENDUM NO. 1, Project: Owner: Architect: TECHNOLOGY CENTER WAREHOUSE ADDITION ADMINISTRATIVE SERVICE CENTER MOORE PUBLIC SCHOOLS 1500 S.E. 4 th Street Moore, Oklahoma Moore
More informationDIVISION 4100 SITEWORK
DIVISION 4100 SITEWORK SECTION 4115 EARTHWORK PART 1 - GENERAL 1.01 SCOPE This section covers the grading and compaction of excavations, embankments, structural foundations, and planted areas. 1.02 REFERENCES
More informationSECTION EXCAVATING, BACKFILLING AND COMPACTING
SECTION 02220 - EXCAVATING, BACKFILLING AND COMPACTING PART 1 GENERAL 1.1 DESCRIPTION A. Provide excavation, overexcavation, fill, backfill and compaction for areas under buildings and structures shown
More informationEXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013
GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary
More informationSECTION SOILS REPORT
SECTION 02300 SOILS REPORT 1. GENERAL: 1.1 All work included under this heading shall be subject to the General Conditions of the entire operation. This Contractor is required to refer especially thereto.
More informationSECTION EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK: A. This section specifies the requirements for furnishing all equipment, materials, labor, tools, and techniques for earthwork including, but
More informationC. Foundation stabilization for pipe and utility structures.
PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization
More informationSECTION SUBSURFACE INVESTIGATION
SECTION 02010 SUBSURFACE INVESTIGATION PART 1 GENERAL 1.1 SUMMARY A. Geotechnical Report: A copy of the geotechnical report and boring logs is available in this document. B. Information Not Guaranteed:
More informationSECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.
SECTION 02200 PART 1 GENERAL 1.1 SECTION INCLUDES A. Subsoil and aggregate materials. B. Removal of subsoil and excavating all classes of material encountered. C. Handling, storage, transportation and
More information.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.
SECTION 31 22 00- GRADING 1.0 GENERAL.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.. 2 Excavate to exact line and grade as
More informationSECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.
PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and
More informationCITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP
INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried
More informationSECTION ASPHALT CONCRETE
SECTION 02740 ASPHALT CONCRETE PART 1. GENERAL 1.01 SECTION INCLUDES A. Work includes but is not limited to the following: 1.02 RELATED SECTIONS 1. Provide all material, labor, and equipment to prepare
More informationSECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES
SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and
More information1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1
1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include
More informationA. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.
SECTION 02230 SITE CLEARING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationThe Six-Inch Layer Compaction Method
1/7 1.0 PURPOSE This specification describes the minimum requirements for the backfilling of trenches or the construction of berms primarily for the installation of buried pipelines, cables, ducts and
More informationExhibit A - Construction Project Manual and Drawings CONTRACT DOCUMENTS AND SPECIFICATIONS FOR
Exhibit A - Construction Project Manual and Drawings CONTRACT DOCUMENTS AND SPECIFICATIONS FOR UTHSC Student and Faculty Housing Pavement Repair Phase IV TO SERVE Walter P Moore 1301 McKinney, Suite 1100
More informationSECTION FLEXIBLE PAVING
SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications
More informationSECTION BUILDING EARTHWORK
SECTION 02200 BUILDING EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections,
More informationSECTION EARTHWORK AND GRADING
Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK Conditions of Use/ Responsibility of Data These guideline specifications are to be used by the A/E as a base document in the development
More informationINDEX TO GENERAL PAVING AND DRAINAGE TECHNICAL SPECIFICATIONS
INDEX TO GENERAL PAVING AND DRAINAGE TECHNICAL SPECIFICATIONS Section Title 01300 SUBMITTALS 02230 CLEARING & GRUBBING 02300 EARTHWORK 02320 UNDERDRAIN AND EXFILTRATION TRENCH 02340 RIPRAP 02400 GRADED
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18.1 18-2 ROADWAY EXCAVATION... 18.1 18-2.01 General... 18.1 18-2.02 Unsuitable Roadway Excavation and Backfill... 18.1 18-2.03 Surplus
More informationSECTION STRUCTURAL EXCAVATION FOR STRUCTURES
1 1 1 0 1 0 1 0 1 SECTION 1. STRUCTURAL EXCAVATION FOR STRUCTURES BASED ON DFD MASTER SPECIFICATION DATED /1/1 P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all
More informationB. Missouri Office of Administration's Land Disturbance Permit No. MOR from the State of Missouri Department ofnatural Resources.
Guhleman and Hearnes Boiler Plant Project Number: Ml411-05 SECTION 310270 - SEDIMENT AND EROSION CONTROL PART 1 -GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including
More informationStandard Test Method for Minimum Index Density and Unit. Weight of Soils Using a Vibratory Table
SECTION 31 23 00 EXCAVATION AND FILL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections,
More informationEARTHWORK. C. Handling, storage, transportation, and disposal of excavated material
EARTHWORK PART 1 GENERAL 1.1 SECTION INCLUDES A. Clearing, grubbing and site preparation B. Removal and disposal of debris C. Handling, storage, transportation, and disposal of excavated material D. Sheeting,
More informationABNER CLAY PARK RENOVATIONS RICHMOND, VIRGINIA SECTION GENERAL SITEWORK REQUIREMENTS PART 1 - GENERAL
SECTION 01 0200 GENERAL SITEWORK REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The provisions of the Contract Documents apply to the work of this Section. 1.2 SITEWORK LAYOUT A. Monuments and
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL...18.1 18-2 ROADWAY EXCAVATION...18.1 18-2.01 General...18.1 18-2.02 Unsuitable Roadway Excavation and Backfill...18.1 18-2.03 Surplus
More informationSECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals.
SECTION 312333 - TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION EXCAVATION AND FILL
SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18-2 18-2 ROADWAY EXCAVATION... 18-2 18-2.01 General... 18-2 18-2.02 Unsuitable Roadway Excavation and Backfill... 18-2 18-2.03 Surplus
More informationPUBLIC WORKS DEPARTMENT Engineering Division
PUBLIC WORKS DEPARTMENT Engineering Division Escambia County Technical Specifications GENERAL EXCEPTIONS: Any reference to FDOT Standard Specifications for Road and Bridge Construction, Latest Edition,
More informationSECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.
SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationThis specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.
SPEC-1100 1/9 1.0 PURPOSE This specification describes the minimum requirements for general grading, excavation of earth, rock and solid slag, embankment construction, ditching, use of explosives, and
More information205 - EXCAVATION AND EMBANKMENT FOR HIGHWAYS SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS. Common Excavation (Contractor-Furnished)
SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS 205.1 DESCRIPTION Excavate, haul, place, remove and dispose of the specified materials. Construct the embankments as specified in the Contract Documents.
More informationSECTION TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 - GENERAL
SECTION 01 57 13 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings of the Contract, including General and supplementary Conditions and Division 01 Specification
More informationSECTION 14 EMBANKMENT
SECTION 14 EMBANKMENT 14.1 DESCRIPTION A. General: This work consists of constructing roadway embankments, including preparation of the areas upon which embankments are to be placed; the construction of
More informationSpecification Manual. UPAWS Marquette, Michigan
Specification Manual UPAWS Marquette, Michigan New Shelter Project Architect Issued for Bids August 7, 2017 IDI Project Number: 17-669 SECTION 00005 TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT
More informationA. This Section includes excavation support and protection systems.
SECTION 31 01 50 - EXCAVATION SUPPORT AND PROTECTION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationConstruction Specification for General Excavation
Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03
More informationSECTION STRUCTURE EXCAVATION AND EARTHWORK
SECTION 02200 STRUCTURE EXCAVATION AND EARTHWORK PART 1 GENERAL 1.1 SECTION INCLUDES A. Pavement Removal B. Stripping Topsoil C. Rock Excavation D. Excavation E. Subgrade Preparation F. Filling 1.2 REFERENCES
More informationMichigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS
PAGE 312300-1 SECTION 312300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationThis specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.
1/6 1.0 PURPOSE This specification describes the minimum requirements for filling depressions and for backfilling excavations for structural footings, slabs, floors, buildings, trestles, and the like..
More informationEXCAVATION & BACKFILL SPECIFICATION
REVISION DATE DESCRIPTION BY REVIEWER 0 12/14/2009 ISSUED FOR CONSTRUCTION MJS TDJ SECTION 1 EARTHWORK 1.1 GENERAL. This section covers general earthwork and includes preparation of the construction areas;
More informationB. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.
SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building
More informationBASED ON DFD MASTER SPECIFICATION DATED 2/24/2014
1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 02210 - Site Grading C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 STRUCTURE PROTECTION... 2 1.03 JOB CONDITIONS... 3 PART 2 - PRODUCTS...
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PORTLAND CEMENT. Section PORTLAND CEMENT STABILIZED SUBGRADE
PART 1 GENERAL 1.01 SUMMARY Section 02338 PORTLAND CEMENT This Section includes foundation course of Portland cement stabilized natural subgrade material. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1.
More informationUNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems
SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems PART 1 - GENERAL 1.1 SUMMARY A. Section includes soil media for the bioretention systems and rain gardens specified according to performance
More informationMSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS
219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,
More informationSECTION EARTH MOVING
SECTION 31 20 00 SPEC WRITER NOTES: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section
More informationSECTION Section Excavation and Backfill For Structures Section Embedment and Base Course Aggregate
SECTION 2110 EXCAVATION AND EMBANKMENT 1.00 GENERAL 1.01 Scope. Work to be performed under this section shall include all labor, equipment, materials and miscellaneous items necessary to perform all clearing
More informationSECTION BITUMINOUS CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES: SECTION 02400 BITUMINOUS CONCRETE PAVING A. The intent of this specification section is to provide requirements for materials, equipment, and methods for constructing
More informationCity of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING
January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01
More information378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE
378-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION 378 - POND I. SCOPE The work shall consist of constructing an earthfill embankment and appurtenances to the lines, grades,
More informationA. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):
SECTION 31 32 13.16 CEMENT STABILIZATION PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the specifications for cement stabilization of sandy or silty soil and consists of pulverizing, addition
More informationExcavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.
Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet
More informationSECTION TRENCH EXCAVATION AND BACKFILL
SECTION 02221 - TRENCH EXCAVATION AND BACKFILL CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Sections... 2 1.03 Reference Standards... 2 1.04 Quality Assurance... 2 1.05 Measurement
More informationTOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION. June 1984
1 TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION June 1984 1. DEFINITIONS APPROVAL, APPROVED, ACCEPTED OR WORDS OR TERMS OF SIMILAR MEANING: Written approval of the Highway Superintendent. BASE
More informationSECTION BUILDING EARTHWORK
Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development
More informationCITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL
CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL 13.01 GENERAL The work included in this section shall consist of furnishing all materials and equipment and performing all labor