SABO EARTHING SOLUTION

Size: px
Start display at page:

Download "SABO EARTHING SOLUTION"

Transcription

1 SABO SABO EARTHING SOLUTION The installation and maintenance of an effective low resistance earthing system is essential due to the following- - Efficiently dissipate heavy fault currents and electrical surges, both in magnitude and duration, to protect equipment being damaged so as to minimize down time, service interruption and replacement cost. - Provide a stable reference for electrical and RF circuits at the installation to minimize noise during normal operation. - Protection of personnel who work within the area from dangerous electric shock caused due to step potential or touch potential. Characteristics of good Earthing system - Excellent electrical conductivity - Low resistance and electrical impedance - Conductors of sufficient dimensions capable of withstanding high fault currents with no evidence of fusing or mechanical deterioration. - Lower earth resistance ensures that energy is dissipated into the ground in the safest possible manner. - Lower the earth circuit impedance, the more likely that high frequency lightning impulses will flow through the ground electrode path, in preference to any other path. - High corrosion resistance - The choice of the material for grounding conductors, electrodes and connections is vital as most of the grounding system will be buried in the earth mass for many years. Hence, highly galvanised electrodes should be used to avoid corrosion. - Mechanically robust and reliable. Location for Earth - Low lying areas close to the building or equipment are good for locating Earth Electrodes. - The location can be close to any existing water bodies or water points but not naturally welldrained. - Dry sand, lime stone, granite and any stony ground should be avoided. - Earthing electrode should not be installed on high bank or made-up soil. Acceptable Earth Resistance value The acceptable Earth Resistance at electrode terminal shall not be more than 5 Ohm. Components of Earthing & Bonding system The components of Earthing & Bonding system are- Earth electrode, Earth enhancement material, Earth pit, Equi-potential earth busbar, connecting cable & tape/strip and all other associated accessories. Design of Earthing & Bonding system GI Electrode (SABO-Electrode) 1. Highly galvanised pipe is used for electrode 2. Highly conductive & non corrosive mixture is poured inside the electrode so that inner strip or pipe will never corrode and provide lowest possible resistance. 3. Made of G.I. 4. ISI marked pipe.

2 SABO 5. Weight of 40mm dia electrode SABO-MFE-40-3 is > 17.0 Kg, 50mm dia electrode SABO-MFE is> 23.0Kg and 80mm dia electrode is > 45Kg. Earth Enhancement material : (30Kg per electrode ) SABO-EREC Earth enhancement material (NABL lab tested) is a superior conductive material that improves earthing effectiveness, especially in areas of poor conductivity (rocky ground, areas of moisture variation, sandy soils etc.). It improves conductivity of the earth electrode and ground contact area. It shall have following characteristics: - shall have high conductivity, improves earth s absorbing power and humidity retention capability. - shall be non-corrosive in nature having low water solubility but highly hygroscopic. - shall be suitable for installation in dry form or in a slurry form. - shall not depend on the continuous presence of water to maintain its conductivity. - shall be permanent & maintenance free and in its set form, maintains constant earth resistance with time. - shall be thermally stable between C to C ambient temperatures. - shall not dissolve, decompose or leach out with time. - shall not require periodic charging treatment nor replacement and maintenance. - shall be suitable for any kind of electrode and all kinds of soils of different resistivity. - shall not pollute the soil or local water table and meets environmental friendly requirements for landfill. - shall not be explosive. - shall not cause burns, irritation to eye, skin etc. Backfill material The excavated soil is suitable as a backfill but should be sieved to remove any large stones, plastic or debris and placed around the electrode taking care to ensure that it is well compacted. Material like sand, salt, coke breeze, cinders and ash shall not be used because of its acidic and corrosive nature. Earth Pit Construction of unit earth pit - A hole of > 100mm dia shall be augured /dug to a depth of about 3.0 meters. - Sieved soil should be poured inside the hole for about 100mm and earth enhancing material thoroughly mixed with 6 times of water should be poured (around 5 litres in the pit). Now the earth electrode shall be placed into this hole. - Remaining earth enhancement material mixed with 6 times of water shall be filled into the augured/dug hole in slurry form and allowed to set. After the material gets set, the diameter of the composite structure (earth electrode + earth enhancement material) shall be of minimum 100mm dia covering entire length of the hole for SABO-MFE-40-3 and SABO-MFE-50-3 and 150mm dia.. - Top of the pit should be covered with normal sieved soil for about 50mm. - A GI strip of 25mmX6mm in case of SABO-MFE-40-3 and 32x6 in case of SABO-MFE-50-3 and 50x6 mm in case of shall b used for interconnections to the earth pits or to the MEBB (Main equipotential bus bar). All the joints between the GI strips or between the GI strip and earth electrode or GI strip to MEBB should be done by welding or Stainless steel nuts and bolts. - Earth pit shall be located as near to the MEBB in the equipment room as possible. - MEBB should be of size 450*50*6 and should be mounted on the wall and insulators are provided so that it should not touch the wall.

3 Construction of loop Earth by providing multiple earth pits SABO - At certain locations, it may not be possible to achieve earth resistance of 2ohm / as desired with one earth electrode /pit due to higher soil resistivity. In such cases, provision of loop earth consisting of more than one earth pit shall be done. The number of pits required shall be decided based on the resistance achieved for the earth pits already installed. The procedure mentioned above for one earth pit shall be repeated for other earth pits. However, for rocky soils, it is recommended to make 4 earth pits. - The distance between two successive earth electrodes shall be min. 3mtrs. and max. upto twice the length of the earth electrode i.e. 6 mtrs. approx. - These earth pits shall then be inter linked using min. 32X5 mm. GI strip to form a loop and connected by suitable galvanized or SS nuts and bolts. - The interconnecting tape shall be buried at depth not less than 500mm below the ground level. This interconnecting tape shall also be covered with earth enhancing compound. In such cases, 10Kg. earth enhancing compound is required for each interconnection of electrodes, i.e, for every 3m. 10Kg earth enhancing compound is required. Measurement of Earth resistance The earth resistance shall be measured at the Main Equi-potential Earth Busbar (MEEB) or at the electrode itself with all the earth pits interconnected using Fall of Potential method as per para 37 of IS: Inspection Chamber - A 300X300X300 mm concrete chamber with smooth cement plaster finish shall be provided on the top of the pit. A concrete lid, painted black, approx. 50 mm. thick with pulling hooks, shall be provided to cover the earth pit. In case of remote sites, the pit of bricks of suitable size / as per the availability of material, can be prepared and the cover of C.I./other material should be provided. Earth pit is necessary. - Care shall be taken regarding level of the floor surrounding the earth so that the electrode terminal is not too deep in the masonry or projecting out of it. Note: It is avoided to construct earth pit in the road side so that it may not destroy or the place exposed to drainage to avoid chemical reaction of drain water. Which model should be used - For all LT (low voltage) body earth SABO-MFE-40-3 should be used - For all MV/HT body earth SABO-MFE-50-3 should be used - For all neutral earthing should be used - SABO-EREC 30Kg should be used for all types of earth pits - In rocky soils, it is recommend to use 4 earth pits so that round the year there will be almost no fluctuation in the earth resistance achieved.

4 SELECTION OF EARTH SYSTEM SABO SN Neutral earthing 1. House hold earth/3ka 2. Commercial premises Office buildings/ 5kA 3 Transformers, substation earthing, LT line equipment/ 15kA 4 Transformers, substation earthing, HT line equipment/ 40kA 5 Extra high current applications etc./ 50kA 6 PRS, UTS, RTUs,FOIS, COIS, ATMs and data processing centre etc./5ka IR Value Soil Type/ Resistivity Required 8 ohm Normal Soil/ upto 50 ohmmtr Sandy Soil/ between 50 to ohm Normal Soil/ upto 50 ohmmtr 1-2 ohm Normal Soil/ upto 50 ohmmtr less than Normal Soil/ upto 50 ohmmtr 1 ohm less than Normal Soil/ upto 50 ohmmtr 1 ohm less than Normal Soil/ upto 50 ohmmtr 0.5 ohm Earth System Single Electrode SABO-MFE-40-3 / SABO-MFE-50-3 Single Electrode Two Electrodes Single Electrode 3/ Note: For body earthing and lightning arrester earthing, earth resistance required for anything at any type of soil is less than 10 Ohm.

5 TYPE OF SOILS Soil can be classified in to various types, though based on the size of the particles it contains: SABO Normal soil Black cotton soil, vegetable soil, garden soil, loamy garden, soil shallow black, soil medium black soil,deep black soil and marshy soil etc having low soil resistivity value ( up to 50 ohm meter) Sandy soil This type has the big particles and the size of the particles does determine the degree of aeration and drainage that the soil allows. It is granular and consists of rock and mineral particles that are very small. Therefore the texture is gritty and sandy soil is formed by the disintegration and weathering of rocks such as limestone, granite, quartz and shale, thus resulting in over-drainage. It warms very fast in the spring season. Coastal area, silt soil, red sandy soil, sandy clay and coastal alluvium etc having soil resistivity up to 2000 ohm-meter are considered as sandy soil. Rocky soil The area containing rocks, pebbles, uneven hard surface laterite soil, lime stone, sand stone, gravel, granite and chalk etc having soil resistivity more than 2000 ohm-meter is considered as rocky soil. This type of soil does not absorb moisture and are extremely poor conductor.

6 SABO SABO EARTHING SOLUTION CROSS SECTIONAL DIAGRAM 300X300X300 CONRETE CHAMBER WITH HOOKS MEBB 450*50*6 GROUND LEVEL NORMAL SIEVED SOIL 50MM 0.5M 25*6 GI STRIP SABO-EREC EARTH PIT 3000MM X 100MM NORMAL SIEVED SOIL 50MM (NOT TO SCALE)

Earthing in electrical network purpose, methods and measurement

Earthing in electrical network purpose, methods and measurement Earthing in electrical network purpose, methods and measurement Earth / Ground Conductive ground whose electrical potential at each point is set equal to zero, It is a conductor which provides a low impedance

More information

Grounding Principles. The need to ground! Definitions. Introduction. Grounding Codes and Standards. 2 Ph:

Grounding Principles. The need to ground! Definitions. Introduction. Grounding Codes and Standards. 2 Ph: Introduction Grounding and bonding are an integral part of any modern electrical protection system design. An effective, low-impedance ground system is a key element of this system. It is crucial in ensuring

More information

Improvement of Substation Earthing

Improvement of Substation Earthing International Journal of Engineering and Advanced Technology (IJEAT) Improvement of Substation Earthing Mohammad Ali Adelian Abstract Designing a proper substation grounding system is quite complicated.

More information

DESIGNING FOR A LOW RESISTANCE EARTH INTERFACE (GROUNDING)

DESIGNING FOR A LOW RESISTANCE EARTH INTERFACE (GROUNDING) Newage Energy Holdings DESIGNING FOR A LOW RESISTANCE EARTH INTERFACE (GROUNDING) http://newage-energy.net http://newage-energy.com Newage Energy Page 1 Introduction Grounding (or earthing) is the art

More information

COMPANY: Aplicaciones Tecnológicas, S.A.

COMPANY: Aplicaciones Tecnológicas, S.A. COMPANY: Aplicaciones Tecnológicas, S.A. AREA: Lightning Protection PRODUCT: CONDUCTIVER PLUS REFERENCE: AT 10L AT-10L CONDUCTIVER PLUS 1 / 12 AT-10L CONDUCTIVER PLUS CONDUCTIVER PLUS is a non-corrosive

More information

INFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF:

INFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF: Page 1 of 7 Authorised by: A.B. Network Services Manager Proposed Review Date: Dec. 11 Issue Date: Dec. 06 No of this copy: INFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF: ITEM: TERMINATIONS

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

Facility and Equipment Grounding

Facility and Equipment Grounding Facility and Equipment Grounding - 2005 Course: PQE203 Presented by: PowerCET Corporation 3350 Scott Blvd. Bldg. 55 Unit 1 Santa Clara, CA 95054 408/988-1346 Fax 408/988-4869 E-mail: training@powercet.com

More information

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR FINANCIAL BID Item DSR Item Description Qty Units No No. Total 1.1.1 Excavating trenches of

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING.

4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING. 4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING. 4.1 All equipment (i.e., switches, breakers, control cabinets, etc.) inside switchyards or substations which require operations by workers must

More information

An Overview of Earthing

An Overview of Earthing 2018 Earthing An Overview of Earthing Gary Blackshaw, Global Business Development Manager Founded by William Joseph Furse Originally as a Steeplejack company Relocated to Traffic Street More emphasis on

More information

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17

More information

Tender No.:- RITES/CO/B&A/EE/CUK- Gulbarga/External/E-2/2012.

Tender No.:- RITES/CO/B&A/EE/CUK- Gulbarga/External/E-2/2012. Amendment No. 1. Sub. : Tender: Supply, Erection, Testing & Commissioning of 11kV/440 V substation, Transformers, DG Sets, HT/ LT panels, HT/LT Cables, Street Lighting etc at University Campus at Khadaganchki

More information

Introduction. A publication by Aquamor

Introduction. A publication by Aquamor Introduction Very large numbers of family owned wells have been built in Zimbabwe. This number far exceeds 100 000. In almost every case the family itself has excavated the well and in many cases also

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

Description Unit Quantity Rate Kshs. Amount Kshs.

Description Unit Quantity Rate Kshs. Amount Kshs. BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove

More information

SECTION GROUNDING

SECTION GROUNDING SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment

More information

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION E11 : General Electrical Earthing and LIGHTNING Protection PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION 1 2009-05-12 Review of Mechanical / Electrical and Control

More information

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL). 16450 GROUNDING ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 05 26 An optional keynote to the

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the

More information

CONNECTION TO INSPECTION CHAMBERS PRAKTO

CONNECTION TO INSPECTION CHAMBERS PRAKTO CONNECTION TO INSPECTION CHAMBERS PRAKTO The inspection chambers PRAKTO made by Pipelife are designed and manufactured to be conveniently and securely connected to pipes and fittings of the Pragma series

More information

SECTION EARTHING AND EARTH FAULT PROTECTION

SECTION EARTHING AND EARTH FAULT PROTECTION SECTION 16660 PART 1 - GENERAL 1.01 DESCRIPTION A. The work to be performed includes, but is not necessarily limited to, all work involved with the construction and assembly of a complete electrical earthing

More information

Dr. Ali Kadhim. Bricks

Dr. Ali Kadhim. Bricks Bricks Classification of bricks according to constituent raw material: 1. Clay bricks 2. Lime sand bricks 3. Concrete bricks 1. Clay bricks: 1.1 Raw materials: a. Alumina Alumina is main constituent of

More information

GB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA

GB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA Translated English of Chinese Standard: GB50169-2016 www.chinesestandard.net Buy True-PDF Auto-delivery. Sales@ChineseStandard.net GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA UDC P GB 50169-2016

More information

SCHEDULE OF RATES. WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT

SCHEDULE OF RATES. WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SCHEDULE OF RATES SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT 1 Excavation for foundation in earth all types of soils like clay,

More information

SECTION FACILITY LIGHTNING PROTECTION

SECTION FACILITY LIGHTNING PROTECTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 41 00 FACILITY LIGHTNING PROTECTION SPEC WRITER NOTE: Delete between //----//if not applicable to project. Also delete any other item or paragraph not applicable

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

31-SDMS-03 REV. 01 SPECIFICATIONS FOR

31-SDMS-03 REV. 01 SPECIFICATIONS FOR 31-SDMS-03 REV. 01 SPECIFICATIONS FOR LOW VOLTAGE CABINET FOR POLE MOUNTED TRANSFORMER This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Description

More information

TECHNICAL SPECIFICATION FOR 1.1KV XLPE POWER CABLE SECTION-1

TECHNICAL SPECIFICATION FOR 1.1KV XLPE POWER CABLE SECTION-1 ANNEXURE TO TENDER NO. PUR42396GM DATED 06 th FEBRUARY 2014 SUPPLY OF 1.1KV GRADE LT POWER CABLES FOR THE PERIOD APRIL 2014 MARCH 2016 TECHNICAL SPECIFICATION FOR 1.1KV XLPE POWER CABLE SECTION-1 1.1 SCOPE

More information

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID SBI INFRA MANAGEMENT SOLUTIONS PVT.LTD. 3 rd Floor, Local Head Office,Bank Street, Koti, Hyderabad- 500095 On behalf of On behalf of On behalf of Cash Management Product GOC (CMP GOC) & Internal Audit

More information

56-SDMS-01 REV. 01 SPECIFICATIONS FOR

56-SDMS-01 REV. 01 SPECIFICATIONS FOR 56-SDMS-01 REV. 01 SPECIFICATIONS FOR 13.8KV UNIT SUBSTATIONS This specification is property of SEC and subject to change or modification without any notice CONTENTS PAGE No. 1.0 SCOPE 3 2.0 CROSS REFERENCES

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.)

SUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.) SBI-AO2 Project Residency Rd Br-elect/RBO-4 SCHEDULE OF QUANTITIES FOR ELECTRICAL WORKS. DATE : 24/4/2018 Sl. No. DESCRIPTION OF WORK UNIT QTY 1 READYMADE FINAL DISTRIBUTION BOARDS Supply, Instillation,

More information

Chapter 10. Pipeline Installation

Chapter 10. Pipeline Installation Chapter 10 CHAPTER 10 STOCKWATER PIPELINE INSTALLATION TABLE OF CONTENTS PART 10.1 TRENCHING 10-1 10.1.1 Backhoe Constructed Trench 10-1 10.1.2 Trencher Constructed Trench 10-1 10.1.3 Backfilling and Maintenance

More information

SECTION PART 1 GENERAL

SECTION PART 1 GENERAL SECTION 16060 GROUNDING AND BONDING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Grounding of electrical systems and equipment and basic requirements for ground for equipment, circuits, and systems.

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

4 EXTREME FOUNDATION PANELS

4 EXTREME FOUNDATION PANELS 4 EXTREME FOUNDATION PANELS For Garages On Granular Footings 1. The type of soil is a factor in determining foundation construction details such as footing design, backfill, and drainage provisions. Soils

More information

Part 1: On-land pipelines

Part 1: On-land pipelines Provläsningsexemplar / Preview INTERNATIONAL STANDARD ISO 15589-1 Second edition 2015-03-01 Petroleum, petrochemical and natural gas industries Cathodic protection of pipeline systems Part 1: On-land pipelines

More information

Septic Tank Guidelines

Septic Tank Guidelines Septic Tank Guidelines Septic tanks are suitable for conditions where the wastewater can drain away and be absorbed into the soil without contaminating ground water where it is extracted. Sealed solid

More information

STANDARD SPECIFICATION EARTH GROUNDING Section (Straight Shaft Model)

STANDARD SPECIFICATION EARTH GROUNDING Section (Straight Shaft Model) STANDARD SPECIFICATION EARTH GROUNDING Section 16000 (Straight Shaft Model) PART 1 - GENERAL 1.01 DESCRIPTION A. Related Work Specified Elsewhere: 1. Electrical General Provisions ( Section xxx) 2. Basic

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

1. IS: 3043/1987 Code of practice for Earthing 2. IEC Requirement of Earthing Enhancement Compound

1. IS: 3043/1987 Code of practice for Earthing 2. IEC Requirement of Earthing Enhancement Compound Gujarat Power Research & Development Cell (A Govt. of Gujarat Initiative) Gujarat Urja Vikas Nigam Ltd CIN: U40109GJ2004SGC045195, IIT Gandhinagar Research Park, IIT Gandhinagar, Palaj-382355, Gandhinagar,

More information

SECTION LIGHTNING PROTECTION SYSTEM

SECTION LIGHTNING PROTECTION SYSTEM SECTION 16670 - LIGHTNING PROTECTION SYSTEM PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General: Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Cross Borehole Electrical Resistivity Tomography (ERT) Measurements

Cross Borehole Electrical Resistivity Tomography (ERT) Measurements Introduction Cross Borehole Electrical Resistivity Tomography (ERT) Measurements Resistivity imaging at the surface may be used for applications such as cavity detection, geotechnical investigation, site

More information

Northern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning

Northern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning Version:- 2.0 Date of Issue:- Sept 2013 Page 1 of 10 Northern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning Framework for design and planning, materials specification,

More information

ABSTRACT EXECUTIVE SUMMARY

ABSTRACT EXECUTIVE SUMMARY MIE TALK August 2016 Compiled by: Schalk J. P. Kruger ABSTRACT Corrosion is a major issue in industrial plant processes especially where any part of the structure is submerged in ground or water. The management

More information

De Montfort Mark 7 Incinerator (Flatpack)

De Montfort Mark 7 Incinerator (Flatpack) De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where

More information

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION A. This section specifies the furnishing, installation, and connection of precast manholes and pullboxes with ducts

More information

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS SECTION 26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide labor, materials, equipment, and incidentals as shown, specified, and

More information

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS Version 2014-11-11 Prepared by: Building Development Division Department of Development Services 5 County Complex Ct. Suite 120 Prince William, VA 22192

More information

16300 HIGH VOLTAGE DISTRIBUTION

16300 HIGH VOLTAGE DISTRIBUTION 16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served

More information

BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI

BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI Page 1 BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI-110075 I. INSTALLATION OF SUB-STATION EQUIPMENT The rates shall include the following : 1. Assembling loose

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS

More information

h Installation Manual

h Installation Manual h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires

More information

A.2.a Random Riprap... Table

A.2.a Random Riprap... Table 3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide

More information

Biogas Construction Process

Biogas Construction Process Paper presented at the Biogas Training Programme Conducted at CARD, Alam Village, Myitkyina. Metta Development Foundation Biogas Construction Process Govinda Prasad Devkota P.O. Box 20506 Kathmandu, Napal

More information

SAS Micropile Manual. Basic dimensioning and design recommendations. Table of Content:

SAS Micropile Manual. Basic dimensioning and design recommendations. Table of Content: SAS Micropile Manual Basic dimensioning and design recommendations Table of Content: Page System Description 2 Load Capacities 2 Minimum Drill Hole Diameter 3 Load Transfer to Ground 4 Corrosion Protection

More information

Tender ref no: SBIIMS/BHU/AO2/ / 57 Date: PRICE BID FOR CIVIL WORKS AT SBI UDALA BRANCH (A) RAIN WATER HARVESTING. Cum 15.

Tender ref no: SBIIMS/BHU/AO2/ / 57 Date: PRICE BID FOR CIVIL WORKS AT SBI UDALA BRANCH (A) RAIN WATER HARVESTING. Cum 15. Tender ref no: SBIIMS/BHU/AO/08-9/ Date: 0.0.09 Sl. No. ITEM SPECIFICATION UNIT QTY RATES AMOUNT PRICE BID FOR CIVIL WORKS AT SBI UDALA BRANCH (A) RAIN WATER HARVESTING Earth work in excavation of recharge

More information

Building Materials I Lect :Ameer M. H. Lecture (4)

Building Materials I Lect :Ameer M. H. Lecture (4) Thermo Stone Thermo stone is a lightweight cement-based material, containing many gas bubbles evenly distributed in the volume, produced by blending and maturing of a mixture of cement, lime, sand, water,

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Sr. No. Description Qty Unit Rate Amount. S e t

Sr. No. Description Qty Unit Rate Amount. S e t GUJARAT ENERGY TRANSMISSION CORPORATION LTD. TRANSMISSION CIRCLE OFFICE, NADIAD SCHEDULE -B Name of work : ARC for Erection of Structure, Equipments, Earthing, Termination, Laying Control Cables 66/11KV

More information

Wind Power Solutions. Company Registration No: Vat Registration No.:

Wind Power Solutions. Company Registration No: Vat Registration No.: Wind Power Solutions Foundation Grounding and Construction, Bonding, Power Connections, Surge Protection, and Lightning Protection ERICO offers a complete range of foundation grounding and construction,

More information

THE OFFICIAL TRADE JOURNAL OF BICSI

THE OFFICIAL TRADE JOURNAL OF BICSI ICT TODAY THE OFFICIAL TRADE JOURNAL OF BICSI January/February 2017 PLUS + + Information Security and ESS in the Age of the Internet of Things + Grounding System Design and Testing for Critical Facilities

More information

ENGINEERING SPECIFICATION EE SPEC

ENGINEERING SPECIFICATION EE SPEC /. Company Directive ENGINEERING SPECIFICATION EE SPEC : 84/1 Relating to Surge Arresters EE SPEC : 84/1 20 December 2013-1 of 7 - IMPLEMENTATION PLAN Introduction This document defines the surge arresters

More information

HUITEX GEOCELL INSTALLATION MANUAL

HUITEX GEOCELL INSTALLATION MANUAL Table of Contents 1 Site Preparation 2 Installation for the Retaining Wall 2.1 Base Preparation 2.2 Footing Installation 2.3 Placement of the Drainage System 2.4 Placement of the HUITEX Geocell panels

More information

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING

More information

Building Construction

Building Construction Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When

More information

SUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM

SUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM 31 st July 2017 TENDER FOR RELOCATION OF ONE GE FRAME 6 GAS TURBINE FROM EMBAKASI IN NAIROBI TO MUHORONI NEAR KISUMU: KGN-GT-012-2017 KenGen wishes to make the following clarification and changes through

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Rehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL Bill of Quantity : Package2 - Lot 3

Rehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL Bill of Quantity : Package2 - Lot 3 ITB 2016-279 Rehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL-10-00098764 Bill of Quantity : Package2 - Lot 3 Package 2 Lot1- Installation, Connection

More information

Homogenous cement-based powder, modified with high quality polymers and cellulose additives.

Homogenous cement-based powder, modified with high quality polymers and cellulose additives. Page: 1 от 5 (winter formula) adhesive mortar solution for bonding thermo insulation EPS/XPS boards on different bases when thermo-insulating buildings, in mild winter conditions (temperatures from 0 C

More information

SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building

SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building 2004 Specifications CSJ 0720-03-095 SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building 1. Description. Furnish and install Environmentally Controlled Communications Building

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

SWITCHYARD BOQ FOR 400kV ASOJ SUB-STATION - (220/66kv System)

SWITCHYARD BOQ FOR 400kV ASOJ SUB-STATION - (220/66kv System) Sr. A and of 220kV Equipments as per respective technical specifications and relevant special conditions. B Surge Arrester 98kV, 0kA, Cl-3 with str and clamp connectors as per Technical spec 6 6 2 BPI

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

NOTICE INVITING QUOTATION

NOTICE INVITING QUOTATION Ref. No: SR-13011(42)/1/2016-APD-SR-MADURAI Subject: Installation of chemical Earthing systems. Date: 29.06.2016 NOTICE INVITING QUOTATION Sealed quotations are invited by Deputy. General Manager (CNS),

More information

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2 CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA Adopted September 5, 1989 Table of Contents Page Part 1 Introduction...2 32-1 Purpose...2 32-2 Applicability...2 32-3 Definitions...2 32-4

More information

CHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS

CHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS IAC 5/12/93, 4/8/98 Environmental Protection[567] Ch 39, p.1 IAC 5/12/93, 4/8/98 CHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS 567 39.1(455B) Purpose. The purpose of this chapter is to

More information

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR GROUNDING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN

More information

50 lbs (23 kg) of + #8 (+2.36 mm) material plus 50 lbs (23 kg) of pile run material.

50 lbs (23 kg) of + #8 (+2.36 mm) material plus 50 lbs (23 kg) of pile run material. 5.5 REQUIRED SAMPLE SIZES 1. SCOPE This section covers the size of samples to be submitted to the s and Research Center for testing. The sample sizes listed are minimums and in special cases the Engineer

More information

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS ISSUE DATE: 5/1/90 EFFECTIVE DATE: 2/4/92 REVIEW DATE:

More information

SECTION AGGREGATES

SECTION AGGREGATES SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS

More information

Drilling a tube-well inside a wide-diameter well (preliminary trials)

Drilling a tube-well inside a wide-diameter well (preliminary trials) Drilling a tube-well inside a wide-diameter well (preliminary trials) Peter Morgan 2016 Introduction In an earlier manual, the method of connecting a PVC pipe from an underground water chamber to the headworks

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin February 2019 Page 1 of 8 2018 CANADIAN ELECTRICAL CODE SUBJECT: Section 10 Grounding and bonding Rule 10-102 Grounding electrodes Replacing metal water service lines

More information

CHAPTER 13 GROUNDING AND BONDING

CHAPTER 13 GROUNDING AND BONDING GROUNDING AND BONDING CHAPTER 13 GROUNDING AND BONDING Grounding and bonding must be in accordance with Article 250 of the National Electrical Code (NEC). Bonding is defined in the NEC as the permanent

More information

Galvanic and Stray Current Corrosion

Galvanic and Stray Current Corrosion Chapter 5 Galvanic and Stray Current Corrosion MElec-Ch5-1 Overview Galvanic Corrosion Understanding Galvanic Corrosion Controlling Galvanic Corrosion Stray Current Corrosion Understanding Stray Current

More information

NATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 SUPPLEMENTARY EXAMINATION

NATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 SUPPLEMENTARY EXAMINATION MARKING GUIDELINE NATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 SUPPLEMENTARY EXAMINATION 2010 This marking guideline consists of 6 pages. (MARKING GUIDELINE) -2- NC1530(E)(F19)V QUESTION 1: INTRODUCTION

More information

Construction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750

Construction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750 1 Preparation of a 18-Classroom School BoQ for constructing a 18-Classroom School - Najaf Site Preparation:Works for leveling the site and remove the garbage to authorized location according to supervisor

More information

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches,

More information

UNIT RATE ( IN Rs. ) Sl. No ITEM DESCRIPTION QTY UNIT AMOUNT. 80 Nos.

UNIT RATE ( IN Rs. ) Sl. No ITEM DESCRIPTION QTY UNIT AMOUNT. 80 Nos. (SECTION : A :- SUPPLY OF EQUIPMENTS/MATERIALS/ITEMS) TENDER NO. BHEL: NR (SCT): BAWANA:11 KV RING MAIN:579 1(A) POLES FOR STRAIGHT RUN / DP STRUCTURE / Four pole structure- Supply of Steel Tubular swaged

More information