SABO EARTHING SOLUTION
|
|
- Bathsheba Page
- 5 years ago
- Views:
Transcription
1 SABO SABO EARTHING SOLUTION The installation and maintenance of an effective low resistance earthing system is essential due to the following- - Efficiently dissipate heavy fault currents and electrical surges, both in magnitude and duration, to protect equipment being damaged so as to minimize down time, service interruption and replacement cost. - Provide a stable reference for electrical and RF circuits at the installation to minimize noise during normal operation. - Protection of personnel who work within the area from dangerous electric shock caused due to step potential or touch potential. Characteristics of good Earthing system - Excellent electrical conductivity - Low resistance and electrical impedance - Conductors of sufficient dimensions capable of withstanding high fault currents with no evidence of fusing or mechanical deterioration. - Lower earth resistance ensures that energy is dissipated into the ground in the safest possible manner. - Lower the earth circuit impedance, the more likely that high frequency lightning impulses will flow through the ground electrode path, in preference to any other path. - High corrosion resistance - The choice of the material for grounding conductors, electrodes and connections is vital as most of the grounding system will be buried in the earth mass for many years. Hence, highly galvanised electrodes should be used to avoid corrosion. - Mechanically robust and reliable. Location for Earth - Low lying areas close to the building or equipment are good for locating Earth Electrodes. - The location can be close to any existing water bodies or water points but not naturally welldrained. - Dry sand, lime stone, granite and any stony ground should be avoided. - Earthing electrode should not be installed on high bank or made-up soil. Acceptable Earth Resistance value The acceptable Earth Resistance at electrode terminal shall not be more than 5 Ohm. Components of Earthing & Bonding system The components of Earthing & Bonding system are- Earth electrode, Earth enhancement material, Earth pit, Equi-potential earth busbar, connecting cable & tape/strip and all other associated accessories. Design of Earthing & Bonding system GI Electrode (SABO-Electrode) 1. Highly galvanised pipe is used for electrode 2. Highly conductive & non corrosive mixture is poured inside the electrode so that inner strip or pipe will never corrode and provide lowest possible resistance. 3. Made of G.I. 4. ISI marked pipe.
2 SABO 5. Weight of 40mm dia electrode SABO-MFE-40-3 is > 17.0 Kg, 50mm dia electrode SABO-MFE is> 23.0Kg and 80mm dia electrode is > 45Kg. Earth Enhancement material : (30Kg per electrode ) SABO-EREC Earth enhancement material (NABL lab tested) is a superior conductive material that improves earthing effectiveness, especially in areas of poor conductivity (rocky ground, areas of moisture variation, sandy soils etc.). It improves conductivity of the earth electrode and ground contact area. It shall have following characteristics: - shall have high conductivity, improves earth s absorbing power and humidity retention capability. - shall be non-corrosive in nature having low water solubility but highly hygroscopic. - shall be suitable for installation in dry form or in a slurry form. - shall not depend on the continuous presence of water to maintain its conductivity. - shall be permanent & maintenance free and in its set form, maintains constant earth resistance with time. - shall be thermally stable between C to C ambient temperatures. - shall not dissolve, decompose or leach out with time. - shall not require periodic charging treatment nor replacement and maintenance. - shall be suitable for any kind of electrode and all kinds of soils of different resistivity. - shall not pollute the soil or local water table and meets environmental friendly requirements for landfill. - shall not be explosive. - shall not cause burns, irritation to eye, skin etc. Backfill material The excavated soil is suitable as a backfill but should be sieved to remove any large stones, plastic or debris and placed around the electrode taking care to ensure that it is well compacted. Material like sand, salt, coke breeze, cinders and ash shall not be used because of its acidic and corrosive nature. Earth Pit Construction of unit earth pit - A hole of > 100mm dia shall be augured /dug to a depth of about 3.0 meters. - Sieved soil should be poured inside the hole for about 100mm and earth enhancing material thoroughly mixed with 6 times of water should be poured (around 5 litres in the pit). Now the earth electrode shall be placed into this hole. - Remaining earth enhancement material mixed with 6 times of water shall be filled into the augured/dug hole in slurry form and allowed to set. After the material gets set, the diameter of the composite structure (earth electrode + earth enhancement material) shall be of minimum 100mm dia covering entire length of the hole for SABO-MFE-40-3 and SABO-MFE-50-3 and 150mm dia.. - Top of the pit should be covered with normal sieved soil for about 50mm. - A GI strip of 25mmX6mm in case of SABO-MFE-40-3 and 32x6 in case of SABO-MFE-50-3 and 50x6 mm in case of shall b used for interconnections to the earth pits or to the MEBB (Main equipotential bus bar). All the joints between the GI strips or between the GI strip and earth electrode or GI strip to MEBB should be done by welding or Stainless steel nuts and bolts. - Earth pit shall be located as near to the MEBB in the equipment room as possible. - MEBB should be of size 450*50*6 and should be mounted on the wall and insulators are provided so that it should not touch the wall.
3 Construction of loop Earth by providing multiple earth pits SABO - At certain locations, it may not be possible to achieve earth resistance of 2ohm / as desired with one earth electrode /pit due to higher soil resistivity. In such cases, provision of loop earth consisting of more than one earth pit shall be done. The number of pits required shall be decided based on the resistance achieved for the earth pits already installed. The procedure mentioned above for one earth pit shall be repeated for other earth pits. However, for rocky soils, it is recommended to make 4 earth pits. - The distance between two successive earth electrodes shall be min. 3mtrs. and max. upto twice the length of the earth electrode i.e. 6 mtrs. approx. - These earth pits shall then be inter linked using min. 32X5 mm. GI strip to form a loop and connected by suitable galvanized or SS nuts and bolts. - The interconnecting tape shall be buried at depth not less than 500mm below the ground level. This interconnecting tape shall also be covered with earth enhancing compound. In such cases, 10Kg. earth enhancing compound is required for each interconnection of electrodes, i.e, for every 3m. 10Kg earth enhancing compound is required. Measurement of Earth resistance The earth resistance shall be measured at the Main Equi-potential Earth Busbar (MEEB) or at the electrode itself with all the earth pits interconnected using Fall of Potential method as per para 37 of IS: Inspection Chamber - A 300X300X300 mm concrete chamber with smooth cement plaster finish shall be provided on the top of the pit. A concrete lid, painted black, approx. 50 mm. thick with pulling hooks, shall be provided to cover the earth pit. In case of remote sites, the pit of bricks of suitable size / as per the availability of material, can be prepared and the cover of C.I./other material should be provided. Earth pit is necessary. - Care shall be taken regarding level of the floor surrounding the earth so that the electrode terminal is not too deep in the masonry or projecting out of it. Note: It is avoided to construct earth pit in the road side so that it may not destroy or the place exposed to drainage to avoid chemical reaction of drain water. Which model should be used - For all LT (low voltage) body earth SABO-MFE-40-3 should be used - For all MV/HT body earth SABO-MFE-50-3 should be used - For all neutral earthing should be used - SABO-EREC 30Kg should be used for all types of earth pits - In rocky soils, it is recommend to use 4 earth pits so that round the year there will be almost no fluctuation in the earth resistance achieved.
4 SELECTION OF EARTH SYSTEM SABO SN Neutral earthing 1. House hold earth/3ka 2. Commercial premises Office buildings/ 5kA 3 Transformers, substation earthing, LT line equipment/ 15kA 4 Transformers, substation earthing, HT line equipment/ 40kA 5 Extra high current applications etc./ 50kA 6 PRS, UTS, RTUs,FOIS, COIS, ATMs and data processing centre etc./5ka IR Value Soil Type/ Resistivity Required 8 ohm Normal Soil/ upto 50 ohmmtr Sandy Soil/ between 50 to ohm Normal Soil/ upto 50 ohmmtr 1-2 ohm Normal Soil/ upto 50 ohmmtr less than Normal Soil/ upto 50 ohmmtr 1 ohm less than Normal Soil/ upto 50 ohmmtr 1 ohm less than Normal Soil/ upto 50 ohmmtr 0.5 ohm Earth System Single Electrode SABO-MFE-40-3 / SABO-MFE-50-3 Single Electrode Two Electrodes Single Electrode 3/ Note: For body earthing and lightning arrester earthing, earth resistance required for anything at any type of soil is less than 10 Ohm.
5 TYPE OF SOILS Soil can be classified in to various types, though based on the size of the particles it contains: SABO Normal soil Black cotton soil, vegetable soil, garden soil, loamy garden, soil shallow black, soil medium black soil,deep black soil and marshy soil etc having low soil resistivity value ( up to 50 ohm meter) Sandy soil This type has the big particles and the size of the particles does determine the degree of aeration and drainage that the soil allows. It is granular and consists of rock and mineral particles that are very small. Therefore the texture is gritty and sandy soil is formed by the disintegration and weathering of rocks such as limestone, granite, quartz and shale, thus resulting in over-drainage. It warms very fast in the spring season. Coastal area, silt soil, red sandy soil, sandy clay and coastal alluvium etc having soil resistivity up to 2000 ohm-meter are considered as sandy soil. Rocky soil The area containing rocks, pebbles, uneven hard surface laterite soil, lime stone, sand stone, gravel, granite and chalk etc having soil resistivity more than 2000 ohm-meter is considered as rocky soil. This type of soil does not absorb moisture and are extremely poor conductor.
6 SABO SABO EARTHING SOLUTION CROSS SECTIONAL DIAGRAM 300X300X300 CONRETE CHAMBER WITH HOOKS MEBB 450*50*6 GROUND LEVEL NORMAL SIEVED SOIL 50MM 0.5M 25*6 GI STRIP SABO-EREC EARTH PIT 3000MM X 100MM NORMAL SIEVED SOIL 50MM (NOT TO SCALE)
Earthing in electrical network purpose, methods and measurement
Earthing in electrical network purpose, methods and measurement Earth / Ground Conductive ground whose electrical potential at each point is set equal to zero, It is a conductor which provides a low impedance
More informationGrounding Principles. The need to ground! Definitions. Introduction. Grounding Codes and Standards. 2 Ph:
Introduction Grounding and bonding are an integral part of any modern electrical protection system design. An effective, low-impedance ground system is a key element of this system. It is crucial in ensuring
More informationImprovement of Substation Earthing
International Journal of Engineering and Advanced Technology (IJEAT) Improvement of Substation Earthing Mohammad Ali Adelian Abstract Designing a proper substation grounding system is quite complicated.
More informationDESIGNING FOR A LOW RESISTANCE EARTH INTERFACE (GROUNDING)
Newage Energy Holdings DESIGNING FOR A LOW RESISTANCE EARTH INTERFACE (GROUNDING) http://newage-energy.net http://newage-energy.com Newage Energy Page 1 Introduction Grounding (or earthing) is the art
More informationCOMPANY: Aplicaciones Tecnológicas, S.A.
COMPANY: Aplicaciones Tecnológicas, S.A. AREA: Lightning Protection PRODUCT: CONDUCTIVER PLUS REFERENCE: AT 10L AT-10L CONDUCTIVER PLUS 1 / 12 AT-10L CONDUCTIVER PLUS CONDUCTIVER PLUS is a non-corrosive
More informationINFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF:
Page 1 of 7 Authorised by: A.B. Network Services Manager Proposed Review Date: Dec. 11 Issue Date: Dec. 06 No of this copy: INFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF: ITEM: TERMINATIONS
More informationSECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph
More informationFacility and Equipment Grounding
Facility and Equipment Grounding - 2005 Course: PQE203 Presented by: PowerCET Corporation 3350 Scott Blvd. Bldg. 55 Unit 1 Santa Clara, CA 95054 408/988-1346 Fax 408/988-4869 E-mail: training@powercet.com
More informationSPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR
SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR FINANCIAL BID Item DSR Item Description Qty Units No No. Total 1.1.1 Excavating trenches of
More informationCONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS
More information4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING.
4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING. 4.1 All equipment (i.e., switches, breakers, control cabinets, etc.) inside switchyards or substations which require operations by workers must
More informationAn Overview of Earthing
2018 Earthing An Overview of Earthing Gary Blackshaw, Global Business Development Manager Founded by William Joseph Furse Originally as a Steeplejack company Relocated to Traffic Street More emphasis on
More informationPART 7 Technical Specification for Overhead and Underground Service Connection works for the Year
PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17
More informationTender No.:- RITES/CO/B&A/EE/CUK- Gulbarga/External/E-2/2012.
Amendment No. 1. Sub. : Tender: Supply, Erection, Testing & Commissioning of 11kV/440 V substation, Transformers, DG Sets, HT/ LT panels, HT/LT Cables, Street Lighting etc at University Campus at Khadaganchki
More informationIntroduction. A publication by Aquamor
Introduction Very large numbers of family owned wells have been built in Zimbabwe. This number far exceeds 100 000. In almost every case the family itself has excavated the well and in many cases also
More informationCONTENTS. B. System Design and Performance Requirements
16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or
More informationDescription Unit Quantity Rate Kshs. Amount Kshs.
BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove
More informationSECTION GROUNDING
SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment
More informationPARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION
E11 : General Electrical Earthing and LIGHTNING Protection PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION 1 2009-05-12 Review of Mechanical / Electrical and Control
More informationA. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).
16450 GROUNDING ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 05 26 An optional keynote to the
More informationTitle: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards
Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the
More informationCONNECTION TO INSPECTION CHAMBERS PRAKTO
CONNECTION TO INSPECTION CHAMBERS PRAKTO The inspection chambers PRAKTO made by Pipelife are designed and manufactured to be conveniently and securely connected to pipes and fittings of the Pragma series
More informationSECTION EARTHING AND EARTH FAULT PROTECTION
SECTION 16660 PART 1 - GENERAL 1.01 DESCRIPTION A. The work to be performed includes, but is not necessarily limited to, all work involved with the construction and assembly of a complete electrical earthing
More informationDr. Ali Kadhim. Bricks
Bricks Classification of bricks according to constituent raw material: 1. Clay bricks 2. Lime sand bricks 3. Concrete bricks 1. Clay bricks: 1.1 Raw materials: a. Alumina Alumina is main constituent of
More informationGB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA
Translated English of Chinese Standard: GB50169-2016 www.chinesestandard.net Buy True-PDF Auto-delivery. Sales@ChineseStandard.net GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA UDC P GB 50169-2016
More informationSCHEDULE OF RATES. WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT
WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SCHEDULE OF RATES SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT 1 Excavation for foundation in earth all types of soils like clay,
More informationSECTION FACILITY LIGHTNING PROTECTION
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 41 00 FACILITY LIGHTNING PROTECTION SPEC WRITER NOTE: Delete between //----//if not applicable to project. Also delete any other item or paragraph not applicable
More informationConstruction Specification for Utility Adjustments
Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS
More information31-SDMS-03 REV. 01 SPECIFICATIONS FOR
31-SDMS-03 REV. 01 SPECIFICATIONS FOR LOW VOLTAGE CABINET FOR POLE MOUNTED TRANSFORMER This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Description
More informationTECHNICAL SPECIFICATION FOR 1.1KV XLPE POWER CABLE SECTION-1
ANNEXURE TO TENDER NO. PUR42396GM DATED 06 th FEBRUARY 2014 SUPPLY OF 1.1KV GRADE LT POWER CABLES FOR THE PERIOD APRIL 2014 MARCH 2016 TECHNICAL SPECIFICATION FOR 1.1KV XLPE POWER CABLE SECTION-1 1.1 SCOPE
More informationELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID
SBI INFRA MANAGEMENT SOLUTIONS PVT.LTD. 3 rd Floor, Local Head Office,Bank Street, Koti, Hyderabad- 500095 On behalf of On behalf of On behalf of Cash Management Product GOC (CMP GOC) & Internal Audit
More information56-SDMS-01 REV. 01 SPECIFICATIONS FOR
56-SDMS-01 REV. 01 SPECIFICATIONS FOR 13.8KV UNIT SUBSTATIONS This specification is property of SEC and subject to change or modification without any notice CONTENTS PAGE No. 1.0 SCOPE 3 2.0 CROSS REFERENCES
More informationPlease check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must
More informationPLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationSUPPLY ERECTION TOTAL RATE AMOUNT RATE AMOUNT AMOUNT (Rs.) (Rs.) (Rs.) (Rs.) (Rs.)
SBI-AO2 Project Residency Rd Br-elect/RBO-4 SCHEDULE OF QUANTITIES FOR ELECTRICAL WORKS. DATE : 24/4/2018 Sl. No. DESCRIPTION OF WORK UNIT QTY 1 READYMADE FINAL DISTRIBUTION BOARDS Supply, Instillation,
More informationChapter 10. Pipeline Installation
Chapter 10 CHAPTER 10 STOCKWATER PIPELINE INSTALLATION TABLE OF CONTENTS PART 10.1 TRENCHING 10-1 10.1.1 Backhoe Constructed Trench 10-1 10.1.2 Trencher Constructed Trench 10-1 10.1.3 Backfilling and Maintenance
More informationSECTION PART 1 GENERAL
SECTION 16060 GROUNDING AND BONDING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Grounding of electrical systems and equipment and basic requirements for ground for equipment, circuits, and systems.
More informationSECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS
SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment
More information4 EXTREME FOUNDATION PANELS
4 EXTREME FOUNDATION PANELS For Garages On Granular Footings 1. The type of soil is a factor in determining foundation construction details such as footing design, backfill, and drainage provisions. Soils
More informationPart 1: On-land pipelines
Provläsningsexemplar / Preview INTERNATIONAL STANDARD ISO 15589-1 Second edition 2015-03-01 Petroleum, petrochemical and natural gas industries Cathodic protection of pipeline systems Part 1: On-land pipelines
More informationSeptic Tank Guidelines
Septic Tank Guidelines Septic tanks are suitable for conditions where the wastewater can drain away and be absorbed into the soil without contaminating ground water where it is extracted. Sealed solid
More informationSTANDARD SPECIFICATION EARTH GROUNDING Section (Straight Shaft Model)
STANDARD SPECIFICATION EARTH GROUNDING Section 16000 (Straight Shaft Model) PART 1 - GENERAL 1.01 DESCRIPTION A. Related Work Specified Elsewhere: 1. Electrical General Provisions ( Section xxx) 2. Basic
More informationTYPICAL INSTALLATION INSTRUCTIONS
TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect
More information1. IS: 3043/1987 Code of practice for Earthing 2. IEC Requirement of Earthing Enhancement Compound
Gujarat Power Research & Development Cell (A Govt. of Gujarat Initiative) Gujarat Urja Vikas Nigam Ltd CIN: U40109GJ2004SGC045195, IIT Gandhinagar Research Park, IIT Gandhinagar, Palaj-382355, Gandhinagar,
More informationSECTION LIGHTNING PROTECTION SYSTEM
SECTION 16670 - LIGHTNING PROTECTION SYSTEM PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General: Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationCross Borehole Electrical Resistivity Tomography (ERT) Measurements
Introduction Cross Borehole Electrical Resistivity Tomography (ERT) Measurements Resistivity imaging at the surface may be used for applications such as cavity detection, geotechnical investigation, site
More informationNorthern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning
Version:- 2.0 Date of Issue:- Sept 2013 Page 1 of 10 Northern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning Framework for design and planning, materials specification,
More informationABSTRACT EXECUTIVE SUMMARY
MIE TALK August 2016 Compiled by: Schalk J. P. Kruger ABSTRACT Corrosion is a major issue in industrial plant processes especially where any part of the structure is submerged in ground or water. The management
More informationDe Montfort Mark 7 Incinerator (Flatpack)
De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where
More informationSECTION UNDERGROUND ELECTRICAL CONSTRUCTION
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION A. This section specifies the furnishing, installation, and connection of precast manholes and pullboxes with ducts
More informationSECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide labor, materials, equipment, and incidentals as shown, specified, and
More informationGUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS
GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS Version 2014-11-11 Prepared by: Building Development Division Department of Development Services 5 County Complex Ct. Suite 120 Prince William, VA 22192
More information16300 HIGH VOLTAGE DISTRIBUTION
16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served
More informationBILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI
Page 1 BILL OF QUANTITIES - PROJECT ELECTRICAL WORK OF PH-I FOR ASSAM RIFLES, DWARKA, NEW DELHI-110075 I. INSTALLATION OF SUB-STATION EQUIPMENT The rates shall include the following : 1. Assembling loose
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS
More informationh Installation Manual
h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires
More informationA.2.a Random Riprap... Table
3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide
More informationBiogas Construction Process
Paper presented at the Biogas Training Programme Conducted at CARD, Alam Village, Myitkyina. Metta Development Foundation Biogas Construction Process Govinda Prasad Devkota P.O. Box 20506 Kathmandu, Napal
More informationSAS Micropile Manual. Basic dimensioning and design recommendations. Table of Content:
SAS Micropile Manual Basic dimensioning and design recommendations Table of Content: Page System Description 2 Load Capacities 2 Minimum Drill Hole Diameter 3 Load Transfer to Ground 4 Corrosion Protection
More informationTender ref no: SBIIMS/BHU/AO2/ / 57 Date: PRICE BID FOR CIVIL WORKS AT SBI UDALA BRANCH (A) RAIN WATER HARVESTING. Cum 15.
Tender ref no: SBIIMS/BHU/AO/08-9/ Date: 0.0.09 Sl. No. ITEM SPECIFICATION UNIT QTY RATES AMOUNT PRICE BID FOR CIVIL WORKS AT SBI UDALA BRANCH (A) RAIN WATER HARVESTING Earth work in excavation of recharge
More informationBuilding Materials I Lect :Ameer M. H. Lecture (4)
Thermo Stone Thermo stone is a lightweight cement-based material, containing many gas bubbles evenly distributed in the volume, produced by blending and maturing of a mixture of cement, lime, sand, water,
More informationEstimate FOR THE SEPTIC TANK
Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks
More informationNEC 2014 Code Changes
NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge
More informationITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS
ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing
More informationSr. No. Description Qty Unit Rate Amount. S e t
GUJARAT ENERGY TRANSMISSION CORPORATION LTD. TRANSMISSION CIRCLE OFFICE, NADIAD SCHEDULE -B Name of work : ARC for Erection of Structure, Equipments, Earthing, Termination, Laying Control Cables 66/11KV
More informationWind Power Solutions. Company Registration No: Vat Registration No.:
Wind Power Solutions Foundation Grounding and Construction, Bonding, Power Connections, Surge Protection, and Lightning Protection ERICO offers a complete range of foundation grounding and construction,
More informationTHE OFFICIAL TRADE JOURNAL OF BICSI
ICT TODAY THE OFFICIAL TRADE JOURNAL OF BICSI January/February 2017 PLUS + + Information Security and ESS in the Age of the Internet of Things + Grounding System Design and Testing for Critical Facilities
More informationENGINEERING SPECIFICATION EE SPEC
/. Company Directive ENGINEERING SPECIFICATION EE SPEC : 84/1 Relating to Surge Arresters EE SPEC : 84/1 20 December 2013-1 of 7 - IMPLEMENTATION PLAN Introduction This document defines the surge arresters
More informationHUITEX GEOCELL INSTALLATION MANUAL
Table of Contents 1 Site Preparation 2 Installation for the Retaining Wall 2.1 Base Preparation 2.2 Footing Installation 2.3 Placement of the Drainage System 2.4 Placement of the HUITEX Geocell panels
More informationINSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST
Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING
More informationBuilding Construction
Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When
More informationSUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM
31 st July 2017 TENDER FOR RELOCATION OF ONE GE FRAME 6 GAS TURBINE FROM EMBAKASI IN NAIROBI TO MUHORONI NEAR KISUMU: KGN-GT-012-2017 KenGen wishes to make the following clarification and changes through
More informationH. Underground Transmission System Design
H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,
More informationNOVEMBER 2016 GRANDWALL. retaining walls installation guide
NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationRehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL Bill of Quantity : Package2 - Lot 3
ITB 2016-279 Rehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL-10-00098764 Bill of Quantity : Package2 - Lot 3 Package 2 Lot1- Installation, Connection
More informationHomogenous cement-based powder, modified with high quality polymers and cellulose additives.
Page: 1 от 5 (winter formula) adhesive mortar solution for bonding thermo insulation EPS/XPS boards on different bases when thermo-insulating buildings, in mild winter conditions (temperatures from 0 C
More informationSPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building
2004 Specifications CSJ 0720-03-095 SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building 1. Description. Furnish and install Environmentally Controlled Communications Building
More informationSECTION GROUNDING AND BONDING
SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationTECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE
GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used
More informationSWITCHYARD BOQ FOR 400kV ASOJ SUB-STATION - (220/66kv System)
Sr. A and of 220kV Equipments as per respective technical specifications and relevant special conditions. B Surge Arrester 98kV, 0kA, Cl-3 with str and clamp connectors as per Technical spec 6 6 2 BPI
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationNOTICE INVITING QUOTATION
Ref. No: SR-13011(42)/1/2016-APD-SR-MADURAI Subject: Installation of chemical Earthing systems. Date: 29.06.2016 NOTICE INVITING QUOTATION Sealed quotations are invited by Deputy. General Manager (CNS),
More informationCHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2
CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA Adopted September 5, 1989 Table of Contents Page Part 1 Introduction...2 32-1 Purpose...2 32-2 Applicability...2 32-3 Definitions...2 32-4
More informationCHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS
IAC 5/12/93, 4/8/98 Environmental Protection[567] Ch 39, p.1 IAC 5/12/93, 4/8/98 CHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS 567 39.1(455B) Purpose. The purpose of this chapter is to
More informationCONSTRUCTION SPECIFICATION FOR GROUNDING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN
More information50 lbs (23 kg) of + #8 (+2.36 mm) material plus 50 lbs (23 kg) of pile run material.
5.5 REQUIRED SAMPLE SIZES 1. SCOPE This section covers the size of samples to be submitted to the s and Research Center for testing. The sample sizes listed are minimums and in special cases the Engineer
More informationMANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS
DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS ISSUE DATE: 5/1/90 EFFECTIVE DATE: 2/4/92 REVIEW DATE:
More informationSECTION AGGREGATES
SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational
More informationCONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS
More informationDrilling a tube-well inside a wide-diameter well (preliminary trials)
Drilling a tube-well inside a wide-diameter well (preliminary trials) Peter Morgan 2016 Introduction In an earlier manual, the method of connecting a PVC pipe from an underground water chamber to the headworks
More informationELECTRICAL SAFETY Information Bulletin
ELECTRICAL SAFETY Information Bulletin February 2019 Page 1 of 8 2018 CANADIAN ELECTRICAL CODE SUBJECT: Section 10 Grounding and bonding Rule 10-102 Grounding electrodes Replacing metal water service lines
More informationCHAPTER 13 GROUNDING AND BONDING
GROUNDING AND BONDING CHAPTER 13 GROUNDING AND BONDING Grounding and bonding must be in accordance with Article 250 of the National Electrical Code (NEC). Bonding is defined in the NEC as the permanent
More informationGalvanic and Stray Current Corrosion
Chapter 5 Galvanic and Stray Current Corrosion MElec-Ch5-1 Overview Galvanic Corrosion Understanding Galvanic Corrosion Controlling Galvanic Corrosion Stray Current Corrosion Understanding Stray Current
More informationNATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 SUPPLEMENTARY EXAMINATION
MARKING GUIDELINE NATIONAL CERTIFICATE (VOCATIONAL) NQF LEVEL 2 SUPPLEMENTARY EXAMINATION 2010 This marking guideline consists of 6 pages. (MARKING GUIDELINE) -2- NC1530(E)(F19)V QUESTION 1: INTRODUCTION
More informationConstruction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750
1 Preparation of a 18-Classroom School BoQ for constructing a 18-Classroom School - Najaf Site Preparation:Works for leveling the site and remove the garbage to authorized location according to supervisor
More informationSECTION SECONDARY UNIT SUBSTATIONS
SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches,
More informationUNIT RATE ( IN Rs. ) Sl. No ITEM DESCRIPTION QTY UNIT AMOUNT. 80 Nos.
(SECTION : A :- SUPPLY OF EQUIPMENTS/MATERIALS/ITEMS) TENDER NO. BHEL: NR (SCT): BAWANA:11 KV RING MAIN:579 1(A) POLES FOR STRAIGHT RUN / DP STRUCTURE / Four pole structure- Supply of Steel Tubular swaged
More information