ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 PAVEMENT SMOOTHNESS TESTING AND EVALUATION USING INTERNATIONAL ROUGHNESS INDEX CRITERIA

Size: px
Start display at page:

Download "ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 PAVEMENT SMOOTHNESS TESTING AND EVALUATION USING INTERNATIONAL ROUGHNESS INDEX CRITERIA"

Transcription

1 ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 PAVEMENT SMOOTHNESS TESTING AND EVALUATION USING INTERNATIONAL ROUGHNESS INDEX CRITERIA Background Beginning in early 2014 all paving projects include smoothness testing specifications using high speed inertial profilers (IP) and International Roughness Index (IRI) criteria. This construction bulletin replaces section Pavement Smoothness Assessment in the Consultant Engineering Guidelines for Highway and Bridge Projects Volume 2, Construction Contract Administration for contracts including IRI specifications. Acceptance testing is to be provided by the Contractor. Verification testing, discussed later in this bulletin, is only completed when required by the Project Sponsor. This bulletin provides guidance on the monitoring and reporting activities to be completed by the Consultant. Pavements not subject to smoothness testing shall be checked by the Consultant for surface evenness using a three (3) metre long straightedge as outlined in the specifications. Prior to Testing Prior to testing the Consultant shall liaison with the Contractor and/or the IP operator to review which portions of the job are to be tested and/or excluded from assessment and the type of smoothness criteria to be applied (i.e. multi-lift versus single lift versus mill and inlay). Paint markings should be used on the pavement, or other visual means, to indicate limits of excluded areas or changes in smoothness criteria. A listing of pre-qualified firms for Pavement Smoothness Inertial Profilers is provided on the Transportation web-site. Report Submissions After testing the Contractor is to provide the Consultant with an electronic copy (.ppf format) of profile data along with reports for Ride Quality (IRI reported for each wheel path on a sublot basis) and Smoothness Assurance (Areas of Localized Roughness). The Consultant shall review the reports to identify sublots in reject and Areas of Localized Roughness (ALR). The Consultant shall inspect and drive these areas to determine if repairs are required or penalties applied without repair as outlined in the specification. Sample reports are attached. These reports are generated using the software program known as ProVAL (Profile Viewing and Analysis). This program was developed under the sponsorship of the Federal Highway Administration (FHWA) and can be downloaded for free at The Consultant is to review the ProVAL reports to ensure that the proper parameters and settings were applied as outlined in the specification, specifically: 250 mm filter is applied for IRI analysis, Ride Quality IRI is calculated using a fixed interval of 100 m. ALR analysis is completed using a continuous short interval of 7.62 m for the right wheel path and an IRI limiting value of 2.40 m/km (or as specified in the contract). Areas to be excluded from testing or assessment are properly identified. April,

2 ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 Consultants should also have the capability to use the ProVAL software in order to complete their own profile analysis for quality assurance checks completed on a limited basis. Profile viewing using ProVAL is also helpful in dealing with rejected sublots or ALR. The Contractor is to provide Smoothness Summary Spreadsheets for Ride Quality Bonus/Penalty and Areas of Localized Roughness. The Consultant shall review the spreadsheet reports in regards to: Completeness of contract header information. Proper identification of areas to be excluded from testing or assessment. Proper type of construction identified (i.e. multi-lift versus single lift). Proper payment assessment rates used (penalty rates changed in January 2014). Km stations reported matches reasonably well to contract limits (minor deviations may be expected due to the operation of the Distance Measure Instrument). Random calculation checks for a few sublots and ALR. The Consultant shall inform the Contractor and/or IP operator to correct and resubmit any reports with incomplete or erroneous information. Sample summary spreadsheets for penalty/bonus payment assessments are attached and are located on-line in Appendix B of the Engineering Consultant Guidelines for Highways and Bridges Volume 2. Once the following reports have been checked by the Consultant they are to be sent to trans.constructqa@gov.ab.ca as soon as possible but no later than three weeks after the IP testing. ProVAL summary reports for Ride Quality and Smoothness Assurance (.pdf) Smoothness Summary Spreadsheets (.xlxs format). Electronic profile data as submitted by the IP operator. The ProVAL and spreadsheet reports are to be included within the Final Details package in.pdf format along with the form D.18 Final Details (IRI ACP-EPS) that is located in Appendix D of the Engineering Consultant Guidelines for Highway and Bridge Projects Volume 2. Verification Testing Verification testing is described in the IRI smoothness specification and may be initiated by the Department to re-test a project, or portion of, using a pre-qualified firm different to that used by the Contractor. When verification testing is requested by the Project Sponsor, the Consultant shall arrange for and coordinate the testing including liaison with the Contractor. Effective Date: 2014 construction season with contracts containing IRI specifications. 2 April, 2014

3

4 FIGURE 1 Sample ProVAL Analysis: Ride Quality Inputs Threshold (m/km): 1.55 Segment Length (m): Selections File Profile Section Apply 250mm Filter 12435_630_02_r1 Left Elevation Full Yes 12435_630_02_r1 Right Elevation Full Yes Threshold is the lowest MIRI value to trigger reject of a sublot. Sublot length of 100 m. Both wheel paths used to determine the Mean IRI (MIRI). Leave-outs 12435_630_02_r1 Contract No.: Hwy No.: 630 Control Section: 02 1 st lane right of centerline: R1 Start Distance (km) Stop Distance (km) Results 12435_630_02_r1 Start Distance (km) Length (m) Name RailTracks1 Stop Distance (km) Length (m) Left Elevation - IRI (m/km) Right Elevation - IRI (m/km) Within ProVAL this Ride Quality data (and ALR) can be copied and then inserted into the AT spreadsheets for calculating penalty/bonus assessments. ProVAL Page 1 of 2 Tuesday, February 04, :17:20 AM

5 FIGURE 2 Sample ProVAL Analysis: Smoothness Assurance Selections File Profile Section Apply 250mm Filter 12435_630_02_r1 Right Elevation Full Yes Right wheel path used for ALR. Leave-outs 12435_630_02_r1 Start Distance (km) Stop Distance (km) Contract No.: Hwy No.: 630 Control Section: 02 1 st lane right of centerline: R1 Length (m) Name RailTracks1 Short Continuous Segment Length (m): 7.62 Threshold (m/km): 2.40 Specified inputs to determine ALR Leave-outs a.k.a. Excluded Areas are not subject to assessement. All results to be reported without using the Grinding option within ProVAL. No Grinding Start Distance (km) Stop Distance (km) IRI (m/km) Pavement with short continuous IRI greater than 2.40 m/km are defined as Areas of Localized Roughness (ALR). Ride Quality summary (Fixed Interval) is also contained at the end of this report. Other ProVAL summaries within this report (not required for AT) includes Long Continuous and histograms in both table and chart format. ProVAL Page 1 of 6 Tuesday, February 04, :16:42 AM

6 Ride Quality Report Contract No: Type of Test: Acceptance Hwy Number: 630 Contractor: ABC Paving Control Section: Lane: Direction: 2 R1 EB IP Operator: John Fisher Test Date: (mm/dd/yyyy) 2/4/2014 Ride Quality Bonus/Penalty Summary Appendix B20.a Excluded Area? Type of Cons. Sublot Payment Sublot Station (km) Length IRI (m/km) MIRI Yes or SI,SII,or SIII Assessment Number Start End (m) Left Right (m/km) No ($) no SII no SII no SII no SII yes SII Excluded Area Total Assessment Comments: Rail tracks excluded from km to Sublot #5 speed limit < 70 km/hr through the town of Jonesville Notes:Rejected sublots are assessed at -$500 and to be evaluated by Consultant for need of repair. Appendix B20.a, Revised on January 2014 Page 1 of 1

7 Areas of Localized Roughness Report Contract No: Type of Test: Acceptance Hwy Number 630 Contractor: ABC Paving Control Section 2 IP Operator: John Fisher Test Date: Lane: R1 (mm/dd/yyyy) 2/4/2014 Direction: EB Appendix B20.b Areas of Localized Roughness Summary Station (km) IRI (m/km) Length Excluded Area? Type of Cons. Penalty Start End Right (m) Yes or No SI,SII,or SIII Assessment $ no SII -$ no SII -$ no SII $ no SII -$ yes SII Excluded Area Comments: Man hole cover at km Total Assessment -$ Page 1 of 1 Appendix B20.b, revised on January 2014

INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB

INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB 1.1 TESTING AND EVALUATION OF FINISHED PAVEMENT SURFACE SMOOTHNESS USING INTERNATIONAL ROUGHNESS INDEX (IRI) CRITERIA 1.1.1 General Contrary to the requirements of Specification 3.50, Asphalt Concrete

More information

2399 Pavement Surface Smoothness

2399 Pavement Surface Smoothness 2399 Pavement Surface Smoothness 2399.1 DESCRIPTION The final mainline and all other pavement surfaces where the posted vehicle speed is 30 mph [48 km/hr] or greater shall be measured using an Inertial

More information

Special Provision No. 103F31 December 2014

Special Provision No. 103F31 December 2014 ASPHALTIC CONCRETE SURFACE SMOOTHNESS Special Provision No. 103F31 December 2014 Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial

More information

Special Provision No. 103F31 June This Special Provision covers all surface smoothness requirements for hot mix asphalt construction.

Special Provision No. 103F31 June This Special Provision covers all surface smoothness requirements for hot mix asphalt construction. ASPHALTIC CONCRETE SURFACE SMOOTHNESS - Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial Profiler Special Provision No. 103F31 June

More information

Special Provision No. 103F31 January 2014

Special Provision No. 103F31 January 2014 AMENDMENT TO OPSS 313, APRIL 2007 Special Provision No. 103F31 January 2014 Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial Profiler

More information

ASTM Definition of Roughness

ASTM Definition of Roughness Pavement Smoothness ASTM Definition of Roughness The deviations of a pavement surface from a true planar surface with characteristic dimensions that affect vehicle dynamics Pavement Smoothness is a lack

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 6/2/2014 Project 140353 Addendum No. 1 PID No. 86675 MOT IR 75 11.75/11.80

More information

Mississippi DOT s MRI Pilot Specification. James Watkins, P.E. State Research Engineer

Mississippi DOT s MRI Pilot Specification. James Watkins, P.E. State Research Engineer Mississippi DOT s MRI Pilot Specification James Watkins, P.E. State Research Engineer 1 Overview of Presentation MRI Pilot Specification Details Smoothness Pay Incentives Analysis Procedure Profiler Certification

More information

Pay Schedule for Ride Quality

Pay Schedule for Ride Quality Pay Schedule for Ride Quality 2007 Design & Bridge Conference Dale A. Rand, P.E. TxDOT Const. Div. Ride Specification International Roughness Index (IRI) is the International Roughness Index and measures

More information

Comparing 10 Year Performance of Cold In-Place Recycling (CIR) with Emulsion versus CIR with Expanded Asphalt on Highway 7, Perth, Ontario

Comparing 10 Year Performance of Cold In-Place Recycling (CIR) with Emulsion versus CIR with Expanded Asphalt on Highway 7, Perth, Ontario Comparing 10 Year Performance of Cold In-Place Recycling (CIR) with Emulsion versus CIR with Expanded Asphalt on Highway 7, Perth, Ontario Becca Lane, P. Eng. Manager, Materials Engineering and Research

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT AND BRIDGE DECK SMOOTHNESS

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT AND BRIDGE DECK SMOOTHNESS 430-2QA(a-i) 09 OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT AND BRIDGE DECK SMOOTHNESS These Special Provisions amend and where in conflict, supersede applicable sections of the

More information

LIGHT WEIGHT PROFILING SYSTEM

LIGHT WEIGHT PROFILING SYSTEM LIGHT WEIGHT PROFILING SYSTEM Calibration Verification & Operator Certification Program Manual DEPARTMENT OF TRANSPORTATION BUREAU OF MAINTENANCE AND OPERATIONS ASSET MANAGEMENT DIVISION ROADWAY INVENTORY

More information

Josh Bowman, P. E. District 7 Area Engineer

Josh Bowman, P. E. District 7 Area Engineer Josh Bowman, P. E. District 7 Area Engineer Plan acceptance is ultimately granted through the Office of Construction Administration in the District This presentation serves as a guide to what a reasonable

More information

COLD IN-PLACE RECYCLING

COLD IN-PLACE RECYCLING COLD IN-PLACE RECYCLING Southeast Pavement Preservation Partnership Stephen Damp, P.Eng. Senior Vice President, The Miller Group Thursday, May 8, 2008 Presentation Overview Definition of Cold In-Place

More information

Special Provision No. 313F51 March Section of OPSS 313 is amended by the addition of the following:

Special Provision No. 313F51 March Section of OPSS 313 is amended by the addition of the following: SMA 9.5 -... mm LIFT THICKNESS - Item No. SMA 12.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 9.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 12.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 12.5FC 1

More information

Special Provision No. 399F01 December 2014

Special Provision No. 399F01 December 2014 FULL DEPTH CRACK REPAIRS Item No. Special Provision No. 399F01 December 2014 1.0 SCOPE This Special Provision covers the requirements for full depth crack repairs in asphaltic concrete pavements. 2.0 REFERENCES

More information

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures

More information

FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS. T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017

FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS. T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017 FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017 1 2 $2.5 billion of capital program 62 miles of roadway Western section completed in 2014

More information

Evaluation of Smoothness of Louisiana Pavements Based on International Roughness Index and Ride Number

Evaluation of Smoothness of Louisiana Pavements Based on International Roughness Index and Ride Number Jordan Journal of Civil Engineering, Volume 2, No. 3, 28 Evaluation of Smoothness of Louisiana Pavements Based on International Roughness Index and Ride Number Hani H. Titi 1) and Masood Rasoulian 2) 1)

More information

We Are Finally in the 21 st Century

We Are Finally in the 21 st Century We Are Finally in the 21 st Century Nevada Department of Transportation s Switch from PRI (Profile Index) to IRI (International Roughness Index) Steven Hale, P.E. Quality Assurance Engineer 775-888-7226

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE

PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE Quality Assurance is not Quality Control Quality control is Contractors responsibility during construction. Quality Assurance

More information

COURSE MANUAL March, 2009

COURSE MANUAL March, 2009 COURSE MANUAL March, 2009 The Ohio Department of Transportation (ODOT) 1980 W. Broad St., Columbus, OH 43223 TABLE OF CONTENTS INTRODUCTION 25 System Requirements 25 Installation 26 Overview of ProVAL

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 18, 2008 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04

More information

State of New Jersey Department of Transportation

State of New Jersey Department of Transportation State of New Jersey Department of Transportation Special Provisions For State Aid Projects Chris Christie Governor Richard T. Hammer Acting Commissioner Kim Guadagno Lt. Governor Edition 011 SPECIAL PROVISIONS

More information

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It LTRC Seminar - Building Quality Pavements QUALITY What It Is and How to Get It LTRC Seminar - Building Quality Pavements Quality in General What is it? Who s Quality? How do we get it? LTRC Seminar - Building

More information

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report. JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine

More information

FHWA Pavement Surface Characteristics Program And Research Update

FHWA Pavement Surface Characteristics Program And Research Update Focus Area Leadership and Coordination (FALCON) FHWA FHWA Pavement Surface Characteristics Program And Research Update Southeastern States Pavement Management and Design Conference May 11, 2009 Robert

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS

More information

DESIGN BULLETIN #13 (Revised September Supersedes March 2017)

DESIGN BULLETIN #13 (Revised September Supersedes March 2017) DESIGN BULLETIN #3 (Revised September 208. Supersedes March 207) Revisions to Pavement Design Manual for Selection of ACP Mix Types and Asphalt Binder Grades Updates to Design Bulletin #3 (September 208)

More information

2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT

2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT 2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)

More information

Roadway Inspection Recertification. Quality Control / Quality Assurance

Roadway Inspection Recertification. Quality Control / Quality Assurance Roadway Inspection Recertification Quality Control / Quality Assurance **IMPORTANT** Recertification is only for individuals currently certified and actively participating on Asphalt Concrete Projects

More information

SPECIFICATION AMENDMENTS and SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION

SPECIFICATION AMENDMENTS and SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION SPECIFICATION AMENDMENTS and SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION (Supplemental to the Standard Specifications for Highway Construction, Edition 12, 2005, and the Specifications

More information

Prepaving Conferences

Prepaving Conferences Prepaving Conferences Presenters ODOT: Bob Townsend Assistant Project Manager The Dalles Construction Office Knife River: Tyrone Belgarde Project Superintendent Knife River Corporation-Northwest Prepaving

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 Sheet 1 of 14 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 NOTE: This special provision is generally written in the imperative mood. The subject,

More information

Ohio Department of Transportation

Ohio Department of Transportation Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 Ted Strickland, Governor Jolene M. Molitoris, Director THE DEPARTMENT UTILIZES BID EXPRESS (http://www.bidx.com)

More information

IGGA Guide Specification: Conventional Diamond Grinding of City Streets Introduction

IGGA Guide Specification: Conventional Diamond Grinding of City Streets Introduction IGGA Guide Specification: Conventional Diamond Grinding of City Streets Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures for

More information

Roadway Profile Testing in North Carolina

Roadway Profile Testing in North Carolina Roadway Profile Testing in North Carolina PAST PERFORMANCE AND LESSONS LEARNED PRESENTED BY CHRISTOPHER BACCHI, TRIMAT MATERIALS TESTING, INC AND NILESH SURTI, NCDOT Why is Pavement Smoothness Important?

More information

Establishing International Roughness Indices for a dense urban area case study in Washington, DC

Establishing International Roughness Indices for a dense urban area case study in Washington, DC The Sustainable City VI 275 Establishing International Roughness Indices for a dense urban area case study in Washington, DC S. A. Arhin 1, E. C. Noel 1 & M. Lakew 2 1 Howard University, USA 2 District

More information

Regional Engineers. Jack A. Elston

Regional Engineers. Jack A. Elston Regional Engineers Jack A. Elston Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling April 20, 2018 This special provision was developed by the Bureau

More information

Special Provision No. 103F31 February Asphaltic Concrete Surface Tolerance and Payment Adjustment for Surface Smoothness

Special Provision No. 103F31 February Asphaltic Concrete Surface Tolerance and Payment Adjustment for Surface Smoothness AMENDMENT TO OPSS 313, MARCH 1993 Special Provision No. 103F31 February 2007 Asphaltic Concrete Surface Tolerance and Payment Adjustment for Surface Smoothness 313.01 SCOPE Section 313.01 of OPSS 313 is

More information

Section 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS

Section 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS TABLE OF CONTENTS 5.22 SUPPLY AND INSTALL SMOOTH WALL STEEL PIPES... 1 5.22.1 GENERAL... 1 5.22.2 MATERIALS... 1 5.22.2.1 Culvert Material... 1 5.22.2.2 Material for Bedding, Backfill and Sealing... 1

More information

NCAT PAVEMENT TEST TRACK

NCAT PAVEMENT TEST TRACK NCAT PAVEMENT TEST TRACK 1 REPLACEMENT SECTIONS Red Mill and Inlay New Mix Performance Sections (11) Blue Excavate and Install New Structural Sections (5) 2 RESEARCH SPONSORS (+ FHWA) 3 CHAIN OF COMMAND

More information

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL 1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and

More information

CONSTRUCTION SPECIFICATION FOR THE GRINDING OF CENTRELINE AND SHOULDER RUMBLE STRIPS IN ASPHALT

CONSTRUCTION SPECIFICATION FOR THE GRINDING OF CENTRELINE AND SHOULDER RUMBLE STRIPS IN ASPHALT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 342 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR THE GRINDING OF CENTRELINE AND SHOULDER RUMBLE STRIPS IN ASPHALT TABLE OF CONTENTS 342.01 SCOPE

More information

EXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM

EXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM EXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM Completed forms are due in the NCPA office no later than Tuesday, October 23, 2018 for projects substantially complete in 2018. (Please feel free

More information

DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents

DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents Introduction This design bulletin provides a number

More information

Regional Engineers. Maureen M. Addis. Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling

Regional Engineers. Maureen M. Addis. Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling Regional Engineers Maureen M. Addis Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling September 29, 2017 This special provision was developed by the

More information

Section 200 Design Process and Quality Management. Electrical Engineering Centre

Section 200 Design Process and Quality Management. Electrical Engineering Centre Section 200 Design Process and Quality Management Electrical Engineering Centre April 2013 TABLE OF CONTENTS 200 DESIGN PROCESS AND QUALITY MANAGEMENT 201 INTRODUCTION TO DESIGN PROCESS... 1 201.1 ABOUT

More information

Section 3 Specification 3.50 Asphalt Concrete Pavement -EPS TABLE OF CONTENTS

Section 3 Specification 3.50 Asphalt Concrete Pavement -EPS TABLE OF CONTENTS TABLE OF CONTENTS 3.50 ASPHALT CONCRETE PAVEMENT - END PRODUCT SPECIFICATION... 1 3.50.1 GENERAL... 1 3.50.1.1 Description... 1 3.50.1.2 Definitions... 1 3.50.1.2.1 Acceptance Limits... 1 3.50.1.2.2 Asphalt

More information

PCC Pavement Rideability

PCC Pavement Rideability Supplemental Technical Specification for PCC Pavement Rideability SCDOT Designation: SC-M-502 (04/16) 1. SCOPE 1.1. The Resident Construction Engineer (RCE) will evaluate Portland cement concrete (PCC)

More information

MATERIAL SPECIFICATION FOR PERFORMANCE GRADED ASPHALT CEMENT

MATERIAL SPECIFICATION FOR PERFORMANCE GRADED ASPHALT CEMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1101 NOVEMBER 2002 MATERIAL SPECIFICATION FOR PERFORMANCE GRADED ASPHALT CEMENT 1101.01 SCOPE 1101.02 REFERENCES 1101.03 DEFINITIONS TABLE OF CONTENTS

More information

KDOT Road to Pavement Preservation Maintenance Conference Kansas City, Missouri November 1, 2005

KDOT Road to Pavement Preservation Maintenance Conference Kansas City, Missouri November 1, 2005 KDOT Road to Pavement Preservation 2005 Maintenance Conference Kansas City, Missouri November 1, 2005 System 9,565 Centerline miles 25,872 Lane miles 4,932 Bridges 2,688,418 Population National Survey

More information

GUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES

GUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES GUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES EDITION 2 JULY, 2006 Page left blank intentionally EDITION 2 JULY, 2006 FOREWORD Alberta Infrastructure & Transportation's Pavement

More information

CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER

CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 320 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER TABLE OF CONTENTS 320.01 SCOPE 320.02 REFERENCES 320.03 DEFINITIONS 320.04

More information

Section 3 Specification 3.30 Asphalt Pavement Crack Routing and Sealing TABLE OF CONTENTS

Section 3 Specification 3.30 Asphalt Pavement Crack Routing and Sealing TABLE OF CONTENTS TABLE OF CONTENTS 3.30 ASPHALT PAVEMENT CRACK ROUTING AND SEALING... 1 3.30.1 GENERAL... 1 3.30.2 MATERIALS... 1 3.30.2.1 Crack Sealant... 1 3.30.2.2 Blotting Agents... 2 3.30.3 EQUIPMENT... 2 3.30.4 CRACK

More information

PERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT

PERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT PERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT PERMIT # DATE: Name Of Applicant Address City, State, Zip ( ) Fax: ( ) Email Telephone Number permit faxed (date) permit emailed (date) Permission is

More information

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS 603.1 DESCRIPTION Determine the smoothness of the pavement surface and correct the deficiencies as specified in the Contract Documents. For the purposes of this

More information

SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER)

SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER) C&T:JWB 1 of 10 C&T APPR:KPK:CJB:08-02-06 FHWA:APPR:08-21-06 a.

More information

AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS

AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS INTRODUCTION With alternate bidding, road and highway agencies offer the opportunity to

More information

Georgia DOT Micro-milling and Thin Overlay

Georgia DOT Micro-milling and Thin Overlay Georgia DOT Micro-milling and Thin Overlay Presented by Yichang (James) Tsai, Ph.D., P.E., Professor Georgia Institute of Technology Erany Robinson-Perry, P.E., Assistant State Maintenance Engineer Georgia

More information

CONSTRUCTION SPECIFICATION FOR TACK COATING AND JOINT PAINTING

CONSTRUCTION SPECIFICATION FOR TACK COATING AND JOINT PAINTING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 308 APRIL 2012 CONSTRUCTION SPECIFICATION FOR TACK COATING AND JOINT PAINTING TABLE OF CONTENTS 308.01 SCOPE 308.02 REFERENCES 308.03 DEFINITIONS

More information

NYSDOT TRANSPORTATION MAINTENANCE DIVISION PAVING PROJECT QUALITY ASSURANCE ASSESSMENT Rating Guidelines (Revision #1)

NYSDOT TRANSPORTATION MAINTENANCE DIVISION PAVING PROJECT QUALITY ASSURANCE ASSESSMENT Rating Guidelines (Revision #1) NYSDOT TRANSPORTATION MAINTENANCE DIVISION PAVING PROJECT QUALITY ASSURANCE ASSESSMENT Rating Guidelines (Revision #1) INTRODUCTION The condition assessment is intended to be performed from a customer

More information

Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association

Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association Representatives of VDOT (consultant or inspector) must be familiar with the VDOT Road and Bridge Specifications as well as Special

More information

Pavement Data Quality Management Plan. As required by 23 CFR (c)

Pavement Data Quality Management Plan. As required by 23 CFR (c) Pavement Data Quality Management Plan As required by 23 CFR 490.319(c) 05/10/2018 Table of Contents Pavement Data Quality Management Plan... 1 Data Collection Equipment... 1 Equipment Calibration... 3

More information

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE 1) PAVEMENT 1.1 Ride quality All roadways have a smooth surface course (including bridge deck approaches, covers, gratings, frames and boxes). 24 hours 28 days 6 months a. Measurement of International

More information

AC 15/ H UPDATE

AC 15/ H UPDATE FAA Airport Construction Guide Specifications AC 15/5370-10H UPDATE Gary L. Mitchell, P.E. Vice President Airports Acknowledgement Doug Johnson Greg Cline Why Update Scheduled 3 5 years Update References

More information

25 th ANNUAL BEST IN COLORADO

25 th ANNUAL BEST IN COLORADO 25 th ANNUAL BEST IN COLORADO ASPHALT PAVEMENT AWARDS PROGRAM 2018 AWARD CRITERIA The Colorado Asphalt Pavement Association (CAPA) recognizes the highest quality asphalt pavement construction and performance

More information

3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS

3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS 3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS 3.70.1 GENERAL 3.70.1.1 Description 3.70.1.2 Definitions 3.70.1.2.1 Acceptance Limits 3.70.1.2.2 Bridge Construction

More information

Special Provision No. 308F01 May 2010

Special Provision No. 308F01 May 2010 TACK COAT Item No. Special Provision No. 308F01 May 2010 OPSS.PROV 308, April 2007, Construction Specification for Tack Coating and Joint Painting, is deleted in its entirety and replaced with the following:

More information

Washington State DOT: Pavement and Bridge Performance NPRM Comments for federal docket,

Washington State DOT: Pavement and Bridge Performance NPRM Comments for federal docket, MAP-21 NPRM for National Performance Management Measures; Assessing Pavement Condition for the National Highway Performance Program and Bridge Condition for the National Highway Performance Program The

More information

2006 RPUG Changing from PI to IRI. Colorado DOT Experience Eric Prieve

2006 RPUG Changing from PI to IRI. Colorado DOT Experience Eric Prieve 2006 RPUG Changing from PI to IRI Colorado DOT Experience Eric Prieve Current Specification Since 1999 CDOT has used the profilograph for pavement smoothness quality Incentives based on the average PI

More information

< ~ -n~rtz, Concrete Engineer Office of Materials

< ~ -n~rtz, Concrete Engineer Office of Materials Minnesota Department of Transportation MEMO Office of Materials Mailstop 645 1400 Gervais Avenue Maplewood, MN 55109 'stribution 57, 612, 618, 650 ~ < ~ -n~rtz, Concrete Engineer Office of Materials Implementation

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER) CFS:JWB 1 of 9 APPR:KPK:CJB:11-02-15 FHWA:APPR:11-02-15

More information

CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING

CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 333 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING TABLE OF CONTENTS 333.01 SCOPE 333.02 REFERENCES 333.03 DEFINITIONS 333.04

More information

Pavement Preservation and Thin Lift Asphalt NCAUPG and Illinois Bituminous Paving Conference February 3, 2015

Pavement Preservation and Thin Lift Asphalt NCAUPG and Illinois Bituminous Paving Conference February 3, 2015 Pavement Preservation and Thin Lift Asphalt NCAUPG and Illinois Bituminous Paving Conference February 3, 2015 Dr. Michael Heitzman, PE Dr. Mary Robbins Mr. Don Watson, PE Pavement Preservation A program

More information

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 334 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX TABLE OF CONTENTS 334.01 SCOPE 334.02 REFERENCES 334.03 DEFINITIONS 334.04

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MATERIALS AND WORKMANSHIP PAVEMENT WARRANTY

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MATERIALS AND WORKMANSHIP PAVEMENT WARRANTY MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MATERIALS AND WORKMANSHIP PAVEMENT WARRANTY CFS:EMC 1 of 8 APPR:KPK:CJB:06-13-17 FHWA:APPR:06-14-17 a. Description. The materials and workmanship

More information

KENTUCKY TRANSPORTATION CENTER

KENTUCKY TRANSPORTATION CENTER Research Report KTC-04-22/SPR-209-00-1F KENTUCKY TRANSPORTATION CENTER OPTIMIZATION AND STANDARDIZATION OF PAVEMENT MANAGEMENT PROCESSES UNIVERSITY OF KENTUCKY College of Engineering OUR MISSION We provide

More information

END RESULT ASPHALT PAVEMENT SPECIFICATION FOR P3 PROJECTS BENEFITS FOR THE OPERATOR AND CONTRACTOR

END RESULT ASPHALT PAVEMENT SPECIFICATION FOR P3 PROJECTS BENEFITS FOR THE OPERATOR AND CONTRACTOR END RESULT ASPHALT PAVEMENT SPECIFICATION FOR P3 PROJECTS BENEFITS FOR THE OPERATOR AND CONTRACTOR Graham Clark, P.Eng. Project Manager Brun Way Highways Operations Inc. Paper prepared for presentation

More information

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 334 NOVEMBER 2007 CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX TABLE OF CONTENTS 334.01 SCOPE 334.02 REFERENCES 334.03 DEFINITIONS 334.04 DESIGN

More information

Make copies of all test results and control charts readily available to the Engineer at the project site.

Make copies of all test results and control charts readily available to the Engineer at the project site. 5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN NOTE: This document is generally written in the imperative mood. The subject, "the Contractor" is implied. Also implied in this language are "shall",

More information

APPENDIX A1 State Test Case #1, Florida: FDOT SECTION 334A Airport Pavement for <60,000# AGW

APPENDIX A1 State Test Case #1, Florida: FDOT SECTION 334A Airport Pavement for <60,000# AGW Appendix A1 of Final Report for AAPTP Project 06-05 State Test Case #1, Florida Airports (not authorized for use) APPENDIX A1 State Test Case #1, Florida: FDOT SECTION 334A Airport Pavement for

More information

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS I. INTRODUCTION...1 II. III. Purpose...1 What Is LCCA?...1 History of

More information

ALBERTA TRANSPORTATION. Subject Area Bituminous Material and Mixes. Project No. Report No. Report Date. August 2002 Type of Report ABTR/RD/TM-02/01

ALBERTA TRANSPORTATION. Subject Area Bituminous Material and Mixes. Project No. Report No. Report Date. August 2002 Type of Report ABTR/RD/TM-02/01 Report No. ABTR/RD/TM-02/01 Subject Area Bituminous Material and Mixes Project No. 8454-000001 Title Validation and Revision of Asphalt Concrete Mix Type Selection and Characteristics Study Author(s) Alberta

More information

53.5 ASPHALT PAVEMENT CRACK ROUTING AND SEALING

53.5 ASPHALT PAVEMENT CRACK ROUTING AND SEALING 53.5 ASPHALT PAVEMENT CRACK ROUTING AND SEALING 53.5.1 GENERAL The Work consists of routing, cleaning and drying cracks in pavement surfaces and sealing them with the crack sealant. 53.5.2 MATERIALS The

More information

FIELD REPORT: TEXAS EQUIPMENT LOAN EL Implementation Assistance Program. Tools to Improve PCC Pavement Smoothness During Construction (R06E)

FIELD REPORT: TEXAS EQUIPMENT LOAN EL Implementation Assistance Program. Tools to Improve PCC Pavement Smoothness During Construction (R06E) EL04-2015 Implementation Assistance Program Tools to Improve PCC Pavement Smoothness During Construction (R06E) Seeking widespread adoption of the realtime smoothness (RTS) technology by contractors and

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 NOVEMBER 2015 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES 1821.03 DEFINITIONS

More information

39 HOT MIX ASPHALT, SUPERPAVE

39 HOT MIX ASPHALT, SUPERPAVE 39-1.01 GENERAL 39-1.01A Summary Replace section 39 with: 39 HOT MIX ASPHALT, SUPERPAVE Section 39 includes specifications for producing and placing HMA by mixing aggregate and asphalt binder at a mixing

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 APRIL 2004 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES

More information

THE EFFECT OF INITIAL PAVEMENT SMOOTHNESS ON LONG- TERM ROUGHNESS PROGRESSION: SOME FINDINGS FROM C-LTPP AND US-LTPP STUDIES

THE EFFECT OF INITIAL PAVEMENT SMOOTHNESS ON LONG- TERM ROUGHNESS PROGRESSION: SOME FINDINGS FROM C-LTPP AND US-LTPP STUDIES THE EFFECT OF INITIAL PAVEMENT SMOOTHNESS ON LONG- TERM ROUGHNESS PROGRESSION: SOME FINDINGS FROM C-LTPP AND US-LTPP STUDIES This brief provides findings on the observed effect of initial pavement smoothness

More information

Minnesota Concrete Flatwork Specifications for Local Government Agencies

Minnesota Concrete Flatwork Specifications for Local Government Agencies Minnesota Concrete Flatwork LTAP Concrete Flatwork Specifications Mn Concrete Flatwork Specifications for Local MN Concrete Flatwork Agencies Approved for use on Local Government Agency Projects and State

More information

SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers.

SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers. SECTION 31 62 16 STEEL H PILES PART 1 - GENERAL 1.01 SCOPE OF WORK A. Section includes steel H piles embedded into drilled concrete piers. B. Furnish all labor, materials, equipment and incidentals required

More information

TEMPORARILY SUSPENDED

TEMPORARILY SUSPENDED DESIGN BULLETIN #83/2014 0. (REVISED May 26, 2014) Project Identification Sign for Capital and Rehabilitation Construction Projects May 26, 2014 Amendment to Design Bulletin #83/2014 This amendment is

More information

Procedures. Model Procedure for Sampling Inspection of Isolated Lots. Procedure based on S-S-04

Procedures. Model Procedure for Sampling Inspection of Isolated Lots. Procedure based on S-S-04 Procedures Category: STATISTICAL METHODS Procedure: P-S-04-A (rev. 1) Page: i of ii Model Procedure for Sampling Inspection of Isolated Lots Procedure based on S-S-04 Category: STATISTICAL METHODS Procedure:

More information

**************************************************************************

************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 01 16.71 (February 2017) ------------------------------ Preparing Activity: USACE Superseding UFGS-32 01 16.17 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

**************************************************************************

************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 01 16.71 (February 2017) ------------------------------ Preparing Activity: USACE Superseding UFGS-32 01 16.17 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SMOOTHNESS OF PAVEMENTS IN CONNECTICUT Phase 2-Report DATA ANALYSES and TRENDS. June, Prepared by Dr. Charles E. Dougan

SMOOTHNESS OF PAVEMENTS IN CONNECTICUT Phase 2-Report DATA ANALYSES and TRENDS. June, Prepared by Dr. Charles E. Dougan SMOOTHNESS OF PAVEMENTS IN CONNECTICUT Phase 2-Report DATA ANALYSES and TRENDS June, 2001 Prepared by Dr. Charles E. Dougan Report Number 2226-F-2001-1 This project was sponsored by the Connecticut Department

More information

REQUEST FOR PROPOSAL Department of Public Works Highway Division

REQUEST FOR PROPOSAL Department of Public Works Highway Division REQUEST FOR PROPOSAL Department of Public Works Highway Division Town Office Location: 2417 Franklin Street Telephone: (802) 247-3635 Ext. 211 Pre-Bid Meeting: Monday, April 6 th Bid Opening: Monday, April

More information