ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 PAVEMENT SMOOTHNESS TESTING AND EVALUATION USING INTERNATIONAL ROUGHNESS INDEX CRITERIA
|
|
- Aubrey Craig
- 5 years ago
- Views:
Transcription
1 ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 PAVEMENT SMOOTHNESS TESTING AND EVALUATION USING INTERNATIONAL ROUGHNESS INDEX CRITERIA Background Beginning in early 2014 all paving projects include smoothness testing specifications using high speed inertial profilers (IP) and International Roughness Index (IRI) criteria. This construction bulletin replaces section Pavement Smoothness Assessment in the Consultant Engineering Guidelines for Highway and Bridge Projects Volume 2, Construction Contract Administration for contracts including IRI specifications. Acceptance testing is to be provided by the Contractor. Verification testing, discussed later in this bulletin, is only completed when required by the Project Sponsor. This bulletin provides guidance on the monitoring and reporting activities to be completed by the Consultant. Pavements not subject to smoothness testing shall be checked by the Consultant for surface evenness using a three (3) metre long straightedge as outlined in the specifications. Prior to Testing Prior to testing the Consultant shall liaison with the Contractor and/or the IP operator to review which portions of the job are to be tested and/or excluded from assessment and the type of smoothness criteria to be applied (i.e. multi-lift versus single lift versus mill and inlay). Paint markings should be used on the pavement, or other visual means, to indicate limits of excluded areas or changes in smoothness criteria. A listing of pre-qualified firms for Pavement Smoothness Inertial Profilers is provided on the Transportation web-site. Report Submissions After testing the Contractor is to provide the Consultant with an electronic copy (.ppf format) of profile data along with reports for Ride Quality (IRI reported for each wheel path on a sublot basis) and Smoothness Assurance (Areas of Localized Roughness). The Consultant shall review the reports to identify sublots in reject and Areas of Localized Roughness (ALR). The Consultant shall inspect and drive these areas to determine if repairs are required or penalties applied without repair as outlined in the specification. Sample reports are attached. These reports are generated using the software program known as ProVAL (Profile Viewing and Analysis). This program was developed under the sponsorship of the Federal Highway Administration (FHWA) and can be downloaded for free at The Consultant is to review the ProVAL reports to ensure that the proper parameters and settings were applied as outlined in the specification, specifically: 250 mm filter is applied for IRI analysis, Ride Quality IRI is calculated using a fixed interval of 100 m. ALR analysis is completed using a continuous short interval of 7.62 m for the right wheel path and an IRI limiting value of 2.40 m/km (or as specified in the contract). Areas to be excluded from testing or assessment are properly identified. April,
2 ALBERTA TRANSPORTATION CONSTRUCTION BULLETIN #25 Consultants should also have the capability to use the ProVAL software in order to complete their own profile analysis for quality assurance checks completed on a limited basis. Profile viewing using ProVAL is also helpful in dealing with rejected sublots or ALR. The Contractor is to provide Smoothness Summary Spreadsheets for Ride Quality Bonus/Penalty and Areas of Localized Roughness. The Consultant shall review the spreadsheet reports in regards to: Completeness of contract header information. Proper identification of areas to be excluded from testing or assessment. Proper type of construction identified (i.e. multi-lift versus single lift). Proper payment assessment rates used (penalty rates changed in January 2014). Km stations reported matches reasonably well to contract limits (minor deviations may be expected due to the operation of the Distance Measure Instrument). Random calculation checks for a few sublots and ALR. The Consultant shall inform the Contractor and/or IP operator to correct and resubmit any reports with incomplete or erroneous information. Sample summary spreadsheets for penalty/bonus payment assessments are attached and are located on-line in Appendix B of the Engineering Consultant Guidelines for Highways and Bridges Volume 2. Once the following reports have been checked by the Consultant they are to be sent to trans.constructqa@gov.ab.ca as soon as possible but no later than three weeks after the IP testing. ProVAL summary reports for Ride Quality and Smoothness Assurance (.pdf) Smoothness Summary Spreadsheets (.xlxs format). Electronic profile data as submitted by the IP operator. The ProVAL and spreadsheet reports are to be included within the Final Details package in.pdf format along with the form D.18 Final Details (IRI ACP-EPS) that is located in Appendix D of the Engineering Consultant Guidelines for Highway and Bridge Projects Volume 2. Verification Testing Verification testing is described in the IRI smoothness specification and may be initiated by the Department to re-test a project, or portion of, using a pre-qualified firm different to that used by the Contractor. When verification testing is requested by the Project Sponsor, the Consultant shall arrange for and coordinate the testing including liaison with the Contractor. Effective Date: 2014 construction season with contracts containing IRI specifications. 2 April, 2014
3
4 FIGURE 1 Sample ProVAL Analysis: Ride Quality Inputs Threshold (m/km): 1.55 Segment Length (m): Selections File Profile Section Apply 250mm Filter 12435_630_02_r1 Left Elevation Full Yes 12435_630_02_r1 Right Elevation Full Yes Threshold is the lowest MIRI value to trigger reject of a sublot. Sublot length of 100 m. Both wheel paths used to determine the Mean IRI (MIRI). Leave-outs 12435_630_02_r1 Contract No.: Hwy No.: 630 Control Section: 02 1 st lane right of centerline: R1 Start Distance (km) Stop Distance (km) Results 12435_630_02_r1 Start Distance (km) Length (m) Name RailTracks1 Stop Distance (km) Length (m) Left Elevation - IRI (m/km) Right Elevation - IRI (m/km) Within ProVAL this Ride Quality data (and ALR) can be copied and then inserted into the AT spreadsheets for calculating penalty/bonus assessments. ProVAL Page 1 of 2 Tuesday, February 04, :17:20 AM
5 FIGURE 2 Sample ProVAL Analysis: Smoothness Assurance Selections File Profile Section Apply 250mm Filter 12435_630_02_r1 Right Elevation Full Yes Right wheel path used for ALR. Leave-outs 12435_630_02_r1 Start Distance (km) Stop Distance (km) Contract No.: Hwy No.: 630 Control Section: 02 1 st lane right of centerline: R1 Length (m) Name RailTracks1 Short Continuous Segment Length (m): 7.62 Threshold (m/km): 2.40 Specified inputs to determine ALR Leave-outs a.k.a. Excluded Areas are not subject to assessement. All results to be reported without using the Grinding option within ProVAL. No Grinding Start Distance (km) Stop Distance (km) IRI (m/km) Pavement with short continuous IRI greater than 2.40 m/km are defined as Areas of Localized Roughness (ALR). Ride Quality summary (Fixed Interval) is also contained at the end of this report. Other ProVAL summaries within this report (not required for AT) includes Long Continuous and histograms in both table and chart format. ProVAL Page 1 of 6 Tuesday, February 04, :16:42 AM
6 Ride Quality Report Contract No: Type of Test: Acceptance Hwy Number: 630 Contractor: ABC Paving Control Section: Lane: Direction: 2 R1 EB IP Operator: John Fisher Test Date: (mm/dd/yyyy) 2/4/2014 Ride Quality Bonus/Penalty Summary Appendix B20.a Excluded Area? Type of Cons. Sublot Payment Sublot Station (km) Length IRI (m/km) MIRI Yes or SI,SII,or SIII Assessment Number Start End (m) Left Right (m/km) No ($) no SII no SII no SII no SII yes SII Excluded Area Total Assessment Comments: Rail tracks excluded from km to Sublot #5 speed limit < 70 km/hr through the town of Jonesville Notes:Rejected sublots are assessed at -$500 and to be evaluated by Consultant for need of repair. Appendix B20.a, Revised on January 2014 Page 1 of 1
7 Areas of Localized Roughness Report Contract No: Type of Test: Acceptance Hwy Number 630 Contractor: ABC Paving Control Section 2 IP Operator: John Fisher Test Date: Lane: R1 (mm/dd/yyyy) 2/4/2014 Direction: EB Appendix B20.b Areas of Localized Roughness Summary Station (km) IRI (m/km) Length Excluded Area? Type of Cons. Penalty Start End Right (m) Yes or No SI,SII,or SIII Assessment $ no SII -$ no SII -$ no SII $ no SII -$ yes SII Excluded Area Comments: Man hole cover at km Total Assessment -$ Page 1 of 1 Appendix B20.b, revised on January 2014
INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB
1.1 TESTING AND EVALUATION OF FINISHED PAVEMENT SURFACE SMOOTHNESS USING INTERNATIONAL ROUGHNESS INDEX (IRI) CRITERIA 1.1.1 General Contrary to the requirements of Specification 3.50, Asphalt Concrete
More information2399 Pavement Surface Smoothness
2399 Pavement Surface Smoothness 2399.1 DESCRIPTION The final mainline and all other pavement surfaces where the posted vehicle speed is 30 mph [48 km/hr] or greater shall be measured using an Inertial
More informationSpecial Provision No. 103F31 December 2014
ASPHALTIC CONCRETE SURFACE SMOOTHNESS Special Provision No. 103F31 December 2014 Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial
More informationSpecial Provision No. 103F31 June This Special Provision covers all surface smoothness requirements for hot mix asphalt construction.
ASPHALTIC CONCRETE SURFACE SMOOTHNESS - Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial Profiler Special Provision No. 103F31 June
More informationSpecial Provision No. 103F31 January 2014
AMENDMENT TO OPSS 313, APRIL 2007 Special Provision No. 103F31 January 2014 Asphaltic Concrete Payment Adjustment for Surface Smoothness Based on Quality Assurance Measurements Taken by an Inertial Profiler
More informationASTM Definition of Roughness
Pavement Smoothness ASTM Definition of Roughness The deviations of a pavement surface from a true planar surface with characteristic dimensions that affect vehicle dynamics Pavement Smoothness is a lack
More informationOhio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 6/2/2014 Project 140353 Addendum No. 1 PID No. 86675 MOT IR 75 11.75/11.80
More informationMississippi DOT s MRI Pilot Specification. James Watkins, P.E. State Research Engineer
Mississippi DOT s MRI Pilot Specification James Watkins, P.E. State Research Engineer 1 Overview of Presentation MRI Pilot Specification Details Smoothness Pay Incentives Analysis Procedure Profiler Certification
More informationPay Schedule for Ride Quality
Pay Schedule for Ride Quality 2007 Design & Bridge Conference Dale A. Rand, P.E. TxDOT Const. Div. Ride Specification International Roughness Index (IRI) is the International Roughness Index and measures
More informationComparing 10 Year Performance of Cold In-Place Recycling (CIR) with Emulsion versus CIR with Expanded Asphalt on Highway 7, Perth, Ontario
Comparing 10 Year Performance of Cold In-Place Recycling (CIR) with Emulsion versus CIR with Expanded Asphalt on Highway 7, Perth, Ontario Becca Lane, P. Eng. Manager, Materials Engineering and Research
More informationOKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT AND BRIDGE DECK SMOOTHNESS
430-2QA(a-i) 09 OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT AND BRIDGE DECK SMOOTHNESS These Special Provisions amend and where in conflict, supersede applicable sections of the
More informationLIGHT WEIGHT PROFILING SYSTEM
LIGHT WEIGHT PROFILING SYSTEM Calibration Verification & Operator Certification Program Manual DEPARTMENT OF TRANSPORTATION BUREAU OF MAINTENANCE AND OPERATIONS ASSET MANAGEMENT DIVISION ROADWAY INVENTORY
More informationJosh Bowman, P. E. District 7 Area Engineer
Josh Bowman, P. E. District 7 Area Engineer Plan acceptance is ultimately granted through the Office of Construction Administration in the District This presentation serves as a guide to what a reasonable
More informationCOLD IN-PLACE RECYCLING
COLD IN-PLACE RECYCLING Southeast Pavement Preservation Partnership Stephen Damp, P.Eng. Senior Vice President, The Miller Group Thursday, May 8, 2008 Presentation Overview Definition of Cold In-Place
More informationSpecial Provision No. 313F51 March Section of OPSS 313 is amended by the addition of the following:
SMA 9.5 -... mm LIFT THICKNESS - Item No. SMA 12.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 9.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 12.5 -... mm LIFT THICKNESS - Item No. SUPERPAVE 12.5FC 1
More informationSpecial Provision No. 399F01 December 2014
FULL DEPTH CRACK REPAIRS Item No. Special Provision No. 399F01 December 2014 1.0 SCOPE This Special Provision covers the requirements for full depth crack repairs in asphaltic concrete pavements. 2.0 REFERENCES
More informationIGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction
IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures
More informationFIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS. T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017
FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017 1 2 $2.5 billion of capital program 62 miles of roadway Western section completed in 2014
More informationEvaluation of Smoothness of Louisiana Pavements Based on International Roughness Index and Ride Number
Jordan Journal of Civil Engineering, Volume 2, No. 3, 28 Evaluation of Smoothness of Louisiana Pavements Based on International Roughness Index and Ride Number Hani H. Titi 1) and Masood Rasoulian 2) 1)
More informationWe Are Finally in the 21 st Century
We Are Finally in the 21 st Century Nevada Department of Transportation s Switch from PRI (Profile Index) to IRI (International Roughness Index) Steven Hale, P.E. Quality Assurance Engineer 775-888-7226
More informationExtraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method
3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed
More informationPAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE
PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE Quality Assurance is not Quality Control Quality control is Contractors responsibility during construction. Quality Assurance
More informationCOURSE MANUAL March, 2009
COURSE MANUAL March, 2009 The Ohio Department of Transportation (ODOT) 1980 W. Broad St., Columbus, OH 43223 TABLE OF CONTENTS INTRODUCTION 25 System Requirements 25 Installation 26 Overview of ProVAL
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 18, 2008 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
More informationState of New Jersey Department of Transportation
State of New Jersey Department of Transportation Special Provisions For State Aid Projects Chris Christie Governor Richard T. Hammer Acting Commissioner Kim Guadagno Lt. Governor Edition 011 SPECIAL PROVISIONS
More informationLTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It
LTRC Seminar - Building Quality Pavements QUALITY What It Is and How to Get It LTRC Seminar - Building Quality Pavements Quality in General What is it? Who s Quality? How do we get it? LTRC Seminar - Building
More information2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.
JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine
More informationFHWA Pavement Surface Characteristics Program And Research Update
Focus Area Leadership and Coordination (FALCON) FHWA FHWA Pavement Surface Characteristics Program And Research Update Southeastern States Pavement Management and Design Conference May 11, 2009 Robert
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS
More informationDESIGN BULLETIN #13 (Revised September Supersedes March 2017)
DESIGN BULLETIN #3 (Revised September 208. Supersedes March 207) Revisions to Pavement Design Manual for Selection of ACP Mix Types and Asphalt Binder Grades Updates to Design Bulletin #3 (September 208)
More information2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT
2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)
More informationRoadway Inspection Recertification. Quality Control / Quality Assurance
Roadway Inspection Recertification Quality Control / Quality Assurance **IMPORTANT** Recertification is only for individuals currently certified and actively participating on Asphalt Concrete Projects
More informationSPECIFICATION AMENDMENTS and SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION
SPECIFICATION AMENDMENTS and SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION (Supplemental to the Standard Specifications for Highway Construction, Edition 12, 2005, and the Specifications
More informationPrepaving Conferences
Prepaving Conferences Presenters ODOT: Bob Townsend Assistant Project Manager The Dalles Construction Office Knife River: Tyrone Belgarde Project Superintendent Knife River Corporation-Northwest Prepaving
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990
Sheet 1 of 14 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 NOTE: This special provision is generally written in the imperative mood. The subject,
More informationOhio Department of Transportation
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 Ted Strickland, Governor Jolene M. Molitoris, Director THE DEPARTMENT UTILIZES BID EXPRESS (http://www.bidx.com)
More informationIGGA Guide Specification: Conventional Diamond Grinding of City Streets Introduction
IGGA Guide Specification: Conventional Diamond Grinding of City Streets Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures for
More informationRoadway Profile Testing in North Carolina
Roadway Profile Testing in North Carolina PAST PERFORMANCE AND LESSONS LEARNED PRESENTED BY CHRISTOPHER BACCHI, TRIMAT MATERIALS TESTING, INC AND NILESH SURTI, NCDOT Why is Pavement Smoothness Important?
More informationEstablishing International Roughness Indices for a dense urban area case study in Washington, DC
The Sustainable City VI 275 Establishing International Roughness Indices for a dense urban area case study in Washington, DC S. A. Arhin 1, E. C. Noel 1 & M. Lakew 2 1 Howard University, USA 2 District
More informationRegional Engineers. Jack A. Elston
Regional Engineers Jack A. Elston Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling April 20, 2018 This special provision was developed by the Bureau
More informationSpecial Provision No. 103F31 February Asphaltic Concrete Surface Tolerance and Payment Adjustment for Surface Smoothness
AMENDMENT TO OPSS 313, MARCH 1993 Special Provision No. 103F31 February 2007 Asphaltic Concrete Surface Tolerance and Payment Adjustment for Surface Smoothness 313.01 SCOPE Section 313.01 of OPSS 313 is
More informationSection 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS
TABLE OF CONTENTS 5.22 SUPPLY AND INSTALL SMOOTH WALL STEEL PIPES... 1 5.22.1 GENERAL... 1 5.22.2 MATERIALS... 1 5.22.2.1 Culvert Material... 1 5.22.2.2 Material for Bedding, Backfill and Sealing... 1
More informationNCAT PAVEMENT TEST TRACK
NCAT PAVEMENT TEST TRACK 1 REPLACEMENT SECTIONS Red Mill and Inlay New Mix Performance Sections (11) Blue Excavate and Install New Structural Sections (5) 2 RESEARCH SPONSORS (+ FHWA) 3 CHAIN OF COMMAND
More informationDRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL
1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and
More informationCONSTRUCTION SPECIFICATION FOR THE GRINDING OF CENTRELINE AND SHOULDER RUMBLE STRIPS IN ASPHALT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 342 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR THE GRINDING OF CENTRELINE AND SHOULDER RUMBLE STRIPS IN ASPHALT TABLE OF CONTENTS 342.01 SCOPE
More informationEXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM
EXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM Completed forms are due in the NCPA office no later than Tuesday, October 23, 2018 for projects substantially complete in 2018. (Please feel free
More informationDESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents
DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents Introduction This design bulletin provides a number
More informationRegional Engineers. Maureen M. Addis. Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling
Regional Engineers Maureen M. Addis Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling September 29, 2017 This special provision was developed by the
More informationSection 200 Design Process and Quality Management. Electrical Engineering Centre
Section 200 Design Process and Quality Management Electrical Engineering Centre April 2013 TABLE OF CONTENTS 200 DESIGN PROCESS AND QUALITY MANAGEMENT 201 INTRODUCTION TO DESIGN PROCESS... 1 201.1 ABOUT
More informationSection 3 Specification 3.50 Asphalt Concrete Pavement -EPS TABLE OF CONTENTS
TABLE OF CONTENTS 3.50 ASPHALT CONCRETE PAVEMENT - END PRODUCT SPECIFICATION... 1 3.50.1 GENERAL... 1 3.50.1.1 Description... 1 3.50.1.2 Definitions... 1 3.50.1.2.1 Acceptance Limits... 1 3.50.1.2.2 Asphalt
More informationPCC Pavement Rideability
Supplemental Technical Specification for PCC Pavement Rideability SCDOT Designation: SC-M-502 (04/16) 1. SCOPE 1.1. The Resident Construction Engineer (RCE) will evaluate Portland cement concrete (PCC)
More informationMATERIAL SPECIFICATION FOR PERFORMANCE GRADED ASPHALT CEMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1101 NOVEMBER 2002 MATERIAL SPECIFICATION FOR PERFORMANCE GRADED ASPHALT CEMENT 1101.01 SCOPE 1101.02 REFERENCES 1101.03 DEFINITIONS TABLE OF CONTENTS
More informationKDOT Road to Pavement Preservation Maintenance Conference Kansas City, Missouri November 1, 2005
KDOT Road to Pavement Preservation 2005 Maintenance Conference Kansas City, Missouri November 1, 2005 System 9,565 Centerline miles 25,872 Lane miles 4,932 Bridges 2,688,418 Population National Survey
More informationGUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES
GUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES EDITION 2 JULY, 2006 Page left blank intentionally EDITION 2 JULY, 2006 FOREWORD Alberta Infrastructure & Transportation's Pavement
More informationCONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 320 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER TABLE OF CONTENTS 320.01 SCOPE 320.02 REFERENCES 320.03 DEFINITIONS 320.04
More informationSection 3 Specification 3.30 Asphalt Pavement Crack Routing and Sealing TABLE OF CONTENTS
TABLE OF CONTENTS 3.30 ASPHALT PAVEMENT CRACK ROUTING AND SEALING... 1 3.30.1 GENERAL... 1 3.30.2 MATERIALS... 1 3.30.2.1 Crack Sealant... 1 3.30.2.2 Blotting Agents... 2 3.30.3 EQUIPMENT... 2 3.30.4 CRACK
More informationPERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT
PERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT PERMIT # DATE: Name Of Applicant Address City, State, Zip ( ) Fax: ( ) Email Telephone Number permit faxed (date) permit emailed (date) Permission is
More information603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS
SECTION 603 ASPHALT PAVEMENT SMOOTHNESS 603.1 DESCRIPTION Determine the smoothness of the pavement surface and correct the deficiencies as specified in the Contract Documents. For the purposes of this
More informationSPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER)
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER) C&T:JWB 1 of 10 C&T APPR:KPK:CJB:08-02-06 FHWA:APPR:08-21-06 a.
More informationAMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS
AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS INTRODUCTION With alternate bidding, road and highway agencies offer the opportunity to
More informationGeorgia DOT Micro-milling and Thin Overlay
Georgia DOT Micro-milling and Thin Overlay Presented by Yichang (James) Tsai, Ph.D., P.E., Professor Georgia Institute of Technology Erany Robinson-Perry, P.E., Assistant State Maintenance Engineer Georgia
More informationCONSTRUCTION SPECIFICATION FOR TACK COATING AND JOINT PAINTING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 308 APRIL 2012 CONSTRUCTION SPECIFICATION FOR TACK COATING AND JOINT PAINTING TABLE OF CONTENTS 308.01 SCOPE 308.02 REFERENCES 308.03 DEFINITIONS
More informationNYSDOT TRANSPORTATION MAINTENANCE DIVISION PAVING PROJECT QUALITY ASSURANCE ASSESSMENT Rating Guidelines (Revision #1)
NYSDOT TRANSPORTATION MAINTENANCE DIVISION PAVING PROJECT QUALITY ASSURANCE ASSESSMENT Rating Guidelines (Revision #1) INTRODUCTION The condition assessment is intended to be performed from a customer
More informationTrenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association
Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association Representatives of VDOT (consultant or inspector) must be familiar with the VDOT Road and Bridge Specifications as well as Special
More informationPavement Data Quality Management Plan. As required by 23 CFR (c)
Pavement Data Quality Management Plan As required by 23 CFR 490.319(c) 05/10/2018 Table of Contents Pavement Data Quality Management Plan... 1 Data Collection Equipment... 1 Equipment Calibration... 3
More informationATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE
1) PAVEMENT 1.1 Ride quality All roadways have a smooth surface course (including bridge deck approaches, covers, gratings, frames and boxes). 24 hours 28 days 6 months a. Measurement of International
More informationAC 15/ H UPDATE
FAA Airport Construction Guide Specifications AC 15/5370-10H UPDATE Gary L. Mitchell, P.E. Vice President Airports Acknowledgement Doug Johnson Greg Cline Why Update Scheduled 3 5 years Update References
More information25 th ANNUAL BEST IN COLORADO
25 th ANNUAL BEST IN COLORADO ASPHALT PAVEMENT AWARDS PROGRAM 2018 AWARD CRITERIA The Colorado Asphalt Pavement Association (CAPA) recognizes the highest quality asphalt pavement construction and performance
More information3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS
3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS 3.70.1 GENERAL 3.70.1.1 Description 3.70.1.2 Definitions 3.70.1.2.1 Acceptance Limits 3.70.1.2.2 Bridge Construction
More informationSpecial Provision No. 308F01 May 2010
TACK COAT Item No. Special Provision No. 308F01 May 2010 OPSS.PROV 308, April 2007, Construction Specification for Tack Coating and Joint Painting, is deleted in its entirety and replaced with the following:
More informationWashington State DOT: Pavement and Bridge Performance NPRM Comments for federal docket,
MAP-21 NPRM for National Performance Management Measures; Assessing Pavement Condition for the National Highway Performance Program and Bridge Condition for the National Highway Performance Program The
More information2006 RPUG Changing from PI to IRI. Colorado DOT Experience Eric Prieve
2006 RPUG Changing from PI to IRI Colorado DOT Experience Eric Prieve Current Specification Since 1999 CDOT has used the profilograph for pavement smoothness quality Incentives based on the average PI
More information< ~ -n~rtz, Concrete Engineer Office of Materials
Minnesota Department of Transportation MEMO Office of Materials Mailstop 645 1400 Gervais Avenue Maplewood, MN 55109 'stribution 57, 612, 618, 650 ~ < ~ -n~rtz, Concrete Engineer Office of Materials Implementation
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER)
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER) CFS:JWB 1 of 9 APPR:KPK:CJB:11-02-15 FHWA:APPR:11-02-15
More informationCONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 333 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING TABLE OF CONTENTS 333.01 SCOPE 333.02 REFERENCES 333.03 DEFINITIONS 333.04
More informationPavement Preservation and Thin Lift Asphalt NCAUPG and Illinois Bituminous Paving Conference February 3, 2015
Pavement Preservation and Thin Lift Asphalt NCAUPG and Illinois Bituminous Paving Conference February 3, 2015 Dr. Michael Heitzman, PE Dr. Mary Robbins Mr. Don Watson, PE Pavement Preservation A program
More informationCONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 334 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX TABLE OF CONTENTS 334.01 SCOPE 334.02 REFERENCES 334.03 DEFINITIONS 334.04
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MATERIALS AND WORKMANSHIP PAVEMENT WARRANTY
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MATERIALS AND WORKMANSHIP PAVEMENT WARRANTY CFS:EMC 1 of 8 APPR:KPK:CJB:06-13-17 FHWA:APPR:06-14-17 a. Description. The materials and workmanship
More informationKENTUCKY TRANSPORTATION CENTER
Research Report KTC-04-22/SPR-209-00-1F KENTUCKY TRANSPORTATION CENTER OPTIMIZATION AND STANDARDIZATION OF PAVEMENT MANAGEMENT PROCESSES UNIVERSITY OF KENTUCKY College of Engineering OUR MISSION We provide
More informationEND RESULT ASPHALT PAVEMENT SPECIFICATION FOR P3 PROJECTS BENEFITS FOR THE OPERATOR AND CONTRACTOR
END RESULT ASPHALT PAVEMENT SPECIFICATION FOR P3 PROJECTS BENEFITS FOR THE OPERATOR AND CONTRACTOR Graham Clark, P.Eng. Project Manager Brun Way Highways Operations Inc. Paper prepared for presentation
More informationCONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 334 NOVEMBER 2007 CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX TABLE OF CONTENTS 334.01 SCOPE 334.02 REFERENCES 334.03 DEFINITIONS 334.04 DESIGN
More informationMake copies of all test results and control charts readily available to the Engineer at the project site.
5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN NOTE: This document is generally written in the imperative mood. The subject, "the Contractor" is implied. Also implied in this language are "shall",
More informationAPPENDIX A1 State Test Case #1, Florida: FDOT SECTION 334A Airport Pavement for <60,000# AGW
Appendix A1 of Final Report for AAPTP Project 06-05 State Test Case #1, Florida Airports (not authorized for use) APPENDIX A1 State Test Case #1, Florida: FDOT SECTION 334A Airport Pavement for
More informationLife Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS
Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS I. INTRODUCTION...1 II. III. Purpose...1 What Is LCCA?...1 History of
More informationALBERTA TRANSPORTATION. Subject Area Bituminous Material and Mixes. Project No. Report No. Report Date. August 2002 Type of Report ABTR/RD/TM-02/01
Report No. ABTR/RD/TM-02/01 Subject Area Bituminous Material and Mixes Project No. 8454-000001 Title Validation and Revision of Asphalt Concrete Mix Type Selection and Characteristics Study Author(s) Alberta
More information53.5 ASPHALT PAVEMENT CRACK ROUTING AND SEALING
53.5 ASPHALT PAVEMENT CRACK ROUTING AND SEALING 53.5.1 GENERAL The Work consists of routing, cleaning and drying cracks in pavement surfaces and sealing them with the crack sealant. 53.5.2 MATERIALS The
More informationFIELD REPORT: TEXAS EQUIPMENT LOAN EL Implementation Assistance Program. Tools to Improve PCC Pavement Smoothness During Construction (R06E)
EL04-2015 Implementation Assistance Program Tools to Improve PCC Pavement Smoothness During Construction (R06E) Seeking widespread adoption of the realtime smoothness (RTS) technology by contractors and
More informationMATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 NOVEMBER 2015 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES 1821.03 DEFINITIONS
More information39 HOT MIX ASPHALT, SUPERPAVE
39-1.01 GENERAL 39-1.01A Summary Replace section 39 with: 39 HOT MIX ASPHALT, SUPERPAVE Section 39 includes specifications for producing and placing HMA by mixing aggregate and asphalt binder at a mixing
More informationMATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 APRIL 2004 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES
More informationTHE EFFECT OF INITIAL PAVEMENT SMOOTHNESS ON LONG- TERM ROUGHNESS PROGRESSION: SOME FINDINGS FROM C-LTPP AND US-LTPP STUDIES
THE EFFECT OF INITIAL PAVEMENT SMOOTHNESS ON LONG- TERM ROUGHNESS PROGRESSION: SOME FINDINGS FROM C-LTPP AND US-LTPP STUDIES This brief provides findings on the observed effect of initial pavement smoothness
More informationMinnesota Concrete Flatwork Specifications for Local Government Agencies
Minnesota Concrete Flatwork LTAP Concrete Flatwork Specifications Mn Concrete Flatwork Specifications for Local MN Concrete Flatwork Agencies Approved for use on Local Government Agency Projects and State
More informationSECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers.
SECTION 31 62 16 STEEL H PILES PART 1 - GENERAL 1.01 SCOPE OF WORK A. Section includes steel H piles embedded into drilled concrete piers. B. Furnish all labor, materials, equipment and incidentals required
More informationTEMPORARILY SUSPENDED
DESIGN BULLETIN #83/2014 0. (REVISED May 26, 2014) Project Identification Sign for Capital and Rehabilitation Construction Projects May 26, 2014 Amendment to Design Bulletin #83/2014 This amendment is
More informationProcedures. Model Procedure for Sampling Inspection of Isolated Lots. Procedure based on S-S-04
Procedures Category: STATISTICAL METHODS Procedure: P-S-04-A (rev. 1) Page: i of ii Model Procedure for Sampling Inspection of Isolated Lots Procedure based on S-S-04 Category: STATISTICAL METHODS Procedure:
More information**************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-32 01 16.71 (February 2017) ------------------------------ Preparing Activity: USACE Superseding UFGS-32 01 16.17 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More information**************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-32 01 16.71 (February 2017) ------------------------------ Preparing Activity: USACE Superseding UFGS-32 01 16.17 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationSMOOTHNESS OF PAVEMENTS IN CONNECTICUT Phase 2-Report DATA ANALYSES and TRENDS. June, Prepared by Dr. Charles E. Dougan
SMOOTHNESS OF PAVEMENTS IN CONNECTICUT Phase 2-Report DATA ANALYSES and TRENDS June, 2001 Prepared by Dr. Charles E. Dougan Report Number 2226-F-2001-1 This project was sponsored by the Connecticut Department
More informationREQUEST FOR PROPOSAL Department of Public Works Highway Division
REQUEST FOR PROPOSAL Department of Public Works Highway Division Town Office Location: 2417 Franklin Street Telephone: (802) 247-3635 Ext. 211 Pre-Bid Meeting: Monday, April 6 th Bid Opening: Monday, April
More information