Technical Memorandum. Trenchless Technology Options for Rehabilitation of the Yambury Road Drainage Culvert
|
|
- Letitia Collins
- 5 years ago
- Views:
Transcription
1 Technical Memorandum Trenchless Technology Options for Rehabilitation of the Yambury Road Drainage Culvert Prepared for: Bob Weir P.Eng. Town of Qualicum Beach Engineering Department Primrose Street. Qualicum Beach, B.C V9K 1S7 Prepared by: M.J. Pawlowski & Associates Infrastructure Management Consultants Suite 739, No. 2 Rd, Richmond, BC, V7C 5J8 Phone: July 4, 2013
2 CONTENTS 1.0 INTRODUCTION CONDITION ASSESSMENT OF THE YAMBURY RD. CULVERT PHYSICAL INSPECTION AND ULTRASOUND MEASUREMENTS CCTV INSPECTION TRENCHLESS REHABILITATION TECHNOLOGIES BENEFITS OF TRENCHLESS TECHNOLOGIES EVALUATION OF TRENCHLESS REHABILITATION METHODS SEGMENTAL SLIPLINERS CONTINUOUS SLIPLINING CURED-IN-PLACE-PIPE SPIRAL WOUND PIPELINE REHABILITATION JOINT REHABILITATION (WRAPPING) ABRASION RESISTANCE OF LINING MATERIALS FLOW CAPACITY REHABILITATION COSTS (APEGBC CLASS C ESTIMATE) CONCLUSIONS M.J. Pawlowski & Associates Page 2 of 18 Town of Qualicum Beach
3 1.0 Introduction The Yambury Road drainage culvert is a 1371mm (54 ) diameter corrugated metal pipe (CMP) located on the west side of Yambury Road allowance and crosses Butterball Drive and terminates at a small slough entering the Georgia Straight. The culvert consists of 2.8mm (12 gauge) thick galvanized corrugated steel and is approximately 43m long (see sketched attached). Record drawings indicate that the culvert was installed in 1979 and laid to a grade of approximately 31%. In 2012 one of the mechanical couplings over the joint located at the lower mitered bend (near beach access) appears to have failed which in turn allowed water to travel outside the culvert and to erode the bedding material. The process caused significant undermining of the embankment. M.J. Pawlowski and Associates (MJP) were retained by the Town of Qualicum Beach to access the current condition of the metal culvert and to recommend options for rehabilitation using trenchless technology methods. 2.0 Condition Assessment of the Yambury Rd. Culvert 2.1 Physical Inspection and Ultrasound Measurements Inspections were conducted in three phases. MJP & Associates conducted a preliminary site visit on July 18, 2012 to evaluate (1) accessibility for additional inspection work and (2) the potential working footprint for rehabilitation equipment. In addition we performed a limited inspection through the open manhole at the top end and a cursory inspection from the outfall end to view damaged sections of culvert at previous repair sites. Pipe Eye Video Inspection Services of Nanaimo conducted a CCTV inspection of the culvert on October 1 st, Details of the CCTV inspection are listed below. On October 11 th, 2012 MJP & Associates performed a limited number of measurements of the culvert invert using an ultra sound instrument to establish the current culvert wall thickness. Thickness measurements were taken at the transition from concrete to steel and the first metre from the access manhole. Additional measurements were taken on the culvert surface (outfall end) at the beginning of the change in grade (past the mitred bend). The instrument used was a Panametrics 37DL Plus ultrasonic thickness gauge. The steel surface was cleaned with a wire brush prior to taking measurements. M.J. Pawlowski & Associates Page 3 of 18 Town of Qualicum Beach
4 The thickness of 12 gauge steel has the following dimensions: Material Dimensions (mm) Dimensions (inches) Metal Gauge Galvanized steel Standard steel Tests on an area of unblemished steel at around 09 o clock of the culvert equaled 2.69mm which demonstrates a good correlation with the published thickness for 12 gauge galvanized steel. At some locations it proved difficult to obtain readings. This is attributed to slime and/or corrosion deposits remaining on the surface even after treatment with a wire brush. Upstream end 07 o clock 06 o clock 05 o clock Series mm 2.64mm 3.08mm Series mm 2.21mm 2.71mm Series 3 No reading 2.93mm No reading Downstream end 07 o clock 06 o clock 05 o clock Series 1 No reading 2.27mm 2.87mm Series 2 No reading 2.52mm No reading Series 3 No reading No reading 2.90mm In general, the thickness measurements indicate slight deterioration of the metal culvert surface at the 06 o clock position with a maximum of 20% reduction based on theoretical published thickness values for galvanized steel pipe. 2.2 CCTV Inspection Distance (m) Joint No. Comments 0.0 Manhole some signs of slight surface corrosion Slight bending (lifting) of joint at from 05 o clock to 06 o clock. External coupling visible from 10 o clock to 03 o clock. 8.6 Some light surface corrosion observed 13.0 Slight surface corrosion at invert No observed problems Joint appears to be open at invert from 05 o clock to 07 o clock. Debris and roots trapped at the joint gap. Possible location of perforation at invert 21.9 Junction of 600mm diameter storm main at 09 o clock Open joint impeding flow at invert. Some debris / corrosion at invert 29.9 Slight corrosion at invert possible perforations 33.1 Possible perforation at 06 o clock Separation of joint from 05 o clock to 07 o clock. Debris trapped in joint (rocks) 36.3 Corrosion at invert 40 6 Joint tight good Open joint 05 o clock to 07 o clock at miter bend transition? Survey Abandoned at transition to mitred bend at damaged section of culvert M.J. Pawlowski & Associates Page 4 of 18 Town of Qualicum Beach
5 The lower section of the drainage culvert was not CCTV inspected from the outfall end. However, physical inspection and observations note the damage section of CMP at the downstream mitered bend and joint. This is the location of the original damage and embankment erosion. View from outfall end, first mitre joint Joint No. 3 at 20m from upstream manhole M.J. Pawlowski & Associates Page 5 of 18 Town of Qualicum Beach
6 Joint No. 4 at 27.5m from upstream manhole; note lifting of water at joint Joint No. 5 at 34m downstream of manhole; arrows indicate separated joint M.J. Pawlowski & Associates Page 6 of 18 Town of Qualicum Beach
7 Joint No. 7 at 41.5m (zoomed image) downstream of manhole; arrow indicates major separation 3.0 Trenchless Rehabilitation Technologies 3.1 Benefits of trenchless technologies The use of trenchless technologies is recognized by many communities as a method of reducing social disruption and minimizing the impact of construction activities on adjacent underground utilities, pavement surfaces, and environmentally sensitive areas. Some technologies provide the ability to overcome complex and challenging construction issues such as depth and high water table. Studies by the University of Waterloo 1 also imply a considerable reduction in carbon emissions when comparing traditional cut and cover utility construction projects with trenchless technology rehabilitation methods. A significant quantity of carbon emissions are generated during open cut activities such as emissions from backhoes, idling dump trucks, and emissions incurred on route to dump sites and when transporting imported backfill materials. 1 Do Trenchless Pipeline Construction Methods Reduce Greenhouse Gas Emissions?, Knight M. et al, Centre for Advancement of Trenchless Technology, University of Waterloo, 2007 M.J. Pawlowski & Associates Page 7 of 18 Town of Qualicum Beach
8 4.0 Evaluation of Trenchless Rehabilitation Methods We have conducted an evaluation of the following five (5) trenchless technology methods deemed suitable for the rehabilitation of the culverts. Segmental Sliplining Continuous Sliplining Cured-in-Place-Pipe Spiral Wound Linings Joint Rehabilitation (Wrapping) 4.1 Segmental Slipliners Sliplining technology entails inserting a new pipe of smaller diameter into the host pipe and filling the resulting annulus space with grout. There are a number of PVC and High Density Polyethylene (HDPE) segmental lining products available to slipline the Yambury Road culvert including short length segmental liners. Of note are the following products: A2 PVC liner by Contech (PVC) Lampson Vylon (PVC) Snap-Tite (HDPE) Weholite (HDPE) Installation of HDPE segmental liners Image courtesy of Snap-Tite M.J. Pawlowski & Associates Page 8 of 18 Town of Qualicum Beach
9 Installation of HDPE segmental liners Easy handling of segmental liners HDPE: Ability to fabricate mitred bends and joints M.J. Pawlowski & Associates Page 9 of 18 Town of Qualicum Beach
10 A crucial component of the sliplining process is filling the annulus void with grout which will provide additional strength to the finished product, and prevent further deterioration of the host pipe and erosion of the surrounding bedding material and soil. Thus, the superimposed loads are transferred through the grout eliminating any point loading. The design of the grout mix must include considerations for density requirements and the ability to flow freely. Thus, to achieve optimum requirements, an additive is used to incorporate air into the mix. The grouting process requires careful monitoring of pressures to ensure the ring compression values of the slipliner are not exceeded which could result in a collapsed liner. The Yambury culvert is constructed at a 30 degree angle and therefore the introduction of the annulus grout must be completed using a process termed stage grouting, where grout is introduced in a controlled manner ( lifts ). Segmental Sliplining Limitations PVC products are difficult to use at mitred bends and changes in direction. Need for annulus space grouting (added expense). Need to provide blocking to prevent flotation of product during annulus grouting. Attributes HDPE has custom fittings available from manufacturer or may be constructed in the field. HDPE offers a variety of products up to 1524mm (60 in.) in diameter. Segmental slipliners allow for more compact construction footprints. Low profile joints available for both PVC and HDPE. The need for bypass pumping can be reduced or eliminated. Good abrasion resistance. 4.2 Continuous Sliplining Continuous sliplining is a similar process to segmental sliplining in that a smaller diameter pipe is inserted into the host pipe and the annulus space is filled with grout. The continuous sliplining method typically utilizes butt-fused joints, polyethylene pipe sections forming one long, continuous length. Continuous Sliplining Limitations Time consuming to fuse joints together (up to 1 hr per joint). Requires unobstructed layout area for fusing and installation. Access pits need to be designed to accommodate allowable bending radius of HDPE pipe. Need for annulus space grouting (added expense). Need to provide blocking to prevent flotation of product during annulus grouting. Attributes HDPE s joint fusion process guarantees joint integrity (high strength, no leaks). The need for bypass pumping can be reduced or eliminated. Good abrasion resistance. M.J. Pawlowski & Associates Page 10 of 18 Town of Qualicum Beach
11 4.3 Cured-In-Place-Pipe The Cured-In-Place-Pipe (CIPP) method was developed by Insituform Technologies, UK in the early 1970 s. The technology utilizes a felt tube impregnated with resin and catalyst which is inserted into the host pipe by means of an inversion process. The resin is then catalyzed by the introduction of heat. The procedure for the installation process and design guidelines was formally adopted in North America as ASTM F1216 in the early 1990 s. Over the past decade, since the expiration of the Insituform original patent for this process, the trenchless rehabilitation industry has developed a number of variations of this procedure using a variety of materials, resins and curing procedures. These include both inversion processes and pull-in-place methods. This type of technology is commonly used in Canada for the rehabilitation of deteriorated sanitary sewer mains. Recent developments in the industry have introduced composite" liners consisting of traditional needle felt liner material in combination with fiber glass or carbon fiber reinforcement. These types of liners become economically feasible for pipe diameters greater than 900mm in diameter. The technology permits for thinner wall liners with superior physical properties. One of the major concerns of using CIPP liners for drainage culvert rehabilitation is the potential for environmental contamination of the surface water downstream of the culvert. The majority of resins used in the CIPP lining process are comprised of approximately 40% by volume of styrene monomer. Styrene is classified as toxic or highly toxic to aquatic life. Styrene has the potential to be released during the installation and curing process and is reported by several studies to continue to leach from the surface of the liner for several weeks after installation at levels that exceed the Canadian Council of Ministers of Environment (CCME) guidelines for the protection of aquatic life. The CIPP resin industry has responded to the environmental concerns and has developed resins that are styrene free. Cured-In-Place-Pipe Limitations Environmental contamination of the surface water downstream of the culvert. Styrene free resins are approximately 3 times more expensive than standard polyester resins. Requires bypass pumping and a dry host pipe. Level of quality control greater than other products. Long cure time (up to 36 hrs) to ensure proper cross-linking of polymer. Poorer abrasion resistance than PVC or HDPE. Attributes Relatively small footprint compared with other lining procedures. No requirement for annulus space grouting. Smaller cross-sectional area loss, low Mannings co-efficient resulting in increased flow capacity. M.J. Pawlowski & Associates Page 11 of 18 Town of Qualicum Beach
12 4.4 Spiral Wound Pipeline Rehabilitation There are several technologies available in North America using this method. Essentially, the PVC or HDPE spiral wound liners are custom fitted with automatic winding machines producing a formwork behind which cement grout is pumped to produce an interactive design with the host pipe. Photo courtesy of RibLoc Photo 2 This method can be used in a variety of geometric configurations including egg-shape, arch and rectangular drainage culverts and sewers. This technology offers the advantage of a minimal reduction in pipe diameter resulting in equal or greater flow capacity than the existing host pipe due to the lower Manning s roughness coefficient of HDPE and PVC material. There are also few environmental concerns compared to Cured-in-Place- Pipe lining systems. 2 Overview of spiral wound pipe lining technologies, Paper 2B-4, International No-Dig Conference 2011, Berlin M.J. Pawlowski & Associates Page 12 of 18 Town of Qualicum Beach
13 Spiral Wound Pipeline Rehabilitation Limitations Limited number of contractors available (all currently US based). Need for annulus space grouting (added expense). Pit access requirements for winding equipment and product installation. Attributes Need for bypass pumping minimized or eliminated. Able to line around bends and variations in pipe geometry. Both PVC and HDPE products have good abrasion resistance. Minimal loss in pipe diameter. 4.5 Joint Rehabilitation (Wrapping) Image courtesy of RibLoc From the CCTV inspection, we note signs of failure at some joints. Joint wrapping would address defects within ~250 mm of each side of each joint (total of 0.5m wide). This procedure addresses localized defects at joints and will not correct any corrosion or invert deterioration at other locations along the length of the culvert. Joint wrapping is an alternative to the technologies described in the preceding sections. The area to be treated is cleaned using sand blasting. A primer coat is then applied and voids are filled with a resin-based putty. Typically, a fibreglass chopped strand matting consisting of three layers will be applied to the joint and anchored with stainless steel screws drilled through the mat and into the culvert. A fourth layer of fibreglass roving is applied over the top of the anchored mat. A wax coat is applied to seal the fibreglass layers. Finally, an epoxy sealer will be used to seal the edges of the fibreglass on the edges of the joint. MJP & Associates solicited quotes from two local suppliers: Chemstar Industries Ltd. (based in Parksville) and Fibrwrap (based in Coquitlam). Chemstar provided pricing (see Rehabilitation Costs section.) Fibrwrap did not reply. M.J. Pawlowski & Associates Page 13 of 18 Town of Qualicum Beach
14 5.0 Abrasion Resistance of Lining Materials The majority of PVC and HDPE lining manufactures reference abrasion resistance tests original developed at the University of Darmstadt, Germany in the 1970 s. These tests are still commonly performed in Europe today on a variety of materials to demonstrate the degree of abrasion resistance and material loss over extended periods of time. Typical Abrasion Resistance Test Values (Darmstadt method) (diagram courtesy of KWH Pipe, The Basics of Weholite Lightweight Pipe System ) The graph above developed under the Darmstadt test procedure indicates that both High Density Polyethylene (HDPE) and PVC pipe material demonstrate high abrasion resistance compared to other materials such as vitrified clay pipe, concrete, fiber glass reinforced pipe (CIPP) and asbestos cement pipe. M.J. Pawlowski & Associates Page 14 of 18 Town of Qualicum Beach
15 6.0 Flow Capacity We have conducted an analysis based on the Manning s equation for open channel flow substituting a variety of coefficients of friction for a variety of trenchless rehabilitation options. The calculations are all based on full-flow (100%) conditions for comparative purposes. Summary of Flow Capacity Location Pipe (mm) Pipe (in.) Flow ft 3 /s Flow m 3 /s Manning coefficient Pipe type % capacity Q Yambury Rd Design Q 31.0% grade Original installation 100% Mature CMP 92% HDPE Snap Tite 102% HDPE Snap Tite 147% CIPP 165% The calculations are sensitive to the Manning s coefficient selected for the various pipe materials and rehabilitation options. Regardless, our computations demonstrate that relining a pipe even with a smaller diameter, smooth surface product will increase the flow capacity of the existing corrugated metal pipe. M.J. Pawlowski & Associates Page 15 of 18 Town of Qualicum Beach
16 7.0 Rehabilitation Costs (APEGBC Class C estimate) Yambury Rd. Drainage Culvert Rehabilitation (54 inch culvert) Segmental - Continuous Sliplining Unit Qty Rate Costs 1.1 Partial By pass pumping / flow diversion Lump sum 1 $ 5, $ 5, Modify manhole entry (temporary) Lump sum 1 $ 5, $ 5, Repair damaged sections of culvert Lump sum 1 $ 5, $ 5, Install 1200mm liner Metres 50 $ 1, $ 80, Annulus space grouting Lump sum 1 $ 22, $ 22, Service connection reinstatement Each 1 $ 1, $ 1, Field construction of HDPE mitred bends Each 2 $ 5, $ 10, Post installation CCTV inspection Metres 50 $ $ 1, Section Total $ 129, Cured-In-Place-Pipe (CIPP) 2.1 Full By pass pumping / flow diversion Lump sum 1 $ 20, $ 20, Modify manhole entry (temporary) Lump sum 1 $ 5, $ 5, Repair damaged sections of culvert Lump sum 1 $ 5, $ 5, Install 1351mm CIPP liner Metres 50 $ 2, $ 125, Service connection reinstatement Each 1 $ 1, $ 1, Construct bulkhead at outlet end Each 1 $ 3, $ 3, Post installation CCTV inspection Each 50 $ $ 1, Section Total $ 160, Spiral Wound Lining (SWL) 3.1 Partial By pass pumping / flow diversion Lump sum 1 $ 5, $ 5, Modify manhole entry (temporary) Lump sum 1 $ 5, $ 5, Repair damaged sections of culvert Lump sum 1 $ 5, $ 5, Install 1350mm HDPE SWL liner Metres 50 $ 2, $ 110, Annulus space grouting Lump sum 1 $ 22, $ 22, Service connection reinstatement Each 1 $ 1, $ 1, Post installation CCTV inspection Metres 50 $ $ 1, Section Total $ 149, M.J. Pawlowski & Associates Page 16 of 18 Town of Qualicum Beach
17 Yambury Rd. Drainage Culvert Rehabilitation (54 inch culvert) Joint Rehabilitation / Wrapping Unit Qty Rate Costs 4.1 Full By pass pumping / flow diversion Lump sum 1 $ 20, $ 20, Modify manhole entry (temporary) Lump sum 1 $ 5, $ 5, Repair damaged sections of culvert Lump sum 1 $ 5, $ 5, Install 1350mm diam. fibre-wrap joints Each 8 $ 14, $ 115, Construct bulkhead at outlet end Each 1 $ 3, $ 3, Post installation CCTV inspection Metres 50 $ $ 1, Section Total $ 150, Class C estimate (±25-40%): An estimate prepared with limited site information and based on probable conditions affecting the project. It represents the summation of all identifiable project elemental costs and is used for program planning, to establish a more specific definition of client needs and to obtain preliminary project approval Conclusions Our field inspections of the Yambury Rd. Culvert together with the analysis of the CCTV inspection survey conclude that the invert of the 54 in. corrugated metal pipe is at a moderate stage of deterioration as observed by the surface corrosion. However, of the eight joints in the corrugated metal pipe, seven exhibited signs of joint separation varying from slight misalignment and bent edges to wide gaps large enough to trap debris and allow root incursion. The original point of failure/washout is believed to have been caused by large joint separation as indicated in the photographic records. Current joint condition is not as advanced; nonetheless, it would be prudent to plan for rehabilitation to avoid a similar mode of failure. We recommend that the Town of Qualicum Beach consider full-length lining over joint wrapping as this will address long term corrosion issues that will inevitably affect the functionality of the invert of the pipe. We have provided preliminary estimates of each trenchless technology that is feasible for this culvert. Current pricing can vary depending on the economic climate, availability of contractors, and costs of mobilization of equipment and crews to Vancouver Island. We recommend that the Town solicit bids on all three full-length lining options and allow the market to offer the best value. 3 APEGBC M.J. Pawlowski & Associates Page 17 of 18 Town of Qualicum Beach
18 This Technical Memorandum entitled Trenchless Technology Options for Rehabilitation of the Yambury Road Drainage Culvert is respectfully submitted by, M.J. Pawlowski & Associates Marek Pawlowski, A.Sc.T. The use of this Report is subject to following Statement of General Conditions. The reader s attention is specifically drawn to these conditions as it is considered essential that they be followed for the proper use and interpretation of this report. Statement of General Conditions: This report was prepared by M.J. Pawlowski and Associates for the Town of Qualicum Beach. The material contained herein, and the recommendations and conclusions reached, reflect M.J. Pawlowski and Associates opinions based upon the information provided to us by the Town of Qualicum Beach and their consultants at the time of report preparation. Any use which a third party makes of this report, or any reliance on or decisions based upon it, are the responsibility of such third parties. M.J. Pawlowski and Associates accepts no responsibility for damages of any kind suffered by any third party as a result of decisions made or actions based on this report. M.J. Pawlowski & Associates Page 18 of 18 Town of Qualicum Beach
19
Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore
Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline
More informationPIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following:
PIPE REHABILITATION PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sliplining Pipe B. Cured-in-place Pipe Lining C. Deformed/Reformed Pipe Lining D. Folded/Formed Pipe Lining E. Spot Repairs by Pipe Replacement
More informationLATEST DEVELOPMENTS INCREASE THE CAPABILITIES OF SPIRAL WOUND LINERS
LATEST DEVELOPMENTS INCREASE THE CAPABILITIES OF SPIRAL WOUND LINERS John Monro, Interflow Pty Limited ABSTRACT For many years spiral wound liners have been the most used type of liner for the rehabilitation
More informationITEM NO SLIPLINING SANITARY SEWERS
ITEM NO. 1100 SLIPLINING SANITARY SEWERS 1100.1 DESCRIPTION: Sliplining is accomplished by pulling or pushing liner pipe into existing sewers by use of mechanical or hydraulic equipment. Once in place,
More informationWeholite LIGHTWEIGHT PIPE SYSTEM
Weholite LIGHTWEIGHT PIPE SYSTEM The lightweight pipe that takes a heavier load Weholite pipe is large diameter, profile wall pipe made from highdensity polyethylene (HDPE) resin, which is manufactured
More informationSPECIAL SPECIFICATION 4411 Cured-In-Place Pipe (CIPP) (Drainage Structures)
2004 Specifications CSJ 6165-86-001 SPECIAL SPECIFICATION 4411 Cured-In-Place Pipe (CIPP) (Drainage Structures) 1. Description. Reconstruct existing cross drainage structures by forming a new pipe within
More informationSpecifying Trenchless Sewer Rehabilitation Projects. Presented by: Todd Stelmacher Visu-Sewer, Inc.
Specifying Trenchless Sewer Rehabilitation Projects Presented by: Todd Stelmacher Visu-Sewer, Inc. Todd Stelmacher Bio Visu-Sewer Sales Engineer MN, ND, SD, WI 30+ years public utilities experience Municipal
More informationSEwEr rehabilitation Spr technologies
SEwer rehabilitation spr technologies SEKISUI SPR s rehabilitation technologies FOR SEWER REHABILITATION SEKISUI SPR is synonymous with the development and implementation of trenchless pipe rehabilitation
More informationCONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS
More informationNo-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.
No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for
More informationSpecial Specification SS1- INTERNAL CIPP POINT REPAIR OF PIPELINES. A. General. 1. Scope
Special Specification SS1- INTERNAL CIPP POINT REPAIR OF PIPELINES A. General 1. Scope The work covered in this item includes the labor, equipment, materials for performing all work necessary to rehabilitate
More informationSECTION IRRIGATION PIPELINE LINING (CURED-IN-PLACE PIPE)
SECTION 02518 IRRIGATION PIPELINE LINING (CURED-IN-PLACE PIPE) PART 1 GENERAL 1.01 SECTION INCLUDES A. Irrigation pipeline lining, as herein specified, consists of installing pipe liner by trenchless methods
More informationBuilding the City of West Palm Beach s Stormwater Infrastructure Rehab Program June 15, 2018
Building the City of West Palm Beach s Stormwater Infrastructure Rehab Program June 15, 2018 2018 HDR, Inc., all rights reserved. Data Evaluation and Literature Review Presentation Outline Condition Assessment
More informationINLINER LAY_InLiner Brochure_FA_ indd 1
INLINER LAY_InLiner Brochure_FA_010913.indd 1 Layne Inliner, LLC is the second largest cured-in-place pipe (CIPP) lining company in the United States. We began as the first U.S. licensee of the Inliner
More informationLateral Thinking The Key To Meeting Sewer Infiltration Reduction Targets & Lowering Operating Costs
Lateral Thinking The Key To Meeting Sewer Infiltration Reduction Targets & Lowering Operating Costs John Monro Interflow Pty Limited Keywords: house service line, lateral, infiltration reduction, rehabilitation,
More informationTable 1 Description of Work Pipe Size (mm) 1 Sunshine Way A/C No. A/C Yes
March 2, 2018 To: Cured-In-Place Pipe (CIPP) Relining Contractors RE: CITY OF GRAND FORKS REQUEST FOR QUOTE FOR CIPP RELINING CONTRACTORS 1.0 INTRODUCTION The City of Grand Forks is requesting quotes to
More informationMokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation
Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Presented by Mike York, Insituform Technologies, Inc. Trenchless v. Dig and Replace What is CIPP? Developed
More informationSliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control
More informationTRANSPORTATION RESEARCH BOARD. The Renewal of Stormwater Systems Using Trenchless Technologies. Wednesday, March 6, :00-3:30 PM ET
TRANSPORTATION RESEARCH BOARD The Renewal of Stormwater Systems Using Trenchless Technologies Wednesday, March 6, 2019 2:00-3:30 PM ET The Transportation Research Board has met the standards and requirements
More informationSPECIFICATIONS FOR PREMIER-PIPE USA CURED-IN-PLACE TECH LINER
SPECIFICATIONS FOR PREMIER-PIPE USA CURED-IN-PLACE TECH LINER 1. General Statement: This specification is for the Cured in Place Pipe process (CIPP) of pipe rehabilitation using a glass fiber reinforced
More informationInfrastructure Solutions Pressure Pipe Overview
Infrastructure Solutions 2017 Pressure Pipe Overview Pipe problems Costly repairs & lost revenue Water quality Water main breaks Water loss Leaking pipes Flow capacity Aging pipelines 2 Infrastructure
More informationCIPP REFERENCE SPECIFICATION
CIPP REFERENCE SPECIFICATION This CIPP Reference Specification serves as only a guideline and is not intended to encompass the requirements of every municipality or industrial application. However, the
More informationInland Pipe Rehabilitation. August 17 OAWWA Canton, OH
Inland Pipe Rehabilitation August 17 OAWWA Canton, OH Presentation Agenda Introduction to IPR IPR Products & Services RS Technik by HammerHead Advanced CIPP Process Spartanburg, SC project review IPR Overview
More informationLessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE
Lessons Learned from a 60 CIPP Storm Sewer Liner Installation Robert Stolt, PE Christopher Beranek, PE Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified 4. Warranty
More informationSUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018
STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 PART 1 - GENERAL... 2 1.1 Work Included... 2 1.2 Related Sections... 2 1.3 Reference Standards... 2 1.4 Shop Drawings... 3 1.5 Certificates...
More informationSPECIAL SPECIFICATION 4631 Cured-In-Place Pipe (CIPP)
2004 Specifications CSJ 0912-34-171 SPECIAL SPECIFICATION 4631 Cured-In-Place Pipe (CIPP) 1. Description. Reconstruct existing drainage structures by forming a new pipe within an existing deteriorated
More informationENGINEERED SOLUTIONS INNERFLOW INSTALLATION GUIDE
ENGINEERED SOLUTIONS INNERFLOW INSTALLATION GUIDE PREFACE InnerFlow is a solid wall HDPE (High Density Polyethylene) pipe typically utilized for culvert/sewer rehabilitation and direct bury applications.
More informationChemical Grouting to Maintain and Sustain Municipal Sewers By: Marc A Anctil Logiball Inc.
Chemical Grouting to Maintain and Sustain Municipal Sewers By: Marc A Anctil Logiball Inc. TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON There could
More informationRENOVATION OF LARGE DIAMETER PIPES & CHAMBERS
RENOVATION OF LARGE DIAMETER PIPES & CHAMBERS OVERVIEW Techniques for renovating large diameter pipes and chambers are probably the oldest forms of trenchless technology. Whereas small diameter pipes could
More informationCondition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains
Condition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains Philip McFarlane, ProjectMax Ltd ABSTRACT This paper discusses techniques for the condition assessment and rehabilitation/replacement
More informationGWINNETT COUNTY STORM SEWER PIPE STANDARDS
1.0 Standard Specifications GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.1 Unless otherwise specifically set forth herein or in the Gwinnett County Standard Drawings, all of the materials, methods of the
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationSpecifications. Chapter 13. Specifications (800) CULVERT 96
Chapter 13 WWW.CULVERT-REHAB.COM (800) CULVERT 96 Material Requirement These specifications cover the purchase of high density polyethylene (HDPE) pipe liners for lining existing culvert pipes. Pipe liners
More informationRowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting
Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project TACWA Meeting September 25, 2009 North Texas Municipal Water District Project Background 1. Rowlett-Cottonwood Transfer
More informationJUST THE FACTS CONCRETE PIPE VS. HDPE
JUST THE FACTS CONCRETE PIPE VS. HDPE Just the FACTS! DRAINAGE PIPE PERFORMANCE AND DESIGN COMPARISON CONCRETE VS. HDPE Contents Current Standards............................2 Corrugation Growth and its
More informationUNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer
More informationStormwater Drainage Restoration and Rehabilitation at Liverpool City Council
John Monro Interflow Pty Limited Stormwater Drainage Restoration and Rehabilitation at Liverpool City Council Abstract Liverpool City Council has underground concrete stormwater drains that have been in
More informationSTIFPIPE : INTRODUCING A NEW HONEYCOMB-FRP PIPE
STIFPIPE : INTRODUCING A NEW HONEYCOMB-FRP PIPE Mo Ehsani, PhD, PE, SE, F.ASCE President, PipeMedic, LLC and Professor Emeritus of Civil Engineering, University of Arizona, 2055 E. 17 th St.,Tucson, AZ
More informationSECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation
SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for
More informationSECTION STORM SEWER COLLECTION SYSTEM
SECTION 02722 STORM SEWER COLLECTION SYSTEM PART 1 GENERAL 1.01 SUMMARY A. This section addresses the installation of storm sewer collection mains and includes the acceptable products, materials, and construction
More information17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.
E M I R A T E S Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation i) Introduction Dubia, UAE 14 March 2017 Trenchless Middle East Faiz Alelweet & Eng. Hamza Ali Maintenance Manager
More informationCS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS
TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger
More information1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.
PAGE 334000-1 SECTION 334000 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More information1 Revised: 2019 Edition
STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with
More informationTrenchless Technology
Trenchless Technology UNIVERSAL NEED FOR REHABILITATION Rising Community Expectations Rising Environmental Expectations Diminishing Financial Resources Aging Infrastructure Rising Risk Management & External
More informationCITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE
CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE 1000.1 DESCRIPTION These specifications shall govern the furnishing of glass-fiber reinforced
More informationTRENCHLESS TECHNOLOGY. Department of Civil Engineering.
TRENCHLESS TECHNOLOGY GUIDED BY Ms. PRAJEESHA.M.P Lecturer. Department of Civil Engineering. PRESENTED BY DEEPAK.C Semester 7,Civil Roll No:58 CONTENTS INTRODUCTION TRENCHLESS CONSTRUCTION METHODS TRENCHLESS
More informationStructural Testing of Geopolymer Pipe & Culvert Mortar Lining System
Structural Testing of Geopolymer Pipe & Culvert Mortar Lining System David Keaffaber, P.E. Midwest Region Manager Joseph Royer, PhD Dan Koo, P.E., PhD Milliken Infrastructure Solutions, LLC Development
More informationSECTION 920 SANITARY AND STORM SEWER MANHOLES
SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C
More informationContact the Jurisdictional Engineer for materials allowed by each jurisdiction.
Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS
ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.
More informationSection Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers
STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES
PART 1 GENERAL 1.01 SUMMARY This Section includes: Section 02081 CAST-IN-PLACE A. Cast-in-place concrete manholes for sanitary sewers and storm sewers, including box sewers. B. Pile-supported concrete
More informationTECHNICAL SPECIFICATION FOR CURED-IN-PLACE MANHOLE REHABILITATION LINER SYSTEM
TECHNICAL SPECIFICATION FOR CURED-IN-PLACE SYSTEM PART 1 GENERAL 1.01 SCOPE OF WORK Furnish all materials, labor, equipment, tools and required incidentals for providing and installing a resin impregnated
More informationSection 401. PIPE CULVERTS
401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials
More informationTECHNICAL SPECIFICATIONS FIBERGLASS/ULTRAVIOLET LIGHT CURED-IN-PLACE PIPE (CIPP) FOR MAINLINE RENEWAL
TECHNICAL SPECIFICATIONS FIBERGLASS/ULTRAVIOLET LIGHT CURED-IN-PLACE PIPE (CIPP) FOR MAINLINE RENEWAL PART 1 - PRODUCTS 1.1 GENERAL It is the intent of this specification to provide for the reconstruction
More informationInstallation Practice InnerSeal
Installation Practice InnerSeal Rehabilitation of a Full-Length Sewer Service Lateral using One-Piece Main and Lateral Cured-In-Place Liner Assembly Installed By Means Of Air Inversion 1. Intent This instruction
More informationHIGH CHEMICAL RESISTANCE LINER (EPOXY RESIN FORMAPOX 301)
HIGH CHEMICAL RESISTANCE LINER (EPOXY RESIN FORMAPOX 301) LINING SPECIFICATIONS FOR UNDERGROUND PROCESS PIPING WITH NO-DIG TECHNOLOGIES FORMADRAIN Inc. 09032015 U.S.A. 2915 Ogletown Road - #132 Newark,
More informationCASE STUDY: Renovation of a Fully-deteriorated Trunk Sewer at a Large U.S. Brewery
CASE STUDY: Renovation of a Fully-deteriorated Trunk Sewer at a Large U.S. Brewery Evanco Environmental Technologies Inc. Kyle Verwey and Randy Cooper TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationGENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM
1. GENERAL 1.01 DESCRIPTION GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM A. The Contractor shall furnish all labor, equipment and materials necessary
More informationAppendix A SURVEY QUESTIONNAIRE
Appendix A SURVEY QUESTIONNAIRE Highway stakeholders recognize the overwhelming need for effective technologies in both the structural and functional stormwater facility renewal while minimizing negative
More informationCIPP Lateral Renewal Connection System
Product Submittal Document Information CIPP Lateral Renewal Connection System ManEntry Lapel Liner Updated 6/12/14 Product Submittal Review ITEM 1. Manufacturer Company Name: LMK Technologies, LLC Contact
More informationSRPE AASHTO Specifications.
SRPE AASHTO Specifications July 19, 2013 Steel Ribbed HDPE = SRHDPE = SRPE Now has AASHTO Design and Construction Specifications for SRPE. 2 But wait there is more AASHTO Bridge Design Specs - Section
More informationAssessing Salem s Oldest Transmission Main for Seismic Resiliency
Assessing Salem s Oldest Transmission Main for Seismic Resiliency ASSESSING AND DEVELOPING OPTIONS TO REDUCE VULNERABILITY OF AGING CRITICAL INFRASTRUCTURE Presented by Troy Bowers, PE Jeff Jones, PE PROBLEM
More informationSECTION 300 STORM SEWER TABLE OF CONTENTS
SECTION 300 STORM SEWER TABLE OF CONTENTS Starts on Page 300 GENERAL... 2 301 MATERIALS... 2 302 CONSTRUCTION PROCEDURES... 5 303 TESTING... 5 304 ABANDONMENT OF EXISTING STORM SEWER FACILITIES... 6 305
More informationCanada s leader of complete geosynthetic solutions. HDPE Pipe Solutions. We offer complete solutions to all your piping needs.
Canada s leader of complete geosynthetic solutions HDPE Pipe Solutions We offer complete solutions to all your piping needs. Subdrains Corrugated HDPE Drainage Tubing terrafix subdrain pipe is used for
More informationA-2000 PVC Pipe for Storm Sewers and Drainage
ENGINEERED SOLUTIONS A-2000 PVC Pipe for Storm Sewers and Drainage A-2000 Drainage Pipe Drainage systems are required to meet multiple criteria. The choice of a particular material depends upon a number
More informationTAMDID PIPES GRP MANHOLE BROCHURE
TAMDID PIPES GRP MANHOLE BROCHURE 1) Types & Description of Manholes: Tamdid Pipes offer two types of Manholes; Structural and Liner Manholes: a. Structural Manholes Tamdid Pipes offers concentric and
More informationSTANDARD SPECIFICATIONS SECTION TEMPORARY BYPASS PUMPING SYSTEMS
STANDARD SPECIFICATIONS SECTION 02960 TEMPORARY BYPASS PUMPING SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for implementing a temporary pumping system for the purpose of diverting
More informationBMEC AUTHORIZATION:
777 Bay Street, 2 nd Floor Toronto, Ontario, M5G 2E5 777, rue Bay, 2 e etage Toronto, Ontario, M5G 2E5 T: F: W: 416 585 4234 416 585 7531 www.ontario.ca/buildingcode/ T: TC: W: 416 585 4234 416 585 7531
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 PRECAST CONCRETE PIPE 10.1.1 General This section covers material requirements,
More informationIndex to Technical Specifications
Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation
More informationFundamentals of Spray-Applied Geopolymer Linings. Extending the life of the world s infrastructure.
Fundamentals of Spray-Applied Geopolymer Linings Extending the life of the world s infrastructure. Fundamentals of Spray-Applied Geopolymer Linings In the 2017 Infrastructure Report Card, the American
More informationSECTION 303 CULVERTS
303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS
Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationFiber Reinforced Cured-in-Place Rehabilitation Under an Interstate
Fiber Reinforced Cured-in-Place Rehabilitation Under an Interstate UCT Conference - February 2017 Presented By Chantal Evans Representing Owner Jonathan Stathis/Cedar City Owner and owner issues Cedar
More informationA-2000 PVC Pipe for Sanitary Sewers
ENGINEERED SOLUTIONS A-2000 PVC Pipe for Sanitary Sewers Engineered for Performance Manufactured by Contech Engineered Solutions, A-2000 represents the leading edge in sanitary sewer pipe technology with
More informationGeopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure
Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure Dwight Silva Business Development Manager IPR, Great Lakes Geopolymers: Structural Rehabilitation Solution
More informationThe Weak Links in the Wastewater Collection System: Manholes and Access Devices. Antonio V Almeida, PE CMOM 2014 Austin Texas August 19, 2014
The Weak Links in the Wastewater Collection System: Manholes and Access Devices Antonio V Almeida, PE CMOM 2014 Austin Texas August 19, 2014 Agenda Manhole Design The Manhole Paradigm past, present & future
More informationITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS
ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing
More informationFold & Form PVC Liners Sewer & Culvert Rehabilitation
Fold & Form PVC Liners Sewer & Culvert Rehabilitation Presented at NASTT Conference Cooperstown, NY November 16, 2017 Scott Mills, P. Eng. Eastern District Manager - Municipal Systems IPEX USA, LLC Agenda
More informationFOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS
FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS Rev: 3/26/18 Pipe and fittings used in sanitary sewer construction shall
More informationDESIGN OF SEWER SYSTEMS
Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials
More informationTRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS
L L S! " # #! " # # $ % & ' (! & ) * + ', - )!!!. &! - * + ', - )!!!. &! - * " # # $ % & ' (! & ) " &! % - / 0 1 2 3 4 3 2 5 6 3 7 8 4 7 9 : 7 5 ; < 7 9 = > / 1 9 3 1 >? @ A A B C 9 1 8 2 D E 1 > > F 8
More informationSANITARY WASTE AND VENT PIPING
SECTION 15420 - SANITARY WASTE AND VENT PIPING PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationULTRA FLO STEEL PIPE PRODUCT GUIDE
DRAINAGE SOLUTIONS SINCE 1908 ULTRA FLO STEEL PIPE PRODUCT GUIDE LARGE-DIAMETER STORM SEWER PIPE DELIVERS SUPERIOR HYDRAULIC PERFORMANCE FAST INSTALLATION DURABLE NESTABLE PIECES VALUE EFFICIENT HYDRAULICS
More informationINDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2
INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...
More informationSKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation
SKSC Civils (pty) LTD Brilliance Technology Quality - Innovation About us SKSC Civils was inspired by numerous individuals in South Africa, ranging from the civil to the construction industry, to truly
More informationSPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer)
2004 Specifications CSJ 0912-71-657 SPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer) 1. Description. Furnish and install cured-in-place pipe. A. Resin-impregnated flexible tubes inserted
More informationJUST THE FACTS CONCRETE PIPE VS. CSP
JUST THE FACTS CONCRETE PIPE VS. CSP Just the FACTS! BURIED PIPELINES PERFORMANCE AND DESIGN COMPARISON CONCRETE VS. CSP Contents Current Standards...........................2 Manning n..............................4
More informationEVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING
ICC-ES Report PMG-1273 Reissued 01/2018 This report is subject to renewal 01/2019 EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: 22 00 00 PLUMBING SECTION: 22 13 16
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES
ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer complete in place and the material therein,
More informationEastern Drainage Services Ltd Drainage investigations for surveyors, engineers and loss adjusters
Eastern Drainage Services Ltd Drainage investigations for surveyors, engineers and loss adjusters Specialists in all drainage renovation techniques including in-situ repairs and sewer connections 6 Drymere,
More informationLS 2760 CURED-IN-PLACE SEWER LINING
LS 2760 CURED-IN-PLACE SEWER LINING A. Related Documents B. Summary C. Submittals D. Quality Assurance E. Project Conditions F. Sequencing and Scheduling G. Quantities H. Liner and Resins I. Initial Sewer
More information