Presentation Outline. Project Information & Background. Project Information & Background. Project Team. Boston, Massachusetts
|
|
- Gwendolyn Reynolds
- 6 years ago
- Views:
Transcription
1 Project Team Owner Tufts Boston, Massachusetts Boston, Massachusetts Tufts $65 Million 8, sqft. Project Schedule Began in 995 Delayed from Completed in 23 Architectural Firm Architectural Lead Architect Resources Cambridge Mark Snyder MEP Construction Structural Bard, Rao + Suffolk LeMessurier Athens Construction Consultants Consulting Engineers Scaffolding GGG Scaffolding Material Hoists Services Corp, Julian Crane & Equip. Corp. Plumbing J.C. Higgins Corp, HVAC Limbach, Ceramic Tile, Carpet & Resiliant Masonry Facade Flooring NER Construction Merrimac Tile Co., Management Inc. Inc. Concrete Flatwork Reliable Concrete Above Grade Two Level Penthouse Nine Occupied Floors Below Grade One Basement Level 8,8 ft 2 Basement
2 First Floor Second Third Floors 9,6 ft 2 8,75 ft 2 Classroom First Level Roof Below Lobby Auditorium 8,75 ft 2 Fourth Floor 8,75 ft 2 Fifth Floor Laboratory/Support Laboratory/Support Shell Shell,75 ft 2 Fifth Level Roof Below Sixth Ninth Floors Laboratory/Support Penthouse Non-Conditioned Space 2
3 Air System (4) Identical % OA Air Handlers 7, cfm each Runaround-Coil Heat Recovery 4% Effectivness 3-5 Year Payback Steam Pre-heat Coil Cooling Coil Sound Attenuators (2) 35, cfm Supply Fans Air System AHU 3 & 4 Level 4 Level 9 AHU & 2 Basement Level 3 AHU 3&4 Air Distribution VAV w / Terminal Reheat VCV w / Terminal Reheat Chilled Steam Hot Water System Water System System () Heated 6 psi ton Supply By Steam Centrifugal HX s Chiller () 42 PRV s Loops 8 ton Double-Effect Steam Absorption Use Terminal Reheat Chiller Primary LPS: Perimeter Pre-heat / Secondary Heating Coils & CHP s HX s 2-Cell MPS: Cooling Laboratory Tower Autoclaves HPS: Absorbtion Chiller AHU &2 Depth: Investigate Possibility of Reducing Operating Cost Breadth: Acoustics Reduce Transmission Through Envelope Breadth: Construction Investigate Feasibility of Including BATT in Exterior Wall Composite 3
4 Design Alternatives to be Investigated Introduction of Recirculation Basement Level 3 Total Energy Recovery Basement Level 3 ONLY AHU 3 & 4 Will Be Redesigned AHU & 2 Will Remain the Same Existing Heat Recovery System Air Side Economizer (Enthalpy Controlled) Meet ASHRAE Standard 62-2 Existing Control Design Strategy Simultaneous Heating & Cooling Preheat RedesignSetpoint = 55F Preheat Setpoint = 4F SA Heating Accomplished by Reheat Eliminates Simultaneous Heating and Cooling Expected Benefit Return Damper Ruskin CD6 Low-Leakage Linear Response System Sizing Summary HAP v 4.2 Major system Components Within 8% of Original Design Resizing not Justified 4
5 Annual Operating Cost Summary Component Air System Fans Cooling Heating Existing Design 45,59 75,435 62,259 Recirculation Redesign 45,925 66,453 47, ,982 5,2 Basement Level 3 ONLY AHU 3 & 4 Will Be Redesigned AHU & 2 Will Remain the Same Existing Heat Recovery System in AHU & 2 Pumps 36,668 29,65 7,53 Cooling Tower Fans 8,636 7, HVAC Sub-Total 338,57 36,73 3,454 Lights Electric Equipment 53,356 22,5 58,369 26,39 Expected Benefit Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total 275,45 284,48 Grand Total 63,562 59, 3,454 Semco EXCLU-SIEVE model TE3-7 Max Airflow: 7, cfm AHU Airflow 55, cfm Face Velocity 8 fpm Optimal Velovity Under Design Conditions eff=78% Purge Volume = 36 cfm Purge Index Setting = 4 System Sizing Summary Chiller Plant 8 ton Absorption Chiller Will Remain New 4 ton Centrifugal Chiller Replaces Old 6 ton Unit Trane EarthWise CenTraVac Model Was Selected 3-Stage Pumps SCHP: Aurora 4 Series Annual Operating Cost Summary Component Air System Fans Cooling Heating Pumps Cooling Tower Fans Lights Electric Equipment Misc. Electric Misc. Fuel Use HVAC Sub-Total Non-HVAC Sub-Total Grand Total Existing Design 45,59 75,435 62,259 36,668 8, ,57 53,356 22,5 275,45 63,562 Total Energy Redesign 42,78 65,69 47,49 29,286 7,43 3,75 57,6,78 282, ,953 2,379,266 5,2 7,382,25 36,442 36,442 5
6 Overview Sample First Floor Classroom Interior Noise from Street Traffic Alternate Wall Composite Higher Transmission Loss (TL) Room Criteria (RC) Freq R T S w TL composit e NR (L p ) source (L p ) rec Alternate Composite Same Wall Construction Different Window Assembly Original: /4 /4 glass w/ /2 Airspace New: /4 3/6 glass w 4 Airspace Alternate Composite TL Calculation Identical to previous calculation Redesign Results Freq R T S w TL com NR (L p ) source (L p ) rec Design Comparison Lp (db) Interior Sound Pressure Levels from Street Traffic Existing Design Levels Reccomended RC Rating Levels Redesign Levels Octave Band Center Frequency (Hz) 6
7 Feasibility Study BATT Insulation in Exterior Wall Composite Primary Research HAP Analysis of Operating Cost Reduction Associated First Cost Secondary Research Scheduling Scheduling Time Schedule Placement Site & Construction Requirements Health Considerations & OSHA Potential Component Air System Fans Cooling Heating Pumps Cooling Tower Fans HVAC Sub-Total Lights Electric Equipment Misc. Electric Misc. Fuel Use Non-HVAC Sub-Total Jaharis Existing Building 45,59 75,435 62,259 36,668 8, ,57 53,356 22,5 275,45 Jaharis Building with BATT 44,66 74,944 6,997 36,378 8,4 335,48 53,356 22,5 275, ,677 Grand Total 63,562 63,562 2,677 First Cost Material 6" Thick, R9, 5" Wide BATT Crew Carpenter Daily Output [sqft.] 5 Labor Hours per sqft..7 Scheduling -/2 Weeks Crew of 5 Carpenters 4 Hour Work Week Material Cost [$/sqft.].36 Labor Cost [$/sqft].8 Total sqft of Wall 435 Total Labor Hours Total First Cost for insulation $2,68.9 Payback Period 8 Years Scheduling Health Considerations and OSHA Prerequisites International Agency for Research On Cancer (IARC) Possible Sidewalls, Carcinogen floors, and ceilings have been framed. Doors, windows, subflooring, and sheathing are in place. Consumer Product Safety Commission (CPSC) Plumbing, heating ventilating and air-conditioning work has Only been Carcinogenic completely roughed if Surgically in. Implanted OSHA Cabling and wiring (including telephone and other low-voltage Minimal wiring) Protective have been Gear completely roughed in. Full Clothing Respiration Filter (in some cases) Delivery Schedule Storage Don t Open Until Use Site and Construction Requirements Redesign All Goals Achieved First Operating Graphs Cost for Summary Cost Decision Summary Making Cooling Existing Tower Fans Annual Cost Summary Pumps Monthly Hourly Remote Electric Power Steam Demand Consumption (January) Recirculation Heating Total Energy 4, 4, 4 Compared to Total Energy Cooling Compared to 35, Existing Recirculation Existing Recovery Air System Fans Existing 3, 35, 2, 2 Design Redesign Design Redesign Design Component 25, 3, Electric Chiller, 22, 22, 93, 29, 2, 25, 8 Chilled Water Pumps 8, 5, 2, 6 Pump Motors, 6, 5, 4 Pump Hardware 3,726 3,726,856 2,87 4,, 2 5, RA Damper , 2, Enthalpy Wheels (4) Existing Recirculation Total Energy 224, -224, $338,57 $36,73 $3,75 Grand Total Jan Feb 35,726Mar Apr 36,8 May Jun Jul -455 Aug Sep 327,856 Oct Nov -92,3 Dec Design Option Hour Month Steam Power Electric Consumption Cost Demand (Therm) (kwh) (kw) 2: AM : AM 2: AM 3: AM 4: AM 5: AM 6: AM 7: AM 8: AM 9: AM : AM : AM 2: PM : PM 2: PM 3: PM 4: PM 5: PM 6: PM 7: PM 8: PM 9: PM : PM : PM 7
8 Small First Cost Increase Comparable to Total Energy Recovery Include BATT in Exterior Wall 8-/2 Year Payback Minimal Impact On Schedule (-/2 Weeks) Replace Windows Providing Acceptable First Cost Existing Windows May Cause Distraction Acknowledgments I Would Like To Thank: Jessica Yeager My Family My Project Contacts Dr. Srebric Dr. Mumma Dr. Bahnfleth Dr. Burroughs Dr. Freihaut Prof. Parfitt Paul Bowers (great work!) AE Dept. Faculty & Staff Penn State God AHU 3 & 4 Redesign Enthalpy Wheel Cooling Coil Draw-Thru 8
9 Why not have total energy recovery on all levels? Laboratory Research Infectious Diseases Cholera Cross Contamination Not an Option Internal pore diameter distribution only absorbs molecules less than 2.8 angstroms Cross Contamination <.4% not possible Third Floor S Street w α w S Traffic g α Noise g S f At 5 meters Correct.4 for 72.7 Distance.2 Freq Cylindrical Spreading Room Constant Gypsum Walls Acoustic Ceiling Tile Carpet α f S c α c A = Siαi Octave Band.65 L p Center (% Truck, 9% Freque Car, 35 mph, nncy ncy uncorrected for for disatance) distance) [Hz] α SAB R T Classroom Exterior Wall Section A-Weight 74 8 Exterior Wall Transmission Loss (TL) Structural Composite TL Interpolated Window Composite TL Taken Directly Area Weighted TL Calculated Octave Band Center Frequennc y[hz] Tl wall [Db] TL window [Db] TL composite [Db] τ τ / Sτ + S2τ = log S TL composite 2 2 TL = TL 2 = / Interior Sound Pressure Levels Calculated Using Noise Reduction (NR) Equations NR = ( L p ) ( L ) source p rec R T NR = TL + log Sw Freq R T S w TL composite NR (L p ) source (L p ) rec
Sample Reports. for. HAP v4.80 Example Problem
Sample Reports for HAP v4.80 Example Problem October, 2013 Carrier Software Systems Copyright 2013 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using the
More informationEMD SERONO RESEARCH CENTER EXISTING
EMD SERONO RESEARCH CENTER EXISTING BILLERICA, MA SHIYUN (SHARON) CHEN MECHANICAL AE SENIOR THESIS Building System Dedicated Outdoor Air System/ Systems Breadth Building Design Team Building: EMD Serono
More informationSample Reports. for. HAP v4.90 Example Problem
Sample Reports for HAP v4.90 Example Problem December, 2014 Carrier Software Systems Copyright 2014 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using
More informationBuilding Load and Energy Estimates Analysis. Instructor: Dr. Mumma. October 28, Thesis Building Sponsor s: INOVA Fairfax Hospital
David Peterson Penn State AE, Mechanical INOVA Fairfax Hospital The INOVA Heart Institute David J. Peterson Mechanical Option Mechanical Technical Report #2b The INOVA HEART INSTITUTE AT INOVA Fairfax
More informationGrunenwald Science and Technology Building
Grunenwald Science and Technology Building Clarion University- Clarion, PA AE 482 Mechanical Project Proposal: Proposal for Alternative Designs Shane Helm The Pennsylvania State University Architectural
More informationTHERMAL STORAGE FEASIBILITY STUDY
THERMAL STORAGE FEASIBILITY STUDY SPRING 2005 NEW HOUSE RESIDENCE HALL PRESENTATION OUTLINE GENERAL PROJECT DATA PROJECT TEAM MECHANICAL REDESIGN ELECTRICAL ANALYSIS ACOUSTICAL ANALYSIS CONCLUSIONS GENERAL
More informationMechanical Project Proposal
Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18
More informationReed Berinato Mechanical Option. Senior Thesis Report Spring Table of Contents
Table of Contents Thesis Abstract..... Insert Acknowledgements... 1 Executive Summary.. 3 1 - Project Background. 4 1.1 Boston Massachusetts and Tufts University... 4 1.2 Project History and Information.
More informationMechanical Systems Proposal
Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December
More informationSHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4
Table of Contents 1 Executive Summary... 1 2 Building Summary 3 3 Existing Mechanical System. 4 4 Mechanical Design Objectives..... 4 5 Mechanical System Evaluation. 5 5.1 Air Distribution System Evaluation....
More information2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.
Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems
More informationAcknowledgements 4. Executive Summary 5
Table of Contents Acknowledgements 4 Executive Summary 5 Building Overview.. 6 Building Summary.. 6 Site. 6 Evaluation of Existing Mechanical System. 7 Mechanical System Overview 7 Design Objective 7 Outdoor
More informationBroad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal
Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...
More informationOklahoma University Children s Medical Office Building
Oklahoma University Children s Medical Office Building Oklahoma City, O.K., BAE Advisor: Laura Miller Presentation Outline VRF System Dedicated Outdoor Air System Evaluation VRF Indoor Units Design Criteria
More informationBroad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal : REVISION I
Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal : REVISION I Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System
More informationCOOLING COIL (35% ETHYLENE GLYCOL)
APPENDIX Contents A1.1 Existing Mechanical Equipment Schedules A1.2 Existing Mechanical System Schematic Drawings A2. Building Design Loads, Energy Loads and Cost Data Tables A3. Standard 62n-2001 Ventilation
More informationProposal: Mechanical System Redesign
Proposal: Mechanical System Redesign The 959 Eighth Avenue 10019 Faculty Advisor: Dr. James Freihaut December 12, 2005 Table of Contents 1.0 Executive Summary 2.0 3.0 Proposal Obectives 4.0 Preliminary
More informationGeorgetown University New Science Center
Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical
More informationProject Proposal Proposal for Investigation of Alternative Systems
Project Proposal Proposal for Investigation of Alternative Systems 01.15.2010 Defense Media Activity Building Fort George G. Meade Penn State University Architectural Engineering Faculty Advisor: Dr. Treado
More informationTable 39 - Mechanical Room Surfaces Surface Area (sf) Floor Ceiling Exterior Walls Interior Walls Total 5245.
Acoustical Analysis There are many different acoustical issues that could be studied and dealt with in a hotel similar to the BWI Hilton. But the new mechanical design work previously described in the
More informationMechanical Systems Project Proposal
Mechanical Systems Project Proposal December 15, 2006 Table of Contents 1.0 Executive Summary... 2 2.0 Building Background... 3 3.0 Proposal Objectives... 5 4.0 Initial Considerations... 6 5.0 Proposed
More informationInterdisciplinary Science and Engineering Building
1 1 Senior Thesis Capstone Project Treado Thesis Proposal Interdisciplinary Science and Engineering Building University of Delaware Newark, DE 19716 2 2 Table of Contents Executive Summary 3-4 Building
More informationMechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion
Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:
More informationInterdisciplinary Science and Engineering Building
1 1 Senior Thesis Capstone Project Treado Thesis Proposal Interdisciplinary Science and Engineering Building University of Delaware Newark, DE 19716 2 2 Table of Contents Executive Summary 3-4 Building
More informationThe Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option
The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study
More informationGerald R. Ford Museum
Gerald R. Ford Museum Grand Rapids, Michigan Executive Summary Building and Plant Energy Analysis Report: Part I Brendan J. Cullen The Pennsylvania State University AE Senior Thesis Mechanical Option September
More informationNASA Langley Research Center Administration Office Building One Hampton, VA TECHNICAL REPORT 2. Building and Plant Energy Analysis Report
NASA Langley Research Center Administration Office Building One Hampton, VA TECHNICAL REPORT 2 Building and Plant Energy Analysis Report Valerie Miller Mechanical Dr. Freihaut 10/06/2014 TABLE OF CONTENTS
More informationTable of Contents. Page 1
Table of Contents Acknowledgments...2 Executive Summary...4 Project Background...5 Existing Mechanical System...8 Proposed Mechanical Redesign...13 Impact of Proposed Mechanical System on Structure...36
More informationThesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin
Thesis Proposal Photo by Fred Martin Clemson University Advanced Material Research Laboratory Anderson, SC David Anderson Mechanical Option Friday, December 15, 2006 Table of Contents 1. Executive Summary
More informationExample LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal
Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal
More informationThe Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario
The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario Visionwall Technologies Inc. 14904-123 Avenue Edmonton, Alberta, Canada T5V 1B4 Tel: 403 451 4000 Fax:
More informationNEW HOUSE RESIDENCE HALL CARNEGIE MELLON UNIVERSITY, OAKLAND, PA
Acoustical Analysis: Design Objective The primary acoustical goal of space planning is to place noisy equipment as far as possible from noise sensitive areas. New House did everything possible to achieve
More informationUniversity of Pennsylvania Pre K-8 th Grade School. James W. Meacham. Philadelphia, Pennsylvania. Construction Management Spring 2003 Senior Thesis
Outline Unique Aspects & Existing Conditions Thesis Approach Four Mechanical Redesigns Recommended Design issues 3D CAD & Mechanical Contractors Research Unique Aspects Educational Forces Involved University
More informationDEA Clandestine Laboratory Training Center
DEA Clandestine Laboratory Training Center David M. Potchak Penn State University Architectural Engineering Mechanical Option Background Information Existing Mechanical Systems Redesign Objectives Alternate
More informationTechnical Report Three
Technical Report Three Mechanical System Existing Conditions Evaluation Prepared by: Timothy Berteotti Prepared for: Date: November 16, 2011 Table of Contents Executive Summary...3 Design Objectives...3
More informationContinuous Commissioning Leading Energy Project Process - An Industry Approach
Continuous Commissioning Leading Energy Project Process - An Industry Approach Mingsheng Liu, Ph.D., P.E. Energy Systems Laboratory, University of Nebraska Jinrong Wang, P.E., Ken Hansen, P.E. Omaha Public
More informationSuburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company
Image Courtesy of The Whiting-Turner Contracting Company Penn State AE Senior Capstone Project Nicholas J. Kline Construction Option Advisor Mr. Ray Sowers 3 Water Drainage 2 Exterior 3 Water Drainage
More informationTechnical Assignment 2 Building and Plant Energy Analysis
Technical Assignment 2 Building and Plant Energy Analysis Des Places Residence Hall Duquesne University Pittsburgh, PA Peter Edwards Advisor: James Freihaut October 4, 2010 Table of Contents Executive
More informationSURNA Grow Facility: Systems Comparison - IEA
SURNA Grow Facility: Systems Comparison - IEA May 2016 SURNA Grow Facility This analysis provides the projected energy and associated cost comparison between the Surna proposed facility in comparison to
More informationExisting Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne
Existing Building Cx: Processes & Results A Cultural Journey Barry Abramson Senior Vice President Servidyne AIA Quality Assurance Learning Objectives 1. Define the key steps in the process of retrocommissioning
More informationLibrary In Metropolitan Washington, D.C.
1 Library In Metropolitan Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Rob Leicht Picture Provided by Multivista 2 Picture Provided by Multivista 3 Building Name: Library
More informationMechanical Tech Report 2
Mechanical Tech Report 2 Design Load Estimation and Energy Analysis M Resort Spa and Casino Tom M. Chirdon Faculty Advisor; William P. Bahnfleth October 24, 2008 Table of Contents 1.0 Executive summary
More informationMechanical Depth. Redesign and Analysis
Depth Redesign and Analysis 14 Analysis Scope The scope of my mechanical redesign will include the 2 nd and 3 rd floors of the SW hospital wing which includes Semi-Private, Private and Isolations rooms.
More informationXavier University of Louisiana
Annual Savings Report Year 2 May 1, 2012 to April 30, 2013 July 2013 For Marion Bracy Vice President Xavier University Facilities Planning 1 Drexel Drive New Orleans LA 70125 (504) 520 1056 Submitted By
More informationEnergy 10/19/2011. Inc. New. Castle, DEE. Image. By: Skanska
Technical Report Two Building, Plant Energy and Emission Analysis Report 10/19/ New Castle Center for Delaware Hospice, Inc. New Castle, DEE Image By: Skanska Pennn State University Architectural Engineering
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE
0067 1110 WEST GREEN STREET URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.810 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 18,640,900 OFFICE BUILDING GROSS SQUARE FEET 175,513
More informationEvaluation of Underfloor Air Distribution
McCarran International Airport Terminal 3 L as Vegas, NV Evaluation of Underfloor Air Distribution and Displacement Ventilation Systems The Pennsylvania State University AESenior ThesisPresentation, Spring
More informationBaffled Openings at Chain Link Fencing: Design shall consist of two end-posts set 4 feet apart, and a 10 foot wide chain-link fence panel equal in height as the adjacent fence. Chain link fence panel shall
More informationAnalysis II Energy Considerations for Green Roofs
Analysis II Energy Considerations for Green Roofs 1099 New York Avenue Background As seen from the previous analysis, many of the credits for sustainability can be obtained through the materials and methods
More informationNorth Pocono High School
Building System Integration Energy and Cost Analysis Architectural Engineering Senior Thesis Presentation Pennsylvania State University Presentation Outline Project Outline Existing System Design Conditions
More informationSound HVAC Choices for Sustainable Design. Julian de Bullet
PLEASE MUTE CELL PHONES Sound HVAC Choices for Sustainable Design Julian de Bullet Director of Industry Relations McQuay International ASHRAE Distinguished Lecturer 703-395-5054 1 2 Rising?? What Is Sustainability?
More informationIndiana University Glick Eye Institute. LEED Measurement & Verification Plan
Indiana University Glick Eye Institute LEED Measurement & Verification Plan April 10, 2012 1 Table of Contents General Introduction... 3 Facility Description... 4 M&V Objectives... 4 M&V Approach/Option...
More informationAE Senior Thesis Single Zone vs. Multi Zone
AE Senior Thesis Single Zone vs. Multi Zone - Science and Technology Building Scott Davis Faculty Advisor: Dr. Bahnfleth April 9, 2008 Table of Contents Table of Contents 2 Executive Summary 3 Acknowledgements
More informationWhat s My Baseline? ASHRAE
2010 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions (2010, vol 116,part 2). For personal use only. Additional reproduction,
More informationChilled Beams. The new system of choice?
Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams
More informationTechnical Report Three Mechanical Systems Existing Conditions Evaluation
09 10 Technical Report Three Mechanical Systems Existing Conditions Evaluation WESTINGHOUSE ELECTRIC CO. NUCLEAR ENGINEERING HEADQUARTERS CAMPUS Pittsburgh, PA Daniel P. Aughenbaugh Mechanical Dr. Bahnfleth
More informationAchieving acoustical standards in the classroom Study of HVAC systems and classroom acoustics
Achieving acoustical standards in the classroom Study of HVAC systems and classroom acoustics Trane believes the facts and suggestions presented here to be accurate. However, final design and application
More informationGATES-HILLMAN CENTERS
GATES-HILLMAN CENTERS CARNEGIE MELLON UNIVERSITY CASE STUDY ENERGY EFFICIENCY CARNEGIE MELLON UNIVERSITY Carnegie Mellon University looked to SEMCO to provide solutions for their energy efficiency goals.
More informationSCHOOL ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC
SCHOOL ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance
More informationIntegration of Mechanical System Redesign. Geothermal Heat Pumps with DOAS
Integration of Mechanical System Redesign Geothermal Heat Pumps with DOAS Lutheran Theological Seminary at Philadelphia The New Learning Center Prepared For: William P. Bahnfleth, Ph.D., P.E. Department
More informationCHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM
CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM 1. Category (Check one and indicate New or Existing, if applicable) Commercial Buildings New or Existing Institutional Buildings: Educational Facilities New
More informationENERGY MODELING TOOLS: SOLUTIONS FOR CREATING A HIGH PERFORMANCE BUILDING. Presented by Neil Maldeis Energy Solutions Engineering Leader, Trane
ENERGY MODELING TOOLS: SOLUTIONS FOR CREATING A HIGH PERFORMANCE BUILDING Presented by Neil Maldeis Energy Solutions Engineering Leader, Trane LEARNING OBJECTIVES Learn how to use and apply modeling tools,
More informationHolistic Design Approach For Energy Efficiency ASHRAE TECHNOLOGY AWARD CASE STUDIES
ASHRAE TECHNOLOGY AWARD CASE STUDIES This article was published in ASHRAE Journal, June 2018. Copyright 2018 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically
More informationENERGY MANAGEMENT PLAN - HEADQUARTERS. ABC Winery 123 1st Street Franklin, NJ 12345
ENERGY MANAGEMENT PLAN - HEADQUARTERS ABC Winery 123 1st Street Franklin, NJ 12345 TABLE OF CONTENTS Executive Summary 3 Background and Site Information 3 Summary 3 Energy Conservation Opportunities 4
More informationEnergyPro Building Energy Analysis. Single-story School Building
EnergyPro Building Energy Analysis Single-story School Building EnergyPro Building Energy Analysis for a single-story school bulding Project Scope The purpose of the EnergyPro energy model was to evaluate
More informationAE 481W Thesis Proposal
AE 481W Thesis Proposal I I Advisor: Dr. Treado UNIVERSITY OF CALIFORNIA SAN DIEGO RADY SCHOOL OF MANAGEMENT LA JOLLA, CA TABLE OF CONTENTS Executive Summary.3 Mechanical System Overview..4 Design Objectives,
More informationThe energy benefits of View Dynamic Glass
Workplace demonstration Energy monitoring over a period of 12 months resulted in the commercial office room installed with View Dynamic Glass saving 39 percent of the total energy consumed compared to
More informationHamilton Way - Case Study of a High Performance Community in a Cold Climate
March 11, 2010 Northeast Sustainable Energy Association Conference Peter Baker, P.Eng. Building Science Corporation Chris Nelson Nelson Construction Hamilton Way - Case Study of a High Performance Community
More informationCondenser Water Heat Recovery"
PLEASE MUTE CELL PHONES Condenser Water Heat Recovery" Julian de Bullet ASHRAE Distinguished Lecturer Director of Industry Relations McQuay International 703-395-5054 1 What Is Sustainability? sustainable
More informationCHP Case Studies. Midwest CHP Application Center (MAC) .org (312) University of Illinois at Chicago Energy Resources Center UIC
CHP Case Studies Midwest CHP Application Center (MAC) www.chpcentermw.org.org (312)413-5448 University of Illinois at Chicago Energy Resources Center CHP Case Studies Elgin Community College Presbyterian
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #110 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 22420» Total Man Hours on Project: 1081124» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued Hanging
More informationCoppin State University Physical Education Complex - Technical Report 2
Coppin State University Physical Education Complex - Technical Report 2 Building and Plant Energy Analysis Report Kaylee M Damico Advisor: Dr. Jelena Srebric Location: Baltimore, MD Table of Contents Contents
More informationCONSTRUCTION REQUIREMENTS
CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary
More informationRetrocommissioning Investigation Study of the Sheraton Chicago Hotel
Retrocommissioning Investigation Study of the Sheraton Chicago Hotel & Towers Cityfront Center Tracy Phillips May 4, 2007 May 4, 2007 You can go anywhere you want, if you look serious and carry a clip
More informationTechnical Report Two: Building and Plant Energy Analysis Report
The American Swedish Institute Minneapolis, MN Technical Report Two: Building and Plant Energy Analysis Report Name: Option: Mechanical Advisor: Stephen Treado Date: 10.19.11 Table of Contents Executive
More informationLaboratory Building Energy Analysis
Laboratory Building Energy Analysis Course No: M4-11 Credit: 4 PDH Steven Liescheidt, P.E., CCS, CCPR Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 198 P: (877) 322-58
More informationEnergyPro Building Energy Analysis. Nine-story Office Building
EnergyPro Building Energy Analysis Nine-story Office Building EnergyPro Building Energy Analysis for an office building Project Scope The purpose of the EnergyPro energy model was to evaluate the energy
More informationOverbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %
8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior
More informationGreening Your Business Energy Efficiency in Buildings
Greening Your Business Energy Efficiency in Buildings Ben J. Sliwinski Building Research Council School of Architecture University of Illinois at Urbana-Champaign Overview Introduction Where is the Money?
More informationDepth: Mechanical Redesign
Depth: Mechanical Redesign Redesign Objectives The most important objective of the mechanical redesign is to provide Greenbriar East with ventilation that meets the requirements of ASHRAE Standard 62-2001.
More informationThe Mirenda Center for Sports, Spirituality, and Character Development
prepared by: Zachary Heilman MECHANICAL OPTION prepared for: James Freihaut, PhD Technical Report 3: (Mechanical Systems Existing Conditions Evaluation) Due Date: November 29, 2010 The Mirenda Center for
More informationHotels: Water and Energy
Hotels: Water and Energy Agenda 01 Introduction 05 Hotel System Options 02 Company Overview 06 Hotel Energy Conservation 03 Hotel Energy & Water Use 07 Hotel Project Examples 04 Design Philosophy Introduction
More informationEADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel Mechanical Option
EADQUARTERS 707 N. Calvert St. Mechanical System Renovation Construction Management & Lighting/Electrical Breadths Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option
More informationHolistic Design Approach For Energy Efficiency ASHRAE TECHNOLOGY AWARD CASE STUDIES
2018 ASHRAE TECHNOLOGY AWARD CASE STUDIES Holistic Design Approach For Energy Efficiency Using LED and fluorescent lighting, the lighting design was modeled to maximize lighting effect while reducing energy
More informationTOP 10 STRATEGIES FOR NEW AND EXISTING BUILDINGS
TOP 10 STRATEGIES FOR NEW AND EXISTING BUILDINGS Kristine Chalifoux Management Engineer Facility and Services, University of Illinois Big10 & Friends October 10, 2016 WHAT IS HIGH PERFORMANCE DESIGN? What
More informationIntegration of Mechanical System Redesign. The New Learning Center Lutheran Theological Seminary at Philadelphia
Integration of Mechanical System Redesign Geothermal Heat Pump Redesign The New Learning Center Lutheran Theological Seminary at Philadelphia Wesley S. Lawson Architectural Engineering Mechanical Option
More informationTechnical Assignment 2: Building and Plant Energy Analysis Report. Jason Jones Mechanical Option Multipurpose Athletic Center West Long Branch, NJ
Technical Assignment 2: Building and Plant Energy Analysis Report Jason Jones Multipurpose Athletic Center West Long Branch, NJ October 27, 2004 Table of Contents Table of Contents 1 Executive Summary
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using
More informationOptimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning
Optimizing Energy Use in a HealthCare Setting Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning AIA Quality Assurance The Building Commissioning Association is a Registered
More informationSenior Thesis Report Spring Appendix - A. HAP Calculations without Enthalpy Wheel Excel Graphs
Jason Jones Mechanical Option Senior Thesis Report Spring 2005 Appendix - A HAP Calculations without Enthalpy Wheel Excel Graphs Cooling Plant Sizing Summary for Chiller Plant Monmouth CD New Schedule1
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationEffectiveness of Building Information Modeling in Value Engineering, Sequencing, & Site Logistics
Effectiveness of Building Information Modeling in Value Engineering, Sequencing, & T.C. Williams High School Replacement Kyle Conrad AE Senior Spring 2007 Construction Management Presentation Outline Building
More informationLIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC
LIBRARY ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance
More informationDesign Standard Sustainability
Design Standard Sustainability Purpose Educational institutions have the ability to influence the ideals and principles of our future decision makers; as such, East Side Union High School District (ESUHSD)
More informationhow to read an energy model
how to read an energy model Kohler Ronan, LLC is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported
More informationTimmins and District Hospital
Opportunity Assessment Timmins and District Hospital Draft Report December 10 th 2013 Submitted to: Tim Prokopetz, Manager, Materials - Biomedical Engineering Timmins and District Hospital Submitted by:
More informationASHRAE. Wxá zç Performance Innovation Experience. Why Geothermal HVAC Systems Fill The Bill. Kirk Mescher, PE P PE. Education.
ASHRAE AEDG K-12K Why Geothermal HVAC Systems Fill The Bill Kirk Mescher, PE Education Wxá zç Performance Innovation Experience ENGINEERING Bright Solutions in Engineering P PE 1 Simply Efficient 1 2 3
More informationAE Senior Thesis Final Report
AE Senior Thesis Final Report Energy Efficient Mechanical System Alternatives Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State
More informationOSU Richardson and Peavy Hall Energy Study: Energy Conservation Measure Analysis. January 25, 2012 {Revised April 30, 2012}
OSU Richardson and Peavy Hall Study: Conservation Measure Analysis January 25, 2012 OSU Richardson and Peavy Hall Study: Conservation Measure Analysis CONTENTS 1.0 Executive Summary... 1 2.0 Building
More informationWalter Reed National Military Medical Center Bethesda, MD
Walter Reed National Military Medical Center Bethesda, MD Technical Report One: ASHRAE Standard 62.1 2007 and 90.1 2007 Analysis Prepared For: Dr. James D. Freihaut Prepared By: Justin Herzing Date: 10/05/2009
More information