APPENDIX 8. Noise Impact Assessment

Size: px
Start display at page:

Download "APPENDIX 8. Noise Impact Assessment"

Transcription

1 APPENDIX 8 Noise Impact Assessment

2 Orica Australia Pty Limited Noise Impact Assessment for Proposed Ammonium Nitrate Emulsion Production Facility and Continued Operation of Orica Mining Services Technology Centre, Richmond Vale, NSW November 2009

3 Noise Impact Assessment for Proposed Ammonium Nitrate Emulsion Production Facility and Continued Operation of Orica Mining Services Technology Centre, Richmond Vale, NSW Prepared by Umwelt (Australia) Pty Limited on behalf of Orica Australia Pty Limited Project Director: Project Manager: Michelle Kirkman Emma Lodge Report No. 2586/R05/Final Date: November /20 The Boulevarde PO Box 838 Toronto NSW 2283 Ph: Fax: Website:

4 Orica Noise Impact Assessment Table of Contents TABLE OF CONTENTS 1.0 Introduction Project Description Project Area and Surrounds Plant and Equipment Proposed Hours of Operation Receiver Locations Traffic and Access Existing Noise Criteria Noise Impact Assessment Procedure Noise Environment and Project Noise Criteria Existing Noise Environment Environmental Noise Loggers Attended Noise Monitoring Operational Noise Criteria Construction Noise Criteria Sleep Disturbance Noise Goals Road Traffic Noise Criteria Noise Modelling Methodology Noise Modelling Meteorological Parameters Default Meteorological Conditions Site Specific Meteorological Conditions Modelling Conditions Operational Noise Sources Construction Noise Sources Road Traffic Noise Noise Predictions Predicted ANE Production Facility Operational Noise Levels Predicted Construction Noise Levels Sleep Disturbance Umwelt (Australia) Pty Limited 2586/R05/Final November 2009 i

5 Orica Noise Impact Assessment Table of Contents 6.4 Road Traffic Noise Assessment Cumulative Noise Impact Assessment Summary of Findings and Noise Management Noise Management Measures Mitigation of Road Traffic Noise References FIGURES 1.1 Orica Mining Services Technology Centre, Richmond Vale, NSW Existing Operations and Proposed ANE Production Facility Proposed ANE Production Facility and Residential Receivers APPENDICES A B C D E Glossary and Definitions - Acoustics Noise Impact Assessment Procedures Noise Monitoring Results Specifications of Plant and Equipment Road Traffic Noise Umwelt (Australia) Pty Limited 2586/R05/Final November 2009 ii

6 Orica Noise Impact Assessment Introduction 1.0 Introduction Orica Australia Pty Limited (Orica) is seeking development consent for the continuation of existing operations and the construction and operation of a proposed Ammonium Nitrate Emulsion (ANE) Production Facility at their Mining Services Technology Centre site (Technology Centre), located at Richmond Vale, New South Wales (NSW) (refer Figure 1.1). The Technology Centre currently operates under three development consents granted by Cessnock City Council in 1991, 1998 and The existing operations include offices, research and manufacturing facilities, stores, water storage, sewage treatment and car parking. There are approximately 200 people employed at the Technology Centre. The proposed ANE Production Facility will involve the construction of new infrastructure within the existing Technology Centre. The new facilities will allow for the production of up to 250,000 tonnes per annum of ANE which will be transported via road to other Orica operations and customers located in South Eastern Australia. Orica is seeking to obtain a new project approval that will incorporate the existing operations at the Technology Centre which will remain unchanged and the proposed ANE Production Facility (the Project). This consolidation of the existing operations and the proposed ANE Production Facility under a single development consent will enable more effective whole of site environmental management. The Project is a Part 3A Project as defined by the State Environmental Planning Policy (SEPP) Major Projects 2005, and requires the approval of the NSW Minister for Planning under Part 3A of the Environmental Planning and Assessment Act 1979 (EP&A Act). An Environmental Assessment (EA) will be lodged with the Department of Planning (DoP) for assessment. This Noise Impact Assessment (NIA) has been prepared by Umwelt (Australia) Pty Limited (Umwelt) as a part of the EA that will support the Part 3A project application for the Project. Umwelt (Australia) Pty Limited 2586/R05/Final November

7

8 Orica Noise Impact Assessment Project Description 2.0 Project Description 2.1 Project Area and Surrounds Orica s Technology Centre is located on the southern side of George Booth Drive which is a main arterial road in Richmond Vale, approximately 22 kilometres west of Newcastle, NSW (refer to Figure 1.1) in the Cessnock local government area (LGA). The Technology Centre is located on Lot 2, DP The property is approximately 292 hectares and is owned by Orica. The closest townships to the Technology Centre are Kurri Kurri, approximately 5 kilometres to the north-west and Seahampton, approximately 4 kilometres to the south-east of the Technology Centre. The surrounding area encompasses a variety of land use activities including agriculture, bush land, rural residential area, rural industrial activities and transport corridors. Tasman Underground Mine is located on George Booth Drive approximately 2.5 kilometres to the south-east of the Technology Centre. 2.2 Plant and Equipment The key infrastructure at the proposed ANE Production Facility is shown in Figure 2.1 and will include: chemical, fuel and product storage tanks; ANE manufacturing plant; truck weighing, loading and unloading facilities; utilities including hot water, cooling water and compressed air systems, electricity distribution cables and a transformer; stormwater/spill management structures; a plant site office, control room, switch room, and quality control laboratory; and an access road from the site entrance to the proposed ANE Production Facility. 2.3 Proposed Hours of Operation The proposed ANE Production Facility will operate 24 hours a day, 7 days a week. It is proposed to transport raw materials to site and ANE product off site 24 hours a day, 7 days a week. 2.4 Receiver Locations There are approximately 21 private residences located within a 3 kilometres radius of the Technology Centre boundary, with the nearest residential property approximately 1.8 kilometres from the proposed ANE Production Facility (refer to Figure 2.2). The majority of the private residences are located along George Booth Drive, with the remainder on Sheppeard Drive (refer to Table 2.1). Umwelt (Australia) Pty Limited 2586/R05/Final November

9

10

11 Orica Noise Impact Assessment Project Description Table 2.1 Residential Receivers Receiver Location Receivers North-west of Technology Centre along George Booth Drive Receivers - South-west of Technology Centre on Sheppeard Drive Receiver IDs R1 to R16 R17 to R Traffic and Access Access to the Technology Centre is gained via a dedicated intersection between George Booth Drive and the internal site access road, Echidna Drive. The access road for the proposed ANE Production Facility will be connected to Echidna Drive via a roundabout (refer to Figure 2.1). All materials currently utilised by the existing operations are transported to the Technology Centre by road. It is proposed to transport all raw materials for the proposed ANE Production Facility and all ANE from the proposed ANE Production Facility by road. Raw materials will be delivered to the proposed ANE Production Facility from Kooragang Island and other locations, including Sydney. Trucks transporting raw materials from Sydney will travel via the F3 Freeway, John Renshaw Drive and George Booth Drive. Trucks transporting materials from Kooragang Island will access the Technology Centre using the Pacific Highway and New England Highway for approximately 20 kilometres then continue along John Renshaw Drive and 4 kilometres down George Booth Drive (refer to Figure 2.2). Trucks exporting product will travel to the Hunter Valley from George Booth Drive via John Renshaw Drive and Cessnock Road (through Kurri Kurri) to the New England Highway at Maitland. Traffic associated with the project will utilise the F3 extension to Branxton in the future, once it is constructed, via the proposed Buchanan interchange. 2.6 Existing Noise Criteria The existing Environment Protection Licence (EPL 4121) and development consents for the Technology Centre do not contain conditions relating specifically to noise. Umwelt (Australia) Pty Limited 2586/R05/Final November

12 Orica Noise Impact Assessment Noise Impact Assessment Procedures 3.0 Noise Impact Assessment Procedure This Noise Impact Assessment (NIA) has been prepared by Umwelt to assess the potential noise impacts of the Project in accordance with the NSW Industrial Noise Policy (INP) (Department of Environment and Climate Change (DECC), 2000). A glossary of noise terminology is included in Appendix A. A detailed summary of the INP (DECC 2000) requirements and the noise impact assessment methodology used for this NIA is provided in Appendix B. To satisfy the requirements of the INP (DECC 2000), this NIA: identifies noise sensitive locations that could be affected by activities at the site and assesses the existing noise environment at noise sensitive locations in accordance with the INP (DECC 2000) guidelines for the determining background and amenity noise level; identifies all noise sources from the operational and construction phase of the development and determines the expected noise levels and noise characteristics (e.g. tonality, impulsiveness, vibration, etc) likely to be generated from the noise sources; identifies the times of operation for the development and for all noise-producing activities; considers the influence of meteorological conditions such as wind and temperature inversions on the propagation of noise from the Project to the receiver locations; predicts the noise levels likely to be received at the most sensitive locations under worst case meteorological conditions; compares the predicted noise levels with the appropriate noise criteria for the phase of development or activity being considered; predicts and then assesses the impact of the road traffic noise likely to be generated by the Project; and discusses the findings from the predictive modelling and, where relevant noise criteria have not been met, discusses additional mitigation measures. The noise level prediction modelling takes into account all the noise sources that may reasonably be expected when the Project is fully operational. The modelling was undertaken using the commercially available software packages Environmental Noise Model (ENM) for the industrial noise sources, construction noise and sleep arousal, and CoRTN (Calculation of Road Traffic Noise) for the road traffic noise. Umwelt (Australia) Pty Limited 2586/R05/Final November

13 Orica Noise Impact Assessment Noise Environment and Project Noise Criteria 4.0 Noise Environment and Project Noise Criteria 4.1 Existing Noise Environment The existing noise environment in the area surrounding the Project was assessed in accordance with Section 3 of the INP (DECC 2000) using a combination of Acoustic Research Laboratories (ARL) environmental noise loggers and attended noise monitoring. The results of the noise monitoring program were used to determine the Project-specific Noise Levels for the Project Environmental Noise Loggers ARL environmental loggers were used at the locations illustrated in Figure 2.2, to measure the ambient noise levels in the region surrounding the Orica Technology Centre. Details of the monitoring program are presented in Table 4.1. Table Details of Noise Monitoring using Environmental Loggers Monitoring Location Logger Serial No. Measurement Started Measurement Stopped L1 - George Booth Drive :15 30/07/09 09:45 18/08/09 L2 - Sheppeard Drive :00 30/07/09 10:00 18/08/09 The results of the monitoring program, reported as the Rating Background Level (RBL) and the Mean LAeq, period (where period = day, evening and night) are presented in Appendix C and summarised in Table 4.2. Table 4.2 Monitoring Results, RBL and Mean LAeq, period db(a) Monitoring Location Time Period RBL Mean LAeq, period L1 - George Booth Drive (Representative of R1 to R16) L2 - Sheppeard Drive ( Representative of R17 to R21) Day Evening Night Day Evening Night Note 1: Monday to Saturday Day is 7.00 am to 6.00 pm, Evening 6.00 pm to pm and Night pm to 7.00 am; on Sundays and Public Holidays Day is 8.00 am to 6.00 pm, Evening 6.00 pm to pm and Night pm to 8.00 am Attended Noise Monitoring The objective of the attended noise monitoring program was to determine the sources of noise contributing to the ambient noise environment and determine the contribution from industrial noise sources to the existing ambient noise levels. Attended noise monitoring was undertaken on two occasions in the region surrounding the Technology Centre during the day, evening and night time on the 21 January 2009 and 17 August The monitoring locations are shown on Figure 2.2 and represent the nearest potentially noise affected receiver areas to the north-west and south-west of the Technology Centre. The results of the operator-attended noise monitoring program are presented in Appendix C. Umwelt (Australia) Pty Limited 2586/R05/Final November

14 Orica Noise Impact Assessment Noise Environment and Project Noise Criteria The monitoring results were used to assess the background (LA90) and ambient (LAeq) noise levels within the residential receiver areas adjacent to the Project and determine the contribution from industrial noise sources to the existing ambient noise levels. The results of the attended noise monitoring program are presented graphically in Appendix C and summarised in Table 4.3. The results in Appendix C include a low pass filter to remove insect noise in frequencies greater than 1 khz. Table 4.3 Attended Noise Monitoring Results, db(a) Monitoring Location L1 - George Booth Drive (Representative of R1 to R16) L2 - Sheppeard Drive (Representative of R17 to R21) Note 1: Elevated background due to road traffic noise Note 2: Ambient noise levels affected by insects Note 3: Helicopter overhead Time Period Industrial LA90, 15min LAeq, 15min Contribution 20/01 17/08 20/01 17/08 20/01 17/08 Day < 30 < 30 Evening < 30 < 30 Night <30 < < 30 < 30 Day < 30 < 30 Evening 38 2 < < 30 < 30 Night 40 2 < < 30 < Operational Noise Criteria The acoustic environment in the region surrounding the Technology Centre is typical of a rural receiver type. The residential receiver areas south-west of the project area along Sheppeard Drive are dominated by natural sounds with little or no road traffic noise. To the north of the project area the residential receiver areas along George Booth Drive are, at times, heavily influenced by road traffic noise. Both residential receivers areas have been assessed using the rural receiver criterion in accordance with the INP (DECC 2000) guidelines. The operational project-specific noise criteria for the receiver areas surrounding the Technology Centre have been determined in Appendix C and are summarised in Table 4.4. Table Project-Specific Noise Criteria at Receivers Areas, db(a) Receiver Location Time Period Intrusiveness Criteria, LAeq,15 minute L1 - George Booth Drive (Representative of R1 to R16) L2 - Sheppeard Drive (Representative of R17 to R21) Amenity Criteria, LAeq, period Project-Specific Noise Criteria LAeq, 15 minute 1 Day Evening Night Day Evening Night Note 1: The Project-specific criterion is the most stringent of the intrusive and amenity criteria. Umwelt (Australia) Pty Limited 2586/R05/Final November

15 Orica Noise Impact Assessment Noise Environment and Project Noise Criteria 4.3 Construction Noise Criteria The DECC recognises that construction activities could generate higher noise levels than normal operational noises. The Interim Construction Noise Guideline DECC 2009 provides criteria for construction activities as presented in Table 4.5. Table DECC Construction Noise Criteria, db(a) Construction Time Recommended standard hours Monday to Friday 7 am to 6 pm Saturday 8 am to 1 pm No work on Sundays or public holidays Outside recommended standard hours Construction Noise Criterion LAeq, 15 minute RBL + 10 db RBL + 5 db Whilst construction activities for the Project will generally occur during the recommended standard hours of Monday to Saturday, there may be a need to undertake construction activities outside of these hours. The assessment of construction noise is therefore undertaken for standard day time hours and for periods outside standard hours including night times from 6:00pm to 7:00am week days and weekends from 1:00pm Saturday to 7:00am Monday. 4.4 Sleep Disturbance Noise Goals The DECC have provided an application note for the assessment of sleep disturbance (DECC July 2006),which suggests that to prevent sleep arousal, the LA1,1minute level of a noise source should not exceed the LA90 background noise level by more than 15 db. This is based on measurement outside the bedroom window of the receiver during the night-time hours (10.00 pm to 7.00 am) in accordance with the INP (DECC, 2000) and the guidance note reproduced in Appendix B. The relevant sleep disturbance noise goals for the residential receivers are provided in Table 4.6. Table 4.6 Sleep Disturbance Criteria at Residential Receivers, db(a) Receiver Location RBL LA90,15minute db(a) L1 - George Booth Drive (Representative of R1 to R16) L2 - Sheppeard Drive (Representative of R17 to R21) Note 1: Measured during the night-time period (10.00 pm to 7.00 am). 1 Night Time Construction Noise Criterion LA10, 15 minute Road Traffic Noise Criteria At maximum production levels the Project is expected to contribute an additional 100 heavy vehicle movements (50 vehicle trips) per day on weekdays and 76 heavy vehicle movements (38 vehicle trips) on weekends. These heavy vehicle movements will be a mixture of rigid and articulated vehicles. In addition to this, at maximum production light vehicle movements are expected to increase by approximately 20 per day (10 vehicle trips). Umwelt (Australia) Pty Limited 2586/R05/Final November

16 Orica Noise Impact Assessment Noise Environment and Project Noise Criteria During the construction phase of the Project it is expected that there will be 2 to 3 heavy vehicles accessing the site per day during a 6 day week and up to 50 small contractor vehicles. Road traffic noise criteria are set out in the Environmental Criteria for Road Traffic Noise (ECRTN) (EPA, 1999). These criteria are based on the functional categories applied by the RTA to the subject roads. George Booth Drive would currently be classified as sub-arterial roads in accordance with Section 2.2 of the ECRTN. A sub-arterial road is defined as a road that connects the arterial roads to areas of development and carry traffic from one part of a region to another. The construction of the F3 Link to Branxton highway link between the F3 Freeway near Seahampton and the New England Highway, west of Branxton (Hunter Expressway) will significantly reduce the regional traffic using George Booth Drive. As a result, George Booth Drive will revert to a collector road for local traffic. A collector road is defined as a road that connects the sub-arterial roads to the local road system in developed areas. Details of the predicted traffic volumes on George Booth Drive as a result of the proposed F3 Link to Branxton are presented in Appendix E. The relevant road traffic noise criteria as per the requirements of Table 1 of the ECRTN for George Booth Drive are provided in Table 4.7. Table Road Traffic Noise Criteria (EPA, 1999) Type of Development Criteria Day 1 Night 2 Where Criteria are Already Exceeded 7. Land use developments with potential to create additional traffic on existing freeways/arterials 3 60 db(a) LAeq, 15 hour 55 db(a) LAeq, 9 hour Where feasible, existing noise levels should be mitigated to meet the noise criteria. Examples of applicable strategies include appropriate location of private access roads; regulating times of use; using clustering; using quiet vehicles; and using barriers and acoustic treatments. In all cases, traffic arising from the development should not lead to an increase in existing noise levels of more than 2 db. 8. Land use developments with potential to create additional traffic on collector road 60 db(a) LAeq, 1 hour 55 db(a) LAeq, 1 hour Note 1: Daytime 7:00 am to 10:00 pm. Note 2: Night time 10:00 pm to 7:00 am. Note 3: Arterial roads and sub-arterial roads are grouped together ECRTN (EPA 1999). Where feasible and reasonable, existing noise levels should be mitigated to meet the noise criteria. Examples of applicable strategies include appropriate location of private access roads; regulating times of use; using clustering; using quiet vehicles; and using barriers and acoustic treatments. In all cases, traffic arising from the development should not lead to an increase in existing noise levels of more than 2 db. From Table E5 it can be seen that the re-classification of George Booth Drive from a subarterial road to a collector road results in the application of the road traffic noise criteria from a period assessment (15 hrs - day and 9hrs night) to a one (1) hour assessment. Umwelt (Australia) Pty Limited 2586/R05/Final November

17 Orica Noise Impact Assessment Noise Modelling Methodology 5.0 Noise Modelling Methodology 5.1 Noise Modelling Noise level predictions must take into account all the noise sources that may reasonably be expected when the Project is fully operational. A computer model of the proposed operations was developed using a commercially available software package as per Section 6 of the INP (DECC 2000) to determine the impact of project related noise sources on receivers. The model used was Environmental Noise Model (ENM), developed by RTA Technology Pty Ltd. ENM is recognised and accepted by the DECC as a computer modelling program suited to predicting noise impacts from industrial noise sources. A computer model of the Project was prepared incorporating identifiable noise source data, meteorological data, surrounding terrain characteristics and effects of nearby buildings and structures. The model was used to predict the expected contribution to noise levels from the Project at the nearest potentially affected receiver areas under typical operating conditions. ENM calculates noise levels at either specified receiver locations (Single Point calculation) or generates noise level contours over a defined area (Contour calculation). The Single Point calculation feature of ENM was used to assess the noise impacts from the Project for the meteorological conditions described in Section 5.2 as it provides an increased level of accuracy over the contour method. 5.2 Meteorological Parameters Default Meteorological Conditions In Section 5 of the INP (DECC 2000) the simple approach for assessing the effects of meteorological conditions on the propagation of noise is to assume that the default worstcase meteorological conditions presented in the INP (DECC 2000) are present a significant amount of time. The INP (DECC 2000) notes that this approach is used to test whether further analyses are warranted. The default worst-case meteorological conditions include: a 3 m/s wind from source to receiver; and during the night-time period, a temperature inversion with a lapse rate of 3 o /100 metres and 2 m/s drainage flow from source to receiver. Section 5 of the INP (DECC 2000) notes that this approach is conservative, in that it is likely to predict the upper range of meteorological enhanced noise levels and that actual noise levels may be less than predicted Site Specific Meteorological Conditions In Section 5 of the INP (DECC 2000) the detailed approach notes that, when warranted, site specific meteorological conditions can be derived from the analysis of meteorological data representative of the site. The Orica Technology Centre does not have a weather station, however, there is a weather station located approximately 2.5 kilometres to the east at the Tasman Mine. Umwelt (Australia) Pty Limited 2586/R05/Final November

18 Orica Noise Impact Assessment Noise Modelling Methodology The Noise Impact Assessment (NIA) Heggies, 2002 in the Tasman Underground Mine EIS, Newcastle Coal Company, 2002 analysed meteorological data from the weather station maintained by Tasman Mine. The analysis of the meteorological data indicated the presence of seasonal winds up to 3m/s at greater than 30 per cent of the time from the south to southeast and the north-west. The analysis of the meteorological data (Heggies, 2002) did not include the assessment of inversion conditions. The NIA (Heggies, 2002) used the Seasonal Frequency of Occurrence data in Appendix F of the INP (DECC 2000). As a result it was concluded temperature inversions did not need to be considered as a part of the assessment Modelling Conditions The noise model described in Section 5.1 was used to predict noise levels under INP (DECC 2000) default wind and temperature inversion conditions presented in Table 5.1. Table Meteorological Conditions for Noise Modelling Scenario Temperature ( C) Humidity (%) Wind Speed (m/s) Wind Direction (deg from North) Temperature Gradient ( C/100 m) Calm Daytime Calm Evening Calm Night NE Wind (Source to South-west Receivers) Temperature Inversion and SE Drainage Flow Temperature Inversion (Night - Calm) Operational Noise Sources The specifications of the equipment to be utilised as part of the Project are presented in Appendix D. All plant and equipment have been specified to achieve a maximum sound pressure level of 85 db(a) at 1 metre from the source. The assumptions used in modelling the Project include the following: all acoustically significant plant and equipment operate simultaneously; and the sound power level specifications for all plant items would ensure the elimination of noise characteristics such as tonality, impulsiveness and low frequency noise. Consequently, modifying factor adjustments for these noise characteristics do not need to be considered in the noise assessment. 5.4 Construction Noise Sources Construction activities will include vegetation clearance, earthworks and site preparation, civil works such as laying of foundations and internal access road construction, structural steel erection, and installation of plant equipment, piping, instruments and electricals The Umwelt (Australia) Pty Limited 2586/R05/Final November

19 Orica Noise Impact Assessment Noise Modelling Methodology construction phase activities will involve the use of typical machinery and equipment as shown in Table 5.2. Construction may be undertaken outside the recommended standard hours identified in Table 4.5. Excessively noisy activities will be scheduled during daylight hours. Table 5.2- Expected Construction Equipment Typical Sound Power Levels Equipment Description Operating Condition Sound Power Level Bulldozer (e.g. CAT D10) Clearing vegetation 120 db(a) Backhoe Digging 108 db(a) Concrete Truck (delivery) Discharging 122 db(a) Crawler Crane Lifting 111 db(a) Compressor Operating 110 db(a) Noise emissions from these activities were incorporated into the ENM noise model to determine potential noise impacts from construction at the nearest receiver areas. 5.5 Road Traffic Noise The Environmental Criteria for Road Traffic Noise (ECRTN) EPA, 1999 provides a framework for the assessment of road traffic noise. To facilitate the assessment, the road traffic noise levels from George Booth Drive were modelled using the United States Federal Highway Administration (USFHWA) LAeq calculation method (ref: US EPA Report 550/ , (March 1974) as modified using the equations in Appendix A-13 & CoRTN amendments). The likely impacts of the traffic generated by the Project on the road traffic noise levels from George Booth Drive took into consideration: the current traffic levels on George Booth Drive; the traffic levels on George Booth Drive as a result of the proposed development; the future traffic levels on George Booth Drive with and without the F3 Link to Branxton in place. The details of the current and future traffic volumes on George Booth Drive and the associated road traffic noise level predictions are presented in Appendix E. Umwelt (Australia) Pty Limited 2586/R05/Final November

20 Orica Noise Impact Assessment Noise Predictions 6.0 Noise Predictions 6.1 Predicted ANE Production Facility Operational Noise Levels The proposed Orica ANE Production Facility was modelled using the ENM s Single Point calculation feature to determine noise levels at the nearest receiver areas for the six (6) meteorological scenarios in Table 5.1. The proposed ANE Production Facility operating hours will increase in line with future demand for ANE product up to 24 hours, 7 days per week. The predicted noise levels are presented in Table 6.1 and are compared to the respective Project-specific Noise Levels (PSNLs). Table 6.1 Predicted Operational LAeq, 15 minute Noise Levels, db(a) Meteorological Conditions George Booth Drive (R1 to R16) Sheppeard Drive (R17 to R21) Predicted Noise Level Projectspecific Noise Level Predicted Noise Level Projectspecific Noise Level Calm Daytime <30 46 <30 37 Calm Evening <30 43 <30 36 Calm Night <30 37 <30 35 NE Wind (Source to South-west Receivers) <30 37 <30 35 Temperature Inversion and SE Drainage Flow Temperature Inversion (Night - Calm) <30 35 <30 37 <30 35 The predicted noise levels from the Project for normal operating conditions are predicted to meet the criteria at all residential receiver areas during all operating periods. 6.2 Predicted Construction Noise Levels ENM s Single Point calculation model was used to determine noise levels at the nearest residential receiver areas for the representative construction phase of the Project. Calculations were undertaken for calm daytime and night time conditions. The predicted day time and night time LA10, 15 minute construction noise levels are compared to the relevant construction noise criteria in Tables 6.2 and 6.3. Table Predicted Day Time LAeq, 15 minute Construction Noise Levels, db(a) Receiver Area George Booth Drive (R1 to R16) Sheppeard Drive (R17 to R21) Predicted Day Time Construction Noise Levels Day Time Construction Noise Criteria < < Umwelt (Australia) Pty Limited 2586/R05/Final November

21 Orica Noise Impact Assessment Noise Predictions Table Predicted Night Time LAeq, 15 minute Construction Noise Levels Receiver Area George Booth Drive (R1 to R16) Sheppeard Drive (R17 to R21) Predicted Night Time Construction Noise Levels Night Time Construction Noise Criteria < < The results presented in Tables 6.2 and 6.3 indicate that construction noise levels are predicted to comply with the DECC s daytime construction noise criteria and the adopted night time construction noise criteria at all residential receiver locations for construction during the daytime and night time periods. 6.3 Sleep Disturbance The noise sources associated with the Project are typically continuous in nature, and as a result the typical LAmax noise levels experienced at the nearest residential receivers are expected to be within 3 db(a) of the calculated LAeq noise levels. This increase was modelled during the worst-case meteorological conditions, being a night time temperature inversion to determine the maximum sleep disturbance noise levels as a result of the Project. The predicted LA1, 1 minute noise levels are presented in Table 6.4 and are compared to the relevant sleep disturbance noise goals. Table Predicted LA1 1minute Noise Levels, db(a) Receiver Area George Booth Drive (R1 to R16) Sheppeard Drive (R17 to R21) Predicted Maximum Sleep Disturbance Noise Levels Sleep Disturbance Noise Criteria The results presented in Table 6.4 indicate that the predicted noise levels meet the recommended sleep disturbance noise goals at all residential receiver locations. 6.4 Road Traffic Noise Assessment Existing noise levels have been calculated from measurements of truck and car passby events during the attended monitoring program on the period 20 January, 30 July and 17 August This data was used in conjunction with the proposed traffic generation estimations to calculate the change in traffic noise levels associated with the Project. The modelling of road traffic noise assumed exhaust braking would not be used. Predictions of road traffic noise were made at each of the potential residential receiver on George Booth Drive. The details of the traffic noise monitoring, modelling and assessment are presented in Appendix E. and summarised in Table 6.5. Umwelt (Australia) Pty Limited 2586/R05/Final November

22 Orica Noise Impact Assessment Noise Predictions Table 6.5 Predicted Increase in Road Traffic Noise, db(a) Property ID Setback from centerline of road (m) Day Time - Predicted Existing 1 Commence 1 Operations Full 2 Operations Predicted Night Time Existing 1 Commence 1 Operations Full 2 Operations Criteria - LAeq, period Criteria - LAeq, 1 hour Note 1: From Appendix E, Table E12 - Predicted Increase in Road Traffic Noise at the Commencement of Operations Note 2: From Appendix E, Table E13 - Predicted Increase in LAeq, 1 hour Road Traffic Noise at Full Production in 2023 Note 3: Assessed as a sub-arterial road Note 4: Assessed as a collector road The results in Table 6.5 indicate that during the initial stage of the development the increase in road traffic associated with the Project will not increase the road traffic noise level more than 0.4 db nor will the noise levels exceed the relevant road traffic noise level criteria at all but one potentially affected residential receiver locations along George Booth Drive. The façade of one property (Property 3) is within 20 metres of the centre line of George Booth Drive. The predicted noise levels at the façade of the Property 3 for a 7187 AADT (existing traffic level) without the traffic movement associated with the Project would be 61.0 db(a) LAeq, 15 hour day and 55.0 db(a) LAeq, 9 hour night. The increase in road traffic associated with the Project at the commencement of operations would increase the road traffic noise level by 0.1 db during the day time and 0.3 db during the night time. Table 6.5 indicates that following the construction of the F3 Link to Branxton the road traffic noise levels, including noise generated by road traffic associated with the Project at full production levels, at each of the properties along George Booth Drive would not exceed the day time and night time criteria of 60 db(a) LAeq, 1 hour day and 55 db(a) LAeq, 1 hour night. Umwelt (Australia) Pty Limited 2586/R05/Final November

23 Orica Noise Impact Assessment Cumulative Noise Impact Assessment 7.0 Cumulative Noise Impact Assessment The INP (DEC 2000) addresses potential cumulative noise impacts from existing and proposed developments in an area by ensuring that appropriate noise emission criteria and consent limits are established with a view to maintaining acceptable noise amenity levels for residents. Based on the INP (DEC 2000), the amenity noise level is measured as the LAeq, period noise level (where period = day, evening or night). In relation to industrial noise sources, the acceptable amenity criteria applicable to the region surrounding the Project would be: Table 7.1 Cumulative Noise Goals based on Amenity Level Period Acceptable Cumulative Noise Level LAeq period, db(a) Maximum Cumulative Noise Level LAeq period, db(a) Day Evening Night The predicted intrusive LAeq, 15 minute noise levels during the operational phase of the Project are below 33 db(a) at the nearest residential receivers. Noise levels associated with construction are predicted to be less than 15 db(a) LAeq, 15 minute at the nearest potentially affected receiver. As a result, the predicted contribution from the Project to the amenity noise level would be 33 db(a) LAeq, Period or less. One of the objectives of the attended noise monitoring program was to identify the contribution to the ambient noise levels from existing developments in the region surrounding the Project. Two possible sources of industrial noise were identified: Tasman Mine; and the existing operations at the Orica Technology Centre. During the night time attended monitoring period mining infrastructure related noise was audible at the Sheppeard Drive monitoring location. The run charts presented in Appendix C of this NIA show that the noise levels from Tasman Mine contributed to the background noise environment with a noise level of approximately 25 to 26 db(a). No sources of industrial noise were identified attributable to the existing operations at the Orica Technology Centre and Tasman Mine was not audible at the monitoring location on George Booth Drive. As there are no significant industrial noise sources contributing to the cumulative noise levels at the residential receiver locations on Sheppeard Drive and George Booth Drive the combined noise impacts due to the Project and the existing developments in the region would result in a predicted cumulative noise level of 33 db(a) LAeq, Period or less. This is well below the acceptable amenity noise levels of 40 db(a) LAeq, night, 45 db(a) LAeq, evening and 50 db(a) LAeq, day. Umwelt (Australia) Pty Limited 2586/R05/Final November

24 Orica Noise Impact Assessment Summary of Findings and Noise Management 8.0 Summary of Findings and Noise Management Umwelt has undertaken a Noise Impact Assessment in accordance with the INP (DECC 2000) of the proposed Orica ANE Production Facility at Orica s Technology Centre site located at Richmond Vale, NSW. The key findings of the NIA are as follows: The results of the Noise Impact Assessment indicate that the operational noise levels are predicted to meet the project-specific noise criteria at all residential receivers under default INP (DECC 2000) weather conditions. The cumulative noise impact of the Project would also comply with INP (DECC 2000) criteria. Construction noise levels will not result in any discernible impact on surrounding receivers as predicted noise levels comply with the DECC s daytime construction noise criteria and the adopted night time construction noise criteria at all residential receiver locations. Predicted noise levels are predicted to comply with the recommended sleep disturbance noise goals at all residential receivers. Prior to the completion of the F3 Link to Branxton (the Hunter Expressway), road traffic noise from the Project is predicted to meet the relevant ECRTN road traffic noise criteria at all but one potentially affected residential receiver locations along George Booth Drive. The façade of one property (Property 3) is within 20 metres of the centre line of George Booth Drive. Based on the CoRTN modelling of George Booth Drive, Property 3 experiences noise levels from the existing traffic on George Booth Drive at or above ECRTN road traffic noise criteria. Prior to the completion of the F3 Link to Branxton the increase in road traffic associated with the Project would increase the road traffic noise level by 0.1 db during the day time and 0.3 db during the night time. Following the construction of the F3 Link to Branxton road traffic noise from the Project is predicted to meet the relevant ECRTN road traffic noise criteria at all the potentially affected residential receiver locations along George Booth Drive. 8.1 Noise Management Measures While the Project is predicted to satisfy all relevant noise criteria, Orica have undertaken to minimise noise from construction and operation where practicable. The design of the Project has been undertaken to ensure that equipment noise is considered during the specification of equipment, including a design criteria of 85dB(A) at 1m. Activities that are likely to generate greater noise, especially during construction, will be undertaken where possible during the day. Orica will continue to review noise management practices as required during construction and operation. 8.2 Mitigation of Road Traffic Noise Increased noise annoyance or increased sleep disturbance could occur during the night time due to the movement of heavy vehicles associated with the Project. The greatest risk is associated with the use of heavy vehicle exhaust brakes at night when decelerating on the approach to the bend in George Booth Drive at the intersection of Richmond Vale Road, when travelling towards Technology Centre, or when nearing the intersection with John Renshaw Drive. Umwelt (Australia) Pty Limited 2586/R05/Final November

25 Orica Noise Impact Assessment Summary of Findings and Noise Management To address this risk Orica will implement a Traffic Management Protocol and Driver Code of Conduct with the Transport Company that may include measures such as: restrictions on the use of exhaust brakes in both directions on the section of George Booth Drive between John Renshaw Drive and the entrance road to Orica (i.e. the intersection between Echidna Drive and George Booth Drive); and maintaining a record of vehicles used to transport product to enable monitoring of adherence to the Traffic Management Protocol. Umwelt (Australia) Pty Limited 2586/R05/Final November

26 Orica Noise Impact Assessment References 9.0 References Richard Heggie Associates Pty Limited, Tasman Underground Mine EIS - Noise Impact Assessment Newcastle Coal Company Pty Limited, Tasman Underground Mine EIS NSW Environment Protection Authority, Environmental Noise Control Manual. NSW Environment Protection Authority, New South Wales Industrial Noise Policy. Transport and Urban Planning, Traffic and Impact Assessment for Proposed Ammonium Nitrate Emulsion Manufacturing Plant at Orica s Mining Services Technology Park at Richmond Vale. UK Department of Transport, Calculation of Road Traffic Noise (CoRTN). US EPA Report 550/ March 1974 Umwelt (Australia) Pty Limited 2586/R05/Final November

27 APPENDIX A Glossary and Definitions Acoustics

28 Appendix A - Glossary and Definitions - Acoustics 1/3 Octave Single octave bands divided into three parts Octave ABL ANL A division of the frequency range into bands, the upper frequency limit of each band being twice the lower frequency limit. Assessment background level - A single-figure background level representing each assessment period day, evening and night (that is, three assessment background levels are determined for each 24-h period of the monitoring period). It is determined by taking the lowest 10th percentile of the L 90 level for each assessment period. Acceptable Noise Level is an L Aeq, period (day, evening or night) listed in Table 2.1 of the INP as being a noise level from industrial sources that is recommended not to be exceeded, but may be exceeded in certain circumstances, in which case Table 2.1 lists a Recommended Maximum noise level which is 5 db greater than the ANL, and which provides guidance on an upper limit to noise from industry. Ambient Noise The noise associated with a given environment. Typically a composite of sounds from many sources located both near and far where no particular sound is dominant. A Weighting Background Noise Level Cumulative Daytime Or Day db(a), dba A standard weighting of the audible frequencies designed to reflect the response of the human ear to noise. Defined (Industrial Noise Policy, section 3.1) as the underlying level of noise present in ambient noise when all unusual extraneous noise has been removed. It is considered to be represented by the LA90 usually measured over a 15 minute period. Cumulative noise level is the total of noise from all sources. A cumulative assessment is required when noises from several industrial sources (existing, proposed and potential), each of which might be less than a criterion, can combine to cause a noise level in excess of the criterion. For Monday to Saturday 7.00am 6.00pm; On Sundays and Public Holidays 8.00am 6.00pm. Decibels A-weighted. db(l), db(lin) Decibels Linear or decibels Z-weighted. Decibel (db) Evening The units of sound level and noise exposure measurement where a step of 10 db is a ten-fold increase in intensity or sound energy and actually sounds a little more than twice as loud. 6.00pm to 10.00pm for all seven days of the week. Gradient Wind A hypothetical wind that is the summation of the horizontal components of winds that contributes to the vector direction being assessed. Hertz (Hz) The measure of frequency of sound wave oscillations per second - 1 oscillation per second equals 1 hertz. Intrusive noise refers to noise (measured as LAeq, 15 minutes) that intrudes above the background level measured in the absence of the source by more than 5 db. LA10 The percentile sound pressure level exceeded for 10% of the measurement period with 'A' frequency weighting calculated by statistical analysis. Typically used to assess the impact of an existing operation on a receiver area and is referred to as the cumulative noise levels at the receiver attributable to the noise source. 2586/R05/AA 1

29 LA90 LAmax LA1,1minute LAeq,t LAn Nighttime Or Night Background Noise Level. The percentile sound pressure level exceeded for 90% of the measurement period with 'A' frequency weighting calculated by statistical analysis. The maximum of the sound pressure levels recorded over an interval of 1 second. The measure of the short duration high-level noises that cause sleep arousal. The noise level is measured as the percentile sound pressure level that is exceeded 1 per cent of measurement period with 'A' frequency weighting calculated by statistical analysis during a measurement time interval of 1 minute. Equivalent continuous sound pressure level - The value of the sound pressure level of a continuous steady noise that, a measurement interval of time (t), has the same mean square sound pressure as the sound under consideration whose level varies with time. Usually measured in db with 'A' weighting. Percentile level - A measure of the fluctuation of the sound pressure level which is exceeded n per cent of the observation time. For Monday to Saturday 10.00pm am; On Sundays and Public Holidays 10.00pm am. Noise is the area around an industrial noise source where LAeq, 15 minute levels are above Affectation 5dB above the project-specific noise levels. Zone. Noise Management Zone RBL SPL (dba) is the area around an industrial noise source where LAeq, 15 minute levels are between 1 and 5 db above the project-specific noise levels or criteria Rating background level - The overall single figure background level representing each assessment period over the whole monitoring period determined by taking the median of the ABLs found for each assessment period. Noise: Sound pressure level - The basic measure of noise loudness. The level of the root-mean-square sound pressure in decibels given by: SPL = 10.log10 (p/po) 2 where p is the rms sound pressure in pascals and po is the sound reference pressure at 20 μpa. decibels. SWL Sound power level - A measure of the energy emitted from a source as sound and is given by: SWL = 10.log10 (W/W o ) where W is the sound power in watts and W o is the sound reference power at watts. 2586/R05/AA 2

30 APPENDIX B Noise Impact Assessment Procedures

31 Appendix B - Noise Impact Assessment Procedures Industrial Noise Policy Responsibility for the control of noise emissions in NSW is vested in Local Government and the DECC. The Industrial Noise Policy (INP) released by DECC in December 2000, provides a framework and methodology for deriving limit conditions for consent and licence conditions. Using this policy the DECC regulates premises that are scheduled under the Protection of the Environment Operations Act, 1997 (POEO Act). The specific INP objectives are: to establish noise criteria that would protect the community from excessive intrusive noise and preserve amenity for specific land uses; to use the criteria as the basis for deriving project-specific noise levels; to promote uniform methods to estimate and measure noise impacts, including a procedure for evaluating meteorological effects; to outline a range of mitigation measures that could be used to minimise noise impacts; to provide a formal process to guide the determination of feasible and reasonable noise limits for consent or licence conditions that reconcile noise impacts with the economic, social and environmental considerations of industrial development; and to carry out functions relating to the prevention, minimisation and control of noise from premises scheduled under the POEO Act. The INP is designed for large and complex industrial sources and outlines processes designed to strike a feasible and reasonable balance between the operation of industrial activities and the protection of the community from noise levels that are intrusive or unpleasant. The application of the INP involves the following processes: determining the project-specific noise levels (PSNL) for intrusiveness and amenity based on measurement of the existing background and ambient noise levels; predicting or measuring the noise levels produced by the development; and comparing the predicted noise levels with the project-specific noise levels and assessing impacts. Where the project-specific noise levels are predicted to be exceeded the INP provides guidelines on the assessment of feasible and reasonable noise mitigation strategies, including: weighing up the benefit of the development against the social and environmental costs resulting from the noise impacts; establishment of achievable and agreed noise limits for the development in consultation with the consent authority; and undertaking performance monitoring of environmental noise levels to determine compliance with the consent and licence conditions. 2586/R05/AB 1

Monthly Noise Monitoring Assessment

Monthly Noise Monitoring Assessment Monthly Noise Monitoring Assessment Tomingley Gold Mine, December 2018 Prepared for: Tomingley Gold Operations Pty Limited December 2018 MAC160270RP28 Document Information Monthly Noise Monitoring Assessment

More information

Southlands Remediation and Development Project

Southlands Remediation and Development Project Southlands Remediation and Development Project Environmental Assessment Project Application (MP 06_0191) Appendix M: Noise Assessment August 2009 REPORT 30-1596R1 Southlands Remediation & Redevelopment

More information

Environmental Noise Monitoring. Hanson Quarry Wagga Wagga, NSW. October 2012

Environmental Noise Monitoring. Hanson Quarry Wagga Wagga, NSW. October 2012 Environmental Noise Monitoring Hanson Quarry Wagga Wagga, NSW October 2012 Contents 1. INTRODUCTION... 3 2. UNATTENDED NOISE MONITORING... 3 3. EXISTING BACKGROUND NOISE LEVELS... 5 4. EXISTING AMBIENT

More information

Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan. Appendix 8. Noise Assessment

Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan. Appendix 8. Noise Assessment Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan Appendix 8 Noise Assessment PR104962-1 Rev 0; June 2011 PR104962-1 Rev 0; June 2011 Roma to Brisbane Pipeline Dalby

More information

CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET DEVELOPMENTS

CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET DEVELOPMENTS Acoustics 2008 Geelong, Victoria, Australia 24 to 26 November 2008 Acoustics and Sustainability: How should acoustics adapt to meet future demands? CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET

More information

CRANBOURNE LANDFILL. Environmental Noise Assessment. Rp ML. 10 May 2013

CRANBOURNE LANDFILL. Environmental Noise Assessment. Rp ML. 10 May 2013 CRANBOURNE LANDFILL Environmental Noise Assessment Rp 001 2012351ML 10 May 2013 4/46 Balfour St Chippendale NSW 2008 T: +612 9282 9422 Fax: +612 9281 3611 www.marshallday.com Project: CRANBOURNE LANDFILL

More information

APPENDIX 11. Bushfire Threat Assessment

APPENDIX 11. Bushfire Threat Assessment APPENDIX 11 Bushfire Threat Assessment Orica Mining Services Lot 2 DP 809377 George Booth Drive, Richmond Vale, NSW, 2327 Proposed Ammonium Nitrate Emulsion Production Facility Bushfire Threat Assessment

More information

Appendix B Noise and Blasting Impact Assessment

Appendix B Noise and Blasting Impact Assessment Appendix B Noise and Blasting Impact Assessment 19 August 2010 Ref: J0130-42-L4 Hansen Bailey Pty Ltd P.O. Box 473 SINGLETON NSW 2330 Attn: Ms. Melissa Walker Dear Mel, ABN: 73 254 053 305 78 Woodglen

More information

Environmental Noise Assessment

Environmental Noise Assessment July to September 2014 Rev 0 (Final) Report Details - July to September 2014 Filename: Job #: J0140003 Folder #: F13130 Revision: 0 (Final) Date: Prepared For Clark Potter, Senior Environmental Advisor

More information

Woodlawn Mechanical Biological Treatment Facility. Project Approval (06_0239) Condition 28 - Noise Audit Report. Report Number 610.

Woodlawn Mechanical Biological Treatment Facility. Project Approval (06_0239) Condition 28 - Noise Audit Report. Report Number 610. Veolia Environmental Services (Australia) Pty Ltd Cnr Unwin and Shirley Streets Rosehill NSW 2142 Version: v1.0 Page 2 PREPARED BY: ABN 29 001 584 612 2 Lincoln Street Lane Cove NSW 2066 Australia (PO

More information

Noise Monitoring Management Plan

Noise Monitoring Management Plan Noise Monitoring Management Plan For Woodlawn Bioreactor Document Code: PLA-NSW-XXX-XXX-1 Veolia Australia and New Zealand NSW Resource Recovery Woodlawn Bioreactor 619 Collector Road Tarago NSW 2580 www.veolia.com.au

More information

8. Appendix F Acoustic Assessment

8. Appendix F Acoustic Assessment 8. Appendix F Acoustic Assessment HFT Ltd 06-Jun-2017 Assessment of Noise Effects Mixed Industrial Development at 28 Inlet Road, Takanini Mixed Industrial Development at 28 Inlet Road, Takanini Client:

More information

ORICA VILLAWOOD REMEDIATION

ORICA VILLAWOOD REMEDIATION ORICA VILLAWOOD REMEDIATION NOISE AND VIBRATION ASSESSMENT REPORT NO. 09295 VERSION C ORICA VILLAWOOD REMEDIATION NOISE AND VIBRATION ASSESSMENT REPORT NO. 09295 VERSION C NOVEMBER 2010 PREPARED FOR THIESS

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

Wambo Coal Mine Annual Report

Wambo Coal Mine Annual Report Wambo Coal Mine Annual Report Environmental ise Monitoring 1 January to 31 December 2016 Prepared for Wambo Coal Pty Limited Page i Wambo Coal Mine Annual Report Environmental ise Monitoring 1 January

More information

Santos LNG Facility Noise Assessment

Santos LNG Facility Noise Assessment F4 Noise REPORT 20-2014-R7 Revision 1 Santos LNG Facility Noise Assessment PREPARED FOR URS Australia Pty Ltd Level 16, 240 Queen Street Brisbane QLD 4000 9 NOVEMBER 2009 HEGGIES PTY LTD ABN 29 001 584

More information

Environmental Noise Compliance Assessment Bass Point Quarry

Environmental Noise Compliance Assessment Bass Point Quarry P: 4421 4583 M: 0414 315 775 50 Junction Street, Nowra, NSW 2541 matthew@harwoodacsoutics.com.au www.harwoodacoustics.com.au ABN: 71634 997 937 Environmental Noise Compliance Assessment Bass Point Quarry

More information

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements Blakefield South Mine MANAGEMENT PLAN 1. COMMITMENT AND POLICY 1.1 Purpose The purpose of the Construction Noise Management Plan (CNMP) is to provide a structured process for managing, monitoring and reporting

More information

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KURRI KURRI ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2011 Revision Date Description Author Approver 0 25/07/2011 2011 Annual Environmental Report K Millard Environmental Advisor N Davies Project

More information

Project: FONTERRA STIRLING. Prepared for: Fonterra Limited PO Box 459 Hamilton Attention: Brigid Buckley. Report No.

Project: FONTERRA STIRLING. Prepared for: Fonterra Limited PO Box 459 Hamilton Attention: Brigid Buckley. Report No. FONTERRA STIRLING PROPOSED NOISE CONTROL BOUNDARY Rp 001 2016009C 20 September 2016 Level 369 Cambridge Terrace PO Box 4071 Christchurch 8140 New Zealand T: +64 3365 8455 F: +64 33658477 www.marshallday.com

More information

SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY

SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY 202 Uxbridge Road London W12 7JP Tel: +44(0)203 475 2280 Fax: +44(0)203 475 2281 info@clementacoustics.co.uk www.clementacoustics.co.uk SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY Report 8991-ENS-03

More information

WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS

WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS 1/355 Manukau Road Epsom, Auckland 1023 PO Box 26283 Epsom, Auckland 1344 T: 09 638 8414 E: hegley@acoustics.co.nz WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS Report No

More information

Impacts of Dredging and Reclamation on Noise and Amenity

Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5 Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5.1 Management Goals for Noise and Amenity The management goals for noise and vibration are to: Minimise the noise associated

More information

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS.

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7. NOISE & VIBRATION Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7.1 RECEIVING ENVIRONMENT 7.1.1 Monitoring Continuous noise monitoring was undertaken

More information

Noise monitoring program for assessing the impact of maximum traffic noise levels

Noise monitoring program for assessing the impact of maximum traffic noise levels Proceedings of ACOUSTICS 2005 9-11 November 2005, Busselton, Western Australia Noise monitoring program for assessing the impact of maximum traffic noise levels Treagus, R.* & Beazley, C. J.* Department

More information

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KURRI KURRI ANE PLANT ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2014 Revision Date Description Author Approver 0 2014 Annual Environmental Report D Horne Manufacturing Superintendent Kurri R Powell

More information

100 Avenue Road, Swiss Cottage, London

100 Avenue Road, Swiss Cottage, London 100 Avenue Road, Swiss Cottage, London 296993-01(00) NOVEMBER 2017 RSK GENERAL NOTES Project No.: 296993-01(00) Title: 100 Avenue Road, Swiss Cottage, London - Client: Date: 30 th November 2017 Office:

More information

1 18 August 2017 Version 2 (Noise and vibration)

1 18 August 2017 Version 2 (Noise and vibration) Table 8-6 s (Noise and Vibration only) EES Evaluation Noise and Vibration Health, amenity and environmental quality to minimise adverse air quality, noise and vibration effects on the health and amenity

More information

TABLE OF CONTENTS LIST OF TABLES

TABLE OF CONTENTS LIST OF TABLES CHAPTER 7 NOISE AND VIBRATION TABLE OF CONTENTS 7 NOISE AND VIBRATION... 7-1 7.1 Introduction... 7-1 7.2 Methodology... 7-1 7.3 Existing Environment... 7-2 7.3.1 Project specific operational noise criteria...

More information

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT October 2005 Contents 11. 11-1 11.1. Introduction 11-1 11.1.1. Scope of 11-1 11.2. Existing Noise

More information

HAINE ROAD, RAMSGATE NOISE ASSESSMENT

HAINE ROAD, RAMSGATE NOISE ASSESSMENT PROJECT NAME CLIENT PROJECT RECORD HAINE ROAD, RAMSGATE ACTIVE LAND & BUILD LTD. REPORT DETAILS TYPE REFERENCE 1775\AR\12-2017\748 ISSUE DATE DECEMBER 2017 NICHOLAS JONES AUTHOR REVIEWER BEng(Hons) CEng

More information

APPENDIX G NOISE ASSESSMENT

APPENDIX G NOISE ASSESSMENT Environmental Impact Statement Beryl Solar Farm APPENDIX G NOISE G.1 NOISE REPORT G.2 DRAFT CONSTRUCTION NOISE MANAGEMENT PLAN Beryl Solar Farm 16 347 Final V1 G i Acoustics Vibration Structural Dynamics

More information

WILPINJONG COAL NOISE MANAGEMENT PLAN

WILPINJONG COAL NOISE MANAGEMENT PLAN WILPINJONG COAL NOISE MANAGEMENT PLAN WI-ENV-MNP-0011 June 2017 Document Owner Environmental Advisor Document Approver Environment and Community Manager Version Approval Date Approver Name 3 June 2017

More information

Mt Piper Power Station Extension Environmental Assessment OPERATIONAL AND CONSTRUCTION NOISE IMPACT ASSESSMENT

Mt Piper Power Station Extension Environmental Assessment OPERATIONAL AND CONSTRUCTION NOISE IMPACT ASSESSMENT Mt Piper Power Station Extension Environmental Assessment OPERATIONAL AND CONSTRUCTION NOISE IMPACT ASSESSMENT 18 September 9 Mt Piper Power Station Extension Environmental Assessment OPERATIONAL AND

More information

Muswellbrook Coal Company Limited. Established No.1 Open Cut Extension FINAL NOISE MANAGEMENT PLAN (NMP) December 2010.

Muswellbrook Coal Company Limited. Established No.1 Open Cut Extension FINAL NOISE MANAGEMENT PLAN (NMP) December 2010. Established 1907 FINAL NOISE MANAGEMENT PLAN (NMP) December 2010 Version 1 Originally Prepared (February 2005) by: Muswellbrook Coal Company Technical Services Department and Carbon Based Environmental

More information

Noise. Summary of key outcomes: CHAPTER 22

Noise. Summary of key outcomes: CHAPTER 22 Noise CHAPTER 22 Summary of key outcomes: Construction activities would typically be undertaken during the day time, however some activities, particularly dredging, would also be undertaken at night. Construction

More information

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE Technical Report Prepared For Ardstone Capital Ltd. 48 Fitzwilliam Square Dublin Technical Report

More information

Noise and Vibration Assessment Muswellbrook Coal Company No. 1 Open Cut Extension

Noise and Vibration Assessment Muswellbrook Coal Company No. 1 Open Cut Extension Noise and Vibration Assessment Muswellbrook Coal Company No. 1 Open Cut Extension Prepared for Muswellbrook Coal Company Limited HLA-Envirosciences Project No U888/2 by Neil Pennington MAAS Manager Acoustics

More information

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment.

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment. 8. NOISE AND VIBRATION 8.1 Introduction This report has been prepared by AWN to form part of an EIAR for the proposed residential development at Wonderful Barn, Barnhall, Leixlip. The chapter assesses

More information

Assessment. Assessment. Ripley Valley Amex SUCE Development Stages ROL Phase. Ripley Valley Amex SUCE Development Stages ROL Phase

Assessment. Assessment. Ripley Valley Amex SUCE Development Stages ROL Phase. Ripley Valley Amex SUCE Development Stages ROL Phase Road Traffic Traffic Noise Noise Impact Impact Assessment Assessment Ripley Valley Amex SUCE Development Stages 15-19 ROL Phase Ripley Valley Amex SUCE Development Stages 15-19 ROL Phase A038_790400_02

More information

No significant construction or operational vibration impacts are expected.

No significant construction or operational vibration impacts are expected. 8 NOISE AND VIBRATION 8.1 SUMMARY OF RESIDUAL IMPACTS impacts for the construction and operation of the proposed CCGT power plant development are expected as these will be mitigated through design and

More information

NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING FOR BLUEWATER RIVER CROSSING REPLACEMENT PROJECT

NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING FOR BLUEWATER RIVER CROSSING REPLACEMENT PROJECT Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889 August 9, 2012 File: 160960699 NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING

More information

Gunlake Quarry. Noise and Blast Management Plan

Gunlake Quarry. Noise and Blast Management Plan Gunlake Quarry Noise and Blast Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Noise Criteria 3 2.1 Operational Noise Assessment Criteria 3 2.2

More information

Decibell Consulting pty Ltd

Decibell Consulting pty Ltd db Decibell Consulting pty Ltd Aspire 16-66 Wesley Rd, Griffin REVISED ENVIRONMENTAL NOISE IMPACT REPORT Prepared for Fairmont Group 23 rd January 2019 Decibell Report No. 1901251 Decibell Consulting Pty

More information

Assessment - Draft. Assessment - Draft. Ripley Valley Amex SUCE Development Stages ROL Phase

Assessment - Draft. Assessment - Draft. Ripley Valley Amex SUCE Development Stages ROL Phase Road Traffic Traffic Noise Noise Impact Impact Assessment - Draft Assessment - Draft Ripley Valley Amex SUCE Development Stages 33-37 ROL Phase Ripley Valley Amex SUCE Development Stages 33-37 ROL Phase

More information

6.0. Noise and Vibration.

6.0. Noise and Vibration. 6.0 Noise and Vibration 6.0 Noise and Vibration 6.1 Introduction 6.2 Assessment Methodology 6.3 Noise Sensitive Receptors 6.4 Expected Maximum Noise Emissions 6.1 Introduction This section aims to assess

More information

APPENDIX F VISUAL IMPACT ASSESSMENT

APPENDIX F VISUAL IMPACT ASSESSMENT APPENDIX F VISUAL IMPACT Environmental Impact Statement Wellington Solar Farm 17 76 Final v1.1 F I Acoustics Vibration Structural Dynamics Construction & Operational Noise & Vibration Assessment 24 November

More information

APPENDIX E NOISE AND BLASTING IMPACT ASSESSMENT

APPENDIX E NOISE AND BLASTING IMPACT ASSESSMENT APPENDIX E NOISE AND BLASTING IMPACT ASSESSMENT COWAL GOLD MINE EXTENSION MODIFICATION Barrick (Cowal) Limited PO Box 210 WEST WYALONG NSW 2671 Version: Page ii PREPARED BY: ABN 29 001 584 612 2 Lincoln

More information

ENVIRONMENTAL ASSESSMENT 4B-69 ENHANCE PLACE PTY LIMITED. Management Measures & Impacts Report No. 613/12

ENVIRONMENTAL ASSESSMENT 4B-69 ENHANCE PLACE PTY LIMITED. Management Measures & Impacts Report No. 613/12 ENVIRONMENTAL ASSESSMENT 4B-69 ENHANCE PLACE PTY LIMITED Pine Dale Coal Mine - Yarraboldy Extension Management Measures & Impacts Report No. 613/12 4B.5 HERITAGE The heritage assessment was undertaken

More information

1 Introduction. Mine EPL. report. Dear Leonard, J13083L2_24 assessment. operation of. the crusher, RASP Mine. 2015); and

1 Introduction. Mine EPL. report. Dear Leonard, J13083L2_24 assessment. operation of. the crusher, RASP Mine. 2015); and 14 January 2016 Leonard Sharp Environment and Community Liaison Officer CBH Resources RASP Mine Broken Hill Operations Pty Ltd 130 Eyre St, Broken Hill, NSW 2880 Level 5, 21 Bolton Street Newcastle NSW

More information

Noise Environmental Management Plan

Noise Environmental Management Plan Noise Environmental Management Plan For Sydney s Desalination Plant Kurnell Site Sir Joseph Banks Drive, Kurnell NSW 2231 02 8543 9200 Veolia Water Australia Pty Ltd Level 4, No 65 Pirrama Road NSW 2009

More information

Assessment - Draft. Assessment - Draft. Ripley Valley Amex SUCE Development Stages 42A ROL Phase

Assessment - Draft. Assessment - Draft. Ripley Valley Amex SUCE Development Stages 42A ROL Phase Road Traffic Traffic Noise Noise Impact Impact Assessment - Draft Assessment - Draft Ripley Valley Amex SUCE Development Stages 42A ROL Phase Ripley Valley Amex SUCE Development Stages 42A ROL Phase A038_790147

More information

Appendix P. Construction Noise Assessment. (Prepared by Marshall Day Acoustics, November 2013)

Appendix P. Construction Noise Assessment. (Prepared by Marshall Day Acoustics, November 2013) Appendix P Construction Noise Assessment (Prepared by Marshall Day Acoustics, November 2013) WRIGHTS ROAD STORAGE PONDS Construction Noise Assessment Rp 001 R03 2013523C 5 December 2013 Project: Prepared

More information

Appendix B2 Construction Noise and Vibration Management Plan

Appendix B2 Construction Noise and Vibration Management Plan Appendix B2 Construction Noise and Vibration Management Plan Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31

More information

8 Noise and Vibration

8 Noise and Vibration 8 Noise and Vibration 8.1 Introduction This chapter of the EIS assesses the potential noise and vibration impact of the Proposed Project on the baseline environment. The potential noise impact due to the

More information

LOTS 2 & 3 ANKETELL ROAD, ANKETELL SUBDIVISION ACOUSTIC ASSESSMENT FOR TERRANOVIS

LOTS 2 & 3 ANKETELL ROAD, ANKETELL SUBDIVISION ACOUSTIC ASSESSMENT FOR TERRANOVIS Rochdale Holdings Pty Ltd A.B.N. 85 009 049 067 trading as: HERRING STORER ACOUSTICS Suite 34, 11 Preston Street, Como, W.A. 6152 P.O. Box 219, Como, W.A. 6952 Telephone: (08) 9367 6200 Facsimile: (08)

More information

SECTION 11: NOISE RULES

SECTION 11: NOISE RULES SECTION 11: NOISE RULES This part of the Plan contains rules and performance standards relating to noise. This includes the requirements in terms of the maximum noise levels for activities and acoustic

More information

OBERON WHITE GRANITE QUARRY

OBERON WHITE GRANITE QUARRY Mudgee Stone Company Pty Ltd Document Owner: MSC Revision Period: 3 Years Issue: Draft Last Revision Date: 31/1/2017 NOISE MANAGEMENT PLAN OBERON WHITE GRANITE QUARRY i Endorsement of NMP by Mudgee Stone

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 656 30-November Licensee MUSWELLBROOK COAL COMPANY LTD PO BOX 123 MUSWELLBROOK NSW 2333 Premises MUSWELLBROOK COLLIERY HOLDING COAL ROAD MUSWELLBROOK NSW 2333

More information

Oberon Quarries Pty Limited BLAST MANAGEMENT PLAN. Oberon Quarry FINAL

Oberon Quarries Pty Limited BLAST MANAGEMENT PLAN. Oberon Quarry FINAL Oberon Quarries Pty Limited BLAST MANAGEMENT PLAN Oberon Quarry FINAL May 2016 Oberon Quarries Pty Limited BLAST MANAGEMENT PLAN Oberon Quarry FINAL Prepared by Umwelt (Australia) Pty Limited on behalf

More information

Prepared for Guillaume Nel Environmental Consultants. Prepared by A.W.D. Jongens. A.W.D. Jongens 8 Wingerd Avenue 7806 CONSTANTIA Tel:

Prepared for Guillaume Nel Environmental Consultants. Prepared by A.W.D. Jongens. A.W.D. Jongens 8 Wingerd Avenue 7806 CONSTANTIA Tel: Telephone: +27 21 794 5643 email: jongens@yebo.co.za A.W.D. Jongens 8 Wingerd Avenue 7806 CONSTANTIA Tel: 021 794 5643 Architectural Acoustics Noise & Vibration Control Environmental Noise Traffic Noise

More information

MAIN STREET PRECISE PLAN ENVIRONMENTAL NOISE STUDY REDWOOD CITY, CALIFORNIA

MAIN STREET PRECISE PLAN ENVIRONMENTAL NOISE STUDY REDWOOD CITY, CALIFORNIA MAIN STREET PRECISE PLAN ENVIRONMENTAL NOISE STUDY REDWOOD CITY, CALIFORNIA January 9, 2007 Prepared for: Valerie Young City of Redwood City 1107 Middlefield Road Redwood City, CA 94063 Prepared by: Richard

More information

Out of hours works protocol

Out of hours works protocol Out of hours works protocol March 2017 Document control File name TNR3N_OOH_Work _Protocol_Rev2 Report name Out of hours works protocol Revision number 2 Revision history Revision Date Description Approval

More information

CR Tabs_Main:Layout 1 14/5/09 3:15 PM Page 12 Noise and Vibration 12

CR Tabs_Main:Layout 1 14/5/09 3:15 PM Page 12 Noise and Vibration 12 Noise and Vibration 12 12 Noise and Vibration 12.1 Introduction A noise and vibration assessment was undertaken of the project and a detailed technical report (Appendix M) prepared. This section outlines

More information

NOISE MANAGEMENT PLAN

NOISE MANAGEMENT PLAN Young to Wagga Wagga Pipeline Looping Project Project No.: Q8291 Doc No: 8291-PLN-005 NOISE MANAGEMENT PLAN 1 07-08-10 Details revised as per NSW Dept of Planning G.O Mahony P. Grant G. O Mahony 0 28-07-10

More information

Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan (CNVMP)

Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan (CNVMP) SMC&S-C2S: SYAB Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan () 1/74 Sydney Metro City and Southwest Sydney Yard Access Bridge Construction

More information

Technical Report - Noise Monitoring OOHW: 5 to 7 March Sydney Metro City and Southwest North Corridor Works. Nathan Lynch; Paul Douglass

Technical Report - Noise Monitoring OOHW: 5 to 7 March Sydney Metro City and Southwest North Corridor Works. Nathan Lynch; Paul Douglass 1/8 Sydney Metro City and Southwest North Corridor Works Project Title Client Document Reference No. Laing O Rourke Project No. Noise Monitoring Sydney Metro City and Southwest LOR-NCW-Noise Monitoring_OOHW

More information

WHAKATU ARTERIAL PROJECT ASSESSMENT OF NOISE AND VIBRATION EFFECTS

WHAKATU ARTERIAL PROJECT ASSESSMENT OF NOISE AND VIBRATION EFFECTS WHAKATU ARTERIAL PROJECT ASSESSMENT OF NOISE AND VIBRATION EFFECTS Report No 9462.2 May 2014 Prepared for: Prepared by:.... Hastings District Council Private Bag 9002 Hastings 4156 Rhys Hegley BE, CPEng,

More information

Status: Rev: Comments Date: Author: Reviewer:

Status: Rev: Comments Date: Author: Reviewer: FREE RANGE BROILER FARM, ARAPOHUE ASSESSMENT OF ENVIRONMENTAL EFFECTS Rp 001 R02 20170847 18 September 2017 84 Symonds Street PO Box 5811 Wellesley Street Auckland 1141 New Zealand T: +64 9 379 7822 F:

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20850 24-November Licensee MACH ENERGY AUSTRALIA PTY LTD LEVEL 2, 179 GREY STREET SOUTH BANK QLD 4101 Premises MOUNT PLEASANT OPERATION 1100 WYBONG ROAD MUSWELLBROOK

More information

Technical Report - Noise Monitoring OOHW: 24 and 25 February Sydney Metro City and Southwest North Corridor Works. Nathan Lynch; Paul Douglass

Technical Report - Noise Monitoring OOHW: 24 and 25 February Sydney Metro City and Southwest North Corridor Works. Nathan Lynch; Paul Douglass 1/8 Sydney Metro City and Southwest North Corridor Works Project Title Client Document Reference No. Laing O Rourke Project No. Noise Monitoring Sydney Metro City and Southwest LOR-NCW-Noise Monitoring_OOHW

More information

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario Stationary Noise Feasibility Assessment 315 Chapel Street Ottawa, Ontario REPORT: GWE17 002 Stationary Noise Prepared For: Leanne Moussa Allsaints 10 Blackburn Avenue K1N 6P8 Ottawa, Ontario Prepared By:

More information

ACOUSTIC MODELING REPORT FOR THE DEVELOPMENT OF WIND ENERGY FACILITIES AT NAVSTA NEWPORT, RHODE ISLAND. March 2011

ACOUSTIC MODELING REPORT FOR THE DEVELOPMENT OF WIND ENERGY FACILITIES AT NAVSTA NEWPORT, RHODE ISLAND. March 2011 ACOUSTIC MODELING REPORT FOR THE DEVELOPMENT OF WIND ENERGY FACILITIES AT NAVSTA NEWPORT, RHODE ISLAND March 2011 ACOUSTIC MODELING REPORT FOR THE DEVELOPMENT OF WIND ENERGY FACILITIES AT NAVSTA NEWPORT,

More information

APPENDIX 5: NOISE COMPLIANCE REPORTING QUARTERLY REPORTS (Q1, Q2 AND Q3) KEYSBROOK MINERAL SANDS PROJECT COMPLIANCE ASSESSMENT REPORT 2016

APPENDIX 5: NOISE COMPLIANCE REPORTING QUARTERLY REPORTS (Q1, Q2 AND Q3) KEYSBROOK MINERAL SANDS PROJECT COMPLIANCE ASSESSMENT REPORT 2016 MZI RESOURCES LIMITED KEYSBROOK MINERAL SANDS PROJECT COMPLIANCE ASSESSMENT REPORT 2016 APPENDIX 5: NOISE COMPLIANCE REPORTING QUARTERLY REPORTS (Q1, Q2 AND Q3) Compliance Assessment Report 2016 FINAL.docx

More information

ANNUAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT DURALIE COAL MINE PLANS AND APPENDICES VOLUME 4 SEPTEMBER 2008 PART B

ANNUAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT DURALIE COAL MINE PLANS AND APPENDICES VOLUME 4 SEPTEMBER 2008 PART B ANNUAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT DURALIE COAL MINE PLANS AND APPENDICES VOLUME 4 SEPTEMBER 2008 PART B DURALIE COAL PTY LTD 4 SEPTEMBER 2008 Duralie Coal Mine NOISE SURVEYS Annual Environmental

More information

HANNA STREET REZONING APPLICATION Hanna Street Rezoning Rp ML. 19 June 2012

HANNA STREET REZONING APPLICATION Hanna Street Rezoning Rp ML. 19 June 2012 HANNA STREET REZONING APPLICATION 48-146 Hanna Street Rezoning Rp001 2012141ML 19 June 2012 6 Gipps Street Collingwood 3066 Victoria Australia T: +613 9416 1855 F: +613 9416 1231 A.C.N. 006 675403 www.marshallday.com

More information

Noise October 22, Noise Existing Conditions. Noise Characteristics

Noise October 22, Noise Existing Conditions. Noise Characteristics 3.7 3.7.1 Existing Conditions Characteristics The noise analysis contained in this section of the DEIS has been conducted in accordance with the New York State Department of Environmental Conservation

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I approve the project application referred to in Schedule 1, subject to the conditions in Schedules 2 to 4. These conditions

More information

BOTANY BAY CABLE PROJECT

BOTANY BAY CABLE PROJECT BOTANY BAY CABLE PROJECT CONSTRUCTION & OPERATIONAL NOISE ASSESSMENT REPORT NO. 06096 VERSION A BOTANY BAY CABLE PROJECT CONSTRUCTION & OPERATIONAL NOISE ASSESSMENT REPORT NO. 06096 VERSION A SEPTEMBER

More information

ACOUSTIC STUDY OF THE SUNY CANTON WIND TURBINE CANTON, NEW YORK. June 2013

ACOUSTIC STUDY OF THE SUNY CANTON WIND TURBINE CANTON, NEW YORK. June 2013 ACOUSTIC STUDY OF THE SUNY CANTON WIND TURBINE CANTON, NEW YORK June 2013 ACOUSTIC STUDY OF THE SUNY CANTON WIND TURBINE CANTON, NEW YORK Prepared for: Sustainable Energy Developments, Inc. 317 Route 104

More information

EDINBURGH TRAM LINES ONE AND TWO

EDINBURGH TRAM LINES ONE AND TWO EDINBURGH TRAM LINES ONE AND TWO NOISE AND VIBRATION POLICY MARCH 2006 1 INTRODUCTION This policy statement sets out the approach the promoter proposes to adopt to mitigate noise from the operation of

More information

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario Stationary Noise Feasibility Assessment 315 Chapel Street Ottawa, Ontario REPORT: GWE17-002 - Stationary Noise Prepared For: Leanne Moussa Allsaints 10 Blackburn Avenue K1N 6P8 Ottawa, Ontario Prepared

More information

E25. Noise and vibration

E25. Noise and vibration E25. Noise and vibration E25.1. Background Noise and vibration may cause adverse effects on amenity depending on: when and where it occurs; its duration; physical characteristics, including the sound pressure

More information

15.1. INTRODUCTION AND SUMMARY OF FINDINGS

15.1. INTRODUCTION AND SUMMARY OF FINDINGS Chapter 15: Noise 15.1. INTRODUCTION AND SUMMARY OF FINDINGS This Chapter analyzes the potential for the Proposed Project s operation to have an adverse noise impact on proximate receptors. The potential

More information

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI Traffic Management Plan Environmental Management and Monitoring Program Appendix VI Gunlake Quarries December 2009 Olsen Consulting Group Pty Ltd 6/25 Victoria Street WOLLONGONG 2500 PO Box 353 FIGTREE

More information

STATEMENT OF EVIDENCE OF CURT ROBINSON ON BEHALF THE AUCKLAND UTILITY OPERATORS GROUP

STATEMENT OF EVIDENCE OF CURT ROBINSON ON BEHALF THE AUCKLAND UTILITY OPERATORS GROUP BEFORE THE AUCKLAND UNITARY PLAN INDEPENDENT HEARINGS PANEL IN THE MATTER of the Resource Management Act 1991 and the Local Government (Auckland Transitional Provisions) Act 2010 AND IN THE MATTER of the

More information

Freight Train Noise Assessments

Freight Train Noise Assessments PO Box 717 Hillarys WA 6923 T: 9245 3223 F:9300 4199 E: mike@lgacoustics.com.au W: www.lgacoustics.com.au Freight Train Noise Assessments Reference: 14113026-02 Final.docx Prepared for: Freight & Logistics

More information

Appendix G Noise and Blasting Assessment

Appendix G Noise and Blasting Assessment Appendix G Noise and Blasting Assessment MT ARTHUR COAL OPEN CUT MODIFICATION NOISE & BLASTING ASSESSMENT REPORT NO. 11246 REVISION D JANUARY 2013 PREPARED FOR HUNTER VALLEY ENERGY COAL PTY LTD THOMAS

More information

BORG PANELS TIMBER PANEL PROCESSING FACILITY OBERON NSW

BORG PANELS TIMBER PANEL PROCESSING FACILITY OBERON NSW BORG PANELS TIMBER PANEL PROCESSING FACILITY OBERON NSW Noise and Assessment Vibration Impact May 216 Prepared for Borg Manufacturing Borg Panels, Timber Panel Processing Facility, Oberon NSW - Noise and

More information

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2 Holcim (Australia) Pty Limited Lynwood Quarry Groundwater Monitoring Program Revision 2 June 2011 Lynwood Quarry Groundwater Monitoring Program Revision 2 Prepared by on behalf of Holcim (Australia) Pty

More information

Status: Rev: Comments Date: Author: Reviewer:

Status: Rev: Comments Date: Author: Reviewer: MB ASSESSMENT OF NOISE EFFECTS Rp 002 R02 2016907 3 May 2018 84 Symonds Street PO Box 5811 Wellesley Street Auckland 1141 New Zealand T: +64 9 379 7822 F: +64 9 309 3540 www.marshallday.com Project: MB

More information

2.0 Description of Existing Mine Operations

2.0 Description of Existing Mine Operations 2.0 2.1 Mine History Austar Coal Mine is an amalgamation of several older mines and operates within a number of mining leases under 12 separate development consents issued by Cessnock City Council between

More information

Karuah East Quarry. Monthly Environmental Monitoring Report

Karuah East Quarry. Monthly Environmental Monitoring Report Karuah East Quarry June 2018 Table of Contents 1. INTRODUCTION... 1 2. DUST MONITORING... 1 2.1 Dust Deposition Results... 2 2.2 High Volume Air Sampling Results... 3 2.3 Dust Monitoring Results Summary...

More information

Tidbury Green Farmhouse, Tidbury Green. Proposed new Public House Report on existing noise climate 08/12/17 Revision 3 ACOUSTICS

Tidbury Green Farmhouse, Tidbury Green. Proposed new Public House Report on existing noise climate 08/12/17 Revision 3 ACOUSTICS 08/12/17 Revision 3 ACOUSTICS Tel: +44 (0) 121 450 4800 Audit sheet Hoare Lea Acoustics 6 th Floor West 54 Hagley Road Edgbaston Birmingham B16 8PE REVISION DESCRIPTION DATE ISSUED BY REVIEWED BY 0-DFC

More information

ASSESSMENT REPORT. ALBION PARK QUARRY Increased Production Rate Modification (10639 of 2005 MOD 2)

ASSESSMENT REPORT. ALBION PARK QUARRY Increased Production Rate Modification (10639 of 2005 MOD 2) ASSESSMENT REPORT ALBION PARK QUARRY Increased Production Rate Modification (10639 of 2005 MOD 2) 1 BACKGROUND Cleary Bros (Bombo) Pty Ltd owns and operates a hard rock quarry and processing plant near

More information

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement. Chapter 20: TERRESTRIAL NOISE AND VIBRATION

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement. Chapter 20: TERRESTRIAL NOISE AND VIBRATION ABERDEEN HARBOUR EXPANSION PROJECT November 2015 Volume 2: Environmental Statement Chapter 20: TERRESTRIAL NOISE AND VIBRATION 20. TERRESTRIAL NOISE AND VIBRATION 20.1 Introduction This chapter, which

More information

Chiles Ltd. 13 September 2018 Ref: Shearer Consulting Ltd. Dear Craig

Chiles Ltd. 13 September 2018 Ref: Shearer Consulting Ltd. Dear Craig Chiles Ltd Shearer Consulting Ltd 13 September 2018 Ref: 170202 By email: craig@craigshearer.co.nz Dear Craig Subject: Kaimai Wind Farm Responses to s92 acoustics questions I have reviewed the further

More information

Noise Environmental Management Plan

Noise Environmental Management Plan Noise Environmental Management Plan For Sydney s Desalination Plant Kurnell Site Sir Joseph Banks Drive, Kurnell NSW 2231 Veolia Water Australia Pty Ltd Level 4, No 65 Pirrama Road NSW 2009 Australia Tel:

More information

MT ARTHUR COAL U1 Particulate Matter Control Best Practice Implementation Report Wheel Generated Dust

MT ARTHUR COAL U1 Particulate Matter Control Best Practice Implementation Report Wheel Generated Dust U1 Particulate Matter Control Best Practice Implementation Report Document Owner Donna McLaughlin Document Approver Joel Chin Date Published 15 August 2014 Page 2 of 18 Contents 1. Introduction... 3 2.

More information

PROPOSED CO-OPERATIVE CONVENIENCE STORE AT MARINER PH, MORTIMER ROAD, SOUTH SHIELDS NOISE IMPACT ASSESSMENT. On behalf of: The Co-operative Group

PROPOSED CO-OPERATIVE CONVENIENCE STORE AT MARINER PH, MORTIMER ROAD, SOUTH SHIELDS NOISE IMPACT ASSESSMENT. On behalf of: The Co-operative Group PROPOSED CO-OPERATIVE CONVENIENCE STORE AT MARINER PH, MORTIMER ROAD, SOUTH SHIELDS NOISE IMPACT ASSESSMENT On behalf of: The Co-operative Group May 2016 PROPOSED CO-OPERATIVE CONVENIENCE STORE AT MARINER

More information