1 ADAMS SOLAR PV PROJECT PUBLIC HEARING KIMBERLEY 18 FEBRUARY 2014 Northern Cape PV Project 82,5MW

2 PROJECT COMPANY General information PREFERRED BIDDER IPPID RE_PV_0006_004 Adams Solar PV Project Two (Pty) Ltd 2012/114124/07 Preferred bidder in REIPPPP Round 3 Registered address: No. 3 Atherstone Bower, 77 King Edward Road, Lombardy East 2090 Johannesburg, South Africa PO Box 2005, Edenvale 1610 Tel: Alternative: riccardo.dalisera@enel.com 18/02/2014 NERSA PUBLIC HEARINGS 2

3 COMPANY STRUCTURE: SPV, EPC and O&M Contractors 3

4 THE SPONSOR COMPANY OVERVIEW Enel Green Power South Africa BV A subsidiary of Enel Green Power SpA, the Renewable company of Enel SpA the biggest Italian Electricity Group Established in 2013, specifically for participation in the Third Bid Submission Phase of the Department of Energy s IPP-Renewable Procurement Programme Awarded in the Third Bid Submission Phase for 6 Renewable Projects (4 PV and 2 WIND) > 500 MW Participating in Upington PV Project (Northern Cape) awarded during the Second Submission Phase, currently under construction Focused on long term presence and complex business plan in South Africa 4

5 ENEL GREEN POWER GLOBAL PRESENCE September 2013 North America Iberia & Latin America Italy&Europe Capacity: 1,679 MW Production: 4.9 TWh Technologies: Capacity: 2,898 MW Production: 8.5 TWh Technologies: 2 Capacity: 4,112 MW Production: 15.3 TWh Technologies: Capacity by technology Production by technology 57% 9% 38% 3% 30% 1% 2 2 Total = 8.7 GW Geo Hydro Wind Biomass Solar 20% 39% 2% 1% Reported capacity as of September 30, Reported production latest twelve months 2. Including co-generation 5 Total = 28.7 TWh

6 ENEL TODAY An international energy operator Presence in 40 countries Installed capacity 97,800 MW Annual production 296 TWh EBITDA 16.7 Bln Customers 61 million Employees 73,700 Capex Bln Stock exchange Enel is listed on the Milan stock exchange (~1.33 mln shareholders). 14 companies of the Group are listed on Milan, Madrid, Mosca, New York stock exchanges and in other Latin American countries Data as of

7 THE SPONSOR COMPANY OVERVIEW Enel Green Power South Africa BV The primary investment vehicle of the Royal Bafokeng Nation (RBN), a community of approximately Tswanaspeaking people in South Africa s North West Province Established in 2006 as a community-based investment company Holding assets across the mining, financial services, infrastructure, oil and gas services and industrial sectors Looking for stable and long term growing investments 7

8 LOCATION OF THE PV PLANT The Adams Solar PV project is situated in the Northern Cape Province, 21 kilometers south of Hotazel and 39 kilometers north of Kathu along the R380 tarred road joining these two towns, on the farm Adams 328. The site adjoins the tarred road to the east, while Mamatwan manganese mine (owned by the BHP Billiton mining group) occurs west of the tarred road and open pit excavations occur roughly 2 kilometers west of the site Latitude 27 22' 13.32" S` Longitude 23 05' 52.36" E 8

9 Use: Insert Classification PV PLANT GENERAL TECHNICAL INFORMATION Address: Farm Adams, Number 328, Portion 0 Kuruman RD, Joe Morolang Municipality Total Area: 275 ha Generation type: Solar Photovoltaic Plant (PV) Expected Commissioning: August 2016 Planned Capacity: 82.5 MWp DC Estimated annual output: 167 GWh average over 20 years Specific Output: 2032 kwh/kwp/annum CO2 Saved: tons/year Coal Saved: tons/year PV Module Technology: Thin Film Mounting Structure: Fixed ground mounted 14 x 3 portrait tilted at 20, oriented at 0 N 9

10 PV PLANT SITE & GRID CONNECTION 1/2 Use: Insert Classification The proposed construction of a line from the Project site to the Dougnor substation was dependant on the construction of a second line between the Dougnor Substation and the nearby Ferrum-Umtu 132kV line. This second line has been delayed and therefore it will no longer be possible for Adams Solar PV 2 to supply into the Dougnor substation. As a direct consequence the solution as presented in the Cost Estimate Letter is no longer feasible. The new solution under consideration involves the construction of a Switching Station adjacent to the Ferrum Umtu line. A line of roughly 700m between the on-site transformer and this switching station will be built. Eskom proposes this as a Self-Build project. 10

11 PV PLANT SITE & GRID CONNECTION 2/2 Use: Insert Classification New Ferrum- Umtum OHL ADAMS PV PLANT PV Plant Step Up Dougnor Station 132kV/32kV 700 m OHL between Step-Up and Switching Station Switching Station 11

12 LIST OF PERMITS Permit Status Comments EA Granted Date: 28/03/2013 Civil Aviation Granted Date: 17/06/2013 Heritage Consent Granted Date: 20/04/2012 Consent for Subdivision of Agricultural Land Expected Mid March Currently drafting approval letter Consent for Site Access Granted Date: 12/07/2013 SKA Approval Granted Date: 19/07/2013 DMR Consent Granted Date: 28/11/2012 LCC (Land Claim Consent) No Claims Date: 13/08/2012 Water General Authorization Submitted Consent to Change Land Use - Rezoning To be obtained prior to Financial Close Granted Approved by Municipality (22/01/2014) Building Plan Approval Pending To be obtained prior to Financial Close 12

13 FINANCIAL INFORMATION TIMING Construction Operations Start date 01-Jul Aug-16 Duration 25 months 20 years End date 31-Jul Jul-36 Capital Costs % of Total Modules 37.2% BOP 58.1% Land Acquisition 0.2% Development Costs 2.5% Connection - Eskom 0.3% Connection - EPC 0.6% Scada (BOP - Movable) 0.1% Engineering costs 0.1% Safety costs 0.9% Socio Economic Development 0.1% TOTAL 100% CAPEX SUMMARY AND DRAWDOWN PROFILE 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% ZAR costs 01-Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul-16 Cumulative Capex Spend 13

14 KEY TENETS OF IMPACTFUL ED 1. Learn from Historical Lessons Involve community from the beginning Plan for worker demobilisation 2. Compliance Is Threshold, Development Is Target 3. Give The Communities Voice 4. Recognise Existing Assets: Leverage Resources 5. Legacy achieved only through Sustainability 14

15 JOB CREATION Sub-Elements Complian ce Obligatio ns Constructi on Jobs Operations Jobs Beyond Compliance South African Citizens 93.34% 4 973pm= 414 jobs pm= 1443 jobs Youth and women ensuring representation via EPC contractors Black Citizens 78.06% 3 449pm= 287 jobs pm= 1265 jobs On-site apprenticeship for unskilled labour Skilled Black Citizens 56.24% 463pm = 39 jobs 3 500pm= 292 jobs Demobilisation strategy that will focus on postconstruction education (bursary) Local Citizens 61.81% 2 472pm = 206 jobs pm= 1023 jobs On-site training for O&M phase (diploma programmes) 15

16 LOCAL CONTENT Sub-Elements Compliance Obligations Beyond Compliance Key Components 51,87% Early identification of key suppliers- WOV, QSEs, SMES, local suppliers Local supplier Chain Support- formalisation & record keeping Educate SMMEs & WOV about RE Opportunities Marketing: Cross-project linkages despite different EPC/O&M 16

17 PREFERENTIAL PROCUREMENT Sub-Elements Compliance Obligations Beyond Compliance BBBEE 77,04% Early identification of key suppliers- WOV, QSEs, SMES, local suppliers QSE 17,7% Local supplier Chain Support- formalisation & record keeping Women Owned Vendors 5,26% Educate SMMEs & WOV about RE Opportunities Marketing: Cross-project linkages despite different EPC/O&M 17

18 MANAGEMENT CONTROL Sub-Elements Compliance Obligations Beyond Compliance Black People 100% 100% Black top management Women 50% Skills development in key areas to grow IPP specialisation Working with willing BEE partners to become true Energy Service Providers 18

19 ENTERPRISE DEVELOPMENT Sub-Elements Compliance Obligations Beyond Compliance Enterprise Development Contributions 0,6% Invest in ED during construction to leverage project opportunities Develop local industry to respond to the infrastructure needs of the sector & beyond Connect local enterprises to national & global value chains Create community-based development professionals Measure Impact, not just accounting for expenditure 19

20 SOCIO-ECONOMIC DEVELOPMENT Sub-Elements Compliance Obligations Beyond Compliance Socio-Economic Development Contributions 1,5% First SED project to be implemented during construction phase to avoid delayed social benefit Link skills development to enterprise opportunities to ensure post-qualification demand Measure Impact, not just accounting for expenditure Build a local development institution with research, fund-raising and project management capabilities 20

21 SOCIO-ECONOMIC NEEDS ASSESSMENT 45 Participants in focus groups drawn randomly from various communities 5 Semi-Structured Interviews with leaders ranging from Black Farmers Union to Govt. LED Officer Results of Primary & Secondary Data Analysis Community Priorities: 1. Health Care 2. Education 3. Jobs on existing infrastructure & mining projects IDP Priorities: 1. Water & Sanitation 2. Road Maintenance 3. LED- SMME Dev 21

22 DEFINING THE COMMUNITY Key Beneficiary Communities Tlapeng Tsineng Matoro Dinokaneng Tsineng-Kop Mokalanoga Magobing Magojaneng Masankong Kanana The PRA Tools also revealed the relative development status of each community Gasese Gatshekedi Maipeng 22

23 PROGRAMMATIC RESPONSE Construction Phase Agricultural exchange programme Enterprise Development Operations Phase (first 5 years) Community-Owned Jobs Fund ENELSI Training programme Starting Chance: ECD SMME Support Community Healthcare Targeted Need Agricultural skills Transfer & Social Cohesion Developing SMMEs to become procurement ready Targeted Need Job Creation & Bridging work experience gap Developing construction workers skills Addressing education from developmental phase Technical and financial support for new and existing entrepreneurs Developing NGO capacity to deal with diagnostic health services & mental wellness 23

24 ENEL GREEN POWER Flagship training programme A training programme to develop technical skills in solar photovoltaic, solar PV installation and general business management 1. Basics and advanced elements of electricity & solar photovoltaic 2. How to set up and manage an enterprise 3. Business plan of a solar PV installation 4. Client relationship management Key Outputs Trainees will be capable to deliver solar photovoltaic installations throughout South Africa. Graduates to set-up and manage small businesses individually or as small groups. Long-term Vision EGP franchising network for rooftop installations Preferential procurement for EGP Programme Graduates 24

Soetwater Wind Farm NERSA PUBLIC HEARINGS. 09 September 2015

Soetwater Wind Farm NERSA PUBLIC HEARINGS. 09 September 2015 Soetwater Wind Farm NERSA PUBLIC HEARINGS 09 September 2015 1 Soetwater Wind Farm has been appointed as a Preferred Bidder in the Fourth Round of the Department of Energy s (DoE) Renewable Energy IPP Procurement

More information

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015 Nxuba Wind Farm NERSA PUBLIC HEARINGS 10 September 2015 1 Nxuba Wind Farm has been appointed as a Preferred Bidder in the Fourth Round of the Department of Energy s (DoE) Renewable Energy IPP Procurement

More information

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd Scatec Solar ASA NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd Presented by Jan Fourie Business Development Manager September 2015 Project Company-General Information Dyason s Klip 1 (Pty) Ltd (formerly

More information

Garob Wind Farm. NERSA Hearings Port Elizabeth 10 September NERSA Hearing

Garob Wind Farm. NERSA Hearings Port Elizabeth 10 September NERSA Hearing Garob Wind Farm s Port Elizabeth 10 September 2015 GAROB WIND FARM OVERVIEW Northern Cape NERSA Hearing 20 February 20142015 10 September GAROB WIND FARM OVERVIEW 46 Turbines 138 MW Acciona 3.0 MW AW125

More information

Alessandro Bragantini Chief Operating Officer Building Energy S.p.A. Italy

Alessandro Bragantini Chief Operating Officer Building Energy S.p.A. Italy Alessandro Bragantini Chief Operating Officer Building Energy S.p.A. Italy Kathu 81 MWp Solar Farm Kathu, Northern Cape, South Africa BUILDING ENERGY IS A GLOBAL INTEGRATED INDEPENDENT POWER PRODUCER.

More information

7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA

7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA 7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA South Africa s IPP Procurement Programme SOUTH AFRICA S PREMIER WIND ENERGY CONFERENCE & EXHIBITION South Africa s IPP Procurement Programme is informed by the

More information

Overview of the South Africa s Independent Power Producers Procurement Programme

Overview of the South Africa s Independent Power Producers Procurement Programme Overview of the South Africa s Independent Power Producers Procurement Programme A partnership between: Department of Energy National Treasury Development Bank of Southern Africa - Enabling Renewable Energy

More information

South African Mainstream Renewable Power De Aar PV Pty Ltd

South African Mainstream Renewable Power De Aar PV Pty Ltd South African Mainstream Renewable Power De Aar PV Pty Ltd Presented to : NERSA, Kimberley Club, Kimberley Date: 5 March 2012 Presented by Adam Treki Presentation outline 1. Background 2. The Road Ahead

More information

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer.

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer. Speech by the Minister of Energy, Hon Jeff Radebe, MP at the Renewable Energy Independent Power Producer Programme (REIPPPP) Bid Windows 3.5 and 4 Contractual Close signing ceremony 4 April 2018 I would

More information

South African IPP Procurement Programme. December 2016

South African IPP Procurement Programme. December 2016 South African IPP Procurement Programme December 2016 Where are We? Urbanisation with increasing electricity demand, especially around urban areas; Looking for economic growth, which can be incentivised

More information

ACEF Deep Dive Workshop. 5 8 July 2017 Manila, Philippines

ACEF Deep Dive Workshop. 5 8 July 2017 Manila, Philippines ACEF Deep Dive Workshop 5 8 July 2017 Manila, Philippines Our journey Our challenge Addressing the Gaps Legislative mandate Identifying the blockages Roles and Responsibilities Integrated Resource Plan

More information

Our Activities, Our Commitment

Our Activities, Our Commitment ck_gradient_white 15 hild - 92288 Suresnes - FRANCE Fax : +33 (0)1 57 32 87 87 RÉFÉRENCES COULEUR Our Activities, Our Commitment Zone de protection 1 WHITE Zone de protection 2 Zone de protection 3 South

More information

Independent Power Producer procurement Improving integration with municipal distributors

Independent Power Producer procurement Improving integration with municipal distributors 25 th AMEU Technical Convention 4-7 October 2015 Independent Power Producer procurement Improving integration with municipal distributors Dr Clinton Carter-Brown IPP Office A partnership between: Department

More information

Unlocking the Green Economy and Solar PV Industries

Unlocking the Green Economy and Solar PV Industries Unlocking the Green Economy and Solar PV Industries 11 March 2015 AGENDA Introduction Overview of the sector in South Africa Views on the RE market in South Africa progress, successes, future challenges

More information

The Jeffreys Bay Wind Farm

The Jeffreys Bay Wind Farm The Jeffreys Bay Wind Farm African Utility Week Cape Town, 15 th May 2013 Presented by : Tom Thorogood & Davin Chown Mainstream South Africa A Lead Project with a pioneering history in SA 2001 : Project

More information

NERSA Public Hearing InnoWind / IDC Round 2 Projects

NERSA Public Hearing InnoWind / IDC Round 2 Projects Photomontage Thomas River Wind Farm Eastern Cape (80MW) NERSA Public Hearing InnoWind / IDC Round 2 Projects August 2012, Port Elizabeth Presented by: Kevin Minkoff, InnoWind. AGENDA I. Consortium Overview

More information

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities Presented to Nelson Mandela Bay Business Chamber Ibhayi Town Lodge, Port Elizabeth 16 th March 2012 Presented by Davin Chown

More information

South African Mainstream Renewable Jeffreys Bay Pty Ltd

South African Mainstream Renewable Jeffreys Bay Pty Ltd South African Mainstream Renewable Jeffreys Bay Pty Ltd Presented to : NERSA, Pine Lodge Conference Centre, Port Elizabeth Date: 2 nd March 2012 Presentation outline 1. Background 2. Milestones 3. Project

More information

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) 2 nd Annual California Biomass Collaborative Forum Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) Tony Gonçalves Program Lead Existing Renewable Facilities

More information

Small scale Hydro Electric Power IPP compliance with legislation and REBID process

Small scale Hydro Electric Power IPP compliance with legislation and REBID process Small scale Hydro Electric Power IPP compliance with legislation and REBID process Your project development partner, delivering value through a multi-skilled team 29 th May 2012 Contents 1. Legislation

More information

The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned

The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned June 2016 it (REIPPPP) has already established a flagship public-private partnership model

More information

AFRICA. Transforming Africa s energy landscape today

AFRICA. Transforming Africa s energy landscape today AFRICA Transforming Africa s energy landscape today ABOUT us OUR vision OUR services, & projects WHY juwi? Renewable Energies in South Africa is part of the international juwi Group, one of the world s

More information

Medium-term System Adequacy Outlook 2017 to 2021

Medium-term System Adequacy Outlook 2017 to 2021 Medium-term System Adequacy Outlook 2017 to 2021 31 July 2017 Contents 1. Overview... 3 2. Introduction... 3 3. Methodology and approach... 3 4. Assumptions... 5 4.1 Demand forecast... 5 4.2 Existing and

More information

GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES ABSTRACT

GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES ABSTRACT GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES 1 CAREL VAN DER MERWE, 2 ELZER (JACK) VAN DER MERWE, 3 OLAUS AW VAN ZYL, 4 GEORGE NEGOTA 1 Executive Director, BKS (Pty) Ltd

More information

MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS. Progress in the first half of 2017 (Issue 10)

MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS. Progress in the first half of 2017 (Issue 10) MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS Progress in the first half of 2017 (Issue 10) September 2017 Contents 1. Background on Renewable Energy Support in South Africa... 3 2. Implementation

More information

KINGSTON SOLAR LP. Sol-Luce Project Overview. August 13, 2014

KINGSTON SOLAR LP. Sol-Luce Project Overview. August 13, 2014 KINGSTON SOLAR LP Sol-Luce Project Overview August 13, 2014 PROJECT HIGHLIGHTS Facility to be located on approximately 800 acres of land bridging the City of Kingston and Loyalist Township Comprised of

More information

The Kingdom of Saudi Arabia National Renewable Energy Program. Renewable Project Development Office (REPDO) July, 2017

The Kingdom of Saudi Arabia National Renewable Energy Program. Renewable Project Development Office (REPDO) July, 2017 The Kingdom of Saudi Arabia National Renewable Energy Program Renewable Project Development Office (REPDO) July, 2017 Legal Disclaimer The information contained in this presentation is provided as general

More information

Peter Randall Solar Kingdom Ltd

Peter Randall Solar Kingdom Ltd Peter Randall Solar Kingdom Ltd How is Solar Doing? How is Solar Doing? Now an Established Industry How is Solar Doing? Now an Established Industry UK a Major Market Estimated Total installed capacity

More information

Kor OZAY. Ankara, 27 th March 2013

Kor OZAY. Ankara, 27 th March 2013 Challenges of Wind Energy Integration Kor OZAY Ankara, 27 th March 2013 Agenda Enel and Enel Green Power at a Glance Global Wind Market Wind Production Integration: Key Challenges 1 Enel at a Glance 1

More information

The Future of Electricity: A Market with Costs of Zero? Marginal

The Future of Electricity: A Market with Costs of Zero? Marginal The Future of Electricity: A Market with Costs of Zero? Marginal Richard Green, IAEE European Conference, 217 1 Supply /MWh Marginal Cost Nuclear CCGT OCGT GW 2 Demand and Supply Prices reflect Marginal

More information

NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012

NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012 NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012 Contents I. Introducing BioTherm Energy II. Klipheuwel Dassiesfontein Wind Energy Facility I. Project Information

More information

A Story of Energy and Passion OOW2018, San Francisco 22 October 2018 Fabrizio Brocchieri, Group CFO Building Energy Gualtiero Biella, Managing

A Story of Energy and Passion OOW2018, San Francisco 22 October 2018 Fabrizio Brocchieri, Group CFO Building Energy Gualtiero Biella, Managing A Story of Energy and Passion OOW2018, San Francisco 22 October 2018 Fabrizio Brocchieri, Group CFO Building Energy Gualtiero Biella, Managing Director GN Informatica Agenda Building Energy- Key Value

More information

Enel Green Power and the Renewable Energies Scenario

Enel Green Power and the Renewable Energies Scenario Enel Green Power and the Renewable Energies Scenario Francesco Starace - CEO Enel Green Power IEA Working Party on Renewable Energy Technologies - The Role of Renewables in the Energy Transformation: The

More information

The Future of Electricity: A Market with Costs of Zero? Marginal

The Future of Electricity: A Market with Costs of Zero? Marginal The Future of Electricity: A Market with Costs of Zero? Marginal Imperial College Business School Richard Green, IAEE European Conference, 217 1 Running your mouse over the bubble in the top left corner

More information

Mustard Seed. Company Profile

Mustard Seed. Company Profile Mustard Enterprise Trust (Big Business) The implementation of a Broad-Based Black Economic Empowerment (BBBEE) strategy in South Africa has forced enterprises to comply with the Codes of Good Practice

More information

The Republic of South Africa. Department of Energy

The Republic of South Africa. Department of Energy The Republic of South Africa Department of Energy EXPRESSION OF INTEREST IN RESPECT OF IDENTIFYING ONE OR MORE STRATEGIC PARTNER(S) FOR THE DEVELOPMENT, FINANCING, CONSTRUCTION, OPERATION AND MAINTENANCE

More information

SOLAR ENERGY ASSESSMENT REPORT. For 80.5 kwp. Meteorological Data Source NASA-SSE. Date 18 October, Name of Place Uttar Pradesh.

SOLAR ENERGY ASSESSMENT REPORT. For 80.5 kwp. Meteorological Data Source NASA-SSE. Date 18 October, Name of Place Uttar Pradesh. SOLAR ENERGY ASSESSMENT REPORT For 80.5 kwp Name of Place Uttar Pradesh Client abc Capacity 80 kw Meteorological Data Source NASA-SSE Email ezysolare@gmail.com Order No. #1410180006 Date 18 October, 2014

More information

NEW CODES 2013 CODES SUMMARY

NEW CODES 2013 CODES SUMMARY 1 NEW CODES 2013 CODES SUMMARY CONTENTS BEE in history Ownership Measurement of transformation Management Control Skills Development Enterprise and Supplier Development Socio-Economic Development 4 6

More information

MANCHESTER METROPOLITAN UNIVERSITY, UK VISITING RESEARCH FELLOW, GRADUATE SCHOOL OF BUSINESS LEADERSIP, UNIVERSITY OF SOUTH AFRICA

MANCHESTER METROPOLITAN UNIVERSITY, UK VISITING RESEARCH FELLOW, GRADUATE SCHOOL OF BUSINESS LEADERSIP, UNIVERSITY OF SOUTH AFRICA SOUTH AFRICA s RENEWABLE ENERGY INDEPENDENT POWER PROCUREMENT PROGRAMME (REIPPPP): A CASE OF LOCALISING THE RENEWABLE ENERGY INDUSTRY Dr. TIDINGS P. NDHLOVU MANCHESTER METROPOLITAN UNIVERSITY, UK VISITING

More information

Mobile market dynamics. Telkom SA Limited Analyst day

Mobile market dynamics. Telkom SA Limited Analyst day Mobile market dynamics Telkom SA Limited Analyst day Disclaimer This presentation has been prepared and published by Vodacom Group (Proprietary) Limited. Vodacom Group (Proprietary) Limited is a private

More information

Update on the Power System and the Build Programme: A Presentation to the Media

Update on the Power System and the Build Programme: A Presentation to the Media JOH-ESK010-20080520-JvW-P1 Update on the Power System and the Build Programme: A Presentation to the Media Jacob Maroga, Chief Executive, Eskom Holdings Ltd 23 January 2009 Power System - update JOH-ESK010-20080520-JvW-P1

More information

Solar PV resource for higher penetration through a combined spatial aggregation with wind

Solar PV resource for higher penetration through a combined spatial aggregation with wind Solar PV resource for higher penetration through a combined spatial aggregation with wind Dr. Tobias Bischof-Niemz, Crescent Mushwana, Stephen Koopman 6DO.5.2 EU PVSEC 2016, 20-24 June, Munich, Germany

More information

Derisking Renewable Energy Investment

Derisking Renewable Energy Investment Derisking Renewable Energy Investment A framework to support policymakers in selecting public instruments to promote renewable energy investment in developing countries CESC Webinar 12 June 2013 Andre

More information

Integrated Energy Challenge

Integrated Energy Challenge Integrated Energy Challenge Energy System Overview Transition Challenges 9 December 214 Jeff Douglas Energy Technologies Institute 214 Energy Technologies Institute LLP The information in this document

More information

Wild Horse Solar Photovoltaic Project

Wild Horse Solar Photovoltaic Project Wild Horse Solar Photovoltaic Project Steven J. St.Clair Manager Renewable Assets Phone: 425-462-3057 Email: steven.stclair@pse.com November 19, 2009 Agenda Introduction PSE Renewable Energy Facilities

More information

White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016

White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016 White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016 1 Content 1. Project Status 2. Early Works 3. Modification Application 4. Expected Program 5. Project Organisation

More information

PROCUREMENT HANDBOOK

PROCUREMENT HANDBOOK PROCUREMENT HANDBOOK BUSINESS STREAMLINED The East London Industrial Development Zone SOC Ltd is the operator of the East London Industrial Development Zone (ELIDZ), a multimillion-rand infrastructure

More information

How to stimulate the South African rooftop PV market without putting municipalities financial stability at risk A Net Feed-in Tariff proposal

How to stimulate the South African rooftop PV market without putting municipalities financial stability at risk A Net Feed-in Tariff proposal How to stimulate the South African rooftop PV market without putting municipalities financial stability at risk A Net Feed-in Tariff proposal Radisson Blu Hotel: Sandton 29 September 2015 Dominic Milazi

More information

PV energy A key energy source for a power system with a high share of RES

PV energy A key energy source for a power system with a high share of RES PV energy A key energy source for a power system with a high share of RES 24th European Photovoltaic Solar Energy Conference, Hamburg September 23rd, 2009 M.Sc. Dipl.-Ing. Yves-Marie Saint-Drenan (y.saint-drenan@iset.uni-kassel.de)

More information

A E Solution Utility & Municipal Energy Services. Reg no 2007/ /07

A E Solution Utility & Municipal Energy Services. Reg no 2007/ /07 SMART BUSINESS CASE FOR PHOTO VOLTAIC PANELS Solar Energy available in South Africa 2x10 Perceptions exist in South Africa that renewable energy is only suitable for small-scale scale applications, where

More information

Understanding Your Own Renewable Energy Opportunity

Understanding Your Own Renewable Energy Opportunity Understanding Your Own Renewable Energy Opportunity Community Energy Learning Series (CELs) March 1 st, 2017 Kieran O Neill MSc. CEA Smart Energy Business Strategist Sault Ste. Marie Innovation Centre

More information

Enel Green Power. Clean Energy Summit. Gu Yoon Chung, Head of Business Development for Asia and Pacific area. Sydney, July 27 th 2016

Enel Green Power. Clean Energy Summit. Gu Yoon Chung, Head of Business Development for Asia and Pacific area. Sydney, July 27 th 2016 Enel Green Power Clean Energy Summit Gu Yoon Chung, Head of Business Development for Asia and Pacific area Sydney, July 27 th 2016 Enel today 1 Italy North America Capacity: 2.5 GW Capacity: 30.7 GW Networks:

More information

Future wind deployment scenarios for South Africa

Future wind deployment scenarios for South Africa Future wind deployment scenarios for South Africa CSIR Energy Centre WindAc Africa, 4-5 November 7 Cape Town, South Africa Dr Tobias Bischof-Niemz Chief Engineer Jarrad G. Wright JWright@csir.co.za Joanne

More information

Renewable Energy Tracker TM

Renewable Energy Tracker TM If you want to know the true price of renewable energy in America free from subsidies and mandates look to Mexico - former Energy Secretary Steven Chu Issue 1, June 2016 Contents IPD s Pick of the Month

More information

Building a sustainable world

Building a sustainable world Building a sustainable world INDEX About Bester Introduction History Organizational Chart Team Locations Why Bester? Value Chain Comprehensive Vision Key Highlights Growing Bester Worldwide Projects About

More information

BIGEN AFRICA CORPORATE PROFILE >> Page 1. Corporate Profile

BIGEN AFRICA CORPORATE PROFILE >> Page 1. Corporate Profile BIGEN AFRICA CORPORATE PROFILE >> Page 1 Corporate Profile BIGEN AFRICA CORPORATE PROFILE >> Page 2 BIGEN AFRICA CORPORATE PROFILE >> Page 3 BIGEN AFRICA CORPORATE PROFILE >> Page 4 BIGEN AFRICA s smarter

More information

Overview on Nuclear Power in the World

Overview on Nuclear Power in the World Part 1 Overview on Nuclear Power in the World World Nuclear Power Nuclear Power Generation Prospects of Nuclear Power Europe 197 units Asia 111 units Korea 21 units North America 122 units Africa 2 units

More information

Solar-PV in South Africa

Solar-PV in South Africa Solar-PV in South Africa MARKET UPDATE AND PROJECTS MAP 0 REIPPP UPDATE PROJECT LISTINGS DIRECT NORMAL IRRADIATION DATA MAP PV Project Development Summit Africa - August, Johannesburg Identify PV project

More information

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL DEA ref: 14/12/16/3/3/1/619 MOTIVATION FOR AMENDMENT OF ENVIRONMENTAL AUTHORISATION March 2014 Prepared for: Navosync (Pty) Ltd Suite 103 Dixon Street, Cape

More information

India: Perspectives on the Draft National Wind-Solar Hybrid Policy

India: Perspectives on the Draft National Wind-Solar Hybrid Policy India: Perspectives on the Draft National Wind-Solar Hybrid Policy June 8, 2018 Asia Clean Energy Forum Panel on Renewable Energy Auctions Gu-Yoon Chung Head of Business Development Asia Pacific Enel Green

More information

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES Jay Govender - National Practice Head - Projects and Infrastructure Cliffe Dekker Hofmeyr South Africa STRUCTURE OF PRESENTATION Regulatory Overview

More information

Regulatory Framework PPAs and IPPs

Regulatory Framework PPAs and IPPs Regulatory Framework PPAs and IPPs Perspectives from an IPP African Forum for Utility Regulators Workshop on Regulation 7 December 2016 Agenda Enel Group Overview Introduction to EGP Electricity Policy

More information

Implementation Status & Results Jordan Promotion of a Wind Power Market (P093201)

Implementation Status & Results Jordan Promotion of a Wind Power Market (P093201) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Jordan Promotion of a Wind Power Market (P9321) Operation Name: Promotion of a Wind Power Market

More information

High-renewables scenarios Thought experiments for the South African power system

High-renewables scenarios Thought experiments for the South African power system High-renewables scenarios Thought experiments for the South African power system CSIR Energy Centre Pretoria, 22 August 216 Dr Tobias Bischof-Niemz Chief Engineer Dr Tobias Bischof-Niemz Cell: +27 84118

More information

Amended BBBEE Construction Sector Code

Amended BBBEE Construction Sector Code Amended BBBEE Construction Sector Code Who does it apply to? The Amended B-BBEE Construction Sector Code was gazetted on 01 December 2017 with immediate effect. Those who already have an Amended DTI Code

More information

Renewables investment boost in a global uncertain context

Renewables investment boost in a global uncertain context Renewables investment boost in a global uncertain context 31/3/217 Claudio Machetti 1 Technology cost reduction Cost evolution for selected technologies 28-216 12 Index 28 = 1 8 6 4 2 Upstream oil & gas

More information

B-BBEE contributor status. Level One Contributor. Level Two Contributor. Level Three Contributor. Level Four Contributor. Level Five Contributor

B-BBEE contributor status. Level One Contributor. Level Two Contributor. Level Three Contributor. Level Four Contributor. Level Five Contributor BEE ALERT 18 October 2012 REVISED BROAD-BASED BLACK ECONOMIC EMPOWERMENT CODES OF GOOD PRACTICE On 5 October 2012, the Revised Codes of Good Practice were published in the Government Gazette, for public

More information

Least-cost electricity mix for South Africa by 2040 Scenarios for South Africa s future electricity mix

Least-cost electricity mix for South Africa by 2040 Scenarios for South Africa s future electricity mix Least-cost electricity mix for South Africa by 4 Scenarios for South Africa s future electricity mix CSIR Energy Centre Cape Town, 3 November 16 Jarrad Wright Dr Tobias Bischof-Niemz Joanne Calitz Crescent

More information

Renewable Energy in Albania

Renewable Energy in Albania Renewable Energy in Albania National Agency of Natural Resources Artan Leskoviku,Head of RES Workshop: Renewable Energy UNDA project conclusions and way forward 13-14 December 2017, Lancaster Plaza Hotel,

More information

Financial Costs and Benefits of Renewables in South Africa in February 2015

Financial Costs and Benefits of Renewables in South Africa in February 2015 Financial Costs and Benefits of Renewables in South Africa in 10 February 2015 Date of first release: 21 January 2015 Document Reference Number: CSIR/02400/RD Core/IR/2015/0001/B Author Contact Details:

More information

Renewable Energy in The Netherlands

Renewable Energy in The Netherlands Renewable Energy in The Netherlands Dr. Martien Visser Professor Energy Transition & Network Integration Hanze University of Applied Sciences Groningen Partner of the Energy Academy Europe E-mail: b.m.visser@pl.hanze.nl

More information

The Winds of Change are Blowing

The Winds of Change are Blowing The Business Chamber Renewable Energy Task Team Initiative The Winds of Change are Blowing A provincial perspective on the proposed, planned and approved Energy developments in the Eastern Cape A Nelson

More information

CSP Market Status. Solar Thermal Energy Research Group. Alberto Cuellar. Senior Renewable Energy Engineer Mott MacDonald

CSP Market Status. Solar Thermal Energy Research Group. Alberto Cuellar. Senior Renewable Energy Engineer Mott MacDonald CSP Market Status Solar Thermal Energy Research Group Alberto Cuellar Senior Renewable Energy Engineer Mott MacDonald Source: GE Energy Financial Services Contents 1. Introduction to Mott Macdonald 2.

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Andhra Pradesh Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports

More information

State of the Power System Quarterly Update. Winter Outlook. 5 June Collin Matjila Interim Chief Executive

State of the Power System Quarterly Update. Winter Outlook. 5 June Collin Matjila Interim Chief Executive State of the Power System Quarterly Update 5 June 2014 Winter Outlook Collin Matjila Interim Chief Executive Overview Pre-winter Overview Winter Outlook IPPs and New Build Conclusion 2 Overview Eskom load

More information

CRACKING THE CODES March 2017 Peter Ross and Nicole Copley

CRACKING THE CODES March 2017 Peter Ross and Nicole Copley BBBEE for Education NGOs CRACKING THE CODES March 2017 Peter Ross and Nicole Copley Finding our way: CRACKING THE CODES March 2017 Peter Ross and Nicole Copley To B-BBEE or to BEE? Basic Concepts and Definitions

More information

Heat and the Smart Energy System

Heat and the Smart Energy System Heat and the Smart Energy System Jeff Douglas Energy Technologies Institute Heat and the Smart Energy System 1. Why is Heat Important? 2. Meeting National Emissions Targets 3. Developing Power Networks

More information

Solar power: The African Opportunity

Solar power: The African Opportunity NATIONAL CLEANER PRODUCTION CENTRE SOUTH AFRICA Solar power: The African Opportunity Technical Workshop: Solar SOS Africa Utility Week, May 16th 2018 Sashay Ramdharee Regional Project Manager www.ncpc.co.za

More information

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewable curtailment in China All ready to generate but no place to go RE curtailment in China TWh 100 90 80 70 60

More information

MADHU SHARMA University of Petroleum and Energy Studies, Dehradun, India

MADHU SHARMA University of Petroleum and Energy Studies, Dehradun, India ASSESSMENT OF EXISTING RENEWABLE ENERGY REGULATIONS OF UTTARAKHAND AND FINDING OUT THE LOOPHOLES IN THE REGULATIONS ABHISHEK PANDEY, abhilal26@gmail.com MADHU SHARMA madhusharma@ddn.upes.ac.in KN DINESH

More information

TransCanada Power Market Update January 2018

TransCanada Power Market Update January 2018 Forward Prices Table TransCanada Flat 7x24 ($/MWh) AB - 6x16 On Peak ($/MWh) AB - Off-Peak ($/MWh) AECO Gas ($/GJ) Heat Rate BOM $42. $49.56 $32.76 $1.78 23.6 February $39.75 $46.51 $31.1 $1.69 23.5 218

More information

Leading Insights into Solar

Leading Insights into Solar Leading Insights into Solar Fong Wan Senior Vice President, Energy Procurement Pacific Gas and Electric Company CalSEIA - SolarTech Summit May 7, 2009 Agenda California s Clean Energy History Renewable

More information

SOCIAL IMPACT ASSESSMENT FOR

SOCIAL IMPACT ASSESSMENT FOR SOCIAL IMPACT ASSESSMENT FOR BOITSHOKO SOLAR (RF) (PTY) LTD ENERGY FACILITY NORTHERN CAPE PROVINCE April 2016 Prepared for Boitshoko Solar (RF) (Pty) Ltd By Leandri Kruger EXECUTIVE SUMMARY INTRODUCTION

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

DRAFT SMME POLICY FOR EMNAMBITHI LADYSMITH MUNICIPALITY

DRAFT SMME POLICY FOR EMNAMBITHI LADYSMITH MUNICIPALITY DRAFT SMME POLICY FOR EMNAMBITHI LADYSMITH MUNICIPALITY 1. LEGAL FRAMEWORK Broad-Based Black Economic Empowerment Act 53 of 2003 of the Employment Equity Act 55 of 1998; Preferential Procurement Policy

More information

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5 CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey

More information

SOUTH AFRICA ESKOM BATTERY STORAGE PROGRAM

SOUTH AFRICA ESKOM BATTERY STORAGE PROGRAM SOUTH AFRICA ESKOM BATTERY STORAGE PROGRAM ESMAP Solar Learning Event 2019 February 04, 2019 Eskom Kevin Chetty World Bank Frederic Verdol 1 Eskom Early on Management of Increased Renewable Energy Capacity

More information

JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES

JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES ENERGY TRANSPARENCY 2013 ALI IZADI 20 JUNE 2013 /// Energy / / Transparency, Tokyo, / / 20 / June / / 2013 / / / 1 JAPAN ELECTRICITY CONSUMPTION INTENSITY

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Rajasthan Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include

More information

Manitoba Hydro - Power Plants and SWOT Analysis, 2011 Update

Manitoba Hydro - Power Plants and SWOT Analysis, 2011 Update Manitoba Hydro - Power Plants and SWOT Analysis, 2011 Update #43357 $1000 53 pages In Stock Report Description The report contains the profile of the company that is involved in the field of power generation

More information

Overview of Calls in the H2020 Work Program Energy

Overview of Calls in the H2020 Work Program Energy Overview of Calls in the H2020 Work Program Energy 2018 2020 Selected topics for discussion in Hermes Partnership The Work program is still tentative and not for publication, based on draft version May

More information

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Suite 2B, 08 Arnold Road, Rosebank, 2196, Johannesburg, South Africa Tel: +27 11 447 9852; Website: http://www.espcg.com Transaction advisory

More information

Balancing Supply and Demand in the Energy System

Balancing Supply and Demand in the Energy System Balancing Supply and Demand in the Energy System Alex Buckman Strategy Analyst All Energy 11 th May 2017 2017 Energy Technologies Institute LLP The information in this document is the property of Energy

More information

Presentation to FAO / NAMC / WCDA / US workshop. 6 October 2009

Presentation to FAO / NAMC / WCDA / US workshop. 6 October 2009 Presentation to FAO / NAMC / WCDA / US workshop 6 October 2009 Outline ECIAfrica (Pty) Ltd) Target groups and sub-sector knowledge ECI experience ECI methodology Proposal development ECIAfrica Mission

More information

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS Edwin Castro CNEE Guatemala Viena, september 2009 What is the reason to develop this model? In our own electricity market

More information

Quantifying the capital requirement: 19% RE by 2030

Quantifying the capital requirement: 19% RE by 2030 Shutterstock WWF RE Vision 2030 Quantifying the capital requirement: 19% RE by 2030 Megan Sager, Consulting for Sustainable Solutions 29 August 2014 Presentation at IDC Offices Overview Government plans

More information

Paschal Phelan fulfils the promise of jobs in De Aar, and his Renewable Energy leadership has paid off for the local community.

Paschal Phelan fulfils the promise of jobs in De Aar, and his Renewable Energy leadership has paid off for the local community. Solar Capital (Pty) Ltd MEDIA RELEASE Feb 4th 2014 Paschal Phelan fulfils the promise of jobs in De Aar, and his Renewable Energy leadership has paid off for the local community. The Phelan response to

More information

Technical and Vocational Education & Training (TVET) Reform Project. Phase 1 Workplan (Dec 2007 Dec 2009)

Technical and Vocational Education & Training (TVET) Reform Project. Phase 1 Workplan (Dec 2007 Dec 2009) Technical and Vocational Education & Training (TVET) Reform Project Workplan (Dec 2007 Dec 2009) Government of Bangladesh (GOB) European Commission (EC) International Labour Organisation (ILO) July 2008

More information

MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS

MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS MONITORING RENEWABLE ENERGY PERFORMANCE OF POWER PLANTS Tracking progress of 2017 (Issue 11) March 2018 Contents Glossary of Terms and Abbreviations... 3 GLOSSARY... 3 ABBREVIATIONS... 4 1. Rationale of

More information

Energy Use in Ontario

Energy Use in Ontario Every Joule Counts - Ontario s Energy Use and Conservation Year in Review Chapter Energy Use in Ontario Contents Abstract....17.1 Overall Energy Use Changes...18. Fuel-by-Fuel Use Changes...0..1 Transportation

More information