1 Guest Speaker: Bill Frietsche US EPA 1

2 April 7: QA Systems, EPA definitions, PQAOs and common sense Mike Papp April 14: Routine Quality Control and Data Management (1-pt QC, flow rate, and instrument stability checks) Travis Maki April 21: Audits Overview (NPAP, PEP, Annual PE, Flow Rate Audits) Jeremy Howe April 28: Calculating Bias and Precision and AQS reports Bill Frietsche May 5: 40 CFR 58 App. A- Gaseous Pollutants Glenn Gehring May 12: 40 CFR 58 App. A- Ozone Brenda Jarrell May 19: 40 CFR 58 App. A- PM filter and continuous methods Brandy Toft 2

3 the difference between your answer and the truth th Two components of total error (accuracy): Bias (jump) Precision (wiggle) 3

4 Some imprecision is unavoidable Sometimes up, sometimes down random Difference divided by best estimate of the truth truth is: For gas QC checks: known conc. For PM flow rate: audit (known) FR For PM2.5 collocated: their average 4

5 d i = the difference between a known value and Repeated measurement of the same thing your value (flow rate, conc., voltage, that should remain the Sequence of check k(date, time, same) check number) 5

6 Pairs of simultaneous measurements (collocated instruments) d i (difference between collocated values) date 6

7 Can be sudden or due to slow drift over time: d i = the difference between the true value (audit value) and the analyzer date 7

8 Includes both bias and precision At any one time, an audit value could be close to the analyzer value due to precision errors in both Or, audit value could be far from analyzer value due to precision errors adding Audits estimate Accuracy EPA uses audit results to verify that ongoing QC checks do represent total error 8

9 Auditor s see only one day, while your QC checks see overall big picture 9

10 1-pt QC checks no longer called precision checks, because the results are used (by YOU) to calculate both precision and to estimate total error Each check <= 7% is the CRITICAL criteria for each set of data since last passing check The audits basically verify your precision and bias that have been calculated all along from your QC checks (concentration and flow rate, for PM) 10

11 Method Pollutants Frequency MQO One-Point QC SO 2, NO 2, Every 2 O 3 : SO 2, NO 2, CO : O 3, CO Weeks Precision = Precision = 7% 10% Flow Rate Verification (QC check) Flow Rate Verification (QC check) Collocated Sampling PM 10 (lo- Vol) PM 2.5 PM 10 (high- Vol), TSP PM 10, TSP, PM 2.5 Once every 4 weeks Once per quarter 15% of Network Every 12 Days <= 4% of Standard <= 7% of Standard Precision CV= 10% (which means RPD =14%) *and total error, more on this later. 11

12 Estimates your overall system uncertainty, if you were perfectly calibrated Changes over time can point to operator error, lab error, poorly written procedures, equipment/standards going bad Changes can be fixed sooner rather than at audit EPA compares precision by site and agency 12

13 Useful to track precision (or bias) over time d i See this example (and you fill in your values) at: Another example in the DASC tool: 13

14 The DASC tool automatically writes your values from the columns into the chart: Measured value is your analyzer Audit value is the known d i You may want tto add dddates to the x-axis, or use my example if you want to set up control charts 14 in your program

15 In their annual QA reports, from your RP transactions in AQS: html d i 15

16 Recommendations in redbook say: Critical criteria invalidate every hour that is not met Operational criteria i means something probably wrong, go check it Systematic criteria mean as a set (day? year?) data is not usable for NAAQS, but individual hours or more may be valid 16

17 (NO2 and SO2 are the same) 17

18 Method Pollutants t Frequenc MQO y Flow Rate PM 10 (lo- Once <= 4% of Standard Verification (QC check) Vol), PM 2.5 every 4 weeks Flow Rate PM 10 (high- Once per <= 7% of Standard Verification (QC check) Vol), TSP quarter 18

19 Method Pollutants t Frequency MQO Collocated Sampling PM 10, TSP, PM % of Network Every 12 Days Precision as CV < = 10% (meaning the relative percent diff must be less than 14% for conc > 3 ug/m3) X i Y i d i 100 ( X i Y i ) 2 19

20 Keep the bias component minimized by calibrating and verifying your equipment against a standard d Keep precision component low by consistency You can work to keep bias down, while precision is often out of your control below a certain limit EPA calculates from your RA transactions meas audit d 100 i audit 20

21 Method Pollutants Frequency MQO Annual Performance Evaluation (Audit) SO 2, NO 2, O 3, Once per <= 15% for each audit CO Year concentration OPERATIONAL Semi-Annual Flow PM 10, PM 2.5 Every 6 <= 4% of Standard Rate Audit Months OPERATIONAL Semi-Annual Flow Rate Audit PM 10 (high- Vol), TSP Every 6 Months <= 10% of Standard OPERATIONAL PM 2.5 PEP Program NPAP PM 2.5 SO 2, NO 2, O 3, CO Quarter Year (see QA Requireme nts.xls) Bias = 10% -- OPERATIONAL 21

22 Bias: systematic difference, or jump Precision: random error, or wiggle Accuracy = total error, a combination of both Simple temp bath illustrations at: A101_Resources/AllDownloadableMovies/ 22

23 DASC (Data Assessment Statistical Calculator) l s/qa101_resources/dasc%20epa%20prec / %20and%20Bias%20Calculator/ AQS: Data Quality Indicators Report (AMP255) 23

24 Minimize bias by regular calibrations both accuracy (total error) and precision are first estimated by d i on an ongoing basis, by you Audits verify total error estimates Course website: p// p p / p_ /Q A101_Resources/ Our s: Bill Frietsche: fi frietsche.bill@epamail.epa.gov il Melinda.ronca-battista@nau.edu Christopher.lee@nau.edu 24

25

26 Appendix A to Part 58 Table A-2 of App A AQS TTN web site AQSP&A Spreadsheet Discoverer AMTIC web site AQS Helpline AQS AMP255 Data Quality Indicator Report

27 Appendix A to Part 58 Regulations that define QA reporting requirements for criteria pollutants Define assessments for each criteria pollutant 1 Pt QC check for gases Annual performance evaluation for gases Flow rate verification for particulate matter Semi-annual flow rate audit for particulate t matter Collocated sampling requirements for particulate matter Pb audit strips for laboratory analysis QA Performance Evaluation Program for PM fine, PM coarse, and Pb Formerly called precision and accuracy data still use these terms on AQS transactions

28 This document available at: ep. ep_downloads/qa101oads/q _ Resources/session%204- o prec%20&%20bias/ Table A-2 of Appendix A to Part 58--Minimum Data Assessment Requirements for SLAMS Sites Method Assessment method Coverage Minimum Parameters Frequency reported Automated Methods Response check at 1-Point QC for SO2, NO2, O3, CO concentration Once per 2 Audit concentration 1 and measured Each analyzer ppm SO2, NO2, O3, and 1- weeks.. concentration ppm CO Annual performance evaluation for SO2, See section of this Audit concentration 1 and measured Each analyzer Once per year NO2, O3, CO appendix concentration 2 for each level. Flow rate verification PM10 Check of sampler flow rate Each sampler Once every Audit flow rate and measured flow rate month indicated by the sampler. Flow rate verification PM2.5, Once every Audit flow rate and measured flow rate Check of sampler flow rate Each sampler PM month indicated by the sampler. Check of sampler flow rate Semi-annual flow rate audit Once every 6 Audit flow rate and measured flow rate using independent Each sampler PM10, PM2.5, PM months indicated by the sampler. standard. Collocated sampling PM2.5, PM Performance evaluation program PM2.5, PM Collocated sampling PM10, TSP, PM10-2.5, PM2.5, Pb-TSP, Pb-PM10. Flow rate verification PM10 (low Vol), PM10-2.5, PM2.5, Pb- PM10 Flow rate verification PM10 (High-Vol), TSP, Pb-TSP Semi-annual flow rate audit PM10, TSP, PM10-2.5, PM2.5, Pb-TSP, Pb-PM10. PM10 Pb audit strips Pb-TSP, Pb-PM10 Performance Evaluation Program PM2.5, PM Performance Evaluation Program Pb- TSP, Pb-PM10 Collocated samplers. 15% Every 12 days Collocated samplers. Collocated samplers. 15% Check of sampler flow rate. Check of sampler flow rate. Check of sampler flow rate using independent standard. d Check of analytical system with Pb audit strips. Collocated samplers. Collocated samplers. 1) 5 valid audits for primary QA orgs, with <= 5 sites. 2) 8 valid audits for primary QA orgs, with > 5 sites. 3) All samplers in 6 years Each sampler Each sampler Each sampler, all locations. Analytical. 1) 5 valid audits for primary QA orgs, with <= 5 sites. 2) 8 valid audits for primary QA orgs, with > 5 sites. 3) All samplers in 6 years 1) 1 valid audit and 4 collocated samples for primary QA orgs, with <=5 sites. 2) 2 valid audits and 6 collocated samples for primary QA orgs with > 5 sites. Over all 4 quarters Manual Methods Every 12 days PSD--every 6 days. Once every month Once every quarter Once every 6 months. Each quarter. Over all 4 quarters Over all 4 quarters Primary sampler concentration and duplicate sampler concentration. Primary sampler concentration and performance evaluation sampler concentration. AQS Trans Type RP Reqd Reporting to AQS Y RA Y RP Y RP N RA Y RP Y RP Y Primary sampler concentration and 3 RP (or RD) Y duplicate sampler concentration. Audit flow rate and measured flow rate indicated by the sampler. Audit flow rate and measured flow rate indicated by the sampler. Audit flow rate and measured flow rate indicated by the sampler Actual mass and audit mass for parameters: Pb (TSP) LC FRM/FEM Pb (TSP) LC Non-FRM/FEM Primary sampler concentration and performance evaluation sampler concentration. Primary sampler concentration and performance evaluation sampler concentration. Primary sampler concentration and duplicate sampler concentration. 1 Effective concentration for open path analyzers. 2 Corrected concentration, if applicable, for open path analyzers. 3 Precision data is system generated when raw data is submitted for both collocated monitors for same date-time, and monitor ids are populated on monitor collocation record in AQS. Gaseous Parameter Codes Particulate Parameter Codes RP N RP N RA Y RA Y RP Y RP Y

29 AQS TTN web site AQSP&A Spreadsheet AQS Discoverer AMTIC web site AQS Help Line EPA (4372)

30 Example run of AMP255 shown onscreen

31 All QC data helps EPA balance your costs of QC with needed information to protect health Questions to AQS are welcomed EPA committed to improving user friendliness Course website: A101_Resources/ Our s: Bill Frietsche: epa 31

Data Certification Exercise

Data Certification Exercise Data Certification Exercise PQAO Training January 25 th, 2017 Objective: The data certification process involves certifying that ambient concentration data and quality assurance data for any given year

More information

Quality Assurance - Audit Issues and Expectations

Quality Assurance - Audit Issues and Expectations Quality Assurance - Audit Issues and Expectations Mike Papp Office of Air Quality Planning and Standards MARAMA Air Monitoring Meeting December 10, 2014 1 Recent Data Validation Issues Hayden AZ- No approved

More information

Air Monitoring Data Quality Assessment Report Fourth Quarter Prepared by: Donovan Rafferty. Air Quality Program

Air Monitoring Data Quality Assessment Report Fourth Quarter Prepared by: Donovan Rafferty. Air Quality Program Air Monitoring Data Quality Assessment Report Fourth Quarter Prepared by: Donovan Rafferty Air Quality Program TABLE OF CONTENTS Introduction... 1 Data Quality... 2 Automated Data... 3 Data Quality Indicators

More information

OAQPS Update. Outline. Kevin A Cavender EPA/OAQPS/AAMG. MARAMA Monitoring Meeting September 17, 2012

OAQPS Update. Outline. Kevin A Cavender EPA/OAQPS/AAMG. MARAMA Monitoring Meeting September 17, 2012 OAQPS Update Kevin A Cavender EPA/OAQPS/AAMG MARAMA Monitoring Meeting September 17, 2012 1 Outline Selected NAAQS Updates Notable monitoring program issues Quality Assurance Topics 2 1 NAAQS Summary Table

More information

2013 ANNUAL AIR MONITORING NETWORK PLAN CHECKLIST (Updated 2/27/2013) Year: Agency:

2013 ANNUAL AIR MONITORING NETWORK PLAN CHECKLIST (Updated 2/27/2013) Year: Agency: 2013 ANNUAL AIR MONITORING NETWORK PLAN CHECKLIST (Updated 2/27/2013) Year: Agency: 40.10(a)(1) requires that each ANP include regarding the following types of monitors: SLAMS monitoring stations including

More information

Validation of CSN Data

Validation of CSN Data Validation of CSN Data US EPA Region 3 Air Monitoring Quality Assurance Workshop June 25, 2014 Dennis Crumpler and Beth Landis US Environmental Protection Agency Office of Air Quality Planning and Standards

More information

Ambient Air Quality Monitoring

Ambient Air Quality Monitoring Ambient Air Quality Monitoring Ambient Air Quality Division Air Quality and Noise Management Bureau Pollution Control Department 7/31/2012 2:09 PM 1 Carbon Monoxide (CO) Nitrogen Dioxide (NO 2 ) Ozone

More information

2017 Annual Network Plan for Ambient Air Monitoring

2017 Annual Network Plan for Ambient Air Monitoring 2017 Annual Network Plan for Ambient Air Monitoring July 1, 2017 North Coast Unified Air Quality Management District 707 L Street, Eureka, CA 95501 Telephone (707) 443-3093 - FAX (707) 443-3099 http://www.ncuaqmd.org

More information

2018 Annual Network Plan for Ambient Air Monitoring

2018 Annual Network Plan for Ambient Air Monitoring 2018 Annual Network Plan for Ambient Air Monitoring July 1, 2018 North Coast Unified Air Quality Management District 707 L Street, Eureka, CA 95501 (707) 443-3093 www.ncuaqmd.org Contents Contents... 2

More information

PM 2.5 Continuous Monitoring. Program Objectives, History, Requirements, and Flexibility. National Ambient Air Monitoring Conference Atlanta 2014

PM 2.5 Continuous Monitoring. Program Objectives, History, Requirements, and Flexibility. National Ambient Air Monitoring Conference Atlanta 2014 PM 2.5 Continuous Monitoring Program Objectives, History, Requirements, and Flexibility National Ambient Air Monitoring Conference Atlanta 2014 1 Program Objectives, History, Requirements, and Flexibility

More information

SOP OPERATION OF PARTICULATE MATTER INSTRUMENTS CLARK COUNTY DEPARTMENT OF AIR QUALITY. Monitoring Division PROCEDURE NUMBER 400

SOP OPERATION OF PARTICULATE MATTER INSTRUMENTS CLARK COUNTY DEPARTMENT OF AIR QUALITY. Monitoring Division PROCEDURE NUMBER 400 SOP OPERATION OF PARTICULATE MATTER INSTRUMENTS CLARK COUNTY DEPARTMENT OF AIR QUALITY Monitoring Division PROCEDURE NUMBER 400 STANDARD OPERATING PROCEDURE FOR Particulate Matter Instruments Revision

More information

Statistics for Quality Assurance of Ambient Air Monitoring Data

Statistics for Quality Assurance of Ambient Air Monitoring Data Statistics for Quality Assurance of Ambient Air Monitoring Data Prepared by Will Shuart, M.S. For the Mid-Atlantic Regional Air Management Association And the U.S. Environmental Protection Agency With

More information

Evaluation of methods for analysis of lead in air particulates: An intra-laboratory and interlaboratory

Evaluation of methods for analysis of lead in air particulates: An intra-laboratory and interlaboratory Evaluation of methods for analysis of lead in air particulates: An intra-laboratory and interlaboratory comparison Frank X. Weber, James M. Harrington, Andrea McWilliams, Keith E. Levine Trace Inorganics

More information

QUALITY ASSURANCE PROJECT PLAN FOR THE STATE OF FLORIDA AMBIENT AIR QUALITY LEAD MONITORING PROGRAM

QUALITY ASSURANCE PROJECT PLAN FOR THE STATE OF FLORIDA AMBIENT AIR QUALITY LEAD MONITORING PROGRAM QUALITY ASSURANCE PROJECT PLAN FOR THE STATE OF FLORIDA AMBIENT AIR QUALITY LEAD MONITORING PROGRAM Prepared For: US EPA Region 4 Submitted by The Florida Department of Environmental Protection 2 TABLE

More information

NOy Monitoring Issues and Auditing

NOy Monitoring Issues and Auditing NOy Monitoring Issues and Auditing MARAMA Monitoring Meeting September Kevin A. Cavender EPA/OAR/OAQPS U.S. Environmental Protection Agency 1 Objectives Review NOy monitoring network Review chronology

More information

NOy Monitoring Issues and Auditing

NOy Monitoring Issues and Auditing NOy Monitoring Issues and Auditing MARAMA Monitoring Meeting September Kevin A. Cavender EPA/OAR/OAQPS U.S. Environmental Protection Agency 1 Objectives Review NOy monitoring network Review chronology

More information

QUALITY ASSURANCE PROJECT PLAN (QAPP)

QUALITY ASSURANCE PROJECT PLAN (QAPP) Page 1 of 109 QUALITY ASSURANCE PROJECT PLAN (QAPP) FOR AMBIENT AIR QUALITY MONITORING OF CRITERIA AIR POLLUTANTS 9/5/17 SUBMITTED BY THE FORSYTH COUNTY OFFICE OF ENVIRONMENTAL ASSISTANCE AND PROTECTION

More information

2016 NWDO AIR MONITORING SITES

2016 NWDO AIR MONITORING SITES 2016 NWDO AIR MONITORING SITES Map/AQS # Site Name PM2.5 PM2.5CONT. PM10 O3 SO2 CO NO2 TOXICS PM2.5CSPE Pb/metals 1. 39-003-0009 Lima Bath HS x* x x x 2. 39-051-0001 Delta x* 3. 39-173-0003 Bowling Green

More information

Florida Department of Environmental Protection. Field and Lab Audits

Florida Department of Environmental Protection. Field and Lab Audits Florida Department of Environmental Protection Field and Lab Audits What is an Audit? Check that data and processes are of sufficient quality for environmental decision-making Data Quality Objectives (DQOs)

More information

Measurement Uncertainty Guide. ISO Accreditation Program

Measurement Uncertainty Guide. ISO Accreditation Program Measurement Uncertainty Guide ISO 15189 Accreditation Program Background Why This is Necessary The ISO 15189:2012 standard contains enhanced expectations regarding measurement uncertainty (MU) in clause

More information

APPENDIX B. Second Quarter 2010 IML Quality Assurance Audit Report

APPENDIX B. Second Quarter 2010 IML Quality Assurance Audit Report APPENDIX B Second Quarter 2010 IML Quality Assurance Audit Report Energy Fuels Resources Corporation Piñon Ridge Mill Quality Assurance Audit Report for Meteorological and Ambient Air Monitoring Network

More information

APPENDIX F. Fourth Quarter 2009 IML Quality Assurance Audit Report

APPENDIX F. Fourth Quarter 2009 IML Quality Assurance Audit Report APPENDIX F Fourth Quarter 2009 IML Quality Assurance Audit Report Energy Fuels Resources Corporation Piñon Ridge Mill Quality Assurance Audit Report for Meteorological and Ambient Air Monitoring Network

More information

Monitoring for Round 2 Review and Assessment. Sean Christiansen 33 RD IAPSC Conference 4 December 2002

Monitoring for Round 2 Review and Assessment. Sean Christiansen 33 RD IAPSC Conference 4 December 2002 Monitoring for Round 2 Review and Assessment Sean Christiansen 33 RD IAPSC Conference 4 December 2002 Focus of this session: Focus on: Problem areas associated with monitoring during 1 st Round of Review

More information

Audit Report of SIMAT Particle Monitoring Network

Audit Report of SIMAT Particle Monitoring Network Audit Report of SIMAT Particle Monitoring Network Performed 10-12 November, 2014 Prepared for: Prepared by: Dirección de Monitoreo Atmosférico, Secretaría del Medio Ambiente del Distrito Federal George

More information

DAILY LIFE of CEMS QA & PM

DAILY LIFE of CEMS QA & PM DAILY LIFE of CEMS QA & PM Presented at: ENVIRONMENTAL COMMITTEE TECHNICAL FOCUS GROUP December 8, 2015 DANIEL L. TODD, QEP, CHMM OVERALL CONCEPT To provide the perspective of the folks that are responsible

More information

Data Review & Validation QA Plan for Continuous Gaseous & Non- Speciated Particulate Monitors Section IV. Raleigh Central Office Responsibilities

Data Review & Validation QA Plan for Continuous Gaseous & Non- Speciated Particulate Monitors Section IV. Raleigh Central Office Responsibilities Page 1 of 35 Data Review & Validation QA Plan for Continuous Gaseous & Non- Speciated Particulate Monitors Section IV Raleigh Central Office Responsibilities Page 3 of 35 Table of Contents 2.41.4 Data

More information

NYSDEC In-House Discussion: The Implications of Approved Continuous PM 2.5 FEM III Instruments

NYSDEC In-House Discussion: The Implications of Approved Continuous PM 2.5 FEM III Instruments NYSDEC In-House Discussion: The Implications of Approved Continuous 2.5 FEM III Instruments Dirk Felton Bureau of Air Quality Surveillance Sept 22, 2008 NYS Department of Environmental Conservation ARM:

More information

2012 AMBIENT AIR MONITORING NETWORK PLAN

2012 AMBIENT AIR MONITORING NETWORK PLAN 2012 AMBIENT AIR MONITORING NETWORK PLAN Monitoring and Compliance Division July 9, 2012 SLOAPCD 2012 Network Plan - 1-7/9/2012 Table of Contents 1. Introduction... 1 2. Overview of Network Operation...

More information

Preparing for an On-Site Audit

Preparing for an On-Site Audit Preparing for an On-Site Audit Don Simmons, Karen Owens, Jeff Wasson SHL Lab Symposium September 27, 2018 Iowa s Environmental & Public Health Laboratory The Auditor is Coming Common Thoughts on Activities

More information

Method No.: 8.06/2.0/M Effective Date: January 4, 2012 Location: ###

Method No.: 8.06/2.0/M Effective Date: January 4, 2012 Location: ### QSM Approval: National Air Pollution Surveillance (NAPS) Network Reference Method for the Measurement of PM2.5 Concentration in Ambient Air Using Filter Collection and Gravimetric Mass Determination 1.

More information

Quality Assurance / Quality Control (QA / QC)

Quality Assurance / Quality Control (QA / QC) Quality Assurance / Quality Control (QA / QC) DOCUMENTATION DOCUMENTATION Provides a complete history of any sample from initiation to project completion Includes all associated activities Documentation

More information

Verifying the Reliability of EPA Method 314 to Measure Perchlorate at Sub ppb Levels vs New EPA Method Options

Verifying the Reliability of EPA Method 314 to Measure Perchlorate at Sub ppb Levels vs New EPA Method Options Verifying the Reliability of EPA Method 314 to Measure Perchlorate at Sub ppb Levels vs New EPA Method Options Andrew Eaton, Ph.D. MWH Labs Region 6 QA Conference - 10/21/04 Why Do We Care About Accuracy

More information

An End User s Perspective. Aleta Kennard & Janice Lam Snyder PQAO Training, Sacramento/Diamond Bar May 28-29, 2014 June 11-12, 2014

An End User s Perspective. Aleta Kennard & Janice Lam Snyder PQAO Training, Sacramento/Diamond Bar May 28-29, 2014 June 11-12, 2014 An End User s Perspective Aleta Kennard & Janice Lam Snyder PQAO Training, Sacramento/Diamond Bar May 28-29, 2014 June 11-12, 2014 Key Questions: Why is it so important? What if I don t document? What

More information

MARAMA Agency Roundtable Annual Monitoring Committee Training Workshop April 12-13, Allegheny County Health Department (ACHD)

MARAMA Agency Roundtable Annual Monitoring Committee Training Workshop April 12-13, Allegheny County Health Department (ACHD) MARAMA Agency Roundtable Annual Monitoring ommittee Training Workshop April 12-13, 2011 Allegheny ounty Health Department (AHD) Ozone season updates exceedences, issues, monitor updates (location changes

More information

Checklist of Common Critical Data Issues:

Checklist of Common Critical Data Issues: Checklist of Common Critical Data Issues: EPA s Hazardous Air Pollutants for Coal- and Oil-fired Electric Utility Steam Generating Units Information Collection Request This document contains a checklist

More information

Ambient Monitoring in Central Texas Quality Assurance Project Plan

Ambient Monitoring in Central Texas Quality Assurance Project Plan 2010-2011 Ambient Monitoring in Central Texas Quality Assurance Project Plan Prepared by Air Quality Solutions, Inc. (512) 804-2774 2010-2011 Section A1 A1.1 Preface This (QAPP) is submitted as part of:

More information

EPA REGION 8 QA DOCUMENT REVIEW CROSSWALK Entity (grantee, contract, EPA AO, EPA Program, Other)

EPA REGION 8 QA DOCUMENT REVIEW CROSSWALK Entity (grantee, contract, EPA AO, EPA Program, Other) EPA Region 8 QA Document Review Crosswalk Page 1 of 9 QAPP/FSP/SAP for: (check appropriate box) GRANTEE CONTRACTOR EPA Other Document Title [Note: Title will be repeated in Header] EPA REGION 8 QA DOCUMENT

More information

Standard Operating Procedure (SOP) for. Completing the Annual Network Review. for the. North Carolina Division of Air Quality (DAQ) SECTION 2

Standard Operating Procedure (SOP) for. Completing the Annual Network Review. for the. North Carolina Division of Air Quality (DAQ) SECTION 2 Page 1 of 36 Standard Operating Procedure (SOP) for Completing the Annual Network Review for the North Carolina Division of Air Quality (DAQ) SECTION 2 Page 3 of 36 Table of Contents 2.43 Standard Operating

More information

Document Review 1 2 3

Document Review 1 2 3 01 DOCUMENT CONTROL 01 4.3 The current authorized test method and (7.2.1.2) supporting work instructions are available to the analyst. 02 01 5.4 (7.2.1.5) TEST METHOD VERIFICATION/VALIDATION For standard

More information

Gila River Indian Community 2016 AMBIENT AIR MONITORING NETWORK REVIEW

Gila River Indian Community 2016 AMBIENT AIR MONITORING NETWORK REVIEW Gila River Indian Community 2016 AMBIENT AIR MONITORING NETWORK REVIEW GRIC San Tan Mountains to the north, 2016 Gila River Indian Community Department of Environmental Quality Air Quality Air Monitoring

More information

Gordon Pierce WESTAR Spring Business Meeting Boise, ID May 27, 2014

Gordon Pierce WESTAR Spring Business Meeting Boise, ID May 27, 2014 Gordon Pierce WESTAR Spring Business Meeting Boise, ID May 27, 2014 Traditional monitoring approach Permanent fixed sites Meets all US EPA requirements Number of sites Siting Generally neighborhood scale

More information

Measurement Uncertainty Estimates of Collocated CSN and IMPROVE Data for use in calculating a PM 2.5 light

Measurement Uncertainty Estimates of Collocated CSN and IMPROVE Data for use in calculating a PM 2.5 light Measurement Uncertainty Estimates of Collocated CSN and IMPROVE Data for use in calculating a PM 2.5 light extinction indicator 11/2/2011 1 U.S. Environmental Protection Agency Why? It s a good idea to

More information

2018 ANNUAL NETWORK PLAN DIVISION OF NATURAL RESOURCES AND ENVIRONMENTAL MANAGEMENT AMBIENT AIR QUALITY MONITORING PROGRAM CITY OF HUNTSVILLE, ALABAMA

2018 ANNUAL NETWORK PLAN DIVISION OF NATURAL RESOURCES AND ENVIRONMENTAL MANAGEMENT AMBIENT AIR QUALITY MONITORING PROGRAM CITY OF HUNTSVILLE, ALABAMA 2018 ANNUAL NETWORK PLAN DIVISION OF NATURAL RESOURCES AND ENVIRONMENTAL MANAGEMENT AMBIENT AIR QUALITY MONITORING PROGRAM CITY OF HUNTSVILLE, ALABAMA NATURAL RESOURCES AND ENVIRONMENTAL MANAGEMENT Post

More information

recovery and between 0% and 10% relative standard deviation.

recovery and between 0% and 10% relative standard deviation. THE NEED FOR ANALYTICAL QUALITY CONTROL IN ORDER TO MEET EFFLUENT PERMIT REGULATIONS IN THE METAL FINISHING INDUSTRY JEFFREY GLASS LABORATORY MANAGER ENVIROPACT, INC. MIAMI DIVISION 479 NW 157 STREET MIAMI,

More information

Current Developments in Ambient Air Monitoring EPA Information and Perspectives

Current Developments in Ambient Air Monitoring EPA Information and Perspectives Current Developments in Ambient Air Monitoring EPA Information and Perspectives NESCAUM Monitoring Advisory Committee Meeting May 16-17, 2006 Newport, RI Phil Lorang Ambient Air Monitoring Group EPA Office

More information

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR White paper WP/ANALYTICAL/002 EN ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR ABB FTIR CEMS analyzer successfully monitors cement plant stack emissions in extensive field

More information

BISHOP PAIUTE TRIBE ENVIRONMENTAL MANAGEMENT OFFICE AIR QUALITY PROGRAM Revision Tuesday, May 23, 2017

BISHOP PAIUTE TRIBE ENVIRONMENTAL MANAGEMENT OFFICE AIR QUALITY PROGRAM Revision Tuesday, May 23, 2017 QUALITY ASSURANCE PROJECT PLAN Ambient Air Monitoring Program for Measuring PM-10 Using an Automated Tapered Element Oscillating Microbalance (TEOM 1405) BISHOP PAIUTE TRIBE ENVIRONMENTAL MANAGEMENT OFFICE

More information

Medical Electronic Systems QwikCheck Beads Validation and Training Kit

Medical Electronic Systems QwikCheck Beads Validation and Training Kit Medical Electronic Systems www.mes-global.com Medical Electronic Systems QwikCheck Beads Validation and Training Kit OVERVIEW The QwikCheck Beads Validation and Training Kit is designed as a proficiency,

More information

PLEASE SCROLL DOWN FOR ARTICLE

PLEASE SCROLL DOWN FOR ARTICLE This article was downloaded by:[university of Georgia] On: 3 December 2007 Access Details: [subscription number 775682661] Publisher: Taylor & Francis Informa Ltd Registered in England and Wales Registered

More information

Annual Air Monitoring Network Plan Santa Barbara County

Annual Air Monitoring Network Plan Santa Barbara County Annual Air Monitoring Network Plan July 1, 2018 Prepared by the Air Pollution Control District Section Annual Air Monitoring Network Plan For Table of Contents Page 1.0 Introduction... 4 1.1 Network Design...

More information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025 APPROVED: SIGNED DATE: June 14, 2007 Jon Adams Director of Compliance TITLE: SUBJECT: RULE 1080 STACK MONITORING

More information

November Prepared By: :

November Prepared By: : U.S. EPA Region 2 Brownfields Planning Document for Site-Specific Quality Assurance Region 2 Brownfields Quality Assurance Program Prepared By: : U.S. EPA Region 2 Brownfields Quality Assurance Office

More information

WLTP Test Procedures for Chassis Dynamometer Testing. Chris Laroo - U.S. EPA April 14, 2010

WLTP Test Procedures for Chassis Dynamometer Testing. Chris Laroo - U.S. EPA April 14, 2010 WLTP Test Procedures for Chassis Dynamometer Testing Chris Laroo - U.S. EPA April 14, 2010 WLTP-DTP DTP-01-1313 Outline Overview of current US domestic test procedures, WHDC, and NRMM GTR Overview of proposed

More information

Emerging Sensor Technologies

Emerging Sensor Technologies Emerging Sensor Technologies Ron Williams U.S. EPA, RTP, NC WESTAR September 19, 2018 To cover: EPA s Diverse Array of Monitoring Research FEM/FRM Air Toxics Sensors Special purpose monitoring studies

More information

ADEM LTF Contractor QAPP Review Checklist

ADEM LTF Contractor QAPP Review Checklist Title: Proposal Preparer: Date Submitted for Review: Date of Review: ADEM Reviewer: *Review: A= Adequately Addressed U=Unacceptable NI=Not Included NA=Not Applicable A-1.Title and Approval Page 1 Title

More information

Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring

Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring Section I. Introduction DEQ s Air Quality Division administers the provisions of 40 CFR Part 70 as well as the minor

More information

Pebble Project Environmental Baseline Studies Technical Summary. APPENDIX A. Analytical Quality Assurance/Quality Control Review

Pebble Project Environmental Baseline Studies Technical Summary. APPENDIX A. Analytical Quality Assurance/Quality Control Review Pebble Project Environmental Baseline Studies 2004-2008 Technical Summary APPENDIX A. Analytical Quality Assurance/Quality Control Review TABLE OF CONTENTS TABLE OF CONTENTS... A-i ACRONYMS AND ABBREVIATIONS...A-ii

More information

Collaborative Efforts to Implement On Line Analyzer Technology for Regulatory Total Residual Chlorine Monitoring

Collaborative Efforts to Implement On Line Analyzer Technology for Regulatory Total Residual Chlorine Monitoring Collaborative Efforts to Implement On Line Analyzer Technology for Regulatory Total Residual Chlorine Monitoring Stacie Crandall Chief, Laboratory Division scrandall@hrsd.com 757 460 4217 Topics Proposal

More information

Quality System Guidance

Quality System Guidance Page 1 of 16 TABLE OF CONTENTS 1.0 SCOPE... 2 2.0 REFERENCES... 2 3.0 TERMS AND DEFINITIONS... 2 4.0 BACKGROUND... 5 5.0 GUIDANCE ON IMPLEMENTATION... 5 5.1 Choosing Type A or Type B... 6 5.2 General considerations...

More information

Designing QC Activities to More Precisely Manage Analytical Accuracy and Patient Risk

Designing QC Activities to More Precisely Manage Analytical Accuracy and Patient Risk Designing QC Activities to More Precisely Manage Analytical Accuracy and Patient Risk Curtis A. Parvin, Ph.D. Manager of Advanced Statistical Research Bio-Rad Laboratories, QSD curtis_parvin@bio-rad.com

More information

Quality Assurance / Quality Control. Stephanie Sunderman-Barnes DEAR / WQAP / WMS September 2018

Quality Assurance / Quality Control. Stephanie Sunderman-Barnes DEAR / WQAP / WMS September 2018 Quality Assurance / Quality Control Stephanie Sunderman-Barnes DEAR / WQAP / WMS September 2018 DOCUMENTATION DOCUMENTATION Provides a complete history of any sample from initiation to project completion

More information

2017 Ambient Air Monitoring Network Plan

2017 Ambient Air Monitoring Network Plan 2017 Ambient Air Monitoring Network Plan Fiscal, Administrative & Technical Services June 2017 Table of Contents List of Abbreviations... 4 Introduction... 5 General Information on Air Monitoring Networks...

More information

Monitoring cement plant stack emissions using FTIR

Monitoring cement plant stack emissions using FTIR ABB MEASUREMENT & ANALYTICS WHITE PAPER Monitoring cement plant stack emissions using FTIR ABB FTIR CEMS analyzer successfully monitors cement plant stack emissions in extensive field study Measurement

More information

A G. The Avogadro Group, LLC. Air Quality Consulting and Source Emissions Testing

A G. The Avogadro Group, LLC. Air Quality Consulting and Source Emissions Testing A G The Avogadro Group, LLC Air Quality Consulting and Source Emissions Testing ALL THESE TEST RESULTS ARE THE SAME POLLUTANT FROM THE SAME BOILER!! Different test methods CAN = different results! Recent

More information

Overview of the EPA Office of Water s Alternate Test Procedure Program

Overview of the EPA Office of Water s Alternate Test Procedure Program Overview of the EPA Office of Water s Alternate Test Procedure Program g National Environmental Monitoring Conference J. Kevin Roberts, CSC August 15, 2011 Disclaimer Although this presentation has been

More information

Title: Standard Operating Procedure for Measurement of Ozone in Ambient Air by Ultraviolet (UV) Photometry

Title: Standard Operating Procedure for Measurement of Ozone in Ambient Air by Ultraviolet (UV) Photometry Procedure No: SOP-022 Revision No: 1.1 January 27, 2011 Page No.: 1 of 8 1. INTRODUCTION AND SCOPE To obtain timely data for the purpose of air quality assessment, air quality trend reporting, air quality

More information

CONTINUOUS AUDITING - UPDATE. Travis S. Moser, CISA

CONTINUOUS AUDITING - UPDATE. Travis S. Moser, CISA CONTINUOUS AUDITING - UPDATE Travis S. Moser, CISA CONTINUOUS ASSURANCE FRAMEWORK Third Line of Defense: IA provides independent assurance Second Line of Defense: Functions oversee risks First Line of

More information

THE PITFALLS OF DUPLICATE RADON MEASUREMENTS

THE PITFALLS OF DUPLICATE RADON MEASUREMENTS THE PITFALLS OF DUPLICATE RADON MEASUREMENTS Raymond Johnson, Douglas Heim, and Lori Faiola Key Technology, Inc. Jonestown, PA ABSTRACT The EPA radon measurement device protocols recommend duplicate measurements

More information

Laboratory Report This Page is to be Stamped Introduction: This report package contains total of 8 pages divided into 3 sections:

Laboratory Report This Page is to be Stamped Introduction: This report package contains total of 8 pages divided into 3 sections: May 2, 2018 ENVIRONMENTAL AGRICULTURAL City of Lompoc - Water Treatment Plant Lab ID : CC 1881135 Attn: Mary Erland 100 Civic Center Plaza Lompoc, CA 93436 Customer : 8-45 Laboratory Report This Page is

More information

A69 Checklist for Bulk Asbestos Revision 1.2 May 5, 2015

A69 Checklist for Bulk Asbestos Revision 1.2 May 5, 2015 A69 Checklist for Bulk Asbestos Revision 1.2 May 5, 2015 Laboratory Name: Appendix Name: Appendix Number: Assessor: Date: 01 DOCUMENT CONTROL 01 4.3 : is there a documented method? : Verify that the current

More information

Edward F. Askew PhD Askew Scientific Consulting

Edward F. Askew PhD Askew Scientific Consulting Edward F. Askew PhD Askew Scientific Consulting DO YOU KNOW WHAT IT IS?? (Are the Auditors Listening??) Askew Scientific Consulting LLC 2 Requires specific test procedure: Protocol for Review and Validation

More information

Yes, there is going to be some math (but not much) STATISTICAL APPROACH TO MEDICAL DEVICE VERIFICATION AND VALIDATION

Yes, there is going to be some math (but not much) STATISTICAL APPROACH TO MEDICAL DEVICE VERIFICATION AND VALIDATION Yes, there is going to be some math (but not much) STATISTICAL APPROACH TO MEDICAL DEVICE VERIFICATION AND VALIDATION Medical Device Verification and Validation In the medical device world, verification

More information

United States Office of Environmental EPA/240/R-02/009 Environmental Protection Information December 2002 Agency Washington, DC 20460

United States Office of Environmental EPA/240/R-02/009 Environmental Protection Information December 2002 Agency Washington, DC 20460 United States Office of Environmental EPA/240/R-02/009 Environmental Protection Information Agency Washington, DC 20460 Guidance for Quality Assurance Project Plans EPA QA/G-5 Quality Quality FOREWORD

More information

Control Charts and Trend Analysis for ISO 17025

Control Charts and Trend Analysis for ISO 17025 2015 Webinar Series Control Charts and Trend Analysis for ISO 17025 5/27/2015 Speakers Cynthia Mangione, Microbiology QAO, New York State Department of Agriculture and Markets, Food Laboratory Division,

More information

Met One Instruments BAM-1020 PM 2.5 FEM

Met One Instruments BAM-1020 PM 2.5 FEM Met One Instruments BAM-1020 PM 2.5 FEM David Gobeli, Ph.D. Met One Instruments dgobeli@metone.com 10/21/2007 1 Agenda Background Test Protocol Test Results 10/21/2007 2 Background US Regulations (40CFR

More information

Pinal County Air Quality Control District Ambient Monitoring Network Plan And 2009 Data Summary

Pinal County Air Quality Control District Ambient Monitoring Network Plan And 2009 Data Summary Pinal County Air Quality Control District 2010 Ambient Monitoring Network Plan And 2009 Data Summary June 30, 2010 Final Pinal County Air Quality 31 N. Pinal St., Bldg. F P.O. Box 987 Florence AZ, 85132

More information

(CEMS) Sanjeev K Kanchan. Centre for Science and Environment

(CEMS) Sanjeev K Kanchan. Centre for Science and Environment Continuous Emission Monitoring System (CEMS) Sanjeev K Kanchan CEMS- What & Why? Strong pollution control regime is must Unlike US, EU, developing countries suffers from weak/missingpollution norms, standardised

More information

CRITICAL ASPECT ANALYTICAL TEST REVIEW

CRITICAL ASPECT ANALYTICAL TEST REVIEW CRITICAL ASPECT ANALYTICAL TEST REVIEW Jakarta 14 December 2017 Speaker: HERU PURNOMO, ST QC WORK FLOW Start Sample Received (In-Process & Finished Good) Testing Review Lab Result Yes No Non Conformance

More information

Verification of Method XXXXXX

Verification of Method XXXXXX Reviewed By: Date: Technical Supervisor Reviewed By: Date: General Supervisor Reviewed By: Date: Quality Assurance Coordinator Approved By: Date: Director Page 1 of 11 Table of Contents Purpose and Principle:...

More information

Ainvolved in many aspects of project planning, sample collection,

Ainvolved in many aspects of project planning, sample collection, Chapter 3: SOME BASIC QA /QC CONCEPTS s coordinator of a volunteer monitoring program, you are probably Ainvolved in many aspects of project planning, sample collection, laboratory analysis, data review,

More information

Monitoring Network Design and Changes

Monitoring Network Design and Changes Monitoring Network Design and Changes Craig Anderson Air Quality Analysis Section ARB Air Quality Planning & Science Division PQAO Training 2017: January 24-26, 2017 2 Outline California Monitoring Network

More information

M&V 2.0: A User s Guide

M&V 2.0: A User s Guide M&V 2.0: A User s Guide West Coast Energy Management Congress June 8, 2017 David Jump, Ph.D., P.E. kw Engineering djump@kw-engineering.com 1 Agenda What is M&V 2.0? Process Steps & Tools Non-Routine Events

More information

G 4100 NO x /O 2 Analyzing System. Emission Control

G 4100 NO x /O 2 Analyzing System. Emission Control G 4100 NO x /O 2 Analyzing System Emission Control Document Verification Protocol Document status Draft Document version 12 Date April 2012 Document Responsible Marianne Kyed Ørbæk 1 TABLE OF CONTENTS

More information

CEM Gilles Gonnet Ecomesure, B.P. 13, F Briis Sous Forges, France telephone: fax:

CEM Gilles Gonnet Ecomesure, B.P. 13, F Briis Sous Forges, France telephone: fax: CEM 2004 Real Time Measurement Of Particulate At Low Concentration From The Emission Of Stationary Source In The Steel And Power Industries Using a TEOM based Emissions Monitor Edward C. Burgher Rupprecht

More information

TNI Assessment Forum

TNI Assessment Forum TNI Assessment Forum Traceability and Root Cause Analysis Laboratory Perspective - Bob Di Rienzo Assessor/Data User Perspective - Silky Labie January 26, 2010 TNI Training Disclaimer The material presented

More information

Back TO Basics: Sample Collection & Handling

Back TO Basics: Sample Collection & Handling Back TO Basics: Sample Collection & Handling What is QA/QC? QA stands for Quality Assurance QC stands for Quality Control Both are very important to the integrity of the sample data. Both start at the

More information

Urinalysis and Body Fluids CRg. Laboratory Regulation. Laboratory Regulation for Quality Assessment. Unit 1 B. Quality Assessment

Urinalysis and Body Fluids CRg. Laboratory Regulation. Laboratory Regulation for Quality Assessment. Unit 1 B. Quality Assessment Urinalysis and Body Fluids CRg Unit 1 B Laboratory Regulation Federal Regulations / Regulatory Organizations Laboratory structure / operation Quality test performed by qualified personnel to obtain quality

More information

A24 CALA Checklist for Microbiology Revision 4.1 February 16, 2018

A24 CALA Checklist for Microbiology Revision 4.1 February 16, 2018 A24 CALA Checklist for Microbiology Revision 4.1 February 16, 2018 Laboratory Name: Appendix Name: Appendix Number: Assessor: Date: Rev. 4.1 CALA CHECKLIST FOR MICROBIOLOGY Item 01 SAMPLING AND SAMPLE

More information

ARB PM2.5 Filter Processing and Validation

ARB PM2.5 Filter Processing and Validation ARB PM2.5 Filter Processing and Validation A Lab and Field Perspective Ali Adams PM2.5 Lab Analyst, Inorganic Lab Section Joe Guerrero Manager, Air Monitoring - North Monitoring and Laboratory Division

More information

Merrill Field Lead Monitoring Report

Merrill Field Lead Monitoring Report Municipality of Anchorage Department of Health and Human Services December 2012 Merrill Field Lead Monitoring Report Overview Merrill Field was selected by EPA as one 15 airports nationwide for inclusion

More information

Total Analytic Error From Concept to Application

Total Analytic Error From Concept to Application Página 1 de 5 Clinical Laboratory News Subscribe CLN Daily CLN Stat CLN Articles Total Analytic Error From Concept to Application Author: James O. Westgard, PhD, and Sten A. Westgard, MS // Date: SEP.1.2013

More information

MODULE 2A GENERAL MANAGEMENT SYSTEM REQUIREMENTS

MODULE 2A GENERAL MANAGEMENT SYSTEM REQUIREMENTS MODULE 2A GENERAL MANAGEMENT SYSTEM REQUIREMENTS 2A.1 SCOPE (See ISO/IEC 17025:2005, Section 1) Laboratories shall meet all requirements of the ISO/IEC 17025:2005 International Standard and other AIHA-LAP,

More information

Marcia L. Zucker, Ph.D. ZIVD LLC

Marcia L. Zucker, Ph.D. ZIVD LLC Marcia L. Zucker, Ph.D. ZIVD LLC 1 Two levels of liquid QC available from manufacturers Haphazard implementation 1990 s - POCT awareness increased Increased implementation of QC programs Expense of POCT

More information

SOP SMPS BaltimorePM supersite Version 2 November 20, 2000 Page 1 of 1. SEAS Chemistry

SOP SMPS BaltimorePM supersite Version 2 November 20, 2000 Page 1 of 1. SEAS Chemistry Page 1 of 1 RP DRAFT - MEASUREMENT AND ANALYSIS OF THE CHEMICAL COMPOSTION OF THE AMBIENT AEROSOL USING SEAS Identification code: RP RP Working RP pages APPROVALS Issue Date: /. Local PI: / / Revision

More information

US EPA Roundtable Research Triangle Park. By: Richard A. Hovan Sr., QEP Date: December 05, 2016

US EPA Roundtable Research Triangle Park. By: Richard A. Hovan Sr., QEP Date: December 05, 2016 US EPA Roundtable Research Triangle Park By: Richard A. Hovan Sr., QEP Date: December 05, 2016 SPECIFICATIONS AND TEST PROCEDURES FOR PREDICTIVE EMISSION MONITORING SYSTEMS IN STATIONARY SOURCES Major

More information

NSR Program for PM-2.5 NAAQS. Overview of Potential Proposal

NSR Program for PM-2.5 NAAQS. Overview of Potential Proposal NSR Program for PM-2.5 NAAQS Overview of Potential Proposal PM 2.5 Precursors The CAA defines air pollutant to include any pollutant that enters the air and any precursor to the formation of such pollutant

More information

November 14, 2018 Project No:

November 14, 2018 Project No: November 14, 2018 Project No: 180299 Ashley Ogonowski Macomb Montessori Academy 14057 East 9 Mile Warren, Michigan 48089 Re: Water Testing Macomb Montessori Academy Dear Mrs. Ogonowski: Please find the

More information

2.7.1 Electronics and Calibration Branch Ozone Monitoring

2.7.1 Electronics and Calibration Branch Ozone Monitoring Page 2 of 23-2.7.1 Electronics and Calibration Branch Ozone Monitoring The Electronics and Calibration Branch (ECB) of the Ambient Monitoring Section of the North Carolina Division of Air Quality (DAQ)

More information

Use Statistical Process Control (SPC) as a Tool of Understanding and Managing Variability. Jane Weitzel Independent Consultant

Use Statistical Process Control (SPC) as a Tool of Understanding and Managing Variability. Jane Weitzel Independent Consultant Use Statistical Process Control (SPC) as a Tool of Understanding and Managing Variability Jane Weitzel mljweitzel@msn.com Independent Consultant PHARMAQUAL 360º February 22 24, 2017 Orlando, FL Jane Weitzel

More information

June 8, Submitted to: The Environmental Protection Agency Research Triangle Park, NC. Prepared by:

June 8, Submitted to: The Environmental Protection Agency Research Triangle Park, NC. Prepared by: Performance Specification YY: Specifications and Test Procedures for X- Ray Fluorescence Based Multi-Metals Continuous Emission Monitoring Systems at Stationary Sources June 8, 2005 Submitted to: The Environmental

More information