1 Preliminary Cost and Performance Data Peaking Unit and Combined Cycle Technologies Debra Richert William Frazier Tom Vivenzio April 25, 2016 New York Independent System Operator Installed Capacity Working roup A World of Solutions TM 0
2 Overview Purpose of this presentation is to provide updated, preliminary cost estimates for the peaking unit technologies selected for consideration and the combined cycle configurations being provided for informational purposes only The preliminary cost estimates provided herein will be further refined in the future to reflect data and costs that remain under development, including financial and other information being developed by Analysis roup (A) The final cost data, together with estimates of projected net Energy and Ancillary Services revenues, determined by A, will be used in developing recommendations for the peaking unit technology to be used for each ICAP Demand Curve A World of Solutions TM 1
3 Agenda 1. Overview 2. Key Assumptions 3. Total Capital Investments 4. Fixed and Variable O&M Costs 5. Performance Data A World of Solutions TM 2
4 Overview A World of Solutions TM 3
5 Overview Potential peaking unit technologies 2x0 E LMS100PA+ 1x0 Siemens ST6-5000F(5) 12x0 Wartsila 18V50DF 1x0 E 7HA.02 is being developed for informational purposes As previously indicated in the February 19, 2016 ICAPW meeting presentation, the Frame H unit in simple cycle configuration is not being considered as a potential peaking unit technology option for this reset because there are no units in this configuration with commercial operating experience Informational combined cycle (CC) configurations 1x1x1 Siemens ST6-5000F(5) 1x1x1 Siemens ST6-8000H Details on breakdown of capital investment costs, fixed and variable operation & maintenance (O&M) costs, performance, and air emissions are provided in the Appendix to this presentation. A World of Solutions TM 4
6 Overview Total investment costs for peaking unit technologies and informational combined cycle plants are based on dual fuel designs in all applicable zones Reductions in total investment costs for gas only design were determined for Load Zones C, F, and (Dutchess and Rockland Counties) Current estimates of electrical interconnection costs based on escalation (2.5% per year) of 2013 demand curve reset (DCR) costs. Lummus Consultants cost estimates are in development The NYISO planning study assessing the need for System Deliverability Upgrades (SDUs) is currently underway A World of Solutions TM 5
7 Key Assumptions A World of Solutions TM 6
8 All technologies are dual fuel capable Primary fuel natural gas Back-up fuel ultra-low sulfur diesel (ULSD) Plant designs include ULSD storage based on the capability to provide one week of on-peak operations (6 days X 16 hours/day) Original equipment manufacturers (OEMs) for selected peaking unit technologies have confirmed ability to meet 45 second fuel transfer required in Load Zone J Although not being considered as a potential peaking unit technology for this reset, it is important to note that H class combustion turbines cannot meet the 45 second fuel transfer requirement Initial commissioning of peaking units assumes 40 hours of full load oil use for guarantee and emissions performance testing, 50 hours for combined cycle facilities Fixed O&M costs also include fuel oil testing costs for demonstrating capability plus costs of emissions testing on oil every five years Delivered price of ULSD in 2017 is assumed to be ~ $14/MMBtu* Key Assumptions *Source: EIA March 2016 Short-Term Energy Outlook, costs of distillate fuel oil delivered to electric generating plants. A World of Solutions TM 7
9 Key Assumptions Aero and frame combustion turbine options include evaporative inlet air coolers All technologies include a selective catalytic reduction (SCR) system and carbon monoxide (CO) oxidation catalyst control technology required to meet New Source Review (NSR) Best Available Control Technology (BACT)/Lowest Achievable Emission Rate (LAER) standards Combined cycle plant configurations are dry cooled in all zones except Load Zone C. E LMS100PA+ facilities use dry cooling in all applicable zones Black start costs have not been included as those costs are recovered through a separate cost of service product Con Edison may require black start capability for new units in Load Zone J A World of Solutions TM 8
10 Assessment of site acreage requirements confirmed that assumptions used in 2013 DCR are still valid; site preparation costs were escalated from 2013 DCR (2.5% per year) Construction labor costs Construction crafts base pay and supplemental (fringe) benefits were obtained from the Prevailing Wage Rate Schedules New York State Department of Labor using the latest available data as of October 2015 Labor productivity factor 1.45 in Load Zone J; 1.4 in Load Zone K; and 1.2 in rest of state (ROS) 50 hour workweek Key Assumptions (continued) No allowance to attract labor (not applicable to union projects) A World of Solutions TM 9
11 Construction Financing Cost Assumptions Construction financing costs were based on construction drawdown schedules for each technology option and the 2013 DCR weighted average cost of capital (WACC)* Technology Project Duration (months) 2x0 LMS100PF+ 18 1x0 Siemens 5000F x0 Wartsila 18V50DF 25 1x1x1 Siemens 5000F5 29 1x1x1 Siemens 8000H 29 *Preliminary WACC values were taken from 2013 DCR and will be updated once the financial analysis is completed A World of Solutions TM 10
12 Emission Rate Assumptions 1 NO X (ppmvd) 2 CO (ppmvd) 2 VOC (ppmvd) 2 CO 2 (lb/mwhg) 3 Natural as Firing 2x0 LMS100PF ,020 1x0 Siemens 5000F ,130 12x0 Wartsila 18V50DF x1x1 Siemens 5000F x1x1 Siemens 8000H Ultra-Low Sulfur Diesel Firing 2x0 LMS100PF ,360 1x0 Siemens 5000F ,560 12x0 Wartsila 18V50DF ,370 1x1x1 Siemens 5000F ,160 1x1x1 Siemens 8000H ,050 1) Emission rates assume an SCR/CO catalyst is installed on all technology options 2) Measured at 15% O 2 3) Based on full load, gross plant heat ISO conditions, HHV basis, clean and new condition. reenhouse (H) Best Available Control Technology (BACT) limits will be higher than the values in this table as heat rate degradation, site conditions and part load performance are considered in project-specific BACT determinations. A World of Solutions TM 11
13 Emission Reduction Credit Assumptions Emission reduction credit (ERC) requirements based on; 4,000 hours/year total permitted hours of operation for peaking unit technologies, and 8,760 hours/year for combined cycle plants 720 hours/year of permitted ULSD operation for both peaking unit technologies and combined cycle plants ERC price assumptions based on discussions with an emissions broker familiar with current ERC market in New York A World of Solutions TM 12
14 Total Capital Investments A World of Solutions TM 13
15 EPC Cost Components Equipment Equipment Spare Parts Construction Construction Labor & Materials Plant Switchyard Electrical Interconnection & Deliverability as Interconnect & Reinforcement Site Prep Engineering & Design Construction Mgmt. / Field Engr. Startup & Testing Startup & Training Testing Contingency A World of Solutions TM 14
16 Non-EPC Cost Components Percentage of EPC Owner's Costs Costs Permitting 1.0% Legal 1.0% Owner's Project Mgmt. & Misc. Engr. 1.5% Fuel Oil Testing Calculated Social Justice 0.2%* Owner's Development Costs 3.0% Financing Fees 2.0% Studies (Fin, Env, Market, Interconnect) 0.5% Emission Reduction Credits Calculated Financing (incl. AFUDC, IDC) EPC Portion Calculated Non-EPC Portion Calculated Working Capital and Non-Fuel Inventories** 1.0% Fuel Inventory*** Calculated * 0.9% in Load Zone J ** Includes initial inventory of consumables, working spare parts, and cash for the payment of operating expenses. *** Based on the capability to provide one week of on-peak operation (6 days x 16 hours/day) using ULSD A World of Solutions TM 15
17 as Interconnection Costs The natural gas lateral will need to provide on the order of 50 to 80 MMcf/day of natural gas for the peaking unit technologies, as well as for the combined cycle options being developed for informational purposes only The gas interconnection cost estimate assumes 4 miles of 16 diameter pipeline and a metering station Pipeline and metering station capital costs estimated to be $15.6 million (2015$) A World of Solutions TM 16
18 Electrical Interconnection Costs The current electrical interconnection costs are escalated from the 2013 DCR range from $10 to $14 million Lummus Consultants is preparing an independent estimate of the electrical interconnection costs Assumptions for cost estimate will include: 1 mile interconnect transmission line from plant to existing substation (Attachment Facility) 3 IS circuit breakers and associated electrical components/bulk materials installed in the existing substation (Normally considered System Upgrade Facilities) 20% cost contingency A World of Solutions TM 17
19 Capital Cost Estimates, Dual Fuel Capital Cost Estimates Dual Fuel 1, 2 (2015$ million) K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ $333 $356 $301 $304 $287 $284 1x0 Siemens 5000F5 $272 $290 $243 $245 $229 $226 12x0 Wartsila 18V50DF $419 $439 $372 $375 $352 $344 Combined Cycle Plants 1x1x1 Siemens 5000F5 $714 $757 $605 $613 $557 $517 1x1x1 Siemens 8000H $754 $798 $643 $649 $590 $546 1) Capital Investment includes Engineering, Procurement, Construction Contract, Owner s Cost, Financing Costs, Working Capital and Fuel and Non-Fuel Inventories 2) Pursuant to stakeholder requests, Lummus will be developing costs for the E 7HA.02 combustion turbine configured as Simple Cycle T, however, this option will not be considered eligible for peaking plant technology at this time because none are currently operational (or in-service ) A World of Solutions TM 18
20 Capital Cost Estimates, Dual Fuel Capital Cost Estimates, Dual Fuel 1, 2 (2015$/kW) K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ $1,760 $1,900 $1,600 $1,620 $1,540 $1,530 1x0 Siemens 5000F5 $1,240 $1,330 $1,110 $1,130 $1,050 $1,040 12x0 Wartsila 18V50DF $2,090 $2,190 $1,860 $1,880 $1,760 $1,720 Combined Cycle Plants 1x1x1 Siemens 5000F5 $2,170 $2,310 $1,850 $1,870 $1,710 $1,570 1x1x1 Siemens 8000H $1,960 $2,080 $1,680 $1,700 $1,550 $1,420 1) Capital Investment includes Engineering, Procurement, Construction Contract, Owner s Cost, Financing Costs, Working Capital and Fuel and Non-Fuel Inventories 2) Pursuant to stakeholder requests, Lummus will be developing costs for the E 7HA.02 combustion turbine configured as Simple Cycle T, however, this option will not be considered eligible for peaking plant technology at this time because none are currently operational (or in-service ) A World of Solutions TM 19
21 Reductions in Total Capital Investment for as Only Designs Reductions in Total Capital Investment for as Only Designs (2015$ million) (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ $12 $12 $12 $12 1x0 Siemens 5000F5 $19 $19 $18 $18 12x0 Wartsila 18V50DF $31 $31 $30 $26 Combined Cycle Plants 1x1x1 Siemens 5000F5 $24 $24 $23 $23 1x1x1 Siemens 8000H $29 $25 $24 $24 1) All dual fuel options include costs of the required SCR/CO catalyst emission controls required to meet NSR BACT/LAER regulatory requirements 2) Removal of SCR/CO catalyst in Load Zones C, F and (Dutchess) would further reduce total capital investments in each such zone by approximately $25 to $27 million A World of Solutions TM 20
22 Fixed and Variable O&M Costs A World of Solutions TM 21
23 Operating & Maintenance (O&M) Assumptions Assessment of staffing for the peaking unit technologies confirmed that assumed staffing levels used in the 2013 DCR remain appropriate Staffing for combined cycle plants was reduced from 23 full time equivalents (FTE) used in the 2013 DCR to 20 FTE in this DCR Plant staff average labor rate and benefits escalated from values used in the 2013 DCR Site leasing costs escalated from values used in the 2013 DCR (2.5% per year) Used same methodology for calculating property tax and insurance as used in the 2013 DCR Variable O&M (VOM) cost components in $/MWh obtained from Lummus Consultants power plant cost & performance models updated in late VOM includes major maintenance (including catalyst replacement), water, ammonia, and other chemicals and consumables. A World of Solutions TM 22
24 Fixed O&M Estimates Fixed O&M Estimates (2015$/kW-yr) 1 K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ $39 $120 $35 $35 $32 $31 1x0 Siemens 5000F5 $31 $92 $28 $28 $24 $25 12x0 Wartsila 18V50DF $51 $145 $45 $45 $39 $38 Combined Cycle Plants 1x1x1 Siemens 5000F5 $53 $153 $47 $47 $42 $39 1x1x1 Siemens 8000H $47 $137 $42 $42 $38 $35 1) Based on degraded ICAP capacity rating as stated in the Appendix to this presentation and shown on slide 28 A World of Solutions TM 23
25 Variable O&M Estimates Variable O&M Estimates (2015$/MWh) 1 K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ $5.4 $5.4 $5.3 $5.3 $5.2 $5.2 1x0 Siemens 5000F5 $0.32 $0.32 $0.32 $0.32 $0.32 $ x0 Wartsila 18V50DF $8.4 $8.5 $8.2 $8.2 $7.9 $7.9 Combined Cycle Plants 1x1x1 Siemens 5000F5 $1.0 $1.0 $1.0 $1.0 $0.9 $1.2 1x1x1 Siemens 8000H $1.0 $1.0 $0.9 $0.9 $0.9 $1.2 1) Based on natural gas firing and degraded average summer/winter capacity rating. Oil-fired VOM costs are presented in the Appendix to this presentation. A World of Solutions TM 24
26 Variable Costs per Start Variable Costs per Start (2015$/Start) 1 K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ n/a n/a n/a n/a n/a n/a 1x0 Siemens 5000F5 $11,200 $11,300 $10,900 $10,900 $10,600 $10,500 12x0 Wartsila 18V50DF n/a n/a n/a n/a n/a n/a Combined Cycle Plants 1x1x1 Siemens 5000F5 $11,200 $11,300 $10,900 $10,900 $10,600 $10,500 1x1x1 Siemens 8000H $17,000 $17,100 $16,400 $16,500 $16,000 $15,900 1) Based on natural gas firing A World of Solutions TM 25
27 Performance Data A World of Solutions TM 26
28 Average Degraded Net Plant Capacity ICAP Average Degraded Net Plant Capacity ICAP (MW) 1 K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF x0 Siemens 5000F x0 Wartsila 18V50DF Combined Cycle Plants 1x1x1 Siemens 5000F x1x1 Siemens 8000H ) Based on natural gas firing, with evaporative coolers in service. Average degraded net plant capacity at other ambient conditions are presented in the Appendix A World of Solutions TM 27
29 Average Degraded Net Plant Heat Rate ICAP Average Degraded Net Plant Heat Rate ICAP (Btu/kWh) 1 K - Long Island J - NYC (Dutchess) (Rockland) F Capital C Central Peaking Unit Technologies 2x0 E LMS100PF+ 9,260 9,320 9,260 9,260 9,260 9,260 1x0 Siemens 5000F5 10,310 10,380 10,300 10,300 10,310 10,310 12x0 Wartsila 18V50DF 8,380 8,380 8,380 8,380 8,380 8,380 Combined Cycle Plants 1x1x1 Siemens 5000F5 6,930 6,960 6,930 6,930 6,940 6,850 1x1x1 Siemens 8000H 6,750 6,790 6,760 6,760 6,760 6,650 1) Based on natural gas firing, with evaporative coolers in service, higher heating value (HHV) basis. Average degraded net plant heat rates at other ambient conditions are presented in the Appendix A World of Solutions TM 28
30 Contact Information William Frazier Principal Consultant Lummus Consultants International, Inc. Debra Richert Director Lummus Consultants International, Inc. Phone: Fax: Thomas Vivenzio Senior Principal Consultant Lummus Consultants International, Inc. Phone: Fax: Phone: Fax: A World of Solutions TM 29
Stakeholder Meeting Installed Capacity Demand Curves
Stakeholder Meeting Installed Capacity Demand Curves Debra Richert William Frazier Tom Vivenzio December 16, 2015 New York Independent System Operator A World of Solutions TM 0 Agenda 1. Tariff Requirements
More informationDraft Results Capital Cost and Performance of New Entrant Peaking Unit
Draft Results Capital Cost and Performance of New Entrant Peaking Unit Presentation to Christopher D. Ungate, Senior Consultant 1 Scope of New Entrant Peaking Unit Assumptions Peaking Unit Technology:
More informationNEW YORK INDEPENDENT SYSTEM OPERATOR
NEW YORK INDEPENDENT SYSTEM OPERATOR Proposed NYISO Installed Capacity Demand Curves For Capability Year 2017/2018 and Annual Update Methodology and Inputs For Capability Years 2018/2019, 2019/2020, and
More informationProgress Report Study Approach and Assumptions
Progress Report Study Approach and Assumptions Presentation to NYISO Installed Capacity Working Group Christopher D. Ungate, Senior Principal Consultant March 1, 2013 Topics Update on technology screening
More informationAssumptions and Input Data for Localized, Levelized Cost of Peaking Units
Assumptions and Input Data for Localized, Levelized Cost of Peaking Units Design of Units: Item Technology Base Options Comments LMS100 LM6000 (50,512 kw) and 7EA (85,970 kw) best peaking duty selections.
More informationStakeholder Meeting Installed Capacity Demand Curves
Stakeholder Meeting Installed Capacity Demand Curves Debra Richert William Frazier October 19, 2015 New York Independent System Operator A World of Solutions TM 0 Agenda 1. Introduction 2. Lummus Consultants
More informationStudy to Establish New York Electricity Market ICAP Demand Curve Parameters
Study to Establish New York Electricity Market ICAP Demand Curve Parameters Values for the 2017/18 ICAP Demand Curves All values will be updated in September 2016 with data for the period September 1,
More informationHandout 1: Thermodynamic Resources in the 2016 IRP
Handout 1: Thermodynamic Resources in the 2016 IRP This handout consists of a summary table that provides the Black & Veatch technical and financial parameters for resources considered in the 2016 IRP.
More informationInstalled Capacity Market
Installed Capacity Market Going Forward Costs Input Template Instructions Data Submission Template for Going Forward Cost and Physical Withholding Review March 2014 Table of Contents Table of Contents...
More informationNYISO 2015/2016 ICAP Demand Curve Reset
NYISO 2015/2016 ICAP Demand Curve Reset Dual Fuel Capability and Emissions Control Technology ICAPWG June 15, 2016 BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON
More informationRegulatory Commission s ( Commission ) Office of Energy Market Regulation issued on
2750 Monroe Blvd. Audubon, PA 19403-2497 Chenchao Lu Counsel T: (610) 666-2255 F: (610) 666-8211 Chenchao.Lu@pjm.com The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First
More informationNYISO 2015/2016 ICAP Demand Curve Reset
NYISO 2015/2016 ICAP Demand Curve Reset Business Issues Committee March 17, 2016 BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON Today s Presentation Provide
More informationNet Revenue. Overview Net Revenue. Conclusion. Historical New Entrant CT and CC Revenue Adequacy
Section 7 Net Revenue Net Revenue The Market Monitoring Unit (MMU) analyzed measures of PJM energy market structure, participant conduct and market performance. As part of the review of market performance,
More informationCalifornia Independent System Operator. Variable Operations and Maintenance Costs January 8, 2019
California Independent System Operator Variable Operations and Maintenance Costs January 8, 2019 Agenda Introduction and Background Cost Definitions Methodology Data Sources Variable O&M Cost Information
More informationEagle Mountain Pumped Storage Project Draft License Application Exhibit D Project Costs and Financing
Eagle Mountain Pumped Storage Project Draft License Application Exhibit D Project Costs and Financing Palm Desert, California Submitted to: Federal Energy Regulatory Commission Submitted by: Eagle Crest
More informationNet Revenue. Overview Net Revenue. Net Revenue. Conclusion
Section 7 Net Revenue Net Revenue The Market Monitoring Unit (MMU) analyzed measures of PJM energy market structure, participant conduct and market performance. As part of the review of market performance,
More informationin the NYISO s Market Administration and Control Area Services Tariff ( Services Tariff ).
NYISO 15-25 2015/2016 ICAP Demand Curve Reset RFP 1.3 RFP Objectives, Scope, and Deliverables The objective of this Request for Proposal is to select a consultant to conduct a study of the parameters,
More informationAMEC Report Revision 1: June 13, Thermal Generation Options Assessment
AMEC Report 179019 Revision 1: June 13, 2015 2015 Thermal Generation Options June 13, 2015 BC Hydro 6911 Southpoint Drive, 13 th Floor Burnaby BC, Canada V3N 4X8 Attn: David Fox, Sanjaya De Zoysa Ref:
More informationNet Revenue. Overview Net Revenue. Conclusion
Section 7 Net Revenue Net Revenue The Market Monitoring Unit (MMU) analyzed measures of PJM energy market structure, participant conduct and market performance. As part of the review of market performance,
More informationBC Hydro Vancouver, British Columbia. BC Hydro 2008 Resource Options Update Gas-fired Combustion Turbine Power Plant Costs and Performance Updates
BC Hydro Vancouver, British Columbia BC Hydro 2008 Resource Options Update Gas-fired Combustion Turbine Power Plant Costs and Performance Updates 28 February 2008 Prepared by: D. Bruce, P.Eng. Reviewed
More informationIndependent Study to Establish Parameters of the ICAP Demand Curve for the New York Independent System Operator
Independent Study to Establish Parameters of the ICAP Demand Curve for the New York Independent System Operator Final July 13, 2007 NERA Economic Consulting i Project Team NERA Economic Consulting GENE
More informationWestern Region RFP Supplemental Information Required by Bidders in Connection with Proposal Submission Updated March 4, 2012
Western Region RFP Supplemental Information Required by Bidders in Connection with Proposal Submission Updated March 4, 2012 Below is a list of additional information not currently specified or called
More informationHighlights from the Quarterly Report on the New York ISO Electricity Markets Third Quarter of 2017
Highlights from the Quarterly Report on the New York ISO Electricity Markets Third Quarter of 2017 Pallas LeeVanSchaick Potomac Economics Market Monitoring Unit Market Issues Working Group November 29,
More informationVariable Operations and Maintenance Cost December 26, 2018
EXTERNALLY-AUTHORED REPORT Variable Operations and Maintenance Cost December 26, 2018 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400 EXTERNALLY-AUTHORED REPORT Variable Opertions & Maintenance
More informationRenewables and Self Supply Compliance Filing
Renewables and Self Supply Compliance Filing Dr. Nicole Bouchez Principal Economist, Market Design New York Independent System Operator Dr. Julia Popova Economist, ICAP Market Mitigation New York Independent
More informationAIR PERMITTING CASE STUDY: HARVARD S CHP EXPANSION
Michael X. Macrae, PhD, Harvard University Environmental Health & Safety A.J. Jablonowski, PE, Epsilon Associates AIR PERMITTING CASE STUDY: HARVARD S CHP EXPANSION 1 Overview Harvard University is expanding
More informationSpecial Session Variable Operations & Maintenance Costs (VOM) - First Read of Proposed Packages
Special Session Variable Operations & Maintenance Costs (VOM) - First Read of Proposed Packages Thomas Hauske Sr. Lead Engineer, Operation Analysis & Compliance Market Implementation Committee February
More informationCASE STUDY FOR RETROFIT OF TURBINE INLET COOLING IN BATAM, INDONESIA.
CASE STUDY FOR RETROFIT OF TURBINE INLET COOLING IN BATAM, INDONESIA www.tas.com Introduction About Medco Power About TAS Turbine inlet cooling the impact Indonesia project execution Operating results
More informationPreliminary Assumptions for On-Shore Wind Technologies. Gillian Charles GRAC October 2, 2014
Preliminary Assumptions for On-Shore Wind Technologies Gillian Charles GRAC October 2, 2014 At the last meeting Discussed current status of wind development in PNW Reviewed recent trends in development
More informationResponse to new york energy highway Request for InfoRmatIon
Response to new york energy highway Request for InfoRmatIon BY GENON ENERGY, INC. MAY 30, 2012 WWW.GENONBOWLINE.COM Contents Introduction Required Information Respondent Information Project Description
More informationThe Future of CSP: Dispatchable Solar Power
The Future of CSP: Dispatchable Solar Power Hank Price, P.E. Managing Director Solar Dynamics LLC Slide 1 1/23/2018. U.S. Direct Normal Resource Map & Transmission Interconnections Slide 2 1/23/2018. Decarbonizing
More informationIncremental Black Start RFP Response Template & General Information
Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section
More informationDraft for an Appendix O Cost Structures
CSPBankability Project Report Draft for an Appendix O Cost Structures to the SolarPACES Guideline for Bankable STE Yield Assessment Document prepared by the project CSPBankability funded by the German
More information600 MW (nominal) Combined Cycle Power Plant in Hayward, CA 2 - Siemens Westinghouse 501FD3 Combustion Turbines
Russell City Energy Center Voluntary GHG BACT Determination Bay Area Air Quality Management District June 14, 2011 Brian Lusher Senior Air Quality Engineer RCEC Project Description 600 MW (nominal) Combined
More informationBeyond LCOE: The Value of CSP with Thermal Energy Storage
CSP Beyond LCOE: The Value of CSP with Thermal Energy Storage energy.gov/sunshot Mark S. Mehos, Program Manager, CSP NREL Discussion SunShot and LCOE Understanding the Value of CSP with Thermal Energy
More informationTRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project
TRC Solutions Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project October 2013 Table of Contents: I. Executive Summary II. Cost Estimate and Physical
More information2015 Procurement Plan Thermal Resource Specifications
2015 Procurement Plan Thermal Resource Specifications Presentation to: NorthWestern Energy ETAC June 4, 2015 What Has Changed Since 2013 Plan? Strong dollar handicaps GE gas turbine sales when compared
More informationSouthwest Power Pool, Inc., Docket No. ER13- Submission of Filing to Update Energy Imbalance Market Offer Cap
November 7, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER13- Submission
More informationGeneration Technology Options in a Carbon- Constrained World
Generation Technology Options in a Carbon- Constrained World Prepared by the Energy Technology Assessment Center (Reference: EPRI Report 1022782) Levelized Cost of Electricity Analysis Objectives Provide
More informationCombined Heat & Power (CHP) in New Jersey
COMBINED HEAT & POWER PROJECTS IN NEW JERSEY Combined Heat & Power (CHP) in New Jersey Essex County Correctional Facility, Cogeneration Project financing plant frees capital dollars Public Project 20yr
More informationDIRECT TESTIMONY BRUCE C. HARRINGTON. On Behalf of MISSISSIPPI POWER COMPANY BEFORE THE MISSISSIPPI PUBLIC SERVICE COMMISSION DOCKET NO.
DIRECT TESTIMONY OF BRUCE C. HARRINGTON On Behalf of MISSISSIPPI POWER COMPANY BEFORE THE MISSISSIPPI PUBLIC SERVICE COMMISSION DOCKET NO. 0-AD-01 Q. Would you please state your name, position and business
More informationStakeholder Requests for Information and PJM Responses
Stakeholder Requests for Information and PJM Responses Question: 1 Please identify the increase in Gross CONE for the reference CT unit (GE Frame 7FA) in SWMAAC caused by PJM s adoption of the Brattle
More informationCost and Performance Baseline for Fossil Energy Plants
Cost and Performance Baseline for Fossil Energy Plants CMU Seminar September 26, 2007 Julianne Klara, National Energy Technology Laboratory Fossil Energy Plant Baseline Study -Report Contains- Subcritical
More informationPJM Cost of New Entry Combustion Turbines and Combined-Cycle Plants with June 1, 2022 Online Date
PJM Cost of New Entry Combustion Turbines and Combined-Cycle Plants with June 1, 2022 Online Date PREPARED FOR PJM Interconnection, L.L.C. PREPARED BY Samuel A. Newell J. Michael Hagerty Johannes P. Pfeifenberger
More informationProject Location Village of Lordstown, Ohio
Project Location Village of Lordstown, Ohio Project Location 0 0.25 0.5 1 Miles Project Site Characteristics Potential Laydown Area Project Site Warehouse Laydown Area Laydown Area Electrical Route Utility
More informationAPPENDIX C SCAQMD PERMIT APPLICATION
APPENDIX C SCAQMD PERMIT APPLICATION Application to the South Coast Air Quality Management District for a Permit to Construct and Permit to Operate for the Natural Gas-Fired Long Beach Emergency Repowering
More informationCost Development Guidelines
PJM Manual 15: Cost Development Guidelines Revision: 18 Effective Date: February 8, 2012 Prepared by Cost Development Subcommittee PJM 2012 PJM 2012 i Table of Contents PJM Manual 15: Cost Development
More informationENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE
ENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE Technology, Cost and Regulation of CO 2 SEPTEMBER 22, 2014 Note: All IRP materials presented here are marked preliminary subject to change prior
More informationDIVISION OF AIR QUALITY AIR QUALITY, ENERGY, AND SUSTAINABILITY NATURAL GAS COMBINED CYCLE PROJECTS AND CO 2 BACT EMISSION LIMITS IN NEW JERSEY
DIVISION OF AIR QUALITY AIR QUALITY, ENERGY, AND SUSTAINABILITY NATURAL GAS COMBINED CYCLE PROJECTS AND CO 2 BACT EMISSION LIMITS IN NEW JERSEY Energy Air Quality MARAMA WORKSHOP FEBRUARY 22, 2018 DAVID
More informationVariable Operations and Maintenance (VOM) Costs: Educational Document
Variable Operation & Maintenance Costs - Where we are today Manual 15 does not specifically define Variable Operation & Maintenance (VOM) Costs, nor do any other PJM manuals. In a Review of Generator Compensation
More informationFor Combu. PJM Interconnection, L.L.C. August 24, Prepared for. The Brattle Group. HILL Wood. Samuel A. Newell Robert Carlton.
Cost of New Entry Estimates For Combu ustion Turbine and Combined-Cycle Plants in PJM August 24, 2011 Kathleen Spees Samuel A. Newell Robert Carlton Bin Zhou Johannes P. Pfeifenberger The Brattle Group
More informationBloom Energy Fuel Cells
Bloom Energy Fuel Cells A Cost-Effectiveness Brief Prepared for Bloom Energy by Synapse Energy Economics February 11, 2019 https://bloomenergy.com http://www.synapse-energy.com/bloom-energy-fc Kenji Takahashi,
More informationIsland Park Energy Center A Repowering of E.F. Barrett Power Station Informational Open House
Island Park Energy Center A Repowering of E.F. Barrett Power Station Informational Open House Project Proposal and Development Schedule Table Tripod Boards Project Proposal National Grid, under its current
More informationDynamic Pricing. June 2, 2016 Harvard s Electricity Policy Group
Dynamic Pricing June 2, 2016 Harvard s Electricity Policy Group Discussion Topics Microgrid Architecture Utility Microgrids: Building a Foundation for Price Response The Role of Dynamic Pricing Dynamic
More informationPJM s Experience with the RPM Capacity Market
PJM s Experience with the RPM Capacity Market 2013 Austin Electricity Conference Panel 1: Are Capacity Market Necessary to Ensure Adequate Generating Reserve Paul M. Sotkiewicz, Ph.D. Chief Economist PJM
More informationAppendix D Minimum Requirements. For Request For Proposals For Long-Term, Supply-Side Developmental Resources in In Amite South DRAFT
ESI Draft 7/14/2014 Appendix D Minimum Requirements For 2014 Request For Proposals For Long-Term, Supply-Side Developmental Resources in In Amite South Formatted: Font color: Black Formatted: Font: Tahoma
More informationMPSC Staff s Avoided Cost Methodology Case No.: U Capacity Component of Staff's Proposed Method
MPSC Staff s Avoided Cost Methodology Case No.: U-18090 Capacity Component of Staff's Proposed Method Exhibit: S-14 (JJH-8) Levelized Cost Calculation Simple Cycle Gas Turbine Page: 1 of 2 CT CT No Variable
More informationUPDATE ON THE KEMPER COUNTY IGCC PROJECT Gasification Technologies Conference
UPDATE ON THE KEMPER COUNTY IGCC PROJECT 2012 Gasification Technologies Conference Kemper County IGCC Overview 2x1 Integrated Gasification Combined Cycle (IGCC) 2 Transport Gasifiers 2 Siemens SGT6-5000F
More informationCost Development Guidelines
PJM Manual 15: Cost Development Guidelines Revision: 18 Effective Date: Deleted: June 1, 2011 Prepared by Cost Development Subcommittee PJM 2011 PJM 2011 i Table of Exhibits PJM Manual 15: Cost Development
More informationBefore the Public Utilities Commission of the State of South Dakota. In the Matter of the Application of Black Hills Power, Inc.
Direct Testimony Mark Lux Before the Public Utilities Commission of the State of South Dakota In the Matter of the Application of Black Hills Power, Inc. For the Phase In of Rates Regarding Construction
More informationState of the Art (SOTA) Manual for Stationary Gas Turbines
State of the Art (SOTA) Manual for Stationary Gas Turbines Original Date: July 1997 Revision Date: November 1999 State of New Jersey Department of Environmental Protection Air Quality Permitting Program
More informationGHG BACT Analysis Case Study. May Donald Neal Vice President, EHS
GHG BACT Analysis Case Study Russell City Energy Center May 2010 Donald Neal Vice President, EHS Calpine In California 1 Project Description 612 megawatt natural gas fired combined cycle power plant in
More informationDATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans
ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version
More informationRequest for Proposal Technical Conference: Oregon Meeting (Following Utah Docket
Request for Proposal Technical Conference: Oregon Meeting (Following Utah Docket 05-035 035-47) April 10, 2006 Pacific Power Utah Power Rocky Mountain Power Agenda WorleyParsons Expanded IGCC Study Factors
More information2015 ISO/RTO Metrics Report. Summary. November 2015
2015 ISO/RTO Metrics Report Summary November 2015 ISO/RTO Metrics Report Background Independent system operators (ISOs) and regional transmission organizations (RTOs) that are regulated by the Federal
More informationDemand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144
Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of
More informationLevelized Cost of New Generation Resources in the Annual Energy Outlook 2012
July 2012 Levelized Cost of New Generation Resources in the Annual Energy Outlook 2012 This paper presents average levelized costs for generating technologies that are brought on line in 2017 1 as represented
More informationBOILER/HEATER > 5 MMBTU BACT Size: MINOR SOURCE BACT BOILER. BACT Determination Information
ACTIVE SMAQMD BACT CLEARINGHOUSE CATEGORY: BOILER/HEATER > 5 MMBTU BACT Size: MINOR SOURCE BACT BOILER BACT Determination Number: 157 BACT Determination Date: 6/19/2018 Equipment Information Permit Number:
More information10.0 SUPPLY-SIDE OPTIONS
10.0 The purpose of this section is to summarize the input assumptions that Black & Veatch used related to the various supply-side resource options considered in the RIRP study. Information is provided
More informationGas-fired efficiency in part-load and pulse operation
[ ENERGY / IN DETAIL ] [ ENERGY / IN DETAIL ] Gas-fired efficiency in part-load and pulse operation AUTHOR: Dawn Santoianni Gas-fired power plants are the most responsive and flexible generating assets
More informationNew England States Committee on Electricity
Renewable and Clean Mechanisms 2.0 Study Phase I: Scenario Analysis Winter 2017 New England States Committee on Electricity Overview Context Analytical Approach and Modeling Assumptions Scenario Analysis
More informationUniversity of Illinois at Chicago East Campus
University of Illinois Energy Resources Center Phone: (312) 996-4382 851 S. Morgan St. (MC-156) Fax: (312) 996-5620 Chicago, IL 60607-7054 Website: University of Illinois at Chicago East Campus (Including
More informationBEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION
777 12 th Street, Third Floor Sacramento, CA 95814 BEST AVAILABLE NTROL TECHNOLOGY DETERMINATION DETERMINATION NO.: 203 DATE: ENGINEER: Brian Krebs Category/General Equip Description: Equipment Specific
More informationAir Pollution Control Permitting - Customer Overview
Air Pollution Control Permitting - Customer Overview Self Generation Incentive Program Seminar CHP Project Planning & Permits March 11, 2003 San Diego, CA Presented by: Shirley F. Rivera Alternative Energy
More informationNYS Energy Storage Roadmap. March 16, 2018
NYS Energy Storage Roadmap March 16, 2018 Agenda 2 New York s Commitment to Energy Storage Jason Doling, NYSERDA Team Lead for Energy Storage Storage study scope Jason Doling Storage study inputs, and
More informationAlberta Capacity Market
Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 3: Calculation of Capacity Market Demand Parameters Prepared by: Alberta Electric System Operator Date: January
More informationResource Capability Testing
Resource Capability Testing Amount of Capacity Available Joe Nieminski ICAP Market Operations Engineer, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 1 Objectives Participants will be
More informationRECOMMENDED CPCN CONDITIONS CASE NO CATOCTIN POWER, LLC
RECOMMENDED CPCN CONDITIONS CASE NO. 8997 CATOCTIN POWER, LLC General 1. Except as otherwise provided for in the following provisions, the application for the Certificate of Public Convenience and Necessity
More informationRevision: 16 Effective Date: Prepared by Cost Development Task Force
PJM Manual 15: Cost Development Guidelines Revision: 16 Effective Date: Prepared by Cost Development Task Force PJM 2010 i Table of Exhibits PJM 2010 PJM 2003 Approval and Current Revision PJM Manual 15:
More informationSummary of Integrated Capacity and Energy Revenue Modelling
Summary of Integrated Capacity and Energy Revenue Modelling Prepared by: Alberta Electric System Operator Date: January 26, 2018 Public Table of Contents 1. Summary of Integrated Capacity and Energy Revenue
More informationFINAL DETERMINATION. To Grant a. Temporary Permit/Non-Attainment New Source Review Permit. For. Concord Steam Corporation.
FINAL DETERMINATION To Grant a Temporary Permit/Non-Attainment New Source Review Permit For Concord Steam Corporation To Construct a 305 MMBtu/hr Biomass Boiler (Wood & Natural Gas), 2 Auxiliary Boilers
More informationDry Flexicycle power plants a closed loop combined cycle with unique operational flexibility
Power-Gen Middle East 2014 Dry Flexicycle power plants a closed loop combined cycle with unique operational flexibility Mr. Risto Paldanius, Director, Business Development, Wärtsilä Power Plants Mr. Kristian
More informationBEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP. Exhibit Accompanying Opening Testimony of Brian S. Dickman
Docket No. UM 1794 Witness: Brian S. Dickman BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP Exhibit Accompanying Opening Testimony of Brian S. Dickman Black & Veatch Wind Generation Study October
More informationCOGENERATION: Opportunities in Today s Power Markets
COGENERATION: Opportunities in Today s Power Markets COGEN Europe Annual Conference 2005 10-11 March 2005 Paul Dillon Planning Executive: Europe, Middle East and Africa ExxonMobil Refining & Supply Taking
More informationColorado PUC E-Filings System
Page 1 of 13 ATTACHMENT A Introduction In Decision No. C16-0127 (issued on February 16, 2016), Public Service Company of Colorado ( Public Service or the Company ) was directed to file technical assumptions
More informationCost Development Guidelines
PJM Manual 15: Cost Development Guidelines Revision: 15 Effective Date: Prepared by Cost Development Task Force PJM 2010 PJM 2010 i Table of Exhibits PJM Manual 15: Cost Development Guidelines Table of
More informationThe Cost of New Generating Capacity in Perspective
October 2009 The Cost of New Generating Capacity in Perspective Executive Summary Like all new generating capacity, there is uncertainty about the capital cost of new nuclear power plants. Estimates range
More informationWind Energy Basics & Project Cycle
Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented to: DFCC Bank and RERED Consortia Members January 26 27, 2011 Colombo, Sri
More information2013 Project Schedule Milestone Summary
2013 Project Schedule Milestone Summary Janet Joyce Director, Product & Project Management New York Independent System Operator Budget and Priorities Working Group February 13, 2014 Krey Corporate Center
More informationGASP comments regarding Air Quality Plan Approval C - Tenaska Pennsylvania Partners, LLC Westmoreland Generating Station
Via Email February 23, 2015 Pennsylvania Dept. of Environmental Protection Air Quality Program 400 Waterfront Drive Pittsburgh, PA, 15222 asandy@pa.gov GASP comments regarding Air Quality Plan Approval
More informationWind Energy Basics & Project Cycle
Wind Energy Basics & Project Cycle WIND POWER PROJECT DEVELOPMENT PRACTICAL APPROACHES TO LAUNCHING SUSTAINABLE WIND PROJECTS October 18-19, 2011 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented
More informationPJM s Clean Power Plan Modeling Reference Model and Sensitivities
PJM s Clean Power Plan Modeling Reference Model and Sensitivities Muhsin K. Abdur-Rahman Senior Market Strategist MC Webinar April 25, 2016 What it is Reference Model Robust modeling representation of
More informationPaul M. Sotkiewicz, Ph.D. Chief Economist M. Gary Helm Senior Market Strategist PJM Interconnection October 20, 2011
Coal Capacity at Risk for Retirement in PJM: Potential Impacts of the Finalized EPA Cross State Air Pollution Rule and Proposed National Emissions Standards for Hazardous Air Pollutants Paul M. Sotkiewicz,
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction
More information2011 IRP Public Input Meeting. August 4, Pacific Power Rocky Mountain Power PacifiCorp Energy
2011 IRP Public Input Meeting August 4, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Demand-side management / distributed generation Supply-side Resources Planning Reserve Margin (PRM)
More informationRenewable Energy Feasibility Study for Ione Band of Miwok Indians
Renewable Energy Feasibility Study for Ione Band of Miwok Indians By: Community Assessment of Renewable Energy and Sustainability & The Renewable and Appropriate Energy Laboratory Contents i. About CARES
More informationMonitoring Plan for the. Cornell Combined Heat and Power Project (CCHPP) October 2008
Monitoring Plan for the Cornell Combined Heat and Power Project (CCHPP) October 2008 Submitted to: New York State Energy Research and Development Authority 17 Columbus Circle Albany, New York 12203-6399
More information4 Calculation of Demand Curve Parameters
4 Calculation of Demand Curve Parameters This section addresses the demand curve for the Alberta capacity market, including the calculations for the components of the demand curve. 4.1 Resource adequacy
More informationFinancing Future Power Supply October 4, 2004 Peter Kind
CPUC Installed Capacity Conference Financing Future Power Supply October 4, 2004 Peter Kind Key Questions What are we doing to address fuel diversity/energy independence? Do Least Cost Plans result in
More informationFeasibility of Utility Owned DG for New York
Review of Utility Owned DG Business Models for New York Kenji Takahashi Northeast CHP Initiative Meeting in New York, NY April 13, 2010 www.synapse-energy.com 2008 Synapse Energy Economics Inc. All rights
More information