IV. ENVIRONMENTAL IMPACT ANALYSIS D. HAZARDOUS MATERIALS/RISK OF UPSET

Size: px
Start display at page:

Download "IV. ENVIRONMENTAL IMPACT ANALYSIS D. HAZARDOUS MATERIALS/RISK OF UPSET"

Transcription

1 IV. ENVIRONMENTAL IMPACT ANALYSIS D. HAZARDOUS MATERIALS/RISK OF UPSET ENVIRONMENTAL SETTING Except where footnoted otherwise, this Section is based upon the following site-specific investigation: Phase I Environmental Site Assessment and Phase II Subsurface Investigation, Proposed Emerson College Site, West Sunset Boulevard, Los Angeles, California 90028, Tetra Tech, Inc., March 11, This technical report is incorporated into Appendix D of this Draft EIR. Existing Project Site The Project Site is located at the southeast corner of the intersection of Sunset Boulevard and North Gordon Street in the Hollywood Community Plan Area in the City of Los Angeles. The Project Site is located on an approximately 0.86-acre parcel of land. The Project Site is currently developed with a fence-enclosed, asphalt parking lot that serves employees of nearby KTLA Studios. A guard shack exists in the southwestern part of the Site. The parking lot is entered via an entrance on North Gordon Street. A concrete pad with asphalt patches is located in the northern part of the Site. This appears to have been the area of former gasoline pump islands (i.e., the patches are the areas where the pump islands were removed) at a former gas station (discussed further below). During a site reconnaissance survey to identify potentially hazardous materials on the Project Site, Tetra Tech noted the following conditions: No significant areas of surficial staining were observed on the concrete-paved parking. Localized areas of petroleum-type staining related to parked vehicles were observed. This is considered to be a de minimis condition. No visual evidence (i.e., pipes, vents, and dispensers) indicating existing or historic on-site underground storage tanks (USTs) was observed. No visual evidence (i.e., concrete foundation or containment walls, pedestals, or steel support structures) indicating existing or historic on-site above-ground storage tanks (ASTs) was observed. There are no buildings on the Site, and no debris piles with suspect asbestos containing materials (ACMs) or lead-based paint (LBP) were observed. As a result, it is unlikely that there is asbestos or LBP on the Site. No hazardous materials usage, hazardous waste generation or storage, or solid waste was observed. No transformers or other PCB-containing equipment were observed at the Site. Page IV.D-1

2 The site reconnaissance and a review of local records did not reveal the presence of on-site water supply or irrigation wells. Industrial or domestic wastewater is not generated at the Site. No surface water or wetland areas were observed. There were no observed Site operations involving emissions that appeared to require permitting, emission controls, or abatement activities. The site reconnaissance, as well as review of available municipal records and regulatory records, did not reveal the presence of current or historic on-site dry cleaning operations. No evidence of potential microbial growth and/or moisture intrusion was observed. No significant environmental non-compliance issues associated with current Site use were noted. Historic Use of Project Site Based on a review of historical photographs and records, Sanborn fire insurance maps, agency files, and other data, the Project Site was historically occupied by a City of Los Angeles maintenance yard (apparently utilized for woodworking activities) from at least 1919 to sometime before By 1938, the Site is reported to have been used for auto maintenance/repair activities. From approximately 1947 to 1962, the site was occupied by four buildings, including a residence and three buildings labeled as Auto Radiator Rep g [sic], Auto Trimming, and Auto Rep & Wash g [sic]. From 1962 until before 1989, the Site was occupied by a gas station, and from at least 1989 to the present, by a parking lot. Surrounding Properties The Project Site and surrounding properties are located within the Hollywood area of the City of Los Angeles, which is a developed area that is supported by existing urban infrastructure. The surrounding area is comprised of a mix of low to medium density residential, commercial, and office uses. The properties immediately surrounding the Project Site are as follows: On the north side of the Project Site, across Sunset Boulevard, are several commercial uses, including a two-story motel (6055 West Sunset Boulevard), a surface parking lot (6019 to 6023 W. Sunset Boulevard), a two-story mini-mart (6017 W. Sunset Boulevard), a one-story import store (6009 W. Sunset Boulevard), a single-story liquor store/delicatessen (6007 W. Sunset Boulevard), a two-story hair salon (6003 W. Sunset Boulevard) and print shop (6001 W. Sunset Boulevard), and the site for the future Sunset and Gordon Mixed-Use Project (5939 W. Sunset Boulevard). To the east toward Tamarind Avenue are commercial uses, including restaurants at 5946 and 5936 W. Sunset Boulevard. Adjacent and south, located at the southwest corner of Sunset Boulevard and N. Tamarind Avenue, are commercial uses that include a one-story deli (1471 N. Tamarind Avenue), a two-story residential use (1461 N. Tamarind Avenue), and commercial office uses, including a psychic reader and a public relations firm (1467 and 1463 N. Tamarind Avenue, respectively). To the south of the Project Site are a commercial office building (1456 N. Gordon Street) and a mix of Page IV.D-2

3 single-family and multi-family residential uses located further to the south along both Gordon Street and N. Tamarind Avenue. To the west across Gordon Street are several studio-related commercial uses, including the two-story EastWest Studios building at the southwest corner of Sunset Boulevard and Gordon Street (6000 W. Sunset Boulevard), the one-story Alley Kat Studios building (1455 N. Gordon Street), and a five-level parking structure for the Sunset Gower Studios property (1438 N. Gower Street). A summary of the historic uses of property surrounding the Project Site is presented in Table 4.2 of Appendix D. Database Review of Project Site and Surrounding Properties The Phase I ESA and Phase II Subsurface Investigation prepared by Tetra Tech included a database search of hazardous material sites that are listed on current federal, State, and local environmental regulatory agency databases. While the Project Site is not listed in any of the databases searched, several database listings for sites located within the American Society for Testing and Materials ( ASTM ) designated search radius (i.e., generally one, one-half, or one-quarter mile radius) of the Project Site were identified, and are presented in Table IV.D-1, below. However, an inspection of the abutting properties from curbside and a review of the database records did not reveal the presence of off-site sources that are considered to be of concern to the Project Site. Phase II Subsurface Investigation A focused Phase II subsurface investigation was conducted by Tetra Tech to evaluate the likelihood that: (1) USTs or other former subgrade features related to prior auto repair and/or gas station uses are still present at the Project Site; and (2) Elevated concentrations of total petroleum hydrocarbons (TPH); VOCs, including BTEX; methane gas; and metals are present in near-surface soils (to a depth of approximately 30 feet bgs at the Site). Table IV.D-1 Summary of Regulatory Agency Database Search Database Radius Target Property Surrounding Facilities Federal National Priorities List (NPL) 1 mile No 0 Proposed NPL 1 mile No 0 Delisted NPL 1 mile No 0 Comprehensive Environmental Response, Compensation, and Liability Information System (CERCLIS) ½ mile No 0 CERCLIS No Further Remedial Action Planned Sites (NFRAP) ½ mile No 0 Page IV.D-3

4 Table IV.D-1 Summary of Regulatory Agency Database Search Database Radius Target Property Surrounding Facilities Resource Conservation and Recovery Act (RCRA) Corrective Action Treatment, Storage, and Disposal (TSD) Facilities (CORRACTS) 1 mile No 0 RCRA Non-Corrective Action (TSD) Facilities ½ mile No 0 RCRA Waste Generators Site and adjacent No 1 US Brownfields ½ mile No 0 Institutional Control/Engineering Control (IC/EC) Site No - Emergency Response Notification System (ERNS) Site No - State Bond Expenditure Plan (BEP) 1 mile No 0 Hist Cal-Sites 1 mile No 0 Response 1 mile No 0 EnviroStor 1 mile No 11 California Hazardous Material Incident Report System (CHMIRS) Site No - Cortese 1 mile No 7 Notify 65 1 mile No 0 Toxic Pits 1 mile No 0 Solid Waste Information System (SWF/LF) ½ mile No 0 Waste Management Unit Database System / Solid Waste Assessment Test (WMUDS/SWAT) ½ mile No 0 Leaking Underground Storage Tanks (LUST) databases ½ mile No 7 Underground Storage Tank (UST) databases Aboveground Storage Tank (AST) Site and adjacent Site and adjacent No 0 No 0 Spills, Leaks, Investigation & Cleanup (SLIC) ½ mile No 4 Voluntary Cleanup Plan (VCP) ½ mile No 0 Deed Restriction Listing (DEED) ½ mile No 0 Tribal databases Various No 0 SCH ¼ mile No 0 Drycleaners ¼ mile No 1 Source: Phase I Environmental Site Assessment and Phase II Subsurface Investigation, Proposed Emerson College Site, West Sunset Boulevard, Los Angeles, California 90028, Table 5.0, Tetra Tech, Inc., March 11, Page IV.D-4

5 Soil samples and soil gas samples were analyzed for COPCs, and the results compared to published screening criteria (commonly used for evaluating potential human health and ecological concerns related to compounds detected in soil) to evaluate the significance of the compounds detected in the analyzed soil and soil gas. No elevated concentrations of volatile organic compounds (VOCs), total petroleum hydrocarbons (TPHs), methane gas, or California Code of Regulations (CCR) metals were found in analyzed soil gas and/or soil samples. Based on these results, a 2007 soil vapor investigation performed by Geomatrix Consultants (GC 2007b), and the results of the geotechnical investigation conducted by Ninyo & Moore concurrently with this Phase I ESA, the historic auto-related and gas station facilities at the Project Site and methane gas were not considered to be a recognized environmental condition (REC) or potential environmental concern (PEC). The Project Site is not located within a Methane hazard Site. 1 With regard to the potential presence of subgrade features, no evidence of former underground storage tanks (USTs) or oil/gas wells was found during the geophysical survey. Because no indications of significant impacts were found in the analyzed soil and soil gas samples, groundwater sampling was not considered necessary and, therefore, was not conducted. ENVIRONMENTAL IMPACTS Thresholds of Significance State CEQA Guidelines Initial Study Checklist In accordance with Appendix G to the State CEQA Guidelines, a significant impact with regard to hazards and hazardous materials would occur if the Project were to result in any of the following conditions: (a) Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials; (b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment; (c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school; (d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section and, as a result, would create a significant hazard to the public or the environment; 1 City of Los Angeles Department of City Planning, ZIMAS Property Report, website: accessed 5/27/09. Page IV.D-5

6 (e) For a project located within an airport land use plan, or, where such a plan has not been adopted, within two miles of a public airport or public use airport, result in a safety hazard for people residing or working in the project area; (f) For a project located within the vicinity of a private airport strip, result in a safety hazard for people residing or working in the project area; (g) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan; and (h) Expose people or structures to a significant risk of loss, injury or death involving wildland fires, including where wildlands are adjacent to urbanized areas or where residence are intermixed with wildlands. City of Los Angeles CEQA Thresholds Guide As set forth in the City of Los Angeles CEQA Thresholds Guide (2006), the determination of significance shall be made on a case-by-case basis, considering the following factors: (a) The regulatory framework (for the potential accidental release or explosion of a hazardous substance); (b) The probable frequency and severity of consequences to people or property as a result of a potential accidental release or explosion of a hazardous substance; (c) The degree to which the project may require a new, or interfere with an existing, emergency response or evacuation plan, and the severity of the consequences; (d) The degree to which the project design will reduce the frequency or severity of a potential accidental release or explosion of a hazardous substance; (e) The regulatory framework for the health hazard; (f) The probable frequency and severity of consequences to people from exposure to the health hazards; or (g) The degree to which the project design would reduce the frequency or severity of consequences of exposure to the health hazard. Project Impacts Following is a discussion of the Proposed Project s impacts during construction and operation with respect to hazardous materials and risk of upset. Specific areas that are discussed include routine transport, use, and disposal of hazardous materials; accidental release of hazardous materials; and conflict with emergency response or evacuation plans. Page IV.D-6

7 Construction Construction of the Proposed Project would have a less than significant impact with respect to the routine transport, use, or disposal of hazardous materials. During the construction phase, the Proposed Project is anticipated to require the routine transport, use, and disposal of cleaning solvents, fuels, paints and paint-related products, waste oil, spent solvents, oily rags and other hazardous materials commonly associated with construction projects. All hazardous materials used during demolition and construction activities would be handled in accordance with all applicable local, State, and federal regulations, which include requirements for disposal of hazardous materials at a facility licensed to accept such waste, based on its waste classification and the waste acceptance criteria of the permitted disposal facilities. As compliance with existing regulations is mandatory for all development projects, adherence to all applicable rules and regulations would reduce potentially significant impacts with respect to routine transport, use, and disposal of hazardous materials during construction to less-than-significant levels While construction of the Proposed Project would not result in a potentially significant impact with respect to the accidental release of hazardous materials including ACMs, LBPs, and PCBs, potentially significant impacts could result if hydrocarbon contaminated soils are encountered during proposed site grading and excavation. However, this impact would be reduced to less-than-significant levels with implementation of the recommended mitigation measure. As presented above under Environmental Setting, there are no buildings or debris piles with suspect ACMs or LBPs on the Project Site. Under the Proposed Project, the existing guard shack would be relocated from the Project Site, not demolished. No transformers or other PCB-containing equipment were observed at the Site, and no evidence of significant concentrations of petroleum products was found during the focused Phase II subsurface investigation. Thus, it is unlikely that PCBs are present in subsurface soils at the Site. As such, impacts with regard to accidental release of these hazardous materials would be less than significant. The focused phase II ESA conducted by Tetra Tech found no evidence of former USTs or oil/gas wells during the geophysical survey or elevated concentrations of VOCs, TPH, methane gas, or CCR metals in analyzed soil gas and/or soil samples. Nevertheless, the potential for encountering localized areas of impacted soil during proposed site grading and excavation activities cannot be ruled out based on historic Site use. Thus, impacts would be potentially significant and a soil management plan would be required. This plan, required in Mitigation Measure D-1 below, would addresses compliance procedures, requirements and protocols applicable to the excavation, monitoring, and disposal of impacted soils if encountered during site development. In the event that such soils are encountered, adherence to the soils management plan would provide for the proper management of impacted soils as required by applicable federal, state and local laws and regulations. Therefore, with mitigation, potential impacts associated with the accidental release of hazardous materials would be less than significant. Page IV.D-7

8 The Proposed Project has the potential to result in a potentially significant impact with respect to impeding or restricting emergency access to or from the Project Site or surrounding area during the construction process. This impact would be reduced to less than significant with implementation of the recommended mitigation measures. The Proposed Project is not located on or near a City-designated selected disaster route. 2 Nevertheless, Project-related construction activities may require temporary and/or partial street closures on adjacent roadways due to construction activities. While such closures may cause temporary delays or detours along Sunset Boulevard or Gordon Street, such activities would be temporary in nature and would not be expected to substantially interfere with peak-hour traffic. A potentially significant impact could occur, however, on a temporary basis with respect to delays in emergency access to or from the Project Site or surrounding area during the construction process. Emergency response and evacuation plans and would be conducted in accordance with City permitting requirements. Furthermore, any lane closures would need to be reviewed and approved in advance by the LADOT prior to construction. Implementation of the recommended mitigation measures below to avoid delays and deliveries during peak traffic hours and to ensure that emergency access is provided during the construction period would mitigate this impact to less than significant levels. Therefore, the Proposed Project would not be expected to interfere with any adopted emergency response plan or emergency evacuation plan, and a less than significant impact would occur. Operation Operation of the Proposed Project would result in a less than significant impact with respect to the release of hazardous materials resulting from the routine transport, use, or disposal of potentially hazardous materials. Under the Proposed Project, only minor amounts of potentially hazardous materials would be stored or used on the Property as a part of the planned mixed-use trade school; no industrial land uses are planned. For example, cleaning solvents would be used in association with janitorial cleaning and general maintenance in the mixed-use trade school buildings, including the academic/administrative floor area, student rooms, faculty/staff apartments, ground floor retail and restaurant space, and parking areas. As such, no substantial quantities of hazardous materials would be used, transported, or disposed of in conjunction with routine day-to-day operations of the Proposed Project. The limited quantities of hazardous materials that would be used would be handled, transported, and disposed in accordance with all applicable local, State, and federal regulations. Therefore, impacts related to routine transport, use, and disposal of hazardous materials during operation would be less than significant. 2 City of Los Angeles Department of City Planning, Environmental and Public Facilities Maps, Critical Facilities & Lifeline Systems in the City of Los Angeles, September Page IV.D-8

9 Operation of the Proposed Project would have a less than significant impact with respect to the accidental release of hazardous materials. The Project Site is located within one-quarter mile of Montessori Shir-Hashirim / Jewish Montessori School of Hollywood located at 6047 Carlton Way, and Joseph Le Conte Middle School located at 1316 N. Bronson Avenue. However, as described above, only minor amounts of potentially hazardous materials would be stored or used on the Property as a part of the planned mixed-use trade school. The students and faculty at Emerson College would work with digital video and photography as opposed to film. Therefore, no chemicals that are typically required for film processing would be used. No industrial operations are planned and no substantial quantities of hazardous materials would be used, transported, or disposed of in conjunction with the routine day-to-day operations of the Project once completed. Therefore, while the accidental release of hazardous materials such as janitorial or household chemicals could occur, such releases would be minor and would not be expected to affect neighboring uses or nearby schools. Further, such use of hazardous materials would not involve hazardous emissions or handling of acutely hazardous materials, substances, or waste. Therefore, impacts related to hazardous emissions or hazardous materials handling within ¼ mile of a school would be less than significant. Operation of the Proposed Project would have a less than significant impact with respect to impeding emergency access or response to the Project Site or surrounding area during an evacuation or emergency. With respect to off-site impacts, the Project Site is not located on or near a City-designated selected disaster route. 3 Therefore, operation of the Proposed Project would not cause any permanent alterations to evacuation routes and patterns, or impede emergency access or travel upon public rights-of-way. With respect to on-site emergency response, as shown in Figure II-3, Proposed Site Plan, in Section II., Project Description, access to the proposed subterranean parking garage for Emerson College uses would be through one ingress/egress driveway located on Gordon Street at the southwest corner of the Project Site, while access to the proposed retail uses would be through a separate ingress/egress driveway also located on Gordon Street, on the western side of the Project Site. Gordon Street is a City-designated Local Street that would be able to accommodate the frequent entry and exit of patrons and employees of both Emerson College and the associated retail uses. In addition, the Project Applicant is required to prepare and submit an emergency response plan for approval by the City of Los Angeles Planning Department and the City of Los Angeles Fire Department during the site plan check process. Therefore, during operation, the Proposed Project would not be expected to interfere with any off-site adopted emergency response plan or emergency evacuation plan. While operational impacts to emergency access would be less than significant prior to mitigation, implementation of mitigation measure D-3, below, would further ensure adequate on-site emergency access plans are developed and approved. 3 Ibid. Page IV.D-9

10 CUMULATIVE IMPACTS Development of the Proposed Project in combination with the 70 related projects has the potential to increase the risk for accidental release of hazardous materials. Each of the 70 related projects would require evaluation for potential threats to public safety, including those associated with the accidental release of hazardous materials into the environment during construction and operation, emergency response, transport/use/disposal of hazardous materials, and hazards to sensitive receptors (including schools). Because hazardous materials and risk of upset conditions are largely site-specific, this would occur on a case-by-case basis for each individual project affected, in conjunction with development proposals on these properties. Implementation of the recommended mitigation measures D-1 through D-3 would reduce the Proposed Project s potential impacts associated with the accidental release of hazardous materials during construction and operation as well as emergency response to less-than-significant levels, such that the Proposed Project would not combine with any of the related project to cause a cumulatively significant impact. Further, each related project would be required to follow local, State, and federal laws regarding hazardous materials and other hazards. Therefore, with compliance with local, State, and federal laws pertaining to hazards and hazardous materials, cumulative impacts would be less than significant. MITIGATION MEASURES Project-Specific Mitigation Measures D-1: D-2: D-3: Prior to site demolition at the Project Site, a soil management plan shall be prepared to address how localized area(s) of impacted soil, if encountered during Site development, are to be monitored, excavated from the Site, and disposed of in accordance with applicable regulatory standards. In the event that contaminated soils are identified onsite, appropriate remediation steps such as soil removal and disposal shall be taken and a No Further Action letter shall be obtained by the LARWQCB and submitted to the City of Los Angeles Department of Building and Safety prior to construction of the building s foundation. The Proposed Project shall maintain appropriate fire and police access to the Project Site by keeping driveways and/or alternative accessways clear of construction equipment, building material, and debris during the construction process. The Project Applicant shall prepare and submit an emergency response plan for approval by the City of Los Angeles Planning Department and the City of Los Angeles Fire Department. The emergency response plans shall include, but not be limited to the following: mapping of emergency exits, evacuation routes for vehicles and pedestrians, location of nearest hospitals, and fire departments. Page IV.D-10

11 LEVEL OF SIGNIFICANCE AFTER MITIGATION With the implementation of the mitigation measures recommended, the Proposed Project would result in a less-than-significant impact with respect to hazardous materials and risk of upset. Page IV.D-11

PHASE I ENVIRONMENTAL SITE ASSESSMENT 123 MAIN STREET SAN DIEGO, CALIFORNIA. September 15, 2002

PHASE I ENVIRONMENTAL SITE ASSESSMENT 123 MAIN STREET SAN DIEGO, CALIFORNIA. September 15, 2002 2847 Barnard Street San Diego California 92110 Phone 619.501.0185 Mobile 619.203.9774 Fax 619.501.9843 hoveyenv@cox.net Final Report PHASE I ENVIRONMENTAL SITE ASSESSMENT 123 MAIN STREET SAN DIEGO, CALIFORNIA

More information

IV.ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDOUS MATERIALS

IV.ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDOUS MATERIALS IV.ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDOUS MATERIALS This section summarizes a Phase I Environmental Site Assessment (ESA) Report prepared for parcels located at 11703, 11707 and 11715 San Vicente Boulevard

More information

PHASE I ENVIRONMENTAL SITE ASSESSMENT

PHASE I ENVIRONMENTAL SITE ASSESSMENT PHASE I ENVIRONMENTAL SITE ASSESSMENT Commercial and Light Industrial Development Area North of Prairie Street Between Corbin and Shirley Avenues Northridge, California AES Project No. 02-225 June 13,

More information

Environmental Assessment. Appendix G Hazardous Materials Technical Report

Environmental Assessment. Appendix G Hazardous Materials Technical Report Environmental Assessment Appendix G Hazardous Materials Technical Report Hazardous Materials and Waste Sites Summary Technical Memorandum Kansas City Streetcar Main Street Extension December 20, 2018 DRAFT

More information

Section 3.11: Hazardous Materials

Section 3.11: Hazardous Materials Section 3.11: Hazardous Materials Section 3.11 Hazardous Materials 3.11 HAZARDOUS MATERIALS 3.11.1 Introduction to Analysis This section provides information regarding known contaminated sites and general

More information

3.11 HAZARDOUS MATERIALS

3.11 HAZARDOUS MATERIALS 3.11 HAZARDOUS MATERIALS 3.11.1 Introduction to Analysis This section provides information regarding known contaminated sites and general areas of potentially contaminated properties along the proposed

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS M. HAZARDS AND HAZARDOUS MATERIALS 1. ENVIRONMENTAL SITE ASSESSMENT

IV. ENVIRONMENTAL IMPACT ANALYSIS M. HAZARDS AND HAZARDOUS MATERIALS 1. ENVIRONMENTAL SITE ASSESSMENT IV. ENVIRONMENTAL IMPACT ANALYSIS M. HAZARDS AND HAZARDOUS MATERIALS 1. ENVIRONMENTAL SITE ASSESSMENT A Phase I Environmental Site Assessment (Phase I ESA) for the proposed project was prepared by Gradient

More information

IV. Environmental Impact Analysis D. Hazards and Hazardous Materials

IV. Environmental Impact Analysis D. Hazards and Hazardous Materials IV. Environmental Impact Analysis D. Hazards and Hazardous Materials 1. Introduction This section provides an analysis of potential impacts that would occur relative to hazards and hazardous materials

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDS AND HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDS AND HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS H. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section of the DEIR evaluates potential hazards and hazardous materials that may result from implementation of the

More information

IV. Environmental Impact Analysis E. Hazards and Hazardous Materials

IV. Environmental Impact Analysis E. Hazards and Hazardous Materials IV. Environmental Impact Analysis E. Hazards and Hazardous Materials 1. Introduction This section provides an analysis of the project s potential impacts relative to hazards and hazardous materials. The

More information

4. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS

4. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS 4. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION The section includes information from the following, which are included as Appendix G to this Draft EIR: G-1 Phase I Environmental

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS AND HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS AND HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section evaluates potential impacts related to hazards and hazardous materials associated with development of the

More information

Chapter 9. Hazards and Hazardous Materials

Chapter 9. Hazards and Hazardous Materials Chapter 9. Hazards and Hazardous Materials This chapter evaluates the potential of the two CWP alternatives to affect public health and safety through exposure to hazards and hazardous materials during

More information

Chapter 11: Hazardous Materials A. INTRODUCTION

Chapter 11: Hazardous Materials A. INTRODUCTION Chapter 11: Hazardous Materials A. INTRODUCTION This chapter relies on the analysis from the Fresh Kills Park Final Generic Environmental Impact Statement (FGEIS) and summarizes the conclusions drawn from

More information

4.14 HAZARDOUS MATERIALS

4.14 HAZARDOUS MATERIALS 4.14 HAZARDOUS MATERIALS INTRODUCTION The presence of hazardous materials is a part of everyday life that could affect residents, workers, and visitors within the County. Certain activities can pose a

More information

4.7 HAZARDS AND HAZARDOUS MATERIALS

4.7 HAZARDS AND HAZARDOUS MATERIALS 4.7 HAZARDS AND HAZARDOUS MATERIALS This section describes the environmental setting (existing conditions and regulatory setting) for hazards and hazardous materials relating to the proposed project, as

More information

4.8 HAZARDS AND HAZARDOUS MATERIALS

4.8 HAZARDS AND HAZARDOUS MATERIALS 4.8 HAZARDS AND HAZARDOUS MATERIALS Would the project: Potentially Significant Impact Less Than Significant Impact With Mitigation Incorporated Less Than Significant Impact No Impact a. Create a significant

More information

4.10 Hazardous Waste and Materials

4.10 Hazardous Waste and Materials 4.10 4.10.1 Regulatory Framework and Methodology 4.10.1.1 Regulatory Framework The applicable federal, state, and local regulations that are relevant to an analysis of the proposed project s hazardous

More information

4.5 HAZARDS AND HAZARDOUS MATERIALS

4.5 HAZARDS AND HAZARDOUS MATERIALS 4.5 HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section identifies the potential for the proposed project to expose the public to hazards, hazardous materials, or risk of upset that may be related

More information

12.0 Contaminated Materials

12.0 Contaminated Materials 12.0 Contaminated Materials 12.1 Introduction An investigation was performed to identify hazardous waste and contaminated material sites in the study area of the Columbia Pike Transit Initiative ( the

More information

F. HAZARDS AND HAZARDOUS MATERIALS

F. HAZARDS AND HAZARDOUS MATERIALS F. HAZARDS AND HAZARDOUS MATERIALS This analysis of the potential hazards and hazardous material impacts associated with the proposed project presented in this section is based on a Phase I site investigation

More information

Memorandum. Rian Amiton; City of Brockton Planning Department. John McRobbie and Thomas Biolsi; TRC Environmental Corporation

Memorandum. Rian Amiton; City of Brockton Planning Department. John McRobbie and Thomas Biolsi; TRC Environmental Corporation TRC Wannalancit Mills 650 Suffolk Street Lowell, Massachusetts 01854 Main 978.970.5600 Fax 978.453.1995 Memorandum To: From: Subject: Rian Amiton; City of Brockton Planning Department John McRobbie and

More information

EXECUTIVE SUMMARY. The following is our conclusions of the environmental issues at the Site based on our investigations:

EXECUTIVE SUMMARY. The following is our conclusions of the environmental issues at the Site based on our investigations: EXECUTIVE SUMMARY Engineers, Inc. (), on behalf of the Town of East Lyme, Connecticut performed a Phase II Environmental Site Assessment (Phase II ESA) on the property located at 224 Main Street (the Site

More information

SOIL MANAGEMENT PLAN

SOIL MANAGEMENT PLAN SOIL MANAGEMENT PLAN BELFAST BOATYARD 39 & 41 FRONT STREET BELFAST, MAINE Prepared by: Ransom Consulting, Inc. 400 Commercial Street, Suite 404 Portland, Maine 04101 (207) 772-2891 March 22, 2013 1.0 INTRODUCTION

More information

Realistic Bomber Training Initiative APPENDIX D. Federal and State Environmental Database Search

Realistic Bomber Training Initiative APPENDIX D. Federal and State Environmental Database Search APPENDIX D Federal and State Environmental Database Search Environmental Databases Federal Databases Last Updated TX Last Updated NM Search Radius (mi) NPL, National Priority List (Superfund Sites) 09/97

More information

APPENDIX M: Hazardous Waste Technical Report

APPENDIX M: Hazardous Waste Technical Report APPENDIX M: Hazardous Waste Technical Report M.1 Existing Conditions A hazardous waste review was conducted to provide preliminary information regarding the potential presence of any hazardous substances

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

4.7 HAZARDS AND HAZARDOUS MATERIALS

4.7 HAZARDS AND HAZARDOUS MATERIALS 4.7 This chapter evaluates the potential environmental impacts related to hazards and hazardous materials in Palo Alto that could occur as a result of Scenarios 5 and 6. This analysis is based on the Regulatory

More information

V. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS

V. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS V. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section summarizes the results of a Phase I Environmental Site Assessment (ESA), a Limited Phase II Soil Sampling and

More information

3.10 HAZARDS AND HAZARDOUS MATERIALS

3.10 HAZARDS AND HAZARDOUS MATERIALS 3.10.1 INTRODUCTION 3.10 HAZARDS AND HAZARDOUS MATERIALS This section describes existing hazards and hazardous materials conditions within and around the project site, including surrounding properties;

More information

4.9 HAZARDS AND HAZARDOUS MATERIALS

4.9 HAZARDS AND HAZARDOUS MATERIALS 4.9 HAZARDS AND HAZARDOUS MATERIALS 4.9.1 INTRODUCTION This section describes hazardous materials and other hazards to public health and safety that could result from implementation of the proposed project.

More information

The following provides summary definitions of hazardous materials and hazardous waste:

The following provides summary definitions of hazardous materials and hazardous waste: 4.8 HAZARDS AND HAZARDOUS MATERIALS 4.8.1 Overview This section of the PEA describes the existing conditions related to hazards and hazardous materials for the proposed (TRTP). The management of hazardous

More information

MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No ) Van Nuys Fire Station 39

MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No ) Van Nuys Fire Station 39 MITIGATION MDNITDRING PROGRAM (Accompanies the Van Nuys Fire Station 39 Environmental Impact Report SCH No. 2015031067) Van Nuys Fire Station 39 W.O. E170094B ENGINEERING mtm CITY OF LOS ANGELES Transmittal

More information

SECTION 9.0 Effects Found Not To Be Significant

SECTION 9.0 Effects Found Not To Be Significant SECTION 9.0 Effects Found Not To Be Significant 9.0 EFFECTS FOUND NOT TO BE SIGNIFICANT The City of Santa Clarita conducted an Initial Study in April 2006 to determine significant effects of the proposed

More information

Section 3.7 Hazards and Hazardous Materials ENVIRONMENTAL SETTING EXISTING PHYSICAL CONDITIONS ENVIRONMENTAL SITE ASSESSMENT

Section 3.7 Hazards and Hazardous Materials ENVIRONMENTAL SETTING EXISTING PHYSICAL CONDITIONS ENVIRONMENTAL SITE ASSESSMENT Section 3.7 Hazards and Hazardous Materials This section evaluates potential hazards and hazardous materials impacts that may result from construction and/or operation of the proposed project. The following

More information

4.15 HAZARDOUS WASTE/MATERIALS

4.15 HAZARDOUS WASTE/MATERIALS Hazardous Materials 4.15 HAZARDOUS WASTE/MATERIALS This section presents the findings of an Initial Site Assessment (ISA) prepared for this Tier 1 Environmental Impact Statement/Environmental Impact Report

More information

4.4 HAZARDS AND HAZARDOUS MATERIALS

4.4 HAZARDS AND HAZARDOUS MATERIALS 4.4 HAZARDS AND HAZARDOUS MATERIALS 4.4.1 Environmental Setting a. Physical Setting. In general, the Specific Plan area is already developed, primarily with commercial uses, but also including some residential

More information

IV. Environmental Impact Analysis E. Hazards and Hazardous Materials

IV. Environmental Impact Analysis E. Hazards and Hazardous Materials IV. Environmental Impact Analysis E. Hazards and Hazardous Materials 1. Introduction This section provides an analysis of potential impacts that would occur relative to hazards and hazardous materials

More information

3.12 PUBLIC SAFETY AND HAZARDOUS MATERIALS

3.12 PUBLIC SAFETY AND HAZARDOUS MATERIALS 3.12 PUBLIC SAFETY AND HAZARDOUS MATERIALS This section evaluates the potential impacts of the proposed project on public safety and hazardous materials. The public safety concerns related to the project

More information

4.7 Hazards and Hazardous Materials

4.7 Hazards and Hazardous Materials This section describes the existing setting related to hazards and hazardous materials based on the current conditions, a regulatory database search for the Project Site and surroundings, and the federal,

More information

Appendix D Phase I Environmental Site Assessment, Soil Sampling and Analysis Report, Soil Management Plan, and Community Health and Safety Plan

Appendix D Phase I Environmental Site Assessment, Soil Sampling and Analysis Report, Soil Management Plan, and Community Health and Safety Plan Appendix D Phase I Environmental Site Assessment, Soil Sampling and Analysis Report, Soil Management Plan, and Community Health and Safety Plan PHASE I ENVIRONMENTAL SITE ASSESSMENT 3838 ORANGE AVENUE

More information

MARYLAND DEPARTMENT OF THE ENVIRONMENT

MARYLAND DEPARTMENT OF THE ENVIRONMENT MARYLA DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Suite 620 Baltimore, Maryland 21230-1719 410-537-3442 800-633-6101 x 3442 www.mde.state.md.us Land Management Administration Oil Control Program

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section summarizes the results of four Phase I Environmental Site Assessments (ESAs) prepared for the various properties

More information

F. HAZARDS AND HAZARDOUS MATERIALS

F. HAZARDS AND HAZARDOUS MATERIALS F. HAZARDS AND HAZARDOUS MATERIALS A Phase I Environmental Site Assessment (1997) (Appendix 8) has been prepared by Law Crandall to identify the presence or absence of hazardous materials on-site, as well

More information

Prepared By: VERTEX Environmental Services, Inc. 400 Libbey Parkway Weymouth, MA May 18, Prepared For:

Prepared By: VERTEX Environmental Services, Inc. 400 Libbey Parkway Weymouth, MA May 18, Prepared For: Phase I Environmental Site Assessment 7 th Street Station 1100 Southwest 7 th Street Corvallis, Oregon 97333 VERTEX Project No. 18683 VERTEX Prepared By: VERTEX Environmental Services, Inc. 400 Libbey

More information

3.7 HAZARDS AND HAZARDOUS MATERIALS

3.7 HAZARDS AND HAZARDOUS MATERIALS 3.7 HAZARDS AND HAZARDOUS MATERIALS 3.7 Hazards and Hazardous Materials This section of the Draft EIR addresses the potential for the Merced General Plan to create hazards to the public or residents of

More information

Project Background. Project Purpose

Project Background. Project Purpose August 21, 2015 Ms. Suzanne Wynn Project Manager Gainesville Community Redevelopment Agency 802 NW 5th Avenue, Suite 200 Gainesville, Florida 32601 Re: Order of Magnitude Estimates for Environmental Assessment/Remediation

More information

Chapter 13: Hazardous Materials A. INTRODUCTION Appendix D-5

Chapter 13: Hazardous Materials A. INTRODUCTION Appendix D-5 Chapter 13: Hazardous Materials A. INTRODUCTION This chapter assesses the potential for increased exposure to environmental contamination or hazardous materials as a result of the Proposed Action both

More information

G. HYDROLOGY Existing Conditions

G. HYDROLOGY Existing Conditions G. HYDROLOGY Existing Conditions Surface Water Runoff This section is based on the hydrology and drainage analysis for the proposed Project, which was prepared by KPFF Consulting Engineers and is attached

More information

OVERVIEW SCOPE OF WORK (SOW)

OVERVIEW SCOPE OF WORK (SOW) Site Description The subject property is occupied by the former Parker Service Station, which contained a former Service Garage (now called Former Garage) and Filling Station Store (now called Storage

More information

2.2.3 Hazardous Materials/Wastes Affected Environment Evaluation Criteria Regulatory Setting. Affected Environment, Environmental

2.2.3 Hazardous Materials/Wastes Affected Environment Evaluation Criteria Regulatory Setting. Affected Environment, Environmental FINAL ENVIRONMENTAL IMPACT REPORT/ 2.2.3 Hazardous Materials/Wastes Hazardous materials are generally substances that, by their nature and reactivity, have the capacity for causing harm or health hazards

More information

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA) DRAFT Analysis of Brownfields Cleanup Alternatives (ABCA) Preliminary Evaluation Ball Square Station Site Boston Avenue and Broadway Somerville and Medford, Massachusetts Massachusetts DEP Release Tracking

More information

4.4 HAZARDS AND HAZARDOUS MATERIALS

4.4 HAZARDS AND HAZARDOUS MATERIALS This section addresses the potential presence of hazardous materials and conditions in the area of the proposed project and analyzes the risks associated with the reconfiguration of the existing interchange

More information

4.7 HAZARDS AND HAZARDOUS MATERIALS

4.7 HAZARDS AND HAZARDOUS MATERIALS 4.7 HAZARDS AND HAZARDOUS MATERIALS 4.7.1 INTRODUCTION This section provides information regarding hazards and hazardous materials in the vicinity of the proposed project area. Following an overview of

More information

3.9 Hazards and Hazardous Materials

3.9 Hazards and Hazardous Materials 3.9 Hazards and Hazardous Materials 3.9.1 Introduction This section describes the hazardous materials or hazardous conditions that could be encountered as a result of implementation of the proposed Expo

More information

4.7 HAZARDS AND HAZARDOUS MATERIALS

4.7 HAZARDS AND HAZARDOUS MATERIALS C I T Y O F L O N G B E A C H D R A F T E N V I R O N M E N T A L I M P A C T R E P O R T 4.7 HAZARDS AND HAZARDOUS MATERIALS This section addresses potential hazards and hazardous material impacts at

More information

FINDINGS CALIFORNIA DEPARTMENT OF TRANSPORTATION FINDINGS FOR THE INTERSTATE 10 CORRIDOR PROJECT SAN BERNARDINO AND LOS ANGELES COUNTIES, CALIFORNIA

FINDINGS CALIFORNIA DEPARTMENT OF TRANSPORTATION FINDINGS FOR THE INTERSTATE 10 CORRIDOR PROJECT SAN BERNARDINO AND LOS ANGELES COUNTIES, CALIFORNIA FINDINGS CALIFORNIA DEPARTMENT OF TRANSPORTATION FINDINGS FOR THE INTERSTATE 10 CORRIDOR PROJECT SAN BERNARDINO AND LOS ANGELES COUNTIES, CALIFORNIA DISTRICT 7 LA 10 (PM 44.0/48.3) DISTRICT 8 SBD 10 (PM

More information

4.6 HAZARDS AND HAZARDOUS MATERIALS Existing Conditions

4.6 HAZARDS AND HAZARDOUS MATERIALS Existing Conditions 4.6 HAZARDS AND HAZARDOUS MATERIALS This section describes the known hazardous materials in the vicinity of the existing Cypress College campus with regard to any hazardous materials or previous contamination

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS I. HAZARDS AND HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS I. HAZARDS AND HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS I. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION The information and analysis presented in this section is primarily based on the following reports (refer to Appendix IV.I):

More information

Johanna Heywood, PE, PG

Johanna Heywood, PE, PG Johanna Heywood, PE, PG MEMPHIS BROWNFIELD WORKSHOP, SEPTEMBER 10, 2014 Past use of the site Chemicals used on-site Surrounding property usage Does not generally confirm or delineate contaminated areas

More information

4.7 HAZARDS AND HAZARDOUS MATERIALS

4.7 HAZARDS AND HAZARDOUS MATERIALS 4.7 HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section describes public health and safety and hazardous materials 1 issues related to development of the proposed project that could potentially pose

More information

65 East Project (P18-045) Addendum to an Environmental Impact Report

65 East Project (P18-045) Addendum to an Environmental Impact Report 65 East Project (P18-045) Addendum to an Environmental Impact Report File Number/Project Name: 65 East Project (P18-045) Project Location and Surrounding Land Uses: The proposed project site consists of

More information

4.5 HAZARDS AND HAZARDOUS MATERIALS Introduction Environmental Setting

4.5 HAZARDS AND HAZARDOUS MATERIALS Introduction Environmental Setting 4.5 HAZARDS AND HAZARDOUS MATERIALS 4.5.1 Introduction This section describes the potential adverse impacts on human health and the environment due to exposure to hazards that could result from development

More information

Phase I Environmental Site Assessment

Phase I Environmental Site Assessment Phase I Environmental Site Assessment 97204 Prepared for: Multnomah County 401 NE Dixon Avenue, Suite 274 97227 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY... 1 2.0 PROPERTY AND REPORT INFORMATION... 3 2.1

More information

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS DIVISION 02 EXISTING CONDITIONS 02 01 00 MAINTENANCE OF EXISTING CONDITIONS 1. Maintenance of site remediation, underground storage tank removal, facility remediation, and hazardous waste drum handling

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS & HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS & HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS E. HAZARDS & HAZARDOUS MATERIALS INTRODUCTION The information and analysis in this section is based primarily on the following reports, which are included in Appendix

More information

Sediment control measures, including straw bales, silt fences, sediment traps and/or sediment basins

Sediment control measures, including straw bales, silt fences, sediment traps and/or sediment basins During final design, additional efforts will be taken to minimize wetland impacts, such as minimizing culvert lengths and the use of riprap for bridge abutment protection and stormwater outfalls. Wetland

More information

5.0 ALTERNATIVE VARIATIONS

5.0 ALTERNATIVE VARIATIONS 5.0 ALTERNATIVE VARIATIONS 5.1 INTRODUCTION The Draft EIR for the Beverly Hilton Revitalization Plan evaluated five alternatives to the project, pursuant to Section 15126.6 of the California Environmental

More information

Appendix C Chapter 1 Initial Site Assessment Worksheet

Appendix C Chapter 1 Initial Site Assessment Worksheet Appendix C Chapter 1 Initial Site Assessment Worksheet Contents Section 1 Overview...1-2...1-3 C-1-1 Section 1 Overview Section 1 Overview Disclaimer The following worksheet is an example and provides

More information

Kaaterskill Associates Surveyors, Architects and Engineers

Kaaterskill Associates Surveyors, Architects and Engineers Kaaterskill Associates Surveyors, Architects and Engineers PO Box 1020 Cairo, NY 12413 Phone (518) 622-9667 Fax (518) 622-9047 www.keaeng.com contactus@keaeng.com September 16, 2013 GCSW Watershed Assistance

More information

Atlanta SMAC Conference April 18, 2017

Atlanta SMAC Conference April 18, 2017 Atlanta SMAC Conference April 18, 2017 New Construction Pre-Application Training 3 rd Party Environmental Phase I ESA Scope of Work Compliance with NEPA and other related Federal and state environmental

More information

Tier 1 Vapor Migration Screening for Property Transactions Using ASTM E

Tier 1 Vapor Migration Screening for Property Transactions Using ASTM E Tier 1 Vapor Migration Screening for Property Transactions Using ASTM E2600-15 Presented by Todd Elmore, EDR Business Development Manager Southeast Atlantic Southeastern States Vapor Intrusion Symposium

More information

5.8 HAZARDS AND HAZARDOUS MATERIALS

5.8 HAZARDS AND HAZARDOUS MATERIALS 5.8 This section evaluates the potential impacts of the proposed Project on human health and the environment due to exposure to hazardous materials or conditions associated with the Project area, Project

More information

SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE

SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE MARCH 19, 2015 JN: 12-3259.1 Report Prepared by: Summit Environmental Consultants 640 Main Street Lewiston, Maine

More information

HAZARDS AND HAZARDOUS MATERIALS

HAZARDS AND HAZARDOUS MATERIALS IV.E HAZARDS AND HAZARDOUS MATERIALS 1. INTRODUCTION This section addresses the Project s potential environmental impacts related to hazards and hazardous materials, including analysis of surrounding uses

More information

II. Corrections and Additions to the Draft EIR

II. Corrections and Additions to the Draft EIR II. Corrections and Additions to the Draft EIR II. Corrections and Additions to the Draft EIR This section of the Final EIR provides changes to the Draft EIR that have been made to clarify, correct, or

More information

A-8: Hazardous, Toxic and Radioactive Waste Analysis. Environmental Site Assessment: Phase I

A-8: Hazardous, Toxic and Radioactive Waste Analysis. Environmental Site Assessment: Phase I A-8: Hazardous, Toxic and Radioactive Waste Analysis Environmental Site Assessment: Phase I JCER HTRW Appendix 1.0 Introduction In order to complete a feasibility level HTRW evaluation for the Jefferson

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to

More information

5.10 HAZARDOUS/REGULATED MATERIALS

5.10 HAZARDOUS/REGULATED MATERIALS 5.10 HAZARDOUS/REGULATED ATERIALS 5.10.1 ESA Report Summary A Phase I Environmental Site Assessment (ESA) was performed by LOPEZGARCIA GROUP (LGGROUP) in order to identify significant environmental concerns

More information

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 DECISION DOCUMENT Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 Prepared by Division of Environmental Remediation New York State Department of Environmental

More information

IV.E. HYDROLOGY AND WATER QUALITY

IV.E. HYDROLOGY AND WATER QUALITY IV.E. HYDROLOGY AND WATER QUALITY The following section presents the information provided in the hydrology report prepared by Sukow Engineering. Supporting hydrology data from this report is included in

More information

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008 FINAL PLAN OF REMEDIAL ACTION Burns and McBride South Market and A Streets August 19, 2008 Wilmington, Delaware DNREC Project No. DE-0325 This Revised Final Plan of Remedial Action (Final Plan) presents

More information

6.13 Utilities and Service Systems

6.13 Utilities and Service Systems 6.13 6.13.1 Introduction This section describes impacts for utilities and service systems that would result from construction and operation of the CEQA Alternatives. 6.13.2 Regulatory Setting There are

More information

SANTIAGO HILLS II PLANNED COMMUNITY No mitigation was included in 2000 SEIR No new mitigation is required.

SANTIAGO HILLS II PLANNED COMMUNITY No mitigation was included in 2000 SEIR No new mitigation is required. Section 3O Hazards and Hazardous Materials 3O.1 Summary The following is a summary of the proposed project s potential impacts to hazards and hazardous materials, any necessary mitigation measures, and

More information

Kaaterskill Associates

Kaaterskill Associates Kaaterskill Associates Surveyors, Architects and Engineers PO Box 1020 Cairo, NY 12413 Phone (518) 622-9667 Fax (518) 622-9047 www.keaeng.com contactus@keaeng.com January 15, 2014 Michelle Yost GCSW Watershed

More information

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation November 2013 FACT SHEET Brownfield Cleanup Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: West 28th

More information

Orange County Central Utility Facility Upgrade IP

Orange County Central Utility Facility Upgrade IP MITIGATION MONITORING AND REPORTING PROGRAM The California Public Resources Code, Section 21081.6, requires that a lead or responsible agency adopt a mitigation monitoring and reporting plan when approving

More information

5. Environmental Analysis

5. Environmental Analysis 5.6 This section evaluates the potential impacts of the proposed project on human health and the environment due to exposure to hazardous materials or conditions associated with the project site, project

More information

Appendix E. Phase I Environmental Site Assessment

Appendix E. Phase I Environmental Site Assessment Appendix E Phase I Environmental Site Assessment This page intentionally left blank. Phase I Environmental Site Assessment Wasilla Main Street Rehabilitation Wasilla, Alaska February 2012 Submitted To:

More information

PHASE I ENVIRONMENTAL SITE ASSESSMENT. Block Island Power Company Ocean Avenue Assessor's Plat 17, Lots 35, 36, 37 & 40 New Shoreham, Rhode Island

PHASE I ENVIRONMENTAL SITE ASSESSMENT. Block Island Power Company Ocean Avenue Assessor's Plat 17, Lots 35, 36, 37 & 40 New Shoreham, Rhode Island 172 Armistice Boulevard Pawtucket, RI 286 PHASE I ENVIRONMENTAL SITE ASSESSMENT Block Island Power Company Ocean Avenue Assessor's Plat 17, Lots 35, 36, 37 & 4 New Shoreham, Rhode Island Prepared for:

More information

City of Bishop. Environmental Checklist Form

City of Bishop. Environmental Checklist Form City of Bishop Environmental Checklist Form 1. Project title: Environmental Review / 2007 California Building Codes 2. Lead agency name and address: City of Bishop 377 W. Line Street Bishop, Ca 93514 3.

More information

FACTS ABOUT: Vapor Intrusion

FACTS ABOUT: Vapor Intrusion Maryland Department of the Environment FACTS ABOUT: Vapor Intrusion The Land Restoration Program (LRP) is charged with assessing and cleaning up uncontrolled hazardous waste sites throughout Maryland to

More information

3.7 HAZARDOUS MATERIALS / HUMAN HEALTH

3.7 HAZARDOUS MATERIALS / HUMAN HEALTH 3.7 HAZARDOUS MATERIALS / HUMAN HEALTH This section addresses the potential presence of hazardous materials and conditions on the project site and in the vicinity, and analyzes the risks associated with

More information

3.6 HAZARDS AND HAZARDOUS MATERIALS 2010

3.6 HAZARDS AND HAZARDOUS MATERIALS 2010 3.6 HAZARDS AND HAZARDOUS MATERIALS 2010 The purpose of this section is to disclose and analyze the potential impacts associated with hazards and hazardous materials related to the project site and general

More information

3.3 Hazardous Materials, Toxics, and Safety

3.3 Hazardous Materials, Toxics, and Safety 3.3 Hazardous Materials, Toxics, and Safety This section analyzes the effect of the City of Emeryville General Plan Update on hazardous materials, toxics and safety. It includes a definition of hazardous

More information

PHASE I ENVIRONMENTAL SITE ASSESSMENT REPORT

PHASE I ENVIRONMENTAL SITE ASSESSMENT REPORT PHASE I ENVIRONMENTAL SITE ASSESSMENT REPORT AIP #74 Various Properties South Burlington, Vermont 05403 October 14, 2011 Prepared for: Stantec Consulting Inc. 55 Green Mountain Drive South Burlington,

More information

Phase I and Phase II Environmental Site Assessments

Phase I and Phase II Environmental Site Assessments Phase I and Phase II Environmental Site Assessments Society of Women Environmental Professionals Capital Chapter Ira Walton Environmental Director United Environmental Services, Inc. May 1, 2018 Who Needs

More information

5.7 HAZARDS AND HAZARDOUS MATERIALS

5.7 HAZARDS AND HAZARDOUS MATERIALS 5.7 HAZARDS AND HAZARDOUS MATERIALS This chapter addresses hazards and hazardous materials in the Project area, provides an overview of public safety issues specific to the City of Fontana, and evaluates

More information

RISK BASED CLOSURE ALTERNATIVE TO REMEDIATION AT AN URBAN SITE. Brian H. Hackett CP, EMS LLC January 17, 2011

RISK BASED CLOSURE ALTERNATIVE TO REMEDIATION AT AN URBAN SITE. Brian H. Hackett CP, EMS LLC January 17, 2011 RISK BASED CLOSURE ALTERNATIVE TO REMEDIATION AT AN URBAN SITE Brian H. Hackett CP, EMS LLC January 17, 2011 OVERVIEW This presentation will illustrate the use of the Ohio Voluntary Action Program (OVAP)

More information

The following presents a brief summary of Proposed Project effects found not to be significant, including reasons why they would not be significant.

The following presents a brief summary of Proposed Project effects found not to be significant, including reasons why they would not be significant. VII. EFFECTS FOUND NOT TO BE SIGNIFICANT 1. INTRODUCTION This section of the EIR provides information regarding impacts of the Proposed Project that were determined to be less than significant by the City

More information