SUBMISSION TO THE RENEWABLE ENERGY (ELECTRICITY) AMENDMENT (EXCESSIVE NOISE FROM WIND FARMS) BILL 2012

Size: px
Start display at page:

Download "SUBMISSION TO THE RENEWABLE ENERGY (ELECTRICITY) AMENDMENT (EXCESSIVE NOISE FROM WIND FARMS) BILL 2012"

Transcription

1 SUBMISSION TO THE RENEWABLE ENERGY (ELECTRICITY) AMENDMENT (EXCESSIVE NOISE FROM WIND FARMS) BILL 2012 By Andrea Strong on behalf of the Community for the Accurate Impact Assessment of the Dalton Power Station (CAIAD) I am the owner of a farming property near Dalton, NSW. Our property is in close proximity to the site where AGL has recently received approval to construct the largest open cycle gas fired power station ever built in Australia. Through my involvement in the Dalton project environmental assessment (EA) process it is evident that many of the noise issues relevant to wind farms are the same as those faced by residents living nearby open cycle gas fired power stations. In literature discussing problems of low frequency noise, open cycle gas fired power stations are at the top of the list of low frequency noise emitting industries. The Dalton EA process has highlighted serious deficiencies in government policy in protecting communities from the low frequency noise associated with electricity generating infrastructure. The adverse impacts felt by individuals and communities from approvals of such infrastructure developments under past and present assessment criteria clearly demonstrate that Australia needs to establish criteria based on international best practise for controlling low frequency noise in order to maintain the correct balance between the need for industrial development and the preservation of the acoustic amenity of our rural environment. Recently AGL has suspended the Dalton project citing falling electricity demand as the reason for putting this project on hold. However the proponent has 5 years from the date of approval to commence construction before approval lapses. So our community still faces the real prospect of lost acoustic amenity if the project does go ahead. Our concerns about the noise issues associated with the Dalton project were reinforced when we spoke to residents neighbouring another recently commissioned open cycle gas fired power station in NSW at Uranquinty near Wagga Wagga. Uranquinty was commissioned in Recent reports indicate up to 10 farming families have left the Uranquinty area because of intolerable noise generated by that facility. A. SPECIFIC ISSUES RELATING TO LOW-FREQUENCY NOISE The specific issues relating to low frequency noise are summarised by the UK Department for Environment, Food and Rural Affairs (DEFRA) as follows: 1. Low frequency noise is not attenuated to the same extent as mid and high frequency noise by travelling through the atmosphere and across the surface of the earth. This means that as sound travels its frequency content changes making low frequencies more prominent at greater distances. 2. For people inside buildings with windows closed, this effect is exacerbated by the sound insulation properties of the building envelope. Again mid and high frequencies are attenuated to 1

2 a much greater extent than low frequencies. Thus the frequency content again alters emphasising still further the low frequency content. 3. Resonance can be set up inside a room with nodes (quiet points) and anti-nodes (loud points). The number and position of these nodes and anti-nodes will depend on the specific room dimensions and the frequency of the noise. The consequence is that the room resonances can cause elevated levels of low frequency noise at points within a room. 4. People s hearing tends to deteriorate with age, but not equally across the frequency spectrum. Hearing deteriorates more rapidly at the mid and higher frequencies than at the lower frequencies which means that older people s hearing tends to be proportionately more acute at low frequencies. 5. It has been postulated that some people exhibit discrete peaks in their hearing threshold. This means that a sound could appear tonal to one person but not to another. These characteristics of low frequency noise and the nature of human response to low frequency noise mean that: distances between the industry and dwellings must be much greater; at receptor mitigation such as double glazing a dwelling is unlikely to be an effective remedy and may in fact make the problem worse; and farmers with hearing loss are likely to be a population particularly sensitive to low frequency noise. The Uranquinty case A large number of families for this small community in a 2.5km radius have been bought out by the recently commissioned Uranquinty gas fired power station because of intolerable low frequency noise levels. At the time we wrote our submission in response to the Dalton EA, five families neighbouring the Uranquinty gas fired power station had gone, two more families were in negotiation to go, and another two were being paid compensation. More recent reports put the loss of families to the district at 10. Uranquinty residents comment they can feel vibrations through the ground and that windows rattle even as far as 4 to 5km away. They say: The vibrations are often felt separately to the low frequency noise. They can be noticed through the rattling of windows or felt through the body. If you stand in certain parts of our house you can feel the vibration reverberate through your body from the floor. It is quite an unpleasant feeling when a combination of both vibration & low frequency is felt. Neighbours with 'hearing loss' (which is many of the male farmers) are affected more by the low frequency emissions than those with 'full hearing'. The EA for the Dalton power project didn t assess vibrations from the plant. It said "Gas turbine plant operate at high rotational speed and are very sensitive to vibration and hence very well 2

3 balanced preventing vibration at levels that could be intrusive to surrounding receptors." (AGL and URS 2011, p12-7). When we discussed the reports of vibrations from Uranquinty power station with the EPA they said although residents thought they were feeling vibrations, the vibrations were in fact most likely a manifestation of the low frequency noise. No assessment as to whether low frequency noise would cause a vibration sensation was undertaken in the EA for Dalton. Residents at Uranquinty talked about feeling the need to escape the noise and that they would get in their cars and drive into town to get away from the noise, walking the streets aimlessly and hoping the power station that operates in periods of peak electricity demand would have ceased operating by the time they got home. They discussed the sensation of low frequency noise as something indefinable. The effects however were more tangible and included symptoms of nausea, faintness and "vertigo". The affected residents at Uranquinty are bound by confidentiality agreements having won a legal battle over noise with the plant operator. The lawyer for the residents said he had never seen a case like it. Stoic farmers, not easily rattled by adverse environmental circumstances having endured terrible droughts and bushfires, were coming into his office one after another and breaking down because of the impact the power station had had on their family s quality of life and health. In some cases their farms had been in the family for four generations but the family was finding the noise intolerable and wanted to leave. The Uranquinty power station at 640MW is less than half the size of what was initially proposed at Dalton (a 1500MW power station), and less than two thirds the size of the approved 1000MW Dalton power station. Nevertheless Uranquinty has not been able to meet the EPA noise limits once commissioned despite retro fitting noise abatement measures. When we lodged our submission in response to the EA of the Dalton power station, the owner of the Uranquinty power station was in litigation with the turbine manufacturer and had spent $60million on abatement measures which seemed to make the problem worse rather than better. Our concern at Dalton is that if Uranquinty couldn t meet noise limits with a smaller number of the quieter E class turbines, and AGL proposes to construct with a larger number of the larger noisier F class turbines, then it would seem impossible to prevent unacceptable adverse noise impacts on neighbouring properties. AGL argued that they had done a better job than the Uranquinty gas fired power station at buying surrounding properties to ensure a better buffer between impacted neighbours. There are three reasons why AGL s argument that they have done a better job is incorrect: 1. Low frequency noise is not attenuated effectively by distance so distance from residences is less important than using quieter technology; 2. Dalton is much bigger than Uranquinty and is using noisier technology; and 3. There are in fact a number of dwellings in close proximity to the proposed site. There are three dwellings less than 2.5km from the Dalton site and many a little further out, including the town of Dalton 3.7km away. As residents 2.5km away have been forced from their 3

4 homes in the case of the smaller Uranquinty power station, it would seem the proposed AGL power station, being much larger, will cause significant adverse noise impacts. A map showing the location of residences near the Dalton power station site is shown in Appendix B of this submission. A map, included in our submission in response to the Dalton EA, showing the location of residences near the Uranquinty power station site, where families have left their homes, are in negotiations to leave, or are being paid compensation for noise, is shown in Appendix A of this submission. The inability of the Uranquinty gas fired power stations to meet noise controls once in operation isn t an isolated incident. The Alice Springs case The submission by Canberrans for Power Station Relocation (CPR) Inc to the development proposal for the Tuggeranong 210MW gas turbine power station says the proposed Titan 130 turbines when installed actually produced dba rather than the 87 dba as claimed in the Tuggeranong Noise Assessment. They say that.. the Titan 130, installed at the Ron Goodin Power Station (RGPS) in Alice Springs, produces dba and they apparently cannot get it anywhere near the suggested 87dBa. This is detailed in the comprehensive report which was published in January 2007 (Full report - on_goodin_power_station.htm ) On page 7 of the RGPS report it states: This real world example indicates that a Titan 130 produces levels somewhere between 99.2 and dba which is much higher than Bassett s base data of 87dBa. This once again, calls into serious question the quality of the Noise Assessment. This situation is even more extraordinary when you consider that the above report was commissioned AFTER approximately $800,000 was spent in an effort to reduce the noise to an acceptable level. The Laverton case They failed, so the generator is being moved 25 km out of Alice Springs. Full details can be found here: The original licence for the Laverton North power station only allowed the power station to operate for 10% of the year, but in May 2007 the Victorian Civil and Administrative Tribunal ordered that the plant remain shutdown on weekdays between 8am and 5pm, due to the neighbouring offices being affected by the level of noise and vibration. The restriction on operation was removed in July 2007 because of the drought which was impacting on alternate hydro peaking capacity. 4

5 Herald Sun, May 11, 2007: A POWER station that supplies extra energy in the summer peak has closed in business hours because of health risks. By Wayne Flower The Snowy Hydro gas-fired power station in Laverton North will halt at 8am today after Victorian Civil and Administrative Tribunal deputy president Helen Gibson issued an interim enforcement order. The order follows complaints by office workers across the road from the plant about the level of noise and vibration emanating from the unmanned station. Metroll Victoria general manager Frank Collett said most of the company's 20 office staff had reported headaches, nausea, ear aches and other adverse health effects since the plant fired up last November. The order, which will remain in place until at least July 29 when the matter heads back to VCAT, means the plant will be unable to operate between 8am and 5pm on weekdays. B. PROBLEMS WITH THE ENVIRONMENTAL ASSESSMENT OF THE DALTON POWER STATION AS INDICATORS OF DEFICIENCIES IN THE ASSESSMENT PROCESS GENERALLY The environmental assessment of the Dalton power project, with respect to noise was undertaken with reference to the NSW Industry Noise Policy (INP). The NSW INP and the environmental assessment had problems for the community for a number of reasons. 1. The INP ignores very low ambient noise in a rural environment 2. The INP ignores that power stations are being sited in populations more susceptible to annoyance by low frequency noise 3. Under the NSW INP the proponent is exempt from meeting the noise criteria in adverse weather conditions and these conditions occur most of the time in the region. 4. No noise data were available for the proposed power station stacks so the proponent assumed the noise for the stacks wouldn t exceed limits 5. Instead of a 5dB(A) penalty on the intrusiveness criteria because of the presence of low frequency noise, a db(c) limit is introduced 1. The INP ignores very low ambient noise in a rural environment The NSW Industry Noise Policy (INP) assessment process has problems for people living in a rural area because it doesn t take into account the very low ambient noise levels in the bush. 5

6 People in urban areas don t seem as affected by these developments as farmers. This may be because towns have a higher level of ambient sound. Often farmers may be closer to the developments, but an important factor seems to be that they are going from a no noise environment to a noise environment. This isn t taken into account in the NSW INP assessment process as the Rating Background Level (RBL) of noise, if found to be less than 30 db(a), is raised to 30 db(a). For instance at one location near the Dalton site, the RBL during the day and at night was found to be 25dB(A). As this is less than 30dB(A), for assessment purposes, this was raised to 30dB(A) and the Intrusive Noise Criteria is set at 5 db(a) above this, i.e.35db(a). This allows the power station to increase noise levels by up to 10 db(a) (35 db(a) criteria less 25 db(a) actual RBL). In an urban situation where the RBA is 30dB(A), industry can only raise ambient noise 5dB(A). It is noted that the WHO guidelines for community noise states that noise has the potential to disrupt tranquillity and existing quiet outdoor areas should be preserved, On many properties, waterways and old remnant stands of trees are fenced off for conservation purposes, and should have their tranquillity preserved. It is also noted that the Interim Guidelines for the Control of Noise from Industry in Country Victoria, EPA Publication No N3/89, 2010 makes provision for lower noise limits in areas where background sound levels are very low (i.e. <25). This suggests that governments are beginning to recognise that allowing noise generating industry in areas of otherwise very low ambient noise has problems. 2. The INP ignores that power stations are being sited in populations more susceptible to annoyance by low frequency noise The aim of the NSW INP is to protect at least 90 per cent of the population living in the vicinity of industrial noise sources from the adverse effects of noise for at least 90 per cent of the time. The Dalton power station is being located in a population expected to be sensitive to low frequency noise, farmers with hearing loss, and therefore more stringent controls are needed to protect that community from annoyance by low frequency noise. 3. The proponent is exempt from meeting the noise criteria in adverse weather conditions The proponent predicted adverse weather conditions would only increase noise 3-4db and therefore noise won t exceed the criteria in these conditions. However the NSW INP says adverse weather conditions generally increase noise by 5-10db and up to 20db. Our community raised concerns that the proponent had seriously underestimated the impacts of weather on noise propagation. The conditions of consent for the power station currently exempt AGL meeting 35dBa intrusiveness criteria under certain weather conditions. The weather conditions when AGL is not required to meet the noise criteria are when wind exceeds 4m/s and during strong G class temperature inversions. In the Dalton region wind speeds exceed 4m/s 50% of the time 6

7 and G class stability conditions are estimated to occur 15% of the time. Therefore for 65% of the time there are no limits on the noise the power station can make. Exempting industry from meeting noise controls during certain weather conditions has been a problem for the people Uranquinty. Residents there claimed that the power station exceeded limits but the plant operator said those noise events were excluded from the noise sampling as the weather conditions were propagating the noise. However the propagation of noise by the prevailing weather conditions was and is part of the problem for the residents. 4. No noise data were available for the proposed power station stacks so the proponent assumed the noise for the stacks wouldn t exceed limits Quite extraordinarily in a footnote to Table 5-4 (Appendix G) of the Dalton EA it is stated that the Sound power level of the exhaust stack has been estimated based on the maximum cumulative sound power level the site can generate in order to meet noise limits. To ensure the compliance with the noise limit, sound power level of exhaust stack opening and body combined should not exceed 110 db(a). This assumption and subsequent testing seemed completely without scientific rigour. It is assumed the stacks wont emit more than 110 db(a), and then this figure is put into the model to see if it exceeds the noise limits. By assumption it doesn t. 5. Instead of a 5dB(A) penalty on the intrusiveness criteria because of the presence of low frequency noise, a db(c) limit is introduced There is an urgent need for a comprehensive review of competing international assessment criteria to be undertaken rather than allowing proponents to propose criteria which suit their applications. The Dalton project failed to meet existing NSW INP noise criteria for low frequency noise and the proponent successfully argued for their project to be assessed against another criteria. NSW INP is a whole of government agreed position on industry noise and has been developed with all stakeholders involved: industry; the community; and government. It is essential we have robust best practise policy that cannot be altered when a proponent fails to satisfy the criteria. The current NSW INP controls industry noise by intrusiveness and amenity criteria. The intrusiveness criteria was the relevant constraint in the Dalton case, limiting noise emissions to 35dB(A) at the closest receptor. Under the NSW INP if the noise has annoying characteristics such as low frequency elements and/or tonality a penalty of 5dBA is applied for each annoying characteristic which effectively reduces the criteria to 30dBa for the first penalty and 25dBa for the second. The NSW INP guidelines say the 5dBa penalty needs to be applied if the difference between the A and C weighted levels is greater than 15. The NSW guidelines are less stringent than 7

8 the WHO guidelines which state that low frequency should be considered if the difference between the A and C weighted levels is more than 10 ( Although the Dalton Gas Fired power station substantially exceeded the INP difference approach for assessing low frequency noise impacts, the EA successfully argued recent literature by Broner (2008) indicated the INP difference approach is not suitable for use in assessments when the noise levels are low (AGL and URS 2011, p12-24). As such, no 5db(A) penalty was applied to the intrusiveness criteria for low frequency noise. Instead a direct control on low frequency noise was applied. DP&I argued a direct control on low frequency noise would better protect the community. DP&I said The EPA has advised that alternative approaches to low frequency noise are being investigated. However, they have not sufficiently progressed to an agreed industry standard. Once finalised, it is expected that an Application Note to the NSW Industrial Noise Policy will be prepared to guide the assessment of low frequency noise. Discussions have been held between the Department and the EPA Noise Policy Branch regarding the assessment of low frequency noise for the proposed Dalton Power Project. The agreed outcome was that low frequency noise from gas-fired power stations should be regulated on a case-by-case basis until the Application Note to the NSW Industrial Noise Policy is finalised by the EPA. Further, it was considered that the C-A weighting plus 5 db(a) penalty approach as defined in the NSW Industrial Noise Policy, was not a good measure of annoyance, and could result in the application of measures that would not improve environmental outcomes. Consequently, following consultation with the OEH, the Department formed the opinion that the most appropriate criteria for the measurement of noise, and in particular low frequency noise, should be the addition of a db(c) criteria, rather than the NSW Industrial Noise Policy penalty approach. In this respect, the Department has recommended a condition of approval limiting noise levels at the nearest sensitive receivers to 65 db(c) during the day and 60 db(c) during the evening and night, in addition to the maximum allowable noise limit of 35 db(a) during the day, evening and night. The EPA, and subsequently the PAC, has agreed to this approach which is more stringent than that recommended by the OEH in its response to the Submissions Report (Director- General s Environmental Assessment Report, Section 75I of the Environmental Planning and Assessment Act 1979, May 2012, p29). It is important to note that the DP&I and the EPA have accepted the Broner criteria despite the fact that no peer review of the criteria against international best practise has been made available. International standards point to a reference curve with the db limit determined by the Hz level as the best means of controlling low frequency noise. 8

9 Further, no assessment has been carried out to determine whether affected residents nearby other facilities, such as Uranquinty, would have been protected with his criteria. Nor has there been any assessment of the effectiveness of the Broner criteria for preventing sleep disturbance or disturbance inside a dwelling. It is noted that Broner s criteria are criticised as being far too high by the Parkesbourne/Mummel Landscape Guardians Inc. in their submission to the NSW PLANNING GUIDELINES: WIND FARMS: A resource for the community, applicants and consent authorities, pp We contacted Dr Broner to see if his criteria would have protected the community of Uranquinty. He said it would be interesting to review the data from Uranquinty and doing so would allow him to check his proposed criteria ( 6/5/2012). The community questioned why the project was approved before the criteria had been checked and peer reviewed. We also pointed out in a submission to the Planning Assessment Commission (PAC) that the 5dBC penalty on the criteria recommended by Broner, if the low frequency noise is fluctuating, has not been adopted as policy or a condition of consent for the Dalton power project. Broner recommends that his criteria for low frequency noise be reduced to 55dBC (night) and 60dBC (day) if the low frequency noise is fluctuating. The fact that this penalty does not form part of the conditions of consent is a major omission for the community. AGL failed the existing NSW INP difference approach for controlling low frequency noise and argued for using the Broner approach. To then only implement those aspects of the Broner approach with which the proponent is able to comply is very frustrating and unfair for the community and poor government policy. Our please explain letter to the Minister for Planning on this specific issue remains unanswered. One of the reasons DP&I argue for the adoption and application of the Broner db(c) criteria is that it is simple. However, it is submitted that protection of amenity rather than simplicity should be driving criteria selection. C. VITAL CONDITION OF CONSENT The community has had one small win in the Dalton power station approval process. During the consultation the proponent gave a public undertaking to the community that if the Dalton power station exceeded noise limits AGL would shut it down. The PAC recommended that if environmental criteria are exceeded, operation shall be ceased or limited to ensure compliance. The normal process, when industry exceeds environmental noise limits, after the plant is built, is for the power station owner to: i. Mitigate at source retro fit abatement measures to the power station. If that fails then ii. Mitigate at the receptor insulate and double glaze the neighbouring homes. If that fails then iii. Pay compensation. If that fails then 9

10 iv. Acquire the dwelling. This process puts the cost of the power station failing to meet noise limits on the community. There is no incentive to get the noise assessment correct or build plant within noise limits. It is a small cost to a $1.5billion power station owner to buy out affected residents. The requirement that the plant is shut down if it exceeds noise limits puts a big incentive on the owner to get it right. An idle $1.5billion power station is a big incentive to ensure the plant is constructed so noise limits aren t exceeded. The community strongly believes that all development approvals in Australia should require that if environmental criteria are exceeded, operation shall be ceased or limited to ensure compliance. This internalises the noise pollution cost to the proponent and drives noise efficient plant development. CONCLUSION Whether low frequency noise is caused by wind farms, open cycle gas fired power stations or other industry, it is responsible for forcing residents from their homes. Low frequency noise is a complex problem. Much greater separation of industry from dwellings is needed to allow attenuation of low frequency noise and the practise of sound proofing dwellings is largely ineffective. At Uranquinty windows rattle up to 5km away from that open cycle gas fired power station. It is possible to make industry less noisy by spending more money on quieter technology and building smaller plant. Government policy that sets limits on low frequency noise needs to be based on international best practise to encourage industry to invest in plant with better environmental outcomes. Such best practise policy will encourage the equitable balance between industry development and preservation of amenity for residents. The existing low ambient noise in rural environments needs to be taken into account when allowing noise emitting industry in rural areas. Also the characteristics of the population neighbouring noise emitting industry needs to be understood and more stringent controls on low frequency noise are needed where there is a high level of hearing loss in the community. Further it is vital for the protection of acoustic amenity of communities that if plant exceeds noise limits once commissioned, that operation is ceased or limited to ensure compliance with environmental criteria. This puts an incentive on industry do their homework and build plant to meet approved environmental criteria. It also means that it is essential that the criteria are set appropriately and that industry is not exempt from meeting the criteria in weather conditions that occur frequently in a region. 10

11 These industries emitting low frequency noise are being located are peaceful rural areas. The communities in these areas want their tranquillity preserved. 11

12 Appendix A: Appendix A contains details of the families at Uranquinty who have been seriously impacted by noise in excess of NSW INP guidelines. Of the families: 5 have been bought out by Origin and left the area (see Figure A-1 below)- Wyrilla & The Pines were 4th generation families; 2 have taken compensation payments for the next 5 years with the option to be bought out if the noise levels cannot be mitigated; 2 are currently in negotiations with Origin. Residents at Uranquinty say that initially engineers installed prongs into the top of the stacks to reduce the rumbling but have now created low frequency noise and vibration problems. Origin has had engineers from Germany and Canada on site trying to find a solution and is looking at rebuilding the stack configuration at a cost of $60 million. In Figure A-2 the circle with a 2.5km radius shows the location of residents relative to the Uranquinty power station. 12

13 Appendix A: Figure A-1 Figure 13

14 Figure A-2: Radius of 2.5km from the Uranquinty power station and the location of dwellings 14

15 Appendix B: Figure B-1: Radius of 2.5km and 4.5lm from the proposed Dalton power station and the location of dwelling in the Dalton area. 15

Noise Impact Assessment

Noise Impact Assessment APPENDIX C Noise Impact Assessment CBCL Limited Appendices NOISE IMPACT ASSESSMENT PUGWASH WIND FARM, NOVA SCOTIA Client Pugwash Wind Farm Inc. Contact Charles Demond Document No Issue B Status Classification

More information

Gisborne District Council

Gisborne District Council 11.0 NOISE AND VIBRATION... 1 11.1 STRUCTURE OF THIS CHAPTER... 1 11.2 INTRODUCTION... 1 11.3 ISSUES... 2 11.4 OBJECTIVES (NOISE INCLUDING VIBRATION)... 2 11.5 POLICIES (NOISE INCLUDING VIBRATION)... 2

More information

COMPONENTS OF THE NOISE ELEMENT

COMPONENTS OF THE NOISE ELEMENT COMPONENTS OF THE NOISE ELEMENT Definitions Following is a list of commonly used terms and abbreviations that may be found within this element or when discussing the topic of noise. This is an abbreviated

More information

Possible Impacts of Low Frequency Wind. Rita B. Messing, Ph.D. Carl Herbrandson, Ph.D. Risk Assessment Course, Feb. 2011

Possible Impacts of Low Frequency Wind. Rita B. Messing, Ph.D. Carl Herbrandson, Ph.D. Risk Assessment Course, Feb. 2011 Possible Impacts of Low Frequency Wind Turbine Noise on Public Health Rita B. Messing, Ph.D. Carl Herbrandson, Ph.D. Risk Assessment Course, Feb. 2011 Environmental Review of LWECS in Minnesota Large Wind

More information

hard reflecting surfaces close by (such as tall buildings) increasing noise levels by up to 3dB(A)

hard reflecting surfaces close by (such as tall buildings) increasing noise levels by up to 3dB(A) Noise Definition Noise is generally defined as unwanted sound. The noise from a fleet of heavy plant working twelve hours a day within 50m of some houses and always within 500m of a residential property

More information

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS 23 rd International Congress on Sound & Vibration Athens, Greece 10-14 July 2016 ICSV23 USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS Chris Skinner, Paul Shields and Yuyou Liu AECOM,

More information

CHAPTER 8 NOISE NORTHAMPTON GATEWAY

CHAPTER 8 NOISE NORTHAMPTON GATEWAY CHAPTER 8 NOISE NORTHAMPTON GATEWAY 8 NOISE & VIBRATION 8.1 INTRODUCTION 8.1.1 8.1.2 8.1.3 8.1.4 8.1.5 This chapter considers the potential noise and vibration effects that may arise as a result of the

More information

APPENDIX 8. Noise Impact Assessment

APPENDIX 8. Noise Impact Assessment APPENDIX 8 Noise Impact Assessment Orica Australia Pty Limited Noise Impact Assessment for Proposed Ammonium Nitrate Emulsion Production Facility and Continued Operation of Orica Mining Services Technology

More information

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE Technical Report Prepared For Ardstone Capital Ltd. 48 Fitzwilliam Square Dublin Technical Report

More information

Noise Control and Impact Assessment at Health Canada

Noise Control and Impact Assessment at Health Canada Health Santé Noise Control and Impact Assessment at Health Stephen Bly Acoustics Division Health Santé Noise Control in other Federal Departments (some examples) CANADA LABOUR CODE PART II occupational

More information

WINDFARMperception Visual and acoustic impact of wind turbine farms on residents

WINDFARMperception Visual and acoustic impact of wind turbine farms on residents Project no. 044628 WINDFARMperception Visual and acoustic impact of wind turbine farms on residents FP6-2005-Science-and-Society-20 Specific Support Action Publishable Final Activity Report Period covered:

More information

Noise Forum Conference 20 May The UK National Noise Incidence Study 2000/2001

Noise Forum Conference 20 May The UK National Noise Incidence Study 2000/2001 Noise Forum Conference 20 May 2002 CIEH, Chadwick Court, 15 Hatfields, London SE1 8DJ The UK National Noise Incidence Study 2000/2001 C.J. Skinner & C.J. Grimwood, BRE, Watford, WD25 9XX 1 The UK National

More information

THE RESULTS OF AN ACOUSTIC TESTING PROGRAM CAPE BRIDGEWATER WIND FARM R7:MSC

THE RESULTS OF AN ACOUSTIC TESTING PROGRAM CAPE BRIDGEWATER WIND FARM R7:MSC THE RESULTS OF AN ACOUSTIC TESTING PROGRAM CAPE BRIDGEWATER WIND FARM 44.5100.R7:MSC Prepared for: Level 11, 474 Flinders Street MELBOURNE VIC 3000 Date: The Results of an Acoustic Testing Program Cape

More information

Content Copy Of Original

Content Copy Of Original Content Copy Of Original Ministry of the Environment Ministère de l Environnement ENVIRONMENTAL COMPLIANCE APPROVAL NUMBER 4495-9FUQDY Issue Date: February 5, 2014 Holcim (Canada) Inc. 2300 Steeles Ave

More information

Biodiversity Certification: what it is, how it works

Biodiversity Certification: what it is, how it works Biodiversity Certification: what it is, how it works Nari Sahukar Senior Policy & Law Reform Solicitor, EDO NSW Leumeah, 16 November 2017 About EDO NSW: Community legal centre Independent from Government

More information

Variations of sound from wind turbines during different weather conditions

Variations of sound from wind turbines during different weather conditions Variations of sound from wind turbines during different weather conditions Conny Larsson 1 Olof Öhlund 2 Department of Earth Sciences, Uppsala University, Villavägen 16, SE-752 36 Uppsala, Sweden Long-term

More information

You have applied in accordance with Section 9 of the Environmental Protection Act for approval of:

You have applied in accordance with Section 9 of the Environmental Protection Act for approval of: Ministry of the Environment Ministère de l Environnement CERTIFICATE OF APPROVAL AIR NUMBER 7970-7QNRDJ Issue Date: April 2, 2009 William Day Construction Limited 2500 Elm Street, P.O. Box 700 Copper Cliff,

More information

Crown copyright 2013 Published February 2013 NSW Department of Planning & Infrastructure

Crown copyright 2013 Published February 2013 NSW Department of Planning & Infrastructure Community Consultation associated with Compliance Audits of Cullerin Range, Woodlawn and Capital Wind Farms February 2013 Cover Photograph: Cullerin Range Wind Farm Crown copyright 2013 Published February

More information

APPENDIX C NOISE STUDY TECHNICAL REPORT

APPENDIX C NOISE STUDY TECHNICAL REPORT APPENDIX C NOISE STUDY TECHNICAL REPORT Noise Study Technical Report Watertown South Connector US 81 to 29 th Street SE Watertown, South Dakota HDR Project No. 39319 Prepared by 6300 So. Old Village Place

More information

Environmental Impact Assessment in Western Australia

Environmental Impact Assessment in Western Australia Environmental Impact Assessment in Western Australia Fact Sheet Updated February 2011 An introduction to Environmental Impact Assessment in Western Australia Environmental impact assessment under the Environmental

More information

Environmental Noise Assessment

Environmental Noise Assessment July to September 2014 Rev 0 (Final) Report Details - July to September 2014 Filename: Job #: J0140003 Folder #: F13130 Revision: 0 (Final) Date: Prepared For Clark Potter, Senior Environmental Advisor

More information

DRAFT SUBMISSION REGARDING

DRAFT SUBMISSION REGARDING DRAFT SUBMISSION REGARDING Biodiversity Certification Draft Assessment Methodology DATE July 2010 Opening: The Local Government Association of NSW and Shires Association of NSW (the Associations) are the

More information

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 Claudia Mollina 1 The Environment, Resources and Development

More information

NATIVE VEGETATION REFORMS IN NSW

NATIVE VEGETATION REFORMS IN NSW NATIVE VEGETATION REFORMS IN NSW Australian Centre for Environmental Law 29 September 2004 Peter Cosier Deputy Director General Department of Infrastructure, Planning and Natural Resources Over the past

More information

EARTHQUAKE- PRONE BUILDINGS POLICY

EARTHQUAKE- PRONE BUILDINGS POLICY EARTHQUAKE- PRONE BUILDINGS POLICY 2009 1. Introduction CONTENTS 2. Policy Objectives and Principles 3. Key Policy Components - Assessing earthquake-prone buildings - Standard of strengthening required

More information

Infrasound levels near windfarms and in other environments

Infrasound levels near windfarms and in other environments www.epa.sa.gov.au www.resonateacoustics.com Infrasound levels near windfarms and in other environments Infrasound levels near windfarms and in other environments Page i Infrasound levels near windfarms

More information

WILPINJONG COAL NOISE MANAGEMENT PLAN

WILPINJONG COAL NOISE MANAGEMENT PLAN WILPINJONG COAL NOISE MANAGEMENT PLAN WI-ENV-MNP-0011 June 2017 Document Owner Environmental Advisor Document Approver Environment and Community Manager Version Approval Date Approver Name 3 June 2017

More information

FIGURE N-1 LAND USE COMPATIBILITY FOR NEW DEVELOPMENT NEAR TRANSPORTATION NOISE SOURCES

FIGURE N-1 LAND USE COMPATIBILITY FOR NEW DEVELOPMENT NEAR TRANSPORTATION NOISE SOURCES NOISE ELEMENT OBJECTIVES AND POLICIES Noise Standards N1. To protect the citizens of Arroyo Grande from the harmful and annoying effects of exposure to excessive noise. Policy N1-1 The noise standards

More information

Capital II Wind Farm - Noise Impact Assessment

Capital II Wind Farm - Noise Impact Assessment Capital II Wind Farm - Noise Impact Assessment Capital II Wind Farm Document No.: 50B-10-0075-TRP-773565-2 9 Dec 2010 Vipac Engineers & Scientists Ltd 17-19 King William Street Kent Town SA 5067 Phone:

More information

MEASUREMENT AND LEVEL OF INFRASOUND FROM WIND FARMS AND OTHER SOURCES

MEASUREMENT AND LEVEL OF INFRASOUND FROM WIND FARMS AND OTHER SOURCES MEASUREMENT AND LEVEL OF INFRASOUND FROM WIND FARMS AND OTHER SOURCES Chris Turnbull 1, Jason Turner 1 and Daniel Walsh 2 1 Sonus Pty Ltd, 17 Ruthven Avenue, Adelaide, South Australia 5000 2 Pacific Hydro

More information

Response to the Health Canada Wind Turbine Noise and Health Study: Summary of Results. John Harrison

Response to the Health Canada Wind Turbine Noise and Health Study: Summary of Results. John Harrison Response to the Health Canada Wind Turbine Noise and Health Study: Summary of Results John Harrison Introduction The Health Canada manuscript: Wind Turbine Noise and Health Study Summary of Results has

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

Law enforcement on proactive protection of noise and vibration pollution for

Law enforcement on proactive protection of noise and vibration pollution for Law enforcement on proactive protection of noise and vibration pollution for residential in Thailand Thalearngsak Petchsuwan Director of Air Quality and Noise Management Bureau Pollution Control Department

More information

EPA GUIDANCE NO. 8 ENVIRONMENTAL NOISE

EPA GUIDANCE NO. 8 ENVIRONMENTAL NOISE EPA GUIDANCE NO. 8 ENVIRONMENTAL NOISE Draft for public and stakeholder review Seminar Presented by Environmental Noise Management and SVT Engineering Consultants 25 June 2007 Overview Development of Guidance

More information

Section 75J of the Environmental Planning & Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979 Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 I approve the project application referred to in schedule 1, subject to the conditions in schedule 2. These conditions are

More information

Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan (CNVMP)

Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan (CNVMP) SMC&S-C2S: SYAB Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan () 1/74 Sydney Metro City and Southwest Sydney Yard Access Bridge Construction

More information

Urban Development Institute of Australia Western Australian Division Incorporated

Urban Development Institute of Australia Western Australian Division Incorporated Our Ref: 22.20 29 th April 2005 Swan River Trust PO Box 6740 Hay St, East Perth WA 6892 Attn: Darryl Miller Dear Sir, Draft Swan and Canning Rivers Management Bill 2005 The Urban Development Institute

More information

Noise Impact Assessment. For Proposed Extension to Landfill Operations. Gowy Landfill Site Ince Lane Chester. For. FCC Environment

Noise Impact Assessment. For Proposed Extension to Landfill Operations. Gowy Landfill Site Ince Lane Chester. For. FCC Environment 56a Leabrooks Road Somercotes Derbyshire DE55 4HB Tel No: 01773 607483 Fax No:01773 603331 e-mail: drk.nvc@btopenworld.com For Proposed At Gowy Landfill Site Ince Lane Chester For Report No.: R16.0605/DRK

More information

NSW Planning Assessment Commission Determination Report Gullen Range Wind Farm Project (MP07_0118), Upper Lachlan Shire LGA

NSW Planning Assessment Commission Determination Report Gullen Range Wind Farm Project (MP07_0118), Upper Lachlan Shire LGA 2 October 2014 NSW Planning Assessment Commission Determination Report Gullen Range Wind Farm Project (MP07_0118), Upper Lachlan Shire LGA Background The Gullen Range Wind Farm Project was granted approval

More information

APPENDIX C. Environmental Noise Assessment

APPENDIX C. Environmental Noise Assessment APPENDIX C Environmental Noise Assessment This page intentionally left blank. Environmental Noise Assessment San Joaquin Valley Christian School Merced County, California BAC Job # 2015-085 Prepared For:

More information

NSW Planning Renewable Energy Development. July 2017

NSW Planning Renewable Energy Development. July 2017 NSW Planning Renewable Energy Development July 2017 Contents 1. Overview of the renewable energy industry 2. Legislative framework for development 3. Development assessment framework 4. New guidelines

More information

ADVERSE IMPACTS FROM WIND TURBINES IN WAUBRA, AUSTRALIA AND SURROUNDING AREA

ADVERSE IMPACTS FROM WIND TURBINES IN WAUBRA, AUSTRALIA AND SURROUNDING AREA Green & Ribnick "Adverse impacts from wind turbines in Australia" 2/9/11 Page 1 of 9 We have spent almost one year attempting to understand the complexities of wind energy. We have researched the potential

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

H2. Residential Rural and Coastal Settlement Zone

H2. Residential Rural and Coastal Settlement Zone H2. Residential Rural and Coastal Settlement Zone H2.1. Zone description The Residential Rural and Coastal Settlement Zone applies to rural and coastal settlements in a variety of environments including

More information

Theme Comment Response. All neighbours should be entitled to revenue sharing, not just those who have signed an option agreement with Suncor.

Theme Comment Response. All neighbours should be entitled to revenue sharing, not just those who have signed an option agreement with Suncor. The following table summarizes the comments provided during and after the October 3 rd, 2012 Public Meeting for the Suncor Energy Adelaide Wind Project (the Project) via the questionnaire and email. The

More information

4. Submitting a project for ENTRUST approval

4. Submitting a project for ENTRUST approval 4. Submitting a project for ENTRUST approval 4.1 The project approval process The project approval process ensures that proposed LCF expenditure is in compliance with the Regulations. No LCF monies may

More information

4.10 NOISE. A. Fundamental Concepts of Environmental Acoustics

4.10 NOISE. A. Fundamental Concepts of Environmental Acoustics 4.10 This section evaluates the noise impacts upon existing and future noise sensitive receivers in and around the project area. The chapter includes background information on acoustics, a summary of the

More information

Clean Air for New South Wales Submission from Asthma Foundation Queensland and New South Wales

Clean Air for New South Wales Submission from Asthma Foundation Queensland and New South Wales Clean Air for New South Wales Submission from Asthma Foundation Queensland and New South Wales Ms Tanya Raineri Senior Manager Advocacy, Policy and Research Asthma Foundation Queensland and New South Wales

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

Rick Willson s new book, Parking Management for Smart Growth, is a how-to

Rick Willson s new book, Parking Management for Smart Growth, is a how-to PARKING MANAGEMENT Author, professor, and consultant Rick Willson on his new book and future vision for parking. FOR SMART GROWTH Rick Willson s new book, Parking Management for Smart Growth, is a how-to

More information

Central NSW Regional Contaminated Land Policy Template

Central NSW Regional Contaminated Land Policy Template Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction

More information

Final Revisions : Retention of Trommel in existing position and raising height of acoustic fence on western side of site.

Final Revisions : Retention of Trommel in existing position and raising height of acoustic fence on western side of site. LOCATION: GBN Services Ltd, The Railway Sidings, Oakleigh Road South, London, N11 1HJ REFERENCE: B/03582/12 Received: 20 September 2012 Accepted: 27 September 2012 WARD(S): Brunswick Park Expiry: 27 December

More information

What you need to know about 6 Star. 6 Star. for new homes, home renovations, alterations, additions and relocations

What you need to know about 6 Star. 6 Star. for new homes, home renovations, alterations, additions and relocations What you need to know about 6 Star 6 Star for new homes, home renovations, alterations, additions and relocations Introduction From 1 May 2011, all new homes, home renovations, additions, alterations and

More information

NOISE IMPACT ASSESSMENT PROTOCOL. Number Three Wind Farm Lewis County, New York. Case 16-F-0328

NOISE IMPACT ASSESSMENT PROTOCOL. Number Three Wind Farm Lewis County, New York. Case 16-F-0328 NOISE IMPACT ASSESSMENT PROTOCOL Number Three Wind Farm Lewis County, New York Case 16-F-0328 October 2016 CONTENTS 1 Background... 3 2 Noise-Sensitive Receptors... 4 3 Ambient Noise Assessment... 5 3.1

More information

Exposure-response relationships for annoyance by wind turbine noise: a comparison with other stationary sources

Exposure-response relationships for annoyance by wind turbine noise: a comparison with other stationary sources Edinburgh, Scotland EURONOISE 2009 October 26-28 Exposure-response relationships for annoyance by wind turbine noise: a comparison with other stationary sources Sabine A. Janssen a Henk Vos b TNO Department

More information

Study on human reactions to vibration from blasting activities nearby dwellings

Study on human reactions to vibration from blasting activities nearby dwellings 12 th ICBEN Congress on Noise as a Public Health Problem Study on human reactions to vibration from blasting activities nearby dwellings Iiris Turunen-Rindel 1, Ronny Klæboe 2, Karin Norén-Cosgriff 3 1

More information

Action Plan for a New Local Governance System in New Brunswick

Action Plan for a New Local Governance System in New Brunswick Action Plan for a New Local Governance System in New Brunswick December 2011 A message from the Premier As part of our 2010 election platform, Putting New Brunswick First, our Government committed to forging

More information

Wind farms and Selby District

Wind farms and Selby District Wind farms and Selby District Wind turbines are huge industrial structures. In the numbers proposed they would transform Selby area into an extensive wind farm landscape. You may prefer wind turbines to

More information

E. NOISE AND VIBRATION

E. NOISE AND VIBRATION NOVEMBER 2008 TRUCKEE RAILYARD DRAFT MASTER PLAN EIR This section describes existing noise conditions in the Truckee Railyard Master Plan Area, describes criteria for determining the significance of noise

More information

DIFFERENCES BETWEEN APPA- AQA AUTHORISATION REGIMES

DIFFERENCES BETWEEN APPA- AQA AUTHORISATION REGIMES DIFFERENCES BETWEEN APPA- AQA AUTHORISATION REGIMES Lekgotla Session 2.4, 12:15 12:30, Monday 29 September 2008 Presentation to the 3 rd Annual Air Quality Governance Lekgotla, Nelspruit, Emnotweni Arena,

More information

Board Staff Discussion Paper

Board Staff Discussion Paper Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction

More information

Chapter 5 Renewable Energy. Helping to Sustainably Power the Town of Veteran into the Future

Chapter 5 Renewable Energy. Helping to Sustainably Power the Town of Veteran into the Future Chapter 5 Renewable Energy Helping to Sustainably Power the Town of Veteran into the Future VISION: The Town of Veteran understands the potential to diversify their energy mix and is encouraging the deployment

More information

NaturEner Wild Rose 1 Energy Inc.

NaturEner Wild Rose 1 Energy Inc. Decision 2013-348 Amendment to Wild Rose 1 Wind Power Plant September 13, 2013 The Alberta Utilities Commission Decision 2013-348: Amendment to Wild Rose 1 Wind Power Plant Application No. 1609685 Proceeding

More information

APPENDIX 7 - AIRPORT NOISE AND DE VE LOPMENT CONTROL

APPENDIX 7 - AIRPORT NOISE AND DE VE LOPMENT CONTROL JUNE 2 016 A7.1 APPENDIX 7 AIRPORT NOISE AND DEVELOPMENT CONTROLS A7.1 INTRODUCTION The Rotorua Airport is an important resource for the Rotorua district and wider Bay of Plenty, East Coast and Central

More information

Environmental management: challenges and opportunities for the resource sector in PNG

Environmental management: challenges and opportunities for the resource sector in PNG Environmental management: challenges and opportunities for the resource sector in PNG With an appropriate level of attention, support and effort, now is the time for industry, regulators and other stakeholders

More information

10 Must Have SoundProofing Tips Which No Ones Talks About

10 Must Have SoundProofing Tips Which No Ones Talks About 2012 Craig Williams, www.soundproofingsecrets.com 10 Must Have SoundProofing Tips Which No Ones Talks About Hiring an Expensive Acoustical Consultant Most people should be able to isolate and solve noise

More information

Vegetation management on private land

Vegetation management on private land City Plan guideline Managing assessable vegetation Vegetation within the City of Gold Coast is managed through the Vegetation management code of the City Plan. The purpose of the code is to provide for

More information

Offsets Payment Calculator

Offsets Payment Calculator Offsets Payment Calculator This part of the submission comments on the draft Offsets Payment Calculator (Calculator). Further to our technical submission in August 2016, we remain concerned that the Calculator

More information

Terms of Reference. Quality and Value Audits

Terms of Reference. Quality and Value Audits Terms of Reference Quality and Value Audits Table of Contents SECTION 1 General 3 1.1 Introduction 3 1.2 Statutory authority 3 1.3 Purpose and Scope 4 SECTION 2 Methodology 6 2.1 The audit programme 6

More information

MANAGING THE NOISE IMPACT FROM SHALE GAS DRILLING

MANAGING THE NOISE IMPACT FROM SHALE GAS DRILLING WHITE PAPER MANAGING THE NOISE IMPACT FROM SHALE GAS DRILLING Phil Stollery Brüel & Kjær Sound & Vibration Measurement A/S, Denmark ABSTRACT Shale gas has transformed the energy market in the United States

More information

1. The impacts of development and settlement intensification on biodiversity and Aboriginal cultural heritage;

1. The impacts of development and settlement intensification on biodiversity and Aboriginal cultural heritage; Your reference Our reference: DOC13/40624 Contact: Liz Mazzer (02) 68835325 Date 8 th August 2013 General Manager Lithgow City Council PO Box 19 Lithgow NSW 2790 Attention: Ms Sherilyn Hanrahan, Strategic

More information

Division 8 Intensive Animal Husbandry Code

Division 8 Intensive Animal Husbandry Code Division 8 Intensive Animal Husbry Code 12.8.1 Intensive Animal Husbry Code (1) The provisions in this division comprise the Intensive Animal Husbry Code. (2) They are compliance with the Intensive Animal

More information

Managing a complaint at work A step-by-step guide

Managing a complaint at work A step-by-step guide Be prepared In running your business, you expect that at some point there could be a complaint from someone who works for you. It could be to do with their work, where they work, or who they work with.

More information

STATEMENT OF EVIDENCE OF MARK BULPITT CHRISP

STATEMENT OF EVIDENCE OF MARK BULPITT CHRISP IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER of submissions by Contact Energy Ltd in relation to Proposed Plan Changes 29 and 33 to the Taupo District Plan STATEMENT OF EVIDENCE

More information

Public opinion surveys across New Zealand - trends, comparisons & messages

Public opinion surveys across New Zealand - trends, comparisons & messages Public opinion surveys across New Zealand - trends, comparisons & messages Paper presented by James Baines at the New Zealand Wind Energy Conference, Wellington Tuesday, 30 August 2005 In the past few

More information

H3. Residential Single House Zone

H3. Residential Single House Zone H3. Residential Single House Zone H3.1. Zone description The purpose of the Residential Single House Zone is to maintain and enhance the amenity values of established residential neighbourhoods in number

More information

Vibration and noise from heavy weapons and explosions

Vibration and noise from heavy weapons and explosions Vibration and noise from heavy weapons and explosions European Conference of the Defence and the Environment Timo Markula / Akukon Ltd Tapio Lahti / TL Acoustics 22nd May 2013 Helsinki Background FDF has

More information

Contracting for Goods and Services

Contracting for Goods and Services Contracting for Goods and Services Northwest Territories Office of the Auditor General of Canada Bureau du vérificateur général du Canada Ce document est également publié en français. This document is

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

Register of Contaminated Land Consent Conditions

Register of Contaminated Land Consent Conditions Regional Contaminated Land Capacity Building Program Register of Contaminated Land Consent Conditions AUGUST 2017 Regional Contaminated Land Capacity Building Program This publication was produced by the

More information

A T Adams Consulting. West Belconnen Project Environment protection matters Summary report. report prepared for: Riverview Group

A T Adams Consulting. West Belconnen Project Environment protection matters Summary report. report prepared for: Riverview Group A T Adams Consulting West Belconnen Project Environment protection matters Summary report report prepared for: Riverview Group 9 April 2015 TABLE OF CONTENTS 1.0 -------- Introduction 2 1.1. ------- This

More information

The Voice of the Networks Energy Networks Association

The Voice of the Networks Energy Networks Association The Voice of the Networks Energy Networks Association Fair and Effective Management of DNO Connection Queues: Progression Milestones Best Practice Guide 3 November 2016 1. Purpose and Objective 1.1. The

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Monitoring of the Environmental Noise Level in San Juan, Puerto Rico

Monitoring of the Environmental Noise Level in San Juan, Puerto Rico Monitoring of the Environmental Noise Level in San Juan, Puerto Rico José Alicea-Pou Olga Viñas-Curiel Wanda Cruz-Vizcarrondo Osvaldo Alomar Noise Control Area, Puerto Rico Environmental Quality Board

More information

Airport Noise Assessment in Thailand

Airport Noise Assessment in Thailand Airport Noise Assessment in Thailand Krittika Lertsawat Legal Researcher, Project on the Development on Draft Law of Environmental Judicial Process 24/9 m.6, Khlongsong, Khlongluang, Pathumthani 12120

More information

The Pipelines Regulations, 2000

The Pipelines Regulations, 2000 PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21; and by Saskatchewan Regulations

More information

The rezoning application and proposed transportation facility warrants consideration.

The rezoning application and proposed transportation facility warrants consideration. Date: November 11, 2014 To: Re: Chair and Members Planning & Development Committee PDE File Number: REZ1400020 275 Conception Bay South Bypass Road, Ward 5 Application to Rezone Land to Industrial General

More information

Prof. John Fitzgerald. The Citizens Assembly

Prof. John Fitzgerald. The Citizens Assembly Paper of Prof. John Fitzgerald Chair of the Climate Change Advisory Council delivered to The Citizens Assembly on 05 November 2017 Tackling Climate Change in Ireland John FitzGerald, Chairman, The Climate

More information

28 JULY 2015 PLANNING COMMITTEE. 5i 14/1315 Reg d: Expires: Ward: OW. of Weeks on Cttee Day:

28 JULY 2015 PLANNING COMMITTEE. 5i 14/1315 Reg d: Expires: Ward: OW. of Weeks on Cttee Day: 5i 14/1315 Reg d: 25.11.2014 Expires: 29.04.15 Ward: OW Nei. Con. Exp: 14.01.15 BVPI Target Minor (13) Number of Weeks on Cttee Day: 21/8 On Target? No LOCATION: PROPOSAL: TYPE: London House, 134 High

More information

Evaluating Appropriate Residential Ventilation Strategies in Dense Urban Environments and the Challenges for Passive Design

Evaluating Appropriate Residential Ventilation Strategies in Dense Urban Environments and the Challenges for Passive Design Evaluating Appropriate Residential Ventilation Strategies in Dense Urban Environments and the Challenges for Passive Design Ashley Bateson CEng CEnv MCIBSE MEI Partner, Hoare Lea Chair, CIBSE Homes for

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Proof of Evidence on Noise Helene C S Evans BSc(Hons) MIOA MASA

Proof of Evidence on Noise Helene C S Evans BSc(Hons) MIOA MASA Proof of Evidence on Noise Helene C S Evans BSc(Hons) MIOA MASA Appeal Ref No: APP/R0660/W/15/3027388 Cheshire East Application No: 14/0114M Hybrid planning proposal by Argonaught Holdings Ltd c/o LPC

More information

Strategy and Structure

Strategy and Structure Whole Foods Market Strategy and Structure Jawaher Alotaibi June 18, 2015 WFM s Environment Whole Foods Market (WFM) is a natural and organic supermarket that it s known for healthy and natural food products.

More information

Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332

Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332 Pg 'P. Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332 Heidelberg i#i..wr. David, u.,0 Victoria 3054 Phone 0412 375 234 Email: acausteblgpond.corn ABN 49 095 932 092

More information

Section 10 - Airport Business Zone (Titanium Park)

Section 10 - Airport Business Zone (Titanium Park) 10.1 Introduction 10.1.1 The Hamilton International Airport (the Airport) is a facility of economic and social importance to the Waikato Region. The Airport Business Zone associated with it (Titanium Park)

More information

ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) OF THE 1976 CODE OF THE COUNTY OF FAIRFAX, VIRGINIA

ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) OF THE 1976 CODE OF THE COUNTY OF FAIRFAX, VIRGINIA ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) 36-07-120 (Also see Heritage, Specimen, Memorial and Street Trees Ordinances 37-07-N adopted simultaneously on October 15, 2007) OF THE 1976 CODE OF

More information

Place Vanier Édifice AEFO

Place Vanier Édifice AEFO Place Vanier Édifice AEFO Martineau Architecture Inc. + Smith Carter Architects & Engineers Inc. TRAFFIC NOISE ASSESSMENT 250 Montreal Road Gradient Microclimate Engineering Inc. Prepared by Thomas Couper,

More information

NOISE Management Plan

NOISE Management Plan Bulli Seam Operations NOISE Management Plan Schedule 4, Condition 5 - BSO Project Approval 08_0150 Review History Revision Description of Changes Date By New Document September 2012 As per below 1.0 Revised

More information

Wind Power Land Use and Policy Issues. M. Klepinger, Land Policy Institute Michigan State University

Wind Power Land Use and Policy Issues. M. Klepinger, Land Policy Institute Michigan State University Wind Power Land Use and Policy Issues M. Klepinger, Land Policy Institute Michigan State University 1 Interest in Wind Power Why is everyone talking about wind power? 1. Farmers and large tract owners,

More information

South Australian Multiple Land Use Framework

South Australian Multiple Land Use Framework Government of South Australia South Australian Multiple Land Use Framework SNOWTOWN WIND FARM CASE STUDY 2 www.yoursay.sa.gov.au South Australian Multiple Land Use Framework Synopsis What is the issue?

More information