PROJECT AT THE DENVER

Size: px
Start display at page:

Download "PROJECT AT THE DENVER"

Transcription

1 POROUS ASPHALT DEMONSTRATION PROJECT AT THE DENVER WASTEWATER BUILDING Ken A. MacKenzie, P.E. Manager, Master Planning Program Urban Drainage and Flood Control District 36 th Annual Rocky Mountain Asphalt Conference and Equipment Show Denver, Colorado February 19, 2009

2 Denver Wastewater Building

3 Denver Wastewater Building

4 Porous Asphalt Watershed 12,180 SF (0.28 Acres)

5 Porous Asphalt Area 90 x20

6 Porous Asphalt Section 3 porous asphalt 2 of #67 aggregate 7 of #3 aggregate 1 of C-33 sand Geotextile filter 6 of C-33 sand Geotextile filter 4 perforated pipe Impermeable liner Woven geotextile fabric meeting: ASTM D AOS U.S. STD. sieve #50 to #70 ASTM D Min. trapezoidal tear strength 100 X 60 lbs, Minimum COE specified open area of 4% ASTM C-33 Sand Base Course: #3 Aggregate (CDOT Section 703-2) AASHTO #67, all fractured faces; (CDOT SECT , #67 course aggregate) Open-Graded HMA 2% Min. Fill under-drain trench around pipe with AASHTO #67 stone 6.0" 6.0" 18.0" Min. 1" Thick sand cushion layer 2.5" 2.0" 16 mil impermeable liner under all paved areas wrapped to top of pavement Schedule 40 HDPE 4" Under-drain 7.0" 1.0" 6.0"

7 Demo the Site

8 Survey the subase for drainage

9 Prepare the underdrain

10 Place the underdrain and liner

11 Place the sand filter layer

12 Place the filter Place the filter fabric or geotextile

13 Place 1 sand atop the filter fabric

14 Place 1 sand atop the filter fabric

15 Place CDOT #3 Place CDOT #3 aggregate

16 Place CDOT #3 Place CDOT #3 aggregate

17 Place CDOT #3 aggregate

18 Place CDOT Place CDOT #67 aggregate

19 Bringinthe Bring in the asphalt

20 Check the temperature

21 Roll the asphalt Roll the asphalt not too much!

22 Placing the asphalt

23

24 Miller Time!

25 Replace the inlet concrete

26 Earth Day ribbon cutting

27 Recognition of the partners time, money, and equipment contributions

28 Soaks the water right in!

29 PERFORMANCE TESTING

30

31

32

33

34 INFILTRATION TESTING

35

36 Infiltration Test Denver Wastewater Building 08/19/2008 Location Amt Liquid (ml) Height Liquid (in) Delta T (sec) (in/sec) Infiltration Rate (in/hr) PPPA

37 SAMPLING EQUIPMENT

38

39

40

41 Tipping bucket rain gage measures every 0.01 of rainfall

42 1 1/8 hole for Pressure Transducer ¾ Orifice Hole Sampler Collection Line Cipoletti Weir

43

44 Porous Asphalt Considerations (adapted from Dauphin County Conservation District, PA) Test soil to 2 feet below base of stone reservoir for permeability of at least 0.5 inch per hour. If less, use underdrain system. Porous surface permeability should be at least 8 inches per hour. Avoid compaction of soil base; if new fill is required, the addition of extra stone is recommended over adding compacted soil. Use light equipment with tracks or oversized tires during grading to prevent compaction of the soil base. Install at least 4 feet above the seasonal high groundwater table to avoid contamination Design should include overflow drainage to remove excess stormwater

45 Porous Asphalt Considerations (adapted from Dauphin County Conservation District, PA) Stone reservoir layer is placed in lifts and lightly rolled. Stone bedding layer should drain within 72 hours of a rain event. Slope of pavement surface should be less than 5%. Aggregate g for reservoir bed should be approximately 1 to 3 inches in diameter. Aggregate for reservoir must be clean-washed and contain at least 40% void space. Reservoir layer is typically 12 to 36 inches deep. Place porous asphalt directly on stone bed in a single 3.5 inch lift then roll to a finished depth of 2.5 inches.

46 Porous Asphalt Considerations (adapted from Dauphin County Conservation District, PA) Use 85 to 100% penetration grade to prevent surface from being scuffed by vehicle wheels. Temperature of asphalt should be between 240 and 260 F. Air temperature during paving must be at least 50 F. Not suitable for areas of recent fill (less than 5 years). Roll asphalt when it has cooled enough to withstand a ten-ton roller. Compact surface layer with one or two passes of roller; more frequent rolling can reduce infiltration capacity of pavement.

47 Porous Asphalt Considerations (adapted from Dauphin County Conservation District, PA) Control of sediment is critical - remove surface sediment with a vacuum or by sweeping; avoid power washing, as it will clog the system. Prohibit use of sand, salt or other de-icers that may clog system. Design must provide for a backup method for water to enter stone reservoir (ex. stone-edged drain near wheel stop if curbing is not in place). Not suitable for stormwater hot spots (truck stops, gas stations, etc.) due to high level of contaminants present. Use snow plows with caution during snow removal.

48 Porous Asphalt Considerations (adapted from Dauphin County Conservation District, PA) Not recommended for installation in areas of high traffic or heavy vehicle loads. Not recommended in areas where wind erosion supplies significant amounts of windblown sediment. Protect pavement from vehicular traffic for at least two days after installation. Post signs to prevent vehicles with muddy tires from entering area. Potholes and cracks may be patched with traditional patching mix, unless more than 10% of porous surface area needs to be repaired.

Presentation to the 60 th Annual NJ Asphalt Paving Conference March 14, 2017 Ewing, NJ

Presentation to the 60 th Annual NJ Asphalt Paving Conference March 14, 2017 Ewing, NJ Presentation to the 60 th Annual NJ Asphalt Paving Conference March 14, 2017 Ewing, NJ James J. Purcell, PE, PMP Technical Director, New Jersey Asphalt Pavement Association Reduce impervious surface Recharge

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231. DRIVEWAYS, DRIVEWAYS & PATIOS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - CHARACTERISTICS CSA A231.2 TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min. Absorption - 5 % max. Freeze-thaw

More information

Sand Filter T-6. Description. Site Selection

Sand Filter T-6. Description. Site Selection Description A sand filter is a filtering or infiltrating BMP that consists of a surcharge zone underlain by a sand bed with an underdrain system (when necessary). During a storm, accumulated runoff collects

More information

StormwaterWise Landscapes: Pervious Surfaces Specifications

StormwaterWise Landscapes: Pervious Surfaces Specifications StormwaterWise Landscapes: Pervious Surfaces Specifications Purpose & Benefits Stormwater runoff reduction High pollutant removal Control localized drainage problems Attractive alternative for walkways

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016

DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016 DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016 INTRODUCTION Storm water management is a challenge facing our ever expanding

More information

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE 3.33' 3.0' 2.0' 4.33' 4.0' 3.0' 1.00' TO BACK OF CURB LINE TOP OF GRATE ELEV. - SEE PLAN NEENAH CASTING R-3067-V OR AS NOTED ON PLANS. "INFA-SHIELD" SEAL OR EQUAL. RINGS (2 MIN., 1' MAX. OF RINGS AND MORTAR).

More information

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO)

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO) SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO) This guide specification for U.S. applications describes construction of bio-infiltration bump outs (or bioretention ) systems. From the surface down to the

More information

At least 2 feet above the seasonal high water table Overflow path or structure provided

At least 2 feet above the seasonal high water table Overflow path or structure provided General Conditions Map of proposed subwatershed to each subbasin, including total area and CN Design Flow or Design Volume to each STF, as appropriate Operation and Maintenance instructions for each STF

More information

VA DEQ STORMWATER DESIGN SPECIFICATION NO. 7 PERMEABLE PAVEMENT. VERSION 1.8 March 1, 2011 SECTION 1: DESCRIPTION

VA DEQ STORMWATER DESIGN SPECIFICATION NO. 7 PERMEABLE PAVEMENT. VERSION 1.8 March 1, 2011 SECTION 1: DESCRIPTION VIRGINIA DEQ STORMWATER DESIGN SPECIFICATION No. 7 VERSION 1.8 March 1, 2011 SECTION 1: DESCRIPTION Permeable pavements are alternative paving surfaces that allow stormwater runoff to filter through voids

More information

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers 4.1-a PERVIOUS PAVEMENT Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers DESCRIPTION Pervious pavement is any system comprised of a load bearing surface that allows for movement of

More information

BRADLEY UNIVERSITY. The Performance and Sustainability of Permeable Pavement Progress Report on the Work Performed Under IAPA Scholarship

BRADLEY UNIVERSITY. The Performance and Sustainability of Permeable Pavement Progress Report on the Work Performed Under IAPA Scholarship BRADLEY UNIVERSITY The Performance and Sustainability of Permeable Pavement Progress Report on the Work Performed Under IAPA Scholarship Anne Riemann 12/19/2016 1 INTRODUCTION Permeable pavement is an

More information

Rhode Island Stormwater Design and Installation Standards Manual

Rhode Island Stormwater Design and Installation Standards Manual Rhode Island Stormwater Design and Installation Standards Manual Public Workshop Infiltration (Including Permeable Paving) March 24, 2011 Infiltration Section 5.3: Appendix F.3 & H.1 Approved WQ BMPs Infiltration

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

DATE: December 10, 2012 REPORT NO. PW CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION

DATE: December 10, 2012 REPORT NO. PW CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION PUBLIC WORKS COMMISSION DATE: December 10, 2012 REPORT NO. PW2012-073 TO: FROM: CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION GEOFF RAE, MBA, P.ENG. GENERAL MANAGER, PUBLIC WORKS

More information

4.2 Permeable Pavement Systems

4.2 Permeable Pavement Systems 4.2 Permeable Pavement Systems Permeable Pavement provides the structural support of conventional pavement, but allows stormwater to drain directly through the surface into the underlying stone base and

More information

Infiltration Guidelines

Infiltration Guidelines Appendix E Infiltration Guidelines As a stormwater management method, infiltration means retaining or detaining water within soils to reduce runoff. Infiltration can be a cost-effective method to manage

More information

StormTech Construction Guide

StormTech Construction Guide A division of StormTech solid end caps and pre-cored end caps StormTech chambers StormTech manifolds and fittings Acceptable fill materials per Table 1 Woven and non-woven geotextiles 80-7 DC REQUIRED

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min.

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min. DRIVEWAYS, DRIVEWAYS & PATIOS PHYSICAL AND GEOMETRICAL CHARACTERISTICS CHARACTERISTICS CSA A231.2 2 TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min. Freeze-thaw durability

More information

TYPE "A" CATCH BASIN

TYPE A CATCH BASIN 27" 1.67' TO BACK OF CURB LINE TOP OF GRATE ELEV. - SEE PLAN NEENAH CASTING R-3250-BV OR APPROVED EQUAL. "INFI SHIELD" SEAL OR APPROVED EQUAL RINGS (2 MIN., 1' MAX. OF RINGS AND MORTAR). PLASTER OUTSIDE,

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating

More information

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS DRAINAGE SOLUTIONS SINCE 1908 BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS PROTECT FOUNDATIONS IMPROVE HIGHWAY

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

Permeable Pavement. Kristen Buccier Program Manager Chagrin River Watershed Partners, Inc.

Permeable Pavement. Kristen Buccier Program Manager Chagrin River Watershed Partners, Inc. Permeable Pavement Kristen Buccier Program Manager Stormwater Management Training for MS4 Municipal Employees Training Session Agenda Pre-Training Survey Presentation & Site Visit Post-Training Survey

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS PERMEABLE PAVEMENTS (SUDS) This leaflet highlights the basic requirements for laying Ibstock clay pavers to form a permeable pavement. Ibstock clay pavers are intended for domestic use only i.e. patios

More information

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17 S&L Gravel, Section B: Proposal Page 10701.0 - TRAFFIC CONTROL - LUMP SUM 1.00 $6,425.00 $6,425.00 $6,425.00 $10,000.00 10720.0 - TRAFFIC CONTROL SIGN - PORTABLE ARROW BOARD - DAYS 25.00 $25.00 $625.00

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Integrating Structural and Hydrologic Design in Permeable Pavement David R. Smith Technical Director Interlocking Concrete Pavement Institute

Integrating Structural and Hydrologic Design in Permeable Pavement David R. Smith Technical Director Interlocking Concrete Pavement Institute Integrating Structural and Hydrologic Design in Permeable Pavement David R. Smith Technical Director Interlocking Concrete Pavement Institute 2010 Concrete Sustainability Conference 1 National Ready Mixed

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

BASE CONSTRUCTION MATERIALS A Aggregate

BASE CONSTRUCTION MATERIALS A Aggregate BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3

More information

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments Asphalt Pavement Preservation: Evaluation, Maintenance & Rehabilitation Maintenance & Rehabilitation Treatments Identification of Alternative Treatments Before selecting a treatment for a pavement, we

More information

PERMEABLE PAVEMENTS FOR ROADWAY SHOULDERS

PERMEABLE PAVEMENTS FOR ROADWAY SHOULDERS PERMEABLE PAVEMENTS FOR ROADWAY SHOULDERS David K. Hein, P. Eng. 1 and Lori Schaus, P.Eng. 2 1 Principal Engineer, Applied Research Associates Inc., 5401 Eglinton Avenue West, Suite 105, Toronto, ON, Canada,

More information

Corrugated Metal Pipe Design Guide

Corrugated Metal Pipe Design Guide Corrugated Metal Pipe Temporary Cover For Construction Loads Height-Of-Cover Finished Grade Backfill D Bedding INNOVATIVE SITE SOLUTIONS & STORMWATER MANAGEMENT Corrugated Metal Pipe Table of Contents

More information

Applications. 5 reasons why you should choose Hebden X Grid cellular paving

Applications. 5 reasons why you should choose Hebden X Grid cellular paving 5 reasons why you should choose Hebden X Grid cellular paving The British-made Hebden X Grid cellular paving system can be filled with grass or gravel, then driven over, parked on and walked on whilst

More information

SECTION FOUNDATION DRAINAGE

SECTION FOUNDATION DRAINAGE SECTION 33 41 13 SPEC WRITER NOTES: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

INTERLOCK BETWEEN PARTICLES AT EACH PERFORATION

INTERLOCK BETWEEN PARTICLES AT EACH PERFORATION for Storm Water Management RUN OFF CONTROLS Porous Parking & Vehicle Access Cellular Confinement Systems (CCS) A Cellular Confinement System (CCS) is an engineered, expandable, polyethylene, honeycomb-like

More information

BIO-AQUIFER STORM SYSTEM

BIO-AQUIFER STORM SYSTEM BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone

More information

Appendix B: Green Infrastructure Typical Details and Specifications

Appendix B: Green Infrastructure Typical Details and Specifications Appendix B: Green Infrastructure Typical Details and Specifications Typical Details for Site-Specific Design 2 Specifications and Design Guidelines 101 September 2016 Version - Updates and errata will

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19-1 19-1.01 Exploratory Excavation... 19-1 19-1.02 Trench... 19-1 19-1.02.AStorm Drain Pipe...

More information

Evaluation of Structural Performance of Pervious Concrete in Construction

Evaluation of Structural Performance of Pervious Concrete in Construction International Journal of Engineering and Technology Volume 2 No. 5, May, 2012 Evaluation of Structural Performance of Pervious Concrete in Construction S.O. Ajamu 1, A.A. Jimoh 2, J.R. Oluremi 1 1 Department

More information

SECTION ECO-CITYLOCK PERMEABLE INTERLOCKING CONCRETE UNIT PAVING

SECTION ECO-CITYLOCK PERMEABLE INTERLOCKING CONCRETE UNIT PAVING SECTION 32 14 13.19 ECO-CITYLOCK PERMEABLE INTERLOCKING CONCRETE UNIT PAVING 1-800-245-PAVE http://www.pavestone.com ATLANTA, GA: (770) 306-9691 AUSTIN/SAN ANTONIO, TX: (512) 558-7283 BOSTON, MA: (508)

More information

GROUNDtrax GROUNDGRIDZ

GROUNDtrax GROUNDGRIDZ INSTALLATION GUIDE The product is asymmetric and must be lifted by placing the hands on the diagonally opposed corners of the central paver (as shown). 1. Place grids onto the prepared well consolidated

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

R-TANK SPECIFICATIONS

R-TANK SPECIFICATIONS TECHNICAL STORMWATER MANAGEMENT R-TANK SPECIFICATIONS PART 1 GENERAL 1.01 Related Documents A. Drawings, technical specification and general provisions of the Contract as modified herein apply to this

More information

Riverside County. Stormwater Quality Best Management Practice. Design Handbook

Riverside County. Stormwater Quality Best Management Practice. Design Handbook Riverside County Stormwater Quality Best Management Practice Design Handbook Riverside County Flood Control and Water Conservation District 1995 Market Street Riverside CA 92501 July 21, 2006 TABLE OF

More information

Treatment Volume: Curve Numbers. Composite CN or Not? Treatment Volume: Curve Numbers. Treatment Volume: Calculation. Treatment Volume: Calculation

Treatment Volume: Curve Numbers. Composite CN or Not? Treatment Volume: Curve Numbers. Treatment Volume: Calculation. Treatment Volume: Calculation Stormwater Engineering Bioretention Design Bill Hunt, PE, Ph.D. Extension Specialist & Assistant Professor NCSU-BAE www.bae.ncsu.edu/stormwater Bioretention Design Six Step Process 1 Determine Volume to

More information

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated.

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated. ZGF Partnership Page 1 of 7 SECTION 33 46 00 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes subdrainage systems for foundations and underslab areas. 1.2 SUBMITTALS A. Product Data: For each type

More information

the 2001 season. Allison brought high winds and street flooding to Houston, after

the 2001 season. Allison brought high winds and street flooding to Houston, after Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay Overlays February 22, 2012 ACPA Pennsylvania Chapter Overlays John M. Becker, P.E. ACPA Penn Chapter February 22, 2012 One of 25 state paving associations affiliated with ACPA National Comprised of approximately

More information

Porous Pavements in Cold Climates Part 1: Design, Installation, and Maintenance

Porous Pavements in Cold Climates Part 1: Design, Installation, and Maintenance Porous Pavements in Cold Climates Part 1: Design, Installation, and Maintenance A Green Infrastructure, Green Jobs, and Green Funding Workshop Onondaga Environmental Institute March 2011 Robert Roseen,

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE 1.0 GENERAL 1.1 Scope A. This specification guideline covers the technical requirements for furnishing all labor, materials, equipment, and incidentals

More information

Construction Specification for Concrete Unit Pavers

Construction Specification for Concrete Unit Pavers Engineering & Construction Services Division Standard Specifications for Road Works TS 3.80 September 2017 for Concrete Unit Pavers Table of Contents TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS

More information

DIVISION 32 EXTERIOR IMPROVMENTS

DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVEMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

A Design Review of Waterproofing Codes

A Design Review of Waterproofing Codes A Design Review of Waterproofing Codes Section 1807 of Chapter 18 of the International Building Code addresses waterproofing under the section title of Dampproofing and Waterproofing. The section defines

More information

Paraprofessional Training Session 1

Paraprofessional Training Session 1 Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor

More information

Fabrication and Installation Table of Contents

Fabrication and Installation Table of Contents Fabrication and Installation Table of Contents HDPE AQUASHIELD PRODUCTS 2 Fabrication and Installation 2 System Fabrication 3 Aqua-Swirl Installation 4 Step 1 Excavation and Bedding 4 Step 2 Pipe Connection

More information

SECTION INTERLOCKING CONCRETE PAVERS

SECTION INTERLOCKING CONCRETE PAVERS SECTION 23 14 13 INTERLOCKING CONCRETE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for concrete paver applications in the U.S. for concrete pavers and bedding sand over a compacted

More information

CHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS

CHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS CHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS Section Title Page 10.1 General... 10-1 10.1.1 Existing Streets...10-1 10.1.2 AASHTO Design...10-1 10.1.3 Pavement Type...10-1 10.1.4 Treated Subgrade...10-1

More information

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete

More information

Providing proper drainage system

Providing proper drainage system Environment Friendly and Cost Effective Alternative to Conventional Graded Filters Providing proper drainage system for structures such as earth retaining structures, pavements, water front structures,

More information

SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG):

SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG): SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG): ARHM-GG shall conform to the provisions for Type "A" asphalt concrete in Section 39, "Asphalt Concrete," of the State Standard Specifications

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

HydraPressed Slabs. Yorkstone Tan. Wherefunctionmeetsstyle

HydraPressed Slabs. Yorkstone Tan. Wherefunctionmeetsstyle HydraPressed Slabs Yorkstone Tan Wherefunctionmeetsstyle Texada This series is named after the rugged and beautiful Gulf Islands of the Pacific Northwest. Texada HydraPressed Slabs have a light shot-blast

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

THE MOST ADVANCED NAME IN WATER MANAGEMENT SOLUTIONS THERMOPLASTIC LINERS FOR DETENTION SYSTEMS

THE MOST ADVANCED NAME IN WATER MANAGEMENT SOLUTIONS THERMOPLASTIC LINERS FOR DETENTION SYSTEMS THE MOST ADVANCED NAME IN WATER MANAGEMENT SOLUTIONS THERMOPLASTIC LINERS FOR DETENTION SYSTEMS STORMTECH VERSATILITY StormTech chambers offer the versatility to be designed as 1) retention systems, 2)

More information

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2

More information

Installation and Maintenance of Erosion Control BMPs

Installation and Maintenance of Erosion Control BMPs Installation and Maintenance of Erosion Control BMPs Or Common BMPs Applications Specifications Installation Problems Maintenance Utility Design Professionals Clarifications, proactive problem solving

More information

4-07 Asphalt Treated Permeable Base (ATPB)

4-07 Asphalt Treated Permeable Base (ATPB) 1 1 0 1 0 1 Supplement Division with the following: (November 0,, APWA GSP) -0 Asphalt Treated Permeable Base (ATPB) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course

More information

Summary of the 2011 Changes

Summary of the 2011 Changes The following is a list of amendments to the Residential Site Improvement s, N.J.A.C. 5:21, adopted in 2011. The Notice of Adoption of these changes appeared in the New Jersey Register on May 16, 2011.

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

PART 1 - GENERAL 1.01 General Provisions A. The Conditions of the Contract and all Sections of Division 1 are hereby made a part of this Section.

PART 1 - GENERAL 1.01 General Provisions A. The Conditions of the Contract and all Sections of Division 1 are hereby made a part of this Section. Specification Sheet Grass Paver TECHNICAL SPECIFICATION - Grass Covered Flexible Porous Paver with 92% Void Space and Soil Conditioner/Fertilizer Mixture CSI Master Format 32 12 43 Flexible Porous Pavement

More information

PERMEABLE PAVER MAINTENANCE GUIDE

PERMEABLE PAVER MAINTENANCE GUIDE PERMEABLE PAVER MAINTENANCE GUIDE PERMEABLE PAVER MAINTENANCE GUIDE This guide is specific to Unilock permeable pavers as a maintainable system for storm water runoff and does not cover cleaning concrete

More information

NCMA TEK CONCRETE GRID PAVEMENTS. TEK 11-3 Pavers (2001)

NCMA TEK CONCRETE GRID PAVEMENTS. TEK 11-3 Pavers (2001) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE GRID PAVEMENTS TEK -3 Pavers (200) Keywords: ASTM specifications,

More information

Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007

Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007 Ontario Ministry of Transportation Carpool Parking Lot (Campbellville) Location: Campbellville Constructed: 2007 Case Study Public Lands Project Objectives, Design and Performance Construct a green carpool

More information

Future Trends. Asphalt Rubber. Gregory S. Cleveland, P.E. TxDOT Construction Division. f HMA. f 1

Future Trends. Asphalt Rubber. Gregory S. Cleveland, P.E. TxDOT Construction Division. f HMA. f 1 Future Trends Asphalt Rubber N f = f ε 1 ( ) f 2 ( ) f E 3 t HMA Gregory S. Cleveland, P.E. TxDOT Construction Division Outline TxDOT 2003 Standard Specifications Guidance from Flexible Pavement Design

More information

SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...

SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS... SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK... 20-2 2. MATERIAL REQUIREMENTS... 20-2 3. CONSTRUCTION AND INSTALLATION REQUIREMENTS... 20-2 4. METHOD OF MEASUREMENT... 20-5 20-1 SECTION 20 PAVING FABRIC

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

DuPage County Division of Transportation 421 N. County Farm Road Wheaton, IL / (Fax) 630/

DuPage County Division of Transportation 421 N. County Farm Road Wheaton, IL / (Fax) 630/ Within DuPage County Highway Rights-of-Way NOTE: All construction shall be performed and materials specified/installed according to IDOT S Standard Specifications for Road and Bridge Construction (latest

More information

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators Page 1 of 5 STREAMLINES A Newsletter for North Carolina Water Supply Watershed Administrators Volume 2, Number 2 May 1997 Non-Point Source (NPS) Pollution This issue of Streamlines provides basic information

More information

Advanced Enviro-Septic TM Basic Design and Installation Manual

Advanced Enviro-Septic TM Basic Design and Installation Manual Advanced Enviro-Septic TM Basic Design and Installation Manual New Zealand Distributors Environment Technology Ltd 14 Onekaka Iron Works Rd Takaka 7182 (03) 9707 979 www.et.nz info@et.nz Technical support

More information

BMP #: Infiltration Basin

BMP #: Infiltration Basin Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase. SECTION 20.22 LEVELING COURSE Article 22.1 General The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase. Article

More information

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength psi [45 MPa] min.

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength psi [45 MPa] min. PATIOS, WALKWAYS, POOLSIDES & STEPPING STONES PHYSICAL AND GEOMETRICAL CHARACTERISTICS CHARACTERISTICS CSA A231.1 2 TECHO-BLOC Compressive strength - 6 500 psi [45 MPa] min. Flexural strength 650 psi [4.5

More information

Specifications per pallet. Number of rows = 8 9 ft 2 /row (0.84 m 2 )/row T W

Specifications per pallet. Number of rows = 8 9 ft 2 /row (0.84 m 2 )/row T W Permea code 1810 texture eveled Pallet Overview Specifications per pallet Imperial Metric ubing 72 ft 2 (6.70 m 2 ) Weight 2,470 lb (1,120 kg) Number of rows = 8 9 ft 2 /row (0.84 m 2 )/row L T W Unit

More information

DELTA -GARDEN ROOF SYSTEM with DELTA -FLORAXX

DELTA -GARDEN ROOF SYSTEM with DELTA -FLORAXX HIGH PERFORMANCE AIR & MOISTURE BARRIERS Water Retention & Drainage Membrane for Garden Roof Systems. tainability & sus th o t ronment nvi ee Comm itte d DELTA -GARDEN ROOF SYSTEM with DELTA -FLORAXX DELTA

More information

Asphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC

Asphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC Asphalt Guidelines Courtney Rousseau, P.E. Lloyd Consulting Group, LLC Objectives Review typical asphalt sections and other key components to ensure optimal material usage for your project Review hot mix

More information

SECTION BITUMINOUS CONCRETE PAVEMENT

SECTION BITUMINOUS CONCRETE PAVEMENT SECTION 321216 BITUMINOUS CONCRETE PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Polymeric Sand. Guide. for Pavement Joints. Installation. Easy to use Stays within joints HP POLYMERIC SAND RG+ POLYMERIC SAND. techniseal.

Polymeric Sand. Guide. for Pavement Joints. Installation. Easy to use Stays within joints HP POLYMERIC SAND RG+ POLYMERIC SAND. techniseal. Polymeric Sand for Pavement Joints Easy to use Stays within joints Installation Guide techniseal.com TECHNISEAL POLYMERIC SAND FOR PAVEMENT JOINTS is a high-tech mix of graded sand and binder, specially

More information