Clach Liath Wind Farm

Size: px
Start display at page:

Download "Clach Liath Wind Farm"

Transcription

1 ES Non Technical Summary volume 4 Clach Liath Wind Farm For further information, please contact: RSK Environment Ltd: 65 Sussex Street, Glasgow G41 1DX, UK Tel: +44 (0) Contact: Joe Somerville clachliath@rsk.co.uk Clach_covers_A4.indd 3 APRIL /3/12 13:21:52

2 NON TECHNICAL SUMMARY Background to the Proposed Development Coriolis Energy LLP (Coriolis) is seeking planning permission on behalf of Falck Renewables Wind Limited (Falck) for a proposal to construct and operate a new wind farm development within Swordale Moor in Easter Ross, Highland (Clach Liath Wind Farm). Falck is part of the substantial Italian company Gruppo Falck SPA who have a long history of involvement in the energy sector. Their Highland wind farms include Millenium, Kilbrauer and Ben Aketil. Since 2002, Falck has become one of the leading independent renewable energy businesses in Europe and is one of the largest owner-occupiers of wind farms in the UK. Coriolis is a specialist independent wind farm development company operating throughout the UK. Coriolis works in partnership with Falck to assist in project development and planning. The site for the Clach Liath Wind Farm is located approximately 6km north of Dingwall and 3km south of Loch Glass. Figure 1: Site Location Plan The proposed development comprises: 17 turbines capable of generating approx. 42.5MW of electricity; a substation/site office/control building; and two permanent anemometer masts to collect weather data. Site access would initially be via an existing track associated with Novar Wind Farm, with several new tracks formed within Swordale Moor to allow access during construction and future maintenance events. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 1

3 Consents and Authorisations Coriolis has submitted a planning application, on behalf of Falck, for the proposed development to the Highland Council, to seek consent for the proposed development under the provisions of the Town and Country Planning (Scotland) Act In accordance with statutory processes detailed in the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011, an Environmental Impact Assessment (EIA) has been undertaken to identify the likely significant effects the proposed development on the receiving environment. The planning application for the proposed development comprises an area totalling 412 hectares in size, within which the infrastructure associated with the proposals forms a relatively small component. Should planning consent be granted, Falck will be responsible for the construction and operation of the proposed development. Environmental Impact Assessment The EIA for the proposed development has been undertaken by RSK Environment Limited, on behalf of Coriolis and Falck. An Environmental Statement has been prepared that accompanies the planning application and reports the findings and outcomes of the EIA process. This Non-Technical Summary (NTS) outlines the principal environmental impacts reported in the Environmental Statement, and summarises mitigation measures proposed to address adverse impacts. Consultation Consultation has formed an important part of both the EIA and the ongoing design-development of the Clach Liath Wind Farm. Extensive consultation has been undertaken with agencies, and organisations by way of correspondence, meetings and exhibitions. This served to obtain environmental data and information on the site and its immediate surroundings and to provide interested parties with an opportunity to influence both the scope of the EIA and the design of the proposed development. Public consultation was undertaken, through two maildrops to the local community and through public exhibitions held in Culbokie, Dingwall and Evanton in July and August Alternatives Part of the design-development and EIA process has been the consideration of alternatives for the location, design form, and operational aspects of the proposed development. Coriolis has an ongoing search programme for sites with potential suitability for wind energy development. Site search criteria include a range of environmental, commercial, technical and policy considerations such as meteorological conditions, connectivity to the electricity network, and overall accessibility. Following identification of the site, the development process commenced with an initial review of sitespecific constraints and opportunities such as geography, settlement pattern, planning policy objectives, and the location of areas designated for the protection of ecological, landscape or heritage interest. From this review, Coriolis established that Swordale Moor offered significant potential to accommodate the operational requirements of a wind farm development. A preliminary development layout comprising 18 wind turbines was subsequently developed, based on available information relating to the local topography, prevailing wind speeds and direction, and the relationship to environmental sensitivities. Potential environmental constraints and issues arising from the EIA and consultation resulted in a reduction in the number of wind turbines within the proposed development to 17. Further modifications and refinements were made to the locations of individual turbines, access tracks, construction compounds, and the positions of ancillary infrastructure in pursuit of a final layout for the proposed development. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 2

4 Existing Environment The Site is positioned approximately 5km southwest of the Novar Wind Farm principally comprises open moorland primarily used for sporting activity. To the northwest of the Site lies Ben Wvyis, and to the south of the Site is River Sgitheach. Strath Glass and Evanton are located east of the site, and the Allt nan Caorach stream forms the site s northern boundary. A coniferous plantation, established between 1964 and 1985, forms the eastern boundary through which the site would be accessed via an un-surfaced track. Notable peaks within the Site include the eastern flank of Meall na Speireig (620m) and Cnoc nan Each (467m). The Proposed Development The proposed development comprises 17 turbines, each with a maximum 126.5m height to blade tip and up to 80m to hub height - the point at which the blades attach to the structure. The proposed turbines are of modern design with tubular towers and three blades attached to the main body (the nacelle), containing a generator, gearbox and other operating equipment. The operational lifetime of the turbines is proposed to be 25 years. Figure 2: Proposed Layout of the Development Construction would last around 12 months, and it is anticipated that works would start in 2013 and finish in An experienced contractor would be appointed who would be required to employ best practice in respect of quality, health, safety and environmental conservation. The types of plant anticipated to be used during the construction phase would include HGVs, mobile cranes; compaction plant and earth moving equipment. A temporary construction compound and lay down area would be formed within a flat cleared area within the plantation woodland east of the site. Small temporary laydown and construction areas along the proposed access track to the Site would initially be required for the purposes of track widening and construction. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 3

5 Existing access tracks would be used and upgraded where possible, with new sections of track formed to provide a means of access between individual turbines. An area of hard ground would be formed next to each individual turbine location in order to provide a suitable working platform for cranes to assemble the turbines from. Stone for the turbine foundations and access tracks would be excavated from two borrow pits located within the site, which will provide approximately 70,000 cubic metres of stone each. The turbine components would be delivered to site and stored at the temporary construction compound. The bottom turbine tower sections would firstly be bolted onto the foundations, followed by the upper turbine tower sections which would be lifted into place with a crane. The nacelle would then be fitted into place at the top section of the turbine tower. The turbine blades would be fitted to a rotor hub attached to the nacelle. Once construction works are nearly complete, the substation/site office/control building would be erected across part of the compound area. Two 80m high masts would also be erected within the site to collect local weather data. Crane platforms would be left in place after installation for use as parking by visiting staff and other maintenance vehicles during the operational phase, and would also be used at the end of the operational lifetime to dismantle the turbines. The two borrow pits would be restored with a top layer of soil or peat. The construction of the turbines, access tracks and use of borrow pits would affect areas of peat at the site. This valuable resource would initially be excavated and temporarily stored on-site during construction, and then used to reinstate the site once works have been completed. Best practice construction methods would also be employed on site, such as the use of floating roads to cross deep areas of peat to minimise potential damage. Some areas of woodland would need to be cleared to allow access; it is proposed to plant new areas of woodland at the site to compensate for this loss, the locations of which would be agreed with the landowner. A separate planning application would be made to obtain consent for the installation of a cable connection between the proposed development and the local electricity distribution network. Planning Policy National policy guidance and local development plans relevant to the form, location and nature of the proposed development were identified and reviewed to establish overall compliance with planning policy objectives. National policy identifies a requirement to encourage the use of renewable technologies to tackle the issue of climate change. Local policy acknowledges a need to promote onshore wind energy projects to help to meet renewable energy targets, recognising that the Highlands have a generous wind resource but also contain an abundance of natural resources and high quality landscapes which require safeguarding from inappropriate development. The existing Structure Plan and the Ross and Cromarty East Local Plan are soon to be replaced by the Highland Wide Local Development Plan and the Inner Moray Firth Local Development Plan. Both of these documents will be supported by a number of Supplementary Guidance documents, including one specific to onshore wind energy developments (Interim Onshore Wind Draft Supplementary Guidance ). This provides detailed guidance on where future large-scale wind farms could potentially be located and the Site is located within a broad area of search. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 4

6 Environmental Impacts and Mitigation The proposed development and associated mitigation measures have been designed to minimise adverse environmental effects. Nonetheless the EIA has identified that some impacts would arise from the proposals, the most significant of which are summarised below. Physical Environment Surveys confirmed that ground conditions at the site comprise peat underlain with glacial till and sand and gravel deposits. The site is positioned between two main watercourses - the Allt nan Caorach and Abhainn Sgitheach - which flow into the Cromarty Firth some 5km to the east. Figure 3: The Allt nan Caorach The assessment highlighted that the construction phase could potentially result in damage to peat resources, and cause contamination of watercourses and groundwater resources. The proposed development has accordingly been designed to avoid the deepest areas of peat (and areas sensitive to peat slide) and to minimise the potential impacts on soil resources. A number of new culverts and bridge crossings are proposed to enable access across the site, and to minimise impacts on river flows, flooding and natural habitats. Additional mitigation in the form of site-specific pollution and drainage control measures will also be employed to protect hydrological and geological interests. The assessment recorded that no significant impacts on assets associated with the physical environment would occur during the operational phase. Ecology The site lies in proximity to designated areas including: Ben Wyvis National Nature Reserve, Special Area of Conservation, Special Protection Area and Site of Special Scientific Interest; and the Allt nan Caorach Site of Special Scientific Interest. The western edge of the Site is close to the boundary of Ben Wyvis SAC and SSSI, designated for its blanket bog, heath and upland plant species. The central section of Ben Wyvis NNR is designated as a SPA for a nationally important population of breeding dotterel and lies further northwest from the Site (approximately 1.2km). Furthermore, the northern boundary of the Site is close to the Allt nan Caorach, where an SSSI has been designated for its streamside woodland and sub-alpine dry heath. The proposed access route to the Site crosses the Allt nan Caorach SSSI close to an existing ford. Detailed species and habitat surveys were accordingly undertaken as part of an ecological assessment to determine existing biodiversity value and interest at the site and wider locality. These Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 5

7 confirmed that habitats are those expected in an area dominated by deep peat with acidic mineral soils. Blanket bog is the most commonly occurring habitat, with unimproved grassland, scattered bracken and semi-natural woodland less widespread and more commonly associated with the Allt nan Caorach river corridor. Surveys also confirmed that the proposed site access route is dominated by coniferous and young plantation woodland. Evidence of otter and water vole was found along the Allt na h-eiridh burn within the Site. Limited evidence of bats, pine marten and badger were also recorded outwith the open moorland of the site, and walkover evidence also returned evidence of adder, common lizard and toad. Figure 4: Water Vole The layout of the proposed turbines and access tracks has been designed such that it avoids the most sensitive areas of habitat where possible, and construction works would be programmed to avoid seasonal constraints where possible. The assessment identified that construction of the proposed development would result in the permanent loss of 27.7ha of habitat comprising blanket bog and young plantation woodland, some of which has been identified as suitable for protected species (most notably Water Vole). The crossing of the designated Allt nan Caorach would require removal of a small amount of woodland and scrub vegetation. Ecological mitigation for impacts on the designated SSSI at Allt nan Caorach would be provided in the form of re-establishment of gorge woodland, planting to improve the woodland structure, and implementation of deer control measures. A programme of ecological works would also be implemented to restore habitats temporarily affected by construction works. Subject to the implementation of mitigation, the assessment concluded that no significant effects would arise on designated sites of nature conservation interest, valuable habitats or protected species. Ornithology The assessment of ornithological interests was informed by a series of consultations, desk studies and extensive site surveys (undertaken over bird breeding and migration periods) to initially establish the nature conservation value of the study area and bird species present. The Ben Wyvis Special Area of Conservation and Special Protection Area and are located adjacent to and 1.5km northwest of the site respectively. The site lies some 6.5km north of the Cromarty Firth Special Protection Area, and a proposed Special Protection Area at Novar lies approximately 3.5km east of the site. Collectively these sites are of very high conservation value, and are designated on the basis of their inherent ornithological interest. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 6

8 Surveys recorded a range of high value bird species to be present within the study area, including: Red-throated Diver; Whooper Swan; Pink-footed Goose; Greylag Goose; Osprey; Red Kite; Golden Eagle; Hen Harrier; Goshawk; Peregrine Falcon; Merlin; Black Grouse; Golden Plover; Dotterel; Greenshank; Short-eared Owl; Crested Tit; Scottish Crossbill; and Capercaillie. A range of lower value species were also recorded, including Skylark and Red Grouse, which were identified as breeding within the site. The moorland habitats on the site itself were found to be of relatively low importance for breeding birds. The design and layout of the proposed development has given due regard to the avoidance of sensitive habitats and designations of value in order to reduce potential ornithological impacts. Following confirmation of Capercaillie presence, the alignment of the main access road and substation location were carefully selected to minimise potential impacts on this protected species. The assessment concluded there would be no direct impacts on species associated with designated sites as a consequence of development, and that woodland habitats affected by the proposals comprise commercial conifer species that are a common feature in the locality and throughout Easter Ross. The assessment recorded little potential for operational disturbance on most identified species. Collision risk modelling recorded risks of limited significance on Greylag Goose and Golden Plover species; however the predictions for Red Kite identified a potentially significant issue warranting the development of appropriate mitigation to reduce the magnitude of risk. This would take the form of removal of deer carcasses from the site and immediate surroundings to reduce scavenging and therefore the risk of collision mortality. The implementation of a suite of habitat enhancement measures - including the replanting and management of Scot s Pine, retention of windblown areas, and selective felling and thinning of woodland - will result in a degree of benefit on Capercaillie and other species including Black Grouse. No significant cumulative impacts in relation to Red Kite collision risk with the proposed development and other wind farms were found to be likely in the assessment. Landscape and Visual Impact Figure 5: Computer generated view of the proposed development from the Black Isle An assessment of the existing landscape and visual context of a study area extending to 35km beyond the site was undertaken to establish the implications that construction and operation of the proposed development would have on established landscape features and visual amenity. The assessment identified that the study area comprises a number of distinctive landscape character areas, within which sensitivities have been protected by way of designations in the form of National Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 7

9 Scenic Areas, Special Landscape Areas, Wild Land, and Historic Gardens and Designed Landscapes. A number of representative viewpoints were identified and assessed from various locations within the study area, supported by computer generated photography and modelling of the proposed development to accurately determine visual impact. The EIA process has resulted in a number of design and layout modifications to the proposed turbines and access tracks which sought to improve landscape integration and reduce visual intrusion across the study area. The assessment concluded there would be no significant impacts on landscape character a result of development progression, save for impacts of local significance on one area of distinct character within which the proposals would be located. Significant impacts were also indentified in relation to one special quality of the Ben Wyvis Special Landscape Area in relation to the outlook towards this designation from the Black Isle. Of the 19 representative viewpoints assessed, the proposed development would result in significant impacts from seven viewpoints, specifically: Viewpoint 1 - Glenglass Old Dance Hall; Viewpoint 2 - Near Milton Lodge; Viewpoint 3 - Heights of Docharty; Viewpoint 5 - Ben Wyvis; Viewpoint 6 Knockfarrel; Viewpoint 7 - Cnoc Fyrish; and Viewpoint 8 B9169 near Culbokie. These views all relate to residential dwellings or recreational viewpoints within 8km of the site. Consideration was given in the assessment to potential cumulative impacts of the proposed development in combination with other existing and proposed wind energy developments in the local area. The cumulative assessment concluded that the proposed development would be well positioned between the operational Novar and Fairburn wind farms, with clear separation between it and these developments. There would be no significant issues in relation to a proposed single turbine scheme at Foulis Farm located south of the site. No significant impacts were identified in relation to sequential views of the proposed development (and other wind energy schemes) from major transport routes along the A9 from Tomatin to Inverness and beyond to Tain, the A862 Inverness to Ardullie Lodge (A9), and the A96 Inverness Nairn. Archaeology and Cultural Heritage In respect of the archaeological and built environment, the assessment identified the Balnacrae Chambered Cairn as the closest Scheduled Monument to the site, located approximately 1km to the southeast. Figure 6: Balnacrae chambered cairn The nearest designated Conservation Area to the site is Dingwall, located some 6.2km to the southeast. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 8

10 Records indicate there are ten Listed Buildings within 5km of the site, and a further nine Category A Listed Buildings located within 15km. There are also six Historic Gardens and Designed Landscapes within 15km of the site, and fifty-four non-scheduled heritage assets within 2km of the Site. As a consequence of detailed design and layout modifications, the vast majority of archaeological sites and features would not be directly affected by the proposed development. Four known site of low/negligible importance would be subject to direct impacts of no greater than moderate significance through development progression; for these sites a comprehensive mitigation strategy of archaeological monitoring is proposed. In relation to indirect impacts built heritage features, the assessment identified low levels of impact on the contextual setting of three assets: Balnacrae Chambered Cairn; Heights of Brae Chambered Cairn, and Fairburn Historic Garden and Designed Landscape. The assessment concluded that such impacts would be temporary and reversible upon decommissioning of the proposed development, and that no significant cumulative impacts would arise. Archaeological monitoring in the form of a watching brief would be undertaken to record any archaeological deposits or artefacts encountered during the construction phase. Noise In relation to noise impacts, site surveys were undertaken at a number of locations within and immediately surrounding the site to establish the existing noise climate. The potential impact of noise from the operational Development has been assessed using the methodology set out in ETSU R-97 (as required by the Scottish Government). Noise receptors to be considered in the assessment were agreed with THC. Figure 7: Monitoring location at Eileanach Lodge (2.7km from the nearest turbine) The assessment of worst-case noise levels against established guidance and standards concluded that construction noise would be generated by the operation of plant and machinery, but would be in keeping with typical daytime noise levels experienced by residents of nearby dwellings. The modelling and assessment of operational noise associated with the movement of the turbine blades concluded that noise levels would be below defined limits at all assessed locations. No significant impacts were recorded in relation to cumulative noise impacts associated with the proposed development and the existing Novar Wind Farm. Best practice site management techniques would be employed to control noise levels and minimise disturbance throughout the construction period, including the imposition of working hour restrictions and regular maintenance of plant and equipment. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 9

11 Traffic and Transport Consultation with the Highland Council identified an appropriate route for traffic to use during construction of the proposed development, this being a route previously used during the construction of the Novar Wind Farm. This route was accordingly taken into account in the assessment of potential traffic and transport impacts associated with construction and operation of the proposed development. The assessment also took consideration of site access via the existing Novar Wind Farm access track and then along a new and upgraded section of forest track. Figure 8: Existing Novar Wind Farm Extension Access Track The assessment determined that construction vehicles would only use the local road network for a relatively short distance between the A9 trunk road and the Novar Wind Farm access track (this route ensures that this traffic avoids travelling through the village of Evanton), and for a short distance along the Glen Glass Road. Temporary impacts would be associated with increased vehicles on the network which may generate conflicts with pedestrians and result in journey delays. Post construction of the proposed development, there would be a very limited number of vehicle movements associated with future maintenance events and periodic inspections. A number of traffic management measures would be employed during construction to reduce disruption and delays on the local network. These would take the form of regulated timings for the delivery of plant and equipment to/from the site to avoid conflicts with peak periods, regular consultation with local residents throughout the works, and adherence to traffic safety procedures. Climate Change In establishing the net impact on greenhouse gas (GHG) emissions and the overall impact of the proposed development on climate change, a Carbon Balance Assessment across the entire development life-cycle identified that construction works would result in net GHG emissions (due to activities such as the manufacture of the wind turbine and the loss of organic carbon from excavated peat at the site). The assessment identified that some GHG savings would be realised through the storage and reinstatement of peat at the site. The net impact from the construction and decommissioning of the proposed development would be circa 165,000 tonnes of carbon dioxide (tco2e). GHG savings predicted from the operation of the proposed development would be over 64,000 tco2e annually. Over a 25-year operational lifespan, the proposed development would have a payback period of 2.6 years (this being the period before the proposals would begin to deliver GHG savings). The assessment calculated that the total net GHG impact would be positive, and would be in the order million tonnes of CO2e over its lifespan. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 10

12 Socio Economics In relation to the impacts on employment, tourism and the local economy, the assessment of socioeconomic aspects identified that existing uses of the site centre on commercial forestry and deer stalking. Local accommodation for visitors and tourists is available in Evanton and Dingwall, some 5km east and 6km south of the site respectively. The site is located southeast of the munro of Ben Wyvis, a popular hill with walkers and people visiting the nature reserve on the summit plateau. North of the site, Loch Glass and Loch Morie are frequently used for recreational activities such as fishing and accommodate a series of holiday homes near their banks. Within the wider area golf courses, historical and cultural sites and outdoor pursuits such as shooting and cycling are a draw for tourists. The construction phase of the proposed development would generate short term labour demands in the form of construction jobs; the appointed principal contractor would be encouraged to use local labour and materials wherever possible, in order to maximise and retain benefits locally. The assessment has identified that construction would require a temporary halt to deer stalking activities on the site during the works, and that potential exists for localised disruption and disturbance to local walkers and visitors. The assessment has identified that recreational users of the tracks and paths very close to and within the site could experience combined noise and visual impacts associated with the construction and operation of the development (sometimes in combination with other wind farms in the wider area); however these are not considered to constitute significant impacts. During the operational phase, there would be a small number of full time equivalent jobs created as a result of the proposed development. No significant impacts are predicted on local employment, commercial estate operations or on local visitor attractions/recreational facilities during this phase. Falck intend to pay annual community benefit payments into a community fund during the operational lifespan of the proposed development, the details of which would be formulated and agreed with the Highland Council and other relevant parties. In conjunction with Energy4All, Falck would offer the local community opportunities to invest in the proposed development. EMI, Telecommunications and Aviation An assessment of potential interference on electromagnetic signals associated with communication networks, television reception and the telemetry systems used by utilities providers revealed that the proposed development would not have a significant impact on radio-communications once operational. With regard to aviation, the site is located 68km to the east of RAF Lossiemouth - an operational airfield equipped with surveillance radar for air traffic control with a range of 111km. The assessment concluded that operation of the proposed development would have no effect on their primary surveillance radar. Inverness Airport is located 28km south of the site and handles approximately 28,000 aircraft movements per year. An assessment of the radar line of sight from the airport primary surveillance radar to the blade tip height of each of the proposed turbines concluded that the radar would have line of sight to 15 of the proposed turbines. Discussions with Highlands & Islands Airports Ltd regarding the significance of this have commenced; should this be considered an operational issue, appropriate mitigation will be developed. Although parts of the site are located within military restricted airspace / tactical training areas, the assessment recorded there to be no significant impacts on low flying operations. Shadow Flicker The assessment identified no residential properties are located in the area within which the effect of operational shadow flicker may occur, this being a distance of 930m (or ten rotor diameters) from any of the proposed turbines. The assessment identified that planning consent is in place for a single residential property (to be owned by the Landowner at Clach Liath) that would be built following construction of the proposed development. An assessment of the implications for this property confirmed that the shadow flicker effect would not prove significant post construction of the dwelling. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 11

13 Environmental Management Mitigation of construction related impacts would be addressed through the required adoption and implementation of a Construction Environmental Management Plan (CEMP). The CEMP would include details of measures to be employed by the appointed contractor to ensure that potential noise, pollution, nuisance and/or disturbance during the construction phase are minimised or avoided. The CEMP would include procedures for providing regular correspondence and updates to local residents and community organisations about the project, and will contain a number of secondary plans that will address specific aspects of the works such as traffic management and habitat restoration. Further Information Copies of the submitted planning application, Environmental Statement and other supporting documentation are available for inspection at public venues as specified by Highland Council. The person who may be contacted for further information on the project is: Joe Somerville RSK Environment Ltd 65 Sussex St Glasgow G41 1DX Tel: clachliath@rsk.co.uk Further copies of the ES may be obtained from the RSK office at the above address. The cost for an electronic copy on DVD (including Non Technical Summary) is 25. A quote for hard copies can be provided on request. A copy of the Non Technical Summary is available free of charge from the above RSK office. Falck Renewables Wind Ltd and Coriolis Energy LLP NTS - 12

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition and Stronelairg s Overview SSE Renewables SSE Renewables is the renewable energy development division of SSE. The company is responsible for the development of onshore and offshore wind farms in the UK,

More information

Introduction. The Need for Wind Energy. Consultation. The Applicant

Introduction. The Need for Wind Energy. Consultation. The Applicant Introduction Peel Wind Farms (UKC) Ltd (Peel) propose to construct a wind farm on an area of land that forms part of the former Asfordby mine and tip site and part of the existing Asfordby Business Park

More information

LINE ONE LINE TWO LINE THREE

LINE ONE LINE TWO LINE THREE LINE ONE LINE TWO LINE THREE Environmental Statement Volume 1: Non-Technical Summary Prepared by This document has been prepared by Limited for the sole use of our client (the Client ) and in accordance

More information

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION Force 9 Energy is seeking to develop a 5 turbine wind farm 1.5km to the east of Auldgirth, approximately 15km north of Dumfries. It is bounded to the north

More information

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

State code 23: Wind farm development

State code 23: Wind farm development 23.1 Purpose statement The purpose of the code is to protect individuals, communities and the environment from adverse impacts as a result of the construction, operation and decommissioning of wind farm

More information

SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT

SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT Volume 3: Figures December 2008 VOLUME THREE: FIGURES INTRODUCTION 1.1 Location of Wind Farms Requiring Connection

More information

Ardchonnel Wind Farm. Environmental Statement Non-Technical Summary. November 2013

Ardchonnel Wind Farm. Environmental Statement Non-Technical Summary. November 2013 Ardchonnel Wind Farm Environmental Statement Non-Technical Summary November 2013 Contents Introduction 2 Renewable Energy Policy 3 Environmental Impact Assessment 4 Site Selection and Design Strategy 4

More information

Harelaw Renewable Energy Park Environmental Statement. Final. Delivering sustainable solutions in a more competitive world. Non Technical Summary

Harelaw Renewable Energy Park Environmental Statement. Final. Delivering sustainable solutions in a more competitive world. Non Technical Summary Harelaw Renewable Energy Park Environmental Statement Non Technical Summary Final January 2009 www.erm.com Delivering sustainable solutions in a more competitive world Gamesa Energy UK Harelaw Renewable

More information

Environmental Statement South Kyle Wind Farm August 2013

Environmental Statement South Kyle Wind Farm August 2013 19 AVIATION, RADAR, INFRARED LIGHTING AND ELECTROMAGNETIC INTERFERENCE (EMI)... 2 19.1 Aviation and Radar... 2 19.1.1 Executive Summary... 2 19.1.2 Introduction... 2 19.1.3 Approach... 3 19.1.4 Potential

More information

Clyde Extension Wind Farm Non-Technical Summary

Clyde Extension Wind Farm Non-Technical Summary Clyde Extension Wind Farm Non-Technical Summary Preface This document forms the non-technical summary (NTS) of the to the Environmental Statement (ES) that accompanies an application made by Clyde Windfarm

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0 RMB Chivenor Flood Defence Scheme Non-Technical Summary FINAL Version 3.0 RMB CHIVENOR FLOOD DEFENCE SCHEME ENVIRONMENTAL STATEMENT CONTENTS 1 INTRODUCTION AND BACKGROUND II 2 THE PROPOSED PROJECT III

More information

Glenmuckloch Pumped Storage Hydro Scheme

Glenmuckloch Pumped Storage Hydro Scheme Glenmuckloch Pumped Storage Hydro Scheme Contents Introduction 1 The Applicant 2 Purpose of the NTS 2 Further Information 2 Project Benefits 3 Objectives & Need for Development 3 Economic Benefits 4 How

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

Ben Aketil Wind Farm. Non-Technical Summary. Volume 4. August 2002

Ben Aketil Wind Farm. Non-Technical Summary. Volume 4. August 2002 Ben Aketil Wind Farm Non-Technical Summary Volume 4 August 2002 WIND - CLEAN ENERGY FOR A SUSTAINABLE FUTURE WIND ENERGY IN EUROPE OVERALL CONCLUSION FURTHER INFORMATION There is now increasing evidence

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

Oweninny Wind Farm. Oweninny Power Ltd. Environmental Impact Statement. Chapter 20. Indirect and Interaction of Impacts

Oweninny Wind Farm. Oweninny Power Ltd. Environmental Impact Statement. Chapter 20. Indirect and Interaction of Impacts Oweninny Wind Farm Oweninny Power Ltd. Chapter 20 Indirect and Interaction of Impacts Copyright ESB International Limited, all rights reserved. TABLE OF CONTENTS 20. INDIRECT AND INTERACTION OF IMPACTS

More information

KIRKBY MOOR WIND FARM LIFE EXTENSION

KIRKBY MOOR WIND FARM LIFE EXTENSION SCOPING REPORT ENVIRONMENTAL IMPACT ASSESSMENT KIRKBY MOOR WIND FARM LIFE EXTENSION Date of Issue: 26 July 2016 Version: FINAL Prepared by: RWE Innogy UK Ltd Recipient: South Lakeland District Council

More information

Alan Fielding & Paul Haworth

Alan Fielding & Paul Haworth Alan Fielding & Paul Haworth Outline Loss of sub-adult habitat (displacement) Population-level effects of mortality (collision) Non-breeding birds Breeding birds Loss of golden eagle ranges (displacement)

More information

APPENDIX A14.6 SITE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX A14.6 SITE ENVIRONMENTAL MANAGEMENT PLAN APPENDIX A14.6 SITE ENVIRONMENTAL MANAGEMENT PLAN SITE ENVIRONMENTAL MANAGEMENT PLAN VIKING WIND FARM Document Ref. SEMP Version 1 Page i SITE ENVIRONMENTAL MANAGEMENT PLAN VIKING WIND FARM CONTENTS DOCUMENT

More information

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow Environmental Statement Non-Technical Summary Rectory Farm, Hounslow Introduction This document is the Non-Technical Summary (NTS) of the Environmental Statement (ES) for a proposed development at the

More information

SECTION 36 OF THE ELECTRICITY ACT 1989 AND SECTION 57 OF THE TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997

SECTION 36 OF THE ELECTRICITY ACT 1989 AND SECTION 57 OF THE TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 Directorate for Planning and Environmental Appeals Report to the Scottish Ministers SECTION 36 OF THE ELECTRICITY ACT 1989 AND SECTION 57 OF THE TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 Report by

More information

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows: SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Chapter 12 Traffic and Transport

Chapter 12 Traffic and Transport Chapter 12 Traffic and Transport Introduction 12.1 This chapter considers the potential access and traffic impacts associated with the construction, operation and decommissioning of the proposed Wind Farm.

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy

Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy Migratory Soaring Birds Project Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy Importance of the sector Energy consumption is rapidly increasing all over

More information

energy, environment & design aterman Poniel, South Lanarkshire Environmental Statement: Non-Technical Summary

energy, environment & design aterman Poniel, South Lanarkshire Environmental Statement: Non-Technical Summary aterman energy, environment & design Poniel, South Lanarkshire Poniel, South Lanarkshire Non-Technical Summary INTRODUCTION SRG Estates Limited (SRGE) (hereafter referred to as the Applicant ) is seeking

More information

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. The site comprises the employment element of the South West Rugby allocation

More information

RWE npower renewables welcomes you to our exhibition about the proposed Glenmount Wind Farm.

RWE npower renewables welcomes you to our exhibition about the proposed Glenmount Wind Farm. WIND FARM EXHIBITION RWE npower renewables welcomes you to our exhibition about the proposed Glenmount Wind Farm. The purpose of this exhibition is to: explain why we have identified this site for a potential

More information

20 INDIRECT AND INTERACTION OF IMPACTS

20 INDIRECT AND INTERACTION OF IMPACTS 20 INDIRECT AND INTERACTION OF IMPACTS 20.1 INTRODUCTION The EU Guidelines for the Assessment of Indirect and Cumulative Impacts as well as Impact Interactions states that Including an assessment of the

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

Decision by Richard Dent, a reporter appointed by the Scottish Ministers

Decision by Richard Dent, a reporter appointed by the Scottish Ministers Directorate for Planning and Environmental Appeals Appeal Decision Notice T: 01324 696 400 F: 01324 696 444 E: dpea@scotland.gsi.gov.uk Decision by Richard Dent, a reporter appointed by the Scottish Ministers

More information

Inveraray to Crossaig Overhead Line Reinforcement

Inveraray to Crossaig Overhead Line Reinforcement About Scottish Hydro Electric (SHE) Transmission plc Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in

More information

Ardersier Wastewater Treatment Works

Ardersier Wastewater Treatment Works Ardersier Wastewater Treatment Works Environmental Statement: Non-Technical Summary March 2010 Scottish Water Ardersier Wastewater Treatment Works 251886 SNI INV ES 021 10 March 2010 Environmental Statement:

More information

It will be of particular interest to those potentially affected by the Government s proposals for high speed rail.

It will be of particular interest to those potentially affected by the Government s proposals for high speed rail. HIGH SPEED TWO INFORMATION PAPER E8: ARCHAEOLOGY This paper outlines HS2 Ltd's approach to assess and reduce as far as reasonably practicable the impact on archaeological remains that could result from

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

Longbridge Town Centre Planning Application

Longbridge Town Centre Planning Application Longbridge Town Centre Planning Application Non-Technical Summary of the Environmental Statement January 2011 Introduction An application for Planning Permission has been submitted to Birmingham City Council

More information

Enclosed farmland: Arable and Horticultural, Improved and Neutral Grasslands

Enclosed farmland: Arable and Horticultural, Improved and Neutral Grasslands executive summary Executive summary 1 Countryside Survey 2000 (CS2000) and the Northern Ireland Countryside Survey 2000 (NICS2000) have been designed to provide detailed information about the habitats

More information

South Bristol Link Sustainability Statement. May 2013

South Bristol Link Sustainability Statement. May 2013 May 2013 1 2 Notice This document and its contents have been prepared and are intended solely for West of England Partnership s information and use in relation to the of South Bristol Link. It may not

More information

Scottish Forestry Grants Scheme review: Consultation questions.

Scottish Forestry Grants Scheme review: Consultation questions. Scottish Forestry Grants Scheme review: Consultation questions. Use this document to provide your answers to the questions contained in the consultation document. Please use as much space as you require

More information

IN THE MATTER of the Resource Management Act 1991 MERIDIAN ENERGY LIMITED. Appellant SOUTHLAND DISTRICT COUNCIL. Respondent NOTICE OF APPEAL

IN THE MATTER of the Resource Management Act 1991 MERIDIAN ENERGY LIMITED. Appellant SOUTHLAND DISTRICT COUNCIL. Respondent NOTICE OF APPEAL BEFORE THE ENVIRONMENT COURT AT CHRISTCHURCH ENV-2014-CHC- IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER BETWEEN of an appeal under Clause 14(1), First Schedule of the Act in relation

More information

Wind Turbine Zoning for CERTs

Wind Turbine Zoning for CERTs Turbine Northwest Energy Workshop August 3rd, 2006 University of Minnesota Crookston Mark Lindquist The Minnesota Project www.mnproject.org The Model Ordinance Project Collaboration of: The Minnesota Project

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

Gores Wind Farm. Environmental Statement. Volume 1 - Written Text

Gores Wind Farm. Environmental Statement. Volume 1 - Written Text Gores Wind Farm Environmental Statement Volume 1 - Written Text Prepared By West Coast Energy Limited Mynydd Awel Mold Business Park Maes Gwern Mold CH7 1XN VOLUME ONE - WRITTEN TEXT CHAPTER ONE - INTRODUCTION

More information

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions. 18. Air The Project Air quality team prepared an Air Quality Assessment Report for the Project, which is included in Volume 3 (Part 1). The Report provides an assessment of air quality effects associated

More information

Thorn Turn Winter Maintenance and Highways Depot

Thorn Turn Winter Maintenance and Highways Depot Thorn Turn Winter Maintenance and Highways Depot Non-Technical Summary Central Bedfordshire Council 12 May 2015 1 Notice This document and its contents have been prepared and are intended solely for Central

More information

Park Spring Wind Farm Non-Technical Summary

Park Spring Wind Farm Non-Technical Summary Park Spring Wind Farm Prepared for EDF Energy Renewables Endeavour House Victory Way Doxford Business Park Sunderland SR3 3XL Prepared by Parsons Brinckerhoff Amber Court William Armstrong Drive Newcastle

More information

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES SECTION 1601 Wind Energy Installation In any zoning district, a conditional use permit or building permit may be granted to allow a wind energy conversion

More information

Western Rail Link To Heathrow

Western Rail Link To Heathrow Non-T echnical Summar y - Initi al Envir onmental Infor mati on R eport Networ k R ail Western Rail Link To Heathrow Network Rail Non-Technical Summary - Initial Environmental 129088-JAC-REP-HEN-000014

More information

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards 06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards THE APPLICATION Planning permission is sought for the construction of a noise attenuation

More information

Rural Living Environment

Rural Living Environment 1 RLE.1 Rural Living Environment RLE.1.1 Description & Expectations The Rural Living Environment (RLE) covers rural areas within the District that are either already characterised by lifestyle activities

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

Woodland Assessment Grant Guide

Woodland Assessment Grant Guide GENERAL DETAILS PLANNING Version 1/June 2005 For updates and the latest version go to: www.forestry.gov.uk/ewgs 3 English Woodland Grant Scheme Woodland Assessment Grant Guide Purpose ASSESSMENT Woodland

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Appendix General Environmental Risk Analysis

Appendix General Environmental Risk Analysis Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

WIND ENERGY AND YOUR LAND

WIND ENERGY AND YOUR LAND WIND ENERGY AND YOUR LAND WIND FARMS & your land Wind turbines and farmland can work very well together, but choosing the right partner is critical. RES works with landowners, farmers and estate managers

More information

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5 CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

Rising Sun. Scaffold Hill. Flood Risk Assessment

Rising Sun. Scaffold Hill. Flood Risk Assessment Rising Sun Scaffold Hill Flood Risk Assessment August 2010 Contents 1.0 Introduction... 4 2.0 Site Description... 5 3.0 Legislative Framework... 6 4.0 Flood Risk... 10 5.0 Surface Water Drainage... 11

More information

Chapter 14 Overall Project Assessment

Chapter 14 Overall Project Assessment Chapter 14 Overall Project Assessment TABLE OF CONTENTS 14 OVERALL PROJECT ASSESSMENT... 14-1 14.1 Introduction... 14-1 14.2 Development of the ESIA... 14-1 14.2.1 Adopted Process... 14-1 14.2.2 Challenges

More information

High Pressure Natural Gas Pipeline Pembroke Refinery. Environmental Statement Non-technical Summary

High Pressure Natural Gas Pipeline Pembroke Refinery. Environmental Statement Non-technical Summary High Pressure Natural Gas Pipeline Pembroke Refinery Environmental Statement Non-technical Summary July 2010 1. Introduction 1.1 Overview 1. Chevron Limited (Ltd) is seeking detailed planning permission

More information

Siting Guidelines for Windpower Projects in Kansas

Siting Guidelines for Windpower Projects in Kansas Siting Guidelines for Windpower Projects in Kansas The Kansas Renewable Energy Working Group Environmental and Siting Committee Introduction The Environmental and Siting Committee of the Kansas Renewable

More information

The Isles Wind Farm proposal. Consultation Document Stage One Consultation under Section 42 Planning Act 2008

The Isles Wind Farm proposal. Consultation Document Stage One Consultation under Section 42 Planning Act 2008 The Isles Wind Farm proposal Consultatio on Document The Isles Wind Farm proposal Prepared by: Reviewed by: Approved by: Laura Keetley Consultant AECOM Ltd. Andrew Range Senior Consultantt AECOM Ltd. James

More information

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm EXECUTIVE SUMMARY This (SEIS) has been prepared for the proposed Jericho Rise Wind Farm (the Project). LLC (the Applicant), a wholly owned subsidiary of EDP Renewables (EDPR), is proposing to construct

More information

Palm Beach County Project, LLC

Palm Beach County Project, LLC Palm Beach County Project, LLC February 9, 2011 Agenda Introductions Wind Capital Group Four basics of a wind farm Why Florida? Environmental Process How we build a wind farm Wind Capital Group Independently

More information

Ecological Mitigation and Management Plan

Ecological Mitigation and Management Plan Ecological Mitigation and Management Plan LONDON ARRAY OFFSHORE WIND FARM PROJECT AND ASSOCIATED GRID CONNECTION WORKS Version / Date : Ver 1.00 / October 2007 Prepared by : Tim Proudler / Keith Henson

More information

Nance County Zoning Regulations for Wind Energy Conversion Systems

Nance County Zoning Regulations for Wind Energy Conversion Systems Nance County Zoning Regulations for Wind Energy Conversion Systems ARTICLE 1: SMALL / NON-COMMERCIAL WIND ENERGY SYSTEMS Section 1. Purpose It is the purpose of this regulation to promote safe, effective

More information

Documents submitted in response to Regulation 22 request. Additional documents submitted by Provectus Remediation Ltd

Documents submitted in response to Regulation 22 request. Additional documents submitted by Provectus Remediation Ltd Documents submitted in response to Regulation 22 request The documents recently submitted by Provectus Remediation Ltd in response to the Planning Inspectors request under Regulation 22 add nothing of

More information

Former MOD Site Hempsted Lane, Gloucester

Former MOD Site Hempsted Lane, Gloucester FORMER MOD SITE, HEMPSTED LANE, GLOUCESTER NON-TECHNICAL SUMMARY Introduction Bovale Ltd proposes to undertake the redevelopment of the former MOD site, Hempsted Lane, Gloucester. The redevelopment will

More information

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England West East Link Main 55km pipeline, carrying 100 million litres, is one of the largest ever undertaken by a water company by Jon Higham The West East Link Main is a 125 million pipeline project that will

More information

7 Environmental Impact Assessment Process and Methodology

7 Environmental Impact Assessment Process and Methodology 7 Environmental Impact Assessment Process and Methodology EIA Process 7.1 Environmental Impact Assessment (EIA) is a process that identifies the potential environmental effects 1 (both positive and negative)

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Volume Three: SEA Statement and Natura Impact Report 3 Volume 3: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Contents Section 1 Strategic

More information

Cassadaga Wind Project Exhibit 6. Wind Power Facilities

Cassadaga Wind Project Exhibit 6. Wind Power Facilities Case No. 14-F-0490 1001.6 Exhibit 6 Wind Power Facilities WIND POWER FACILITIES (a) Factors Considered During Placement of Wind Turbines (Setback Requirements/Recommendations/Fall-Down Distances) The primary

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Environmental Impact Statement for the Slave Falls Tramway Conversion Project Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT

More information

Longlands Lane Wind Turbine Newport. Volume I Non Technical Summary

Longlands Lane Wind Turbine Newport. Volume I Non Technical Summary Newport Volume I Non Technical Summary Hyder Consulting (UK) Limited 2212959 Hyder Consulting UK Ltd HCL House, St Mellons Business Park, St Mellons, Cardiff, CF3 0EY Tel: +44 (0) 2920 926 700 Fax: +44

More information

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT Welcome Eggborough Power Ltd (EPL) is proposing to develop a new gas-fired power station on the site of its existing coal-fired

More information

U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE

U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE May 11, 2009 STANDARD RECOMMENDATIONS TO AVOID, MINIMIZE AND MITIGATE POTENTIAL IMPACTS OF WIND ENERGY

More information

High Speed Rail (London- West Midlands)

High Speed Rail (London- West Midlands) High Speed Rail (London- West Midlands) Draft Environmental Minimum Requirements Annex 4: Draft Environmental Memorandum November 2013 ESA 4.2 High Speed Rail (London- West Midlands) Draft Environmental

More information

Port of Hull Local Development Order

Port of Hull Local Development Order Port of Hull Local Development Order Integrated Environmental Assessment Non Technical Summary March 2012 Final Prepared for: Hull City Council UNITED KINGDOM & IRELAND REVISION SCHEDULE Rev Date Details

More information

Sustainable Catchment Area Management Planning (SCAMP NI)

Sustainable Catchment Area Management Planning (SCAMP NI) CIEEM Conference 24 th November 2014 Sustainable Catchment Area Management Planning (SCAMP NI) a more environmentally sustainable approach to improving water quality Roy Taylor Catchment Manager Presentation

More information

NIGG YARD FOR SALE. TAIN, NEAR INVERNESS, SCOTLAND

NIGG YARD FOR SALE.  TAIN, NEAR INVERNESS, SCOTLAND NIGG YARD TAIN, NEAR INVERNESS, SCOTLAND A unique 96.14 ha (238 acre) facility combining extensive fabrication/warehouse buildings, generous yards, craneage, dry dock, and quayside, in a strategic North

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective

BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective 1. Provide a miture of sustainably designed new housing to provide everybody in South East Lincolnshire with the opportunity

More information

Wind Energy Development Specialist Report

Wind Energy Development Specialist Report United States Department of Agriculture Forest Service Southwestern Region Cibola National Forest and National Grasslands Wind Energy Development Specialist Report Kiowa, Rita Blanca, Black Kettle and

More information

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 AGENDA Opening and Welcome Introduction of Consultants Profile of Izwelisha Consortium Explanation of the EMF process Environmental

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

ERCHLESS FOREST EAST. Nr Beauly, Inverness-shire Hectares / 1, Acres. John Clegg & Co CHARTERED SURVEYORS & FORESTRY AGENTS

ERCHLESS FOREST EAST. Nr Beauly, Inverness-shire Hectares / 1, Acres. John Clegg & Co CHARTERED SURVEYORS & FORESTRY AGENTS ERCHLESS FOREST EAST Nr Beauly, Inverness-shire 450.65 Hectares / 1,113.55 Acres John Clegg & Co CHARTERED SURVEYORS & FORESTRY AGENTS ERCHLESS FOREST EAST Beauly 10 miles Dingwall 19 miles Inverness 20

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information