A Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling
|
|
- Andrea Grant
- 6 years ago
- Views:
Transcription
1 A Radiation Protection Perspective- Decommissioning of the Moata Reactor Biological Shield Dismantling Australian Nuclear Science & Technology Organisation IAEA Workshop (R2D2) Sydney Australia 7 th -11 th May 2012
2 Shutdown & Decommissioning Two phases of dismantling: Preliminary Dismantling the removal of the internal components of the reactor, including the steel core structures, graphite moderator and beam line facilities Structural (Biological Shield) Dismantling the cutting and removal of the concrete shielding and the floor area below the shielding.
3 Structural (Biological Shield) Dismantling
4 Structural (Biological Shield) Dismantling Reactor housed in a building used for other operational task A containment tent with HEPA filtered extraction system built around the reactor
5 Getting There The steps involved in planning, completing and evaluating the success of the Biological shield Dismantling: Radiation Protection Plan Characterisation Radiation Management & Monitoring Dose Estimation & Constraints Personal Protective Equipment Final Status Surveys Outcomes & Lessons Learnt
6 Characterisation Survey A radiological survey was carried out to determine the dose rates within the empty cavity areas. The data from this exercise was used to prepare a dose estimate for the Biological shield dismantling. This helped us estimate the maximum individual and collective dose for this part of the project. Measured dose rates ranged from Sv/hr
7 Dose Estimation and Constraints TASK SET 2 Est. Exp Time (hours) for most exposed individual Estimated Doserate Estimated Dose Estimated Dose Estimated Dose Estimated Dose Main Bioshield (Heavy Density Concrete) Estimated time to (µsv/hr) for Worker Received (µsv) Worker Received (µsv) Worker Received (µsv) for Received (µsv) for Estimated Doserate Active Zone perform task 1,2,3 or 4 1-Cardinal 2-Cardinal Worker 3-Cardinal Worker 4-Cardinal (µsv/hr) for HPS 1 Machine demolition-remote operation HPS Monitoring surveys Bobcat waste removal Dose Estimates: Material removal with 5tonne excavator 16 Collective ,400 man-μsv 560 Manual filling of waste containers Av. Individual 1156μSv (assuming 9 workers) Estimated Dose Received (µsv) HPS 1 Total For Cutting and Removal Of Main Max. Individual 1444μSv Bioshield (Active concrete) Dose Constraints: Individual 1500μSv Daily 50μSv Summary Dose = Estimated Collective dose man- Sv
8 Radiation Management & Monitoring Controlling exposure using distance
9 Radiation Management & Monitoring Controlling exposure using shielding Steel Plates for shielding
10 Radiation Management & Monitoring Controlling exposure using shielding Shielded containers for activated waste: Specially designed 6mm steel boxes for active concrete
11 Radiation Management & Monitoring Dose Management: Radiological surveys Dose Monitoring: EPD System TLDs Whole Body Monitoring
12 Radiation Management & Monitoring External gamma monitors and air samplers were placed close to work areas. Barrier and exit monitoring equipment were used to ensure that no contamination was taken out of the classified areas.
13 Personal Protective Equipment Since there was a high potential of generating dust while cutting and demolishing the active concrete it was decided to start from the highest level of PPE which included ; Respiratory protection with particulate cartridge) Tyveks Overshoes and gloves This was than downgraded as we gained operational understanding of the project risks.
14 Final Status Survey Dose rate surveys were carried out on marked survey points (grid survey) Acceptance criteria of 0.5uSv/hr was met to ensure a brown-field condition was met Samples were taken in and around the foundations of the reactor and analysed for activity. The following guides were also used to determine the exemption and clearance criteria for the site IAEA No. RS-G.1.7 ARPANSA Reg 1999, Schedule 2, Part 2
15 Outcomes & Lessons Learnt Estimated doses vs. actual doses: Dose Collective Max. Individual ANSTO Estimated 10,400 personμsv ARPANSA Constraint 13,000 personμsv ANSTO Constraint 10,400 personμsv Actual 1,679 personμsv 1444 μsv 1750 μsv 1500 μsv 252 μsv Daily μSv 46μSv (max)
16 Outcomes & Lessons Learnt From a radiation protection perspective the Biological Shield Dismantling was completed safely and without incident. Dose estimates were higher than those recorded by staff. This was attributed to being overly conservative and some of the contributing factors were; Self shielding by the dismantled concrete Time taken to dismantle and remove the active concrete was less than anticipated. No surface or airborne contamination was detected throughout the project There were no personal contamination events
17
18
Alec Kimber Australian Nuclear Science & Technology Organisation
Decommissioning and Dismantling of the Moata Reactor Alec Kimber Australian Nuclear Science & Technology Organisation A History of Moata Constructed at ANSTO in 1961 ARGONAUT type reactor Built as a 10
More informationANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007
ANSTO s POLICY for MOATA & HIFAR Prepared by John Rowling November 2007 Content Australian Nuclear Regulatory Systems Compare to International Recommendations Licencing Transition Period Major Issues Requirements
More informationExperiences on a Regulatory Clearance of the Radioactive Wastes at KAERI
Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI - 8323 D.S. Hong, Y. Y. Ji, J. S. Shon, S. B. Hong Korea Atomic Energy Research Institute 1045 Daedeokdaero, Yuseong, Daejeon, Korea
More informationPLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO
PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO Sungjoong (Shane) KIM Australian Nuclear Science and Technology Organisation New Illawarra Road, Lucas Heights, N.S.W., 2234, Australia Email: skx@ansto.gov.au
More informationRadiation Protection Challenges associated with the dismantling of Nuclear Power Plant
Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant Ludovic Vaillant ISOE International Symposium Rio de Janeiro, May 2015 Context (1/2) For various reasons - economical,
More informationDecommissioning Group Ketut Kamajaya
Decommissioning Group Ketut Kamajaya Contents of presentation Briefly history of Bandung TRIGA reactor Location of the facility Decommissioning options Characterization of System, Structure and Component
More informationRESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED
RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft
More informationC. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant
C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant Content Regulatory framework Strategy Status of the project Role
More informationPham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC
IAEA RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT Regional Workshop on Release of Sites and Building Structure, Karlsruhe,, GERMANY, 27 September 01 October 2010 THE IMPROVEMENTS MADE ON THE
More informationADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR
ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR K. KRISTOFOVA, M. HORNACEK, V. SLUGEN Institute of Nuclear and Physical Engineering, Faculty of Electrical
More informationRADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.
RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom Abstract. The UK nuclear power industry is predominantly based on gas-cooled,
More information2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America
2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization 16-19 September 2007, Chattanooga, TN, United States of America Safety of Decommissioning of Nuclear Facilities B. Batandjieva,
More informationBest practices for preparing vessel internals segmentation projects
Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse
More informationJoint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria
2473-9 Joint ICTP-IAEA School on Nuclear Energy Management 15 July - 3 August, 2013 Lecture Notes I. Mele IAEA, Vienna, Austria The IAEA Nuclear Energy Management School ICTP, Trieste, 15-2 August 2013
More informationTOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES
TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES Waste Technology Section WATEC 2004, 18-22 Oct 2004 Presentation Objectives Highlight the interactions between decommissioning and waste management
More informationDevelopment of Decommissioning Plan in Indonesia
Development of Decommissioning Plan in Indonesia Endang Kurnia and Berthie Isa R²D ²P: Review of a Decommissioning Plan Bucharest, Romania, 4-8 July 2011 IAEA International Atomic Energy Agency Legal and
More informationWM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS
RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS ABSTRACT M England, BNFL, Risley, Warrington, Cheshire, England As with all nuclear facilities, research reactors will, at some stage, reach
More informationTAKEN FROM A DOE TECHNOLOGY SUMMARY ON THE CONCRETE SHAVER DEMONSTRATED AT THE HANFORD SITE, RICHLAND, WA
The Marcrist Industries Limited Concrete Shaver is an electrically driven, selfpropelled concrete and coating removal system that can be used for radiological decontamination of large areas or hot spots
More informationDecommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective
Lesson Objectives International Atomic Energy Agency Define specific decommissioning terms of Nuclear Facilities The Process Understand the decommissioning process Review the various decommissioning strategies
More informationSTRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY
GUIDE YVL C.1 / 15 November 2013 STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 General design requirements 3 4 Radiation safety aspects in the layout design
More informationNews this quarter. Environment, Safety&Health Quarterly Performance Report. Reporting period: 1 October to 30 December 2015
Environment, Safety&Health Quarterly Performance Report Reporting period: 1 October to 30 December 2015 Welcome to AWE s fourth quarterly performance report for 2015. This document is designed to inform
More informationSAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING
SAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING S.V. Komarov, A.Z. Gaiazov, A.A. Rozhnovskaia, I.V. Kuzmin, O.E. Polovnikov Sosny Research and Development Company (Sosny
More informationRADIOLOGICAL PROTECTION
Title of document ONR GUIDE RADIOLOGICAL PROTECTION Document Type: Unique Document ID and Revision No: Nuclear Safety Technical Assessment Guide Date Issued: November 2017 Review Date: November 2020 Approved
More informationDecommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M
Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M Giorgi Nabakhtiani Grigol Kiknadze Nuclear and Radiation Safety Service Ministry of Environment Protection and Natural
More informationDecommissioning Worldwide and NEA Activities
Decommissioning Worldwide and NEA Activities Claudio Pescatore - Ivo Tripputi NEA Principal Administrator - NEA CPD Management Board Chair WM Symposia, Phoenix, 2-6 March 2014 Decommissioning: what does
More informationDecommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment
: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment Dr. M Knaack TÜV NORD GmbH, Hamburg / Germany Overwiew Decommissioning when and why? Law, regulations and guidelines Three main
More informationRESEARCH REACTOR DECOMMISSIONING PLAN
RESEARCH REACTOR DECOMMISSIONING PLAN Clédola Cássia O. de Tello Pablo Andrade Grossi Brazil Contents General Aspects Ongoing Activities Decommissioning Plan Conclusion 1 TRIGA IPR-R1 REACTOR Four research
More informationBerkeley Boilers Project. Studsvik Symposium April 2014
Berkeley Boilers Project Studsvik Symposium April 2014 Berkeley NPP Twin Magnox Reactors Operating 1962 1989 First UK commercial reactor to enter decommissioning Currently managed on behalf of the Nuclear
More informationNiagara Falls Storage Site Safety Measures During Remediation
Niagara Falls Storage Site Safety Measures During Remediation On-Site Worker Protection Community and Environmental Protection Transportation and Disposal Safety Fully enclosed Retrieval Facility Regular
More informationDecommissioning of Nuclear Facilities. Waste Management
Decommissioning of Nuclear Facilities Waste Management Lesson Objectives Describe the requirements and methods for managing waste from decommissioning Review IAEA and US waste classification systems Review
More informationSafety Assessment for Decommissioning of a Nuclear Laboratory
SAFETY ASSESSMENT FOR DECOMMISSIONING Annex I, Part C Safety Assessment for Decommissioning of a Nuclear Laboratory INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1. INTRODUCTION... 1 1.1. Background...
More informationTENORM A Premier for Industrial Hygienists
TENORM A Premier for Industrial Hygienists Presentation Topics Cliff Notes Rad Fundamentals NORM and TENORM Definitions Impacted Industries Issues Work Practices and Measurement Tips for IHs Radiological
More informationThe EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»
The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants» 40 th MPA-Seminar Stuttgart, 6 th & 7 th October2014 Peter Daiß, EnBW Kernkraft GmbH Content 1. Introduction and Company Profile
More informationDecommissioning Planning
Decommissioning Planning Ingemar Lund - Swedish Radiation Protection Authority, SSI, Sweden IAEA Regional Workshop: Legal and Regulatory Aspects of Decommissioning of Research Reactors Manila, Philippines,
More informationAustralia s Regulation of Low and Intermediate Level Radioactive Waste
Australia s Regulation of Low and Intermediate Level Radioactive Waste NEA Workshop on the Management of Non-Nuclear Radioactive Waste Legnaro, Italy, 2-4 May 2017 John Templeton Acting Manager, Facility
More information- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz
- 1 - Strategies for Radiological Characterisation in Decommissioning S. Thierfeldt, K. Haneke - Brenk Systemplanung GmbH, Aachen OECD/NEA Workshop on Radiological Characterisation for Decommissioning
More informationApplicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects
Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International
More informationPlanning for the Decommissioning of the ASTRA-Reactor
Planning for the Decommissioning of the ASTRA-Reactor Konrad Mück, Jörg Casta Austrian Research Center Seibersdorf Introduction The ASTRA Reactor, a 10 MW multipurpose MTR research reactor at the Austrian
More informationOperational Decommissioning Experience in France Radioactive Waste Management and Radiation Protection Issues
Operational Decommissioning Experience in France Radioactive Waste Management and Radiation Protection Issues L. Vaillant ISPRA, Italy, 11 th September 2014 Content Dismantling of nuclear facilities in
More informationGroupe INTRA : Activities and Organization in France
Groupe INTRA : Activities and Organization in France March, 2014 Groupe INTRA Pascal IZYDORCZYK Deputy Manager Pascal.izydorczyk@groupe-intra.com 1 1 9 8 8 Groupe I N T R A creation Groupe INTRA was created
More informationNews this quarter. Environment, Safety&Health Quarterly Performance Report. Reporting period: 1 April to 30 June 2015
Environment, Safety&Health Quarterly Performance Report Reporting period: 1 April to 30 June 2015 Welcome to AWE s second quarterly performance report for 2015. This document is designed to inform you
More informationNew Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN
New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN Abstract The Swedish Radiation Safety Authority (SSM) has developed
More informationDismantling of nuclear facilities in France: what is at stake?
Decommissioning of nuclear facilities Feedback from France L. Vaillant ISPRA, Italy, 16 th September 2015 Content Dismantling of nuclear facilities in France: what is at stake? Radioactive Waste Management
More informationUranium mining legal and regulatory framework
South Australia s Environment Protection Authority Uranium mining legal and regulatory framework An Australian perspective Keith Baldry Director Mining Radiation and Regulatory Support IAEA Seminar on
More informationANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally
Presentation 8 Session 3 ANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally Jayne Senior General Manager, ANSTO Nuclear Medicine Pty Ltd (ANM) Biography Jayne Senior is General Manager for
More informationPROGRESS IN THE PREPARATION OF A DECOMMISSIONING PLAN
PROGRESS IN THE PREPARATION OF A DECOMMISSIONING PLAN WORKSHOP ON RESEARCH REACTOR DECOMMISSIONING ACTVITIES: COST ESTIMATES 30 MARCH 03 APRIL 2009, MANILA, PHILIPPINES KHAIRONIE MOHAMED TAKIP MALAYSIA
More informationWM 00 conference, February 27 March 2, 2000, Tucson, AZ
WM 00 conference, February 27 March 2, 2000, Tucson, AZ REACTOR PRESSURE VESSEL REMOVAL AT A BOILING WATER REACTOR WITH SPENT FUEL IN THE ADJACENT FUEL POOL By Albert A. Freitag, WMG, Inc Greg Harttraft,
More informationRadiation
Radiation 04 Background radiation occurs all around us and is easily measured and controlled. In fact, the radiation risks to those working and living near a mine are very low. June 2016 WWW.ARULTD.COM
More informationDismantling Techniques applied at MZFR
Wiederaufarbeitungsanlage Karlsruhe Rückbau- und Entsorgungs- GmbH The Decommissioning Project Multi-Purpose Research Reactor ( MZFR ) Dismantling Techniques applied at MZFR E. Prechtl Projekt MZFR WAK
More informationRadiation Protection and ALARA Program Highlights at Ontario Power Generation
2017 International ISOE ALARA Symposium 10-Jan-2017 Radiation Protection and ALARA Program Highlights at Ontario Power Generation Josip Zic Radiation Protection Manager Pickering Nuclear Generating Station
More informationRadioactive Waste Management at the NCSR Demokritos - Greece
Radioactive Waste Management at the NCSR Demokritos - Greece Anastasia Savidou Radioactive Materials Management Laboratory Institute of Nuclear & Radiological Sciences & Technology, Energy & Safety, National
More informationAUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY
AUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY C. Perkins Department of Education, Science and Training GPO Box 9880, Canberra, ACT 2601, Australia ABSTRACT The Australian Government is committed
More informationMark Ramsay BEng MSc MSRP, CRadP
Mark Ramsay BEng MSc MSRP, CRadP Radiation Protection Adviser Chartered Radiation Protection Professional Qualified Expert in Radiation Protection Personal Information Profile Nationality: British Age:
More informationRadioactive Waste Management and Environmental Surveillance at KANUPP. Khawaja Ghulam Qasim Sr. Manager (KANUPP)
Radioactive Waste Management and Environmental Surveillance at KANUPP Khawaja Ghulam Qasim Sr. Manager (KANUPP) PAEC Nuclear Power Program K-1 C-1 C-2 C-3 C-4 K-2/K-3 1972 2000 2011 Sep.2016 2017 2021
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1
More informationNuclear decommissioning challenges in the UK a rough guide for roboticists
Nuclear decommissioning challenges in the UK a rough guide for roboticists Rustam Stolkin University of Birmingham, UK With some slides provided by Jeffrey A. Kuo National Nuclear Lab, UK Caveat: I am
More informationDECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE
DECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE Mitsugu Tanaka, Mimori Takeo, Takakuni Hirabayashi and Satoshi Yanagihara Japan Atomic Energy Research Institute
More informationRemote-Controlled Dismantling of the Thermal Isolation and Preparations for the Primary Shield Removal
Remote-Controlled Dismantling of the Thermal Isolation and Preparations for the Primary Shield Removal A. Graf, J. Fleisch, S. Neff, WAK GmbH, Eggenstein-Leopoldshafen, Germany S. Klute, E. Koselowski,
More informationSafety Assessment for Decommissioning of a Nuclear Power Plant
SAFETY ASSESSMENT FOR DECOMMISSIONING Annex I, Part A Safety Assessment for Decommissioning of a Nuclear Power Plant INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1. INTRODUCTION... 1 1.1. Background...
More informationROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General
ROMANIA National Commission for Nuclear Activities Control (CNCAN) Progress in Report on in Decommissioning Activities Dr. Lucian BIRO Director General IAEA R²D²P Workshop on Cost Estimates Manila, 30
More informationRadiation Environment and Shielding Design Optimization at MEIC
Radiation Environment and Shielding Design Optimization at MEIC Pavel Degtiarenko Radiation Physics Group Radiation Control Department, JLab October, 2015 Contents Brief review of MEIC Radiation Protection
More informationDesign of Transport Container
Design of Transport Container Reduction of Occupational Exposure executing Transports of Radioactive Wastes Content 1. The Task 2. 3. Today Status 2 The Task At present there are about 4 000 drums (200
More informationWM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576
Factors Impacting Decommissioning Costs 13576 Karen Kim*, Richard McGrath* *Electric Power Research Institute, 342 Hillview Ave., Palo Alto, California. USA. kkim@epri.com, rmcgrath@epri.com ABSTRACT The
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA
Modular Design of Processing and Storage Facilities for Small Volumes of Low and Intermediate Level Radioactive Waste including Disused Sealed Sources - 12372 David R. Keene*, Susanta Kumar Samanta** and
More informationContamination at Plutonium Fuel Research Facility of Oarai Research and Development Center. July 21, 2017 Japan Atomic Energy Agency
Contamination at Plutonium Fuel Research Facility of Oarai Research and Development Center July 21, 2017 Japan Atomic Energy Agency Table of contents Outline and events in chronological order 1 Outline
More informationTesting of Carbon Filters in Australian
Testing of Carbon Filters in Australian Nuclear Installations 31st International Nuclear Air Cleaning Conference, Charlotte NC 19-21July 9 Ju y 2010 0 0 Luis Rudenas Engineering & Technical Services Australian
More informationRadiation becomes dangerous when it becomes concentrated in some way by human activity.
NORM Naturally occurring radioactive material (NORM): Is radiation that exists naturally in the environment Is also known as background radiation Has many sources, such as soil and rocks Can be found in
More informationOptimization of Reactor Pressure Vessel Internals Segmentation in Korea
DECOMMISSIONING AND WASTE MANAGEMENT 654 Optimization of Reactor Pressure Vessel Internals Segmentation in Korea Byung-Sik Lee 1 Introduction The decommissioning of Kori unit 1, which is the first commercial
More informationEnvironmental Regulator's RWA Syllabus mapped to PHE's RPTS courses. RPTS coverage EA. No
Environmental Regulator's mapped to PHE's RPTS courses EA. No RPTS Sylalbus/Course RPA Reference requirement 1 Basic atomic and nuclear physics Atomic structure and composition of the nucleus Yes F DU
More informationDose and Risk Calculations for Decontamination of a Hot Cell
Dose and Risk Calculations for Decontamination of a Hot Cell Amr Abdelhady and T. Mongy Reactors dept., Nuclear Research Center, Atomic Energy Authority, Cairo, Egypt Received: 1 /2/ 2014 Accepted: 6 /3/
More informationThe Efficiency for Gas Capture Systems for PET Cyclotrons and Hot Cells.
The Efficiency for Gas Capture Systems for PET Cyclotrons and Hot Cells. Modern cyclotrons can produce large amounts (>500 GBq) of PET isotopes (usually F-18) per production run for radiosynthesis of various
More informationRadiation Backgrounds for the APEX experiment
Radiation Backgrounds for the APEX experiment Pavel Degtiarenko Radiation Physics Group at RadCon April, 2014 Contents Radiation Dose Accumulation at JLAB Boundary Radiation Budgeting Process APEX Contribution
More informationRadioactive Waste Management Agency. and. Nuclear Safety Authority. in Belgium
Radioactive Waste Management Agency and Nuclear Safety Authority in Belgium Luc Baekelandt, FANC, Belgium LB/IAEA/2010-06-08/00 Contents 1. Institutional framework 2.The actors FANC ONDRAF/NIRAS 3. Co-operation
More informationWaste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report
Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report Rich McGrath (Presenter) - EPRI Consulting Employee Rick Reid, PhD - Senior Technical Leader Symposium
More informationRadiation Protection of the Public and Protection of the Environment
DS432 IAEA SAFETY STANDARDS Date: March 2015 for protecting people and the environment Status: Step 8 120 day Member States consultation Deadline for comments: 20 July 2015 Radiation Protection of the
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: September 2014 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 11 MS comments incorporated Review Committee Member comments due 31 Oct Predisposal Management
More informationSafety principles of radioactive waste management activities and supportive IAEA documents
Safety principles of radioactive waste management activities and supportive IAEA documents Eric K. Howell, Ph.D. Facilia Projects GmbH Joint ICTP/IAEA Workshop on Radioactive waste management solutions
More informationPeer Review of the RPII s Environmental Monitoring Programme Foundation Document. F. Exposure from Natural Sources in Ireland
Peer Review of the RPII s Environmental Monitoring Programme 2009 Foundation Document F. Exposure from Natural Sources in Ireland 1. Introduction The European Commission is currently in the process of
More informationRETRIEVAL OF INTERMEDIATE LEVEL WASTE AT TRAWSFYNYDD NUCLEAR POWER STATION. I. J. Shaw, AEA Technology
RETRIEVAL OF INTERMEDIATE LEVEL WASTE AT TRAWSFYNYDD NUCLEAR POWER STATION ABSTRACT I. J. Shaw, AEA Technology The generation of electricity at Trawsfynydd Nuclear power station has resulted in the production
More informationSetting up the Medical Cyclotron Facility at Cochin, Kerala. M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin
Setting up the Medical Cyclotron Facility at Cochin, Kerala M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin 682 508 Pillai.m.r.a@gmail.com AERB Approval Stagewise Site Assessment and Approval
More informationBest Practice Form. Open Air Demolition of Asbestos Gunite by Using Track Mounted Wet Cutting Saw DOE Site:
Best Practice Form Best Practice Title: Open Air Demolition of Asbestos Gunite by Using Track Mounted Wet Cutting Saw DOE Site: Lawrence Livermore National Laboratory (LLNL) Facility Name: B328 Demolition
More informationNuclear Metals, Inc. (NMI) purchased undeveloped property in 1957 and the original laboratory facility was built the following year.
Joint Efforts By: Nuclear Metals, Inc. (NMI) purchased undeveloped property in 1957 and the original laboratory facility was built the following year. Owners/Operators 1958 1972: two industrial entities
More informationDECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS
DECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS - 9023 J. Fleisch, M. Weishaupt, W. Pfeifer Wiederaufarbeitungsanlage Karlsruhe,
More informationSummary of Presentation
Summary of Presentation Beginning Tuesday, Oct. 24, Pickering Nuclear hosted a series of Community Information Sessions. Ontario Power Generation (OPG) staff were on hand to share information on all aspects
More informationPackaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517
Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517 Aurélie Brasch-Serres*, Mathias Chazot** * EDF-DP2D, 154 avenue Thiers, CS 60018, 69458 LYON CEDEX 06, FRANCE
More informationThe Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU)
The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU) Chernobyl 25 years on: Time for a giant leap forward BY DICK KOVAN After 25 years, the construction
More informationACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP.
LEARNING OBJECTIVES: 2.10.01 State the purpose of and information found on a Radiological Work Permit (RWP) including the different classifications at your site. 2.10.02 State responsibilities in using
More informationENVIRONET Network on Environmental Management and Remediation. Terms of Reference
ENVIRONET Network on Environmental Management and Remediation Terms of Reference 1. Background Radiologically contaminated sites continue to exist all over the world. They were originated by past activities
More informationWM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA
An Integrated Equipment for Massive Segmentation and Packaging of Control Rod Guide Tubes 15161 Joseph Boucau*, Patrick Gobert** Sébastien Bonne *** * Westinghouse Electric Company, 43 rue de l Industrie,
More informationS. Reyes. Lawrence Livermore National Laboratory. ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison
S. Reyes Lawrence Livermore National Laboratory ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison Work performed under the auspices of the U. S. Department of Energy by University of California Lawrence
More informationInternational Perspective on non-heu Mo-99 Production
International Perspective on non-heu Mo-99 Production International Symposium on HEU Minimisation Vienna 23-25 January 2012 Dr Adrian Paterson Michael Druce Australian Nuclear Science and Technology Organisation
More informationNuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201
Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 ABSTRACT Irin P. Hall, Kimberly Grubb and Ashley Williams Newport News Shipbuilding Since 2007, Newport
More informationPRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.
TECHNICAL MEETING ON THE RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT: CHARACTERIZATION SURVEY PHILIPPINES, 3 7 DECEMBER 2007 PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING
More informationSafety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities
Safety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities Kenkichi ISHIGURE Japan Radioisotope Association 1 Decommissioning of nuclear power facilities
More informationSTURGIS Barge Decommissioning Project
STURGIS Barge Decommissioning Project U.S. Army Corps of Engineers Nov. 17, 2014 US Army Corps of Engineers Today s Presentation History of the STURGIS Environmental Assessment Decommissioning Waste Segregation
More informationWM 00 Conference, February 27 - March 2, 2000, Tucson, AZ
STATUS OF THE AVR DECOMMISSIONING PROJECT WITH SPECIAL RE- GARD TO THE INSPECTION OF THE CORE CAVITY FOR RESIDUAL FUEL ABSTRACT E. Wahlen, J. Wahl, P. Pohl Arbeitsgemeinschaft Versuchsreaktor AVR GmbH
More informationPreliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development
Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of
More informationOHS Ionising Radiation Procedure
OHS 601 - Ionising Radiation Procedure Policy Hierarchy link OHS Policy Responsible Officer Human Resources, Director Contact Officer Radiation Safety Officer or ext. 52912 Superseded Documents Ionising
More informationSpanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero
Spanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero Senior Researcher Head of CIEMAT Quality Management CYTED- Energy Area Technical Secretary of Spanish
More information