Metro Board Action: Motion 22.1

Size: px
Start display at page:

Download "Metro Board Action: Motion 22.1"

Transcription

1 Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016

2 Background Motion 22.1 October 2015 Metro Board approves Motion 22.1 Staff directed to report back in 60 days November December 2015 Staff develops statement of work and cost for additional scope elements January 2016 Metro Board approves allocation of resources for supplemental statement of work to support Motion

3 Background Motion 22.1 Elements are grouped into four general categories: I. Defines those elements to be included in the technical work II. III. IV. scope in the I-710 EIR/EIS process [Technical Work Scope Items] Identifies elements that Metro and it s partner agencies should consider for mitigation during construction, parallel to the I-710 EIR/EIS process Specifies actions Metro and it s partner agencies should take, parallel to the I-710 EIR/EIS process Defines a set of bicycle alignments that the technical team is to undertake as a study separate from the I-710 EIR/EIS process 3

4 I. Technical Work Scope Items Overview Adds the following in the evaluation of Alternatives 5C and 7 within the RDEIR/SDEIS Right-of-way avoidance designs / evaluation (Alternative 7) Zero Emissions Truck Only Option for Freight Corridor (Alternative 7) Use of best available green construction equipment Maximize drought-resistant greenscape coverage, stormwater best management practices [BMPs] and water quality measures High frequency Express Bus Transit along I-710 Additional transit service analysis Upgrades to the existing LA River Bike Path Construction of at least five new pedestrian/bike bridges /underpasses [reduce remaining gaps] 4

5 I. Technical Work Scope Items Overview Included in the evaluation of Alternatives 5C and 7 within the RDEIR/SDEIS [Continued] Replacement / enhancement of 28 existing bridges / underpasses to provide access for pedestrians/bikes across the I-710 / LA River Complete Streets treatments embedded within freeway design (overcrossings, ramp termini, intersections) Complete Streets treatments for local projects [congested intersections] pursued as part of the I-710 Corridor Project Adding transit service on the bus and rail lines serving the I-710 Project Area Traffic Control Measures [ITS/TSM/TDM] Minimize impacts to LA River 5

6 I. Technical Work Scope Items Status / Project Coordination Motion 22.1 Technical Work Scope Items have been incorporated into existing scope and schedule Project team has initiated analysis of these items Analysis will be incorporated into the RDEIR/SDEIS evaluation conducted for the alternatives [costs, benefits, impacts] Progress updates will be provided to TAC, CAC, LACs and PC in conjunction with overall findings for the alternatives Summer 2016 [Project Description - Additional Definitional Detail Needed to Support the Environmental Studies] Winter 2016 [Technical Results] 6

7 Integrating Technical Work Scope Items I 710 Corridor Recirculated Draft EIR Supplemental Draft EIS Motion 22.1 Technical Work Scope Items and Analysis Completed Summer 2015 Define Alts to be Analyzed in RDEIR/SDEIS Complete by 2016 Update Technical Studies (We Are Here) Recirculate in 2017* Circulate RDEIR/SDEIS for Public Review (Incl. proposed mitigations) Scoping (Sept 2008) Alternative Screening 1 st Admin. Draft EIR/EIS Alts Revisions and Updated Tech Studies Draft EIR/EIS (June 2012) Prepare Response to Comments & ID Pref. Alternative Final EIR/EIS 7

8 II. Potential Mitigation II. Mitigation To Be Considered During Construction Monitor Congestion / Transit Service Adjustments / Incentive Fare Program Define Criteria for Potential Mitigation: Summer 2016 Develop Detailed Monitoring Program: Design / Pre-Construction Phase Monitor Congestion / Determine Need for Service Adjustments & Incentives / Board Approval of Service Adjustments/Incentive Fee Structure: Construction Phase Incentive Programs for Transit Services Define Criteria for Potential Mitigation: Fall 2016 Develop Description of Incentive Program: Summer 2017 Community Outreach Plan Define Criteria for Potential Mitigation: Fall 2016 Develop Detailed Community Outreach Plan: Design / Pre-Construction Phase Pedestrian/Bike Safety Plan Define Criteria for Potential Mitigation: Fall 2016 Develop Detailed Bike/Pedestrian Safety Plans: Design / Pre-Construction Phase Residential / School Air and Noise Mitigation Program Description of I-710 Community Health & Benefit Program: Summer 2016 Determine need for additional mitigation: Winter

9 III. Additional Studies III. To be Pursued in Parallel to the EIR/EIS Analysis of a Zero Emission Truck procurement and operations program (Alternative 7 only) in any P3 analysis to be done for the Project Defined technical scope for P3 analysis: Winter 2015 Conduct analysis: Spring 2017 Incorporate results into Project Implementation Plan: Summer 2017 Additional bike transportation planning in the study area STP Plan / Metro Service Coordination: Spring 2016, Summer 2016 Identify Proposed Changes (if required): Fall 2016 Initiate Revisions (if required): Summer 2017 Local and Targeted Hiring Policy and PLA for construction jobs and a First Source Hiring Policy for permanent jobs created by the project Initiate discussions stakeholder groups and FHWA: Winter 2016 Develop draft framework for local and targeted hiring policy and PLA: Winter 2017 Approval and Implementation: Pre-Construction / Construction Phases 9

10 IV. Bike Projects IV. To be Studied Outside the EIR/EIS Class 1 Bike Path, LAFCD ROW, Western Levee [PCH to Imperial] Class 1 Bike Path, SCE ROW parallel to Greenleaf Blvd [LA Blue Line to Sportsman Dr.] Class 1 Bike Path, SCE and LADWP ROW [Willow/TI Freeway to Rio Hondo Bike Trail at Garfield] Key Milestones (Project Definition Phase): Purpose & Need / Constraints Analysis: Spring 2016 Initial Concepts / Screening Analysis: Summer 2016 Best Set of Alignments for Conceptual Engineering: Summer 2016 Project Definition Studies / Stakeholder Workshops: Fall / Winter 2016 Select Preferred Alignment(s) for Environmental Study: Early

11 Long Term Look Ahead I-710 Corridor Project Environmental (EIR/EIS) Phase Design / Pre-Construction Phase Construction Phase 710 Project Opens Increasing Level of Detail Other Motion 22.1 Elements II. Identify as Potential Mitigation III. Additional Studies, Proposals, Policy Criteria II. Develop Detailed Monitoring, Outreach, Safety Plans Specific to I-710 Construction Plans III. Refinements, Approvals II. Implement Mitigation III. Implement Local/Targeted Hire Policy and PLA IV. Independent Bikeway Projects Studies & Environmental Approval IV. Design Phase IV. Construction Phase IV. Bikeway Projects Open 11

12 Next Steps Continue Analysis Update Committees and Community Summer 2016 Winter 2016 Complete RDEIR/SDEIS for Public Review 12

Metro. Board Report I-710 SOUTH CORRIDOR PROJECT EIR/EIS, SCOPE, BUDGET, AND SCHEDULE

Metro. Board Report I-710 SOUTH CORRIDOR PROJECT EIR/EIS, SCOPE, BUDGET, AND SCHEDULE Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #:2015-1656, File Type:Contract Agenda Number:21. PLANNING & PROGRAMMING

More information

I-710 Project Committee Meeting

I-710 Project Committee Meeting Los Angeles County Metropolitan Transportation Authority I-710 Project Committee Meeting January 29, 2009 Meeting Expectations Review I-710 planning context Concur on a port cargo forecast scenario to

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

Gateway Corridor Transitway

Gateway Corridor Transitway Locally Preferred Alternative Summary Gateway Corridor Transitway 1 Metropolitan Council, Nov. 12, 2014 Gateway Corridor Transitway Proposed highcapacity transit improvement connecting east metro suburbs

More information

Placerville, a Unique Historical Past Forging into a Golden Future

Placerville, a Unique Historical Past Forging into a Golden Future Placerville, a Unique Historical Past Forging into a Golden Future City Manager s Report June 24, 2014 City Council Meeting Prepared by: Nathan Stong, City Engineer Item #: Subject: Adopt a Resolution:

More information

LARKSPUR SMART STATION AREA PLAN. Public Workshop December 3, 2013

LARKSPUR SMART STATION AREA PLAN. Public Workshop December 3, 2013 LARKSPUR SMART STATION AREA PLAN Public Workshop December 3, 2013 0 PURPOSE OF Provide information about the regional planning context for the Larkspur Station Area, including Plan Bay Area, SMART, and

More information

Integrated Transportation Plan. TAC Meeting September 16, 2014

Integrated Transportation Plan. TAC Meeting September 16, 2014 Integrated Transportation Plan TAC Meeting September 16, 2014 Project Schedule Today TAC Meeting October 10 TAC Meeting (teleconference) October 29 Public Workshop December 9 JIM Presentation Plan Contents

More information

State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013

State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013 State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013 Frank Quon, P.E. Executive Officer, Metro Highway Program Michelle Smith, P.E. Project Manager, Metro Highway Program

More information

Moving Forward 2040 Long Range Transportation Plan Bicycle Mobility Master Plan Transit Master Plan

Moving Forward 2040 Long Range Transportation Plan Bicycle Mobility Master Plan Transit Master Plan Moving Forward 2040 Long Range Transportation Plan Bicycle Mobility Master Plan Transit Master Plan Paul DiGiuseppe Assistant Chief, Division of Planning Department of Administration (DOA) Needed to keep

More information

WELCOME COMMUNITY ADVISORY GROUP MEETING #2

WELCOME COMMUNITY ADVISORY GROUP MEETING #2 WELCOME COMMUNITY ADVISORY GROUP MEETING #2 Joliet Junior College OUTLINE / AGENDA Recap of CAG #1 Presentation Recap of CAG #1 Workshop Context Audit / Survey Results Draft Problem Statement Draft Purpose

More information

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Interagency Meeting June 19, 2017

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Interagency Meeting June 19, 2017 West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Interagency Meeting June 19, 2017 Agenda > Welcome and Introductions > Purpose of Interagency Scoping > Timeline and Process > Agency Coordination

More information

FACT SHEETS LOS ANGELES COUNTY

FACT SHEETS LOS ANGELES COUNTY FACT SHEETS LOS ANGELES COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares a

More information

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

Chapter 5 Transportation Draft

Chapter 5 Transportation Draft Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the

More information

Frequently Asked Questions Connecting Palo Alto

Frequently Asked Questions Connecting Palo Alto Frequently Asked Questions Connecting Palo Alto www.cityofpaloalto.org/connectingpaloalto General Project Questions Q1: What is Connecting Palo Alto? A1: Connecting Palo Alto (formerly the Palo Alto Rail

More information

Sapphos. February 28, South Alameda Street Project

Sapphos. February 28, South Alameda Street Project Sapphos environmental inc. William Lamborn Major Projects Department of City Planning 200 N. Spring Street, Rm 750 Phone: 213.978.1470 Dear Mr. Lamborn, In preparation for the City Council Hearing on the

More information

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX Southern California Association of Governments ADOPTED APRIL 2012 INTELLIGENT TRANSPORTATION SYSTEMS Introduction 1 Existing System Description 1 Existing System

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

Growth in the Fresno Metro Area

Growth in the Fresno Metro Area 1 Growth in the Fresno Metro Area 2 A Unique Opportunity Meeting City and Regional Challenges SEGA 9,000 Acres 3 A Unique Planning Process Measuring Up to the Challenge Modeling the Impacts of Different

More information

Fact Sheet What is ground-level ozone pollution? How is ground-level ozone pollution harmful?

Fact Sheet What is ground-level ozone pollution? How is ground-level ozone pollution harmful? Fact Sheet What is ground-level ozone pollution? Ground-level ozone is a harmful air pollutant that is formed when emissions from gas-powered vehicles and lawn equipment, industrial processes, and even

More information

Project Initiation Form

Project Initiation Form Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

Atlanta BeltLine Corridor Environmental Study. Technical Advisory Committee/Agency Coordination. Kick-Off Meeting

Atlanta BeltLine Corridor Environmental Study. Technical Advisory Committee/Agency Coordination. Kick-Off Meeting Atlanta BeltLine Corridor Environmental Study Technical Advisory Committee/Agency Coordination Kick-Off Meeting July 17, 2008 Overview Project Overview Objectives Milestones Why GEPA and NEPA? Environmental

More information

I-710 Technical Advisory Committee Wednesday, June 18, :30 3:30 PM

I-710 Technical Advisory Committee Wednesday, June 18, :30 3:30 PM I-710 Technical Advisory Committee Wednesday, June 18, 2014 1:30 3:30 PM Gateway Cities Council of Governments 16401 Paramount Boulevard, 2 nd Floor Conference Room Paramount, California AGENDA STAFF REPORTS

More information

Welcome High Desert Corridor

Welcome High Desert Corridor Los Angeles County Metropolitan Transportation Authority Welcome High Desert Corridor Open House Meetings 6 8pm Monday, July 15, Lake Los Angeles Elementary School Tuesday, July 16, Stater Bros Stadium

More information

Richard Clarke Executive Director Program Management. Capital Program Management

Richard Clarke Executive Director Program Management. Capital Program Management Richard Clarke Executive Director Program Management Capital Program Management Department Overview > Transit, Highway Programs, and Regional Rail o Transit Deliver construction projects on-time and within

More information

Regional Transportation Studies Regional Council

Regional Transportation Studies Regional Council Pima Association of Governments 1 E. Broadway, Tucson, Arizona Santa Rita Conference Room Regional Transportation Studies Regional Council September 28, 2017 I-11 Tier 1 Environmental Impact Statement

More information

Update and Status Report for the Comprehensive Transportation Plan. December 2, 2011

Update and Status Report for the Comprehensive Transportation Plan. December 2, 2011 Update and Status Report for the Comprehensive Transportation Plan December 2, 2011 Overview Comprehensive Transportation Plan (CTP) and Outreach CTP Framework and Program of Projects Alternative Transportation

More information

I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough

I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough December, 2014 Introduction / Welcome Paul Matthews, Executive Director, 495 MetroWest Partnership Renata Welch, MassDOT

More information

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012 2030 Transportation Policy Plan SUMMARY PRESENTATION Land Use Advisory Committee November 15, 2012 Today s Topics Transportation Policy Plan (TPP) Requirements and Background Current TPP Policies, Issues

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

Pottstown Pike Congestion Mitigation Feasibility Study

Pottstown Pike Congestion Mitigation Feasibility Study Pottstown Pike Congestion Mitigation Feasibility Study Study Advisory Committee Meeting #3 November 15, 2017 Transportation Solutions Building Better Communities Agenda 1. Background Information 2. Review

More information

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS). This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit

More information

1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\

1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\ 1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\ Executive Summary 3UHSDUHGýIRUã 3UHSDUHGýE\ã.DQVDVý'HSDUWPHQWýRI 7UDQVSRUWDWLRQ,QýDVVRFLDWLRQýZLWKã (DUWKý7HFKý,QFï EXECUTIVE SUMMARY Introduction This Northwest

More information

Draft Alternatives and Screening Criteria

Draft Alternatives and Screening Criteria Draft Alternatives and Screening Criteria 1 *Reasonable Alternatives 1. Initial Screening Use a series of yes/no questions to determine what alternatives are reasonable. Viable Alternatives 2. Quantitative

More information

Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs)

Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs) Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs) What is Going Forward The Plan to Maintain & Improve Mobility (Plan) and why does the region need a Long Range Transportation

More information

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495 Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495 January 13, 2015 1 Project Status Update Transit P3 Procurement I-66 Corridor Briefing Overview Major Project

More information

CAPITAL- ALAMO CONNECTION STUDY

CAPITAL- ALAMO CONNECTION STUDY CAPITAL- ALAMO CONNECTION STUDY TECHNICAL ADVISORY COMMITTEE BRIEFING November 27, 2017 What is the Capital-Alamo Connection Study? A JOINT EFFORT BY: OBJECTIVE: To develop a regional strategy to enhance

More information

CAPITAL- ALAMO CONNECTION STUDY

CAPITAL- ALAMO CONNECTION STUDY CAPITAL- ALAMO CONNECTION STUDY TECHNICAL ADVISORY COMMITTEE BRIEFING December 1, 2017 What is the Capital-Alamo Connection Study? A JOINT EFFORT BY: OBJECTIVE: To develop a regional strategy to enhance

More information

South Bay Metro Green Line Extension

South Bay Metro Green Line Extension Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public

More information

ATTACHMENT 3. Background:

ATTACHMENT 3. Background: Colorado Tolling Enterprise (CTE) or High Performance Transportation Enterprise Additional Information Requirements for Amendment Submittals for the DRCOG Fiscally Constrained RTP Adopted by DRCOG Board

More information

Sunrise Project South I-205 Corridor Improvement Project

Sunrise Project South I-205 Corridor Improvement Project Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205

More information

A long-term, comprehensive solution

A long-term, comprehensive solution A long-term, comprehensive solution Nancy Boyd CRC Project Director for Washington Portland State University Transportation Seminar April 15 2011 Frank Green April 15, 2011 CRC Structural Engineering Manager

More information

TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID:

TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID: FINAL REPORT TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID: 165.10.09 Prepared for Los Angeles County Metropolitan Transportation Authority December

More information

2018 Comprehensive Guide Plan Steering Committee. Wednesday, October 11, Minnehaha Room, Minnetonka City Hall. 6:00 8:00 p.m.

2018 Comprehensive Guide Plan Steering Committee. Wednesday, October 11, Minnehaha Room, Minnetonka City Hall. 6:00 8:00 p.m. 2018 Comprehensive Guide Plan Steering Committee Wednesday, October 11, 2017 Minnehaha Room, Minnetonka City Hall 6:00 8:00 p.m. Agenda: 6:00 6:15 Dinner 6:15 6:45 Transportation planning overview 6:45

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017 Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives December 14, 2017 Today s Agenda Project Overview Project Schedule Purpose and Need Concept Screening Process Level

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager

More information

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017 West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Meeting June 2017 Agenda > Welcome and Introductions > Purpose of Scoping > Timeline and Process > Environmental Approach and Methodology >

More information

Appendix G Analysis of Project Impacts Compared to Existing Conditions

Appendix G Analysis of Project Impacts Compared to Existing Conditions Appendix G Analysis of Project Impacts Compared to Existing Conditions This page intentionally left blank. Analysis of Project Impacts Compared to Existing Conditions Introduction The analysis scenarios

More information

Re: Mobility Plan 2035 FEIR Greenhouse Gas Emissions Analysis

Re: Mobility Plan 2035 FEIR Greenhouse Gas Emissions Analysis Sirius Environmental Claire Bowin, Senior City Planner City of Los Angeles, Department of City Planning 200 North Spring Street, Room 272 Los Angeles, California 90012 Dear Claire: Re: Mobility Plan 2035

More information

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015 ACTIVE TRANSPORTATION ADVISORY COMMITTEE Memphis MPO March 30, 2015 Agenda Welcome & Introductions Announcements and Briefings Livability 2040: Regional Transportation Plan Congestion Management Process

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Village of Forest Park Council Meeting Presented by Carole Morey, CTA Chief Planning Officer October 13, 2015 Slide 2: Purpose and Study

More information

Chapter 5 - Transportation

Chapter 5 - Transportation Chapter 5 - Transportation Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the residents

More information

Regional Goods Movement Planning in the Bay Area

Regional Goods Movement Planning in the Bay Area M E T R O P O L I T A N T R A N S P O R T A T I O N C O M M I S S I O N Regional Goods Movement Planning in the Bay Area Matt Maloney, Principal September 17, 2015 Metropolitan Transportation Commission

More information

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County Department of Transportation 1 Agenda Overview & Assumptions

More information

MEETING SUMMARY FOR APRIL 13, 2017

MEETING SUMMARY FOR APRIL 13, 2017 SARASOTA/MANATEE METROPOLITAN PLANNING ORGANIZATION Performance Measures/Project Prioritization Process Ad Hoc Committee 7632 15 th Street East Sarasota, Florida 34243 3:00-5:00 PM MEETING SUMMARY FOR

More information

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012 Midtown Corridor Alternatives Analysis Technical Advisory Committee Meeting November 15, 2012 Today s Agenda Introductions Roles and Responsibilities Alternatives Analysis Process Overview Outreach Overview

More information

Chapter 14 Work Program

Chapter 14 Work Program Chapter 14 Work Program The Metropolitan Council will carry out or participate in many studies and plans over the next three years. This is not an exhaustive list of all work to be completed by the Metropolitan

More information

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018 Livability 2050 Regional Transportation Plan Update Transportation Policy Board (TPB) August 23, 2018 1 Oct. 2017 Plan Kick-Off Sept. 2019 Plan Adoption Timeline Livability 2050 Regional Transportation

More information

I-70 East PACT DRAFT EVALUATION DATA

I-70 East PACT DRAFT EVALUATION DATA I-70 East PACT DRAFT EVALUATION DATA Future Current Alignment NEIGHORHOOD QUALITY: Maintain quality of life and protect community values. Improve or maintain neighborhood connectivity Assess neighborhood

More information

Southeastern Minnesota Freight Rail Capacity Study

Southeastern Minnesota Freight Rail Capacity Study P U R P O S E A N D N E E D S T A T E M E N T Southeastern Minnesota Freight Rail Capacity Study Feasibility and Alternatives Analysis Study Prepared for: Prepared by: July 2012 Kimley-Horn and Associates,

More information

EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050

EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050 EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050 Introduction Goals Policies, and Performance Measures Growth Forecast and Planned Land Use Development Key Recommendations i Executive Summary April

More information

CMAA - BREAKFAST OF CHAMPIONS May 2, 2012

CMAA - BREAKFAST OF CHAMPIONS May 2, 2012 CMAA - BREAKFAST OF CHAMPIONS May 2, 2012 SIXTH STREET VIADUCT REPLACEMENT Gary Lee Moore, P.E. City Engineer Deborah Weintraub, AIA, LEED AP Chief Deputy City Engineer Alfred L. Mata, P.E. Project Manager

More information

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives. 4 Goals & Objectives INTRODUCTION The 2015-2040 MTP preserves and promotes the quality of life and economic prosperity of the MAB by providing a transportation system consistent with the regional goals.

More information

CONTINUING THE DISCUSSION ON-LINE

CONTINUING THE DISCUSSION ON-LINE INTRODUCTIONS 2 CONTINUING THE DISCUSSION ON-LINE Facebook: facebook.com/sr710conversations Twitter: E-mail: Web: twitter.com/sr710convos sr710conversations@metro.net www.metro.net/sr710conversations 3

More information

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures 7.2 Natural Environment/Environmental Planning Executive Summary/Key Points The Environmental Consultation and Mitigation Plan establishes: o A process for consultation with environmental resource agencies

More information

METROPOLITAN BAKERSFIELD GENERAL PLAN UPDATE GREATER BAKERSFIELD CHAMBER OF COMMERCE

METROPOLITAN BAKERSFIELD GENERAL PLAN UPDATE GREATER BAKERSFIELD CHAMBER OF COMMERCE METROPOLITAN BAKERSFIELD GENERAL PLAN UPDATE GREATER BAKERSFIELD CHAMBER OF COMMERCE JUNE 12, 2009 PURPOSE OF WORKSHOP MAJOR INFLUENCES PUBLIC OUTREACH REPORT EXISTING CONDITIONS REPORT SB 375/AB 32/AB

More information

The Future of Transit in Colorado

The Future of Transit in Colorado Note: Will be adding photos to slides before finalizing The Future of Transit in Colorado CDOT Division of Transit and Rail Speakers: David Krutsinger, AICP Manager, Rail and Special Projects Tracey MacDonald

More information

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1 Locally Preferred Alternative 1 Riverview Corridor Study Area 12 mile study area between Saint Paul and Bloomington. Connects major destinations, neighborhoods and job concentrations. Serves growing and

More information

Comparison of I-210 and I-710 as Potential ICM Corridors

Comparison of I-210 and I-710 as Potential ICM Corridors Comparison of I-210 and I-710 as Potential ICM Corridors Positive Aspects Traffic sensors Very good PeMS coverage of freeway mainline, HOV lanes, and ramps Many intersections within Pasadena already equipped

More information

The Level of Service Metric and. Alternatives for Multi-Modal Transportation. in Oakland

The Level of Service Metric and. Alternatives for Multi-Modal Transportation. in Oakland The Level of Service Metric and Alternatives for Multi-Modal Transportation in Oakland By Jill Nevins For the City of Oakland, Public Works Agency Mills College Public Policy Program May 2012 Executive

More information

Technical Advisory Committee Meeting #1. December 13, 2011 MARTA Headquarters

Technical Advisory Committee Meeting #1. December 13, 2011 MARTA Headquarters Technical Advisory Committee Meeting #1 December 13, 2011 MARTA Headquarters Meeting Agenda Project Purpose Project Schedule TAC s Roles and Responsibilities Study Area Previous Studies Big Themes from

More information

Attachment 2: Draft Business Plan Scope of Work

Attachment 2: Draft Business Plan Scope of Work Attachment 2: Draft Business Plan Scope of Work Background: The following pages present a high level draft scope of work for the Caltrain Business Plan along with a description of outreach plans, project

More information

Chapter 3 - Goals, Objectives, & Strategies

Chapter 3 - Goals, Objectives, & Strategies Chapter 3 - This chapter presents goals, objectives, and strategies that have been developed as part of the Richmond Area MPO 2026 Long-Range Transportation Plan (LRTP) update. Strategies have been developed

More information

Southwest LRT Management Committee. September 7, 2011

Southwest LRT Management Committee. September 7, 2011 Southwest LRT Management Committee September 7, 2011 Today s Topics Project Status Updates Follow-Up Requests Funding Partner Commitments Communications and Public Involvement Process 2 Project Status

More information

I-270 NORTH EA PERFORMANCE MEASURES IN NEPA

I-270 NORTH EA PERFORMANCE MEASURES IN NEPA I-270 NORTH EA PERFORMANCE MEASURES IN NEPA Buddy Desai, PE CH2M St. Louis THE ISSUE US State Departments of Transportation continue to struggle with addressing current and emerging problems with increasingly

More information

(Image of a moving Muni light rail vehicle in the Geneva Yard at night)

(Image of a moving Muni light rail vehicle in the Geneva Yard at night) (Page 1) Transportation Sustainability Program SFMTA Board of Directors February 2012 Partnership of the San Francisco County Transportation Authority, San Francisco Planning Department, San Francisco

More information

New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA

New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA Transportation Advisory Commission September 11, 2014 Transportation Performance Measures Overview of OPR s Draft

More information

2045 Long Range Transportation Plan Scope

2045 Long Range Transportation Plan Scope 2045 Long Range Transportation Plan Scope CONTENTS Scope Background... 1 Introduction:... 1 Tasks and Subtasks... 1 1)Background... 1 1-A Community Data and Demographics... 1 1-B Review of Current Plans...

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

Category 3, BART Capacity, Access and Parking Improvements. Contra Costa Transportation Authority STAFF REPORT Page 2 of 5 The Authority directed staf

Category 3, BART Capacity, Access and Parking Improvements. Contra Costa Transportation Authority STAFF REPORT Page 2 of 5 The Authority directed staf Meeting Date: Subject Summary of Issues Recommendations Financial Implications Options Attachments Changes from Committee Development of a Potential Transportation Expenditure Plan (TEP) Review and Discussion

More information

Regional Transit System Plan

Regional Transit System Plan Policy, Program Development & Intergovernmental Relations Committee Item III-A October 14, 2010 Regional Transit System Plan Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions 2016/2017 Organizational Chart Effective 7/1/2016 ed 29 FTE Positions ed 1 Part-Time Position ed 4 Intern Positions Ricardo Sandoval Administrative Secretary (1) Transportation/Land Development Project

More information

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-6. Century City 1/4-Mile Station Area August 16, 2010 Page 5-14 Figure 5-7. Wilshire/Westwood 1/4-Mile Station Area August 16, 2010 Page 5-15 Alternative 1 would be constructed underneath existing

More information

Congestion Management Process (CMP)

Congestion Management Process (CMP) Congestion Management Process (CMP) Introduction The Congestion Management Process (CMP) is a systematic, data-driven, and regionally accepted approach that aims to improve the performance of the transportation

More information

A three-stage process was implemented in order to develop and evaluate the project concepts and provide recommendations for the project.

A three-stage process was implemented in order to develop and evaluate the project concepts and provide recommendations for the project. MEMORANDUM TO: FROM: Highway 36/Rice Street PMT Mark Benson DATE: March 23, 2009 RE: Selection of a Preferred Alternative SEH No. 105803 The purpose of this memorandum is to document the process for selecting

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275 C-034-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church. See Section 2.5.1 for a description of the refined Segment A alternatives that avoid

More information

Highway and Freight Current Investment Direction and Plan. TAC August 2, 2017

Highway and Freight Current Investment Direction and Plan. TAC August 2, 2017 Highway and Freight Current Investment Direction and Plan TAC August 2, 2017 Today s Topics Highway & Freight Where are we now? The Highway Story What are the issues? How is the system performing? Where

More information

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11 Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...

More information

Riverview Corridor Pre-Project Development Study

Riverview Corridor Pre-Project Development Study Riverview Corridor Pre-Project Development Study American Society of Civil Engineers - Minnesota May 25, 2016 Work in Progress; Subject to Change 1 History 2000: Major Investment Study (MIS) offered several

More information

Outer Loop/Rail Bypass Study

Outer Loop/Rail Bypass Study Outer Loop/Rail Bypass Study Outer Loop Stakeholder Roundtable Southwest Segment Joshua City Hall April 16, 2008 North Central Texas Council of Governments Transportation Department Stakeholder Roundtable

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216 C-013-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church to the Latvian community in western Canada. See Section 2.5.1 for a description of the

More information

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report

More information